80m xhd webinar slides

Post on 21-Dec-2014

474 Views

Category:

Self Improvement

2 Downloads

Preview:

Click to see full reader

DESCRIPTION

Webinar Slides, 3/24/2011 (2MB)

TRANSCRIPT

80-meter XHDI N S T A L L A T I O N O V E R V I E W W E B I N A R

Paul Dawson – Global Sales ManagerLarry Jacobs – Marketing ManagerSteve Clark – P.E., Mechanical Engineer & Technical LeadEmeric Rochford – Mechanical Engineer & Crew Leader

24 March 2011

• Provide a high-level overview of the 80m XHD• Underscore critical installation steps• Answer your questions• Share next steps and resources

This webinar DOES NOT replace a thorough review of

the 80m XHD Manual

Webinar Objectives

Webinar Agenda

• Introduction

• 80m XHD tower overview

• Testing and beta program

• Design

• Installation

• Lighting and compliance

• Critical Steps and Safety

• Q&A

• Wrap-up

Laboratory tests of base plate and joints (axial and bending)

Off-site laboratory tests on guy wire

breaking strengths

Testing and Beta Program

Multiple on-site installs

Three (3) North American beta

installations for final testing and feedback

Testing and Beta Program

Component 60-meter XHD(197.7 ft or 60.3m)

80-meter XHD(266.7 ft or 81.3m)

Tube diameter (OD) 10 inch (254 mm) 8 inch (203.2 mm)

10 inch (254 mm) 8 inch (203.2 mm)

Tube wall 10 inch thickness

8 inch

0.109 inch nominal (12 ga) 0.134 inch nominal (10 ga)

0.109 inch nominal (12 ga) 0.134 inch nominal (10 ga)

Tube transition 101 feet, 5 inch (30.9 m) 182 feet, 2 inch (55.8 m)

Shipping weight(tower and ginpole)

4323 lbf (1960.9 kg) 9050 lbf (4105 kg)

Footprint 50 meters to outermost anchor 55 meters to outermost anchor

Bolted Joints No bolts; flared, lanced joint Flared, lanced and bolted joint

Base plate 0.134 inch (3.4 mm), 10 ga steel 0.188 inch (4.8 mm), 7 ga steel

Guy levels 6 8

Guy wire diameter All levels: 1/4 inch (6.3mm) Levels 1-6: 5/16 inch (7.9mm)Levels 7-8: 3/8 inch (9.5mm)

60m vs. 80m Comparison: Design

Component 60-meter XHD 80-meter XHD

Total erection forces (tower plus NOW System)

35.6 kN (8000 lbf) 66.7 kN (15000 lbf)

Erection forces (winch cable force)

11.9 kN (2667 lbf) 13.3 kN (3000 lbf)

Winch rigging 3-part line 5-part line

Wire rope length 300 ft (91.4 m) 750 ft (228.6 m)

Maximum anchor load 5,100 lbf (2313 kg) 12,400 lbf (5625 kg)

Anchor number and type Fifteen 8-inch, single-helix screw-in earth anchors

• Sixteen 8-inch, double-helix power installed screw anchors

• Two 8-inch, single-helix screw-in earth anchors

60m vs. 80m Comparison: Installation

• Resources and Time• Terrain/slope Requirements• Anchors and Pull Test• Joint Assembly• Ginpole and Jumper-struts• Winch

Installation

Topics Covered

Resources and Time• Site layout / anchor setting: 1 day• Tube bolting: 3.5 hours• Laying out guy wires: 3.5 hours• Ginpole assembly: 1.5 hours• Lighting installation: 2.5 hours• Raising & plumbing tower: 3.5 hours

TOTAL: 3-4 days

Installation

80m XHD Terrain/slope Requirements• Terrain/slope ≤ ±3°

Slopes greater than +1.5° Slopes less than -2°

Installation

• Double Helix Power-Installed Screw Anchors.

• Maximum anchor load: 12,400 lbf (5625 kgf).

• CRITICAL STEP:Anchors must be pull-tested to 15,000 lbf (6804 kgf).

Installation

Anchors and Pull Test 1

1. Hold top fastener up while tubes are slid together.

2. Using a block of wood and sledge hammer, pound 2 to 3 times to seat joint.

3. Using a torque wrench, torque 5/8” – 11 nuts to 203 Nm (150 ft-lbs).

Installation

Joint Assembly

• CRITICAL STEP:Jumper-strut cables must be tensioned to 1000 lbf using provided tension gauge.

Installation

Ginpole and Jumper-struts2

Installation

Ginpole and Jumper-struts• CRITICAL STEP:

Carefully follow the manual instructions for reeving the 5-part line for the lift cable.

3

Installation

Winch• 750 ft of 3/8 in diameter

cable.

• 3000 lbf (1361 kgf) winch cable erection force.

• CRITICAL STEP:Winch base plate must be secured to winch anchor using sling provided.

4

Installation Toolkit

• Chicago grip

• Come-along

• Shackles

• CRITICAL STEP:Mechanical tensioning is required to tension guy wires.

Toolkit Includes: 5

Anchor Pull Test

Jumper-Strut Tension

Summary: Critical Steps & Safety

Winch Anchor

Guy-wire Tension

1

5-Part Line(Ginpole)

2

3

4

5

Top mounted, L-864 RED LED flashing beacon

Side-mounted L-810 RED LED steady burning side markers

Red light controller (RLC)

PV Integrated Lighting & Remote Monitoring System

PV Power Supply

Lighting Options

Compliance: ANSI/TIA-222-GNo Ice 0.25 in Ice 0.5 in Ice 0.75 in Ice 1 in Ice

33 Foot 3-second Gust WindVelocity (mph) 131 103 82 68 57

Summary of Key 80m/60mDifferences

Final Thoughts

• 60m XHD performance at 80m

• More steel means more weight

• Similar installation, new tools and anchoring required

• Thoroughly review the 80m XHD Manual

Questions?

Resources

• Installation Manual

• Training and Live Demonstrations

• http://forum.nrgsystems.com/

Provides links to slides and FAQs

• Webinar Recording

• Support:

• support@nrgsystems.com

• sales@nrgsystems.com

Thank you for attending

– The NRG Systems Team

top related