america house snagging list 25.05.06 (east)

408
AMERICA HOUSE SNAGGIN Ref. Location Defect Rating Date Date Comme No. Classif. Rectified Checked 1 Generator Room (East) PE 24 Remove fixing on wall C 2 Generator Room (East) PE 24 Install door threshold plates to three (3) external double doors B Water an 3 Generator Room (East) PE 24 Make good to external wall (internal face) where fuel pipes pass through (2 No.) C 4 Generator Room (East) PE 24 Insert pipe sleeves where fuel pipes pass through external wall (2 No.) B 5 Generator Room (East) PE 24 Appl y anti -cor rosi ve paint to mani fold exhaust br acket s (4 No.) suspended from ceil ing C 6 Generator Room (East) PE 24 Take out eight (8) bolt assemblies in soffit of ceiling slab and make good C 7 Generator Room (East) PE 24 Power wire with unfixed end to be connected or removed (East Side) A 8 Generator Room (East) PE 24 Seal holes around cable trays at high level to Mains Power Room (2 No) A 9 Generator Room (East) PE 24 Make good at wall and floor junction around the room and repair as required C 10 Generator Room (East) PE 24 Make good around grille (West side) high level where cables etc pass through wall and seal B 11 Generator Room (East) PE 24 Make good to underside of down stand beam near doors and repaint C 12 Generator Room (East) PE 24 Insert pipe sleeves to 2 No manifold exhaust pipes where they pass through the external wall B 13 Generator Room (East) PE 24 Resolve locati on of UPS syst em near external door s and pr ot ect fr om adverse weat her A 14 Generator Room (East) PE 24 No fire extinguishers A 15 Generator Room (East) PE 24 Fix Door stop to internal door B 16 Generator Room (East) PE 24 Fix Door Stop to all external doors No 1 B 17 Generator Room (East) PE 24 Fix Door Stop to all external doors No 2 B 18 Generator Room (East) PE 24 Fix Door Stop to all external doors No 3 B 19 Generator Room (East) PE 24 Fire Fighting Equipment is missing A W4A to a 20 Generator Room (East) PE 24 Door signage B 21 22 23 24 25 26 27 28 29 30 31 32 33 4/10/2013 1

Upload: frinaru-ciprian

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 1/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Generator Room (East) PE 24 Remove fixing on wall

2 Generator Room (East) PE 24 Install door threshold plates to three (3) external double doors

3 Generator Room (East) PE 24 Make good to external wall (internal face) where fuel pipes pass through (2 No.)

4 Generator Room (East) PE 24 Insert pipe sleeves where fuel pipes pass through external wall (2 No.)

5 Generator Room (East) PE 24 Apply anti-corrosive paint to manifold exhaust brackets (4 No.) suspended from ceiling

6 Generator Room (East) PE 24 Take out eight (8) bolt assemblies in soffit of ceiling slab and make good

7 Generator Room (East) PE 24 Power wire with unfixed end to be connected or removed (East Side)

8 Generator Room (East) PE 24 Seal holes around cable trays at high level to Mains Power Room (2 No)

9 Generator Room (East) PE 24 Make good at wall and floor junction around the room and repair as required

10 Generator Room (East) PE 24 Make good around grille (West side) high level where cables etc pass through wall and seal

11 Generator Room (East) PE 24 Make good to underside of down stand beam near doors and repaint

12 Generator Room (East) PE 24 Insert pipe sleeves to 2 No manifold exhaust pipes where they pass through the external wall

13 Generator Room (East) PE 24 Resolve location of UPS system near external doors and protect from adverse weather

14 Generator Room (East) PE 24 No fire extinguishers

15 Generator Room (East) PE 24 Fix Door stop to internal door

16 Generator Room (East) PE 24 Fix Door Stop to all external doors No 1

17 Generator Room (East) PE 24 Fix Door Stop to all external doors No 2

18 Generator Room (East) PE 24 Fix Door Stop to all external doors No 3

19 Generator Room (East) PE 24 Fire Fighting Equipment is missing

20 Generator Room (East) PE 24 Door signage

21

22

2324

25

26

27

28

29

30

31

Page 2: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 2/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Main Switch Room (East) PW 14 Rubber mats 6mm (tested to 11,000 volt) in front of main switch cabinets (1 m wide)

2 Main Switch Room (East) PW 14 Tidy up cables on wall near door

3 Main Switch Room (East) PW 14 Remove empty cable spool

4 Main Switch Room (East) PW 14 Seal holes around cable trays at high level to Generator Power Room (2 No)

5 Main Switch Room (East) PW 14 Install door threshold plates to external double doors

6 Main Switch Room (East) PW 14 Remove loose wire

7 Main Switch Room (East) PW 14 Digital Power Factor Control Box is not lockable (2 doors)

8 Main Switch Room (East) PW 14 Digital Power Factor Control Box seal and make good to power entry slot in base of unit (2 No)

9 Main Switch Room (East) PW 14 Digital Power Factor Control Box (left) remove loose item in base

10 Main Switch Room (East) PW 14 Make good at wall and floor junction around the room and repair as required

11 Main Switch Room (East) PW 14 Remove cable connection to rear of Main Switch Cabinets supply power to Containers

12 Main Switch Room (East) PW 14 No fire extinguishers

13 Main Switch Room (East) PW 14 Fix door stop to Internal Door

14 Main Switch Room (East) PW 14 Fix door stop to External Doors

15 Main Switch Room (East) PW 14 Door signage

16

17

18

19

20

21

22

2324

25

26

27

28

29

30

31

Page 3: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 3/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Security Room East PE16 Fitment approval and its poor ergonomical design and is also VERY unstable

2 Security Room East PE16 Make good floor covering that is short at door to Docking Bay

3 Security Room East PE16 Remove wires coming out of ceiling or reroute and tidy up

4 Security Room East PE16 Remove unconnected cables in ceiling or connect as required

5 Security Room East PE16 Complete suspended ceiling

6 Security Room East PE16 Floor seal joint (left of fitment) to be repaired

7 Security Room East PE16 Bolt fixings piercing intumescent strip of door to Docking Bay to be reviewed and resolved

8 Security Room East PE16 Hole in intumescent strip head frame of door to Docking Bay to be repaired

9 Security Room East PE16 Remove protection film still remaining on door

10 Security Room East PE16 External Window to be screened

11 Security Room East PE16 Cover Plate required to two (2) boxes in the UPS Unit near the entry door

12 Security Room East PE16 Ivorine Labels required to all boxes in Security Room in Romanian (& English if possible)

13 Security Room East PE16 Make good skirting to RH of entry door

14 Security Room East PE16 Make good to uncompleted box conduit cover to LH of door above box unit

15 Security Room East PE16 Remove general rubbish behind the fitment unit

16 Security Room East PE16 Tidy up ALL wires behind the fitment unit

17 Security Room East PE16 Paint pipe to radiator

18 Security Room East PE16 Make good paint finish to radiator where damaged

19 Security Room East PE16 Replace damaged ceiling tile (1 No)

20 Security Room East PE16 Replace stained ceiling tiles (water damaged) 3 No

21 Security Room East PE16 Make good poor cutting of ceiling tiles around heating pipes

22 Security Room East PE16 Redo pipe holdfasts on wall (2 No)

23 Security Room East PE16 Repair pipework that is distorted for radiator24 Security Room East PE16 Clean window of labels and written identification numbers etc.

25 Security Room East PE16 Reset light fitting (left)

26 Security Room East PE16 LH switch plate upper (LH of entry door) is loose and is to be refixed

27 Security Room East PE16 Repair wall between upper and lower LH switch plates to the LH of entry door

28 Security Room East PE16 Incombustible Fire Plan

29 Security Room East PE16 No fire extinguishers

30 Security Room East PE16 Fix Door stop to door

31 Security Room East PE16 Door Signage

Page 4: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 4/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Security Room Toilet (East)PE17 Complete suspended ceiling

2 Security Room Toilet (East)PE17 Clean up WHB

3 Security Room Toilet (East)PE17 Clean up WC

4 Security Room Toilet (East)PE17 Clean floor tiles

5 Security Room Toilet (East)PE17 Tidy up pipe holdfasts to radiator

6 Security Room Toilet (East)PE17 Review protruding screw fixing within door frame rebates

7 Security Room Toilet (East)PE17 Make good poor cutting of ceiling tiles around heating pipes

8 Security Room Toilet (East)PE17 Pipes to radiator cross over and need to be redone so that they are tidy

9 Security Room Toilet (East)PE17 Make good hole in wall below water heater

10 Security Room Toilet (East)PE17 Insert sleeves to water heater pipes going through wall

11 Security Room Toilet (East)PE17 Make good to wall around pipes to water heater in wall

12 Security Room Toilet (East)PE17 Paint pipe to radiator

13 Security Room Toilet (East)PE17 Repair walls where damaged and repaint

14 Security Room Toilet (East)PE17 Clean mirror of identification marks

15 Security Room Toilet (East)PE17 Remove sellotape on mirror

16 Security Room Toilet (East)PE17 Touch up door paintwork where chipped and damaged

17 Security Room Toilet (East)PE17 Regrout to wall tiles to RH of door

18 Security Room Toilet (East)PE17 Make good to uneven grouting to wall tiles and remove laitance and excess grout deposits

19 Security Room Toilet (East)PE17 Mage good to ceiling edge trim (West Wall)

20 Security Room Toilet (East)PE17 Replace 1 damaged ceiling tile

21 Security Room Toilet (East)PE17 Identification Schedule for CCTV Cameras

22 Security Room Toilet (East)PE17 Door Signage

23 Security Room Toilet (East)PE17 Refix skirting fixed with panel pins and refix with adhesive or clip-on system complete

Page 5: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 5/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Docking Bay Area (East)PE15 Handrails required to stair steps

2 Docking Bay Area (East)PE15 Skirting to wall at stair steps has been done but badly

3 Docking Bay Area (East)PE15 Repaint black and yellow strip to rear of docking bay

4 Docking Bay Area (East)PE15 Make good PVC skirting at two (2) corners

5 Docking Bay Area (East)PE15 PVC Skirting to rear of docking bay undulates and needs to be reset

6 Docking Bay Area (East)PE15 Make good and seal wall on East Wall near grille to Generator Room

7 Docking Bay Area (East)PE15 Roller Shutter door does not function

8 Docking Bay Area (East)PE15 Install door threshold plates to external door

9 Docking Bay Area (East)PE15 Make good to two (2) holes in wall

10 Docking Bay Area (East)PE15 Remove loose wire on north wall

11 Docking Bay Area (East)PE15 Reset light fitting at rear of Docking Bay LH side looking south

12 Docking Bay Area (East)PE15 Make good wall (West) at high level and finish off and paint

13 Docking Bay Area (East)PE15 Complete wall finish including paint and detail to roller shutter door on west wall

14 Docking Bay Area (East)PE15 Remove loose black PVC above roller shutter doors

15 Docking Bay Area (East)PE15 Remove large concrete snot on area in front of Security Room

16 Docking Bay Area (East)PE15 Repair pavement/trottoir to Security Room threshold

17 Docking Bay Area (East)PE15 Make good to edge of pavement in front of Security and Garbage Room

18 Docking Bay Area (East)PE15 Make good to wall base at junction with floor (west)

19 Docking Bay Area (East)PE15 Make good to wall base at junction with floor (east)

20 Docking Bay Area (East)PE15 Remove assembly instruction door label on Security Room door

21 Docking Bay Area (East)PE15 Repair/replace chipped stair treads (terrazzo) to East side

22 Docking Bay Area (East)PE15 Install missing cover plate to junction box at high level in rear of Docking Bay

23 Docking Bay Area (East)PE15 Remove or connect two unconnected wires at high level in the rear of the Docking Bay24 Docking Bay Area (East)PE15 Make good poor insulation to HVAC pipe at the rear of the Docking Bay (Right looking South)

25 Docking Bay Area (East)PE15 Fill in missing blockwork on South Wall at the rear of the docking bay at high level

26 Docking Bay Area (East)PE15 Make good wall finish and paint at high level at the rear of the Docking Bay

27 Docking Bay Area (East)PE15 Replace damaged light fitting in rear of Docking Bay (LH looking South)

28 Docking Bay Area (East)PE15 Running Man Sign to RH of Roller Shutter Door is not properly fixed

29 Docking Bay Area (East)PE15 Complete grille etc above side door to Roller Shutter

30 Docking Bay Area (East)PE15 Approval Certificate for Roller Shutter Door (Authorities and W4A)

31 Docking Bay Area (East)PE15 Fix door stop to external door

Page 6: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 6/407

AMERICA HOUSE

Ref. Location Defect

No.

35 Docking Bay Area (East)PE15 Skirting to Docking Bay on East Wall is poor and badly done

36 Docking Bay Area (East)PE15 Skirting to Docking Bay on West Wall is poor and badly done

37 Docking Bay Area (East)PE15 Replace five (5) chipped steps to stair

38 Docking Bay Area (East)PE15 Paint docking bay floor at ground level

39 Docking Bay Area (East)PE15 Make good floor around floor gulley

40 Docking Bay Area (East)PE15 Remove obsolete conduit to LH side of Roller shutter door including fixings and make good to wall

41 Docking Bay Area (East)PE15 Fire Fighting equipment is not available

42 Docking Bay Area (East)PE15 Refix skirting fixed with panel pins and refix with adhesive or clip-on system complete (South Wall)

43 Docking Bay Area (East)PE15 Refix black/yellow edge angle to docking bay which is not level or matched to the floor

44 Docking Bay Area (East)PE15 Make good edge of concrete landing at head of steps which is very rough

45 Docking Bay Area (East)PE15 Side door does not close properly

46 Docking Bay Area (East)PE15 Intruder Alarm Contacts do not align properly

47 Docking Bay Area (East)PE15 Door controls to Roller Shutter door do not seem to work

48 Docking Bay Area (East)PE15 Make good to hole in upper part of Open frame to side door

49 Docking Bay Area (East)PE15 Make good to four (4) holes in Hinge frame to side door

50 Docking Bay Area (East)PE15 Install door stop to Side Door

51 Docking Bay Area (East)PE15 Remove paint splashes etc on door surfaces and make good

52 Docking Bay Area (East)PE15 Remove key set and fix blanking piece

53 Docking Bay Area (East)PE15 Make good to hole in wall plasterboard below Running Man Sign and repaint

54 Docking Bay Area (East)PE15 Why are there two (2) CCTV cameras operating in the Docking Bay Area ?

55 Docking Bay Area (East)PE15 Provide housing for Pneumatic Safety Edge control and coiled wire cable

56 Docking Bay Area (East)PE15 LH end of floor rubber edging to Roller Shutter Door is damaged and requires to be renewed

57 Docking Bay Area (East)PE15 Rubber seal to bottom edge of Roller Shutter Door is damaged and to be replaced58 Docking Bay Area (East)PE15 Check pressure regulator at LH Bottom end of roller shutter door that appears to have burnt out

59 Docking Bay Area (East)PE15 Docking Bay Door Fire Officer Approval is required

60 Docking Bay Area (East)PE15 Install angle at step area in Docking Bay marked with diagonal black and yellow stripes near Security Room and Garbage Room

61 Docking Bay Area (East)PE15 Replace small gulley with proper gulley as in Docking Bay West

Page 7: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 7/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Boiler Room (East) S1 E10 Water leak in northwest corner to be remedied

2 Boiler Room (East) S1 E10 Car Park Exhaust Duct system to be relocated or enclosed in a fireproof enclosure

3 Boiler Room (East) S1 E10 Remove four (4) loose metal plates on west wall

4 Boiler Room (East) S1 E10 Remove two (2) temporary cables suspended at ceiling level

5 Boiler Room (East) S1 E10 Remove or connect electric wires not connected

6 Boiler Room (East) S1 E10 Repaint floor (north wall) where drain inserted

7 Boiler Room (East) S1 E10 Make good hole in wall near ABB Cabinet

8 Boiler Room (East) S1 E10 Fill in open plates spaces within ABB control box on Northeast wall

9 Boiler Room (East) S1 E10 Clean surface of ABB Control box on northeast wall of paint and green stains

10 Boiler Room (East) S1 E10 Refix conduit on northeast wall

11 Boiler Room (East) S1 E10 Remove reinforcement rod on northeast wall

12 Boiler Room (East) S1 E10 Remove obsolete angle bracket on northeast wall

13 Boiler Room (East) S1 E10 Remove cable to watchman's hut that is improperly wired into a plug outlet with another cable

14 Boiler Room (East) S1 E10 Repaint metal platform to Water purifier

15 Boiler Room (East) S1 E10 Tidy up (South) general rubbish behind pipework etc.

16 Boiler Room (East) S1 E10 Remove identification marks on glazing and profiles to blast wall

17 Boiler Room (East) S1 E10 Remove identification marks on entry door

18 Boiler Room (East) S1 E10 Make good to door finish at edges

19 Boiler Room (East) S1 E10 Make good to aperture in entry door head frame

20 Boiler Room (East) S1 E10 Make good to damaged arris at LH return to entry door reveal

21 Boiler Room (East) S1 E10 Install the remainder of MEP Labels

22 Boiler Room (East) S1 E10 Make good to the 'hotchpotch' assembly at the floor gulley

23 Boiler Room (East) S1 E10 Fuel pipe to LH Boiler (looking north) needs to be properly fixed in position and protected24 Boiler Room (East) S1 E10 Make good to boiler bases upstands

25 Boiler Room (East) S1 E10 Make good to hole in floor southeast corner

26 Boiler Room (East) S1 E10 Make good to hole in wall in southeast corner near ceiling

27 Boiler Room (East) S1 E10 Pipe flange ES TAVC PO8 is under stress and requires to be reset or replace

28 Boiler Room (East) S1 E10 Pipe label E-AC-TO3 is temporary and to be replaced

29 Boiler Room (East) S1 E10 Repair Pipe label EST AC PO6

30 Boiler Room (East) S1 E10 Install pipe label to EST AC PO7

31 Boiler Room (East) S1 E10 Remove loose wire (south wall)

Page 8: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 8/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Boiler Room (East) S1 E10 Fill in opening for tap unit in sink unit with blanking piece

35 Boiler Room (East) S1 E10 Tidy up under skirts at rear of both boilers

36 Boiler Room (East) S1 E10 Remove film covering to both boiler control panels (upper)

37 Boiler Room (East) S1 E10 Remove protective covering to profiles of blast wall

38 Boiler Room (East) S1 E10 Repair sealant cover to head frame of blast wall

39 Boiler Room (East) S1 E10 Seal opening to LH Upper of Blast wall where a duct and cable tray pass through 40 Boiler Room (East) S1 E10 Provide Methane Gas detector

41 Boiler Room (East) S1 E10 Provide electrical power emergency isolation switch

42 Boiler Room (East) S1 E10 Plant and Equipment Diagram

43 Boiler Room (East) S1 E10 No fire fighting equipment

44 Boiler Room (East) S1 E10 Fix Door stops to Boiler Room Double Doors

45 Boiler Room (East) S1 E10 Fix Door stops to Boiler Room Blast Double Doors No 1

46 Boiler Room (East) S1 E10 Fix Door stops to Boiler Room Blast Double Doors No 2

47 Boiler Room (East) S1 E10 Fire Fighting Equipment is missing including sand box etc.

48 Boiler Room (East) S1 E10 Door Signage

49 Boiler Room (East) S1 E10 Fire seal threshold required to Boiler entry door

50 Boiler Room (East) S1 E10 Fire Alarm required

51

52

53

54

55

56

57

58

59

60

61

62

63

64

Page 9: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 9/407

AMERICA HOUSE

Ref. Location Defect

No.

1 EXTERNAL Repaint kerb on BRD wall with black and yellow markings

2 EXTERNAL Repaint Kerb on LH of East access road with black and yellow markings

3 EXTERNAL Provide Gas Pipe enclosure and remove fibreglass insulation

4 EXTERNAL Change five (5) plastic labels on fire hydrant entry points on division wall to incombustible

5 EXTERNAL Repaint edge (top) of divider wall between access road and ramp (East) with black and yellow markings

6 EXTERNAL Finish top of divider wall between access road and East ramp

7 EXTERNAL Reset checker plate access cover on Access Road near BRD and at front

8 EXTERNAL Repair top edge (BRD side) of divider wall to East Ramp where fibre mat and metal edging is exposed

9 EXTERNAL Remove four (4) broken kerb and timber plank in access road near East Ramp

10 EXTERNAL Car Park Barrier Rest post is not stable and to be fixed properly

11 EXTERNAL Car Park Barrier Arm Box is not stable and requires to be fixed properly

12 EXTERNAL Repair top edge (AH side) of divider wall to East Ramp where fibre mat and metal edging is exposed

13 EXTERNAL Make good paint finish to East ramp wall at the base on the west side where repaired

14 EXTERNAL Make good and seal around gas pipe entry

15 EXTERNAL Reset Vehicle Height sign to 2.13m for complete length as LH side is only 2.08 metres

16 EXTERNAL Road gulley drain at base of East Ramp is short by 280mm and requires to be completed

17 EXTERNAL Make good defective concrete on both sides of the East Ramp road gully at the base of the ramp

18 EXTERNAL Make good to East Ramp Wall on west side above the gas supply pipe which is unfinished

19 EXTERNAL Remove reinforcement bar protruding from ceiling in the East Ramp entrance and make good

20 EXTERNAL Clean ramp surface finish

21 EXTERNAL Reset cover plate at top of East ramp that is distorted and a potential hazard to vehicles

22 EXTERNAL Replace eight (8) missing pavior tiles at East Elevation

23 EXTERNAL Reset pavior tiles on west side of Retail Entrance (East)24 EXTERNAL Remove cable near East Boiler flues LH side

25 EXTERNAL Clean East boiler flues of concrete etc at base

26 EXTERNAL Re-execute pavior tiles around East Boiler flues

27 EXTERNAL Re-level paviors near East Boiler flues that are uneven

28 EXTERNAL Make good joint between building and paviors on East Elevation

29 EXTERNAL Install tiles skirtings to ALL external columns

30 EXTERNAL Make good joint between building and paviors on South Elevation

31 EXTERNAL Make good joint between building and paviors on West Elevation

Page 10: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 10/407

AMERICA HOUSE

Ref. Location Defect

No.

34 EXTERNAL Re-level paviors to third column from the West Entrance near BCR Bank that are uneven

35 EXTERNAL Make good defective recessed skirting to glass walled column near BCR Bank (West)

36 EXTERNAL Replace thirty (30) cracked paviors

37 EXTERNAL Provide Gas Pipe enclosure West

38 EXTERNAL Tidy up edge of paviors near Dr Felix Str and edging reveals

39 EXTERNAL Complete grassed areas to South Elevation

40 EXTERNAL Complete grassed areas to West Elevation

41 EXTERNAL Make good tiling on top and down stands to railing to English Courtyard on all three sides

42 EXTERNAL Touch up paintwork to metal railing to English Courtyard which is stained with cement slurry and unfinished

43 EXTERNAL Complete remaining landscaping in West Elevation

44 EXTERNAL Kerbing to West grassed area is really edging and not sufficient and damaged - to be redone

45 EXTERNAL Access toby box to fuel tank to be installed

46 EXTERNAL Make good to road kerbs at West Road access near north boundary at the return

47 EXTERNAL Fuel Tank (West) vent pipe seems undersized and the open end is not protected from debris etc.

48 EXTERNAL Seal joint between PVC pipe sleeve and fuel POL line (West)

49 EXTERNAL Make good to two cover plates in the West Access Road near the boiler flues

50 EXTERNAL Bollard Protection to West Boiler Flues is incomplete

51 EXTERNAL Corner of Building (northwest) is not protected from impact collision damage

52 EXTERNAL Clean up road generally

53 EXTERNAL Clean out road gully on West Access Road

54 EXTERNAL Bollard Protection to West Generator Exhausts is incomplete

55 EXTERNAL Bollard Protection to East Generator Exhausts is incomplete

56 EXTERNAL Bollards are fitted with reinforcement rods and slotted into holes drilled in concrete which is not acceptable57 EXTERNAL Complete landscaped areas on north boundary

58 EXTERNAL Small Bollards appear loose, two are missing and two bollards are lying on the ground - bollards to be fixed

59 EXTERNAL Remove containers to northeast corner

60 EXTERNAL Finish parking areas to northeast corner including car park bays marking lines and numbers

61 EXTERNAL Make good to concrete road surfacing which undulates in the northeast area

62 EXTERNAL Make good to concrete road surfacing where do paw marks are visible (East Rear)

63 EXTERNAL Make good to concrete road surfacing where excavation repair has been made and also near the paviors

64 EXTERNAL Complete the grille work to the gas trench (East) which has a large gap at the upper end

Page 11: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 11/407

AMERICA HOUSE

Ref. Location Defect

No.

67 EXTERNAL Fuel Tank cover (East) to be painted with high quality corundum paint

68 EXTERNAL Make good to lower cover inside Fuel Tank Box (East) which is badly distorted, rusty and damaged

69 EXTERNAL Remove rubbish and water that has collected inside the lower cover of the fuel tank covering equipment

70 EXTERNAL Label required for Fuel Pipe fill line on West

71 EXTERNAL Label required for Fuel Pipe fill line on East

72 EXTERNAL Fuel Tank (East) vent pipe seems undersized and the open end is not protected from debris etc.73 EXTERNAL Seal joint between PVC pipe sleeve and fuel POL line (East)

74 EXTERNAL Directional arrows on access roads

75 EXTERNAL Car Park Barrier East to have arm adjusted so that it fits properly in the cradle 'U'

76 EXTERNAL Install proper manhole to access to Water Tanks in access road (present cover and frame is substandard and damaged)

77 EXTERNAL Install proper manhole access and frame to water tanks at top of ramp (present cover is substandard and damaged)

78 EXTERNAL Install access ladder to water tanks

79 EXTERNAL Clean out general debris in water tanks and timber

Page 12: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 12/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Reception (East) PE01 Replace damaged floor tile (West Rear) near door to docking bay

2 Reception (East) PE01 Floor tile finish has many uneven edges throughout that need to be taken up and re-laid

3 Reception (East) PE01 Reception Desk LH Fin return is loose and unstable

4 Reception (East) PE01 Reception Desk RH Fin return is loose and unstable

5 Reception (East) PE01 Make good uneven tiles at rear wall behind Reception Desk

6 Reception (East) PE01 Heating to Reception Area is under designed and insufficient

7 Reception (East) PE01 Tiling to Lift Lobby with 50mm strip tile is of poor quality and requires to be redone

8 Reception (East) PE01 There are marked colour variations in the glass panel wall lining generally

9 Reception (East) PE01 Remove protective remnants at head frame to three lifts

10 Reception (East) PE01 Clean down stainless steel returns and above lift doors to all three lifts

11 Reception (East) PE01 Make good skirting to ALL lift returns that do not fit cleanly

12 Reception (East) PE01 Remove paint on ceiling fixtures to Lift Lobby suspended light fittings (6 No)

13 Reception (East) PE01 Make good seal between glass wall panels and floor base

14 Reception (East) PE01 Clean down excess grout still on tiled wall on both east and west elevations

15 Reception (East) PE01 Make good vertical joint between glass panelled wall and render near LH Door Rear

16 Reception (East) PE01 Make good joint at glass wall angle near LH Door Rear

17 Reception (East) PE01 Glass Wall Joint LH next to Lift Lobby is standing proud of the wall and to be adjusted

18 Reception (East) PE01 Make good joint at glass wall angle LH next to Lift Lobby

19 Reception (East) PE01 Refix loose section of Reception Desk top in the middle

20 Reception (East) PE01 Make good seal between glazing and floor finish on both sides of the Main Entrance Door

21 Reception (East) PE01 Replace defective tile in floor finish on the right of the Main Entrance Door near the front window

22 Reception (East) PE01 Reset uneven wall tiles near window on east side of the Reception Area

23 Reception (East) PE01 Reset uneven wall tiles near window on west side of the Reception Area24 Reception (East) PE01 Make good between gap between glazed fin and wall east side near front window

25 Reception (East) PE01 Make good between gap between glazed fin and wall west side near front window

26 Reception (East) PE01 Make good to seal at all glass fins to the front window and the floor finish

27 Reception (East) PE01 Hose reel lock defective and to be repaired or replaced

28 Reception (East) PE01 Clean out debris etc. in Hose reel Enclosure

29 Reception (East) PE01 Break Glass box for key to replace unlocked key box

30 Reception (East) PE01 Seal hole in base of Hose reel Enclosure

31 Reception (East) PE01 Remove wooden batten to RH side of door to Hose reel enclosure and make good

Page 13: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 13/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Reception (East) PE01 Make good to blockwork to RH side of Hose reel enclosure

35 Reception (East) PE01 Remove reinforcement rod sticking out of block wall and make good

36 Reception (East) PE01 Make good hole towards Glass Panelled wall LH Side in Hose reel Enclosure

37 Reception (East) PE01 Make good blockwork to LH side of Hose reel Enclosure as there is presently a gap

38 Reception (East) PE01 Make good blockwork to south side of Hose reel Enclosure at upper level

39 Reception (East) PE01 Small diameter pipe to RH side of Hose reel Enclosure to be fixed properly to wall

40 Reception (East) PE01 Small diameter pipe to RH side of Hose reel Enclosure to be labelled

41 Reception (East) PE01 Glass in Hose reel Enclosure Door is not set in a gasket and shakes

42 Reception (East) PE01 Make good surface to ceiling in rear recessed ceiling light trough (east)

43 Reception (East) PE01 Reset two glass wall panels in the rear wall of the Reception Area behind the desk as out of line

44 Reception (East) PE01 Repair wall hole in rear wall above glass panels

45 Reception (East) PE01 Fill in hole in light trough (East)

46 Reception (East) PE01 Fill in hole in light trough LH side of Reception Desk

47 Reception (East) PE01 Tidy up wires in light trough LH side of Reception Desk

48 Reception (East) PE01 Fill in hole in light trough (west)

49 Reception (East) PE01 Reset uneven wall tiles near window on east side of the Reception Area

50 Reception (East) PE01 Make good vertical joint between glass wall panelling and render (East)

51 Reception (East) PE01 Remove paint smears from HVAC ceiling grilles (6 No)

52 Reception (East) PE01 Remove paint smears from the Running Man sign

53 Reception (East) PE01 Sprinkler heads to be set flush with ceiling finish (2 No)

54 Reception (East) PE01 Screws to Entrance Wind Fang (8 No) are silvery and are to be replaced with black headed screws

55 Reception (East) PE01 Floor finish indicates that several tiles are 'bossed' and require to be refixed and set properly

56 Reception (East) PE01 The Door to the rear and Docking Bay is not fire rated57 Reception (East) PE01 Remove remaining polythene protective cover from LH rear door

58 Reception (East) PE01 Remove paint stains on door and make good as required

59 Reception (East) PE01 Clean paint off floor tiles at LH Door Rear threshold

60 Reception (East) PE01 Touch up ceiling at joint to south front

61 Reception (East) PE01 Fire Alarm point has no instructions for use in Romanian and English

62 Reception (East) PE01 Intruder alarm on door (black) is white coloured. Why are they not compatible with the frame of the door ?

63 Reception (East) PE01 Fix Door Stop to (LH) Door to Docking Bay

64 Reception (East) PE01 Fix Door Stop to (RH) Door to Rear Passage

Page 14: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 14/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Reception East Entrance PE01A Make good to damage (2 No) to recess box on RH side of the enclosure

2 Reception East Entrance PE01A Make good damage to the two ceiling frames

3 Reception East Entrance PE01A Take out the four shims between the inner ceiling frame and the glass cover ceiling

4 Reception East Entrance PE01A Remove protective covering at end (RH) of both ceiling frames

5 Reception East Entrance PE01A Clean glass cover ceiling from paint marks, mastic etc.

6 Reception East Entrance PE01A Make good to floor tiles at all four corners as workmanship is poor7 Reception East Entrance PE01A Make good joint between floor tiles and walls to both sides of entry enclosure

8 Reception East Entrance PE01A LH Inner leaf door to be reset to allow keepers to operate properly

9 Reception East Entrance PE01A Refix loose seal to LH inner leaf door near frame bottom

10 Reception East Entrance PE01A Make good to top of left hand inner leaf door at top of pull handle both sides

11 Reception East Entrance PE01A Make good to base of LH frame (right of door near the floor)

12 Reception East Entrance PE01A Remove green sticker on glass ceiling above inner door

13 Reception East Entrance PE01A Remove concrete slurry on door handle outer door

14 Reception East Entrance PE01A Re-level floor tiles at threshold to inner door leaves

15 Reception East Entrance PE01A Reset keeper plate set at angle to LH Outer door leaf

16 Reception East Entrance PE01A Bottom keeper to LH outer door leaf is loose and to be tightened

17 Reception East Entrance PE01A Outer leaves of doors to realigned as they are uneven and the gap between them varies in the vertical

18 Reception East Entrance PE01A The frame bases LH and RH to inner door to be finished

19 Reception East Entrance PE01A Relevel mat well as at rear Maxwell is below the surrounding tile edge

20 Reception East Entrance PE01A Refix door handle to Inner Door leaf (RH) south which is loose at top frame fixing

21 Reception East Entrance PE01A Make good to chipped hole in northwest corner of Reception East Entrance and seal completely

Page 15: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 15/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level One Corridor (East) E1 E01 Joint Plate between East and West buildings is partially distorted

2 Level One Corridor (East) E1 E01 Floor tiles are generally uneven, not aligned and 'bossed' or debonded in many places

3 Level One Corridor (East) E1 E01 Cills of Profiles at floor level are stained with tile grout and require to be cleaned

4 Level One Corridor (East) E1 E01 Metallic ceiling panels - replace distorted, stained etc. panels

5 Level One Corridor (East) E1 E01 Metallic ceiling panels - clean down ceiling panels with oily stain marks etc.

6 Level One Corridor (East) E1 E01 Joint Plate between East and West buildings is not continuous at columns7 Level One Corridor (East) E1 E01 Repair crack in ceiling plasterboard ceiling at East/West building joint

8 Level One Corridor (East) E1 E01 Make good to large 'X' scratch on middle cill profile on 2nd bay from East/West Buildings joint

9 Level One Corridor (East) E1 E01 Reset sprinkler heads that have excessive projection from the ceiling (5 No)

10 Level One Corridor (East) E1 E01 Remove paint from sprinkler heads (4 No)

11 Level One Corridor (East) E1 E01 Paint white cable box conduit for fire alarm installation (West) on column to match column gray colour

12 Level One Corridor (East) E1 E01 Fire alarm push alarm (West) has no written instruction for use

13 Level One Corridor (East) E1 E01 Remove grout from glass seals and floor finish to all shopfronts generally

14 Level One Corridor (East) E1 E01 Door West Stair : the fixing screws again protrude as driven at an angle

15 Level One Corridor (East) E1 E01 Intumescent strip around Door to West Stair is not continuous

16 Level One Corridor (East) E1 E01 Door West Stair : the intumescent strip is not provided to the door threshold and bases of frames

17 Level One Corridor (East) E1 E01 Repair skirting at Door to West Stair bases and make good all round

18 Level One Corridor (East) E1 E01 Remove paint on 'Running Man' sign to corridor to West Stair

19 Level One Corridor (East) E1 E01 Clean off paint to top seal to all glazed shopfronts generally

20 Level One Corridor (East) E1 E01 Remove all labels, written pane identifications, adhesive from removed labels to shop front glazing generally

21 Level One Corridor (East) E1 E01 Re-align metal edge trims to metallic ceiling generally

22 Level One Corridor (East) E1 E01 Re-align shopfront glass at LH corner of corridor to East Staircase and redo joint 14mm wide which is substandard

23 Level One Corridor (East) E1 E01 Clean paint off shopfront glass at corridor to East Stair LH side near door24 Level One Corridor (East) E1 E01 Intumescent strip around Door to East Stair is not continuous

25 Level One Corridor (East) E1 E01 Door East Stair : the intumescent strip is not provided to the door threshold and bases of door frames

26 Level One Corridor (East) E1 E01 Repair skirting at Door to East Stair bases and make good all round

27 Level One Corridor (East) E1 E01 Remove protective tape to top seal of shop front along RH of East Stair corridor

28 Level One Corridor (East) E1 E01 Make good at base of all columns where they join the floor finish

29 Level One Corridor (East) E1 E01 Paint white cable box conduit for fire alarm installation (East) on column to match column gray colour

30 Level One Corridor (East) E1 E01 Fire alarm push alarm (East) has no written instruction for use

31 Level One Corridor (East) E1 E01 Remove are 2 No wooden pegs contraptions that penetrate the joint seal to the shop fronts on East and make good

Page 16: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 16/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Level One Corridor (East) E1 E01 On north side of eastern part of main corridor the seal is missing between the shop fronts and the floor tiling

35 Level One Corridor (East) E1 E01 Eastern part of corridor the return to the steel handrail is still a potential hazard and could catch clothes

36 Level One Corridor (East) E1 E01 Eastern part of corridor there are seven (7) missing light fittings to be installed

37 Level One Corridor (East) E1 E01 Eastern part of corridor corrugated steel wall lining : install bolt head covers that are missing

38 Level One Corridor (East) E1 E01 There are some different types of bolt covers to the corrugated sheet wall lining and to be changed to match

39 Level One Corridor (East) E1 E01 Closure of angle eastern corridor is unsatisfactory and needs to be reviewed40 Level One Corridor (East) E1 E01 Fire seal to threshold to Door East Stair is required

41 Level One Corridor (East) E1 E01 Fire seal to threshold to Door West Stair is required

Page 17: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 17/407

Page 18: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 18/407

AMERICA HOUSE

Ref. Location Defect

No.

34 East Entrance (Mall) PE25 Remove paint on south façade head frames on complete length

35 East Entrance (Mall) PE25 Realign trim to ceiling finish at south façade head frame

36 East Entrance (Mall) PE25 Make good to exposed wires to door intruder contact

37 East Entrance (Mall) PE25 Install door close to outer leaf of Entrance Door

38 East Entrance (Mall) PE25 Remove bolt fixing in stringer of stair upper flihgt and make good

39 East Entrance (Mall) PE25 Repair hole to bulkhead near East Mall Entrance and make good all round

Page 19: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 19/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vest. to Boiler Room East SE1.08 Remove pen writing on door surfaces

2 Vest. to Boiler Room East SE1.08 Make good wall above main outer door where pipes etc pass into car park and remove reinforcement rod

3 Vest. to Boiler Room East SE1.08 Clean cement stains on door frames

4 Vest. to Boiler Room East SE1.08 Make good poor rendering above outer door especially at joint to ceiling

5 Vest. to Boiler Room East SE1.08 Repaint wall where wall has been repaired (3 No)

6 Vest. to Boiler Room East SE1.08 Make good to wall to LH side of outer door7 Vest. to Boiler Room East SE1.08 Remove all protective coverings to doors (Outer)

8 Vest. to Boiler Room East SE1.08 Paint floor

9 Vest. to Boiler Room East SE1.08 Refix intumescent strip to head frame of outer door

10 Vest. to Boiler Room East SE1.08 Repair hole in head frame of outer door

11 Vest. to Boiler Room East SE1.08 Make good to gap between wall and door frame on RH of outer door

12 Vest. to Boiler Room East SE1.08 Reset facing to LH of outer door

13 Vest. to Boiler Room East SE1.08 Door frame fixing screws protrude - refix

14 Vest. to Boiler Room East SE1.08 Intumescent strip is broken to side frame due to outer door security prong

15 Vest. to Boiler Room East SE1.08 Inner leaf (RH) does not open - refix

16 Vest. to Boiler Room East SE1.08 Install threshold plate and seal to outer door

17 Vest. to Boiler Room East SE1.08 Remove manufacturer's label on Outer door

18 Vest. to Boiler Room East SE1.08 Repair damaged insulation to pipes above outer door (3 No)

19 Vest. to Boiler Room East SE1.08 Make good to door fames on both sides and head frame to door North

20 Vest. to Boiler Room East SE1.08 Seal hole in wall to Boiler Room where cable tray passes through

21 Vest. to Boiler Room East SE1.08 Seal hole in wall to Car Park Area where cable tray passes through

22 Vest. to Boiler Room East SE1.08 Make good to RH side of door frame to outer door (Car Park)

23 Vest. to Boiler Room East SE1.08 Reset inner leaf of double door to Boiler Room which does not open

24 Vest. to Boiler Room East SE1.08 Repair wall to RH side of door to Boiler Room

25 Vest. to Boiler Room East SE1.08 Remove protective covering to Boiler Room Door

26 Vest. to Boiler Room East SE1.08 Remove cement stains from head frame to Boiler Room Door

27 Vest. to Boiler Room East SE1.08 Complete insulation to pipe returns at high level on East Wall (Boiler Room)

28 Vest. to Boiler Room East SE1.08 Install missing pipe sleeves (5 No)

29 Vest. to Boiler Room East SE1.08 Make good protruding sealant to single door on South Wall

30 Vest. to Boiler Room East SE1.08 Remove manufacturer's label on door (South)

31 Vest to Boiler Room East SE1 08 Seal hole in South Wall near floor level

Page 20: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 20/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Vest. to Boiler Room East SE1.08 Make good joint between floor and wall generally

35 Vest. to Boiler Room East SE1.08 Remove red paint marks on wall to Car Park

36 Vest. to Boiler Room East SE1.08 Install threshold plate and seal to Boiler Room Door

37 Vest. to Boiler Room East SE1.08 Make good to threshold to Car Park Exhaust Room (North Wall)

38 Vest. to Boiler Room East SE1.08 Make good to threshold to Storage Room (South Wall)

39 Vest. to Boiler Room East SE1.08 Make good to intumescent strip where damaged to Boiler Room Door40 Vest. to Boiler Room East SE1.08 Intumescent strip is broken to side frame due to Boiler Room door security prong

41 Vest. to Boiler Room East SE1.08 Make good to area above door to boiler room where it has been patched up with a door frame larger than the door

42 Vest. to Boiler Room East SE1.08 Make good wall crack to LH of Boiler Room Door on East Wall to column

43 Vest. to Boiler Room East SE1.08 Refix loose junction box on North Wall

44 Vest. to Boiler Room East SE1.08 Clean concrete snots on ceiling

45 Vest. to Boiler Room East SE1.08 Make good to joint between wall and ceiling to Boiler Room Wall

46 Vest. to Boiler Room East SE1.08 Make good to joint between wall and ceiling to Car Park Wall

47 Vest. to Boiler Room East SE1.08 Refix flexible conduit at Light Fitting near West Wall (South)

48 Vest. to Boiler Room East SE1.08 Install door stops to double door to Car Park Area

49 Vest. to Boiler Room East SE1.08 Install door stop to door to Car Park Exhaust Room (North)

50 Vest. to Boiler Room East SE1.08 Install door stop to door to Storage Room (South)

51 Vest. to Boiler Room East SE1.08 Fire threshold strip required to entry door to car park

52 Vest. to Boiler Room East SE1.08 Warning Notice required for boiler flue pipes horizontal with clearance height of 1.68 to 1.73 metres

Page 21: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 21/407

AMERICA HOUSE

Ref. Location Defect

No.

