EMCal Meeting Nantes – July 15-17 2008 1 J-F Muraz
Grenoble Status
Assembly and test Hall.
EMCal Meeting Nantes – July 15-17 2008 2 J-F Muraz
Grenoble Status
Trigger support structure.
- Done for Yale and Grenoble assembly sites.
EMCal Meeting Nantes – July 15-17 2008 3 J-F Muraz
Grenoble Status
Trigger light guides.
- delivered.
- Ready to be glued to scintillators produced by Yale
EMCal Meeting Nantes – July 15-17 2008 4 J-F Muraz
Grenoble Status
Test bench electronic setup.
PMT DFC
x32
…
Delay
ADC TDC
VME
NIM
CAMAC
EMCal FEE
…Trigger module
Transl.
CCUSB DAQ/PC
Delay
Analog
splitter
To be delivered
EMCal Meeting Nantes – July 15-17 2008 5 J-F Muraz
Grenoble Status
DAQ.
- DAQ installed by Terry and David last week
EMCal Meeting Nantes – July 15-17 2008 6 J-F Muraz
Grenoble Status
4 SM Platforms:
- Done.
- Successfully load tested and certified.
- Delivery expected next week. (after painting!)
EMCal Meeting Nantes – July 15-17 2008 7 J-F Muraz
Grenoble Status
Strip handling tools.
- By the end of July, I will send to YALE:
- 1 Strip handling tool fully equipped.
- 1 Strip handling tool support frame.
- all trigger scintillator support and positioning structure.
EMCal Meeting Nantes – July 15-17 2008 8 J-F Muraz
Grenoble Status
Strap Foils.
- 3600 precutted (Full EU production : 3 SM)
- 1200 machined and cleaned (1 SM)
Hand precutting station Final cleaning
Wire cutting operation(80 straps stack)