1 English Courtyard S1E.11 Floor to have Tiles as F.02

2 English Courtyard S1E.11 Remove protective cover from Profiles on Glazed wall to Boiler Room

3 English Courtyard S1E.11 Renew grille grating to street level in accordance with W4A revised drawing

4 English Courtyard S1E.11 Seal Wall (Glazed) where cable tray passes through and make good

5 English Courtyard S1E.11 Paint Walls

6 English Courtyard S1E.11 Refix loose ladder access to street level (Ladder has steel reinforcement bar rungs - back street manufacture)7 English Courtyard S1E.11 Paint ladder to street level

8 English Courtyard S1E.11 Paint grille and frame to street level

9 English Courtyard S1E.11 Remove cement/concrete on pipe hangers on wall to Pump Room

10 English Courtyard S1E.11 Remove and connect loose wire above door to pump room

11 English Courtyard S1E.11 Intumescent strip to Pump Room is damage and requires to be fixed

12 English Courtyard S1E.11 Remove manufacturer's labels on door to Pump Room

13 English Courtyard S1E.11 Make good several repair patches to walls generally

14 English Courtyard S1E.11 Make good to joint between walls and floor generally

15 English Courtyard S1E.11 Refix loose coupling to ceiling conduit (East)

16 English Courtyard S1E.11 Make good conduit connections to door alarm contacts

17 English Courtyard S1E.11 Refix seal to door in Blast Wall that is loose

18 English Courtyard S1E.11 Rehang inner leaf of Blast Room Door that 'grinds' along the concrete floor

19 English Courtyard S1E.11 Remove steel reinforcement to RH of opening in pavement slab and make good

20 English Courtyard S1E.11 Fire seal threshold is required to Fire Pump Room Door

Page 22: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 22/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Fire Pump Room -1 S1E.12 Paint Floor

2 Fire Pump Room -1 S1E.12 Paint Walls

3 Fire Pump Room -1 S1E.12 Make good seal around door frame which is protruding

4 Fire Pump Room -1 S1E.12 Remove manufacturer's labels on door

5 Fire Pump Room -1 S1E.12 Install Pump Room Wall Diagram

6 Fire Pump Room -1 S1E.12 Remove or connect loose wire on North Wall7 Fire Pump Room -1 S1E.12 Tidy up hotch potch of loose wires in control boxes (2 No) on North Wall and remove insulating tape repairs

8 Fire Pump Room -1 S1E.12 Make good to North wall at ceiling

9 Fire Pump Room -1 S1E.12 Install pipe sleeves (12 No)

10 Fire Pump Room -1 S1E.12 Make good to flexible conduit connection to pump motor near North Wall

11 Fire Pump Room -1 S1E.12 Remove two protruding reinforcement rods in North Wall and make good

12 Fire Pump Room -1 S1E.12 Make good to North East Corner wall at top

13 Fire Pump Room -1 S1E.12 Provide statutory protection to stair hole access in floor

14 Fire Pump Room -1 S1E.12 Make good holes in East Wall at floor level

15 Fire Pump Room -1 S1E.12 Repair water leaks from tanks ?

16 Fire Pump Room -1 S1E.12 Make good to hole in floor slab on South Wall

17 Fire Pump Room -1 S1E.12 Seal hole in floor slab near water tanks

18 Fire Pump Room -1 S1E.12 Remove Paper "Danger' label to Electrical Distribution Board and provide proper signage

19 Fire Pump Room -1 S1E.12 Seal hole in floor slab at southwest corner

20 Fire Pump Room -1 S1E.12 Make good and seal to West Wall near door (LH) at ceiling level where pipes etc pass through

21 Fire Pump Room -1 S1E.12 Paint floor drain grille and frame

22 Fire Pump Room -1 S1E.12 Install Door stop to single door

23 Fire Pump Room -1 S1E.12 Door Signage

24 Fire Pump Room -1 S1E.12 Fire Fighting equipment is missing

25 Fire Pump Room -1 S1E.12 Fire Alarm to be installed

Page 23: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 23/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 3 East Open Space Window No 1 North Repair defective seal at corner and refix seal to opening window

2 Level 3 East Open Space Window No 2 North Repair defective seal at corner and refix seal to opening window

3 Level 3 East Open Space Window No 3 North Repair defective seal at corner and refix seal to opening window

4 Level 3 East Open Space Window No 4 North Repair defective seal at corner and refix seal to opening window

5 Level 3 East Open Space Window No 5 North Repair defective seal at corner and refix seal to opening window

6 Level 3 East Open Space Window No 6 North Repair defective seal at corner and refix seal to opening window7 Level 3 East Open Space Window No 7 North Repair defective seal at corner and refix seal to opening window

8 Level 3 East Open Space Window No 8North Repair defective seal at corner and refix seal to opening window

9 Level 3 East Open Space Window No 9 North Repair defective seal at corner and refix seal to opening window

10 Level 3 East Open Space Window No 10 North Repair defective seal at corner and refix seal to opening window

11 Level 3 East Open Space Window No 11 North Repair defective seal at corner and refix seal to opening window

12 Level 3 East Open Space Window No 12 North Repair defective seal at corner and refix seal to opening window

13 Level 3 East Open Space Window No 13 North Repair defective seal at corner and refix seal to opening window

14 Level 3 East Open Space Window No 1 East Repair defective seal at corner and refix seal to opening window

15 Level 3 East Open Space Window No 2 East Repair defective seal at corner and refix seal to opening window

16 Level 3 East Open Space Window No 3 East Repair defective seal at corner and refix seal to opening window

17 Level 3 East Open Space Window No 4 East Repair defective seal at corner and refix seal to opening window

18 Level 3 East Open Space Window No 5 East Repair defective seal at corner and refix seal to opening window

19 Level 3 East Open Space Window No 6 East Repair defective seal at corner and refix seal to opening window

20 Level 3 East Open Space Window Fan No 1 East Repair seal broken at top both ends and remove excess mastic sealant

21 Level 3 East Open Space Window Fan No 1 South Repair seal broken at top both ends and remove excess mastic sealant

22 Level 3 East Open Space Window Fan No 2 South Repair seal broken at top both ends and remove excess mastic sealant

23 Level 3 East Open Space Window Fan No 2 South Repair seal broken at top both ends and remove excess mastic sealant

24 Level 3 East Open Space Window Fan No 4 South Repair seal broken at top both ends and remove excess mastic sealant

25 Level 3 East Open Space Window Fan No 5 South Repair seal broken at top both ends and remove excess mastic sealant

26 Level 3 East Open Space Window Fan No 6 South Repair seal broken at top both ends and remove excess mastic sealant

27 Level 3 East Open Space Window Fan No 7 South Repair seal broken at top both ends and remove excess mastic sealant

28 Level 3 East Open Space Make good to joint between flexible building floor joint and façade wall

29 Level 3 East Open Space Finish joint on South façade between two buildings

30 Level 3 East Open Space Make good at head of vertical South façade joint and ceiling finish

31 Level 3 East Open Space Remove protective tape to profiles at South Façade joint

Page 24: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 24/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Level 3 East Open Space Make good by removing concrete snots to Column A19

35 Level 3 East Open Space Make good by removing concrete snots to Column A18

36 Level 3 East Open Space Make good by removing concrete snots to Column A17

37 Level 3 East Open Space Make good by removing concrete snots to Column A16

38 Level 3 East Open Space Make good by removing concrete snots to Column A15

39 Level 3 East Open Space Make good by removing concrete snots to Column A1440 Level 3 East Open Space Make good by removing concrete snots to Column B20

41 Level 3 East Open Space Make good by removing concrete snots to Column B19

42 Level 3 East Open Space Make good by removing concrete snots to Column C20

43 Level 3 East Open Space Make good by removing concrete snots to Column C19

44 Level 3 East Open Space Make good by removing concrete snots to Column D20

45 Level 3 East Open Space Make good by removing concrete snots to Column D19

46 Level 3 East Open Space Make good by removing concrete snots to Column D18

47 Level 3 East Open Space Make good by removing concrete snots to Column D17

48 Level 3 East Open Space Make good by removing concrete snots to Column D14

49 Level 3 East Open Space Remove steel reinforcement in slab behind columns A 12 & 13 and make good

50 Level 3 East Open Space Remove paint smears etc on ceiling grilles South Façade

51 Level 3 East Open Space Remove paint smears etc on ceiling grilles North Façade

52 Level 3 East Open Space Remove paint smears etc on ceiling grilles East Facade

53 Level 3 East Open Space Remove label on door to Stair Corridor Grid 14/15 South

54 Level 3 East Open Space Make good around Fire Damper grille to LH of Door to Stair Corridor South Grid B14/15 and realign and install proper lock

55 Level 3 East Open Space Operating label required on Fire Alarm South Grid B14/15

56 Level 3 East Open Space Operating label required on Fire Alarm North Grid C14/15

57 Level 3 East Open Space Operating label required on Fire Alarm South Grid B17/18

58 Level 3 East Open Space Operating label required on Fire Alarm North Grid C17/18

59 Level 3 East Open Space Make good around Fire Damper grille to LH of Lift Lobby Grid B16 and realign and install proper lock

60 Level 3 East Open Space Wall tiles to Lift Lobby have out of alignment, bossed and not level throughout and to be redone

61 Level 3 East Open Space Floor tiles to Lift Lobby are uneven , out of alignment, and bossed generally and to be redone

62 Level 3 East Open Space Stainless steel skirtings to be refixed flush with wall returns to lift opening PE7

63 Level 3 East Open Space Stainless steel skirtings to be refixed flush with wall returns to lift opening PE8

64 Level 3 East Open Space Stainless steel skirtings to be refixed flush with wall returns to lift opening PE9

Page 25: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 25/407

AMERICA HOUSE

Ref. Location Defect

No.

67 Level 3 East Open Space Remove Protective covering to head panel of lift openings at head of side framed Lift Opening PE09

68 Level 3 East Open Space Make good to wall tile pointing at Lift PE07 at RH side

69 Level 3 East Open Space Make good to wall tile pointing at Lift PE09 at LH side

70 Level 3 East Open Space Clean stains on upper lift panels above lift door opening PE07 near ceiling

71 Level 3 East Open Space Clean stains on upper lift panels above lift door opening PE08 near ceiling

72 Level 3 East Open Space Clean stains on upper lift panels above lift door opening PE09 near ceiling 73 Level 3 East Open Space Remove paint stains on air grille in middle of Lift Lobby

74 Level 3 East Open Space North Area Grid C D 12/20 Refix ceiling edge trims to suspended ceiling generally that have warped or are out of alignment

75 Level 3 East Open Space Replace three (3) damaged ceiling tiles in North Area Grid CD 15/19

76 Level 3 East Open Space Remove labels on all windows generally

77 Level 3 East Open Space Reset ceiling grille in northeast corner

78 Level 3 East Open Space Make good to wall lining in northeast corner at floor

79 Level 3 East Open Space Repoint at window head near Boiler Flue as open

80 Level 3 East Open Space Clean general building debris out of runnels to all twenty seven opening sashes

81 Level 3 East Open Space Remove excess mastic at window corner to RH side of Boiler Flue internally

82 Level 3 East Open Space Replace damaged opening sash window in South East corner with twisted frame

83 Level 3 East Open Space Remove excess mastic at window corner facing Boiler Flue internally

84 Level 3 East Open Space Remove excess mastic at windows to southeast corner internally

85 Level 3 East Open Space Make good scratch to opening window 1 Grid A 19/20

86 Level 3 East Open Space Tighten window handles to opening windows South Façade No 2

87 Level 3 East Open Space Tighten window handles to opening windows South Façade No 3

88 Level 3 East Open Space Tighten window handles to opening windows South Façade No 4

89 Level 3 East Open Space Tighten window handles to opening windows South Façade No 5

90 Level 3 East Open Space Tighten window handles to opening windows South Façade No 6

91 Level 3 East Open Space Tighten window handles to opening windows South Façade No 7

92 Level 3 East Open Space Make good to rough floor at Column A 18 near window façade

93 Level 3 East Open Space Make good to rough floor at Column A 17 near window façade

94 Level 3 East Open Space Repair damaged joints in expansion joint between the buildings Grid Line 12/13 (3 No)

95 Level 3 East Open Space Replace broken window restrainer to opening window sash on Window 5 North Facade

96 Level 3 East Open Space Install medium ceiling hatch near Grid Line B/C 18

97 Level 3 East Open Space Install small ceiling hatch near Grid Line B/C 18

Page 26: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 26/407

AMERICA HOUSE

Ref. Location Defect

No.

100 Level 3 East Open Space Glass Key Box to Fire Hose reel box the glass is loose and should be replaced with a Break Glass Key Box B18

101 Level 3 East Open Space Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse B18

102 Level 3 East Open Space Seal hole in floor slab inside Fire Hose reel Cabinet B 18

103 Level 3 East Open Space Seal openings between Fire Hose reel door frame and blockwork all round B18

104 Level 3 East Open Space Clean airbourne dirt around circular ceiling vents in plasterboard 'corridor' ceiling north area C 12/20

105 Level 3 East Open Space Clean airbourne dirt around circular ceiling vents in plasterboard 'corridor' ceiling south area B 12/20

106 Level 3 East Open Space Make good access ceiling hatch Grid B/C 14

107 Level 3 East Open Space Make good around Fire Damper grille to grid C14 and realign and install proper lock

108 Level 3 East Open Space Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box C14

109 Level 3 East Open Space Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse C14

110 Level 3 East Open Space Seal openings between Fire Hose reel door frame and blockwork all round C14

111 Level 3 East Open Space Seal holes in wall lining to RH of door opening inside the Fire Hose reel enclosure C 14

112 Level 3 East Open Space Seal hole in ceiling slab of Fire Hose reel Enclosure C 14

113 Level 3 East Open Space Replace stained ceiling tile in Area AB 18/19

114 Level 3 East Open Space Replace damaged ceiling tile on Area AB 18/19 115 Level 3 East Open Space Fire Fighting Equipment is missing

Page 27: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 27/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet Grd. East PW25 Repaint wall as substandard

2 Electrical Closet Grd. East PW25 Make good 'messy' joint between floor and wall finish all round

3 Electrical Closet Grd. East PW25 Seal opening on south wall at high level (@ No.) and make good

4 Electrical Closet Grd. East PW25 Cabinet TEG-E make good to panel internally where badly cut for flexible conduit

5 Electrical Closet Grd. East PW25 Cabinet TEG-E replace damaged/chipped panel RH second down

6 Electrical Closet Grd. East PW25 Remove protective covering from TESra 2GE

7 Electrical Closet Grd. East PW25 Make good eleven (11) drill holes on south wall and repaint

8 Electrical Closet Grd. East PW25 Make good to render around wall door returns which are poorly executed and repaint

9 Electrical Closet Grd. East PW25 Clean rust marks on floor paint and repaint

10 Electrical Closet Grd. East PW25 Clean off concrete grout and snots on door frames amend repaint as required

11 Electrical Closet Grd. East PW25 Reset protruding door screws to frame fixing all round

12 Electrical Closet Grd. East PW25 Install door stop

13 Electrical Closet Grd. East PW25 Intumescent strip is missing on RH side of door frame needs to be replaced

14 Electrical Closet Grd. East PW25 Intumescent strip to head frame is covered in cement grout and needs to be cleaned or replaced

15 Electrical Closet Grd. East PW25 Intumescent strip to both sides of frame is not complete at the heads and required to be replaced16 Electrical Closet Grd. East PW25 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

17 Electrical Closet Grd. East PW25 Apply paint to threshold plate as rusting

18 Electrical Closet Grd. East PW25 Door Signage

19 Electrical Closet Grd. East PW25 Fire seal threshold required to door to Closet

Page 28: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 28/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 6 Open Area Window No 1 North Repair defective seal at corner and refix seal to opening window

2 Level 6 Open Area Window No 2 North Repair defective seal at corner and refix seal to opening window

3 Level 6 Open Area Window No 3 North Repair defective seal at corner and refix seal to opening window

4 Level 6 Open Area Window No 4 North Repair defective seal at corner and refix seal to opening window

5 Level 6 Open Area Window No 5 North Repair defective seal at corner and refix seal to opening window

6 Level 6 Open Area Window No 6 North Repair defective seal at corner and refix seal to opening window7 Level 6 Open Area Window No 7 North Repair defective seal at corner and refix seal to opening window

8 Level 6 Open Area Window No 8 North Repair defective seal at corner and refix seal to opening window

9 Level 6 Open Area Window No 10 North Repair defective seal at corner and refix seal to opening window

10 Level 6 Open Area Window No 11 North Repair defective seal at corner and refix seal to opening window

11 Level 6 Open Area Window No 12 North Repair defective seal at corner and refix seal to opening window

12 Level 6 Open Area Window No 13 North Repair defective seal at corner and refix seal to opening window

13 Level 6 Open Area Window No 1 East Repair defective seal at corner and refix seal to opening window

14 Level 6 Open Area Window No 2 East Repair defective seal at corner and refix seal to opening window

15 Level 6 Open Area Window No 3 East Repair defective seal at corner and refix seal to opening window

16 Level 6 Open Area Window No 4 East Repair defective seal at corner and refix seal to opening window

17 Level 6 Open Area Window No 5 East Repair defective seal at corner and refix seal to opening window

18 Level 6 Open Area Window No 6 East Repair defective seal at corner and refix seal to opening window

19 Level 6 Open Area Window Fan No 1 East Repair seal broken at top both ends and remove excess mastic sealant

20 Level 6 Open Area Window Fan No 1 South Repair seal broken at top both ends and remove excess mastic sealant

21 Level 6 Open Area Window Fan No 2 South Repair seal broken at top both ends and remove excess mastic sealant

22 Level 6 Open Area Window Fan No 2 South Repair seal broken at top both ends and remove excess mastic sealant

23 Level 6 Open Area Window Fan No 4 South Repair seal broken at top both ends and remove excess mastic sealant and tighten handle

24 Level 6 Open Area Window Fan No 5 South Repair seal broken at top both ends and remove excess mastic sealant and remove wire in stay

25 Level 6 Open Area Window Fan No 6 South Repair seal broken at top both ends and remove excess mastic sealant

26 Level 6 Open Area Window Fan No 7 South Repair seal broken at top both ends and remove excess mastic sealant and protective tape to profile

27 Level 6 Open Area Remove paint smears to ceiling grilles South Façade and realign as required

28 Level 6 Open Area Remove paint smears to ceiling grilles East Façade and realign as required

29 Level 6 Open Area Make good around Fire Damper grille to grid C14 and realign and install proper lock fastening

30 Level 6 Open Area Remove paint/cement splashes to internal surface of glass to FHE C14 Door

31 Level 6 Open Area Clean airbourne dirt around circular ceiling vents in plasterboard 'corridor' ceiling north area C 12/20

Page 29: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 29/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor North C14/18 (E6E.01) Install operator signage to Fire Alarm Button at South Wall near door to Stair Vestibule E4E.03

2 Corridor North C14/18 (E6E.01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby

3 Corridor North C14/18 (E6E.01) Clean paint off grille to Fire Damper panel (Lower) near Lift Lobby

4 Corridor North C14/18 (E6E.01) Provide proper locking device to Low Fire Damper Grille on South Wall near Lift Lobby

5 Corridor North C14/18 (E6E.01) Install operator signage to Fire Alarm Button at South Wall RH of Service Elevator Vestibule

6 Corridor North C14/18 (E6E.01) Install operator signage to Door Release Button at South Wall to RH of Service Elevator Vestibule

7 Corridor North C14/18 (E6E.01) Install break glass to Emergency Door Release Button on South Wall to RH of Service Elevator Vestibule

8 Corridor North C14/18 (E6E.01) Remove paint from Running Man Sign above door to Stair Vestibule E4E.16

9 Corridor North C14/18 (E6E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby

10 Corridor North C14/18 (E6E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby

11 Corridor North C14/18 (E6E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on South Wall near Lift Lobby

12 Corridor North C14/18 (E6E.01) Make good round Fire Damper Grille panel (Low) on South Wall near to RH side of Service Elevator Lobby

13 Corridor North C14/18 (E6E.01) Clean paint off grille to Fire Damper panel (Lower) to RH side of Service Lift Lobby

14 Corridor North C14/18 (E6E.01) Provide proper locking device to Low Fire Damper Grille on South Wall to RH side of Service Lift Lobby

Page 30: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 30/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor West B/C 14 (E6E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor West B/C 14 (E6E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor West B/C 14 (E6E.01) Make good round Fire Damper Grille panel C14 East Wall near Fire Hose reel Enclosure (FHE)

4 Corridor West B/C 14 (E6E.01) Clean paint off grille to Fire Damper panel C14 near FHE

5 Corridor West B/C 14 (E6E.01) Provide proper locking device to C14 Fire Damper Grille on East Wall near FHE

6 Corridor West B/C 14 (E6E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box

7 Corridor West B/C 14 (E6E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor West B/C 14 (E6E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor West B/C 14 (E6E.01) Build up blockwork below threshold and seal to door

10 Corridor West B/C 14 (E6E.01) Seal to head of door frame with blockwork and make good

11 Corridor West B/C 14 (E6E.01) Divider Wall to LH to be sealed full length to back wall

12 Corridor West B/C 14 (E6E.01) Seal wall at RH side of enclosure for waste pipe and make good

13 Corridor West B/C 14 (E6E.01) Seal two holes in ceiling slab within FHE and make good

14 Corridor West B/C 14 (E6E.01) Seal around conduit to RH side of FHE internally near concrete beam

15 Corridor West B/C 14 (E6E.01) Fit two (2) nozzles to hosereels16 Corridor West B/C 14 (E6E.01) Seal wall RH side to drain pipe and make good

17 Corridor West B/C 14 (E6E.01) Remove large open cable in floor slab and make good

18 Corridor West B/C 14 (E6E.01) Remove small cable left in FHE and make good at floor and ceiling slabs when removed

19 Corridor West B/C 14 (E6E.01) Make good hole in wall below FHE externally and repaint

20 Corridor West B/C 14 (E6E.01) Remove hardboard shim on LH side frame of FH Enclosure

Page 31: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 31/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Elevator Vestibule E6E.18 Prepare for and paint ceiling

2 Service Elevator Vestibule E6E.18 Remove paint on Access Card Reader

3 Service Elevator Vestibule E6E.18 Remove paint stains on f loor covering generally

4 Service Elevator Vestibule E6E.18 Fill in hole to door head frame

5 Service Elevator Vestibule E6E.18 Remove paint splashes etc on doors

6 Service Elevator Vestibule E6E.18 Fixing screws to frame protrude and are to be refixed to Door

7 Service Elevator Vestibule E6E.18 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Service Elevator Vestibule E6E.18 Intumescent strip on inner hinge frame is broken and short at base and prong receiver and to be replaced

9 Service Elevator Vestibule E6E.18 Intumescent strip on hinge frame of outer door leaf is short at base and to be replaced

10 Service Elevator Vestibule E6E.18 Install door stops to Doors

11 Service Elevator Vestibule E6E.18 Clean paint off Door Frames

12 Service Elevator Vestibule E6E.18 Door Signage

13 Service Elevator Vestibule E6E.18 Fire/Smoke Threshold seal is required to door

14 Service Elevator Vestibule E6E.18 Install closer with selector on doors

15 Service Elevator Vestibule E6E.18 Remove all remaining parts of the protective covering to doors16 Service Elevator Vestibule E6E.18 Install rubber seal to door

17 Service Elevator Vestibule E6E.18 Intumescent strip to meeting style is not continuous and missing at door lock

18 Service Elevator Vestibule E6E.18 Realign door intruder alarm contacts

19 Service Elevator Vestibule E6E.18 Inner leaf of door has too much play when closed and to be adjusted

20 Service Elevator Vestibule E6E.18 Tidy up wiring to door intruder contact

21 Service Elevator Vestibule E6E.18 Screw missing form door locking plate

22 Service Elevator Vestibule E6E.18 Connect door closer to outer door leaf

23 Service Elevator Vestibule E6E.18 Touch up to damaged paintwork to door frames generally

24 Service Elevator Vestibule E6E.18 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

25 Service Elevator Vestibule E6E.18 Relay floor covering that is distorted and 'bubbled' and prepare floor screed below

26 Service Elevator Vestibule E6E.18 Replace missing external angle corner piece to LH side of lift entrance return

27 Service Elevator Vestibule E6E.18 Replace missing skirting and external angle corner piece to RH side of lift entrance return

28 Service Elevator Vestibule E6E.18 Install edging between floor covering and lift threshold

29 Service Elevator Vestibule E6E.18 Paint sprinkler pipework

30 Service Elevator Vestibule E6E.18 Tidy up joint at sprinkler head and elbow joints including removing excess joint hemp fibres on sprinkler pipework

31 Service Elevator Vestibule E6E 18 Replace screws at grille to LH side with white headed screws as elsewhere

Page 32: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 32/407

AMERICA HOUSE

Ref. Location Defect

No.

33 Service Elevator Vestibule E6E.18 Seal and make good to one (1) sprinkler pipe in northeast corner at near ceiling level

34 Service Elevator Vestibule E6E.18 Remove paint on Arrow Lift Indicator and make good

35 Service Elevator Vestibule E6E.18 Remove remaining parts of protective covering to Lift frames

36 Service Elevator Vestibule E6E.18 Clean off paint splashes on Lift Door and frames

37 Service Elevator Vestibule E6E.18 Make good to floor finishes etc at base of LH frame of door

38 Service Elevator Vestibule E6E.18 Make good to floor finishes etc at base of RH frame of door and fill in sinking to screed

39 Service Elevator Vestibule E6E.18 Complete conduit to ceiling smoke detector

Page 33: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 33/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 6 (E6E.16) Remove paint to South Door Frames

2 Stair Vestibule Level 6 (E6E.16) Fit rubber seal all round door South

3 Stair Vestibule Level 6 (E6E.16) Intumescent strip is not complete to hinge frame at head and bases of Door South : to be replaced

4 Stair Vestibule Level 6 (E6E.16) Intumescent strip is not complete to base and head of open frame of Door South and is also loose : to be replaced

5 Stair Vestibule Level 6 (E6E.16) Fixing screws to frame protrude and are to be refixed to Door South

6 Stair Vestibule Level 6 (E6E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door South

7 Stair Vestibule Level 6 (E6E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

8 Stair Vestibule Level 6 (E6E.16) Intumescent strip to head frame is missing

9 Stair Vestibule Level 6 (E6E.16) Remove remaining protective covering to Door South

10 Stair Vestibule Level 6 (E6E.16) Install fire/smoke seal threshold plate to Door South

11 Stair Vestibule Level 6 (E6E.16) Screw missing in lock plate to door South

12 Stair Vestibule Level 6 (E6E.16) Install door closer to Door South

13 Stair Vestibule Level 6 (E6E.16) Why are there locks on Stair Egress Doors operated with Card Reader Access and Release Push button ?

14 Stair Vestibule Level 6 (E6E.16) Terrazzo tile floor is uneven and needs to be levelled, polished and resealed

15 Stair Vestibule Level 6 (E6E.16) Terrazzo Skirting at LH wall return to doors to have rounded or pencil arrissed corner to Stair Egress Door16 Stair Vestibule Level 6 (E6E.16) Provide operation label to Door Push Button in Romanian and English

17 Stair Vestibule Level 6 (E6E.16) Remove paint etc. from top edge of skirting on all walls

18 Stair Vestibule Level 6 (E6E.16) Reset double power socket outlet near Door North on East wall to be level

19 Stair Vestibule Level 6 (E6E.16) Reset double power socket outlet near Door South on East wall to be level

20 Stair Vestibule Level 6 (E6E.16) Clean paint etc from two (2) light fittings

21 Stair Vestibule Level 6 (E6E.16) Screw missing from door lock plate on Door North

22 Stair Vestibule Level 6 (E6E.16) Clean paint off door frame to Door North

23 Stair Vestibule Level 6 (E6E.16) Touch up chipped paintwork to door frames

24 Stair Vestibule Level 6 (E6E.16) Intumescent strip is not complete to open frame being short at base and missing in top section of Door North : to be replaced

25 Stair Vestibule Level 6 (E6E.16) Intumescent strip to hinge frame is missing at top and short to base to Door North : to be replaced

26 Stair Vestibule Level 6 (E6E.16) Fixing screws to frame protrude and are to be refixed to Door North

27 Stair Vestibule Level 6 (E6E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door North

28 Stair Vestibule Level 6 (E6E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

29 Stair Vestibule Level 6 (E6E.16) Install door stop to Door North

30 Stair Vestibule Level 6 (E6E.16) Fit rubber seal all round door North

31 Stair Vestibule Level 6 (E6E 16) Fire/Smoke Threshold seal is required to door North

Page 34: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 34/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 6 (E6E.16) Make good to floor terrazzo tiling that finished short at Door North

35 Stair Vestibule Level 6 (E6E.16) Set Running Man Sign straight at ceiling

36 Stair Vestibule Level 6 (E6E.16) Remove all remaining parts of protective covering to door North

37 Stair Vestibule Level 6 (E6E.16) Remove paint to three (3) sprinkler head in ceiling and make good

38 Stair Vestibule Level 6 (E6E.16) Make good round Fire Damper Grille panel (Upper)

39 Stair Vestibule Level 6 (E6E.16) Clean paint off grille to Fire Damper panel (Upper)

40 Stair Vestibule Level 6 (E6E.16) Provide proper locking device to Upper Fire Damper Grille (Upper)

41 Stair Vestibule Level 6 (E6E.16) Make good round Fire Damper Grille panel (Lower)

42 Stair Vestibule Level 6 (E6E.16) Clean paint off grille to Fire Damper panel (Lower)

43 Stair Vestibule Level 6 (E6E.16) Provide proper locking device to Upper Fire Damper Grille (Lower)

44 Stair Vestibule Level 6 (E6E.16) Make good to skirting to LH of Door South as missing

45 Stair Vestibule Level 6 (E6E.16) Make good to skirting to LH of Door North as missing

46 Stair Vestibule Level 6 (E6E.16) Make good to skirting to RH of Door North

47 Stair Vestibule Level 6 (E6E.16) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

48 Stair Vestibule Level 6 (E6E.16) Remove paint from Running Man Sign and make good49 Stair Vestibule Level 6 (E6E.16) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

50 Stair Vestibule Level 6 (E6E.16) Seal internally around Dry Riser Access Panel and make good

51 Stair Vestibule Level 6 (E6E.16) Fill in gaps around Upper Fire Damper on West Wall and make good all round

Page 35: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 35/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E6E.15 No floor gulley installed

2 Handicapped Toilet E6E.15 Clean excess grouting to tiles generally

3 Handicapped Toilet E6E.15 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E6E.15 Make good to floor finish at LH Base Frame of door

5 Handicapped Toilet E6E.15 Make good to floor finish at RH Base Frame of door

6 Handicapped Toilet E6E.15 Remove paint on door frames and make good

7 Handicapped Toilet E6E.15 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E6E.15 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E6E.15 Screw missing to lock plate on door

10 Handicapped Toilet E6E.15 Remove all remaining parts of protective covering to door

11 Handicapped Toilet E6E.15 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E6E.15 WHB tap is loose and to be reset properly

13 Handicapped Toilet E6E.15 Install plug

14 Handicapped Toilet E6E.15 Install rubber seal around door

15 Handicapped Toilet E6E.15 Install Door stop16 Handicapped Toilet E6E.15 Clean general dirt etc in floor pointing and make good

17 Handicapped Toilet E6E.15 Repoint to wall tiling where short or insufficient

18 Handicapped Toilet E6E.15 Make good to tiled floor finish to door frame bases LH

19 Handicapped Toilet E6E.15 Make good to tiled floor finish to door frame bases RH

20 Handicapped Toilet E6E.15 Make good to wall tiling at north east corner

21 Handicapped Toilet E6E.15 Make good to wall tiling at northwest corner where missing

22 Handicapped Toilet E6E.15 Make good to joint between wall and floor tiling on South Wall

23 Handicapped Toilet E6E.15 Make good to door dent at lock plate

Page 36: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 36/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule Level 6 (E6E.05) Remove paint to three sprinkler heads

2 Vestibule Level 6 (E6E.05) Make good to floor and finish at frames bases of Door South

3 Vestibule Level 6 (E6E.05) Remove paint to South Door Frames

4 Vestibule Level 6 (E6E.05) Fit rubber seal all round door South

5 Vestibule Level 6 (E6E.05) Intumnescent strip is not installed to side or head frames

6 Vestibule Level 6 (E6E.05) Fixing screws to frame protrude and are to be refixed to Door South

7 Vestibule Level 6 (E6E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door South

8 Vestibule Level 6 (E6E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Vestibule Level 6 (E6E.05) Install door stop to Door South

10 Vestibule Level 6 (E6E.05) Remove remaining protective covering to Door South

11 Vestibule Level 6 (E6E.05) Install fire/smoke seal threshold plate to Door South

12 Vestibule Level 6 (E6E.05) Screw missing in lock plate to door South

13 Vestibule Level 6 (E6E.05) Install door closer to Door South

14 Vestibule Level 6 (E6E.05) Install edging and recut floor covering to door South threshold

15 Vestibule Level 6 (E6E.05) Clean paint off door frame to Door North16 Vestibule Level 6 (E6E.05) Intumescent strip is installed to side or head frames of Door North

17 Vestibule Level 6 (E6E.05) Fixing screws to frame protrude and are to be refixed to Door North

18 Vestibule Level 6 (E6E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door North

19 Vestibule Level 6 (E6E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

20 Vestibule Level 6 (E6E.05) Install door stop to Door North

21 Vestibule Level 6 (E6E.05) Fit rubber seal all round door North

22 Vestibule Level 6 (E6E.05) Fire/Smoke Threshold seal is required to door North

23 Vestibule Level 6 (E6E.05) Install door closer to Door North

24 Vestibule Level 6 (E6E.05) Remove all remaining parts of protective covering to door

25 Vestibule Level 6 (E6E.05) Screw missing in lock plate to door North

26 Vestibule Level 6 (E6E.05) Replace missing external angle corner to skirting to LH of door to Handicapped Toilet E6E.15

27 Vestibule Level 6 (E6E.05) Replace missing external angle corner to skirting to RH of door to Toilet E6E.14

28 Vestibule Level 6 (E6E.05) Replace missing external angle corner to skirting to RH of door to Pantry

29 Vestibule Level 6 (E6E.05) Replace missing external angle corner to skirting to LH of door to Pantry

30 Vestibule Level 6 (E6E.05) Replace missing skirting between Pantry and Vestibule E6E.08

31 Vestibule Level 6 (E6E 05) Refix all skirting as attached with panel pins with adhesive or clip-on system

Page 37: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 37/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Vestibule Level 6 (E6E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E4E.11

35 Vestibule Level 6 (E6E.05) Install edging strip between PVC floor covering and tile f loor f inish to Toilet E4E.12

36 Vestibule Level 6 (E6E.05) Install edging strip between PVC floor covering and tile f loor f inish to Toilet E4E.13

37 Vestibule Level 6 (E6E.05) Install edging strip between PVC floor covering and tile f loor f inish to Toilet E4E.14

38 Vestibule Level 6 (E6E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E4E.15

Page 38: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 38/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E6\4E.08 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

2 Vestibule E6\4E.08 Make good to floor finishes at door frame bases

3 Vestibule E6\4E.08 Clean light of dirt and paint stains

4 Vestibule E6\4E.08 Touch up chipped paint on door frames

5 Vestibule E6\4E.08 Remove paint on door frames and make good

6 Vestibule E6\4E.08 Fixing screws to frame protrude and are to be refixed to door

7 Vestibule E6\4E.08 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Vestibule E6\4E.08 Screw missing to lock plate on door

9 Vestibule E6\4E.08 Remove all remaining parts of protective covering to door

10 Vestibule E6\4E.08 Install rubber seal around door

11 Vestibule E6\4E.08 Install door stop

12 Vestibule E6\4E.08 Refix all skirting as attached with panel pins with adhesive or clip-on system

Page 39: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 39/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Data Room Level 6 E6E.10 Paint Ceiling and beams

2 Data Room Level 6 E6E.10 Seal hole at north wall where sprinkler pipe enters

3 Data Room Level 6 E6E.10 Clean out light fitting

4 Data Room Level 6 E6E.10 Remove paint on door frames and make good

5 Data Room Level 6 E6E.10 Fixing screws to frame protrude and are to be refixed to door

6 Data Room Level 6 E6E.10 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Data Room Level 6 E6E.10 Screw missing to lock plate on door

8 Data Room Level 6 E6E.10 Remove all remaining parts of protective covering to door

9 Data Room Level 6 E6E.10 Install rubber seal around door

10 Data Room Level 6 E6E.10 Install door stop

11 Data Room Level 6 E6E.10 Seal North wall to two (2) HVAC pipes and make good all round

12 Data Room Level 6 E6E.10 Seal conduit at ceiling level on South Wall

13 Data Room Level 6 E6E.10 Refix all skirting as attached with panel pins with adhesive or clip-on system

Page 40: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 40/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E6E 09 Paint ceiling

2 Electrical Closet E6E 09 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

3 Electrical Closet E6E 09 Make good to floor level on South Wall near door and refix floor covering

4 Electrical Closet E6E 09 Install skirting to South Wall as missing

5 Electrical Closet E6E 09 Skirting missing at return on East Wall

6 Electrical Closet E6E 09 Skirting loose on northern side of East Wall

7 Electrical Closet E6E 09 Skirting is missing on West wall (North)

8 Electrical Closet E6E 09 Make good to north wall next floor sinking and refix floor covering complete

9 Electrical Closet E6E 09 Infill large hole in southeast of room (fire stopping) Hole at present is a safety issue

10 Electrical Closet E6E 09 Skirting missing at North wall

11 Electrical Closet E6E 09 Remove manufacturer's labels from door and make good

12 Electrical Closet E6E 09 Paint walls

13 Electrical Closet E6E 09 Make good to door plasterboard ingoings to both door frames and head frame

14 Electrical Closet E6E 09 Remove paint to Door Frames

15 Electrical Closet E6E 09 Fit rubber seal all round door 16 Electrical Closet E6E 09 Intumescent strip is short to hinge frame at base of door and to be replaced

17 Electrical Closet E6E 09 Intumescent strip is short to open frame at base and to be replaced

18 Electrical Closet E6E 09 Fixing screws to frame protrude and are to be refixed to door

19 Electrical Closet E6E 09 Cover four (4) protruding screw ends in angle plate to top corner to Door h

20 Electrical Closet E6E 09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Electrical Closet E6E 09 Install door stop to door

22 Electrical Closet E6E 09 Remove remaining protective covering to door

23 Electrical Closet E6E 09 Install fire/smoke seal threshold plate to door

24 Electrical Closet E6E 09 Two (2) screw missing in lock plate to door

25 Electrical Closet E6E 09 Door frames are 8mm above finished floor level and to be reset

26 Electrical Closet E6E 09 Install door closer

27 Electrical Closet E6E 09 Realign intruder alarm door contacts

28 Electrical Closet E6E 09 Door sign

29 Electrical Closet E6E 09 Make good to wall base at return to East wall in middle and repaint

30 Electrical Closet E6E 09 Tighten up thirteen (13) screws to the five control boxes to RH of SBS 10E

31 Electrical Closet E6E 09 Screw in the seven (7) missing screws to the five (5) control boxes to RH of SBS-10E

AMERICA HOUSE

Page 41: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 41/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Electrical Closet E6E 09 Replace label to cabinet SBS 10E which is plastic with paper printed sign and install ivorine label

35 Electrical Closet E6E 09 Clean paint from two (2) ceiling lights and make good

36 Electrical Closet E6E 09 Make good to plasterboard at wall return near Bus Bars on East Wall and paint

37 Electrical Closet E6E 09 Reconnect or remove to three (3) wires at beam level above SBS-10E

38 Electrical Closet E6E 09 Reconnect or remove to three (3) wires to Box 3 above SBS-10E

39 Electrical Closet E6E 09 Reconnect or remove to five (5) wires to Box 3 above SBS-10E

40 Electrical Closet E6E 09 Electrical Cabinet TCT-6E : reset upper panel internally

41 Electrical Closet E6E 09 Clean out internal of Electrical Cabinet TL6E

42 Electrical Closet E6E 09 Clean out internal of Electrical Cabinet TUPS-6E

AMERICA HOUSE

Page 42: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 42/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Basement -3 East General Area Make good wall at corner A22 including underside of slab

2 Basement -3 East General Area Remove concrete dropping to SVP pipe and generally clean up A22

3 Basement -3 East General Area Provide impact Protection to SVP Pipe A22

4 Basement -3 East General Area Provide impact protection to SVP Pipe A20

5 Basement -3 East General Area Provide impact protection to SVP Pipe A18

6 Basement -3 East General Area Provide impact protection to SVP Pipe A16

7 Basement -3 East General Area Provide impact protection to SVP Pipe A14

8 Basement -3 East General Area Provide impact protection to SVP Pipe D14

9 Basement -3 East General Area Provide impact protection to SVP Pipe D16

10 Basement -3 East General Area Provide impact protection to SVP Pipe D18

11 Basement -3 East General Area Provide impact protection to SVP Pipe D20

12 Basement -3 East General Area Provide impact protection to SVP Pipe at C21 near ALA Entrance

13 Basement -3 East General Area Provide impact protection to car exhaust extracts A22 LH

14 Basement -3 East General Area Provide impact protection to car exhaust extracts A21 RH

15 Basement -3 East General Area Provide impact protection to car exhaust extracts A21 LH16 Basement -3 East General Area Provide impact protection to car exhaust extracts A20 RH

17 Basement -3 East General Area Provide impact protection to car exhaust extracts A20 LH

18 Basement -3 East General Area Provide impact protection to car exhaust extracts A19 RH

19 Basement -3 East General Area Provide impact protection to car exhaust extracts A19 LH

20 Basement -3 East General Area Provide impact protection to car exhaust extracts A18 RH

21 Basement -3 East General Area Provide impact protection to car exhaust extracts A18 LH

22 Basement -3 East General Area Provide impact protection to car exhaust extracts A17 RH

23 Basement -3 East General Area Provide impact protection to car exhaust extracts A17 LH

24 Basement -3 East General Area Provide impact protection to car exhaust extracts A16 RH

25 Basement -3 East General Area Provide impact protection to car exhaust extracts A16 LH

26 Basement -3 East General Area Provide impact protection to car exhaust extracts A16 LH

27 Basement -3 East General Area Provide impact protection to car exhaust extracts A15 RH

28 Basement -3 East General Area Provide impact protection to car exhaust extracts A15 LH

29 Basement -3 East General Area Provide impact protection to car exhaust extracts A14 RH

30 Basement -3 East General Area Provide impact protection to car exhaust extracts A14 LH

31 Basement -3 East General Area Provide impact protection to car exhaust extracts A13 LH

AMERICA HOUSE

Page 43: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 43/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Basement -3 East General Area Provide impact protection to water supply pipe Column A 20

35 Basement -3 East General Area Provide impact protection to water supply pipe Column A 18

36 Basement -3 East General Area Provide impact protection to water supply pipe Column A 16

37 Basement -3 East General Area Provide impact protection to water supply pipe Column A 14

38 Basement -3 East General Area Provide impact protection to water supply pipe Column D 20

39 Basement -3 East General Area Provide impact protection to water supply pipe Column D 18

40 Basement -3 East General Area Provide impact protection to water supply pipe Column D 16

41 Basement -3 East General Area Provide impact protection to water supply pipe Column D 14

42 Basement -3 East General Area Clean out void between Column Walls A 12 and 13

43 Basement -3 East General Area Clean out void between Column Walls D 12 and 13

44 Basement -3 East General Area Provide impact Protection to CO Warning Sign A 12

45 Basement -3 East General Area Provide impact Protection to CO Warning Sign D 12

46 Basement -3 East General Area Provide impact Protection to CO Warning Sign A 17

47 Basement -3 East General Area Provide impact Protection to CO Warning Sign D 17

48 Basement -3 East General Area Clean out floor drain near D20 as blocked and also remove blue plastic bedding 49 Basement -3 East General Area Paint floor drain grating near D 20

50 Basement -3 East General Area Clean out floor drain near D18

51 Basement -3 East General Area Paint floor drain grating near D 18

52 Basement -3 East General Area Clean out floor drain near D16

53 Basement -3 East General Area Paint floor drain grating near D 16

54 Basement -3 East General Area Clean out floor drain near D14

55 Basement -3 East General Area Paint floor drain grating near D 14

56 Basement -3 East General Area Clean out floor drain near A20

57 Basement -3 East General Area Paint floor drain grating near A 20

58 Basement -3 East General Area Clean out floor drain near A18 which needs also to be aligned as place squint

59 Basement -3 East General Area Paint floor drain grating near A 18

60 Basement -3 East General Area Clean out floor drain near A16

61 Basement -3 East General Area Paint floor drain grating near A 16

62 Basement -3 East General Area Clean out floor drain near A14 as blocked

63 Basement -3 East General Area Paint floor drain grating near A 14

64 Basement -3 East General Area Clean concrete group to SVP Pipe at Column D 20

AMERICA HOUSE

Page 44: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 44/407

AMERICA HOUSE

Ref. Location Defect

No.

67 Basement -3 East General Area South east corner of cover plate to Sewage Pumping Station is curling and wil l cause tyre problems. Replace as 66 above

68 Basement -3 East General Area Cover plate and frame for rear part of Sewage Pumping Station not yet installed

69 Basement -3 East General Area Paint support metalwork to Sewage Pumping Station to prevent rust etc.

70 Basement -3 East General Area D19 : take down cable tray support left in and make good

71 Basement -3 East General Area Make good to back kerb to outer wall between D19 and D20

72 Basement -3 East General Area Seal hole in wall upper to RH of Column D 19

73 Basement -3 East General Area Make good and seal four holes in wall to ALA D21

74 Basement -3 East General Area Remove timber packer plate at wall head above ALA entrance and make good

75 Basement -3 East General Area Provide finishing ventilation plates to three (3) ventilation opening to ALA above entrance door to ALA

76 Basement -3 East General Area Provide impact protection to wall mounted ventilation unit near Column D20

77 Basement -3 East General Area Provide impact protection to Running Man Sign on column C 20

78 Basement -3 East General Area Provide impact protection to Running Man Sign on column B 20

79 Basement -3 East General Area Provide impact protection to Running Man Sign on wall C18

80 Basement -3 East General Area Provide impact protection to Running Man Sign on wall B18

81 Basement -3 East General Area Provide impact protection to Running Man Sign on wall B1582 Basement -3 East General Area Provide impact protection to Running Man Sign on wall C14

83 Basement -3 East General Area Make good leak between A16 and A17 and repaint wall

84 Basement -3 East General Area Make good two (2) leaks between A15 and A16 and repaint wall

85 Basement -3 East General Area Make good large leak between A14 and A15 and repaint wall

86 Basement -3 East General Area Make good leak between A13 and A14 and repaint wall

87 Basement -3 East General Area Make good leak between at column D15 and repaint wall and column

88 Basement -3 East General Area Make good leak between D 15 and D16 and repaint wall

89 Basement -3 East General Area Make good leak between D17 and D18 and repaint wall

90 Basement -3 East General Area Make good leak between D18 and D19 and repaint wall

91 Basement -3 East General Area Make good leak between D19 and D20 and repaint wall

92 Basement -3 East General Area Repair sprinkler pipe installation between D 13 and D14 as out of line and level and suspended holdfasts are squint

93 Basement -3 East General Area Provide impact protection to wall mounted ventilation unit near Column D14

94 Basement -3 East General Area Realign sprinkler pipe installation between D16 and D17

95 Basement -3 East General Area Make good to wall external to RH of Wall Column D16 and repaint

96 Basement -3 East General Area Remove 60mm plastic water pipe protruding over 1 m from ceiling and seal hole and make good at Column D18

97 Basement -3 East General Area Install operator signage to Fire Alarm Button at wall C17 and remove paint

AMERICA HOUSE

Page 45: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 45/407

AMERICA HOUSE

Ref. Location Defect

No.

100 Basement -3 East General Area Install operator signage to Fire Alarm Button at Wall D15

101 Basement -3 East General Area Take out temporary electrical cabinet and supply wire including making good to slab soffit when removed at Wall BC 14

102 Basement -3 East General Area Remove timber packer at wall head and make good Wall BC 14

103 Basement -3 East General Area Make good to vertical runnel (LH) to concrete Wall BC 14 and repaint

104 Basement -3 East General Area Remove steel rod in wall BC 14 to the left of the HVAC/Plumbing Shafts and make good

105 Basement -3 East General Area Remove concrete snotting and splatter to LH side of door to Corridor C 14/15

106 Basement -3 East General Area Make good formwork rod hole to Wall C14/15 on RH side of Door to Corridor

107 Basement -3 East General Area Seal pipes passing through to Service Lift Vestibule Wall C14/15

108 Basement -3 East General Area Make good to honeycombed wall B 14/15 and repaint

109 Basement -3 East General Area Make good hole in ceiling slab at D14

110 Basement -3 East General Area Remove 100mm diameter cupped plate on Wall B17/18 and make good

111 Basement -3 East General Area Make good to honeycombed wall B 18 and repaint

112 Basement -3 East General Area Make good to wide vertical wall runnel on Wall B/C 18 and repaint

113 Basement -3 East General Area Make good botched ceiling slab repair near Wall B/C 18

114 Basement -3 East General Area Seal two (2) holes near slab at HVAC/Plumbing Ducts on Wall B/C 18115 Basement -3 East General Area Make good to four (4) holes near slab

116 Basement -3 East General Area Make good seven (7) formwork rod holes on LH of Wall C 17/18

117 Basement -3 East General Area Make good four (4) formwork rod holes on RH of Wall C 17/18

118 Basement -3 East General Area Make good honeycombed wall to RH of Wall C 17/18 and repaint

119 Basement -3 East General Area Seal two (2) pipes that pass through wall above door to Elevator Lobby on Wall C 17/18

120 Basement -3 East General Area Make good to arrises of plasterboard lined duct in middle of wall (East) to Elevator Lobby

121 Basement -3 East General Area Remove pipe between A17/18 in external wall kerb and seal

122 Basement -3 East General Area Repair water leaks in AREA B/C 21 and 22 and make good to finishes

123 Basement -3 East General Area Remove wire in wall to ALA to LH side of emergency exit to ALA

124 Basement -3 East General Area Remove timber packing to wall to ALA C21 to B22 and make good

125 Basement -3 East General Area Repair hole in slab ceiling between A 21/22 and B21/22

126 Basement -3 East General Area Seal off cable tray as it passes through wall between Car Park Area and Annex Room S3E.9

127 Basement -3 East General Area Seal conduit as it passes through wall above door to Service Corridor S3E .8

128 Basement -3 East General Area Warning notice needed in Car Park Area B/C 21 as clearance height is 1.83 metres

129 Basement -3 East General Area Warning notice needed in Car Park Area A/B 22 at sprinkler pipe as clearance height is 2.01metres

130 Basement -3 East General Area Warning notice needed in Car Park Area A/B 22 along wall under large dia exhaust pipe as clearance height is 2 07metres

AMERICA HOUSE

Page 46: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 46/407

AMERICA HOUSE

Ref. Location Defect

No.

133 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera A21

134 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera B18

135 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera B14

136 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera A12

137 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera D12

138 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera C14

139 Basement -3 East General Area Make good flexible conduit connections to CCTV Camera C18

140 Basement -3 East General Area Make good to white water pipe at ceiling D18

141 Basement -3 East General Area Complete conduit connection to CO Warning Sign A 12

142 Basement -3 East General Area Complete conduit connection to CO Warning Sign D 12

143 Basement -3 East General Area Complete conduit connection to CO Warning Sign A 17

144 Basement -3 East General Area Complete conduit connection to CO Warning Sign D 17

145 Basement -3 East General Area Make good painting to black and yellow threshold strip Service Elevator Vestibule.

146 Basement -3 East General Area Make good painting to black and yellow threshold strip Corridor B14/15 South.

147 Basement -3 East General Area Make good painting to black and yellow threshold strip Corridor C14/15 North

148 Basement -3 East General Area Make good painting to black and yellow threshold strip Corridor B17/15 South.

149 Basement -3 East General Area Make good painting to black and yellow threshold strip Corridor C17/18 North

150 Basement -3 East General Area Tidy conduit connections to control panel for Sewage Pumping Station D17/18

151 Basement -3 East General Area Paint floor after leak repaired between A 13/14

152 Basement -3 East General Area Make good to wall paint near six gang wall switch where missing to LH of Door to Corridor S3E.06 South side

153 Basement -3 East General Area Paint to missing area at six gang light switch on North Wall C 17/18

154 Basement -3 East General Area Fire fighting equipment is missing

155

156157

158

159

160

161

162

163

AMERICA HOUSE

Page 47: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 47/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair S3E.04 Replace three (3) chipped steps

2 Stair S3E.04 Repair skirting that is debonding at mid landing

3 Stair S3E.04 Clean light fitting on landing that is covered in paint etc.

4 Stair S3E.04 Landing tiles are uneven and need to be levelled and repolished

5 Stair S3E.04 Stair are badly stained and need deep cleaned and repolished

6 Stair S3E.04 Floor tiling at -3 is uneven and needs levelled and repolished

7 Stair S3E.04 Make good to wall where black conduit passes through wall

8 Stair S3E.04 Remove paint on Running Man sign

9 Stair S3E.04 Remove paint on wall grille

10 Stair S3E.04 Fix handles to doors and make good

11 Stair S3E.04 Remove masking tape to door frames

12 Stair S3E.04 Intumescent strip is not complete to both frame bases

13 Stair S3E.04 Fixing screws to frame protrude and are to be refixed

14 Stair S3E.04 Cover four (4) protruding screw ends in angle plate to top corner

15 Stair S3E.04 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

16 Stair S3E.04 Install door stop

17 Stair S3E.04 Install door closer

18 Stair S3E.04 Remove paint stains to top edges of skirting to landing and stairs throughout

19 Stair S3E.04 Door Signage

20 Stair S3E.04 Fire /Smoke seal threshold required to Door

AMERICA HOUSE

Page 48: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 48/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor Vestibule S3E.03 Remove paint to South Door and Frames

2 Corridor Vestibule S3E.03 Fix handles to door South and make good

3 Corridor Vestibule S3E.03 Intumescent strip is not complete to both frame bases of Door South

4 Corridor Vestibule S3E.03 Fixing screws to frame protrude and are to be refixed to Door South

5 Corridor Vestibule S3E.03 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Corridor Vestibule S3E.03 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Corridor Vestibule S3E.03 Install door stop to Door South

8 Corridor Vestibule S3E.03 Install door closer to Door South

9 Corridor Vestibule S3E.03 Paint ceiling

10 Corridor Vestibule S3E.03 Seal two (2) holes in wall through which pipes/conduit pass (South)

11 Corridor Vestibule S3E.03 Refix steel conduit with proper fixings to Light Switch near Door South

12 Corridor Vestibule S3E.03 Remove paint from conduit near Door South

13 Corridor Vestibule S3E.03 Make good to two (2) holes near Door South

14 Corridor Vestibule S3E.03 Running Man sign obstructs the sprinkler head in operation mode and needs to be reviewed

15 Corridor Vestibule S3E.03 Carbon Monoxide Warning sign obstructs the operation of the sprinkler head and requires to be relocated

16 Corridor Vestibule S3E.03 Carbon Monoxide sign to have English Warning

17 Corridor Vestibule S3E.03 Clean paint etc from two (2) light fittings

18 Corridor Vestibule S3E.03 Remove red paint stains from wall generally

19 Corridor Vestibule S3E.03 Make good round Fire Damper Grille panel (Lower)

20 Corridor Vestibule S3E.03 Make good round Fire Damper Grille panel (Upper)

21 Corridor Vestibule S3E.03 Provide proper locking device to Lower Fire Damper Grille

22 Corridor Vestibule S3E.03 Provide proper locking device to Upper Fire Damper Grille

23 Corridor Vestibule S3E.03 Make good ceiling at northeast corner of corridor

24 Corridor Vestibule S3E.03 Refix steel conduit with proper fixings to Light Switch near Door North25 Corridor Vestibule S3E.03 Remove paint from conduit near Door North

26 Corridor Vestibule S3E.03 Remove labels from Door North

27 Corridor Vestibule S3E.03 Fix handles to door North and make good

28 Corridor Vestibule S3E.03 Intumescent strip is not complete to both frame bases of Door North

29 Corridor Vestibule S3E.03 Fixing screws to frame protrude and are to be refixed to Door North

30 Corridor Vestibule S3E.03 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Corridor Vestibule S3E 03 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

AMERICA HOUSE

Page 49: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 49/407

Ref. Location Defect

No.

34 Corridor Vestibule S3E.03 Seal wall where small pipe passes through North Wall both sides

35 Corridor Vestibule S3E.03 Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box

36 Corridor Vestibule S3E.03 Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

37 Corridor Vestibule S3E.03 Seal openings between Fire Hose reel (FHE) door frame and blockwork all round

38 Corridor Vestibule S3E.03 Remove masking tape to FHE Door panel frames

39 Corridor Vestibule S3E.03 Remove paint on door to FHE

40 Corridor Vestibule S3E.03 Make good door cill inside FHE

41 Corridor Vestibule S3E.03 Seal pipe holes Two (2) in ceiling slab

42 Corridor Vestibule S3E.03 Inside this duct the two walls to the HVAC shafts have not been installed and require to be executed

43 Corridor Vestibule S3E.03 Wall to LH side of FHE is not complete at the upper level and needs to be completed

44 Corridor Vestibule S3E.03 Tidy up blockwork above door and generally

45 Corridor Vestibule S3E.03 Remove timber and wood around HVAC vent shaft

46 Corridor Vestibule S3E.03 Install access cover and frame to Dry Riser Outlet

47 Corridor Vestibule S3E.03 Provide Type C connection to Dry Riser

48 Corridor Vestibule S3E.03 Seal in FHE to vent HVAC at slab level ceiling

49 Corridor Vestibule S3E.03 Remove paint to top edges of skirting throughout

50 Corridor Vestibule S3E.03 Provide angle steel threshold step to Door South and paint with black and yellow diagonal stripes

51 Corridor Vestibule S3E.03 Provide angle steel threshold step to Door North and paint with black and yellow diagonal stripes

52 Corridor Vestibule S3E.03 Fire/Smoke threshold seal required to Door North

53 Corridor Vestibule S3E.03 Fire/Smoke threshold seal required to Door South

AMERICA HOUSE

Page 50: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 50/407

Ref. Location Defect

No.

1 Service Lift Vestibule S3E.05 Replace damaged door frame

2 Service Lift Vestibule S3E.05 Fit door handles

3 Service Lift Vestibule S3E.05 Tidy up door seal to LH side of door

4 Service Lift Vestibule S3E.05 Fill in hole to door head frame

5 Service Lift Vestibule S3E.05 Seal hole to door bulkhead where pipes pass through

6 Service Lift Vestibule S3E.05 Fixing screws to frame protrude and are to be ref ixed to Door

7 Service Lif t Vestibule S3E.05 Cover four (4) protruding screw ends in angle plate to top corner to Door

8 Service Lift Vestibule S3E.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Lift Vestibule S3E.05 Remove red paint daubs on walls

10 Service Lift Vestibule S3E.05 Inner leaf of door is binding on the head frame and does not close properly and requires adjustment

11 Service Lift Vestibule S3E.05 Outer leaf of door is binding on the head frame and requires to be adjusted

12 Service Lift Vestibule S3E.05 Skirting is fixed with panel pins and requires to fixed with adhesive or better

13 Service Lift Vestibule S3E.05 Paint ceiling

14 Service Lift Vestibule S3E.05 Make good paint work to LH side of Service Lift Frames

15 Service Lift Vestibule S3E.05 Install door stops to Doors

16 Service Lift Vestibule S3E.05 Clean paint off Service Lift Door Frames

17 Service Lift Vestibule S3E.05 Clean paint off service lift call and indicator wall panels

18 Service Lift Vestibule S3E.05 Remove all protective covering from Lift Doors

19 Service Lift Vestibule S3E.05 Replace light diffuser as not standard

20 Service Lift Vestibule S3E.05 Seal conduit hole at ceiling level

21 Service Lift Vestibule S3E.05 Provide angle steel threshold step to Door North and paint with black and yellow diagonal stripes

22 Service Lift Vestibule S3E.05 Door Signage

23 Service Lift Vestibule S3E.05 Fire/Smoke threshold seal required to entry door

AMERICA HOUSE

Page 51: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 51/407

Ref. Location Defect

No.

1 Telephone Closet S3E.13 Prepare floor to be level

2 Telephone Closet S3E.13 Paint floor

3 Telephone Closet S3E.13 Seal wall hole (East Upper) where conduit tray passes through into Car Park Area

4 Telephone Closet S3E.13 Seal wall hole (West Upper) where conduit tray passes through into Car Park Area

5 Telephone Closet S3E.13 Align four (4) control boxes on west wall

6 Telephone Closet S3E.13 Clean all paint and cement grout of conduits

7 Telephone Closet S3E.13 Generally tidy up wires in cable trays

8 Telephone Closet S3E.13 Clean light fitting

9 Telephone Closet S3E.13 Make good joint between wall and floor

10 Telephone Closet S3E.13 Remove concrete snots etc to wall and paint

11 Telephone Closet S3E.13 Remove labels to door

12 Telephone Closet S3E.13 Fixing screws to frame protrude and are to be refixed to Door

13 Telephone Closet S3E.13 Cover four (4) protruding screw ends in angle plate to top corner to Door

14 Telephone Closet S3E.13 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

15 Telephone Closet S3E.13 Intumescent strip is not complete to both frame bases of Door

16 Telephone Closet S3E.13 Intumescent strip is not complete to door head frame

17 Telephone Closet S3E.13 Install door handles

18 Telephone Closet S3E.13 Install door stop

19 Telephone Closet S3E.13 Install door closer

20 Telephone Closet S3E.13 Clean threshold plate and paint

21 Telephone Closet S3E.13 Paint ceiling

22 Telephone Closet S3E.13 Door Signage

23 Telephone Closet S3E.13 Fire/Smoke threshold seal required to entry door

Page 52: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 52/407

AMERICA HOUSE

Page 53: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 53/407

Ref. Location Defect

No.

1 Lift Lobby S3E.01 Socket Outlet externally on Wall C16/17 has unconnected wires to LH of Door

2 Lift Lobby S3E.01 Fixing screws to frame protrude and are to be refixed to Double Door South

3 Lift Lobby S3E.01 Cover four (4) protruding screw ends in angle plate to top corners to Double Door South

4 Lift Lobby S3E.01 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

5 Lift Lobby S3E.01 Intumescent strip is not complete to both frame bases of Door jambs

6 Lift Lobby S3E.01 Intumescent strip is not complete to door head frame

7 Lift Lobby S3E.01 Install permanent door handles Door South

8 Lift Lobby S3E.01 Install door stops to Double Door South

9 Lift Lobby S3E.01 Install door closers and selector to Door South

10 Lift Lobby S3E.01 Clean threshold plate and paint Door South

11 Lift Lobby S3E.01 Remove all protective covering to Double Door South

12 Lift Lobby S3E.01 Intumescent strip to meeting stile is damaged and to be replaced to Door South

13 Lift Lobby S3E.01 Remove red paint stain on Door Frame (South)

14 Lift Lobby S3E.01 Make good to rectangular hole in head frame Door South

15 Lift Lobby S3E.01 Fixing screws to frame protrude and are to be refixed to Double Door North

16 Lift Lobby S3E.01 Cover four (4) protruding screw ends in angle plate to top corners to Double Door North

17 Lift Lobby S3E.01 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

18 Lift Lobby S3E.01 Intumescent strip is not complete to RH frame of Door North

19 Lift Lobby S3E.01 There is no intumescent strip to LH Door Frame of Door North

20 Lift Lobby S3E.01 Intumescent strip is not complete to door head frame

21 Lift Lobby S3E.01 Install permanent door handles on Double Door North

22 Lift Lobby S3E.01 Install door stops to Double Door North

23 Lift Lobby S3E.01 Install door closers and selector to Double Door North

24 Lift Lobby S3E.01 Clean threshold plate and paint to Double Door North25 Lift Lobby S3E.01 Remove all protective covering to Door North

26 Lift Lobby S3E.01 Intumescent strip to meeting stile is missing and to be replaced to Door North

27 Lift Lobby S3E.01 Outer North Door leaf (LH) scrapes along the floor surface and requires to be reset

28 Lift Lobby S3E.01 Make good to rectangular hole in head frame Door North

29 Lift Lobby S3E.01 Finish floor covering paint around door jamb bases at Double Door North

30 Lift Lobby S3E.01 Refix skirting with proper fixing system and remove panel pins throughout

31 Lift Lobby S3E 01 Fix missing skirting to North and East walls with proper system

AMERICA HOUSE

Page 54: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 54/407

Ref. Location Defect

No.

34 Lift Lobby S3E.01 Make good to ceiling where rebar reinforcement is exposed

35 Lift Lobby S3E.01 Remove piece of timber formwork still attached to the ceiling soffit and make good

36 Lift Lobby S3E.01 Seal two (2) holes in wall at northwest corner for small dia. Pipes

37 Lift Lobby S3E.01 Seal one (1) hole in southwest corner wall for small dia pipe

38 Lift Lobby S3E.01 Firm up supports of sprinkler pipes within this area

39 Lift Lobby S3E.01 Clean two (2) light fittings of paint and dirt inside

40 Lift Lobby S3E.01 Make good to wall returns and arrises to both sides of door to store and repaint

41 Lift Lobby S3E.01 Make good to hole in ceiling in northwest corner for conduit

42 Lift Lobby S3E.01 Make good hole in North wall above door for conduit

43 Lift Lobby S3E.01 Finish floor paint finish along East Wall where not completed

44 Lift Lobby S3E.01 Remove protective covering from Lift Doors and Frames

45 Lift Lobby S3E.01 Clean out water in base of Lift Shaft PE 7 and effect repair

46 Lift Lobby S3E.01 Remove paint to frames of lift shaft doors

47 Lift Lobby S3E.01 Remove all builder's debris in base of Lift Shaft PE7

48 Lift Lobby S3E.01 Carbon Monoxide Warning to also be in English

49 Lift Lobby S3E.01 Make good hole in ceiling in Southwest area

50 Lift Lobby S3E.01 Clean grill on West Wall of paint etc.

51 Lift Lobby S3E.01 Tidy up conduit on north side to light fitting conduits to both sides

52 Lift Lobby S3E.01 Provide angle steel threshold step to Door North and paint with black and yellow diagonal stripes

53 Lift Lobby S3E.01 Provide angle steel threshold step to Door South and paint with black and yellow diagonal stripes

54 Lift Lobby S3E.01 Door Signage South

55 Lift Lobby S3E.01 Door Signage North

56 Lift Lobby S3E.01 Fire/Smoke threshold seal required to entry door South

57 Lift Lobby S3E.01 Fire/Smoke threshold seal required to entry door North58

59

60

61

62

63

64

AMERICA HOUSE

Page 55: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 55/407

Ref. Location Defect

No.

1 Corridor Vestibule B/C 18/19 S3E.06 Remove paint and cement to South Door and Frames

2 Corridor Vestib B/C 18/19 S3E.06 Fix handles to door South and make good

3 Corridor Vestib B/C 18/19 S3E.06 Intumescent strip is not complete to both frame bases of Door South

4 Corridor Vestib B/C 18/19 S3E.06 Fixing screws to frame protrude and are to be refixed to Door South

5 Corridor Vestib B/C 18/19 S3E.06 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Corridor Vestib B/C 18/19 S3E.06 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Corridor Vestib B/C 18/19 S3E.06 Install door stop to Door South

8 Corridor Vestib B/C 18/19 S3E.06 Install door closer to Door South

9 Corridor Vestib B/C 18/19 S3E.06 Paint ceiling

10 Corridor Vestib B/C 18/19 S3E.06 Seal two (2) holes in wall through which pipes/conduit pass (South)

11 Corridor Vestib B/C 18/19 S3E.06 Refix steel conduit with proper fixings to Light Switch near Door South

12 Corridor Vestib B/C 18/19 S3E.06 Remove paint from conduit near Door South

13 Corridor Vestib B/C 18/19 S3E.06 Make good to two (2) holes above Door South

14 Corridor Vestib B/C 18/19 S3E.06 Running Man sign obstructs the sprinkler head in operation mode and needs to be reviewed

15 Corridor Vestib B/C 18/19 S3E.06 Carbon Monoxide sign to have English Warning

16 Corridor Vestib B/C 18/19 S3E.06 Remove labels from Door South

17 Corridor Vestib B/C 18/19 S3E.06 Clean paint etc from two (2) light fittings

18 Corridor Vestib B/C 18/19 S3E.06 Remove red paint stains from wall generally

19 Corridor Vestib B/C 18/19 S3E.06 Make good round Fire Damper Grille panel (Lower)

20 Corridor Vestib B/C 18/19 S3E.06 Make good round Fire Damper Grille panel (Upper)

21 Corridor Vestib B/C 18/19 S3E.06 Provide proper locking device to Lower Fire Damper Grille

22 Corridor Vestib B/C 18/19 S3E.06 Provide proper locking device to Upper Fire Damper Grille

23 Corridor Vestib B/C 18/19 S3E.06 Remove paint from door and frames North

24 Corridor Vestib B/C 18/19 S3E.06 Refix steel conduit with proper fixings to Light Switch near Door North25 Corridor Vestib B/C 18/19 S3E.06 Remove paint from conduit near Door North

26 Corridor Vestib B/C 18/19 S3E.06 Remove labels from Door North

27 Corridor Vestib B/C 18/19 S3E.06 Fix handles to door North and make good

28 Corridor Vestib B/C 18/19 S3E.06 Intumescent strip is not complete to both frame bases of Door North

29 Corridor Vestib B/C 18/19 S3E.06 Fixing screws to frame protrude and are to be refixed to Door North

30 Corridor Vestib B/C 18/19 S3E.06 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Corridor Vestib B/C 18/19 S3E 06 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

AMERICA HOUSE

Page 56: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 56/407

Ref. Location Defect

No.

34 Corridor Vestibule B/C 18/19 S3E.06 Seal wall where small pipe passes through North Wall both sides

35 Corridor Vestib B/C 18/19 S3E.06 Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box

36 Corridor Vestib B/C 18/19 S3E.06 Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

37 Corridor Vestib B/C 18/19 S3E.06 Seal openings between Fire Hose reel (FHE) door frame and blockwork all round

38 Corridor Vestib B/C 18/19 S3E.06 Remove masking tape to FHE Door panel frames

39 Corridor Vestib B/C 18/19 S3E.06 Remove paint on door to FHE

40 Corridor Vestib B/C 18/19 S3E.06 Make good door cill inside FHE

41 Corridor Vestib B/C 18/19 S3E.06 Seal pipe holes Two (2) in ceiling slab

42 Corridor Vestib B/C 18/19 S3E.06 Inside this duct the two wall to the HVAC shafts have not been installed and require to be executed

43 Corridor Vestib B/C 18/19 S3E.06 Wall to RH side of FHE is not complete at the upper level and needs to be completed

44 Corridor Vestib B/C 18/19 S3E.06 Clean out building debris and remove

45 Corridor Vestib B/C 18/19 S3E.06 Seal to HVAC vent at slab

46 Corridor Vestib B/C 18/19 S3E.06 Install access cover and frame to Dry Riser Outlet

47 Corridor Vestib B/C 18/19 S3E.06 Provide Type C connection to Dry Riser

48 Corridor Vestib B/C 18/19 S3E.06 Floor tiling is uneven and needs to be levelled and repolished

49 Corridor Vestib B/C 18/19 S3E.06 Seal wall to South Wall where small pipes passes through

50 Corridor Vestib B/C 18/19 S3E.06 Make good skirting to RH side of Door South

51 Corridor Vestib B/C 18/19 S3E.06 Make good hole above Upper Fire Damper Grille

52 Corridor Vestib B/C 18/19 S3E.06 Fire Damper Door Upper fouls the Running Man sign and RMS to be relocated

53 Corridor Vestib B/C 18/19 S3E.06 Clean paint stains on Fire Damper Upper Grille

54 Corridor Vestib B/C 18/19 S3E.06 Make good hole above Lower Fire Damper Grille

55 Corridor Vestib B/C 18/19 S3E.06 Refit grille door to Lower Fire Damper Panel

56 Corridor Vestib B/C 18/19 S3E.06 Make good hole at conduit above Fire Damper and at Light Fitting on ceiling

57 Corridor Vestib B/C 18/19 S3E.06 Make good skirting to LH side of Door North58 Corridor Vestib B/C 18/19 S3E.06 Make good skirting to RH side of Door North

59 Corridor Vestib B/C 18/19 S3E.06 Make good at slab ceiling near Door North for conduit entry to light switch

60 Corridor Vestib B/C 18/19 S3E.06 Remove paint from skirting top edges throughout

61 Corridor Vestib B/C 18/19 S3E.06 Provide angle steel threshold step to Door North and paint with black and yellow diagonal stripes

62 Corridor Vestib B/C 18/19 S3E.06 Provide angle steel threshold step to Door South and paint with black and yellow diagonal stripes

63 Corridor Vestib B/C 18/19 S3E.06 Fire/Smoke threshold seal required to entry door South

64 Corridor Vestib B/C 18/19 S3E 06 Fire/Smoke threshold seal required to entry door North

AMERICA HOUSE

Page 57: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 57/407

Ref. Location Defect

No.

1 Storage Area S3E.17 Prepare and paint ceiling

2 Storage Area S3E.17 Prepare and paint walls

3 Storage Area S3E.17 Prepare and paint floor

4 Storage Area S3E.17 Install fluorescent light with light switch and conduit

5 Storage Area S3E.17 Install smoke detector with cable etc.

6 Storage Area S3E.17 Install skirting

7 Storage Area S3E.17 Make good formwork fixing holes twenty four (24) to concrete walls8 Storage Area S3E.17 Repair temporary bulkhead lining above entry door and seal

9 Storage Area S3E.17 Remove paint and cement to Door and Frames

10 Storage Area S3E.17 Outer handle is loose and needs to be replaced with permanent handle

11 Storage Area S3E.17 Inner handle is damaged and to be replaced

12 Storage Area S3E.17 Intumescent strip is not complete to RH door jamb frame and to be replaced

13 Storage Area S3E.17 Intumescent strip to LH door jamb is missing and to be installed

14 Storage Area S3E.17 Intumescent strip to head frame is missing and to be installed

15 Storage Area S3E.17 Fixing screws to frame protrude and are to be refixed to Door South

16 Storage Area S3E.17 Cover four (4) protruding screw ends in angle plate to top corner to Door South

17 Storage Area S3E.17 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

18 Storage Area S3E.17 Install door stop to Door

19 Storage Area S3E.17 Install door closer to Door

20 Storage Area S3E.17 Door does not close properly and to be reset

21 Storage Area S3E.17 Install sprinkler with pipework etc.

22 Storage Area S3E.17 Door signage

23 Storage Area S3E.17 Fire/Smoke seal threshold required to entry door

AMERICA HOUSE

Page 58: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 58/407

Ref. Location Defect

No.

1 Egress Stair S3E.07 Replace one (1) chipped stair step

2 Egress Stair S3E.07 Clean down steps of dirt marks, concrete etc complete

3 Egress Stair S3E.07 Floor tiling to mid landing is uneven and to be levelled and resealed/polished

4 Egress Stair S3E.07 Floor tiling to stair floor is uneven and to be levelled and resealed/polished and insert missing grout between some tiles

5 Egress Stair S3E.07 Clean light to mid landing and make good to three (3) loose plastic fixing lugs

6 Egress Stair S3E.07 Change one of the fluorescent tubes as they are different colours

7 Egress Stair S3E.07 Make good to damaged wall at mid landing to stair divider wall8 Egress Stair S3E.07 Make good debonded skirting at mid landing to stair at divider wall

9 Egress Stair S3E.07 Make good holes in wall to RH of lower stair flight at sixth (6th) step

10 Egress Stair S3E.07 Insert Stair Pressurization Grille etc. to Base landing

11 Egress Stair S3E.07 Remove paint from Running Man Sign

12 Egress Stair S3E.07 Clean Light Fitting at Base Level

13 Egress Stair S3E.07 Make good to wall at conduit above entry base door

14 Egress Stair S3E.07 Remove paint to Base Entry Door and Frames

15 Egress Stair S3E.07 Fixing screws to frame protrude and are to be refixed to Door South

16 Egress Stair S3E.07 Cover four (4) protruding screw ends in angle plate to top corner to Door South

17 Egress Stair S3E.07 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

18 Egress Stair S3E.07 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced

19 Egress Stair S3E.07 Intumescent strip to head frame is missing and to be installed

20 Egress Stair S3E.07 Remove all protective covering that remains

21 Egress Stair S3E.07 Fix missing strike plate to open door jamb

22 Egress Stair S3E.07 Fix missing door handles

23 Egress Stair S3E.07 Install door stop to Door

24 Egress Stair S3E.07 Install door closer to Door25 Egress Stair S3E.07 Remove manufacturer's labels on door surface

26 Egress Stair S3E.07 Door signage

27 Egress Stair S3E.07 Remove paint from top edge of skirting to floor, landings and stairs

28 Egress Stair S3E.07 Fire/Smoke seal threshold required to entry door  

AMERICA HOUSE

Page 59: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 59/407

Ref. Location Defect

No.

1 ALA Vestibule S3E.11 Prepare and paint floor

2 ALA Vestibule S3E.11 Remove general cement grout from all conduits

3 ALA Vestibule S3E.11 Insert proper support holdfasts to sprinkler pipe installation

4 ALA Vestibule S3E.11 Make good to conduit on wall near entry door that has been flattened by the application of another conduit

5 ALA Vestibule S3E.11 Electrical junction box has two references deleted and is not identified

6 ALA Vestibule S3E.11 Running Man Sign is squint and to be levelled

7 ALA Vestibule S3E.11 Remove timber formwork to entry door soffit and make good8 ALA Vestibule S3E.11 Fill in wall hole to LH of West Wall

9 ALA Vestibule S3E.11 Paint wall where repairs carried out

10 ALA Vestibule S3E.11 Floor wet - investigate and resolve source

11 ALA Vestibule S3E.11 Remove four (4) nails in wall above entry door and make good

12 ALA Vestibule S3E.11 Paint wall in two areas behind and around wall fixed conduits

13 ALA Vestibule S3E.11 Remove all loose tape from ceiling soffit

14 ALA Vestibule S3E.11 Paint ceiling

15 ALA Vestibule S3E.11 Electrical Cabinet TACA-E install missing cover plates internally

16 ALA Vestibule S3E.11 Make good wall above door to Main ALA Room

17 ALA Vestibule S3E.11 Make good to three (3) holes in wall to Main ALA

18 ALA Vestibule S3E.11 Seal conduit holes two (2) no to LH side of door to Main ALA

AMERICA HOUSE

Page 60: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 60/407

Ref. Location Defect

No.

1 ALA SHELTER S3E.12 Make good to two (2) areas of honeycombed wall to RH of Main Entry Door and repaint

2 ALA SHELTER S3E.12 Clean up conduit generally of cementitious grout

3 ALA SHELTER S3E.12 ALA Vent. Machinery is sitting on a 'bodged up' pile of timber cross sticks and needs a proper concrete or metal base

4 ALA SHELTER S3E.12 Paint floor under ALA vent machinery it metal trestle support is provided

5 ALA SHELTER S3E.12 Running Man sign is squint and to be levelled

6 ALA SHELTER S3E.12 Make good to hole above Running Man Sign

7 ALA SHELTER S3E.12 Paint Wall between A-C 238 ALA SHELTER S3E.12 Make good to honeycombed wall on Wall D 21/22 North and repaint

9 ALA SHELTER S3E.12 Clean out debris in wall holes to vestibule

10 ALA SHELTER S3E.12 Make good to formwork fixing holes (5 No) on wall D21 - C22 and repaint

11 ALA SHELTER S3E.12 Paint floor throughout

12 ALA SHELTER S3E.12 Remove red paint stains on walls

13 ALA SHELTER S3E.12 On first fin wall remove hole stuffed with paper make good and repaint

14 ALA SHELTER S3E.12 Remove timber packer at wall head on fin walls No 4 and make good

15 ALA SHELTER S3E.12 Make good to hole at high level above third opening in finwall and repaint

16 ALA SHELTER S3E.12 Remove loose tape on ceiling

17 ALA SHELTER S3E.12 Make good hole in centre of main ALA ceiling and repaint

18 ALA SHELTER S3E.12 Make good to small pipe passing through wall above entry door of Main ALA

19 ALA SHELTER S3E.12 Make good door jamb returns all round to Main ALA entry door and repaint

AMERICA HOUSE

Page 61: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 61/407

Ref. Location Defect

No.

1 Fire Pump Room S3E.10 Water leaks as water all over the space - investigate and dry out

2 Fire Pump Room S3E.10 Remove all MET and builder's debris

3 Fire Pump Room S3E.10 Change labels to Electrical control box to RH of entry door on West Wall as wrongly applied

4 Fire Pump Room S3E.10 Make good to three (3) holes on West wall including one conduit pipe and repaint

5 Fire Pump Room S3E.10 Make good to three (3) pipes hole in ceiling next to West Wall and repaint

6 Fire Pump Room S3E.10 Make good to three (3) formwork fixtures holes in west wall and repaint

7 Fire Pump Room S3E.10 Make good to ten (1) formwork holes in North Wall and repaint8 Fire Pump Room S3E.10 Remove steel rod in northwest corner near floor and make good

9 Fire Pump Room S3E.10 Clean out central drain gully

10 Fire Pump Room S3E.10 Paint gulley drain grating

11 Fire Pump Room S3E.10 Connect or remove two wires that are unconnected near pump motors on North Wall

12 Fire Pump Room S3E.10 Install all equipment and flow labels throughout

13 Fire Pump Room S3E.10 Make good to ceiling slab at sprinkler pipe main supply

14 Fire Pump Room S3E.10 Make good hole in southwest corner to conduit and cables and repaint

15 Fire Pump Room S3E.10 Make good hole in southwest corner to SVP pipe and repaint

16 Fire Pump Room S3E.10 Clean dirt and debris in Electrical Unit TPI9E

17 Fire Pump Room S3E.10 Provide handrail to steel stair to level above

18 Fire Pump Room S3E.10 Make good to North Wall where SVP pipes passes through towards East Wall

19 Fire Pump Room S3E.10 Paint Floor

20 Fire Pump Room S3E.10 Paint ceiling

21 Fire Pump Room S3E.10 Connect or remove loose wire on north wall that is unconnected

22 Fire Pump Room S3E.10 Remove six (6) nails to northeast corner and make good

23 Fire Pump Room S3E.10 Provide the fixing screws to eight (8) control boxes on North Wall

24 Fire Pump Room S3E.10 Complete conduit cable connections on North Wall25 Fire Pump Room S3E.10 Paint rusting baseplate to pumps on east side of room

26 Fire Pump Room S3E.10 Make good around ceiling opening to access ladder

27 Fire Pump Room S3E.10 Remove two (2) nails at access ladder ceiling opening and make good

28 Fire Pump Room S3E.10 Remove steel fixing plate at access ladder opening and make good

29 Fire Pump Room S3E.10 Make good concrete mound at southwest corner which is an eyesore

30 Fire Pump Room S3E.10 Remove highspot in floor slab to RH of Entry Door and make good

31 Fire Pump Room S3E 10 Fixing screws to frame protrude and are to be refixed to door

AMERICA HOUSE

Page 62: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 62/407

Ref. Location Defect

No.

34 Fire Pump Room S3E.10 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced

35 Fire Pump Room S3E.10 Clean out frames at door base

36 Fire Pump Room S3E.10 Remove all protective covering that remains

37 Fire Pump Room S3E.10 Fix missing strike plate to open door jamb

38 Fire Pump Room S3E.10 Fix missing door handles

39 Fire Pump Room S3E.10 Install door stop to Door

40 Fire Pump Room S3E.10 Install door closer to Door41 Fire Pump Room S3E.10 Remove manufacturer's labels on door surface

42 Fire Pump Room S3E.10 Make good threshold concrete to room as uneven and rough

43 Fire Pump Room S3E.10 Seal door frame all round

44 Fire Pump Room S3E.10 Make good to small hole in wall to the right hand side of the door entry

45 Fire Pump Room S3E.10 Make good to rough door lintol soffit at RH side

46 Fire Pump Room S3E.10 Remove paint on door and frames

47 Fire Pump Room S3E.10 Fire Fighting equipment is missing

48 Fire Pump Room S3E.10 Door Signage

49 Fire Pump Room S3E.10 Fire/Smoke seal threshold required to entry door50 Fire Pump Room S3E.10 Fire Alarm to be installed

AMERICA HOUSE

Page 63: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 63/407

Ref. Location Defect

No.

1 Service Corridor SE3.08 Remove two pieces of wire above door to Fire Pump Room and make good

2 Service Corridor SE3.08 Remove paint and cement to conduit to left and above door to Fire Pump Room

3 Service Corridor SE3.08 Remove timber formwork left in hole formed in southeast corner at ceiling level and make good

4 Service Corridor SE3.08 Seal duct hole at ceiling level in southeast corner and make good both sides

5 Service Corridor SE3.08 Remove six (6) nails left in ceiling slab near entry to Fire Pump Room and make good

6 Service Corridor SE3.08 Paint ceiling

7 Service Corridor SE3.08 Seal large hole in wall to southwest corner with extract duct and tray and make good8 Service Corridor SE3.08 Make good hole to LH side of entry door to Fire Pump Room at high level

9 Service Corridor SE3.08 Make good to wall where flexible conduit passes through and repaint

10 Service Corridor SE3.08 Remove paint on black flexible conduit at high level on splay wall B22 to A23

11 Service Corridor SE3.08 Make good to wall to LH side of entry door to Fire Pump Room and repaint

12 Service Corridor SE3.08 Remove paint on conduit at entry door RH to Car Park Area and along ceiling

13 Service Corridor SE3.08 Remove cement and paint on conduit at high level running along wall to Annex Room S3E.09

14 Service Corridor SE3.08 Clean all three (3) lights fixed as bulkheads to wall

15 Service Corridor SE3.08 Fixing screws to frame protrude and are to be refixed to door

16 Service Corridor SE3.08 Cover four (4) protruding screw ends in angle plate to top corner to door

17 Service Corridor SE3.08 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

18 Service Corridor SE3.08 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced

19 Service Corridor SE3.08 Clean out frames at door base

20 Service Corridor SE3.08 Remove all protective covering that remains

21 Service Corridor SE3.08 Remove metal shim between frame and sub-frame near door strike plate

22 Service Corridor SE3.08 Fix missing door handles

23 Service Corridor SE3.08 Install door stop to Door

24 Service Corridor SE3.08 Install door closer to Door

25 Service Corridor SE3.08 Remove manufacturer's labels on door surface

26 Service Corridor SE3.08 Seal door frame all round

27 Service Corridor SE3.08 Remove paint on door and frames

28 Service Corridor SE3.08 Door Signage

29 Service Corridor SE3.08 Fire/Smoke seal threshold required to entry door

30 Service Corridor SE3.08 Fire Alarm to be installed

AMERICA HOUSE

Page 64: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 64/407

Ref. Location Defect

No.

1 Annex S3E.09 Fixing screws to frame protrude and are to be refixed to door

2 Annex S3E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

3 Annex S3E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Annex S3E.09 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced

5 Annex S3E.09 Clean out frames at door base

6 Annex S3E.09 Remove all protective covering that remains

7 Annex S3E.09 Intumescent strip is loose on head frame and to be refixed8 Annex S3E.09 Fix missing door handles

9 Annex S3E.09 Install door stop to Door

10 Annex S3E.09 Install door closer to Door

11 Annex S3E.09 Remove manufacturer's labels on door surface

12 Annex S3E.09 Replace damaged strike plate

13 Annex S3E.09 Remove cement and paint on door and frames

14 Annex S3E.09 Intumescent strip is short on head frame to hinge jambs

15 Annex S3E.09 Remove four (4) nails in ceiling near south wall and make good

16 Annex S3E.09 Seal rectangular hole in West wall at high level

17 Annex S3E.09 Complete paint to wall near cable trunking on West Wall

18 Annex S3E.09 Make good to hole at high level on West wall near cable tray

19 Annex S3E.09 Paint West wall where timber plate removed

20 Annex S3E.09 Remove three nails on East Wall and make good

21 Annex S3E.09 Tidy up seal to small pipe at East Wall above where timber batten removed

22 Annex S3E.09 Remove red paint daubs to walls

23 Annex S3E.09 Finish paint missing at various parts of the ceiling

24 Annex S3E.09 Generally touch up walls where paint poor or missing

25 Annex S3E.09 Repaint wall and ceiling at wall/ceiling junction the proper colours

26 Annex S3E.09 Seal rectangular hole in East wall at high level in south east corner of room

27 Annex S3E.09 Make good to wall where conduit and light switch box has been relocated to RH of entry door and repaint

28 Annex S3E.09 Make good to six (6) formwork fixtures holes and repaint

29 Annex S3E.09 Clean Two (2) ceiling lights

30 Annex S3E.09 Make good to ceiling above entry door and repaint

31 Annex S3E.09 Remove paint etc to conduits to Rah side of entry door including the switch boxes and plates

AMERICA HOUSE

Page 65: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 65/407

Ref. Location Defect

No.

1 Basement -2 General Area Make good ceiling around SVP at corner A22 including underside of slab

2 Basement -2 General Area Remove concrete dropping to SVP pipe and generally clean up A22

3 Basement -2 General Area Provide impact Protection to SVP Pipe A22

4 Basement -2 General Area Provide impact protection to SVP Pipe A20

5 Basement -2 General Area Provide impact protection to SVP Pipe A18

6 Basement -2 General Area Provide impact protection to SVP Pipe A16

7 Basement -2 General Area Provide impact protection to SVP Pipe A148 Basement -2 General Area Provide impact protection to SVP Pipe D14

9 Basement -2 General Area Provide impact protection to SVP Pipe D16

10 Basement -2 General Area Provide impact protection to SVP Pipe D18

11 Basement -2 General Area Provide impact protection to SVP Pipe D20

12 Basement -2 General Area Provide impact protection to car exhaust extracts A22 LH

13 Basement -2 General Area Provide impact protection to car exhaust extracts A21 RH

14 Basement -2 General Area Provide impact protection to car exhaust extracts A21 LH

15 Basement -2 General Area Provide impact protection to car exhaust extracts A20 RH

16 Basement -2 General Area Provide impact protection to car exhaust extracts A20 LH

17 Basement -2 General Area Provide impact protection to car exhaust extracts A19 RH

18 Basement -2 General Area Provide impact protection to car exhaust extracts A19 LH

19 Basement -2 General Area Provide impact protection to car exhaust extracts A18 RH

20 Basement -2 General Area Provide impact protection to car exhaust extracts A18 LH

21 Basement -2 General Area Provide impact protection to car exhaust extracts A17 RH

22 Basement -2 General Area Provide impact protection to car exhaust extracts A17 LH

23 Basement -2 General Area Provide impact protection to car exhaust extracts A16 RH

24 Basement -2 General Area Provide impact protection to car exhaust extracts A16 LH

25 Basement -2 General Area Provide impact protection to car exhaust extracts A16 LH

26 Basement -2 General Area Provide impact protection to car exhaust extracts A15 RH

27 Basement -2 General Area Provide impact protection to car exhaust extracts A15 LH

28 Basement -2 General Area Provide impact protection to car exhaust extracts A14 RH

29 Basement -2 General Area Provide impact protection to car exhaust extracts A14 LH

30 Basement -2 General Area Provide impact protection to car exhaust extracts A13 LH

31 Basement -2 General Area Provide impact protection to car exhaust extracts Column C19

AMERICA HOUSE

Page 66: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 66/407

Ref. Location Defect

No.

34 Basement -2 General Area Provide impact protection to water supply pipe Column A 20

35 Basement -2 General Area Provide impact protection to water supply pipe Column A 18

36 Basement -2 General Area Provide impact protection to water supply pipe Column A 16

37 Basement -2 General Area Provide impact protection to water supply pipe Column A 14

38 Basement -2 General Area Provide impact protection to water supply pipe Column D 20

39 Basement -2 General Area Provide impact protection to water supply pipe Column D 18

40 Basement -2 General Area Provide impact protection to water supply pipe Column D 1641 Basement -2 General Area Provide impact protection to water supply pipe Column D 14

42 Basement -2 General Area Clean out void between Column Walls A 12 and 13

43 Basement -2 General Area Clean out void between Column Walls D 12 and 13

44 Basement -2 General Area Provide impact Protection to CO Warning Sign A 12

45 Basement -2 General Area Provide impact Protection to CO Warning Sign D 12

46 Basement -2 General Area Provide impact Protection to CO Warning Sign A 17

47 Basement -2 General Area Provide impact Protection to CO Warning Sign D 17

48 Basement -2 General Area Clean out floor drain near D20

49 Basement -2 General Area Paint floor drain grating near D 20

50 Basement -2 General Area Clean out floor drain near D18

51 Basement -2 General Area Paint floor drain grating near D 18

52 Basement -2 General Area Clean out floor drain near D16

53 Basement -2 General Area Paint floor drain grating near D 16

54 Basement -2 General Area Clean out floor drain near D14

55 Basement -2 General Area Paint floor drain grating near D 14

56 Basement -2 General Area Clean out floor drain near A20 as blocked with water inside

57 Basement -2 General Area Paint floor drain grating near A 20

58 Basement -2 General Area Clean out floor drain near A18

59 Basement -2 General Area Paint floor drain grating near A 18

60 Basement -2 General Area Clean out floor drain near A16

61 Basement -2 General Area Paint floor drain grating near A 16

62 Basement -2 General Area Clean out floor drain near A14

63 Basement -2 General Area Paint floor drain grating near A 14

64 Basement -2 General Area Clean concrete group to SVP Pipe at Column A18

AMERICA HOUSE

Page 67: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 67/407

Ref. Location Defect

No.

67 Basement -2 General Area Provide impact protection to wall mounted ventilation unit near Column D14

68 Basement -2 General Area Provide pipe sleeve to SVP pipe at Wall A/B 22 and make good

69 Basement -2 General Area Seal Wall A/B 22 where three (3) conduits pass through wall at high level and make good

70 Basement -2 General Area Seal opening above door to Corridor S2E.08 and make good to both sides

71 Basement -2 General Area Seal around conduits on Wall A/B 22 to RH of door to Service Corridor S2E.08

72 Basement -2 General Area Make good insulation to several pipes that have been damaged and repaired with black tape in A/B 21/22 Area

73 Basement -2 General Area Clean off red paint marks on grille to Car Exhaust ducting in B21/2274 Basement -2 General Area Clean Floor of stain and paint in A/C 21/22

75 Basement -2 General Area Ducts not built in C21 but shown on drawings

76 Basement -2 General Area Provide impact protection to wall mounted ventilation unit near Column D20

77 Basement -2 General Area Provide impact protection to Running Man Sign on column D 20

78 Basement -2 General Area Provide impact protection to Running Man Sign on column B 20

79 Basement -2 General Area Provide impact protection to Running Man Sign on wall C18

80 Basement -2 General Area Provide impact protection to Running Man Sign on wall B18

81 Basement -2 General Area Provide impact protection to Running Man Sign on wall B15

82 Basement -2 General Area Provide impact protection to Running Man Sign on wall C14

83 Basement -2 General Area Make good leak between A21 and A22 and repaint wall

84 Basement -2 General Area Make good leak at D 12/13 and repaint wall

85 Basement -2 General Area Make good to hole in slab around SVP between A 21/22

86 Basement -2 General Area Make good to small hole in splay wall between C21 and B22

87 Basement -2 General Area Make good to splay wall C21/B22 around SVP pipe entry

88 Basement -2 General Area Make good hole to several pipes between B/C 21/22 and remove acrow props that have no warning sign on a main access

89 Basement -2 General Area At C21 make good hole in slab ceiling for Fire Sprinkler supply pipe

90 Basement -2 General Area Realign sprinkler pipes in Area A 20/21

91 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column A20

92 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column A16

93 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column A14

94 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D16

95 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D18

96 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D20

97 Basement -2 General Area Install operator signage to Fire Alarm Button at wall C17 and remove paint

AMERICA HOUSE

Page 68: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 68/407

Ref. Location Defect

No.

100 Basement -2 General Area Install operator signage to Fire Alarm Button at Wall D15

101 Basement -2 General Area Take out temporary electrical supply wire including making good to slab soffit and floor when removed at Wall BC 14

102 Basement -2 General Area Make good to ceiling slab at water pipe at Column A 18

103 Basement -2 General Area Realign sprinkler pipework in Area A 17/18 as not level or straight

104 Basement -2 General Area Replace twisted or distorted hangers to sprinkler installation in Area A 17/18

105 Basement -2 General Area Carbon Monoxide System Warning sign on Column A 17 to be placed vertical

106 Basement -2 General Area Make good to low floor area with water 'ponding' near Area A/B 14/15107 Basement -2 General Area Make good to base of column A14

108 Basement -2 General Area Make good to wall at previous leak between A 13/14

109 Basement -2 General Area Make good to low floor area with water 'ponding' near Area C/D 13/14

110 Basement -2 General Area Make good to low floor area with water 'ponding C/D 17/18

111 Basement -2 General Area Sprinkler handles in D 13/14 are accessible to the General Public and need to be protected

112 Basement -2 General Area Sprinkler pipework in Area D 13/14 to be levelled and realigned properly

113 Basement -2 General Area Remove 150mm piece of timber in wall head at D 14 and make good all round

114 Basement -2 General Area Make good hole in ceiling at water pipe at Column D14

115 Basement -2 General Area Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D14

116 Basement -2 General Area Make good conduit connection to Car Exhaust Grille near Column D14 which is not complete

117 Basement -2 General Area Paint floor between Electrical Closet S2E.17 and Telephone Closet S2E.16

118 Basement -2 General Area Make good to base of column D 14 and repaint as required to floor

119 Basement -2 General Area Make good around SVP pipe at ceiling slab and floor at Column D16

120 Basement -2 General Area Make good to low area to RH of Column Wall D17 with water 'ponding"

121 Basement -2 General Area Make good to ceiling slab around white water feed pipe to Sewage Pump Station Level -3

122 Basement -2 General Area Clean down cement stains on SVP pipe at Column D18

123 Basement -2 General Area Remove 60mm Black pipe and make good holes to floor and ceiling slab etc. at Column D18

124 Basement -2 General Area Realign and level sprinkler pipe installation between D 19/20

125 Basement -2 General Area Warning notice required in area near Column A22 as the clearance height is 1.92 metres

126 Basement -2 General Area Warning Notice needed in Car Park Area B 21/22 as pipes are set at a clearance height of 2.07 metres

127 Basement -2 General Area Warning Notice needed in Car Park Area B/C 21 where pipes are at a clearance height on an access street of 2.07 metres

128 Basement -2 General Area Warning notice needed in Car Park Area B/C 21 as clearance height is 1.87 metres

129 Basement -2 General Area Warning notice needed in Car Park Area A/B 22 at pipe as clearance height is 1.90metres

130 Basement -2 General Area Warning notice needed in Car Park Area B 21/22 as two pipe supports have a clearance height of 1 97metres

AMERICA HOUSE

Page 69: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 69/407

Ref. Location Defect

No.

133 Basement -2 General Area Make good flexible conduit connections to CCTV Camera A21

134 Basement -2 General Area Make good flexible conduit connections to CCTV Camera B18

135 Basement -2 General Area Make good flexible conduit connections to CCTV Camera B14

136 Basement -2 General Area Make good flexible conduit connections to CCTV Camera A12

137 Basement -2 General Area Make good flexible conduit connections to CCTV Camera D12

138 Basement -2 General Area Make good flexible conduit connections to CCTV Camera C14

139 Basement -2 General Area Make good flexible conduit connections to CCTV Camera C18140 Basement -2 General Area Make good to white water pipe at ceiling D18

141 Basement -2 General Area Complete conduit connection to CO Warning Sign A 12

142 Basement -2 General Area Complete conduit connection to CO Warning Sign D 12

143 Basement -2 General Area Complete conduit connection to CO Warning Sign A 17

144 Basement -2 General Area Complete conduit connection to CO Warning Sign D 17

145 Basement -2 General Area Make good painting to black and yellow threshold strip Service Elevator Vestib.

146 Basement -2 General Area Make good painting to black and yellow threshold strip Corridor B14/15 South.

147 Basement -2 General Area Make good painting to black and yellow threshold strip Corridor C14/15 North

148 Basement -2 General Area Make good painting to black and yellow threshold strip Corridor B17/15 South.

149 Basement -2 General Area Make good painting to black and yellow threshold strip Corridor C17/18 North

150 Basement -2 General Area Tidy conduit connections to control panel for Sewage Pumping Station D17/18

151 Basement -2 General Area Make good large rectangular hole in ceiling slab to LH of Column D 19

152 Basement -2 General Area Make good to wall paint near six gang wall switch where missing to LH of Door to Corridor S2E.03 South side

153 Basement -2 General Area Remove red paint stains to wall at duct next to Column D 19

154 Basement -2 General Area Make good to slot hole at high level to RH of Wall Column D 19

155 Basement -2 General Area Seal water pipe at floor level to Column D20 and make good to floor paint

156 Basement -2 General Area Seal holes around three pipes at high level on external wall between D20/21

157 Basement -2 General Area Make good wall paint to RH of Wall Column D 21 on external wall

158 Basement -2 General Area Make good to all door jamb return to Storage Vestibule S2E.14

159 Basement -2 General Area Seal holes to four (4) conduits at wall head to Storage Vestibule S2E.14

160 Basement -2 General Area Make good to formwork fixing holes three (3) no on wall to Storage Vestibule S2E.12

161 Basement -2 General Area Make good to formwork fixing holes four (4) no on wall return C21 near Storage Vestibule S2E.12

162 Basement -2 General Area Make good honeycombing to wall return C21 near Storage Vestibule S2E.12 and repaint

163 Basement -2 General Area Make good to bulkhead panel above door to Storage Vestibule S2E 12

AMERICA HOUSE

Page 70: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 70/407

Ref. Location Defect

No.

166 Basement -2 General Area Make good to two (2) pipes at high level to LH of wall B/C 14

167 Basement -2 General Area Seal pipe on Wall B 14/15 at high level to LH of Door to Stair Vestibule S2E.03

168 Basement -2 General Area Seal holes to conduit and pipes above Door to Stair Vestibule S2E.03 on Wall B14/15

169 Basement -2 General Area Make good joint with floor around Column A14 and repaint as required

170 Basement -2 General Area Seal hole at high level on Wall B 14/15 to RH of door to Stair Vestibule S2E.03

171 Basement -2 General Area Remove paint on conduit near door to Stair Vestibule S2E.03 on Wall B 14/15

172 Basement -2 General Area Provide impact protection to Car Exhaust duct between B/C 15173 Basement -2 General Area Make good around four pipes and conduits at high level on Wall B/C 15

174 Basement -2 General Area Remove Steel rod above Door to Stair Vestibule S2E.03 on Wall C 14/15

175 Basement -2 General Area Make good around two conduits on Wall C 14.15 at high level to LH of door to Stair Vestibule S2E.03

176 Basement -2 General Area Seal pipe at high level to Service Elevator Enclosure LH of door on Wall C 14/15

177 Basement -2 General Area Clean conduit to Fire Alarm near C18

178 Basement -2 General Area Make good to four (4) small holes in ceiling slab at Corner C 18

179 Basement -2 General Area Make good to three (3) formwork fixing holes to Wall C17/18

180 Basement -2 General Area Make good to wall head on Wall C 17/18

181 Basement -2 General Area Clean conduit of paint and cement stains in the area around the Door to Stair Vestibule S2E.06

182 Basement -2 General Area Seal conduit hole on Wall C17/18 to RH of door to Stair Vestibule S2E.06

183 Basement -2 General Area Seal two (2) formwork fixing holes on Wall C17/18 to right of Stair Vestibule S2E.06 door

184 Basement -2 General Area Seal wall at two (2) conduits and two (2) pipes above door to Elevator Lobby S2E.01 on Wall C 16/17

185 Basement -2 General Area Make good to edges and joint to ceiling and floor to duct lining at wall B/C 16/17 to Elevator Lobby S2E.01

186 Basement -2 General Area Make good and seal to pipe at high level to Wall to Elevator Lobby S2E.01 Wall B/C 16/17

187 Basement -2 General Area Make good and seal at high level to two (2) conduits to Wall B 14/15 to Stair S2E.04

188 Basement -2 General Area Fire Fighting equipment is missing

189 Basement -2 General Area Remove red paint on wall near floor B 16/17 and repaint

190 Basement -2 General Area Realign socket outlet on Wall B16/17

191 Basement -2 General Area Make good to wall and floor at floor level to left of South Door to Elevator Room S2E.01 and repaint

192 Basement -2 General Area Parking Bay lines missing to Bay A 21/22

193 Basement -2 General Area Parking Bay lines missing to Bay A 20/21

194 Basement -2 General Area Parking Bay lines missing to Bay A 19/20

195 Basement -2 General Area Seal hole in Wall BC 21 and make good

196 Basement -2 General Area Clean paint of conduit on RH of Wall BC 21

AMERICA HOUSE

Page 71: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 71/407

Ref. Location Defect

No.

1 Egress Stair S2E.04 Clean light at Landing -2

2 Egress Stair S2E.04 Paint divider wall where defaced with graffiti

3 Egress Stair S2E.04 Clean light fitting on landing that is covered in paint etc.

4 Egress Stair S2E.04 Landing tiles are uneven and need to be levelled and repolished

5 Egress Stair S2E.04 Stair are badly stained and need deep cleaned and repolished

6 Egress Stair S2E.04 Floor tiling at -2 is uneven and needs levelled and repolished

7 Egress Stair S2E.04 Fix conduit to Fire Detector which is improperly fixed

8 Egress Stair S2E.04 Remove paint on Running Man sign

9 Egress Stair S2E.04 Remove paint from door and frames

10 Egress Stair S2E.04 Fix permanent handles to doors and make good

11 Egress Stair S2E.04 Remove protective covering that remains on door

12 Egress Stair S2E.04 Intumescent strip is not complete to hinge frame base and loose in some areas

13 Egress Stair S2E.04 Fixing screws to frame protrude and are to be refixed

14 Egress Stair S2E.04 Cover four (4) protruding screw ends in angle plate to top corner

15 Egress Stair S2E.04 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

16 Egress Stair S2E.04 Install door stop17 Egress Stair S2E.04 Install door closer

18 Egress Stair S2E.04 Remove paint stains to top edges of skirting to landing and stairs throughout

19 Egress Stair S2E.04 Intumescent strip is not complete to lock frame base and loose in some areas

20 Egress Stair S2E.04 Door Signage

21 Egress Stair S2E.04 Fire/Smoke Threshold seal is required to door

AMERICA HOUSE

Page 72: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 72/407

Ref. Location Defect

No.

1 Stair Vestibule S2E.03 Remove paint to South Door and Frames

2 Stair Vestibule S2E.03 Fix permanent handles to door South and make good

3 Stair Vestibule S2E.03 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule S2E.03 Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule S2E.03 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule S2E.03 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule S2E.03 Install door stop to Door South8 Stair Vestibule S2E.03 Install door closer to Door South

9 Stair Vestibule S2E.03 Replace damaged door prong receiver in door frame

10 Stair Vestibule S2E.03 Seal two (2) holes in wall through which pipes/conduit pass (South)

11 Stair Vestibule S2E.03 Refix steel conduit with proper fixings to Light Switch near Door South

12 Stair Vestibule S2E.03 Install switch plate to light switch South as currently the wires are unprotected

13 Stair Vestibule S2E.03 Clean conduit to light switch (south) of paint etc

14 Stair Vestibule S2E.03 Running Man sign obstructs the sprinkler head in operation mode and needs to be reviewed

15 Stair Vestibule S2E.03 Carbon Monoxide Warning sign obstructs the operation of the sprinkler head and requires to be relocated

16 Stair Vestibule S2E.03 Carbon Monoxide sign to have English Warning

17 Stair Vestibule S2E.03 Clean paint etc from two (2) light fittings

18 Stair Vestibule S2E.03 Clean paint of grille to Fire Damper Grille (Upper)

19 Stair Vestibule S2E.03 Clean paint of grille to Fire Damper Grille (Lower)

20 Stair Vestibule S2E.03 Make good round Fire Damper Grille panel (Lower)

21 Stair Vestibule S2E.03 Make good round Fire Damper Grille panel (Upper)

22 Stair Vestibule S2E.03 Provide proper locking device to Lower Fire Damper Grille

23 Stair Vestibule S2E.03 Provide proper locking device to Upper Fire Damper Grille

24 Stair Vestibule S2E.03 Refix switch plate to light switch near North Door

25 Stair Vestibule S2E.03 Refix steel conduit with proper fixings to Light Switch near Door North

26 Stair Vestibule S2E.03 Remove paint from conduit near Door North

27 Stair Vestibule S2E.03 Fix permanent handles to door North and make good

28 Stair Vestibule S2E.03 Intumescent strip is not complete to both frame bases of Door North

29 Stair Vestibule S2E.03 Fixing screws to frame protrude and are to be refixed to Door North

30 Stair Vestibule S2E.03 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Stair Vestibule S2E 03 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

Page 73: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 73/407

AMERICA HOUSE

Page 74: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 74/407

Ref. Location Defect

No.

1 Service Elevator Vestibule SE2.05 Paint ceiling

2 Service Elevator Vestibule SE2.05 Fit permanent door handles

3 Service Elevator Vestibule SE2.05 Intumescent strip is short at bases to both jambs and requires to be replaced

4 Service Elevator Vestibule SE2.05 Fill in hole to door head frame

5 Service Elevator Vestibule SE2.05 Seal hole to door bulkhead where pipes pass through

6 Service Elevator Vestibule SE2.05 Fixing screws to frame protrude and are to be refixed to Door

7 Service Elevator Vestibule SE2.05 Cover four (4) protruding screw ends in angle plate to top corner to Door 8 Service Elevator Vestibule SE2.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestibule SE2.05 Remove red paint daubs on walls

10 Service Elevator Vestibule SE2.05 Intumescent strip to meeting style of doors is not the full length and requires to be replaced

11 Service Elevator Vestibule SE2.05 Seal conduit hole above Door North

12 Service Elevator Vestibule SE2.05 Seal hole for sprinkler pipe above Door North

13 Service Elevator Vestibule SE2.05 Skirting is fixed with panel pins and requires to fixed with adhesive or better

14 Service Elevator Vestibule SE2.05 Make good paint work to LH side of Service Lift Frames

15 Service Elevator Vestibule SE2.05 Install door stops to Doors

16 Service Elevator Vestibule SE2.05 Clean paint off Service Lift Door Frames

17 Service Elevator Vestibule SE2.05 Clean paint off service lift call and indicator wall panels

18 Service Elevator Vestibule SE2.05 Remove all protective covering from Lift Doors

19 Service Elevator Vestibule SE2.05 Clean light fitting of paint and dirt inside

20 Service Elevator Vestibule SE2.05 Seal conduit hole at ceiling level

21 Service Elevator Vestibule SE2.05 Install selector and door closers

22 Service Elevator Vestibule SE2.05 Remove paint to door frames

23 Service Elevator Vestibule SE2.05 Relocate sprinkler head at abutting to the soffit of the ceiling which will reduce its effectiveness in the area

24 Service Elevator Vestibule SE2.05 Seal conduit at high level on East Wall

25 Service Elevator Vestibule SE2.05 Remove paint to Arrow Indicator Lift panel

26 Service Elevator Vestibule SE2.05 Make good to floor subsidence near duct to LH side of North Door and repaint etc.

27 Service Elevator Vestibule SE2.05 Fix dome covers to four (4) screws to grille in duct to northwest corner

28 Service Elevator Vestibule SE2.05 Carbon monoxide signage to also be in English

29 Service Elevator Vestibule SE2.05 Refix black/yellow threshold angle

30 Service Elevator Vestibule SE2.05 Repaint black/yellow threshold angle

31 Service Elevator Vestibule SE2 05 Remove masking tape on floor near threshold angle

Page 75: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 75/407

Page 76: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 76/407

AMERICA HOUSE

Page 77: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 77/407

Ref. Location Defect

No.

1 Elevator Lobby S2E.01 Socket Outlet externally on Wall B16/17 to LH of door south has unconnected wires and no plate

2 Elevator Lobby S2E.01 Fixing screws to frame protrude and are to be refixed to Double Door South

3 Elevator Lobby S2E.01 Cover four (4) protruding screw ends in angle plate to top corners to Double Door South

4 Elevator Lobby S2E.01 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

5 Elevator Lobby S2E.01 Intumescent strip is not complete to both frame bases of Door jambs

6 Elevator Lobby S2E.01 Replace keeper to slip bolt to inner door leaf in head frame as damaged

7 Elevator Lobby S2E.01 Install permanent door handles Door South

8 Elevator Lobby S2E.01 Install door stops to Double Door South

9 Elevator Lobby S2E.01 Install door closers and selector to Door South

10 Elevator Lobby S2E.01 Inner door of leaf has a play when closed and requires to be adjusted

11 Elevator Lobby S2E.01 Remove all protective covering to Double Door South

12 Elevator Lobby S2E.01 Clean up lock plate on door south

13 Elevator Lobby S2E.01 Remove paint stains on Door Frame (South)

14 Elevator Lobby S2E.01 Make good to rectangular hole in head frame Door South

15 Elevator Lobby S2E.01 Fixing screws to frame protrude and are to be refixed to Double Door North

16 Elevator Lobby S2E.01 Cover four (4) protruding screw ends in angle plate to top corners to Double Door North 17 Elevator Lobby S2E.01 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

18 Elevator Lobby S2E.01 Adjust inner leaf door as there is play in the closed position

19 Elevator Lobby S2E.01 Remove red paint stains on North door and frames

20 Elevator Lobby S2E.01 Remove wall paint on North door frames

21 Elevator Lobby S2E.01 Install permanent door handles on Double Door North

22 Elevator Lobby S2E.01 Install door stops to Double Door North

23 Elevator Lobby S2E.01 Install door closers and selector to Double Door North

24 Elevator Lobby S2E.01 Remove red paint on floor finish near Door South

25 Elevator Lobby S2E.01 Remove all remaining protective covering to Door North

26 Elevator Lobby S2E.01 Intumescent strip to meeting stile to Door North is incomplete at lock striking plate

27 Elevator Lobby S2E.01 Make good to rectangular hole in head frame Door North

28 Elevator Lobby S2E.01 Replace damaged skirting on East wall

29 Elevator Lobby S2E.01 Replace damaged skirting to North Wall

30 Elevator Lobby S2E.01 Refix skirting with proper fixing system and remove panel pins throughout

31 Elevator Lobby S2E 01 Fix missing skirting on both sides of door to Storage Room S2E 20

AMERICA HOUSE

Page 78: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 78/407

Ref. Location Defect

No.

34 Elevator Lobby S2E.01 Make good to ceiling where rebar reinforcement is exposed and seal completely near Door South

35 Elevator Lobby S2E.01 Make good to two large ducts on upper LH side of Wall B16/17

36 Elevator Lobby S2E.01 Seal to conduit on Wall B16/17 near ceiling to RH of door

37 Elevator Lobby S2E.01 Seal to pipe above Door South on Wall B16/17

38 Elevator Lobby S2E.01 Sprinkler pipe installation to be tidied up and holders set straight

39 Elevator Lobby S2E.01 Clean two (2) light fittings of paint and dirt inside

40 Elevator Lobby S2E.01 Make good square hole in ceiling near south wall

41 Elevator Lobby S2E.01 Remove nail in ceiling and make good

42 Elevator Lobby S2E.01 Remove two wires in ceiling near south door and make good

43 Elevator Lobby S2E.01 Make good to ceiling to RH side of North Wall C 16/17 at ceiling

44 Elevator Lobby S2E.01 Seal wall at conduit in North Wall on LH side C 16/17

45 Elevator Lobby S2E.01 Seal North Wall above door where two sprinkler pipes pass through and repaint

46 Elevator Lobby S2E.01 Remove paint to frames of lift shaft doors

47 Elevator Lobby S2E.01 Clean lift shaft threshold plate from cement and paint stains etc

48 Elevator Lobby S2E.01 Carbon Monoxide Warning to also be in English

49 Elevator Lobby S2E.01 Tighten up all loose screws to Carbon Monoxide sign50 Elevator Lobby S2E.01 Seal West Wall at ceiling level where conduit passes through on LH side

51 Elevator Lobby S2E.01 Seal West Wall at ceiling level where conduit passes through on RH side

52 Elevator Lobby S2E.01 Angle steel threshold step to Door North to be refixed and painted with black and yellow diagonal stripes

53 Elevator Lobby S2E.01 Angle steel threshold step to Door South to be refixed and painted with black and yellow diagonal stripes

54 Elevator Lobby S2E.01 Door Signage South

55 Elevator Lobby S2E.01 Door Signage North

56 Elevator Lobby S2E.01 Remove paint stains on Door South

57 Elevator Lobby S2E.01 Make good and adjust to door leaf outer on Door South as its is scraping along the floor

58 Elevator Lobby S2E.01 Seal West Wall at where small pipe passes through on RH side

59 Elevator Lobby S2E.01 Make good subsidence/damage to wall/floor on West Wall and repaint as required

60 Elevator Lobby S2E.01 Clean paint of both lift panels call and indicator to RH side

61 Elevator Lobby S2E.01 Infill sinking to storage area door and repaint floor

62 Elevator Lobby S2E.01 Make good to dent in Door South on Car Park side

63 Elevator Lobby S2E.01 Fire/Smoke Threshold seal is required to door North

64 Elevator Lobby S2E 01 Fire/Smoke Threshold seal is required to door South

AMERICA HOUSE

Page 79: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 79/407

Ref. Location Defect

No.

1 Egress Stair SE2.07 Remove paint conduit to fire detector

2 Egress Stair SE2.07 Clean down steps of dirt marks, concrete etc complete

3 Egress Stair SE2.07 Floor tiling to mid landing is uneven and to be levelled and resealed/polished

4 Egress Stair SE2.07 Floor tiling to stair floor at -2 is uneven and to be levelled and resealed/polished and insert missing grout between some tiles

5 Egress Stair SE2.07 Clean red paint daubs on stairs

6 Egress Stair SE2.07 Replace four (4) chipped steps

7 Egress Stair SE2.07 Clean light fitting at mid landing

8 Egress Stair SE2.07 Remove paint from Running Man Sign

9 Egress Stair SE2.07 Clean Light Fitting at Base Level

10 Egress Stair SE2.07 Remove paint to Base Entry Door and Frames

11 Egress Stair SE2.07 Fixing screws to frame protrude and are to be refixed to Door South

12 Egress Stair SE2.07 Cover four (4) protruding screw ends in angle plate to top corner to Door South

13 Egress Stair SE2.07 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

14 Egress Stair SE2.07 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced

15 Egress Stair SE2.07 Remove remaining protective covering to doors

16 Egress Stair SE2.07 Fix missing strike plate to open door jamb17 Egress Stair SE2.07 Install permanent door handles

18 Egress Stair SE2.07 Install door stop to Door

19 Egress Stair SE2.07 Install door closer to Door

20 Egress Stair SE2.07 Remove manufacturer's labels on door surface

21 Egress Stair SE2.07 Door signage

22 Egress Stair SE2.07 Fire/Smoke Threshold seal is required to door

23 Egress Stair SE2.07 Remove paint on top edge of skirting throughout including steps

AMERICA HOUSE

Page 80: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 80/407

Ref. Location Defect

No.

1 Stair Vestibule SE2.06 Remove paint and cement to South Door Frames

2 Stair Vestibule SE2.06 Fix permanent handles to door South and make good

3 Stair Vestibule SE2.06 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule SE2.06 Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule SE2.06 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule SE2.06 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule SE2.06 Install door stop to Door South

8 Stair Vestibule SE2.06 Install door closer to Door South

9 Stair Vestibule SE2.06 Remove remaining parts of the protective covering to door South

10 Stair Vestibule SE2.06 Remove red paint on door South

11 Stair Vestibule SE2.06 Paint ceiling

12 Stair Vestibule SE2.06 Remove red paint stain on floor tiling near Door North

13 Stair Vestibule SE2.06 Running man sign is set at an angle and requires to be relocated

14 Stair Vestibule SE2.06 Running Man sign obstructs the sprinkler head in operation mode and needs to be reviewed

15 Stair Vestibule SE2.06 Carbon Monoxide sign to have English Warning

16 Stair Vestibule SE2.06 Remove paint from skirting17 Stair Vestibule SE2.06 Clean paint etc from two (2) light fittings

18 Stair Vestibule SE2.06 Remove red paint stains from wall generally

19 Stair Vestibule SE2.06 Make good round Fire Damper Grille panel (Lower)

20 Stair Vestibule SE2.06 Make good round Fire Damper Grille panel (Upper)

21 Stair Vestibule SE2.06 Provide proper locking device to Lower Fire Damper Grille

22 Stair Vestibule SE2.06 Provide proper locking device to Upper Fire Damper Grille

23 Stair Vestibule SE2.06 Clean paint off grille to Fire Damper panel (Lower)

24 Stair Vestibule SE2.06 Clean paint off grille to Fire Damper panel (Upper)

25 Stair Vestibule SE2.06 Replace missing Hydrant Cover Light sign

26 Stair Vestibule SE2.06 Clean paint and cement off door Frame to Door North

27 Stair Vestibule SE2.06 Fix permanent handles to door North and make good

28 Stair Vestibule SE2.06 Intumescent strip is not complete to both frame bases of Door North

29 Stair Vestibule SE2.06 Fixing screws to frame protrude and are to be refixed to Door North

30 Stair Vestibule SE2.06 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Stair Vestibule SE2 06 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

Page 81: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 81/407

AMERICA HOUSE

Page 82: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 82/407

Ref. Location DefectNo.

67 Stair Vestibule SE2.06 Remove tape to angle threshold frame outside Door North

68 Stair Vestibule SE2.06 Make good to concrete step at Car Park Door South and repaint

69 Stair Vestibule SE2.06 Make good at ceiling on West Wall near South door and repaint

70 Stair Vestibule SE2.06 Make good at ceiling on West Wall near North door and repaint

71 Stair Vestibule SE2.06 Make good on West Wall near ceiling at mid point where two (2) conduits pass through and repaint

72 Stair Vestibule SE2.06 Make good to West wall where sprinkler pipe passes through and repaint

73 Stair Vestibule SE2.06 Provide more support hangers to sprinkler pipework in space and tidy up generally

74 Stair Vestibule SE2.06 Make good hole in ceiling in northeast corner for conduit and repaint

75 Stair Vestibule SE2.06 Repaint area of repair above Door North

76 Stair Vestibule SE2.06 Make good skirting to LH of Door North

77 Stair Vestibule SE2.06 Make good to skirting to RH of Door South

78 Stair Vestibule SE2.06 Fire/Smoke Threshold seal is required to door North

79 Stair Vestibule SE2.06 Fire/Smoke Threshold seal is required to door South

AMERICA HOUSE

Page 83: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 83/407

Ref. Location Defect

No.

1 Storage S2E.25 Ceiling light to be installed and light switch

2 Storage S2E.25 Fire Detector to be installed

3 Storage S2E.25 Sprinkler installation required

4 Storage S2E.25 Paint walls

5 Storage S2E.25 Paint ceiling

6 Storage S2E.25 Prepare, level and paint floor

7 Storage S2E.25 Make good joint between floor and walls all round

8 Storage S2E.25 Remove temporary broken light and wires on East Wall

9 Storage S2E.25 Make good to two (2) formwork fixtures holes on East Wall

10 Storage S2E.25 Make good to eight (8) formwork fixtures holes on North Wall

11 Storage S2E.25 Make good to eight (8) formwork fixtures holes on West Wall

12 Storage S2E.25 Make good to six (6) formwork fixtures holes on South Wall

13 Storage S2E.25 Remove steel reinforcement rods on South Wall near ceiling and make good

14 Storage S2E.25 Seal to small dia. Pipe on West Wall to RH of door

15 Storage S2E.25 Repair temporary bulkhead lining above entry door and seal

16 Storage S2E.25 Remove paint and cement to Door and Frames17 Storage S2E.25 Replace with permanent handle

18 Storage S2E.25 Remove remaining protective covering to door

19 Storage S2E.25 Intumescent strip is not complete to LH hinge door jamb frame and to be replaced

20 Storage S2E.25 Intumescent strip to head frame is short and to be replaced

21 Storage S2E.25 Intumescent strip to head frame is missing and to be installed

22 Storage S2E.25 Fixing screws to frame protrude and are to be refixed to Door South

23 Storage S2E.25 Cover four (4) protruding screw ends in angle plate to top corner to Door South

24 Storage S2E.25 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

25 Storage S2E.25 Install door stop to Door

26 Storage S2E.25 Install door closer to Door

27 Storage S2E.25 Clean out at base of door frames with cement etc

28 Storage S2E.25 Door signage

29 Storage S2E.25 Fire/Smoke seal threshold required to entry door

AMERICA HOUSE

Page 84: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 84/407

Ref. Location Defect

No.

1 Service Corridor S2E.08 Complete wall painting in areas missed

2 Service Corridor S2E.08 Remove red paint daubs on wall generally

3 Service Corridor S2E.08 Clean red paint off Running Man sign

4 Service Corridor S2E.08 Low headroom on Northeast side of corridor

5 Service Corridor S2E.08 Clean paint and cement off conduit at ceiling level to southwest side of corridor on Wall to Annex S2E.09

6 Service Corridor S2E.08 Make good to wall head 300mm high on southwest wall to Annex S2E.09

7 Service Corridor S2E.08 Seal large void above door to Car Park Area

8 Service Corridor S2E.08 Make good to hole at upper wall level near LH of door to Fire Pump Room S2E.10

9 Service Corridor S2E.08 Clean conduit to RH of Door to Fire Pump Room S2E.10

10 Service Corridor S2E.08 Clean paint etc. conduit on South Wall of Corridor and West Wall beside it

11 Service Corridor S2E.08 Make good hole above door with six (6) pipes to Fire Pump Room S2E.10 and seal and repaint to both sides

12 Service Corridor S2E.08 Remove paint on conduit at entry door RH to Car Park Area and along ceiling

13 Service Corridor S2E.08 Make god and seal rectangular hole in southeast corner of corridor at ceiling level

14 Service Corridor S2E.08 Clean all three (3) lights fixed as bulkheads to wall

15 Service Corridor S2E.08 Fixing screws to frame protrude and are to be refixed to door

16 Service Corridor S2E.08 Cover four (4) protruding screw ends in angle plate to top corner to door17 Service Corridor S2E.08 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

18 Service Corridor S2E.08 Intumescent strip to LH door jamb is not complete at bases, loose and to be replaced

19 Service Corridor S2E.08 Intumescent strip to RH door jamb is not complete at bases and to be replaced

20 Service Corridor S2E.08 Clean out frames at door base

21 Service Corridor S2E.08 Remove all protective covering that remains

22 Service Corridor S2E.08 Remove paint and cement on door frames and make good

23 Service Corridor S2E.08 Fix permanent missing door handles

24 Service Corridor S2E.08 Install door stop to Door

25 Service Corridor S2E.08 Install door closer to Door

26 Service Corridor S2E.08 Remove cement on Intumescent strip to head frame

27 Service Corridor S2E.08 Remove paint spills to door and make good

28 Service Corridor S2E.08 Door Signage

29 Service Corridor S2E.08 Make good and seal around ventilation duct on West Wall at southern end of corridor and repaint

30 Service Corridor S2E.08 Make good and seal around conduit on West Wall at southern end of corridor and repaint

31 Service Corridor S2E 08 Install Fire Alarm

AMERICA HOUSE

Page 85: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 85/407

Ref. Location Defect

No.

1 Annex Storage S2E .11 and .13 Fixing screws to frame protrude and are to be refixed to door Service Corridor

2 Annex Storage S2E .11 and .13 Cover four (4) protruding screw ends in angle plate to top corner to door Service Corridor

3 Annex Storage S2E .11 and .13 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Annex Storage S2E .11 and .13 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced on door Service Corridor

5 Annex Storage S2E .11 and .13 Fire/Smoke seal threshold required to entry door Service Corridor

6 Annex Storage S2E .11 and .13 Remove all protective covering that remains

7 Annex Storage S2E .11 and .13 Make good to door seal frame all round on Service Corridor side

8 Annex Storage S2E .11 and .13 Fix permanent door handles

9 Annex Storage S2E .11 and .13 Install door stop to Door

10 Annex Storage S2E .11 and .13 Install door closer to Door

11 Annex Storage S2E .11 and .13 Remove 4 steel rods to LH of Door to Service Corridor on Corridor side LH and make good

12 Annex Storage S2E .11 and .13 Door signage to door to Service Corridor

13 Annex Storage S2E .11 and .13 Wall missing between S2E.11 and S2E.13

14 Annex Storage S2E .11 and .13 Make good joint between wall and floor all round and repaint as required

15 Annex Storage S2E .11 and .13 Clean tape off light fitting

16 Annex Storage S2E .11 and .13 Generally remove paint on conduit throughout17 Annex Storage S2E .11 and .13 Repair water leak to northwest corner under main East Entry Ramp

18 Annex Storage S2E .11 and .13 Make good pipe encasure to drain to car park ramp all round

19 Annex Storage S2E .11 and .13 Paint Southwest wall at northern end

20 Annex Storage S2E .11 and .13 Clean conduit down on southwest wall of paint

21 Annex Storage S2E .11 and .13 Clean conduit near Door to Service Corridor

22 Annex Storage S2E .11 and .13 Make good to bulkhead over door to corridor and fire seal

23 Annex Storage S2E .11 and .13 Make good and seal to flexible conduit to RH of door to service corridor and touch up wall paint

24 Annex Storage S2E .11 and .13 Seal wall at ceiling to vestibule in northwest corner

25 Annex Storage S2E .11 and .13 Seal large rectangular hole to LH at ceiling of wall to vestibule

26 Annex Storage S2E .11 and .13 Seal around three (3) conduits in wall to Vestibule and repaint

27 Annex Storage S2E .11 and .13 Make good paint to LH side lower of Door to Vestibule

28 Annex Storage S2E .11 and .13 Repair wall in northeast corner of Annex Storage near ceiling and repaint

29 Annex Storage S2E .11 and .13 Seal wall head on return wall to Vestibule in northwest and repaint

30 Annex Storage S2E .11 and .13 Seal return wall to Vestibule in northwest corner at floor level and repaint

31 Annex Storage S2E 11 and 13 Make good around and seal to flexible conduit on north wall to Annex Storage area

AMERICA HOUSE

Page 86: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 86/407

Ref. Location DefectNo.

34 Annex Storage S2E .11 and .13 Fixing screws to frame protrude and are to be refixed to door Vestibule

35 Annex Storage S2E .11 and .13 Cover four (4) protruding screw ends in angle plate to top corner to door Vestibule

36 Annex Storage S2E .11 and .13 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

37 Annex Storage S2E .11 and .13 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced on door Vestibule

38 Annex Storage S2E .11 and .13 Fire/Smoke seal threshold required to entry door Vestibule

39 Annex Storage S2E .11 and .13 Remove all protective covering that remains door to Vestibule

40 Annex Storage S2E .11 and .13 Seal returns of door all round on Vestibule side of Door to Vestibule

41 Annex Storage S2E .11 and .13 Fix permanent door handles

42 Annex Storage S2E .11 and .13 Install door stop to Door to Vestibule

43 Annex Storage S2E .11 and .13 Install door closer to Door to Vestibule

44 Annex Storage S2E .11 and .13 Remove cement and paint on door and frames to Vestibule

45 Annex Storage S2E .11 and .13 Door signage

46 Annex Storage S2E .11 and .13 Wall ABC 23 remove four (4) steel rods behind ducting and make good

AMERICA HOUSE

Page 87: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 87/407

Ref. Location DefectNo.

1 Vestibule S2E.12 Fixing screws to frame protrude and are to be refixed to door Vestibule

2 Vestibule S2E.12 Cover four (4) protruding screw ends in angle plate to top corner to door Vestibule

3 Vestibule S2E.12 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Vestibule S2E.12 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced on door Vestibule

5 Vestibule S2E.12 Fire/Smoke seal threshold required to entry door Vestibule

6 Vestibule S2E.12 Remove all protective covering that remains door to Vestibule

7 Vestibule S2E.12 Seal returns of door all round on Vestibule side of Door to Vestibule

8 Vestibule S2E.12 Fix permanent door handles

9 Vestibule S2E.12 Install door stop to Door to Vestibule

10 Vestibule S2E.12 Install door closer to Door to Vestibule

11 Vestibule S2E.12 Remove cement and paint on door and frames to Vestibule

12 Vestibule S2E.12 Door signage

13 Vestibule S2E.12 Remove paint on conduit on wall near door

14 Vestibule S2E.12 Provide light and switch etc. to Vestibule

15 Vestibule S2E.12 Make good damaged wall to LH Lower side of Door to Car Park Area including loose plaster boarding

16 Vestibule S2E.12 Remove damaged paint floor and repaint017 Vestibule S2E.12 Seal gap to wall at joint to ceiling all round

18 Vestibule S2E.12 Make good to rectangular duct hole in South wall and repaint

19 Vestibule S2E.12 Make good to door bulkhead and fire seal

20 Vestibule S2E.12 Repaint walls as required but especially RH side of door to Annex Storage Room

21 Vestibule S2E.12 Remove paint on light switch

22 Vestibule S2E.12 Remove paint on Running Man Sign

23 Vestibule S2E.12 Running Man Sign is not easily visible when vacating in a hurry and to be resited

24 Vestibule S2E.12 Seal gap between wall and ceiling to wall side return to Annex Storage Area S2E.13

AMERICA HOUSE

Page 88: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 88/407

Ref. Location DefectNo.

1 Annex Storage Room S2E.09 Fixing screws to frame protrude and are to be refixed to door

2 Annex Storage Room S2E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

3 Annex Storage Room S2E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Annex Storage Room S2E.09 Intumescent strip to Hinge door jamb is not complete at bases and to be replaced and also loose

5 Annex Storage Room S2E.09 Clean out frames at door base

6 Annex Storage Room S2E.09 Remove all protective covering that remains

7 Annex Storage Room S2E.09 Intumescent strip is loose on head frame and to be refixed

8 Annex Storage Room S2E.09 Fix missing door handles and lock

9 Annex Storage Room S2E.09 Install door stop to Door

10 Annex Storage Room S2E.09 Install door closer to Door

11 Annex Storage Room S2E.09 Remove paint stains on door

12 Annex Storage Room S2E.09 Make good to threshold plate and tidy up metal steel rod fixings

13 Annex Storage Room S2E.09 Remove paint and cement on door frames

14 Annex Storage Room S2E.09 Fire/Smoke seal threshold required to entry door

15 Annex Storage Room S2E.09 Door signage

16 Annex Storage Room S2E.09 Clean floor of rust stains etc17 Annex Storage Room S2E.09 Touch up wall painting near floor on all four walls

18 Annex Storage Room S2E.09 Repaint ceiling as work substandard

19 Annex Storage Room S2E.09 Relocate conduit drop and junction box sunk into wall and make good to wall and refix the assembly properly near door RH

20 Annex Storage Room S2E.09 Remove all paint and cement to conduits to RH of door to Service Corridor

21 Annex Storage Room S2E.09 Remove paint on all ceiling mounted conduits throughout

22 Annex Storage Room S2E.09 Touch up paintwork to wall where missing throughout

23 Annex Storage Room S2E.09 Sprinkler pipe install ion required

24 Annex Storage Room S2E.09 Clear out general rubbish in the room

25 Annex Storage Room S2E.09 Seal two (2) pipes in ceiling at southwest corner of room

26 Annex Storage Room S2E.09 Seal two (2) pipes at floor at southwest corner of room

27 Annex Storage Room S2E.09 Make good to ceiling at SVP Pipe entry

28 Annex Storage Room S2E.09 Make good to one (1) formwork fixtures hole on west wall and repaint

29 Annex Storage Room S2E.09 Clean three (3) ceiling lights

30 Annex Storage Room S2E.09 Make good and seal to conduit entry near ceiling on East wall

31 Annex Storage Room S2E 09 Make good and seal to twp (2) conduit entries near ceiling on West wall

AMERICA HOUSE

Page 89: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 89/407

Ref. Location DefectNo.

1 Fire Pump Room S2E.10 Remove red paint from IT plug in point

2 Fire Pump Room S2E.10 Remove red paint on light switch

3 Fire Pump Room S2E.10 Remove copious red paint on Running Man Sign

4 Fire Pump Room S2E.10 Repair Running Man Sign as panel has fallen and needs to be realigned

5 Fire Pump Room S2E.10 Form protective railing to ladder hole in floor as somebody could easily fall

6 Fire Pump Room S2E.10 Remove red daubs on West, East and South Walls

7 Fire Pump Room S2E.10 Complete insulation to pipes at ceiling level on West Wall

8 Fire Pump Room S2E.10 Tidy up pipes in northwest corner and remove all the cement and concrete etc and repaint as required

9 Fire Pump Room S2E.10 Clean out central drain gully

10 Fire Pump Room S2E.10 Paint gulley drain grating

11 Fire Pump Room S2E.10 Seal three(3) SVP pipes that enter at ceiling

12 Fire Pump Room S2E.10 Install all equipment and flow labels throughout

13 Fire Pump Room S2E.10 Remove red paint daubs on ceiling

14 Fire Pump Room S2E.10 Paint North Wall and short return on East Wall

15 Fire Pump Room S2E.10 Seal off duct in South West Corner at ceiling to SVP and cable tray etc

16 Fire Pump Room S2E.10 Remove loose tying wires on South Wall and make good (LH)17 Fire Pump Room S2E.10 Remove timer formwork piece on ceiling at South Wall, seal to six (6) pipes and make good

18 Fire Pump Room S2E.10 Seal SVP pipe to floor on North Wall LH

19 Fire Pump Room S2E.10 Paint Floor

20 Fire Pump Room S2E.10 Paint ceiling

21 Fire Pump Room S2E.10 Seal drain at floor level on West Wall

22 Fire Pump Room S2E.10 Seal duct hole in southwest corner for SVP and Cables and make good

23 Fire Pump Room S2E.10 Provide closure screws to four (4)\control boxes to LH side of entry door

24 Fire Pump Room S2E.10 Redo bodged up cable tray box under the four (4) control boxes to LH of entry door

25 Fire Pump Room S2E.10 Remove paint on conduits to LH side of entry door

26 Fire Pump Room S2E.10 Make good duct entry to upper LH side of entry door and repaint as required

27 Fire Pump Room S2E.10 Make good to five (5) formwork fixture holes on West Wall

28 Fire Pump Room S2E.10 Seal wall to RH of entry door for two insulated pipes and make good

29 Fire Pump Room S2E.10 Seal wall for three pipes to RH of entry door and make good all round

30 Fire Pump Room S2E.10 Paint area in Northwest upper area of West Wall

31 Fire Pump Room S2E 10 Fixing screws to frame protrude and are to be refixed to door

AMERICA HOUSE

Page 90: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 90/407

Ref. Location DefectNo.

34 Fire Pump Room S2E.10 Intumescent strip to Hinge door jamb is not complete at bases and to be replaced and also loose

35 Fire Pump Room S2E.10 Remove paint on door and frames

36 Fire Pump Room S2E.10 Remove all protective covering that remains

37 Fire Pump Room S2E.10 Fix missing strike plate to open door jamb

38 Fire Pump Room S2E.10 Fix missing door handles

39 Fire Pump Room S2E.10 Install door stop to Door as when opening the door is hitting the Fire Pump Installation equipment

40 Fire Pump Room S2E.10 Install door closer to Door

41 Fire Pump Room S2E.10 Replace missing prong receiver

42 Fire Pump Room S2E.10 Make good threshold concrete to room as uneven and rough

43 Fire Pump Room S2E.10 Seal door frame all round in Service Corridor

44 Fire Pump Room S2E.10 Fire Fighting equipment is missing

45 Fire Pump Room S2E.10 Door Signage

46 Fire Pump Room S2E.10 Fire/Smoke seal threshold required to entry door

47 Fire Pump Room S2E.10 Intumescent strip to open door jamb is not complete at bases and to be replaced

48 Fire Pump Room S2E.10 Intumescent strip to head frame is short and to be replaced

49 Fire Pump Room S2E.10 Seal bulkhead above door where six pipes pass through

50 Fire Pump Room S2E.10 Make good to slab at opening to -1 at access ladder and remove exposed steel reinforcement

51 Fire Pump Room S2E.10 Make good all round to floor opening at 02 floor level

52 Fire Pump Room S2E.10 Provide handrail to access ladder

53 Fire Pump Room S2E.10 Install Fire Alarm

AMERICA HOUSE

Page 91: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 91/407

Ref. Location DefectNo.

1 Storage S2E. 15 (Ericsson) Fixing screws to frame protrude and are to be refixed to door Vestibule

2 Storage S2E. 15 (Ericsson) Cover four (4) protruding screw ends in angle plate to top corner to door Vestibule

3 Storage S2E. 15 (Ericsson) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Storage S2E. 15 (Ericsson) Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced on door Vestibule

5 Storage S2E. 15 (Ericsson) Fire/Smoke seal threshold required to entry door Vestibule

6 Storage S2E. 15 (Ericsson) Remove all protective covering that remains door to Vestibule

7 Storage S2E. 15 (Ericsson) Make good and seal returns of door all round on Vestibule side of Door to Vestibule

8 Storage S2E. 15 (Ericsson) Fix permanent door handles

9 Storage S2E. 15 (Ericsson) Install door stop to Door to Vestibule

10 Storage S2E. 15 (Ericsson) Install door closer to Door to Vestibule

11 Storage S2E. 15 (Ericsson) Remove cement and paint on door frames to Vestibule

12 Storage S2E. 15 (Ericsson) Door signage

13 Storage S2E. 15 (Ericsson) Remove paint on door surfaces

14 Storage S2E. 15 (Ericsson) Intumescent strip to head frame is loose and needs to be refixed

15 Storage S2E. 15 (Ericsson) Intumescent strip to open jamb frame is loose and to be refixed

16 Storage S2E. 15 (Ericsson) Repair wall leak on Wall C 23 and repaint17 Storage S2E. 15 (Ericsson) Make good on Wall C23 at joint to ceiling and repaint

18 Storage S2E. 15 (Ericsson) Seal and make good around duct extract

19 Storage S2E. 15 (Ericsson) Apply paint to sprinkler pipe installation

20 Storage S2E. 15 (Ericsson) Stabilise sprinkler pipe installation as it is NOT stable

21 Storage S2E. 15 (Ericsson) Paint floor

22 Storage S2E. 15 (Ericsson) Paint all walls

23 Storage S2E. 15 (Ericsson) Paint ceiling

24 Storage S2E. 15 (Ericsson) Clean three (3) light fitting that are dirty inside

25 Storage S2E. 15 (Ericsson) Clean up wall head along southwest wall and make good

26 Storage S2E. 15 (Ericsson) Make good to three (3) formwork fixture holes

27 Storage S2E. 15 (Ericsson) Install Fire Detector in south part of area

28 Storage S2E. 15 (Ericsson) Make good to taped joint to flexible conduit to Fire Detector

29 Storage S2E. 15 (Ericsson) Make good and seal off to conduit near ceiling on LH of northwest wall

30 Storage S2E. 15 (Ericsson) Make good and seal to sprinkler pipe to upper LH of door to vestibule

31 Storage S2E 15 (Ericsson) Seal wall at junction with ceiling to both walls to vestibule

AMERICA HOUSE

Page 92: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 92/407

Ref. Location DefectNo.

1 Vestibule S2E.14 (Ericsson) Fixing screws to frame protrude and are to be refixed to door Vestibule

2 Vestibule S2E.14 (Ericsson) Cover four (4) protruding screw ends in angle plate to top corner to door Vestibule

3 Vestibule S2E.14 (Ericsson) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Vestibule S2E.14 (Ericsson) Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced on door to Car Park and also loose

5 Vestibule S2E.14 (Ericsson) Fire/Smoke seal threshold required to entry door Vestibule

6 Vestibule S2E.14 (Ericsson) Remove all protective covering that remains door to Vestibule

7 Vestibule S2E.14 (Ericsson) Seal returns of door all round on Vestibule side of Door to Vestibule

8 Vestibule S2E.14 (Ericsson) Fix permanent door handles

9 Vestibule S2E.14 (Ericsson) Install door stop to Door to Car Park

10 Vestibule S2E.14 (Ericsson) Install door closer to Door to Car Park

11 Vestibule S2E.14 (Ericsson) Remove cement and paint on door frames to Car Park

12 Vestibule S2E.14 (Ericsson) Door signage

13 Vestibule S2E.14 (Ericsson) Clean out frames at bases of dirt and concrete etc.

14 Vestibule S2E.14 (Ericsson) Provide light and switch etc. to Vestibule

15 Vestibule S2E.14 (Ericsson) Remove paint stains on door

16 Vestibule S2E.14 (Ericsson) Paint floor

17 Vestibule S2E.14 (Ericsson) Seal gap to wall at joint to ceiling all round

18 Vestibule S2E.14 (Ericsson) Paint ceiling

19 Vestibule S2E.14 (Ericsson) Make good to door bulkhead and fire seal

20 Vestibule S2E.14 (Ericsson) Make good and seal small pipe to North Wall

21 Vestibule S2E.14 (Ericsson) Remove paint on light switch

22 Vestibule S2E.14 (Ericsson) Make good and seal small pipe to South Wall

23 Vestibule S2E.14 (Ericsson) Running Man Sign is not easily visible when vacating in a hurry and to be resited

24 Vestibule S2E.14 (Ericsson) Seal gap between wall and ceiling to wall side return to Annex Storage Area S2E.15

25 Vestibule S2E.14 (Ericsson) Make good and seal to three (3) conduits at ceiling level in walls and repaint as required26 Vestibule S2E.14 (Ericsson) Ease lock that is stiff to turn

27 Vestibule S2E.14 (Ericsson) Make good plasterboard return to door all round on Car Park side of door

28 Vestibule S2E.14 (Ericsson) Make good to wall at pipe to RH side of entry door to vestibule

AMERICA HOUSE

Page 93: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 93/407

Ref. Location DefectNo.

1 Basement Car Park Level -1 Gen. Make good and seal wall at high level at C 21 for cable tray passing through wall

2 Basement Car Park Level -1 Gen. Make good and seal wall at high level at C 21 for small pipe passing through wall

3 Basement Car Park Level -1 Gen. Make good and seal wall at high level at C 21 for sprinkler pipe passing through wall

4 Basement Car Park Level -1 Gen. Make good and seal hole at high level at C21 in wall

5 Basement Car Park Level -1 Gen. Make good and seal wall at high level for small pipe passing through wall to S1E.13 Car Exhaust

6 Basement Car Park Level -1 Gen. Remove large cable end in wall to Room S1E.13 Car Exhaust

7 Basement Car Park Level -1 Gen. Make good and seal to steel plate with orifice in ceiling between C/B 20/21

8 Basement Car Park Level -1 Gen. Relocate four sprinkler head placed very close to wall to Rooms S1E.13 Car Exhaust and Corridor Vestib S1E.08

9 Basement Car Park Level -1 Gen. Make good and seal round flue ducts as they pass through wall to Room S1E.08

10 Basement Car Park Level -1 Gen. Make good and seal large hole for pipes passing above door to S1E.08 and cover up exposed steel reinforcement

11 Basement Car Park Level -1 Gen. Provide impact protection to SVP Pipe D16

12 Basement Car Park Level -1 Gen. Make good and seal wall at high level A/B 21 for small pipe passing through wall to S1E.08

13 Basement Car Park Level -1 Gen. Make good and seal wall at high level A/B 21 for small pipe and conduit passing through wall to S1E.08

14 Basement Car Park Level -1 Gen. Make good and seal wall at high level at A 20/21 for sprinkler pipe passing through wall to S1E.09

15 Basement Car Park Level -1 Gen. Make good and seal wall at high level A 20/21 for two (2) small pipes passing through wall to S1E.09

16 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A20 LH17 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A19 RH

18 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A19 LH

19 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A18 RH

20 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A18 LH

21 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A17 RH

22 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A17 LH

23 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A16 RH

24 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A16 LH

25 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A16 LH

26 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A15 RH

27 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A15 LH

28 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A14 RH

29 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A14 LH

30 Basement Car Park Level -1 Gen. Provide impact protection to car exhaust extracts A13 LH

31 Basement Car Park Level -1 Gen Provide impact protection to car exhaust extracts Column C19

AMERICA HOUSE

Page 94: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 94/407

Ref. Location DefectNo.

34 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column A 20

35 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column A 18

36 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column A 16

37 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column A 14

38 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column D 20

39 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column D 18

40 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column D 16

41 Basement Car Park Level -1 Gen. Provide impact protection to water supply pipe Column D 14

42 Basement Car Park Level -1 Gen. Clean out void between Column Walls A 12 and 13

43 Basement Car Park Level -1 Gen. Clean out void between Column Walls D 12 and 13

44 Basement Car Park Level -1 Gen. Provide impact Protection to CO Warning Sign A 12

45 Basement Car Park Level -1 Gen. Provide impact Protection to CO Warning Sign D 12

46 Basement Car Park Level -1 Gen. Provide impact Protection to CO Warning Sign A 17

47 Basement Car Park Level -1 Gen. Provide impact Protection to CO Warning Sign D 17

48 Basement Car Park Level -1 Gen. Clean out floor drain near D20

49 Basement Car Park Level -1 Gen. Paint floor drain grating near D 20

50 Basement Car Park Level -1 Gen. Clean out floor drain near D18

51 Basement Car Park Level -1 Gen. Paint floor drain grating near D 18

52 Basement Car Park Level -1 Gen. Clean out floor drain near D16

53 Basement Car Park Level -1 Gen. Paint floor drain grating near D 16

54 Basement Car Park Level -1 Gen. Clean out floor drain near D14

55 Basement Car Park Level -1 Gen. Paint floor drain grating near D 14

56 Basement Car Park Level -1 Gen. Clean out floor drain near A20

57 Basement Car Park Level -1 Gen. Paint floor drain grating near A 20

58 Basement Car Park Level -1 Gen. Clean out floor drain near A18 59 Basement Car Park Level -1 Gen. Paint floor drain grating near A 18

60 Basement Car Park Level -1 Gen. Clean out floor drain near A16

61 Basement Car Park Level -1 Gen. Paint floor drain grating near A 16

62 Basement Car Park Level -1 Gen. Clean out floor drain near A14

63 Basement Car Park Level -1 Gen. Replace missing floor drain grating near A 14

64 Basement Car Park Level -1 Gen Clean out floor drain at bottom of car park entry ramp C22

AMERICA HOUSE

Page 95: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 95/407

Ref. Location DefectNo.

67 Basement Car Park Level -1 Gen. Provide impact protection to wall mounted ventilation unit near Column D20

68 Basement Car Park Level -1 Gen. Provide impact protection to Running Man Sign on column D 20

69 Basement Car Park Level -1 Gen. Provide impact protection to Running Man Sign on column B 20

70 Basement Car Park Level -1 Gen. Provide impact protection to Running Man Sign on wall C17

71 Basement Car Park Level -1 Gen. Provide impact protection to Running Man Sign on wall B18

72 Basement Car Park Level -1 Gen. Provide impact protection to Running Man Sign on wall B15

73 Basement Car Park Level -1 Gen. Provide impact protection to Running Man Sign on wall C14

74 Basement Car Park Level -1 Gen. Provide impact protection to wall mounted ventilation unit near Column D14

75 Basement Car Park Level -1 Gen. Make good flexible conduit connections to CCTV Camera B18

76 Basement Car Park Level -1 Gen. Make good flexible conduit connections to CCTV Camera B15

77 Basement Car Park Level -1 Gen. Make good flexible conduit connections to CCTV Camera D14

78 Basement Car Park Level -1 Gen. Make good flexible conduit connections to CCTV Camera C17

79 Basement Car Park Level -1 Gen. Make good flexible conduit connections to CCTV Camera A 19

80 Basement Car Park Level -1 Gen. Make good and seal at white water pipe at floor D18

81 Basement Car Park Level -1 Gen. Complete conduit connection to CO Warning Sign A 12

82 Basement Car Park Level -1 Gen. Complete conduit connection to CO Warning Sign D 12

83 Basement Car Park Level -1 Gen. Complete conduit connection to CO Warning Sign A 17

84 Basement Car Park Level -1 Gen. Complete conduit connection to CO Warning Sign D 20

85 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Service Elevator Vestib.

86 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Corridor B14/15 South.

87 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Corridor C14/15 North

88 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Corridor B17/15 South.

89 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Corridor C17/18 North

90 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Elevator Vest. B17 South.

91 Basement Car Park Level -1 Gen. Make good painting to black and yellow threshold strip Elevator Vest. C17 North.92 Basement Car Park Level -1 Gen. Remove red paint on walls to S1E.13 at Car Park Area

93 Basement Car Park Level -1 Gen. Sprinkler pipe to be made more stable in area A 18/19

94 Basement Car Park Level -1 Gen. Remove key at sprinkler pipe installation A 18/19 and hand over to Facilities Management

95 Basement Car Park Level -1 Gen. Seal enclosure fire rated to Main Electrical Cable in Area A 18/19

96 Basement Car Park Level -1 Gen. Seal enclosure fire rated to Main Electrical Cable in Area AB 18/19 where angle support are protruding both sides

97 Basement Car Park Level -1 Gen Seal enclosure fire rated to Main Electrical Cable in Area A/B 18/19 as not sealed when an exhaust duct passes underneath

AMERICA HOUSE

Page 96: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 96/407

Ref. Location DefectNo.

100 Basement Car Park Level -1 Gen. Remove reinforcing rod to Water Pipe sleeve and make good all round at Column A18

101 Basement Car Park Level -1 Gen. Remove reinforcing rod to Water Pipe sleeve and make good all round at Column A16

102 Basement Car Park Level -1 Gen. Make good and seal water Pipe sleeve at Column A14

103 Basement Car Park Level -1 Gen. Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D14

104 Basement Car Park Level -1 Gen. Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D16

105 Basement Car Park Level -1 Gen. Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D18

106 Basement Car Park Level -1 Gen. Remove reinforcing rod to Water Pipe sleeve and make good all round at Column D20

107 Basement Car Park Level -1 Gen. Install operator signage to Fire Alarm Button at wall C17

108 Basement Car Park Level -1 Gen. Install operator signage to Fire Alarm Button at wall B18

109 Basement Car Park Level -1 Gen. Install operator signage to Fire Alarm Button at wall B14

110 Basement Car Park Level -1 Gen. Install operator signage to Fire Alarm Button at wall D15

111 Basement Car Park Level -1 Gen. Warning notice required in area near Column A20 as the clearance height is 1.90 metres

112 Basement Car Park Level -1 Gen. Warning Notice needed in Car Park Area A 12/13 for a two meter length as pipes are set at a clearance height of 1.96 metres

113 Basement Car Park Level -1 Gen. Warning Notice needed in Car Park Area C 21 where pipes are at a clearance height on an access street of 2.06 metres

114 Basement Car Park Level -1 Gen. Warning notice needed in Car Park Area B 20/ 21 Boiler Flue as clearance height is 1.42 metres

115 Basement Car Park Level -1 Gen. Warning notice needed in Car Park Area B 20/21 as boiler flue pipes (Horizontal) clearance height is 1.70 to 1.87metres

116 Basement Car Park Level -1 Gen. Warning notice needed in Car Park Area A/B 20/21 as two pipe supports have a clearance height of 1.98metres

117 Basement Car Park Level -1 Gen. Carbon Monoxide signs ( 4 No) to also have warning in English

118 Basement Car Park Level -1 Gen. Refix loose sprinkler holder in A/B 17/18

119 Basement Car Park Level -1 Gen. Remove red paint daubs on soffit of ceiling slab in Area A/B 17/18

120 Basement Car Park Level -1 Gen. Suspended Running Man sign near door south to Stair Vestib S1E.06 is showing opposite flow to RMS on wall B18

121 Basement Car Park Level -1 Gen. Make good and seal at wall head B 17/18

122 Basement Car Park Level -1 Gen. Make good and seal to sprinkler pipe on Wall head B 17/18

123 Basement Car Park Level -1 Gen. Make good and seal around three (3) conduits to wall head B 17/18

124 Basement Car Park Level -1 Gen. Remove red paint daubs to Wall B 17125 Basement Car Park Level -1 Gen. Remove paint on Six Gang wall switch to LH of Door South on Wall B 17/18

126 Basement Car Park Level -1 Gen. Remove paint on flexible conduit to Fire Alarm Button on Wall B 17/18 to LH of door

127 Basement Car Park Level -1 Gen. Make good and seal at high level on Wall C/B 18 for five pipes entering duct in the middle

128 Basement Car Park Level -1 Gen. Remove plastic cover to Car Park Exhaust at A 13

129 Basement Car Park Level -1 Gen. Clean out in area between wall columns A12 and A13

130 Basement Car Park Level -1 Gen Refix supply conduit to Carbon Monoxide Sign on Column A 12

AMERICA HOUSE

Page 97: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 97/407

Ref. Location DefectNo.

133 Basement Car Park Level -1 Gen. Make good and seal wall to two (2) sprinkler pipes above door south to Elevator Lobby on Wall B 16/17

134 Basement Car Park Level -1 Gen. Duct B16/17 at southwest area of Elevator Lobby (external) has not been constructed

135 Basement Car Park Level -1 Gen. Seal wall head to South Wall of Elevator Lobby B 16/17 and make good

136 Basement Car Park Level -1 Gen. Remove timber formwork at ceiling near B16/17 on West Wall to Elevator Lobby and seal to pipe and make good

137 Basement Car Park Level -1 Gen. Complete insulation to two (2) pipes passing through to Elevator Lobby West Wall

138 Basement Car Park Level -1 Gen. Seal wall where two pipes pass through Elevator Lobby West Wall RH of central duct and make good

139 Basement Car Park Level -1 Gen. Seal Wall where one pipe passes through Elevator Lobby West Wall RH of central duct and make good

140 Basement Car Park Level -1 Gen. Seal Wall where one pipe passes through Elevator Lobby West Wall LH of central duct and make good

141 Basement Car Park Level -1 Gen. Seal Wall C 17/18 to four (4) conduits pass into Elevator Lobby to LH of door at wall head and make good

142 Basement Car Park Level -1 Gen. Seal Wall above door north to Elevator Lobby for sprinkler pipe and make good C 16/17

143 Basement Car Park Level -1 Gen. Remove red paint on Wall C 17/18 near sprinkler pipe

144 Basement Car Park Level -1 Gen. Seal Wall C 17/18 to two (2) conduits pass into Elevator Lobby to RH of door at wall head and make good

145 Basement Car Park Level -1 Gen. Running Man Sign (suspended) opposite Door to Stair Vestibule S1E.06 North is very loose and needs to be properly fixed

146 Basement Car Park Level -1 Gen. Running Man Sign (suspended) opposite Door to Stair Vestibule S1E.06 North is in conflict with RMS on Wall C 17

147 Basement Car Park Level -1 Gen. Seal hole in ceiling at C17 and make good

148 Basement Car Park Level -1 Gen. Remove paint to six gang switch on RH of Door North to Stair Vestibule S1E.06

149 Basement Car Park Level -1 Gen. Seal wall head on C17/18 at Stair Vestibule S1E.06

150 Basement Car Park Level -1 Gen. Remove timber formwork at wall head to Wall C 17/18 and make good including repainting

151 Basement Car Park Level -1 Gen. Seal to four (4) conduits and one sprinkler pipe above door north to Stair Vestibule S1E.06 and make good C 17/18

152 Basement Car Park Level -1 Gen. Seal to four (4) conduits and one pipe above door north to Stair Vestibule S1E.06 and make good C 17/18

153 Basement Car Park Level -1 Gen. Seal to two (2) conduits above door north RH to Stair Vestibule S1E.06 and make good C 17/18

154 Basement Car Park Level -1 Gen. Make good to wall C 17/18 LH side near ceiling

155 Basement Car Park Level -1 Gen. Remove paint on flexible conduit to Fire Alarm Button on Wall C 17/18 to LH of door

156 Basement Car Park Level -1 Gen. Clean out area between Wall columns D12 and D13

157 Basement Car Park Level -1 Gen. Fill in twenty six abortive drilled hole in column D12158 Basement Car Park Level -1 Gen. Fix loose conduit supply to Carbon Monoxide sign on Column D12

159 Basement Car Park Level -1 Gen. Make good around three (3) large pipes on North Wall at D 13 and seal

160 Basement Car Park Level -1 Gen. Make good to kerb along North Wall between D13 and 14

161 Basement Car Park Level -1 Gen. Make good electrical connection to exhaust box near D 14/15 and tidy up

162 Basement Car Park Level -1 Gen. Repair and make good to area of crazed plaster render on duct wall at D 14

163 Basement Car Park Level -1 Gen Make good to wall and column at D 15 and repaint

AMERICA HOUSE

Page 98: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 98/407

Ref. Location DefectNo.

166 Basement Car Park Level -1 Gen. Seal to four (4) conduits and one pipe above door north to Stair Vestibule S1E.03 and make good C14/15

167 Basement Car Park Level -1 Gen. Seal to three (3) SVP pipes in ceiling slab in Area C/D 14/15 and make good all round

168 Basement Car Park Level -1 Gen. Make good to Wall C14/15 where conduit and outlet box removed to heater to RH of door to Stair Vestibule S1E.03

169 Basement Car Park Level -1 Gen. Provide impact protection to ceiling mounted heater unit near Wall C 14

170 Basement Car Park Level -1 Gen. Seal to two (2) conduits near door north LH to Stair Vestibule S1E.03 and make good C 14/15

171 Basement Car Park Level -1 Gen. Seal to one (1) conduits near door north LH to Stair Vestibule S1E.03 and make good C 14/15

172 Basement Car Park Level -1 Gen. Seal to two (2) SVP pipes near door north RH to Stair Vestibule S1E.03 and make good C 14/15

173 Basement Car Park Level -1 Gen. Make good to wall near C 14 and repaint

174 Basement Car Park Level -1 Gen. Remove paint on flexible conduit to Fire Alarm Button on Wall C 14/15 to LH of door

175 Basement Car Park Level -1 Gen. Seal large hole in ceiling slab near C 15 and make good all round

176 Basement Car Park Level -1 Gen. Seal to three (3) conduits and one (1) small pipe at ceiling near door north LH to Stair Vestibule S1E.03 and make good C 14/15

177 Basement Car Park Level -1 Gen. Remove large cable end in West Wall BC 14

178 Basement Car Park Level -1 Gen. Make good and seal to five (5) large pipes entering shaft on West Wall to Stair BC 14 and repaint

179 Basement Car Park Level -1 Gen. Stabilise sprinkler pipework in area BC 13/14 as loose

180 Basement Car Park Level -1 Gen. Repaint wall at high level near B14 on west wall to stair S1E.04

181 Basement Car Park Level -1 Gen. Remove small pipe protruding from wall BC 14

182 Basement Car Park Level -1 Gen. Seal to three (3) conduits and one (1) small pipe above door south LH to Stair Vestibule S1E.03 and make good B 14/15

183 Basement Car Park Level -1 Gen. Remove paint on flexible conduit to Fire Alarm Button on Wall B 14/15 to LH of door

184 Basement Car Park Level -1 Gen. Remove paint on Six Gang wall switch to RH of Door South on Wall B 14/15

185 Basement Car Park Level -1 Gen. Make good electrical connection to exhaust box near D 20 and tidy up

186 Basement Car Park Level -1 Gen. Remove temporary water pipe near D18 etc and make good hole and seal

187 Basement Car Park Level -1 Gen. Seal water pipe at floor in corner RH of wall column D 18

188 Basement Car Park Level -1 Gen. Seal water pipe at floor in corner LH of wall column D 18

189 Basement Car Park Level -1 Gen. Remove cement render that is defective and redo near pipes to LH of Wall Column D 18

190 Basement Car Park Level -1 Gen. Make good around four (4) pipes entering north wall to LH of D18 and seal191 Basement Car Park Level -1 Gen. Make good and seal at wall head to North Wall to LH of Wall Column D 18

192 Basement Car Park Level -1 Gen. Provide impact protection for four (4) large pipes in North Wall to LH of Wall Column D18

193 Basement Car Park Level -1 Gen. Provide impact protection for three (3) large pipes in North Wall to LH of Wall Column D13

194 Basement Car Park Level -1 Gen. Make good hole at high level in Wall Column D 19

195 Basement Car Park Level -1 Gen. Make good to Wall D 19/20 where conduit and outlet box removed to heater

196 Basement Car Park Level -1 Gen Provide impact protection to ceiling mounted heater unit near Wall D 19

AMERICA HOUSE

Ref Location Defect

Page 99: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 99/407

Ref. Location Defect

No.

199 Basement Car Park Level -1 Gen. Make good at wall head to North Wall between D 20/21 and repaint

200 Basement Car Park Level -1 Gen. Paint area approx 1m2 of slab with floor paint at base of Car Park Ramp

201 Basement Car Park Level -1 Gen. Make good to two (2) formwork fixture hole in Wall Column D 21 and seal

202 Basement Car Park Level -1 Gen. Seal and make good to SVP at ceiling level near D21

203 Basement Car Park Level -1 Gen. Make good flexible conduit connections to CCTV Camera D21 at base of Ramp

204 Basement Car Park Level -1 Gen. Works related to Valve Room S1E.14 have not been done

205 Basement Car Park Level -1 Gen. Works related to Vestibule Room S1E.15 have not been done

206 Basement Car Park Level -1 Gen. Works related to Storage Area S1E.16 have not been done yet207 Basement Car Park Level -1 Gen. Works related to Area under Car Park Ramp have not been done yet

208 Basement Car Park Level -1 Gen. Remove two hanger rods in ceiling of Area S1E.16 Storage and make good

209 Basement Car Park Level -1 Gen. Make good and seal wall head to splay wall D21/C23

210 Basement Car Park Level -1 Gen. Refix loose ceiling conduits in Area Storage S1E.16

211 Basement Car Park Level -1 Gen. Fire Fighting Equipment is missing

212

213

214

215

216

217

218

219

220

221

222

223

224

225

226

227

228

229

AMERICA HOUSE

Page 100: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 100/407

Ref. Location DefectNo.

1 Egress Stair S1E.04 Clean light at Landing -1

2 Egress Stair S1E.04 Remove paint stains to top edges of skirting to landing and stairs throughout

3 Egress Stair S1E.04 Clean light fitting on mid-landing that is covered in paint etc.

4 Egress Stair S1E.04 Landing tiles are uneven and need to be levelled and repolished

5 Egress Stair S1E.04 Stair are badly stained and need deep cleaned and repolished

6 Egress Stair S1E.04 Floor tiling at -2 is uneven and needs levelled and repolished

7 Egress Stair S1E.04 Replace one (1) chipped step

8 Egress Stair S1E.04 Replace tile at base on divider wall -1 level which has been formed in two parts and not one

9 Egress Stair S1E.04 Make good skirting to bases of door

10 Egress Stair S1E.04 Remove paint on Running Man sign

11 Egress Stair S1E.04 Remove paint from door and frames

12 Egress Stair S1E.04 Fix permanent handles to doors and make good

13 Egress Stair S1E.04 Remove protective covering that remains on door

14 Egress Stair S1E.04 Intumescent strip is not complete to hinge and open frame bases

15 Egress Stair S1E.04 Fixing screws to frame protrude and are to be refixed

16 Egress Stair S1E.04 Cover four (4) protruding screw ends in angle plate to top corner

17 Egress Stair S1E.04 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

18 Egress Stair S1E.04 Install door stop

19 Egress Stair S1E.04 Install door closer

20 Egress Stair S1E.04 Door Signage

21 Egress Stair S1E.04 Fire/Smoke Threshold seal is required to door

22 Egress Stair S1E.04 Door to be adjusted as it has squeak and does not close properly

23 Egress Stair S1E.04 Remove paint on flexible conduit to Fire Detector

24 Egress Stair S1E.04 Seal hole at ceiling level to southeast corner and make good

AMERICA HOUSE

Page 101: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 101/407

Ref. Location DefectNo.

1 Stair Vestibule S1E.03 Remove paint and cement to South Door frames

2 Stair Vestibule S1E.03 Fix permanent handles to door South and make good

3 Stair Vestibule S1E.03 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule S1E.03 Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule S1E.03 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule S1E.03 Intumescent str ip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule S1E.03 Install door stop to Door South

8 Stair Vestibule S1E.03 Install door closer to Door South

9 Stair Vestibule S1E.03 Remove cement render on door south head frame and make good

10 Stair Vestibule S1E.03 Clean paint on floor tiles at Door South

11 Stair Vestibule S1E.03 Fire/Smoke Threshold seal is required to door South

12 Stair Vestibule S1E.03 Remove red paint on floor tiling near Door South

13 Stair Vestibule S1E.03 Clean conduit to light switch (south) of paint etc

14 Stair Vestibule S1E.03 Running Man sign obstructs the sprinkler head in operation mode and needs to be reviewed

15 Stair Vestibule S1E.03 Carbon Monoxide Warning sign obstructs the sighting of the RMS sign when coming from the North Door & should be relocated or re

16 Stair Vestibule S1E.03 Carbon Monoxide sign to have English Warning

17 Stair Vestibule S1E.03 Clean paint etc from two (2) light fittings

18 Stair Vestibule S1E.03 Clean paint of grille to Fire Damper Grille (Upper)

19 Stair Vestibule S1E.03 Clean paint of grille to Fire Damper Grille (Lower)

20 Stair Vestibule S1E.03 Make good round Fire Damper Grille panel (Lower)

21 Stair Vestibule S1E.03 Make good round Fire Damper Grille panel (Upper)

22 Stair Vestibule S1E.03 Provide proper locking device to Lower Fire Damper Grille

23 Stair Vestibule S1E.03 Provide proper locking device to Upper Fire Damper Grille

24 Stair Vestibule S1E.03 Make good to wall on LH side of Door North

25 Stair Vestibule S1E.03 Make good to wall on RH side of Door North26 Stair Vestibule S1E.03 Remove remaining protective covering on door North

27 Stair Vestibule S1E.03 Fix permanent handles to door North and make good

28 Stair Vestibule S1E.03 Intumescent strip is not complete to both frame bases of Door North

29 Stair Vestibule S1E.03 Fixing screws to frame protrude and are to be refixed to Door North

30 Stair Vestibule S1E.03 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Stair Vestibule S1E 03 Intumescent str ip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

AMERICA HOUSE

Page 102: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 102/407

Ref. Location DefectNo.

34 Stair Vestibule S1E.03 Remove paint and cement render off door fames to Door North and make good

35 Stair Vestibule S1E.03 Glass Key Box to Fire Hosereel box the glass is missing and should re replaced with a Break Glass Key Box

36 Stair Vestibule S1E.03 Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

37 Stair Vestibule S1E.03 Seal openings between Fire Hosereel (FHE) door frame and blockwork all round

38 Stair Vestibule S1E.03 Seal Sprinkler pipe at ceiling slab level and make good

39 Stair Vestibule S1E.03 Upper hosereel to be relocated as fouls the door to the FHE

40 Stair Vestibule S1E.03 Make good door cill inside FHE which is 200mm too low

41 Stair Vestibule S1E.03 Seal pipe holes Two (2) in floor slab

42 Stair Vestibule S1E.03 Inside this duct the two walls to the HVAC shafts (RH) have not been installed and require to be executed

43 Stair Vestibule S1E.03 Ventilation duct protrudes into the FHE and requires to be fire rated

44 Stair Vestibule S1E.03 Tidy up blockwork above door and generally and make good

45 Stair Vestibule S1E.03 Wall to LH is missing on the top courses and needs to be completed and sealed

46 Stair Vestibule S1E.03 Lower hosereel feed valve to be relocated as below the door cill and difficult to operate

47 Stair Vestibule S1E.03 Provide Type C connection to Dry Riser

48 Stair Vestibule S1E.03 Remove red paint on floor near Fire Hosereel Enclosure (FHE)

49 Stair Vestibule S1E.03 Remove paint to top edges of skirting throughout

50 Stair Vestibule S1E.03 Paint ceiling

51 Stair Vestibule S1E.03 Screw in fixing screws to Carbon Monoxide sign that protrude

52 Stair Vestibule S1E.03 Door pivot screws to head and cill of Fire Hosereel Door to be fully driven

53 Stair Vestibule S1E.03 Make good at threshold to North Door as floor tiling is not completed

54 Stair Vestibule S1E.03 Repaint black/yellow threshold plate to South Door and remove masking tape

55 Stair Vestibule S1E.03 Refix black/yellow threshold plate to South Door as not even

56 Stair Vestibule S1E.03 Repaint black/yellow threshold plate to North Door and remove masking tape

57 Stair Vestibule S1E.03 Refix black/yellow threshold plate to North Door as not even

58 Stair Vestibule S1E.03 Floor tiling is uneven and requires to be levelled and resealed and repolished59 Stair Vestibule S1E.03 Fix skirting to LH of Door South

60 Stair Vestibule S1E.03 Fix skirting to RH of Door South

61 Stair Vestibule S1E.03 Make good skirting to LH of Door North

62 Stair Vestibule S1E.03 Make good skirting to RH of Door North

63 Stair Vestibule S1E.03 Make good skirting on West Wall South at conduit to light switch

64 Stair Vestibule S1E 03 Make good skirting on West Wall North at conduit to light switch

AMERICA HOUSE

Ref. Location Defect

Page 103: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 103/407

No.

67 Stair Vestibule S1E.03 Remove plaster on skirting near Door South LH and make good

68 Stair Vestibule S1E.03 Seal hole ceiling (South) and make good

69 Stair Vestibule S1E.03 Seal hole in ceiling (Mid) and make good

70 Stair Vestibule S1E.03 Seal wall for four (4) conduits on West Wall to LH of door to Stair and make good including repainting

71 Stair Vestibule S1E.03 Refix conduit at ceiling level on west wall which is poorly installed

72 Stair Vestibule S1E.03 Repaint wall West at northern end near door

73 Stair Vestibule S1E.03 Seal void in West Wall at northwest corner, make good and repaint

74 Stair Vestibule S1E.03 Relocate junction box on south wall LH that is partially in wall and not accessible and thereafter make good all round 75 Stair Vestibule S1E.03 Make good to render repair above Door South and repaint

76 Stair Vestibule S1E.03 Seal wall for four (4) conduits and one (1) small pipe on North Wall above door to Stair and make good including repainting

77 Stair Vestibule S1E.03 Seal wall for two (2) conduits on North Wall to LH of door and make good including repainting

78 Stair Vestibule S1E.03 Seal wall for one (1) conduit on East Wall to at ceiling level and make good including repainting

79 Stair Vestibule S1E.03 Seal wall for one (1) sprinkler pipe on East Wall near ceiling level (Mid) and make good including repainting

80 Stair Vestibule S1E.03 Seal wall for one (1) sprinkler pipe on East Wall near ceiling level (South) and make good including repainting

81 Stair Vestibule S1E.03 Make good at bulkhead in southeast corner and repaint

AMERICA HOUSE

Ref. Location Defect

Page 104: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 104/407

No.

1 Service Elevator Vestibule S1E.05 Paint ceiling

2 Service Elevator Vestibule S1E.05 Fit permanent door handles

3 Service Elevator Vestibule S1E.05 Door frame at bases is 8mm above floor finish and requires to be adjusted

4 Service Elevator Vestibule S1E.05 Fill in hole to door head frame

5 Service Elevator Vestibule S1E.05 Adjust inner leaf of door as it is still loose when closed

6 Service Elevator Vestibule S1E.05 Fixing screws to frame protrude and are to be refixed to Door

7 Service Elevator Vestibule S1E.05 Cover four (4) protruding screw ends in angle plate to top corner to Door

8 Service Elevator Vestibule S1E.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestibule S1E.05 Remove remaining protective covering to doors

10 Service Elevator Vestibule S1E.05 Door outer leaf requires adjustment to close properly

11 Service Elevator Vestibule S1E.05 Seal and make good conduit hole above Door North

12 Service Elevator Vestibule S1E.05 Seal and make good to hole for sprinkler pipe above Door North and remove red paint on wall

13 Service Elevator Vestibule S1E.05 Skirting is fixed with panel pins and requires to fixed with adhesive or better

14 Service Elevator Vestibule S1E.05 Replace missing skirting corner at RH of Lift Entry

15 Service Elevator Vestibule S1E.05 Install door stops to Doors

16 Service Elevator Vestibule S1E.05 Clean paint off Service Lift Door Frames

17 Service Elevator Vestibule S1E.05 Clean paint off service lift call and indicator wall panels

18 Service Elevator Vestibule S1E.05 Seal wall head to North Wall and make good

19 Service Elevator Vestibule S1E.05 Clean light fitting of paint and dirt inside

20 Service Elevator Vestibule S1E.05 Seal conduit hole at ceiling level

21 Service Elevator Vestibule S1E.05 Install selector and door closers

22 Service Elevator Vestibule S1E.05 Remove paint to door frames

23 Service Elevator Vestibule S1E.05 Remove red paint daubs on walls

24 Service Elevator Vestibule S1E.05 Seal wall head to West Wall and make good

25 Service Elevator Vestibule S1E.05 Seal wall head to East Wall and make good26 Service Elevator Vestibule S1E.05 Make good to floor subsidence near duct to LH side of North Door and repaint etc.

27 Service Elevator Vestibule S1E.05 Fix dome covers to four (4) screws to grille in duct to northwest corner or change to white headed screws as elsewhere

28 Service Elevator Vestibule S1E.05 Carbon monoxide signage to also be in English

29 Service Elevator Vestibule S1E.05 Refix black/yellow threshold angle

30 Service Elevator Vestibule S1E.05 Repaint black/yellow threshold angle

31 Service Elevator Vestibule S1E 05 Seal wall head to South Wall and make good

AMERICA HOUSE

Ref. Location Defect

No

Page 105: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 105/407

No.

34 Service Elevator Vestibule S1E.05 Carbon Monoxide Sign is very high and cannot be readily seen and requires to be relocated

35 Service Elevator Vestibule S1E.05 Sprinkler pipework is not stable and requires to be properly fixed

36 Service Elevator Vestibule S1E.05 Make good to floor tiling finish at lift entry

37 Service Elevator Vestibule S1E.05 Make good to damaged wall edging LH of Lift Entry

AMERICA HOUSE

Ref. Location Defect

N

Page 106: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 106/407

No.

1 Telephone Closet S1E.17 Prepare floor to be level and relay floor covering properly

2 Telephone Closet S1E.17 Install skirting to walls all round

3 Telephone Closet S1E.17 Seal wall hole (East Upper) where conduit tray passes through into Car Park Area

4 Telephone Closet S1E.17 Seal wall hole (West Upper) where conduit tray passes through into Car Park Area

5 Telephone Closet S1E.17 Provide and install closure screws to four (4) control boxes on west wall above four control units

6 Telephone Closet S1E.17 Clean all paint and cement grout of conduits

7 Telephone Closet S1E.17 Connect or remove two (2) unconnected wires in Lower box in southwest corner

8 Telephone Closet S1E.17 Paint walls9 Telephone Closet S1E.17 Make good joint between wall and floor

10 Telephone Closet S1E.17 Remove manufacture's labels on door

11 Telephone Closet S1E.17 Remove writing on face of door

12 Telephone Closet S1E.17 Fixing screws to frame protrude and are to be refixed to Door

13 Telephone Closet S1E.17 Cover four (4) protruding screw ends in angle plate to top corner to Door

14 Telephone Closet S1E.17 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

15 Telephone Closet S1E.17 Intumescent strip is not complete to open jamb

16 Telephone Closet S1E.17 Intumescent strip is shirt at base on the hinge jamb and to be replaced

17 Telephone Closet S1E.17 Install permanent door handles

18 Telephone Closet S1E.17 Install door stop

19 Telephone Closet S1E.17 Install door closer

20 Telephone Closet S1E.17 Clean threshold plate and paint and also make good to reinforcing rod anchors

21 Telephone Closet S1E.17 Paint ceiling

22 Telephone Closet S1E.17 Door Signage

23 Telephone Closet S1E.17 Remove cement and paint on door frames and intumescent strip

24 Telephone Closet S1E.17 Remove all remaining protective covering to door

25 Telephone Closet S1E.17 Make good to bodged up cable duct at high level in west wall above door26 Telephone Closet S1E.17 Remove paint on power outlet to RH of door externally

27 Telephone Closet S1E.17 Tighten up screws to grey box on North wall

28 Telephone Closet S1E.17 Make good wall to LH side of door externally and repaint

29 Telephone Closet S1E.17 Make good pointing and seal around door externally to jambs and head frames

30 Telephone Closet S1E.17 Make good to two (2) holes to RH of door externally and seal

31 Telephone Closet S1E.17 Clean cement on door contact (head frame)

AMERICA HOUSE

Ref. Location Defect

No.

Page 107: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 107/407

No.

34 Telephone Closet S1E.17 Make good wiring to door intruder contacts as very untidy

35 Telephone Closet S1E.17 Seal wall (West) on RH side near north wall to RH of door and make good including repainting

36 Telephone Closet S1E.17 Make good to conduits near four control boxes on West Wall

37 Telephone Closet S1E.17 Make good to several drilled abortive holes on West Wall to RH of four control boxes

38 Telephone Closet S1E.17 Make good to several drilled abortive holes on South Wall

Page 108: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 108/407

AMERICA HOUSE

Ref. Location Defect Ra

No. Cl

Page 109: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 109/407

34 Electrical Closet S1E.18 Make good to sixteen (16) abortive holes on south wall and repaint

35 Electrical Closet S1E.18 Make good at wall head on West wall and repaint as required

36 Electrical Closet S1E.18 make good at wall near ceiling around conduit and seal etc.

AMERICA HOUSE

Ref. Location Defect

No.

Page 110: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 110/407

No.

1 Elevator Lobby S1E.01 Remove floor steel plate to RH of Door North to Elevator Lobby externally and make good all round

2 Elevator Lobby S1E.01 Fixing screws to frame protrude and are to be refixed to Double Door South

3 Elevator Lobby S1E.01 Cover four (4) protruding screw ends in angle plate to top corners to Double Door South

4 Elevator Lobby S1E.01 Intumescent str ip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

5 Elevator Lobby S1E.01 Install permanent door handles Door South

6 Elevator Lobby S1E.01 Install door stops to Double Door South

7 Elevator Lobby S1E.01 Install door closers and selector to Door South

8 Elevator Lobby S1E.01 Inner door of leaf has a play when closed and requires to be adjusted9 Elevator Lobby S1E.01 Remove red paint splashes on door frames

10 Elevator Lobby S1E.01 Remove all protective covering to Double Door South

11 Elevator Lobby S1E.01 Make good to rectangular hole in head frame Door South

12 Elevator Lobby S1E.01 Remove masking tape to threshold plate

13 Elevator Lobby S1E.01 Remove general paint to door frames at sides and head all round

14 Elevator Lobby S1E.01 Clean threshold plate to Lift/Elevator

15 Elevator Lobby S1E.01 Fixing screws to frame protrude and are to be refixed to Double Door North

16 Elevator Lobby S1E.01 Cover four (4) protruding screw ends in angle plate to top corners to Double Door North

17 Elevator Lobby S1E.01 Intumescent str ip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

18 Elevator Lobby S1E.01 Make good to wall lining joints in recess and repaint completely

19 Elevator Lobby S1E.01 Refix conduit at ceiling level on East Wall as currently poorly installed

20 Elevator Lobby S1E.01 Remove wall paint on North door frames

21 Elevator Lobby S1E.01 Install permanent door handles on Double Door North

22 Elevator Lobby S1E.01 Install door stops to Double Door North

23 Elevator Lobby S1E.01 Install door closers and selector to Double Door North

24 Elevator Lobby S1E.01 Remove paint on call and arrow indicator panels to Lift on East Wall

25 Elevator Lobby S1E.01 Remove all remaining protective covering to Door North

26 Elevator Lobby S1E.01 Remove manufacture's labels on door and make good

27 Elevator Lobby S1E.01 Make good to rectangular hole in head frame Door North

28 Elevator Lobby S1E.01 Clean two (2) light fittings

29 Elevator Lobby S1E.01 Remove paint to lift stainless steel frames all round

30 Elevator Lobby S1E.01 Refix skirting with proper fixing system and remove panel pins throughout

31 Elevator Lobby S1E 01 Fix missing skirting corners on both sides of door to Lift Entry

AMERICA HOUSE

Ref. Location Defect

No.

Page 111: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 111/407

34 Elevator Lobby S1E.01 Seal and make good hole near ceiling on South wall to RH above door

35 Elevator Lobby S1E.01 Seal and make good hole near ceiling on South wall to LH above door

36 Elevator Lobby S1E.01 Seal and make good to two (2) sprinkler pipes above Door South

37 Elevator Lobby S1E.01 Seal and make good to one (1) sprinkler pipes on West Wall and remove red paint daubs nearby

38 Elevator Lobby S1E.01 Clean paint stains on radiator on West Wall

39 Elevator Lobby S1E.01 Seal and make good to two (2) conduits on North Wall near ceiling RH

40 Elevator Lobby S1E.01 Seal and make good to three (3) conduits on North Wall near ceiling LH

41 Elevator Lobby S1E.01 Seal and make good to two (2) sprinkler pipes above door on North Wall 42 Elevator Lobby S1E.01 Finish wall paint externally to Elevator Lobby North at floor level to RH of North Door

43 Elevator Lobby S1E.01 Remove masking tape to threshold plate to North Door

44 Elevator Lobby S1E.01 Remove paint on outlet socket to North Wall externally the LH side of North Door to Elevator Lobby

45 Elevator Lobby S1E.01 Remove red paint above door to North Wall externally

46 Elevator Lobby S1E.01 Finish wall paint to left of Wall Socket on LH side of Door North externally

47 Elevator Lobby S1E.01 Carbon Monoxide Warning to also be in English

48 Elevator Lobby S1E.01 Tighten up all loose screws to Carbon Monoxide sign

49 Elevator Lobby S1E.01 Seal West Wall at ceiling level where conduit passes through on LH side and make good

50 Elevator Lobby S1E.01 Seal West Wall where conduit sprinkler pipe passes through on RH side and make good

51 Elevator Lobby S1E.01 Angle steel threshold step to Door North to be refixed and painted with black and yellow diagonal stripes

52 Elevator Lobby S1E.01 Angle steel threshold step to Door South to be refixed and painted with black and yellow diagonal stripes

53 Elevator Lobby S1E.01 Door Signage South

54 Elevator Lobby S1E.01 Door Signage North

55 Elevator Lobby S1E.01 Remove floor paint above skirting on West Wall

56 Elevator Lobby S1E.01 Seal West Wall at where small pipe passes through on RH side

57 Elevator Lobby S1E.01 Make good subsidence/damage to wall/floor on West Wall and repaint as required

58 Elevator Lobby S1E.01 Clean paint of both lift panels call and indicator to RH side

59 Elevator Lobby S1E.01 Infill sinking to storage area door and repaint floor

60 Elevator Lobby S1E.01 Make good to dent in Door South on Car Park side

61 Elevator Lobby S1E.01 Fire/Smoke Threshold seal is required to door North

62 Elevator Lobby S1E.01 Fire/Smoke Threshold seal is required to door South

63 Elevator Lobby S1E.01 Make good floor in recess on East wall and paint floor and down stand complete

64

AMERICA HOUSE

Ref. Location Defect

No.

Page 112: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 112/407

1 Egress Stair S1E.07 Remove tape on steps used fro temporary protection in this area

2 Egress Stair S1E.07 Clean down steps of dirt marks, concrete etc complete

3 Egress Stair S1E.07 Floor tiling to mid landing is uneven and to be levelled and resealed/polished

4 Egress Stair S1E.07 Floor tiling to stair floor at -2 is uneven and to be levelled and resealed/polished and insert missing grout between some tiles

5 Egress Stair S1E.07 Make good to damaged skirting at upper flight on first step LH

6 Egress Stair S1E.07 Replace one (1) chipped step

7 Egress Stair S1E.07 Clean light fitting at mid landing

8 Egress Stair S1E.07 Remove paint from Running Man Sign9 Egress Stair S1E.07 Clean Light Fitting at Base Level

10 Egress Stair S1E.07 Remove paint to Base Entry Door and Frames including red paint

11 Egress Stair S1E.07 Fixing screws to frame protrude and are to be refixed to Door South

12 Egress Stair S1E.07 Cover four (4) protruding screw ends in angle plate to top corner to Door South

13 Egress Stair S1E.07 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

14 Egress Stair S1E.07 Intumescent strip to LH and RH door jambs is not complete at bases and to be replaced

15 Egress Stair S1E.07 Remove remaining protective covering to doors

16 Egress Stair S1E.07 Fix missing strike plate to open door jamb

17 Egress Stair S1E.07 Install permanent door handles (temporary handle broken on inner side)

18 Egress Stair S1E.07 Install door stop to Door

19 Egress Stair S1E.07 Install door closer to Door

20 Egress Stair S1E.07 Make good tiles skirting to LH side of door

21 Egress Stair S1E.07 Door signage

22 Egress Stair S1E.07 Fire/Smoke Threshold seal is required to door

23 Egress Stair S1E.07 Remove paint on top edge of skirting throughout including steps

24 Egress Stair S1E.07 Clean paint on flexible conduit to Fire Detector

25

26

27

28

29

30

31

AMERICA HOUSE

Ref. Location Defect

No.

Page 113: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 113/407

1 Stair Vestibule S1E.06 Remove paint and cement to South Door Frames

2 Stair Vestibule S1E.06 Fix permanent handles to door South and make good

3 Stair Vestibule S1E.06 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule S1E.06 Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule S1E.06 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule S1E.06 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

7 Stair Vestibule S1E.06 Install door stop to Door South

8 Stair Vestibule S1E.06 Install door closer to Door South9 Stair Vestibule S1E.06 Remove remaining parts of the protective covering to door South

10 Stair Vestibule S1E.06 Screw missing in lock plate to door South

11 Stair Vestibule S1E.06 Paint ceiling

12 Stair Vestibule S1E.06 Remove paint on floor

13 Stair Vestibule S1E.06 Remove paint on frames of Fire Hosereel Enclosure (FHE)

14 Stair Vestibule S1E.06 Running Man sign obstructs the sprinkler head in operation mode and needs to be reviewed

15 Stair Vestibule S1E.06 Carbon Monoxide sign to have English Warning

16 Stair Vestibule S1E.06 Remove paint from top edge of skirting

17 Stair Vestibule S1E.06 Clean paint etc from two (2) light fittings

18 Stair Vestibule S1E.06 Remove red paint stains from wall generally

19 Stair Vestibule S1E.06 Make good round Fire Damper Grille panel (Lower)

20 Stair Vestibule S1E.06 Make good round Fire Damper Grille panel (Upper)

21 Stair Vestibule S1E.06 Provide proper locking device to Lower Fire Damper Grille

22 Stair Vestibule S1E.06 Provide proper locking device to Upper Fire Damper Grille

23 Stair Vestibule S1E.06 Clean paint off grille to Fire Damper panel (Lower)

24 Stair Vestibule S1E.06 Clean paint off grille to Fire Damper panel (Upper)

25 Stair Vestibule S1E.06 Screw missing in lock plate to door North

26 Stair Vestibule S1E.06 Clean paint and cement off door Frame to Door North

27 Stair Vestibule S1E.06 Fix permanent handles to door North and make good

28 Stair Vestibule S1E.06 Intumescent strip is not complete to both frame bases of Door North

29 Stair Vestibule S1E.06 Fixing screws to frame protrude and are to be refixed to Door North

30 Stair Vestibule S1E.06 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Stair Vestibule S1E 06 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

AMERICA HOUSE

Ref. Location Defect

No.

Page 114: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 114/407

34 Stair Vestibule S1E.06 Remove remaining parts of the protective covering to Door North

35 Stair Vestibule S1E.06 Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box

36 Stair Vestibule S1E.06 Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

37 Stair Vestibule S1E.06 Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

38 Stair Vestibule S1E.06 Remove masking tape to FHE Door panel frames

39 Stair Vestibule S1E.06 Seal to head of door frame with blockwork and make good

40 Stair Vestibule S1E.06 Make good door cill inside FHE

41 Stair Vestibule S1E.06 Seal pipe hole on RH to wall and make good42 Stair Vestibule S1E.06 Inside this duct the two walls to the HVAC shafts have not been installed and require to be executed

43 Stair Vestibule S1E.06 Fire proofing required to ventilation shaft in Fire Hosereel enclosure or relocated

44 Stair Vestibule S1E.06 Seal and make good to floor slab for supply pipe

45 Stair Vestibule S1E.06 Seal to HVAC vent at slab

46 Stair Vestibule S1E.06 Clean out builder's debris in FHE

47 Stair Vestibule S1E.06 Provide Type C connection to Dry Riser

48 Stair Vestibule S1E.06 Floor tiling is uneven and needs to be levelled and repolished

49 Stair Vestibule S1E.06 Take off label to FHE door

50 Stair Vestibule S1E.06 Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

51 Stair Vestibule S1E.06 Remove paint on conduit on East Wall near Door South and make good

52 Stair Vestibule S1E.06 Make proper connection between conduit and light switch near Door South

53 Stair Vestibule S1E.06 Remove paint on conduit on East Wall near Door North and make good

54 Stair Vestibule S1E.06 Make proper connection between conduit and light switch near Door North

55 Stair Vestibule S1E.06 Complete paintwork to Northern parts of East Wall

56 Stair Vestibule S1E.06 Seal and make good to wall head of West wall

57 Stair Vestibule S1E.06 Seal and make good to one (1) sprinkler pipe in North wall above North Door

58 Stair Vestibule S1E.06 Seal and make good to five (5) conduits to RH side of North Door near ceiling

59 Stair Vestibule S1E.06 Seal and make good to four (4) conduits to LH side of North Door near ceiling

60 Stair Vestibule S1E.06 Remove paint from skirting top edges throughout

61 Stair Vestibule S1E.06 Provide angle steel threshold step to Door North and paint with black and yellow diagonal stripes

62 Stair Vestibule S1E.06 Provide angle steel threshold step to Door South and paint with black and yellow diagonal stripes

63 Stair Vestibule S1E.06 Make good to skirting to RH of Door North

64 Stair Vestibule S1E 06 Install threshold plate to Door South

AMERICA HOUSE

Ref. Location Defect

No.

67 Stair Vestibule S1E 06 Seal and make good to one (1) small dia pipe in North wall above North Door

Page 115: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 115/407

67 Stair Vestibule S1E.06 Seal and make good to one (1) small dia pipe in North wall above North Door

68 Stair Vestibule S1E.06 Seal and make good to one (1) sprinkler pipe in South wall to RH side of South Door near ceiling

69 Stair Vestibule S1E.06 Seal and make good to five (5) conduits to RH side of North Door near ceiling

70 Stair Vestibule S1E.06 Seal and make good to two (2) conduits to LH side of North Door near ceiling

71 Stair Vestibule S1E.06 Make good to hole above South Door near ceiling and repaint

72 Stair Vestibule S1E.06 Fire/Smoke Threshold seal is required to door North

73 Stair Vestibule S1E.06 Fire/Smoke Threshold seal is required to door South

AMERICA HOUSE

Ref. Location Defect

No.

1 M h i l R (CEX) S1E 13 Fi i t f t d d t b fi d t d

Page 116: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 116/407

1 Mechanical Room (CEX) S1E.13 Fixing screws to frame protrude and are to be refixed to door

2 Mechanical Room (CEX) S1E.13 Cover four (4) protruding screw ends in angle plate to top corner to door

3 Mechanical Room (CEX) S1E.13 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Mechanical Room (CEX) S1E.13 Intumescent strip to both door jamb is not complete at bases and to be replaced

5 Mechanical Room (CEX) S1E.13 Clean out frames at door base

6 Mechanical Room (CEX) S1E.13 Remove all protective covering that remains

7 Mechanical Room (CEX) S1E.13 Remove manufacturer's labels on door and make good

8 Mechanical Room (CEX) S1E.13 Fix permanent door handles9 Mechanical Room (CEX) S1E.13 Install door stop to Door

10 Mechanical Room (CEX) S1E.13 Install door closer to Door

11 Mechanical Room (CEX) S1E.13 Remove paint stains on door

12 Mechanical Room (CEX) S1E.13 Make good and seal to threshold plate and tidy up metal steel rod fixings

13 Mechanical Room (CEX) S1E.13 Remove paint and cement on door frames

14 Mechanical Room (CEX) S1E.13 Fire/Smoke seal threshold required to entry door

15 Mechanical Room (CEX) S1E.13 Door signage

16 Mechanical Room (CEX) S1E.13 Remove wood piece at RH door frame base

17 Mechanical Room (CEX) S1E.13 Make good and seal to door side and head frames all round on Vestibule side and repaint

18 Mechanical Room (CEX) S1E.13 Make good crack on south wall and repaint

19 Mechanical Room (CEX) S1E.13 Make good to wall and floor joint all around the room

20 Mechanical Room (CEX) S1E.13 Make good floor near threshold and repaint as required to floor

21 Mechanical Room (CEX) S1E.13 Paint wall where repair carried out on North Wall LH

22 Mechanical Room (CEX) S1E.13 Seal and make good the rectangular hole top RH in North Wall and all around cable tray

23 Mechanical Room (CEX) S1E.13 Seal and make good to pipe on south wall LH near floor

24 Mechanical Room (CEX) S1E.13 Seal and make good to pipe on south wall RH above door

25 Mechanical Room (CEX) S1E.13 Clean two (2) light fittings that are dirty inside

26 Mechanical Room (CEX) S1E.13 Remove wire fixing in ceiling and make good to northern end and repaint

27 Mechanical Room (CEX) S1E.13 Make good and seal where conduit passes though west wall at ceiling level

28 Mechanical Room (CEX) S1E.13 Make good to ceiling at several abortive holes to RH side of room and repaint

29 Mechanical Room (CEX) S1E.13 Seal and make good the rectangular hole top RH in East Wall and all around cable tray

30 Mechanical Room (CEX) S1E.13 Seal and make good around large Car Exhaust System duct

31 Mechanical Room (CEX) S1E 13 Make good to six (6) formwork fixing holes on East Wall

AMERICA HOUSE

Ref. Location Defect Ra

No. Cl34 Mechanical Room (CEX) S1E.13 Make good paint to wall on West Wall where repair executed on LH side

Page 117: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 117/407

35 Mechanical Room (CEX) S1E.13 Generally tidy up walls and touch up

36 Mechanical Room (CEX) S1E.13 Seal pipe at low level RH side of East Wall and make good all round

AMERICA HOUSE

Ref. Location Defect

No.

1 Storage S1E 09 Fixing screws to frame protrude and are to be refixed to door

Page 118: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 118/407

1 Storage S1E.09 Fixing screws to frame protrude and are to be refixed to door

2 Storage S1E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

3 Storage S1E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Storage S1E.09 Intumescent strip to both door jamb is not complete at bases and to be replaced

5 Storage S1E.09 Clean out frames at door base

6 Storage S1E.09 Remove all protective covering that remains

7 Storage S1E.09 Remove manufacturer's labels on door and make good

8 Storage S1E.09 Fix permanent door handles9 Storage S1E.09 Install door stop to Door

10 Storage S1E.09 Install door closer to Door

11 Storage S1E.09 Remove paint stains on door

12 Storage S1E.09 Make good and seal to threshold plate and tidy up metal steel rod fixings

13 Storage S1E.09 Remove paint and cement on door frames

14 Storage S1E.09 Fire/Smoke seal threshold required to entry door

15 Storage S1E.09 Door signage

16 Storage S1E.09 Replace missing screw in lock plate to door

17 Storage S1E.09 Make good and seal to door side and head frames all round on Vestibule side and repaint

18 Storage S1E.09 Make good to dent in door and if required replace

19 Storage S1E.09 Adjust door to close tightly as there is play in the door at the moment

20 Storage S1E.09 Seal door to side and head frames in vestibule and make good all round

21 Storage S1E.09 Make good to hole at LH side of entry door in the Vestibule Room S1E.08

22 Storage S1E.09 Relocate one of the sprinkler pipe hangers that fouls itself on one of the heating pipes

23 Storage S1E.09 Stabilise the sprinkler pipe installation as loose

24 Storage S1E.09 Make good joint between wall and floor and repaint as required

25 Storage S1E.09 Clean two (2) light fittings that are dirty inside

26 Storage S1E.09 Seal large hole in top LH side of West Wall around circular exhaust duct and make good all round

27 Storage S1E.09 Remove steel rod on RH side top of West wall and make good

28 Storage S1E.09 Paint West Wall

29 Storage S1E.09 Make good to two (2) formwork fixing holes and repaint as required

30 Storage S1E.09 Fit ventilation plat where hole covered with paper and string on South wall RH

31 Storage S1E.09 Paint South Wall

AMERICA HOUSE

Ref. Location Defect

No.

34 Storage S1E.09 Tidy up pipe in wall including cleaning concrete stain and align and fix properly

Page 119: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 119/407

3 Sto age S 09 dy up p pe a c ud g c ea g co c ete sta a d a g a d p ope y

35 Storage S1E.09 Seal open branch on pipe in wall in northwest corner

36 Storage S1E.09 Seal square hole on North wall and make good to LH side of door

37 Storage S1E.09 Make good and seal to duct opening above entry door and seal all round to six pipes

38 Storage S1E.09 Seal and make good to one sprinkler pipe above entry door and repaint

39 Storage S1E.09 Seal wall head above entry door and make good including repainting

40 Storage S1E.09 Make good to hole on North wall at floor level currently filled with insulation material and repaint LH

41 Storage S1E.09 Make good to hole on North wall at floor level near Entry door

42 Storage S1E.09 Seal and make good to duct hole for seven (7) pipes passing into Boiler Room on East Wall and repaint as required

43 Storage S1E.09 Seal and make good to square hole in top RH corner of East Wall and paint

44 Storage S1E.09 Paint patch repair on LH side of East Wall

45 Storage S1E.09 Remove steel rod near floor and make good to finishes

46 Storage S1E.09 Make good to six (6) formwork fixtures holes and repaint as required

AMERICA HOUSE

Ref. Location Defect

No.

1 Storage Area PE.02 Make good uneven ceiling edge trim to suspended ceiling all round and remove curled edges

Page 120: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 120/407

g g g g p g g

2 Storage Area PE.02 Replace one (1) damaged ceiling tile

3 Storage Area PE.02 Replace on stained ceiling tile near HVAC leak

4 Storage Area PE.02 Plastic skirting to be installed as missing completely

5 Storage Area PE.02 Trim missing to suspended ceiling around column B16 to be installed

6 Storage Area PE.02 Fixing screws to frame protrude and are to be refixed to door

7 Storage Area PE.02 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Storage Area PE.02 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

9 Storage Area PE.02 Intumescent strip to both door jamb is not complete at bases and to be replaced

10 Storage Area PE.02 Fit proper extended lock to inner face

11 Storage Area PE.02 Remove all protective covering that remains

12 Storage Area PE.02 Remove manufacturer's labels on door and make good

13 Storage Area PE.02 Screw fixing missing to lock plate on door

14 Storage Area PE.02 Install door stop to Door

15 Storage Area PE.02 Install door closer to Door

16 Storage Area PE.02 Remove paint stains on door

17 Storage Area PE.02 Make good to gap between mitred joint of frames at both heads18 Storage Area PE.02 Remove paint on door frames

19 Storage Area PE.02 Fire/Smoke seal threshold required to entry door

20 Storage Area PE.02 Door signage

21

22

23

24

25

26

27

28

29

30

31

AMERICA HOUSE

Ref. Location Defect

No.

1 Garbage Room PE.18 Paint sprinkler pipe installation to 2 sprinklers

Page 121: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 121/407

g p p p p

2 Garbage Room PE.18 Clean paint off light switch plate

3 Garbage Room PE.18 Paint floor

4 Garbage Room PE.18 Seal joint gap between floor and wall (this place is sluiced out regularly) and install skirting North Wall

5 Garbage Room PE.18 Seal joint gap between floor and wall (this place is sluiced out regularly) and install skirting South Wall

6 Garbage Room PE.18 Seal joint gap between floor and wall (this place is sluiced out regularly) and install skirting East Wall

7 Garbage Room PE.18 Seal joint gap between floor and wall (this place is sluiced out regularly) and install skirting West Wall

8 Garbage Room PE.18 Seal wall head to top of East Wall and make good to ceiling suffix and wall9 Garbage Room PE.18 Seal East wall to conduit at ceiling level and make good

10 Garbage Room PE.18 Seal wall head to top of South Wall and make good to ceiling soffit and wall

11 Garbage Room PE.18 Seal Wall around beam on South Wall on Grid Line C/D 15

12 Garbage Room PE.18 Seal South Wall for two small pipes and make good all round

13 Garbage Room PE.18 Seal around large duct on South Wall and make good all round

14 Garbage Room PE.18 Seal South Wall at cable tray and make good all round

15 Garbage Room PE.18 Seal wall head to top of West Wall and make good to ceiling soffit and wall

16 Garbage Room PE.18 Seal West Wall for two (2) conduits and make good all round

17 Garbage Room PE.18 Seal wall head to top of North Wall and make good to ceiling soffit and wall

18 Garbage Room PE.18 Seal North Wall at cable tray and make good all round

19 Garbage Room PE.18 Seal North wall for sprinkler pipes (2 No) and make good all round

20 Garbage Room PE.18 Seal North wall at square duct and make good all round

21 Garbage Room PE.18 Seal North Wall to large duct with large void above and make good all round for 2 hour fire rating

22 Garbage Room PE.18 Seal Wall around beam on North Wall on Grid Line C/D 15

23 Garbage Room PE.18 Repaint walls that have been damaged by dirty water

24 Garbage Room PE.18 Clean the two (2) light fittings that are dirty inside

25 Garbage Room PE.18 Make good to concrete threshold which is of poor construction

26 Garbage Room PE.18 Fixing screws to frame protrude and are to be refixed to door

27 Garbage Room PE.18 Cover four (4) protruding screw ends in angle plate to top corner to door

28 Garbage Room PE.18 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

29 Garbage Room PE.18 Intumescent strip to both door jamb is not complete at bases and to be replaced

30 Garbage Room PE.18 Fit proper extended lock to inner face

31 Garbage Room PE 18 Remove all protective covering that remains

AMERICA HOUSE

Ref. Location Defect

No.

34 Garbage Room PE.18 Install door stop to Door

Page 122: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 122/407

35 Garbage Room PE.18 Install door closer to Door

36 Garbage Room PE.18 Remove paint stains on door

37 Garbage Room PE.18 Make good to gap between mitred joint of frames at both heads

38 Garbage Room PE.18 Remove paint and rust on door frames

39 Garbage Room PE.18 Fire/Smoke seal threshold required to entry door

40 Garbage Room PE.18 Door signage

41 Garbage Room PE.18 Adjust door to prevent 'play' when closed

42 Garbage Room PE.18 Make good to wall where damaged by the fixing of the door intruder alarm contact

43 Garbage Room PE.18 Fire Fighting Equipment is missing

AMERICA HOUSE

Ref. Location Defect

No.

1 Storage Area PE.05 Make good uneven ceiling edge trim to suspended ceiling all round and remove curled edges

Page 123: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 123/407

2 Storage Area PE.05 Plastic skirting to be installed as missing completely

3 Storage Area PE.05 Clean wall stain and repaint on West Wall due to HVAC failure to RH of door

4 Storage Area PE.05 Make good wall to LH side of door on West Wall

5 Storage Area PE.05 Fixing screws to frame protrude and are to be refixed to door

6 Storage Area PE.05 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Storage Area PE.05 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

8 Storage Area PE.05 Intumescent strip to both door jamb is not complete at bases and to be replaced

9 Storage Area PE.05 Fit proper extended lock to inner face

10 Storage Area PE.05 Remove all protective covering that remains

11 Storage Area PE.05 Clean out at bases of frames at floor level and make good

12 Storage Area PE.05 Screw fixing missing to lock plate on door

13 Storage Area PE.05 Install door stop to Door

14 Storage Area PE.05 Install door closer to Door

15 Storage Area PE.05 Make good to gap between mitred joint of frames at both heads

16 Storage Area PE.05 Remove paint on door frames

17 Storage Area PE.05 Fire/Smoke seal threshold required to entry door18 Storage Area PE.05 Door signage

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor Area BC 16 (PW.04) Fixing screws to frame protrude and are to be refixed to door

Page 124: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 124/407

2 Corridor Area BC 16 (PW.04) Cover four (4) protruding screw ends in angle plate to top corner to door

3 Corridor Area BC 16 (PW.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

4 Corridor Area BC 16 (PW.04) Intumescent strip to both door jambs and head frame is not provided

5 Corridor Area BC 16 (PW.04) Strike plate is missing and requires to be replaced

6 Corridor Area BC 16 (PW.04) Remove all protective covering that remains

7 Corridor Area BC 16 (PW.04) Clean out at bases of frames at floor level and make good

8 Corridor Area BC 16 (PW.04) Screw fixing missing to lock plate on door

9 Corridor Area BC 16 (PW.04) Install door stop to Door

10 Corridor Area BC 16 (PW.04) Install door closer to Door

11 Corridor Area BC 16 (PW.04) Make good to gap between mitred joint of frames at both heads

12 Corridor Area BC 16 (PW.04) Remove paint on door frames

13 Corridor Area BC 16 (PW.04) Fire/Smoke seal threshold required to entry door

14 Corridor Area BC 16 (PW.04) Door signage

15 Corridor Area BC 16 (PW.04) Fixing screw in hinge frame is missing

16 Corridor Area BC 16 (PW.04) Adjust door as hinges are binding and door resists closure

17 Corridor Area BC 16 (PW.04) Adjust door as there is play in the leaf when the door is shut18 Corridor Area BC 16 (PW.04) Make good to concrete floor where it joins the tiles floor to Reception Area

19 Corridor Area BC 16 (PW.04) Skirting fixed with panel pins and to be fixed with adhesive or clip-o system

20 Corridor Area BC 16 (PW.04) Make good to bottom of lowest step and floor finish as there is a large gap

21 Corridor Area BC 16 (PW.04) Replace bottom step as chipped

22 Corridor Area BC 16 (PW.04) Make good joints at side to all steps

23 Corridor Area BC 16 (PW.04) Clean paint and dirt marks off all steps

24 Corridor Area BC 16 (PW.04) Repair tile capping on LH side going up as uneven

25 Corridor Area BC 16 (PW.04) Realign suspended ceiling light

26 Corridor Area BC 16 (PW.04) Clean ceiling light

27 Corridor Area BC 16 (PW.04) Reconnect open ended wire or remove at ceiling level

28 Corridor Area BC 16 (PW.04) Reconnect or remove black cable in ceiling space area

29 Corridor Area BC 16 (PW.04) Make good to cable with taped joint which is not acceptable and any proposed spicing is subject to Elec. Eng's approval

30 Corridor Area BC 16 (PW.04) Paint sprinkler installation

31 Corridor Area BC 16 (PW 04) South sprinkler head is fouled by duct and requires to be relocated

AMERICA HOUSE

Ref. Location Defect

No.

34 Corridor Area BC 16 (PW.04) Make good around large duct on South Wall and seal all round including gap to RH side at top corner

3 C id A BC 16 (PW 04) S l d b h d f E W ll i d k d

Page 125: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 125/407

35 Corridor Area BC 16 (PW.04) Seal around beam at north end of East Wall in top corner and make good

36 Corridor Area BC 16 (PW.04) Seal around cable tray near ceiling at North end of East Wall and make good

37 Corridor Area BC 16 (PW.04) Seal around smaller cable tray near ceiling at North end of East Wall and make good

38 Corridor Area BC 16 (PW.04) Seal around four (4) pipes near ceiling on East Wall and make good all round

39 Corridor Area BC 16 (PW.04) Seal around cable tray near ceiling at midway of East Wall and make good

40 Corridor Area BC 16 (PW.04) Seal around duct towards south end of East wall and make good

41 Corridor Area BC 16 (PW.04) Seal hole at South end of East Wall and make good

42 Corridor Area BC 16 (PW.04) Seal wall head along most of East wall to ceiling and make good

43 Corridor Area BC 16 (PW.04) Make good to gap between skirting and floor at upper level north end of East Wall

44 Corridor Area BC 16 (PW.04) Make good to poor jointing of skirting at base of steps on East Wall

45 Corridor Area BC 16 (PW.04) Refix all skirting that has been panel pinned and not installed with adhesive or clip-on system as specified

46 Corridor Area BC 16 (PW.04) Skirting missing to door return LH to PE.05

47 Corridor Area BC 16 (PW.04) Skirting missing to door return RH to PE.02

48 Corridor Area BC 16 (PW.04) Paint wall in south top corner of West Wall

49 Corridor Area BC 16 (PW.04) Seal around cable tray near ceiling at South end of West Wall and make good

50 Corridor Area BC 16 (PW.04) Seal around four (4) pipes near ceiling on West Wall and make good all round51 Corridor Area BC 16 (PW.04) Seal around beam at north end of West Wall in top corner and make good

52 Corridor Area BC 16 (PW.04) Seal wall head along most of West wall to ceiling and make good

53 Corridor Area BC 16 (PW.04) Skirting broken between door to Reception Lobby and steps and to be replaced

54 Corridor Area BC 16 (PW.04) Make good to poor jointing of skirting at base of steps on West Wall

55 Corridor Area BC 16 (PW.04) Skirting to West wall at top of steps has been done in bits and pieces and not acceptable and must be replaced

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C16 to 19 (PW.04) Refix skirting fixed with panel pins throughout with adhesive or clip-on system

2 C id C16 t 19 (PW 04) R l b k ki ti t t d f N th ll t t D ki B

Page 126: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 126/407

2 Corridor C16 to 19 (PW.04) Replace broken skirting at west end of North wall on return to Docking Bay

3 Corridor C16 to 19 (PW.04) Replace missing corner piece at west end of North Wall near Docking Bay

4 Corridor C16 to 19 (PW.04) Replace missing end to skirting at RH of Door to Generator Room PE.24

5 Corridor C16 to 19 (PW.04) Replace missing end to skirting at RH of Door to Main Electrical Switchroom PE.14

6 Corridor C16 to 19 (PW.04) Refix loose skirting at eastern end of North Wall

7 Corridor C16 to 19 (PW.04) Replace missing corner piece at west end of South near Docking Bay

8 Corridor C16 to 19 (PW.04) Tidy up skirting at LH of Column C16

9 Corridor C16 to 19 (PW.04) Skirting on South Wall between C16 and C17 is loose and to be refixed

10 Corridor C16 to 19 (PW.04) All f ive (5) suspended ceiling lights to be set level and in line

11 Corridor C16 to 19 (PW.04) Sprinkler installation is above major pipe runs and its effectiveness is very much reduced and to be relocated

12 Corridor C16 to 19 (PW.04) Seal around four (4) pipes at eastern end of South Wall C18/19 and make good

13 Corridor C16 to 19 (PW.04) Seal wall head at C18/19 on South Wall and make good to ceiling

14 Corridor C16 to 19 (PW.04) Tidy up loose wires in C18/19 South Wall in ceiling area

15 Corridor C16 to 19 (PW.04) Install operator signage to Fire Alarm Button at South wall C18

16 Corridor C16 to 19 (PW.04) Seal wall head along most of South wall to ceiling between C16/18 and make good

17 Corridor C16 to 19 (PW.04) Seal South wall above opening to stair corridor for eleven (11) conduits and one (1) pipe and make good all round18 Corridor C16 to 19 (PW.04) Seal South Wall around circular duct pipe and make good

19 Corridor C16 to 19 (PW.04) Seal South Wall around small cable tray and make good at western end

20 Corridor C16 to 19 (PW.04) Seal South Wall around cable tray and make good at western end

21 Corridor C16 to 19 (PW.04) Seal wall around large pipe at western end of South Wall and make good all round

22 Corridor C16 to 19 (PW.04) Remove wall paint on fan

23 Corridor C16 to 19 (PW.04) Realign grille plate to level

24 Corridor C16 to 19 (PW.04) Seal all round grille and make good

25 Corridor C16 to 19 (PW.04) Seal wall head where there is a substantial gap to the ceiling (MAJOR Fire Escape Corridor) and make good all round

26 Corridor C16 to 19 (PW.04) Remove paint on Running Man Sign on North Wall

27 Corridor C16 to 19 (PW.04) Install fixing screws to eleven (11) control boxes on North Wall

28 Corridor C16 to 19 (PW.04) Refix switch plate to RH of Door to Electrical Closet PW 25

29 Corridor C16 to 19 (PW.04) Seal opening at wall head on east side of corridor ingoing at C18 near open duct and make good all round

30 Corridor C16 to 19 (PW.04) Finish open duct at wall head on east side of corridor ingoing at C17

31 Corridor C16 to 19 (PW 04) Finish wall head to eastern wall at corridor ingoing at C18 and seal to ceiling

AMERICA HOUSE

Ref. Location Defect

No.

34 Corridor C16 to 19 (PW.04) Fixing screws to frame protrude and are to be refixed

35 Corridor C16 to 19 (PW 04) Cover four (4) protruding screw ends in angle plate to top corner to door

Page 127: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 127/407

35 Corridor C16 to 19 (PW.04) Cover four (4) protruding screw ends in angle plate to top corner to door

36 Corridor C16 to 19 (PW.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

37 Corridor C16 to 19 (PW.04) Intumescent strip to both door jambs is short at base and to be replaced

38 Corridor C16 to 19 (PW.04) Fit proper locking set on door

39 Corridor C16 to 19 (PW.04) Remove all protective covering that remains

40 Corridor C16 to 19 (PW.04) Tidy up wiring to upper contact for intruder alarm

41 Corridor C16 to 19 (PW.04) Screw fixing missing to lock plate on door

42 Corridor C16 to 19 (PW.04) Install door stop to Door

43 Corridor C16 to 19 (PW.04) Install door closer to Door

44 Corridor C16 to 19 (PW.04) Remove paint on door and make good

45 Corridor C16 to 19 (PW.04) Remove paint on door frames and make good

46 Corridor C16 to 19 (PW.04) Fire/Smoke seal threshold required to entry door

47 Corridor C16 to 19 (PW.04) Door signage

48 Corridor C16 to 19 (PW.04) Fix upper door contact for intruder alarm properly

49 Corridor C16 to 19 (PW.04) Realign door contacts for intruder alarm system

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C/D 18/19 (PW.04) Paint sprinkler Pipe installation throughout

2 Corridor C/D 18/19 (PW 04) Rehang light fitting as not level

Page 128: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 128/407

2 Corridor C/D 18/19 (PW.04) Rehang light fitting as not level

3 Corridor C/D 18/19 (PW.04) Sprinkler installation is placed right under duct and 150mm from west wall and not central for more effectiveness

4 Corridor C/D 18/19 (PW.04) Fire Escape External Door is lockable (locked at present) How do people escape !!!????

5 Corridor C/D 18/19 (PW.04) Install threshold plate and seal to External Door

6 Corridor C/D 18/19 (PW.04) Provide missing skirting to wall return to RH side of External Door

7 Corridor C/D 18/19 (PW.04) Provide missing skirting to wall return to LH side of External Door

8 Corridor C/D 18/19 (PW.04) Refix skirting fixed with panel pins with adhesive or clip-on system throughout

9 Corridor C/D 18/19 (PW.04) Redo contact wiring to External Door Intruder alarm which is poorly executed

10 Corridor C/D 18/19 (PW.04) Make good hole in floor to RH side of External door and repaint

11 Corridor C/D 18/19 (PW.04) Make good hole in floor to LH side of External door and repaint

12 Corridor C/D 18/19 (PW.04) Make good floor near External door which is very rough and unacceptable

13 Corridor C/D 18/19 (PW.04) Seal East wall at north end to Beam all round and make good near ceiling

14 Corridor C/D 18/19 (PW.04) Paint area of wall to North end of East Wall near ceiling

15 Corridor C/D 18/19 (PW.04) Reconnect or remove loose wire near duct at northern end of East Wall

16 Corridor C/D 18/19 (PW.04) Reconnect or remove loose green wire near duct at northern end of West Wall

17 Corridor C/D 18/19 (PW.04) Seal around conduit near ceiling at northern end of East Wall and make good18 Corridor C/D 18/19 (PW.04) Seal wall at southern end of East Wall including bulkhead formation to duct and make good to two hour fire rating

19 Corridor C/D 18/19 (PW.04) Seal East wall to conduit below duct at southern end of East Wall and make good

20 Corridor C/D 18/19 (PW.04) Seal East wall to pipe below duct at southern end of East Wall and make good

21 Corridor C/D 18/19 (PW.04) Remove paint from Running Man Sign

22 Corridor C/D 18/19 (PW.04) Reset twin power outlet in East wall that is squint

23 Corridor C/D 18/19 (PW.04) Seal West Wall at high level along the full length to obtain 2 hour fire rating including any required bulkhead and make good

24 Corridor C/D 18/19 (PW.04) Seal West wall at high level to beam at northern end and make good all round

25 Corridor C/D 18/19 (PW.04) Seal four (4) holes created for duct supports and make good all round on upper West wall

26 Corridor C/D 18/19 (PW.04) Install threshold plate to external door

27 Corridor C/D 18/19 (PW.04) Door open width is only 690mm which is not in accordance with the drawings or requirements 900mm

28

29

30

31

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor B/C 17/18 (PW.04) Reinstall skirting fixed with panel pins and refix with adhesive or clip-on system

2 Corridor B/C 17/18 (PW.04) Refix loose skirting properly to East Wall which has been screwed

Page 129: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 129/407

2 Corridor B/C 17/18 (PW.04) Refix loose skirting properly to East Wall which has been screwed

3 Corridor B/C 17/18 (PW.04) Reset twin power outlet in West wall that is squint

4 Corridor B/C 17/18 (PW.04) Make good to wall at floor level on East Wall at southern end

5 Corridor B/C 17/18 (PW.04) Realign ceiling light that is squint

6 Corridor B/C 17/18 (PW.04) Remove ceiling paint to ceiling light

7 Corridor B/C 17/18 (PW.04) Remove ceiling paint to two (2) sprinkler heads

8 Corridor B/C 17/18 (PW.04) Make good floor at Door to Stair Egress PE.06

9 Corridor B/C 17/18 (PW.04) Fixing screws to frame protrude and are to be refixed

10 Corridor B/C 17/18 (PW.04) Cover four (4) protruding screw ends in angle plate to top corner to door

11 Corridor B/C 17/18 (PW.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

12 Corridor B/C 17/18 (PW.04) Intumescent strip to both door jambs is short at base and to be replaced and also loose

13 Corridor B/C 17/18 (PW.04) Fit proper locking set on door

14 Corridor B/C 17/18 (PW.04) Remove all protective covering that remains

15 Corridor B/C 17/18 (PW.04) Make good tiled floor at RH door frame base

16 Corridor B/C 17/18 (PW.04) Make good tiled floor at LH door frame base

17 Corridor B/C 17/18 (PW.04) Screw fixing missing to lock plate on door18 Corridor B/C 17/18 (PW.04) Install door stop to Door

19 Corridor B/C 17/18 (PW.04) Install door closer to Door

20 Corridor B/C 17/18 (PW.04) Remove paint on door and make good

21 Corridor B/C 17/18 (PW.04) Remove paint on door frames and make good

22 Corridor B/C 17/18 (PW.04) Fire/Smoke seal threshold required to entry door

23 Corridor B/C 17/18 (PW.04) Door signage

24 Corridor B/C 17/18 (PW.04) Realign door contacts for intruder alarm system

25 Corridor B/C 17/18 (PW.04) Refix skirting to LH of door which is poorly fitted

26 Corridor B/C 17/18 (PW.04) Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box

27 Corridor B/C 17/18 (PW.04) Bed Glazing to Fire Hosereel box in neoprene gasket to prevent ratt le and worse

28 Corridor B/C 17/18 (PW.04) Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

29 Corridor B/C 17/18 (PW.04) Seal to head of door frame with blockwork and make good

30 Corridor B/C 17/18 (PW.04) Make good door cill inside FHE

31 Corridor B/C 17/18 (PW 04) Remove hardboard packer on LH side in frame area

AMERICA HOUSE

Ref. Location Defect

No.34 Corridor B/C 17/18 (PW.04) Make good to 'snowman' blockwork to RH side

35 Corridor B/C 17/18 (PW.04) Four divider wall in duct are missing on RH side of FHE and are to be installed

Page 130: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 130/407

36 Corridor B/C 17/18 (PW.04) Divider wall to LH side of FHE is not complete at the top and requires to be installed

37 Corridor B/C 17/18 (PW.04) Dry Riser outlet box to be formed in wall and make good all round

38 Corridor B/C 17/18 (PW.04) Provide Type C connection to Dry Riser

39 Corridor B/C 17/18 (PW.04) Relocate operating valve to lower hosereel to more accessible position

40 Corridor B/C 17/18 (PW.04) Seal holes to ceiling slab above and make good all round

41 Corridor B/C 17/18 (PW.04) Clean out builder's debris in FHE

42 Corridor B/C 17/18 (PW.04) Seal hole in floor slab for pipes (2 No) and make good

43 Corridor B/C 17/18 (PW.04) Make good to holes etc. below H Light on West Wall and repaint

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C 14/15 (PW.04) Reinstall skirting fixed with panel pins and refix with adhesive or clip-on system

2 Corridor C 14/15 (PW.04) Replace missing corner piece to skirting at corridor LH side to Stair PE.21

Page 131: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 131/407

3 Corridor C 14/15 (PW.04) Make good to poorly installed skirting at step base to North Wall

4 Corridor C 14/15 (PW.04) Make good to poorly installed skirting at step base to South Wall

5 Corridor C 14/15 (PW.04) Remove or fix loose large conduit or pipe on North Wall at ceiling level

6 Corridor C 14/15 (PW.04) Refix light (West) that is out of alignment and set level

7 Corridor C 14/15 (PW.04) Refix light (East) that is out of alignment and set level

8 Corridor C 14/15 (PW.04) Seal North wall along full length at ceiling level as corridor is a Major Fire Escape Route and make good including bulkhead

9 Corridor C 14/15 (PW.04) Seal North Wall at pipe (square hole) and make good all round, at upper level

10 Corridor C 14/15 (PW.04) Seal North Wall at cable tray and make good all round, at upper level

11 Corridor C 14/15 (PW.04) Seal North Wall at rectangular duct and make good all round

12 Corridor C 14/15 (PW.04) Seal North Wall to pipe on RH side of rectangular duct and make good

13 Corridor C 14/15 (PW.04) Seal North Wall to two (2) small pipes near ceiling and make good

14 Corridor C 14/15 (PW.04) Seal opening at eastern end of North Wall and make good all round near Docking Bay Area

15 Corridor C 14/15 (PW.04) Seal South Wall at SVP Pipe at eastern end and make good

16 Corridor C 14/15 (PW.04) Seal South Wall at four (4) conduits and one (1) small pipe at eastern end and make good

17 Corridor C 14/15 (PW.04) Seal South wall along full length at ceiling level as corridor is a Major Fire Escape Route and make good including bulkhead18 Corridor C 14/15 (PW.04) Seal South Wall at seven (7) conduits and one (1) small pipe above corridor to Stair PE21 and make good

19 Corridor C 14/15 (PW.04) Seal South wall to one (1) small pipe at eastern end and make good

20 Corridor C 14/15 (PW.04) Seal South Wall at three (3) conduits to RH of corridor to Stair PE21 and make good

21 Corridor C 14/15 (PW.04) Remove or reconnect loose open wire in ceiling area at western end of South Wall

22 Corridor C 14/15 (PW.04) Relocate sprinkler head fouled by many pipes etc in ceiling void area to restore effectiveness

23 Corridor C 14/15 (PW.04) Install operator signage to Fire Alarm Button at South wall C14/15

24 Corridor C 14/15 (PW.04) Clearance height is 2.00 metres to Corridor (Fire Escape Route) to PE.21 and requires to be adjusted

25 Corridor C 14/15 (PW.04) Seal West Wall to corridor which is a large void for 2 hour fire rating and make good all round

26 Corridor C 14/15 (PW.04) Replace four (4) chipped steps

27 Corridor C 14/15 (PW.04) Seal gap between bottom step and floor

28 Corridor C 14/15 (PW.04) Redo floor which is very rough at door to west wall and make good to finishes all round

29 Corridor C 14/15 (PW.04) Make good rough floor at top of steps and repaint

30 Corridor C 14/15 (PW.04) Make good wall finish to LH side of head frame to door where door intruder contact has been installed

31 Corridor C 14/15 (PW 04) Fixing screws to frame protrude and are to be refixed

AMERICA HOUSE

Ref. Location Defect

No.34 Corridor C 14/15 (PW.04) Intumescent strip to both door jambs is short at base and to be replaced and also loose

35 Corridor C 14/15 (PW.04) Fit proper locking set on door

36 C id C 14/15 (PW 04) R ll i i h i

Page 132: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 132/407

36 Corridor C 14/15 (PW.04) Remove all protective covering that remains

37 Corridor C 14/15 (PW.04) Screw fixing missing to lock plate on door

38 Corridor C 14/15 (PW.04) Install door stop to Door

39 Corridor C 14/15 (PW.04) Install door closer to Door

40 Corridor C 14/15 (PW.04) Remove paint on door and make good

41 Corridor C 14/15 (PW.04) Remove paint on door frames and make good

42 Corridor C 14/15 (PW.04) Fire/Smoke seal threshold required to entry door

43 Corridor C 14/15 (PW.04) Door signage

44 Corridor C 14/15 (PW.04) Realign door contacts for intruder alarm system

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor B/C 14/15 (PW.04) Provide skirting to steps

2 Corridor B/C 14/15 (PW.04) Reinstall skirting fixed with panel pins and refix with adhesive or clip-on system

Page 133: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 133/407

3 Corridor B/C 14/15 (PW.04) Remove paint on duct at top of stairs on LH side

4 Corridor B/C 14/15 (PW.04) Clean paint marks etc on steps throughout

5 Corridor B/C 14/15 (PW.04) Remove paint to two (2) sprinkler heads in ceiling

6 Corridor B/C 14/15 (PW.04) Remove paint on light fitting

7 Corridor B/C 14/15 (PW.04) Make good to gap between stair bottom step and floor

8 Corridor B/C 14/15 (PW.04) Reset Running Man sign level on wall

9 Corridor B/C 14/15 (PW.04) Remove wall paint on Running Man sign

10 Corridor B/C 14/15 (PW.04) Remove wall paint on H sign

11 Corridor B/C 14/15 (PW.04) Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box

12 Corridor B/C 14/15 (PW.04) Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

13 Corridor B/C 14/15 (PW.04) Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

14 Corridor B/C 14/15 (PW.04) Seal to head of door frame with blockwork and make good

15 Corridor B/C 14/15 (PW.04) Make good door cill inside FHE

16 Corridor B/C 14/15 (PW.04) Renew lock to FHE Door panel

17 Corridor B/C 14/15 (PW.04) Remove paint on FHE frames all round and make good18 Corridor B/C 14/15 (PW.04) Remove paint on glass panel to FHE Door

19 Corridor B/C 14/15 (PW.04) Wall to LH side of enclosure is missing and to be installed

20 Corridor B/C 14/15 (PW.04) Wall to RH side of enclosure is missing and to be installed

21 Corridor B/C 14/15 (PW.04) Ventilation duct in FHE enclosure requires to be enclosed in fire rated plasterboard etc. and made good

22 Corridor B/C 14/15 (PW.04) Dry Riser outlet box to be formed in wall and make good all round

23 Corridor B/C 14/15 (PW.04) Provide Type C connection to Dry Riser

24 Corridor B/C 14/15 (PW.04) Upper Fire hosereel needs to be relocated as fouls door

25 Corridor B/C 14/15 (PW.04) Lower Fire hosereel needs to be relocated as fouls door

26 Corridor B/C 14/15 (PW.04) Clean out builder's debris in FHE

27 Corridor B/C 14/15 (PW.04) Seal hole in floor slab for pipes (2 No) and make good

28 Corridor B/C 14/15 (PW.04) Make good blockwork to head of FHE Box

29 Corridor B/C 14/15 (PW.04) Seal ceiling slab for two(2) pipes and make good

AMERICA HOUSE

Ref. Location Defect

No.1 Corridor PE.08 Reinstall skirting fixed with panel pins and refix with adhesive or clip-on system

2 Corridor PE.08 Make good to wall above skirting with wall paint East Wall

3 C id PE 08 M k d t ll b ki ti ith ll i t W t W ll

Page 134: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 134/407

3 Corridor PE.08 Make good to wall above skirting with wall paint West Wall

4 Corridor PE.08 Make good to wall above skirting with wall paint South Wall

5 Corridor PE.08 Make good to wall above skirting with wall paint North Wall

6 Corridor PE.08 No sprinkler installation provided

7 Corridor PE.08 Remove paint on light fitting

8 Corridor PE.08 Fixing screws to frame protrude and are to be refixed

9 Corridor PE.08 Cover four (4) protruding screw ends in angle plate to top corner to door

10 Corridor PE.08 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

11 Corridor PE.08 Intumescent strip to both door and head jambs is missing

12 Corridor PE.08 Make good at frame bases at floor level

13 Corridor PE.08 Remove all protective covering that remains

14 Corridor PE.08 Screw fixing missing to lock plate on door

15 Corridor PE.08 Install door stop to Door

16 Corridor PE.08 Install door closer to Door

17 Corridor PE.08 Remove paint on door frames and make good

18 Corridor PE.08 Fire/Smoke seal threshold required to entry door

19 Corridor PE.08 Door signage

20 Corridor PE.08 Realign door contacts for intruder alarm system

21 Corridor PE.08 Redo skirting on South Wall as workmanship is very poor

22 Corridor PE.08 Remove paint on frames to South Door and make good

23 Corridor PE.08 Remove paint on door frames and make good to South Door

24 Corridor PE.08 Fire/Smoke seal threshold required to entry door South

25

AMERICA HOUSE

Ref. Location Defect

No.1 Egress Stair PE.22 Lower  Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair PE.22 Lower Clean light fitting of paint stains etc.

3 Egress Stair PE 22 Lower Seal wall with sloping camb ceiling LH side

Page 135: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 135/407

3 Egress Stair PE.22 Lower Seal wall with sloping camb ceiling LH side

4 Egress Stair PE.22 Lower Reset Running Man Sign level

5 Egress Stair PE.22 Lower Remove masking tape and paint on Running Man Sign

6 Egress Stair PE.22 Lower Tiled Ground floor uneven and dirty and to be reset, polished and sealed

7 Egress Stair PE.22 Lower Seal South wall above door entry to ceiling and make good

8 Egress Stair PE.22 Lower Seal and make good 'patchwork' plasterboard at grille above entry door and repaint all round

9 Egress Stair PE.22 Lower Fixing screws to frame protrude and are to be refixed

10 Egress Stair PE.22 Lower Cover four (4) protruding screw ends in angle plate to top corner to door

11 Egress Stair PE.22 Lower Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

12 Egress Stair PE.22 Lower Intumescent strip to both door jambs is short and to be replaced

13 Egress Stair PE.22 Lower Make good at frame bases at floor level

14 Egress Stair PE.22 Lower Remove all protective covering that remains

15 Egress Stair PE.22 Lower Screw fixing missing to lock plate on door

16 Egress Stair PE.22 Lower Install door stop to Door

17 Egress Stair PE.22 Lower Install door closer to Door

18 Egress Stair PE.22 Lower Remove paint on door frames and make good

19 Egress Stair PE.22 Lower Fire/Smoke seal threshold required to entry door

20 Egress Stair PE.22 Lower Door signage

21 Egress Stair PE.22 Lower Replace lock set that is short in escutcheon of door

22 Egress Stair PE.22 Lower Remove manufacturer's labels and make good

AMERICA HOUSE

Ref. Location Defect

No.1 Egress Stair Upper (PE.22) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Upper (PE.22) Clean light fitting of paint stains etc.

3 Egress Stair Upper (PE 22) Make good to skirting that is showing signs of distress on West Wall

Page 136: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 136/407

3 Egress Stair Upper (PE.22) Make good to skirting that is showing signs of distress on West Wall

4 Egress Stair Upper (PE.22) Reset Running Man Sign level

5 Egress Stair Upper (PE.22) Remove masking tape and paint on Running Man Sign

6 Egress Stair Upper (PE.22) Tiled floor (Ground Level) is uneven and dirty and to be reset, polished and sealed

7 Egress Stair Upper (PE.22) Seal East wall above door entry to ceiling and make good

8 Egress Stair Upper (PE.22) Remove paint stains etc to stair to Level 1

9 Egress Stair Upper (PE.22) Fixing screws to frame protrude and are to be refixed

10 Egress Stair Upper (PE.22) Cover four (4) protruding screw ends in angle plate to top corner to door

11 Egress Stair Upper (PE.22) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

12 Egress Stair Upper (PE.22) Intumescent strip to open door jamb is short and loose and to be replaced

13 Egress Stair Upper (PE.22) Intumescent strip to hinge door jamb is missing and to be replaced

14 Egress Stair Upper (PE.22) Remove all protective covering that remains

15 Egress Stair Upper (PE.22) Screw fixing missing to lock plate on door

16 Egress Stair Upper (PE.22) Install door stop to Door

17 Egress Stair Upper (PE.22) Install door closer to Door18 Egress Stair Upper (PE.22) Remove paint on door frames and make good

19 Egress Stair Upper (PE.22) Fire/Smoke seal threshold required to entry door

20 Egress Stair Upper (PE.22) Door signage

21 Egress Stair Upper (PE.22) Replace lock set that is short in escutcheon of door

22 Egress Stair Upper (PE.22) Adjust door and eliminate 'play'

23 Egress Stair Upper (PE.22) Reset Loudspeaker on wall which is squint

24 Egress Stair Upper (PE.22) Make good to 600 x 500mm hole above entry door and seal all round and repaint

25 Egress Stair Upper (PE.22) Make good hole under wall light fitting and repaint

26 Egress Stair Upper (PE.22) Remove wall paint on pressurization system grille

27 Egress Stair Upper (PE.22) Clean at bases of door frames and make good to finishes

28 Egress Stair Upper (PE.22) Door strike plate is missing and to be replaced

29 Egress Stair Upper (PE.22) Remove plaster to skirting and steps

30 Egress Stair Upper (PE.22) Replace broken mid landing wall light

31 Egress Stair Upper (PE 22) Make good end of divider wall at mid-landing and repaint

AMERICA HOUSE

Ref. Location Defect

No.

34 Egress Stair Upper (PE.22) Tiling floor to mid landing is uneven and dirty and to be relaid, polished and sealed

35 Egress Stair Upper (PE.22) Make good to upper part of divider wall to upper stair flight and repaint

36 Egress Stair Upper (PE.22) Make good skirting to RH side of Door at Ground Floor

Page 137: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 137/407

37 Egress Stair Upper (PE.22) Make good skirting to LH side of Door at Ground Floor

AMERICA HOUSE

Ref. Location Defect

No.1 Service Elevator Vestib. PE.23 Prepare for and paint ceiling

2 Service Elevator Vestib. PE.23 Paint sprinkler pipe

3 Service Elevator Vestib. PE.23 Door frame at bases is 5mm above floor finish and requires to be adjusted

Page 138: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 138/407

3 Service Elevator Vestib. PE.23 Door frame at bases is 5mm above floor finish and requires to be adjusted

4 Service Elevator Vestib. PE.23 Fill in hole to door head frame

5 Service Elevator Vestib. PE.23 Adjust inner leaf of door as it is still loose when closed

6 Service Elevator Vestib. PE.23 Fixing screws to frame protrude and are to be ref ixed to Door

7 Service Elevator Vestib. PE.23 Cover four (4) protruding screw ends in angle plate to top corner to Door

8 Service Elevator Vestib. PE.23 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestib. PE.23 Intumescent strip is short on both side frames and requires to be replaced

10 Service Elevator Vestib. PE.23 Install door stops to Doors

11 Service Elevator Vestib. PE.23 Clean paint off Door Frames

12 Service Elevator Vestib. PE.23 Door Signage

13 Service Elevator Vestib. PE.23 Fire/Smoke Threshold seal is required to door North

14 Service Elevator Vestib. PE.23 Install closers with selector on doors

15 Service Elevator Vestib. PE.23 Remove all remaining parts of the protective covering to doors

16 Service Elevator Vestib. PE.23 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

17 Service Elevator Vestib. PE.23 Skirting broken at LH side of door return to corridor

18 Service Elevator Vestib. PE.23 Skirting loose at RH side of door return to corridor

19 Service Elevator Vestib. PE.23 Skirting corner piece missing on RH side of return to corridor

20 Service Elevator Vestib. PE.23 Make god to damage arris on LH side of door returns to corridor

21 Service Elevator Vestib. PE.23 Skirting missing at wall returns to lift door

22 Service Elevator Vestib. PE.23 Seal and make good to three conduits at North Wall near ceiling

23 Service Elevator Vestib. PE.23 Seal and make good to sprinkler pipe at North Wall above door

24 Service Elevator Vestib. PE.23 Seal and make good to one (1) conduit on South Wall near ceiling

25 Service Elevator Vestib. PE.23 Seal and make good to hole in wall plasterboard lining on South Wall RH side of lift door

AMERICA HOUSE

Ref. Location Defect

No.1 Egress Stair PE 07 (Upper) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair PE 07 (Upper) Clean light fitting of paint stains etc.

3 Egress Stair PE 07 (Upper) Remove paint on Fire Key Box and make good

Page 139: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 139/407

g ( pp ) p y g

4 Egress Stair PE 07 (Upper) Remove paint on Wall Light in Lower landing

5 Egress Stair PE 07 (Upper) Remove paint on Running Man Sign and make good

6 Egress Stair PE 07 (Upper) Tiled floor (Ground Level) is uneven and dirty and to be reset, polished and sealed

7 Egress Stair PE 07 (Upper) Seal East wall above door entry to ceiling and make good

8 Egress Stair PE 07 (Upper) Remove paint stains etc to stair to Level 1

9 Egress Stair PE 07 (Upper) Make good joint to ceiling above door at Eastern Wall and repaint

10 Egress Stair PE 07 (Upper) Make good to distressed tile skirting to RH side of entry Door from Corridor PE.06

11 Egress Stair PE 07 (Upper) Make good to distressed tile skirting to South Wall

12 Egress Stair PE 07 (Upper) Remove builder's marks for handrail etc on lower flight steps and make good

13 Egress Stair PE 07 (Upper) Clean paint marks etc on both stair flights

14 Egress Stair PE 07 (Upper) Remove paint to skirting on stair flights to Level 1

15 Egress Stair PE 07 (Upper) Replace five (5) chipped steps on stair flights to Level 1

16 Egress Stair PE 07 (Upper) Replace broken mid landing wall light

17 Egress Stair PE 07 (Upper) Remove plaster to skirting and steps

18 Egress Stair PE 07 (Upper) Redo skirting to steps as workmanship is poor

19 Egress Stair PE 07 (Upper) Tiling floor to mid landing is uneven and dirty and to be relaid, polished and sealed

20 Egress Stair PE 07 (Upper) Make good to chipped edges to divider wall at mid landing and up to level 1 and repaint

AMERICA HOUSE

Ref. Location Defect

No.1 Egress Stair Lower (PE.07) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Lower (PE.07) Clean light fitting of paint stains etc.

3 Egress Stair Lower (PE.07) Seal wall with sloping camb ceiling LH side

Page 140: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 140/407

4 Egress Stair Lower (PE.07) Reset Running Man Sign level

5 Egress Stair Lower (PE.07) Remove masking tape and paint on Running Man Sign

6 Egress Stair Lower (PE.07) Tiled Ground floor uneven and dirty and to be reset, polished and sealed

7 Egress Stair Lower (PE.07) Fixing screws to frame protrude and are to be refixed

8 Egress Stair Lower (PE.07) Cover four (4) protruding screw ends in angle plate to top corner to door

9 Egress Stair Lower (PE.07) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

10 Egress Stair Lower (PE.07) Intumescent strip to both door jambs is short and to be replaced

11 Egress Stair Lower (PE.07) Seal joint between door frame and wall finishes

12 Egress Stair Lower (PE.07) Remove all protective covering that remains

13 Egress Stair Lower (PE.07) Screw fixing missing to lock plate on door

14 Egress Stair Lower (PE.07) Install door stop to Door

15 Egress Stair Lower (PE.07) Install door closer to Door

16 Egress Stair Lower (PE.07) Remove paint on door frames and make good

17 Egress Stair Lower (PE.07) Fire/Smoke seal threshold required to entry door

18 Egress Stair Lower (PE.07) Door signage

19 Egress Stair Lower (PE.07) Replace lock set that is short in escutcheon of door

20 Egress Stair Lower (PE.07) Adjust door as it does not close properly

21 Egress Stair Lower (PE.07) Make good around Fire Damper grille and seal at upper level

22 Egress Stair Lower (PE.07) Provide proper locking device to Fire Damper Grille at upper level

23 Egress Stair Lower (PE.07) Remove paint to Fire Damper Grille at upper level

24 Egress Stair Lower (PE.07) Seal and make good to rectangular hole at high level on East Wall and repaint

25 Egress Stair Lower (PE.07) Make good to defective skirting on eastern wall (Ground)

26 Egress Stair Lower (PE.07) Make good cracked/distressed wall joint at southeast corner for lower part of wall and repaint27 Egress Stair Lower (PE.07) Skirting to RH of Door is missing and to be replaced

28 Egress Stair Lower (PE.07) Skirting to LH of door is of poor workmanship and to be redone

29

30

31

AMERICA HOUSE

Ref. Location Defect

No.1 Retail Area PE.09 (Mobex) Seal West Wall at south end at high level for two (2) pipes and make good

2 Retail Area PE.09 (Mobex) Seal West Wall at south end at high level for one (1) pipes and make good

3 Retail Area PE.09 (Mobex) Reconnect or remove two loose unconnected cables on West Wall (South)

Page 141: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 141/407

4 Retail Area PE.09 (Mobex) Seal and make good to duct opening on West wall

5 Retail Area PE.09 (Mobex) Seal to cable tray opening on West wall at high level and make good all round

6 Retail Area PE.09 (Mobex) Reconnect or remove one loose unconnected cable on West Wall (South) near circular duct

7 Retail Area PE.09 (Mobex) Seal rectangular opening on West Wall (South) and make good all round

8 Retail Area PE.09 (Mobex) Seal West Wall at near return end at high level for one (1) pipes and make good

9 Retail Area PE.09 (Mobex) Seal and make good on return wall drainage pipe that is half buried in wall

10 Retail Area PE.09 (Mobex) Seal and make good to rectangular duct opening to West Wall (North) LH

11 Retail Area PE.09 (Mobex) Seal and make good to one (1) pipe near ceiling on West Wall (North)

12 Retail Area PE.09 (Mobex) Seal and Make good to rectangular duct opening to West Wall (North) RH

13 Retail Area PE.09 (Mobex) Seal and make good to rectangular duct on West Wall (North) at the right end above door

14 Retail Area PE.09 (Mobex) Seal and make good the length of West Wall at ceiling

15 Retail Area PE.09 (Mobex) Remove timber formwork to door step

16 Retail Area PE.09 (Mobex) Seal and make good to upper part of West Wall CD 19 to ceiling including missing wall infill

17 Retail Area PE.09 (Mobex) Install threshold plate to Double Entrance door on East Façade

18 Retail Area PE.09 (Mobex) Seal and make good to LH of North Wall at ceiling level rectangular opening

19 Retail Area PE.09 (Mobex) Seal and make good to three (3) rectangular openings for ducts all around

20 Retail Area PE.09 (Mobex) Seal and make good at ceiling level on North Wall around beam

21 Retail Area PE.09 (Mobex) Seal and make good to upper part of North Wall D 18/20 to ceiling including missing wall infill

22 Retail Area PE.09 (Mobex) Sprinkler pipe to eastern side of Retail Area is inadequately supported and needs more holders

23 Retail Area PE.09 (Mobex) Install threshold plate to Double Entrance door on South Façade

24 Retail Area PE.09 (Mobex) Make good rubber seals to door where under distress at meeting style

25 Retail Area PE.09 (Mobex) Adjust doors so that they are level at the head frames of doors

26 Retail Area PE.09 (Mobex) Fire dampers to Duct 1 on West Wall27 Retail Area PE.09 (Mobex) Fire dampers to Duct 2 on West Wall

28 Retail Area PE.09 (Mobex) Fire dampers to Duct 3 on West Wall

29 Retail Area PE.09 (Mobex) Fire dampers to Duct 4 on West Wall

30 Retail Area PE.09 (Mobex) Seal West Wall above door around beam and make good

31 Retail Area PE 09 (Mobex) Seal and make good around cable tray at north return wall near door

AMERICA HOUSE

Ref. Location Defect

No.1 Retail Space PE.20 (Cosmote) Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box

2 Retail Space PE.20 (Cosmote) Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

3 Retail Space PE.20 (Cosmote) Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

Page 142: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 142/407

4 Retail Space PE.20 (Cosmote) Seal to head of door frame with blockwork and make good

5 Retail Space PE.20 (Cosmote) Make good door cill inside FHE

6 Retail Space PE.20 (Cosmote) Divider wall RH is not completed in FHE Enclosure

7 Retail Space PE.20 (Cosmote) Divider wall LH is not completed in FHE Enclosure

8 Retail Space PE.20 (Cosmote) Remove heavy electrical cable in FHE

9 Retail Space PE.20 (Cosmote) Clean out builder's debris in FHE

10 Retail Space PE.20 (Cosmote) Seal hole in floor slab for pipes (2 No) and make good

11 Retail Space PE.20 (Cosmote) Make good blockwork to head of FHE Box

12 Retail Space PE.20 (Cosmote) Seal ceiling slab for two(2) pipes and make good

13 Retail Space PE.20 (Cosmote) Seal east wall at large pipe and make good all round near ceiling

14 Retail Space PE.20 (Cosmote) Seal opening with cable tray and four (4) pipes and make good on East wall

15 Retail Space PE.20 (Cosmote) Seal on West Wall for small pipe at south end and make good all round

16 Retail Space PE.20 (Cosmote) Seal on West Wall for small cable tray near ceiling at south end and make good all round

17 Retail Space PE.20 (Cosmote) Seal on West Wall for duct pipe and make good all round

18 Retail Space PE.20 (Cosmote) Seal on West wall near ceiling for two conduits and make good all round

19 Retail Space PE.20 (Cosmote) Seal for small sprinkler pipe on West Wall and make good

20 Retail Space PE.20 (Cosmote) Seal for SVP pipe in West Wall and make good

21 Retail Space PE.20 (Cosmote) Seal for two (2) conduits toward the northern end of West wall and make good

22 Retail Space PE.20 (Cosmote) Seal up large opening on north wall to RH of Column D14 and make good all round

23 Retail Space PE.20 (Cosmote) Install threshold plate to Shopfront entrance door

24 Retail Space PE.20 (Cosmote) Tidy up wiring to door intruder contacts

25 Retail Space PE.20 (Cosmote) Door closers with selector required

26 Retail Space PE.20 (Cosmote) Drop bolt keepers to lower end of door not there27 Retail Space PE.20 (Cosmote) Sprinkler pipe in area needs a general touching up to prevent further rusting etc.

AMERICA HOUSE

Ref. Location Defect

No.1 Retail Space PE.20 (Cocoon) Install threshold plate to Shopfront entrance door

2 Retail Space PE.20 (Cocoon) Seal West Wall (South) for pipe at high level and make good

3 Retail Space PE.20 (Cocoon) Seal wall head to West wall AB 15 and make good

S (C ) S

Page 143: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 143/407

4 Retail Space PE.20 (Cocoon) Seal wall missing at wall head on return wall to West B15 and make good all round

5 Retail Space PE.20 (Cocoon) Seal hole in West Wall (South) around four (4) pipes and cable tray and make good

6 Retail Space PE.20 (Cocoon) Seal hole to pipe at high level RH side of West Wall (South) and make good

7 Retail Space PE.20 (Cocoon) Install operator signage to Fire Alarm Button at West return wall

8 Retail Space PE.20 (Cocoon) Seal wall missing at wall head on West Wall (North) BC 15 and make good all round

9 Retail Space PE.20 (Cocoon) Seal wall to pipe at RH end of West Wall (North) and make good

10 Retail Space PE.20 (Cocoon) Seal wall missing at wall head of North Wall C 15/16 and make good to six (6) pipes, cable tray and beam

11 Retail Space PE.20 (Cocoon) Fill in missing blockwork to North Wall RH at top

12 Retail Space PE.20 (Cocoon) Seal East Wall (North) around four (4) pipes and make good

13 Retail Space PE.20 (Cocoon) Seal East Wall (North) around cable tray and make good

14 Retail Space PE.20 (Cocoon) Seal East Wall (Mid) around one (1) pipe and make good

15 Retail Space PE.20 (Cocoon) Seal East Wall to irregular hole with four (4) pipes and cable tray and make good all round

16 Retail Space PE.20 (Cocoon) Seal East Wall (South) to two (2) pipes at high level and make good all round

AMERICA HOUSE

Ref. Location Defect

No.

1 Retail Space PE.20 (Musette) Install threshold plate to Shopfront entrance door

2 Retail Space PE.20 (Musette) Seal West Wall for pipe at high level RH side and make good

3 Retail Space PE.20 (Musette) Seal West Wall around hole for four (4) pipes and make good all round

4 Retail Space PE 20 (Musette) Seal wall head to West Wall and make good

Page 144: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 144/407

4 Retail Space PE.20 (Musette) Seal wall head to West Wall and make good

5 Retail Space PE.20 (Musette) Seal East Wall around large opening for four (4) pipes and cable tray and make good all round

6 Retail Space PE.20 (Musette) Seal North Wall along complete length at top where unfinished and make good all round including duct

7 Retail Space PE.20 (Musette) Fire Damper required on duct

8 Retail Space PE.20 (Musette) Seal wall head to East Wall and make good

AMERICA HOUSE

Ref. Location Defect

No.1 Egress Stair E1E.13 Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair E1E.13 Clean light fitting of paint stains etc.

3 Egress Stair E1E.13 Reset Light fitting as not level

4 Egress Stair E1E 13 Reset Running Man Sign level as not level

Page 145: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 145/407

4 Egress Stair E1E.13 Reset Running Man Sign level as not level

5 Egress Stair E1E.13 Replace five (5) chipped steps to Level 2

6 Egress Stair E1E.13 Tiled First floor uneven and dirty and to be reset, polished and sealed

7 Egress Stair E1E.13 Fixing screws to frame protrude and are to be refixed

8 Egress Stair E1E.13 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Egress Stair E1E.13 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

10 Egress Stair E1E.13 Intumescent strip to both door jambs is short and to be replaced

11 Egress Stair E1E.13 Refix head rubber filling to door head which is loose

12 Egress Stair E1E.13 Remove all protective covering that remains

13 Egress Stair E1E.13 Two (2) screws fixing missing to lock plate on door

14 Egress Stair E1E.13 Install door stop to Door

15 Egress Stair E1E.13 Door is binding on hinges and is difficult to close and will not fully close on closer

16 Egress Stair E1E.13 Remove paint on door frames and make good

17 Egress Stair E1E.13 Fire/Smoke seal threshold required to entry door

18 Egress Stair E1E.13 Door signage

19 Egress Stair E1E.13 Door intruder alarm contacts to be realigned

20 Egress Stair E1E.13 Remove paint on access card reader and make good

21 Egress Stair E1E.13 Remove paint stains etc on both flights of stairs between Levels 1 and 2 and make good

22 Egress Stair E1E.13 Seal off end of tubular hand rail at bottom Level 1

23 Egress Stair E1E.13 Make good to door arris to RH side of door

24 Egress Stair E1E.13 Mid landing : replace L shaped tile at handrail and make good

25 Egress Stair E1E.13 Mid landing tiles are uneven at bottom of upper flight including 'bossed' tiles

26 Egress Stair E1E.13 Stair Handrail is not stable between Levels 1 and 2 and requires to be reset27 Egress Stair E1E.13 Clean light fitting of paint stains etc. at mid landing

28 Egress Stair E1E.13 Reset Light fitting as not level at mid landing

29 Egress Stair E1E.13 Replace cracked terrazzo floor tile near door

AMERICA HOUSE

Ref. Location Defect

No.1 Stair Vestibule E1E.12 Remove paint to South Door Frames

2 Stair Vestibule E1E.12 Fit rubber seal all round door

3 Stair Vestibule E1E.12 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule E1E 12 Fixing screws to frame protrude and are to be refixed to Door South

Page 146: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 146/407

4 Stair Vestibule E1E.12 Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule E1E.12 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule E1E.12 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

7 Stair Vestibule E1E.12 Install door stop to Door South

8 Stair Vestibule E1E.12 Clean out at bases of door frames and make good

9 Stair Vestibule E1E.12 Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule E1E.12 Screw missing in lock plate to door South

11 Stair Vestibule E1E.12 Make good to arris on RH side of door to stair and repaint

12 Stair Vestibule E1E.12 Tile floor is uneven and needs to be levelled, polished and resealed

13 Stair Vestibule E1E.12 Remove paint on Blue Door Push button and make good

14 Stair Vestibule E1E.12 Provide operation label to Door Push Button in Romanian and English

15 Stair Vestibule E1E.12 Remove paint on Running Man sign and make good

16 Stair Vestibule E1E.12 Remove paint from top edge of skirting on all walls

17 Stair Vestibule E1E.12 Make good to wall paint just above skirting where stained by tiler's bad workmanship

18 Stair Vestibule E1E.12 Provide rubber seal all round to door

19 Stair Vestibule E1E.12 Make good round Fire Damper Grille panel (Lower)

20 Stair Vestibule E1E.12 Make good round Fire Damper Grille panel (Upper)

21 Stair Vestibule E1E.12 Provide proper locking device to Lower Fire Damper Grille

22 Stair Vestibule E1E.12 Provide proper locking device to Upper Fire Damper Grille

23 Stair Vestibule E1E.12 Clean paint off grille to Fire Damper panel (Lower)

24 Stair Vestibule E1E.12 Clean paint off grille to Fire Damper panel (Upper)

25 Stair Vestibule E1E.12 Screw missing in lock plate to door North

26 Stair Vestibule E1E.12 Clean paint off door frame to Door North27 Stair Vestibule E1E.12 Replace prong point keeper that has been damaged

28 Stair Vestibule E1E.12 Intumescent strip is not complete to both frame bases of Door North

29 Stair Vestibule E1E.12 Fixing screws to frame protrude and are to be refixed to Door North

30 Stair Vestibule E1E.12 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Stair Vestibule E1E 12 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule E1E.12 Remove paint to three (3) sprinkler head in ceiling

35 Stair Vestibule E1E.12 Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box

36 Stair Vestibule E1E.12 Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

37 Stair Vestibule E1E.12 Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

Page 147: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 147/407

37 Stair Vestibule E1E.12 Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

38 Stair Vestibule E1E.12 Build up blockwork below threshold and seal to door

39 Stair Vestibule E1E.12 Seal to head of door frame with blockwork (loose block ready to fall) and make good

40 Stair Vestibule E1E.12 Divider Wall to LH to be sealed full length to back wall

41 Stair Vestibule E1E.12 Divider Wall to LH to be completed in upper part of FH enclosure (1.35 linear metres missing)

42 Stair Vestibule E1E.12 Divider Wall to RH to be completed in upper part of FH enclosure

43 Stair Vestibule E1E.12 Divider wall to RH to be sealed to front and back wall where unsealed

44 Stair Vestibule E1E.12 Seal and make good to floor slab for supply pipe

45 Stair Vestibule E1E.12 Seal two holes in floor slab within FHE and make good

46 Stair Vestibule E1E.12 Seal two holes in ceiling slab within FHE and make good

47 Stair Vestibule E1E.12 Seal blockwork around opening panel to Dry Riser Outlet and make good

48 Stair Vestibule E1E.12 Remove timber inside Dry Riser Enclosure

49 Stair Vestibule E1E.12 Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

50 Stair Vestibule E1E.12 Divider wall on LH side of Dry Riser Enclosure is missing

51 Stair Vestibule E1E.12 Replace missing skirting to RH of North door

52 Stair Vestibule E1E.12 Make good to floor covering at North Door which is very untidy

53 Stair Vestibule E1E.12 Make good to skirting to RH of Door South

54 Stair Vestibule E1E.12 Make good to skirting to LH of Door South

55 Stair Vestibule E1E.12 Fire/Smoke Threshold seal is required to door North

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair E1E.08 Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair E1E.08 Clean light fitting of paint stains etc.

3 Egress Stair E1E.08 Reset Light fitting as not level

4 Egress Stair E1E.08 Skirting at lower stair divide wall is of poor workmanship and requires to be redone

Page 148: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 148/407

g g p p q

5 Egress Stair E1E.08 Replace two (2) chipped steps to Level 2

6 Egress Stair E1E.08 Tiled First floor requires to be polished and sealed and repaired where poor workmanship near divide wall to stair

7 Egress Stair E1E.08 Fixing screws to frame protrude and are to be refixed

8 Egress Stair E1E.08 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Egress Stair E1E.08 Intumescent str ip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

10 Egress Stair E1E.08 Intumescent strip to open door jamb is short and to be replaced

11 Egress Stair E1E.08 Intumescent strip to hinge door jamb is short and missing at upper part and to be replaced

12 Egress Stair E1E.08 Strike plate insert damaged and require to be replaced

13 Egress Stair E1E.08 Install door stop to Door

14 Egress Stair E1E.08 Door is binding on hinges and squeaks and requires adjustment as door does not close properly

15 Egress Stair E1E.08 Remove paint on door frames and make good

16 Egress Stair E1E.08 Fire/Smoke seal threshold required to entry door

17 Egress Stair E1E.08 Door signage

18 Egress Stair E1E.08 Door intruder alarm contacts to be realigned

19 Egress Stair E1E.08 Make good between door frame and plaster jambs to door sides

20 Egress Stair E1E.08 Remove paint stains etc on both flights of stairs between Levels 1 and 2 and make good

21 Egress Stair E1E.08 Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

22 Egress Stair E1E.08 Clean light fitting of paint stains etc. at mid landing

23 Egress Stair E1E.08 Reset Light fitting as not level at mid landing

24 Egress Stair E1E.08 Repair tile skirting to LH side of door

25 Egress Stair E1E.08 Make good damage to lower divider wall to stair

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule E1E 07 Remove paint to South Door Frames

2 Stair Vestibule E1E 07 Fit rubber seal all round door South

3 Stair Vestibule E1E 07 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule E1E 07 Fixing screws to frame protrude and are to be refixed to Door South

Page 149: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 149/407

g p

5 Stair Vestibule E1E 07 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule E1E 07 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

7 Stair Vestibule E1E 07 Install door stop to Door South

8 Stair Vestibule E1E 07 Remove remaining protective covering to Door South

9 Stair Vestibule E1E 07 Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule E1E 07 Screw missing in lock plate to door South

11 Stair Vestibule E1E 07 Clean two (2) light fittings

12 Stair Vestibule E1E 07 Tile floor is uneven and needs to be levelled, polished and resealed

13 Stair Vestibule E1E 07 Reset sprinkler head in ceiling that is protruding

14 Stair Vestibule E1E 07 Provide operation label to Door Push Button in Romanian and English

15 Stair Vestibule E1E 07 Remove paint on Running Man sign and make good

16 Stair Vestibule E1E 07 Remove paint from top edge of skirting on all walls

17 Stair Vestibule E1E 07 Make good to wall paint just above skirting where stained by tiler's bad workmanship

18 Stair Vestibule E1E 07 Reset double power outlet in wall that is not level

19 Stair Vestibule E1E 07 Make good round Fire Damper Grille panel (Lower)

20 Stair Vestibule E1E 07 Make good round Fire Damper Grille panel (Upper)

21 Stair Vestibule E1E 07 Provide proper locking device to Lower Fire Damper Grille

22 Stair Vestibule E1E 07 Provide proper locking device to Upper Fire Damper Grille

23 Stair Vestibule E1E 07 Clean paint off grille to Fire Damper panel (Lower)

24 Stair Vestibule E1E 07 Clean paint off grille to Fire Damper panel (Upper)

25 Stair Vestibule E1E 07 Screw missing in lock plate to door North

26 Stair Vestibule E1E 07 Clean paint off door frame to Door North27 Stair Vestibule E1E 07 Adjust door as squeaks and binds on hinges

28 Stair Vestibule E1E 07 Intumescent strip is not complete to both frame bases of Door North

29 Stair Vestibule E1E 07 Fixing screws to frame protrude and are to be refixed to Door North

30 Stair Vestibule E1E 07 Cover four (4) protruding screw ends in angle plate to top corner to Door North

31 Stair Vestibule E1E 07 Intumescent strip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule E1E 07 Remove paint to three (3) sprinkler head in ceiling

35 Stair Vestibule E1E 07 Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box as key is missing

36 Stair Vestibule E1E 07 Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

37 Stair Vestibule E1E 07 Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

Page 150: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 150/407

38 Stair Vestibule E1E 07 Build up blockwork below threshold and seal to door

39 Stair Vestibule E1E 07 Seal to head of door frame with blockwork and make good

40 Stair Vestibule E1E 07 Divider Wall to LH to be sealed full length to back wall

41 Stair Vestibule E1E 07 Divider Wall to LH to be completed in upper part of FH enclosure (1.35 linear metres missing)

42 Stair Vestibule E1E 07 Divider wall to RH to be sealed to front and back wall where unsealed43 Stair Vestibule E1E 07 Seal LH Divider wall to pipe at high level

44 Stair Vestibule E1E 07 Seal RH divider wall to pipe at high level

45 Stair Vestibule E1E 07 Seal two holes in floor slab within FHE and make good

46 Stair Vestibule E1E 07 Install access panel cover for Dry Riser which is missing

47 Stair Vestibule E1E 07 Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

48 Stair Vestibule E1E 07 Divider wall on LH side of Dry Riser Enclosure is missing

49 Stair Vestibule E1E 07 Clean out general rubbish in Dry Riser Enclosure

50 Stair Vestibule E1E 07 Reset H sign as not level

51 Stair Vestibule E1E 07 Replace missing skirting to RH of North door

52 Stair Vestibule E1E 07 Make good to floor covering at North Door which is very untidy

53 Stair Vestibule E1E 07 Make good to skirting to RH of Door South

54 Stair Vestibule E1E 07 Make good to skirting to LH of Door South

55 Stair Vestibule E1E 07 Fire/Smoke Threshold seal is required to door North

56 Stair Vestibule E1E 07 Make good to floor at South Door LH

57 Stair Vestibule E1E 07 Make good to floor at South Door RH

58 Stair Vestibule E1E 07 Make good arris to LH return to Stair Door and repaint

59 Stair Vestibule E1E 07 Make good to tile skirting to LH side of North Door60 Stair Vestibule E1E 07 Make good to tile skirting to RH side of North Door

61 Stair Vestibule E1E 07 Remove reinforcement in wall to LH side of north door and make good to wall including stains made when cutting rod

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Elevator Vestib. E1E.09 Prepare for and paint ceiling

2 Service Elevator Vestib. E1E.09 Paint sprinkler pipe

3 Service Elevator Vestib. E1E.09 Door frame at bases is 5mm above floor finish and requires to be adjusted

4 Service Elevator Vestib. E1E.09 Fill in hole to door head frame

Page 151: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 151/407

5 Service Elevator Vestib. E1E.09 Adjust inner leaf of door as it is still loose when closed

6 Service Elevator Vestib. E1E.09 Fixing screws to frame protrude and are to be ref ixed to Door

7 Service Elevator Vestib. E1E.09 Cover four (4) protruding screw ends in angle plate to top corner to Door

8 Service Elevator Vestib. E1E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestib. E1E.09 Intumescent strip is short on both side frames and requires to be replaced10 Service Elevator Vestib. E1E.09 Install door stops to Doors

11 Service Elevator Vestib. E1E.09 Clean paint off Door Frames

12 Service Elevator Vestib. E1E.09 Door Signage

13 Service Elevator Vestib. E1E.09 Fire/Smoke Threshold seal is required to door North

14 Service Elevator Vestib. E1E.09 Install closers with selector on doors

15 Service Elevator Vestib. E1E.09 Remove all remaining parts of the protective covering to doors

16 Service Elevator Vestib. E1E.09 Install rubber seal to door

17 Service Elevator Vestib. E1E.09 Intumescent strip to meeting style is not continuous and missing at door lock

18 Service Elevator Vestib. E1E.09 Realign door intruder alarm contacts

19 Service Elevator Vestib. E1E.09 Refix loose skirting to LH side of lift door

20 Service Elevator Vestib. E1E.09 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

21 Service Elevator Vestib. E1E.09 Remove paint on light switch to LH side of Lift Door and make good

22 Service Elevator Vestib. E1E.09 Remove paint on both indicator panels to RJ side of lift door and make good

23 Service Elevator Vestib. E1E.09 Seal and make good to sprinkler pipe at North Wall above door

24 Service Elevator Vestib. E1E.09 Fit and fix floor covering

25 Service Elevator Vestib. E1E.09 Make good to concrete threshold to lift door and fit floor covering including edging piece to lift door

26 Serv ice Elevator Vestib. E1E.09 Remove paint on Access Card Reader and make good 27 Service Elevator Vestib. E1E.09 Check lift reprogrammed to stop at Level 1

28 Service Elevator Vestib. E1E.09 Remove paint on lift door frames and make good

29 Service Elevator Vestib. E1E.09 Repair cracked arris at RH side of Lift Door

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C/D 17/18 (E1E.03) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

2 Corridor C/D 17/18 (E1E.03) Skirting loose on East wall of corridor

3 Corridor C/D 17/18 (E1E.03) Fit and fix floor coverings

4 Corridor C/D 17/18 (E1E.03) Fixing screws to frame protrude and are to be refixed

Page 152: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 152/407

5 Corridor C/D 17/18 (E1E.03) Cover four (4) protruding screw ends in angle plate to top corner to door

6 Corridor C/D 17/18 (E1E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Corridor C/D 17/18 (E1E.03) Intumescent strip is not installed and is required to sides and head frames

8 Corridor C/D 17/18 (E1E.03) Install permanent door handles

9 Corridor C/D 17/18 (E1E.03) Screw missing at lock plate10 Corridor C/D 17/18 (E1E.03) Install door stop to Door

11 Corridor C/D 17/18 (E1E.03) Install rubber seal to Door all round

12 Corridor C/D 17/18 (E1E.03) Remove paint on door frames and make good

13 Corridor C/D 17/18 (E1E.03) Fire/Smoke seal threshold required to entry door

14 Corridor C/D 17/18 (E1E.03) Door signage

15 Corridor C/D 17/18 (E1E.03) Install door closer

16 Corridor C/D 17/18 (E1E.03) Remove manufacturer's labels on door and make good

17 Corridor C/D 17/18 (E1E.03) Make good to floor covering at door threshold including edging piece

18 Corridor C/D 17/18 (E1E.03) Seal East Wall at conduit at ceiling level at north end and make good all round

19 Corridor C/D 17/18 (E1E.03) Seal East Wall at cable tray near ceiling level at north end and make good all round

20 Corridor C/D 17/18 (E1E.03) Seal East wall at AHU metal support and make good all round

21 Corridor C/D 17/18 (E1E.03) Seal East Wall at sprinkler pipe near ceiling level at north end and make good all round

22 Corridor C/D 17/18 (E1E.03) Refix loose plasterboard behind AHU on East Wall

23 Corridor C/D 17/18 (E1E.03) Remove paint on Light Fitting on East Wall and make good

24 Corridor C/D 17/18 (E1E.03) Seal wall to hole on East Wall with four (4) pipes and make good all round

25 Corridor C/D 17/18 (E1E.03) Install operator signage to Fire Alarm Button at East Wall

26 Corridor C/D 17/18 (E1E.03) Seal at East Wall (South) near ceiling level a large sprinkler pipe and make good all round27 Corridor C/D 17/18 (E1E.03) Install final layer of plasterboard in top RH side of East Wall above door which is missing and make good all round

28 Corridor C/D 17/18 (E1E.03) Install plasterboard to large full length gap to South Wall above door and seal to duct, sprinkler pipe and two (2) conduits

29 Corridor C/D 17/18 (E1E.03) Rest Running Man Sign which is not level

30 Corridor C/D 17/18 (E1E.03) Make good to South wall where damaged on RH side of door at low level

31 Corridor C/D 17/18 (E1E 03) Seal at West Wall (South) to large sprinkler supply pipe and make good all round

AMERICA HOUSE

Ref. Location Defect

No.

34 Corridor C/D 17/18 (E1E.03) Seal at West Wall to rectangular horizontal hole with two (2) pipes and make good all round

35 Corridor C/D 17/18 (E1E.03) Seal at West Wall to rectangular vertical hole with two (2) pipes and make good all round

36 Corridor C/D 17/18 (E1E.03) Seal West wall at AHU metal support and make good all round

37 Corridor C/D 17/18 (E1E.03) Seal at West Wall and make good to one (1) conduit at ceiling level (mid) and make good all round

38 Corridor C/D 17/18 (E1E 03) Seal at West Wall and make good to one (1) conduit at ceiling level (North) and make good all round

Page 153: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 153/407

38 Corridor C/D 17/18 (E1E.03) Seal at West Wall and make good to one (1) conduit at ceiling level (North) and make good all round

39 Corridor C/D 17/18 (E1E.03) Seal at West Wall (North) to pipe and make good all round

40 Corridor C/D 17/18 (E1E.03) Seal at West wall to cable tray near ceiling at northern end and make good all round

41 Corridor C/D 17/18 (E1E.03) Seal wall head to East Wall and make good all round

42 Corridor C/D 17/18 (E1E.03) Seal wall head to West Wall and make good all round43 Corridor C/D 17/18 (E1E.03) Prepare and paint ceiling

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor D 14 to 18 (E1E.03) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

2 Corridor D 14 to 18 (E1E.03) Fit and fix floor coverings

3 Corridor D 14 to 18 (E1E.03) Prepare and paint ceiling

4 Corridor D 14 to 18 (E1E.03) Seal South Wall to one (1) sprinkler pipe A and make good all round

5 C id D 14 t 18 (E1E 03) S l S th W ll t (1) i kl i B d k d ll d

Page 154: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 154/407

5 Corridor D 14 to 18 (E1E.03) Seal South Wall to one (1) sprinkler pipe B and make good all round

6 Corridor D 14 to 18 (E1E.03) Seal South Wall to one (1) sprinkler pipe C and make good all round

7 Corridor D 14 to 18 (E1E.03) Seal South Wall to one (1) sprinkler pipe D and make good all round

8 Corridor D 14 to 18 (E1E.03) Seal South Wall to one (1) sprinkler pipe E and make good all round

9 Corridor D 14 to 18 (E1E.03) Seal South Wall to one (1) sprinkler pipe F and make good all round10 Corridor D 14 to 18 (E1E.03) Seal at Wall head to South wall for full length and make good as paint is missing on RH side of wall at cable tray

11 Corridor D 14 to 18 (E1E.03) Make good to wall above skirting where paintwork is fouled

12 Corridor D 14 to 18 (E1E.03) Seal at South Wall at cable tray near ceiling (East) and make good all round

13 Corridor D 14 to 18 (E1E.03) Refix loose skirting on South wall

14 Corridor D 14 to 18 (E1E.03) Seal and make good to SVP pipe at East End on ceiling

15 Corridor D 14 to 18 (E1E.03) Seal and make good to SVP pipe at Mid part of ceiling

16 Corridor D 14 to 18 (E1E.03) Seal and make good to SVP pipe at West End on ceiling

17 Corridor D 14 to 18 (E1E.03) Reconnect or remove loose wire in cable tray

18 Corridor D 14 to 18 (E1E.03) Seal and make good to electrical cable at southwest part of ceiling and make good

19 Corridor D 14 to 18 (E1E.03) Repair insulation to SVP pipe in west part of ceiling

20 Corridor D 14 to 18 (E1E.03) Seal Wall return to South Wall (West) around bean and make good all round

21 Corridor D 14 to 18 (E1E.03) Seal wall near ceiling to wall return to South wall (West) and make good around large cable tray and four (4) pipes

22 Corridor D 14 to 18 (E1E.03) Refix skirting to column D15 and make good

23 Corridor D 14 to 18 (E1E.03) Complete sealing of North wall D15/18 at wall head and make good including two (2) conduits

24 Corridor D 14 to 18 (E1E.03) Remove wall paint from five (5) lights and make good

25 Corridor D 14 to 18 (E1E.03) Fill in hole to North Wall and seal (LH)

26 Corridor D 14 to 18 (E1E.03) Fill in hole to North Wall and seal (RH)27 Corridor D 14 to 18 (E1E.03) Complete painting of North wall as not finished

28 Corridor D 14 to 18 (E1E.03) Complete sealing of West wall D15 at wall head and make good

29 Corridor D 14 to 18 (E1E.03) Complete sealing of North wall D14/15 at wall head and make good including two (2) conduits

30 Corridor D 14 to 18 (E1E.03) Seal North Wall D14/15 at wall head and make good all round

31 Corridor D 14 to 18 (E1E 03) Seal North Wall at D15 around beam and make good

AMERICA HOUSE

Ref. Location Defect

No.

34 Corridor D 14 to 18 (E1E.03) Seal South Wall D 15 to sprinkler pipe (LH) near ceiling and make good all round

35 Corridor D 14 to 18 (E1E.03) Seal South Wall D 15 to SVP pipe (LH) near ceiling and make good all round

36 Corridor D 14 to 18 (E1E.03) Repair insulation to SVP pipe to LH side of South Wall D 15

37 Corridor D 14 to 18 (E1E.03) Seal South Wall D15 to beam at ceiling level and make good all round

38 Corridor D 14 to 18 (E1E 03) Seal South wall to sprinkler pipe (RH) near ceiling level and make good all round

Page 155: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 155/407

38 Corridor D 14 to 18 (E1E.03) Seal South wall to sprinkler pipe (RH) near ceiling level and make good all round

39 Corridor D 14 to 18 (E1E.03) Fixing screws to frame protrude and are to be refixed

40 Corridor D 14 to 18 (E1E.03) Cover four (4) protruding screw ends in angle plate to top corner to door

41 Corridor D 14 to 18 (E1E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

42 Corridor D 14 to 18 (E1E.03) Intumescent strip is short at base of both door frames and to be replaced43 Corridor D 14 to 18 (E1E.03) Intumescent strip is short to top frame of door and to be replaced

44 Corridor D 14 to 18 (E1E.03) Screw missing at lock plate

45 Corridor D 14 to 18 (E1E.03) Install door stop to Door

46 Corridor D 14 to 18 (E1E.03) Install rubber seal to Door all round

47 Corridor D 14 to 18 (E1E.03) Remove paint on door frames and make good

48 Corridor D 14 to 18 (E1E.03) Fire/Smoke seal threshold required to entry door

49 Corridor D 14 to 18 (E1E.03) Door signage

50 Corridor D 14 to 18 (E1E.03) Install door closer

51 Corridor D 14 to 18 (E1E.03) Remove manufacturer's labels on door and make good

52 Corridor D 14 to 18 (E1E.03) Make good to floor covering at door threshold including edging piece

53 Corridor D 14 to 18 (E1E.03) Remove paint on door and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C/D 14/15 (E1E.03) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

2 Corridor C/D 14/15 (E1E.03) Fit and fix floor coverings

3 Corridor C/D 14/15 (E1E.03) Prepare and paint ceiling

4 Corridor C/D 14/15 (E1E.03) Replace missing skirting corner at wall return north (Elec. Enclosure)

5 Corridor C/D 14/15 (E1E 03) Repair and make good LH arris to wall return at Electrical Enclosure

Page 156: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 156/407

5 Corridor C/D 14/15 (E1E.03) Repair and make good LH arris to wall return at Electrical Enclosure

6 Corridor C/D 14/15 (E1E.03) Refix skirting to LH of Electrical Enclosure that have become loose

7 Corridor C/D 14/15 (E1E.03) Refix skirting to RH of Electrical Enclosure that have become loose

8 Corridor C/D 14/15 (E1E.03) Refix loose corner piece of skirting at LH of Electrical Enclosure

9 Corridor C/D 14/15 (E1E.03) Repair skirting to both wall ingoings to Door to Female Toilet E1E.0510 Corridor C/D 14/15 (E1E.03) Make good floor covering to Door to Retail Unit including edging piece (E1E.04) (North)

11 Corridor C/D 14/15 (E1E.03) Make good floor covering to Door to Female Toilet including edging piece (E1E.05)

12 Corridor C/D 14/15 (E1E.03) Make good floor covering to Door to Male Toilet including edging piece (E1E.06)

13 Corridor C/D 14/15 (E1E.03) Repair skirting to both wall ingoings to Door to Male Toilet E1E.06

14 Corridor C/D 14/15 (E1E.03) Make good floor coverings including threshold edging strip to Stair Door (E1E.07)

15 Corridor C/D 14/15 (E1E.03) Fixing screws to frame protrude and are to be refixed

16 Corridor C/D 14/15 (E1E.03) Cover four (4) protruding screw ends in angle plate to top corner to door

17 Corridor C/D 14/15 (E1E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

18 Corridor C/D 14/15 (E1E.03) Intumescent strip is not installed and is required to sides and head frames

19 Corridor C/D 14/15 (E1E.03) Install permanent door handles

20 Corridor C/D 14/15 (E1E.03) Screw missing at lock plate

21 Corridor C/D 14/15 (E1E.03) Install door stop to Door

22 Corridor C/D 14/15 (E1E.03) Install rubber seal to Door all round

23 Corridor C/D 14/15 (E1E.03) Remove paint on door frames and make good

24 Corridor C/D 14/15 (E1E.03) Fire/Smoke seal threshold required to entry door

25 Corridor C/D 14/15 (E1E.03) Door signage

26 Corridor C/D 14/15 (E1E.03) Install door closer

27 Corridor C/D 14/15 (E1E.03) Remove manufacturer's labels on door and make good

28 Corridor C/D 14/15 (E1E.03) Remove all remaining protective covering to door

29 Corridor C/D 14/15 (E1E.03) Clean to two (2) light fittings

30 Corridor C/D 14/15 (E1E.03) Seal East Wall (Electrical Enclosure) at wall head and make good all round

31 Corridor C/D 14/15 (E1E 03) Seal East Wall (Electrical Enclosure) at small pipe and make good all round

AMERICA HOUSE

Ref. Location Defect

No.

34 Corridor C/D 14/15 (E1E.03) Install fixing screws to two control boxes on East Wall to Electrical Enclosure

35 Corridor C/D 14/15 (E1E.03) Make good to floor concrete, relevel and prepare for floor covering at door to Retail Area E1E.03 (North)

36 Corridor C/D 14/15 (E1E.03) Seal West Wall (LH) near ceiling to two (2) large pipes and make good all round

37 Corridor C/D 14/15 (E1E.03) Seal West Wall (LH) near ceiling to cable tray and make good all round

38 Corridor C/D 14/15 (E1E.03) Seal West Wall (LH) near ceiling to one (1) small pipe and make good all round

Page 157: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 157/407

( ) ( ) g ( ) p p g

39 Corridor C/D 14/15 (E1E.03) Seal West Wall (LH) near ceiling to one (1) large pipe and make good all round

40 Corridor C/D 14/15 (E1E.03) Seal West Wall (LH) near ceiling to one (1) large circular duct pipe and make good all round

41 Corridor C/D 14/15 (E1E.03) Seal West Wall near ceiling (Mid) to one (1) conduit and make good all round

42 Corridor C/D 14/15 (E1E.03) Seal wall head to West wall and make good to full length43 Corridor C/D 14/15 (E1E.03) Seal West Wall (RH) at hole in wall and make good all round

44 Corridor C/D 14/15 (E1E.03) Seal West Wall (RH) at hole in wall to four (4) pipes and make good all round

45 Corridor C/D 14/15 (E1E.03) Seal West Wall (RH) at cable tray near ceiling and make good all round

46 Corridor C/D 14/15 (E1E.03) Seal West Wall (RH) at one (1) sprinkler pipe near ceiling and make good all round

47 Corridor C/D 14/15 (E1E.03) Seal West Wall (LH) side for one (1) pipe below two large pipes and make good all round

48 Corridor C/D 14/15 (E1E.03) Seal West Wall at beam D 14/15 and make good all round

 

NOTE : Electrical Cabinets with locks were NOT inspected

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C 14/15 (E1E.03) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

2 Corridor C 14/15 (E1E.03) Fit and fix floor coverings

3 Corridor C 14/15 (E1E.03) Prepare and paint ceiling

4 Corridor C 14/15 (E1E.03) Relocate sprinkler heads that are fouled up by other MEP equipment and reduced in effectiveness

5 Corridor C 14/15 (E1E.03) Clean light fitting

Page 158: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 158/407

( ) g g

6 Corridor C 14/15 (E1E.03) Rest Running Man Sign that is not level

7 Corridor C 14/15 (E1E.03) Remove wall paint from Running Man Sign and make good

8 Corridor C 14/15 (E1E.03) Install operator signage to Fire Alarm Button at South Wall

9 Corridor C 14/15 (E1E.03) Install operator signage to Door Release Button at South Wall10 Corridor C 14/15 (E1E.03) Install break glass to Emergency Door Release Button on South Wall

11 Corridor C 14/15 (E1E.03) Complete plasterboard to South Wall at ceiling level yet to be executed and make good to duct and four (4) pipes

12 Corridor C 14/15 (E1E.03) Seal at South Wall around beam C/D 15 and make good

13 Corridor C 14/15 (E1E.03) Seal at wall head on East Wall and make good full length

14 Corridor C 14/15 (E1E.03) Seal East Wall (LH) to small pipe and make good

15 Corridor C 14/15 (E1E.03) Seal East Wall near ceiling to cable tray and make good

16 Corridor C 14/15 (E1E.03) Seal East Wall (RH) to large pipe and make good

17 Corridor C 14/15 (E1E.03) Seal East Wall (RH) to small pipe and make good

18 Corridor C 14/15 (E1E.03) Seal at wall head on North Wall and make good full length

19 Corridor C 14/15 (E1E.03) Seal North wall around beam C/D 15 and make good all round

20 Corridor C 14/15 (E1E.03) Seal North wall near ceiling to one (1) sprinkler pipe and make good all round

21 Corridor C 14/15 (E1E.03) Seal North Wall at western end where hole next to ceiling and make good to two (2) conduits complete

22 Corridor C 14/15 (E1E.03) Fixing screws to frame protrude and are to be refixed

23 Corridor C 14/15 (E1E.03) Cover four (4) protruding screw ends in angle plate to top corner to door

24 Corridor C 14/15 (E1E.03) Intumescent strip is not installed and requires to be on both side frames and head frame

25 Corridor C 14/15 (E1E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

26 Corridor C 14/15 (E1E.03) Make good to floor covering at door threshold including edging piece

27 Corridor C 14/15 (E1E.03) Screw missing at lock plate

28 Corridor C 14/15 (E1E.03) Install door stop to Door

29 Corridor C 14/15 (E1E.03) Install rubber seal to Door all round

30 Corridor C 14/15 (E1E.03) Remove paint on door frames and make good

31 Corridor C 14/15 (E1E 03) Fire/Smoke seal threshold required to entry door

AMERICA HOUSE

Ref. Location Defect

No.

1 Female Toilet E1E.05 Fixing screws to frame protrude and are to be refixed

2 Female Toilet E1E.05 Cover four (4) protruding screw ends in angle plate to top corner to door

3 Female Toilet E1E.05 Remove paint on door frames and make good

4 Female Toilet E1E.05 Replace wrong lockset

5 Female Toilet E1E.05 Tidy up floor covering at door threshold and provide edging strip to floor tiles

Page 159: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 159/407

6 Female Toilet E1E.05 Replace screws to inner door grille to match grille as outside

7 Female Toilet E1E.05 No water supply to sink taps

8 Female Toilet E1E.05 Tap LH is loose and to be tightened

9 Female Toilet E1E.05 Tap RH is loose and to be tightened10 Female Toilet E1E.05 Install plug

11 Female Toilet E1E.05 Light switch plate is not level

12 Female Toilet E1E.05 Reset and make good around floor gulley

13 Female Toilet E1E.05 Remove and tidy up mortar grouting to wall

14 Female Toilet E1E.05 Wall tiling is of mediocre standard and excess mortar to be removed

15 Female Toilet E1E.05 Clean up grout between tiles to floors

16 Female Toilet E1E.05 Clean dirt/dust in and around the two (2) ceiling ventilators

17 Female Toilet E1E.05 Running Man sign is not level and to be aligned

18 Female Toilet E1E.05 Remove wall paint to Running Man sign and make good

19 Female Toilet E1E.05 Make good to rough pointing and join between wall tiling and mosaic on RH leg support

20 Female Toilet E1E.05 Make good and repair to rough patch to mosaic covering to RH of sink on vanity surface

21 Female Toilet E1E.05 Tiling below sink is of poor quality and to be re-executed

22 Female Toilet E1E.05 Mosaic to Vanitory Unit is generally sub-standard and should be redone

23 Female Toilet E1E.05 Make good joint between wall tiling and floor below Vanitory Unit

24 Female Toilet E1E.05 Make good joint between mosaic and wall tiling at top surface of Vanitory Unit and seal

AMERICA HOUSE

Ref. Location Defect

No.

1 Male Toilet (E1E.06 Fixing screws to frame protrude and are to be refixed

2 Male Toilet (E1E.06 Cover four (4) protruding screw ends in angle plate to top corner to door

3 Male Toilet (E1E.06 Remove paint on door frames and make good

4 Male Toilet (E1E.06 Replace wrong lockset

5 Male Toilet (E1E.06 Tidy up floor covering at door threshold and provide edging strip to floor tiles

Page 160: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 160/407

6 Male Toilet (E1E.06 Replace screws to inner door grille to match grille as outside

7 Male Toilet (E1E.06 No water supply to sink taps

8 Male Toilet (E1E.06 Tap LH is loose and to be tightened

9 Male Toilet (E1E.06 Tap RH is loose and to be tightened10 Male Toilet (E1E.06 Install plug

11 Male Toilet (E1E.06 Light switch plate is not level

12 Male Toilet (E1E.06 Reset and make good around floor gulley

13 Male Toilet (E1E.06 Box in water meter and provide access panel

14 Male Toilet (E1E.06 Remove tape at mirror and make good

15 Male Toilet (E1E.06 Wall tiling is generally substandard and excess grout is to be removed

16 Male Toilet (E1E.06 Make good substandard mosaic to top of Vanitory Unit on RH side

17 Male Toilet (E1E.06 Make good to joint between mirror and wall and mosaic tiles at top of Vanitory Unit

18 Male Toilet (E1E.06 Wall tiling below Vanitory Unit to be re-executed including replacing broken tiles

19 Male Toilet (E1E.06 Wall tiles to LH of door are not level and to be redone

20 Male Toilet (E1E.06 Wall tiling very substandard in WC cubicle and requires to be redone

21 Male Toilet (E1E.06 Clean grouting to floor tiles as very dirty

22 Male Toilet (E1E.06 Replace cracked floor tile on South Wall base

23 Male Toilet (E1E.06 Clean dirt/dust at and around the two (2) ceiling ventilators and make good

24 Male Toilet (E1E.06 Mosaic work to Vanitory unit is generally substandard

25 Male Toilet (E1E.06 Modesty screen to Urinal requires to be more firmly fixed

26 Male Toilet (E1E.06 Make good joint to LH side of Vanitory unit between mosaic and wall tiling

27 Male Toilet (E1E.06 Clean out relieving bead between wall tiling and plaster frieze on East Wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Retail Area (Togo) E1E.04 Seal North Wall at Wall head and make good for full length

2 Retail Area (Togo) E1E.04 Seal Wall near ceiling to West Wall around cable tray (North) and make good

3 Retail Area (Togo) E1E.04 Seal West Wall at wall head and make good for full length

4 Retail Area (Togo) E1E.04 Seal East Wall 450mm at wall head and make good for full length

5 Retail Area (Togo) E1E.04 Seal South Wall above bulkhead and make good for full length

6 Retail Area (Togo) E1E 04 Seal East wall for group of four (4) pipes and make good all round

Page 161: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 161/407

6 Retail Area (Togo) E1E.04 Seal East wall for group of four (4) pipes and make good all round

7 Retail Area (Togo) E1E.04 Seal East wall for cable tray (North) and make good all round

Page 162: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 162/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Retail Area A/D 18/21 (E1E.02) Seal wall board missing at upper level to B 18 North and make good all round

2 Retail Area A/D 18/21 (E1E.02) Seal East Wall above bulkhead A/B 18 and make good all round

3 Retail Area A/D 18/21 (E1E.02) Seal East wall at A/B 18 to four (4) HVAC pipes and make good all round

4 Retail Area A/D 18/21 (E1E.02) Seal West above bulkhead A/B 18 and make good all round

5 Retail Area A/D 18/21 (E1E.02) Seal East Wall around Beam B 18/19 and make good all round

6 Retail Area A/D 18/21 (E1E 02) Seal East wall around Beam C 18/19 and make good all round

Page 163: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 163/407

6 Retail Area A/D 18/21 (E1E.02) Seal East wall around Beam C 18/19 and make good all round

7 Retail Area A/D 18/21 (E1E.02) Relocate sprinkler heads near East Wall (Ozer)

8 Retail Area A/D 18/21 (E1E.02) Seal East wall at wall head for full length A/D 19 and make good all round

9 Retail Area A/D 18/21 (E1E.02) Seal West Wall to wall head for full length and make good all round A/D 1810 Retail Area A/D 18/21 (E1E.02) Seal West wall (RH) to four (4) HVAC pipes and make good all round

11 Retail Area A/D 18/21 (E1E.02) Seal West Wall around Beam B 18/19 and make good all round

12 Retail Area A/D 18/21 (E1E.02) Seal West wall around Beam C 18/19 and make good all round

13 Retail Area A/D 18/21 (E1E.02) Seal West Wall (RH) to one (1) small pipe and make good

14 Retail Area A/D 18/21 (E1E.02) Seal West Wall (RH) to one (1) sprinkler small pipe and make good

15 Retail Area A/D 18/21 (E1E.02) Seal West Wall (LH) to one (1) sprinkler small pipe and make good

16 Retail Area A/D 18/21 (E1E.02) Seal West Wall (LH) to one (1) small pipe and make good

17 Retail Area A/D 18/21 (E1E.02) Seal West wall (LH) to four (4) HVAC pipes and make good all round

18 Retail Area A/D 18/21 (E1E.02) Complete wall boarding to West Wall at upper level and make good all round

AMERICA HOUSE

Ref. Location Defect

No.

1 Lift Lobby Level 2 (E2E.01) Tiling to floor is uneven and not aligned and requires to be re-executed

2 Lif t Lobby Level 2 (E2E.01) Wall Til ing to West Wall is debonding, uneven, not aligned and requires to be re-executed

3 Lif t Lobby Level 2 (E2E.01) Wall Til ing to East (Lif t) Wall is uneven, not aligned and requires to be re-executed

4 Lift Lobby Level 2 (E2E.01) Remove paint on loudspeaker in ceiling and make good

5 Lift Lobby Level 2 (E2E.01) Readjust two (2) small downlighters that are not properly aligned and make good

6 Lift Lobby Level 2 (E2E 01) Remove paint on ventilation grille near lifts

Page 164: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 164/407

6 Lift Lobby Level 2 (E2E.01) Remove paint on ventilation grille near lifts

7 Lift Lobby Level 2 (E2E.01) Seal pointing between tiling and lift panelling to PE 09 at head RH

8 Lift Lobby Level 2 (E2E.01) Seal pointing between tiling and lift panelling to PE 08 at head both sides

9 Lift Lobby Level 2 (E2E.01) Seal pointing between tiling and lift panelling to PE 07 at head both sides10 Lift Lobby Level 2 (E2E.01) Refit stainless steel skirting to Lift PE 09 that show gaps between the skirting and wall panelling both sides

11 Lift Lobby Level 2 (E2E.01) Refit stainless steel skirting to Lift PE 08 that show gaps between the skirting and wall panelling both sides

12 Lift Lobby Level 2 (E2E.01) Refit stainless steel skirting to Lift PE 07 that show gaps between the skirting and wall panelling both sides

13 Lift Lobby Level 2 (E2E.01) Clean threshold of Lift PE 07

14 Lift Lobby Level 2 (E2E.01) Clean threshold of Lift PE 08

15 Lift Lobby Level 2 (E2E.01) Clean threshold of Lift PE 07

16 Lift Lobby Level 2 (E2E.01) Make good to floor covering at RH of lift door frame PE7

17 Lift Lobby Level 2 (E2E.01) Make good to floor covering at LH of lift door frame PE7

18 Lift Lobby Level 2 (E2E.01) Make good to floor covering at RH of lift door frame PE819 Lift Lobby Level 2 (E2E.01) Make good to floor covering at LH of lift door frame PE8

20 Lift Lobby Level 2 (E2E.01) Make good to floor covering at RH of lift door frame PE9

21 Lift Lobby Level 2 (E2E.01) Make good to floor covering at LH of lift door frame PE9

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor C 14/18 Level 2 (E2E.01) Clean up ventilated dirt deposits on painted ceiling finish to eight (8) air inlets and make good

2 Corridor C 14/18 Level 2 (E2E.01) Skirting not yet installed

3 Corridor C 14/18 Level 2 (E2E.01) Floor covering not yet installed

4 Corridor C 14/18 Level 2 (E2E.01) Remove tape and paint stain on Fire Alarm to South Wall near door to Stair Vestibule E2E.03

5 Corridor C 14/18 Level 2 (E2E.01) Install operator signage to Fire Alarm Button at South Wall near door to Stair Vestibule E2E.03

6 Corridor C 14/18 Level 2 (E2E 01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby

Page 165: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 165/407

6 Corridor C 14/18 Level 2 (E2E.01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby

7 Corridor C 14/18 Level 2 (E2E.01) Clean paint off grille to Fire Damper panel (Lower) near Lift Lobby

8 Corridor C 14/18 Level 2 (E2E.01) Provide proper locking device to Low Fire Damper Grille on South Wall near Lift Lobby

9 Corridor C 14/18 Level 2 (E2E.01) Tiling to wall at C17 South Wall is uneven and not aligned and requires to be re-executed10 Corridor C 14/18 Level 2 (E2E.01) Tiling to wall at C16 South Wall is uneven and not aligned and requires to be re-executed

11 Corridor C 14/18 Level 2 (E2E.01) Install operator signage to Fire Alarm Button at South Wall RH of Service Elevator Vestibule

12 Corridor C 14/18 Level 2 (E2E.01) Install operator signage to Door Release Button at South Wall to RH of Service Elevator Vestibule

13 Corridor C 14/18 Level 2 (E2E.01) Install break glass to Emergency Door Release Button on South Wall to RH of Service Elevator Vestibule

14 Corridor C 14/18 Level 2 (E2E.01) Complete paintwork in ceiling recess bulkhead (light trough) along South Wall

15 Corridor C 14/18 Level 2 (E2E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby

16 Corridor C 14/18 Level 2 (E2E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby

17 Corridor C 14/18 Level 2 (E2E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on South Wall near Lift Lobby

18 Corridor C 14/18 Level 2 (E2E.01) Make good round Fire Damper Grille panel (Low) on South Wall near to RH side of Service Elevator Lobby

19 Corridor C 14/18 Level 2 (E2E.01) Clean paint off grille to Fire Damper panel (Lower) to RH side of Service Lift Lobby

20 Corridor C 14/18 Level 2 (E2E.01) Provide proper locking device to Low Fire Damper Grille on South Wall to RH side of Service Lift Lobby

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor Level 2 B/C 14 (E2E.01) Install access panel No 1 and frame to ceiling

2 Corridor Level 2 B/C 14 (E2E.01) Install access panel No 2 and make good to frame to ceiling

3 Corridor Level 2 B/C 14 (E2E.01) Glass Key Box to Fire Hosereel box the glass is loose and should re replaced with a Break Glass Key Box as key is missing

4 Corridor Level 2 B/C 14 (E2E.01) Bed Glazing to Fire Hosereel box in neoprene gasket to prevent rattle and worse

5 Corridor Level 2 B/C 14 (E2E.01) Seal LH and RH openings between Fire Hosereel (FHE) door frame and blockwork

6 Corridor Level 2 B/C 14 (E2E.01) Build up blockwork below threshold and seal to door

Page 166: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 166/407

( ) p

7 Corridor Level 2 B/C 14 (E2E.01) Seal to head of door frame with blockwork and make good

8 Corridor Level 2 B/C 14 (E2E.01) Divider Wall to LH to be sealed full length to back wall

9 Corridor Level 2 B/C 14 (E2E.01) Seal wall at RH side of enclosure for waste pipe and make good

10 Corridor Level 2 B/C 14 (E2E.01) Seal two holes in ceiling slab within FHE and make good

11 Corridor Level 2 B/C 14 (E2E.01) Remove cable and make good to ceiling and floor slab when removed

12 Corridor Level 2 B/C 14 (E2E.01) Make good round Fire Damper Grille panel (Upper C 14) on South Wall near Lift Lobby

13 Corridor Level 2 B/C 14 (E2E.01) Clean paint off grille to Fire Damper panel (Upper C 14) near Lift Lobby

14 Corridor Level 2 B/C 14 (E2E.01) Provide proper locking device to Upper (C/14) Fire Damper Grille on South Wall near Lift Lobby

15 Corridor Level 2 B/C 14 (E2E.01) Skirting not yet installed

16 Corridor Level 2 B/C 14 (E2E.01) Floor covering not yet installed

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor Level 2 B 14/18 (E2E.01) Clean up ventilated dirt deposits on painted ceiling finish to eight (8) air inlets and make good

2 Corridor Level 2 B 14/18 (E2E.01) Skirting not yet installed

3 Corridor Level 2 B 14/18 (E2E.01) Floor covering not yet installed

4 Corridor Level 2 B 14/18 (E2E.01) Make good to gap between Low Fire Damper Grille on North Wall and tiling finish

5 Corridor Level 2 B 14/18 (E2E.01) Install operator signage to Fire Alarm Button at North Wall near door to Stair Vestibule E2E.03

6 Corridor Level 2 B 14/18 (E2E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E2E.03

Page 167: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 167/407

( ) g p p ( )

7 Corridor Level 2 B 14/18 (E2E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E2E.03 North Wall

8 Corridor Level 2 B 14/18 (E2E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E2E.03

9 Corridor Level 2 B 14/18 (E2E.01) Tiling to wall at C17 North Wall is uneven and not aligned and requires to be re-executed

10 Corridor Level 2 B 14/18 (E2E.01) Tiling to wall at C16 North Wall is uneven and not aligned and requires to be re-executed

11 Corridor Level 2 B 14/18 (E2E.01) Install operator signage to Fire Alarm Button at North Wall LH of Stair Vestibule E2E.17

12 Corridor Level 2 B 14/18 (E2E.01) Complete paintwork in ceiling recess bulkhead (light trough) along North Wall

13 Corridor Level 2 B 14/18 (E2E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby

14 Corridor Level 2 B 14/18 (E2E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby

15 Corridor Level 2 B 14/18 (E2E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on North Wall near Lift Lobby

16 Corridor Level 2 B 14/18 (E2E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E2E.17 LH

17 Corridor Level 2 B 14/18 (E2E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E2E.17 North Wall

18 Corridor Level 2 B 14/18 (E2E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E2E.17 LH19 Corridor Level 2 B 14/18 (E2E.01) Make good to chipped arris to LH of door to Stair Vestibule E2E.03

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair E2E.18 Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair E2E.18 Clean light fitting of paint stains etc.

3 Egress Stair E2E.18 Reset Light fitting as not level

4 Egress Stair E2E.18 Reset Running Man Sign light as not level

5 Egress Stair E2E.18 Tiled Level 2 floor requires to be polished and sealed and repaired where poor workmanship near divide wall to stair

6 Egress Stair E2E.18 Fixing screws to frame protrude and are to be refixed

Page 168: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 168/407

7 Egress Stair E2E.18 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair E2E.18 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair E2E.18 Intumescent strip to open door jamb is short and to be replaced

10 Egress Stair E2E.18 Intumescent strip to hinge door jamb is short and to be replaced

11 Egress Stair E2E.18 Rubber infill strip to door is loose at head

12 Egress Stair E2E.18 Install door stop to Door

13 Egress Stair E2E.18 Screw missing at lock plate on door

14 Egress Stair E2E.18 Remove paint on door frames and make good

15 Egress Stair E2E.18 Fire/Smoke seal threshold required to entry door

16 Egress Stair E2E.18 Door signage

17 Egress Stair E2E.18 Door intruder alarm contacts to be realigned

18 Egress Stair E2E.18 Clean out and make good to floor at frame bases to door19 Egress Stair E2E.18 Door Access Closer was operational but could be opened by a strong push and needs to be reset

20 Egress Stair E2E.18 Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

21 Egress Stair E2E.18 Clean light fitting of paint stains etc. at mid landing

22 Egress Stair E2E.18 Reset Light fitting as not level at mid landing

23 Egress Stair E2E.18 Make good tiling at mid landing at stair turn as of poor workmanship

24 Egress Stair E2E.18 Lower flight top stair tread moves on strong shaking of the handrail and requires all to be refixed firmly

25 Egress Stair E2E.18 Seal gap between lower flight to step and mid landing

26 Egress Stair E2E.18 Clean two (2) stair flights between Levels 2 and 3 of paint and mortar stains complete

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 2 E2E.17 Remove paint to South Door Frames

2 Stair Vestibule Level 2 E2E.17 Fit rubber seal all round door South

3 Stair Vestibule Level 2 E2E.17 Intumescent strip is not complete to both frame bases of Door South

4 Stair Vestibule Level 2 E2E.17 Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule Level 2 E2E.17 Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule Level 2 E2E.17 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

Page 169: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 169/407

7 Stair Vestibule Level 2 E2E.17 Install door stop to Door South

8 Stair Vestibule Level 2 E2E.17 Remove remaining protective covering to Door South

9 Stair Vestibule Level 2 E2E.17 Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule Level 2 E2E.17 Screw missing in lock plate to door South

11 Stair Vestibule Level 2 E2E.17 Intumescent strip is missing on the head frame

12 Stair Vestibule Level 2 E2E.17 Install door closer

13 Stair Vestibule Level 2 E2E.17 Adjust door to remove squeak and binding

14 Stair Vestibule Level 2 E2E.17 Tile floor is uneven and needs to be levelled, polished and resealed

15 Stair Vestibule Level 2 E2E.17 Make good to wall around Dry Riser including the removal twelve (12) black headed screws

16 Stair Vestibule Level 2 E2E.17 Provide operation label to Door Push Button in Romanian and English

17 Stair Vestibule Level 2 E2E.17 Remove paint on Running Man sign and make good

18 Stair Vestibule Level 2 E2E.17 Remove paint from top edge of skirting on all walls19 Stair Vestibule Level 2 E2E.17 Make good to wall paint just above skirting where stained by tiler's bad workmanship

20 Stair Vestibule Level 2 E2E.17 Reset double power outlet in wall that is not level

21 Stair Vestibule Level 2 E2E.17 Clean two (2) light fittings

22 Stair Vestibule Level 2 E2E.17 Clean paint and masking tape off door frame to Door North

23 Stair Vestibule Level 2 E2E.17 Intumescent str ip to hinge frame is short at upper prong on Door North

24 Stair Vestibule Level 2 E2E.17 Intumescent strip is not complete to both frame bases of Door North

25 Stair Vestibule Level 2 E2E.17 Fixing screws to frame protrude and are to be refixed to Door North

26 Stair Vestibule Level 2 E2E.17 Cover four (4) protruding screw ends in angle plate to top corner to Door North

27 Stair Vestibule Level 2 E2E.17 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

28 Stair Vestibule Level 2 E2E.17 Install door stop to Door North

29 Stair Vestibule Level 2 E2E.17 Fit rubber seal all round door North

30 Stair Vestibule Level 2 E2E.17 Fire/Smoke Threshold seal is required to door North

31 Stair Vestibule Level 2 E2E 17 Install door closer to Door North

Page 170: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 170/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E2E.05 Make good to south sprinkler head and rest

2 Vestibule E2E.05 Clean up stains on ceiling loudspeaker

3 Vestibule E2E.05 Make good to bossed tiles near corridor to Electrical Closet and Data Room

4 Vestibule E2E.05 Remove paint to South Door Frames

5 Vestibule E2E.05 Fit rubber seal all round door South

6 Vestibule E2E.05 Intumescent strip is not complete to both frame bases of Door South

7 V tib l E2E 05 Fi i t f t d d t b fi d t D S th

Page 171: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 171/407

7 Vestibule E2E.05 Fixing screws to frame protrude and are to be refixed to Door South

8 Vestibule E2E.05 Cover four (4) protruding screw ends in angle plate to top corner to Door South

9 Vestibule E2E.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

10 Vestibule E2E.05 Install door stop to Door South

11 Vestibule E2E.05 Remove remaining protective covering to Door South

12 Vestibule E2E.05 Install fire/smoke seal threshold plate to Door South

13 Vestibule E2E.05 Screw missing in lock plate to door South

14 Vestibule E2E.05 Install door closer to Door South

15 Vestibule E2E.05 Install permanent handles etc. to door South

16 Vestibule E2E.05 Clean paint off door frame to Door North

17 Vestibule E2E.05 Intumescent strip is not complete to both frame bases of Door North

18 Vestibule E2E.05 Fixing screws to frame protrude and are to be refixed to Door North19 Vestibule E2E.05 Cover four (4) protruding screw ends in angle plate to top corner to Door North

20 Vestibule E2E.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Vestibule E2E.05 Install door stop to Door North

22 Vestibule E2E.05 Fit rubber seal all round door North

23 Vestibule E2E.05 Fire/Smoke Threshold seal is required to door North

24 Vestibule E2E.05 Install door closer to Door North

25 Vestibule E2E.05 Remove all remaining parts of protective covering to door

26 Vestibule E2E.05 Install missing lock and door handles to North Door

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E2E.06 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E2E.06 Clean grouting to tiles generally

3 Handicapped Toilet E2E.06 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E2E.06 Tidy up floor at LH Base Frame of door

5 Handicapped Toilet E2E.06 Remove paint on door frames and make good

6 Handicapped Toilet E2E.06 Fixing screws to frame protrude and are to be refixed to door

7 Handicapped Toilet E2E 06 Cover four (4) protruding screw ends in angle plate to top corner to door

Page 172: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 172/407

7 Handicapped Toilet E2E.06 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Handicapped Toilet E2E.06 Screw missing to lock plate on door

9 Handicapped Toilet E2E.06 Remove all remaining parts of protective covering to door

10 Handicapped Toilet E2E.06 Reset WC seat and make firm

11 Handicapped Toilet E2E.06 WHB tap is loose and to be reset properly

12 Handicapped Toilet E2E.06 Replace damage collar washer to WHB tap

13 Handicapped Toilet E2E.06 Install plug

14 Handicapped Toilet E2E.06 Install missing chromium insert to overflow to WHB

15 Handicapped Toilet E2E.06 Install Door stop

16 Handicapped Toilet E2E.06 Install rubber seal around door

17 Handicapped Toilet E2E.06 Generally clean off excess grouting on wall tiles

18 Handicapped Toilet E2E.06 No hot water available

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E2E 07 Make good to floor tiling at RH side on door

2 Toilet E2E 07 Make good to floor tiling at LH side on door

3 Toilet E2E 07 Install door stop

4 Toilet E2E 07 Remove paint on door frames and make good

5 Toilet E2E 07 Fixing screws to frame protrude and are to be refixed to door

6 Toilet E2E 07 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Toilet E2E 07 Screw missing to lock plate on door

Page 173: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 173/407

7 Toilet E2E 07 Screw missing to lock plate on door

8 Toilet E2E 07 Remove all remaining parts of protective covering to door

9 Toilet E2E 07 Install rubber seal around door

10 Toilet E2E 07 Generally clean off excess grouting on wall tiles

11 Toilet E2E 07 Clean grout on floor tiles generally

12 Toilet E2E 07 Tidy up joint between wall and floor tiling on South Wall

13 Toilet E2E 07 Remove paint on mirror and make good

14 Toilet E2E 07 WHB tap is loose and to be reset properly

15 Toilet E2E 07 Install plug

16 Toilet E2E 07 No hot water available

17 Toilet E2E 07 Replace door grill screws (Internal) with white headed screws

18 Toilet E2E 07 WC Toilet Flushing mechanism is not working

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E2E 08 Make good to floor tiling at joint with wall tiling at RH side on door2 Toilet E2E 08 Make good to floor tiling at joint with wall tiling along South Wall

3 Toilet E2E 08 Install door stop

4 Toilet E2E 08 Remove paint on door frames and make good

5 Toilet E2E 08 Fixing screws to frame protrude and are to be refixed to door

6 Toilet E2E 08 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Toilet E2E 08 Screw missing to lock plate on door

Page 174: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 174/407

o e 08 Sc e ss g o oc p a e o doo

8 Toilet E2E 08 Remove all remaining parts of protective covering to door

9 Toilet E2E 08 Install rubber seal around door

10 Toilet E2E 08 Generally clean off excess grouting on wall tiles

11 Toilet E2E 08 Clean grout on floor tiles generally

12 Toilet E2E 08 Tidy up joint between wall and floor tiling on South Wall

13 Toilet E2E 08 Install overflow chromium insert

14 Toilet E2E 08 WHB tap is loose and to be reset properly

15 Toilet E2E 08 Install plug

16 Toilet E2E 08 No hot water available

17 Toilet E2E 08 Replace door grill screws (Internal) with white headed screws

18 Toilet E2E 08 Door to be eased as 'loud squeak'

19 Toilet E2E 08 Remove paint splashes on wall tiling

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E2E.09 Make good tile grouting etc around floor gulley 2 Toilet E2E.09 Make good to lower RH Door frame where paint has peeled and frame rusted

3 Toilet E2E.09 Install door stop

4 Toilet E2E.09 Remove paint on door frames and make good

5 Toilet E2E.09 Fixing screws to frame protrude and are to be refixed to door

6 Toilet E2E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Toilet E2E.09 Screw missing to lock plate on door

Page 175: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 175/407

8 Toilet E2E.09 Remove all remaining parts of protective covering to door

9 Toilet E2E.09 Install rubber seal around door

10 Toilet E2E.09 Generally clean off excess grouting on wall tiles

11 Toilet E2E.09 Clean grout on floor tiles generally

12 Toilet E2E.09 Install missing chromium insert to overflow to WHB

13 Toilet E2E.09 Remove paint on mirror and make good

14 Toilet E2E.09 WHB tap is loose and to be reset properly

15 Toilet E2E.09 Install plug

16 Toilet E2E.09 No hot water available

17 Toilet E2E.09 Replace door grill screws (Internal) with white headed screws

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E2E.10 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E2E.10 Clean excess grouting to tiles generally

3 Handicapped Toilet E2E.10 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E2E.10 Tidy up floor at LH Base Frame of door

5 Handicapped Toilet E2E.10 Remove paint on door frames and make good

6 Handicapped Toilet E2E.10 Fixing screws to frame protrude and are to be refixed to door

7 Handicapped Toilet E2E.10 Cover four (4) protruding screw ends in angle plate to top corner to door

Page 176: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 176/407

8 Handicapped Toilet E2E.10 Screw missing to lock plate on door

9 Handicapped Toilet E2E.10 Remove all remaining parts of protective covering to door

10 Handicapped Toilet E2E.10 Clean fan outlet in ceiling of dirt/dust etc.

11 Handicapped Toilet E2E.10 WHB tap is loose and to be reset properly

12 Handicapped Toilet E2E.10 Make good joint between wall tiling and floor tiling on West wall

13 Handicapped Toilet E2E.10 Install plug

14 Handicapped Toilet E2E.10 Install missing chromium insert to overflow to WHB

15 Handicapped Toilet E2E.10 Install Door stop

16 Handicapped Toilet E2E.10 Install rubber seal around door

17 Handicapped Toilet E2E.10 Replace door grill screws (Internal) with white headed screws

18 Handicapped Toilet E2E.10 No hot water available

19 Handicapped Toilet E2E.10 Install rubber seal around door

20 Handicapped Toilet E2E.10 Clean out at bases to door frames and make good to floor finish

Page 177: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 177/407

Page 178: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 178/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E2E.13 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system2 Vestibule E2E.13 Skirting loose on North Wall

3 Vestibule E2E.13 Replace missing external corner piece to LH of door to Data Room

4 Vestibule E2E.13 Replace missing external corner piece to RH of door to Data Room

5 Vestibule E2E.13 Replace missing internal corner piece to LH of door to Electrical Closet

6 Vestibule E2E.13 Floor at entry to Main Vestibule requires to be levelled and floor covering resealed

7 Vestibule E2E.13 Edging strip required at door to main vestibule for joint between tiles floor and PVC Floor covering

Page 179: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 179/407

8 Vestibule E2E.13 Clean light of dirt and paint stains

9 Vestibule E2E.13 Frames of door to Main Vestibule are set some 10mm above floor finish and require to be reset

10 Vestibule E2E.13 Remove paint on door frames and make good

11 Vestibule E2E.13 Fixing screws to frame protrude and are to be refixed to door

12 Vestibule E2E.13 Cover four (4) protruding screw ends in angle plate to top corner to door

13 Vestibule E2E.13 Screw missing to lock plate on door

14 Vestibule E2E.13 Remove all remaining parts of protective covering to door

15 Vestibule E2E.13 Install rubber seal around door

16 Vestibule E2E.13 Install door stop

17 Vestibule E2E.13 Remove labels on door and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Data Room E2E.15 Paint ceiling2 Data Room E2E.15 Paint wall including columns and beams

3 Data Room E2E.15 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

4 Data Room E2E.15 Seal hole in South wall and make good

5 Data Room E2E.15 Seal around conduit pipe in South wall and make good

6 Data Room E2E.15 Frames of door to Main Vestibule are set some 10mm above floor finish and require to be reset

7 Data Room E2E.15 Remove paint on door frames and make good

8 D t R E2E 15 Fi i t f t d d t b fi d t d

Page 180: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 180/407

8 Data Room E2E.15 Fixing screws to frame protrude and are to be refixed to door

9 Data Room E2E.15 Cover four (4) protruding screw ends in angle plate to top corner to door

10 Data Room E2E.15 Screw missing to lock plate on door

11 Data Room E2E.15 Remove all remaining parts of protective covering to door

12 Data Room E2E.15 Install rubber seal around door

13 Data Room E2E.15 Install door stop

14 Data Room E2E.15 Provide threshold plate to door

15 Data Room E2E.15 Complete conduit to smoke detector

16 Data Room E2E.15 Seal North wall to two (2) HVAC pipes and make good all round

17 Data Room E2E.15 Make good joint between plasterboard wall finish and column on RH side of North wall

18 Data Room E2E.15 Seal to conduit on East wall and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E2E.14 Paint ceiling2 Electrical Closet E2E.14 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

3 Electrical Closet E2E.14 Make good to all ingoing of wall around door to frames and head

4 Electrical Closet E2E.14 Complete plasterboard wall lining on East wall

5 Electrical Closet E2E.14 Remove fixing wire set in wall (East) and make good

6 Electrical Closet E2E.14 Make good to floor level on South Wall near door and refix floor covering

7 Electrical Closet E2E.14 Skirting on South wall is not complete

8 El t i l Cl t E2E 14 R l i i t l i t RH f d t V tib l

Page 181: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 181/407

8 Electrical Closet E2E.14 Replace missing external corner piece to RH of door to Vestibule

9 Electrical Closet E2E.14 Infill large hole in southeast of room from which Level 1 is very visible

10 Electrical Closet E2E.14 Infill large hole on East Wall from which Level 1 is very visible

11 Electrical Closet E2E.14 Refix loose skirting on East wall

12 Electrical Closet E2E.14 Make good to north wall next floor sinking and refix floor covering complete

13 Electrical Closet E2E.14 Skirting missing at North wall

14 Electrical Closet E2E.14 Remove paint to Door Frames

15 Electrical Closet E2E.14 Fit rubber seal all round door

16 Electrical Closet E2E.14 Intumescent strip is not complete to both frame bases of door

17 Electrical Closet E2E.14 Fixing screws to frame protrude and are to be refixed to door

18 Electrical Closet E2E.14 Cover four (4) protruding screw ends in angle plate to top corner to Door South19 Electrical Closet E2E.14 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

20 Electrical Closet E2E.14 Install door stop to door

21 Electrical Closet E2E.14 Remove remaining protective covering to Door South

22 Electrical Closet E2E.14 Install fire/smoke seal threshold plate to Door South

23 Electrical Closet E2E.14 Screw missing in lock plate to door South

24 Electrical Closet E2E.14 Tidy up door intruder alarm contact wiring

25 Electrical Closet E2E.14 Install door closer

26 Electrical Closet E2E.14 Realign intruder alarm door contacts

27 Electrical Closet E2E.14 Door sign

28 Electrical Closet E2E.14 Frame bases of door are set 15 to 25mm above floor finish and require to be reset properly

29 Electrical Closet E2E.14 Make good to taped jointed wire to Smoke Detector

30 Electrical Closet E2E.14 Make good to three (3) taped jointed wires in cable trays at ceiling level

31 Electrical Closet E2E 14 Fit sealing screws to five (5) control boxes

Page 182: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 182/407

Page 183: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 183/407

Page 184: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 184/407

Page 185: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 185/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Terrace : South Finish terrace slabs to Area A23 approx 3/4m22 Terrace : South Make good to metal plate/slab level at Area A22 where metal plate is 15.20mm above and is untidy at corner

3 Terrace : South Generally remove mortar stains on window profiles and glass along South Façade A13 to A21

4 Terrace : South Seal and make good joint between terrace paving and base profile to windows along South Façade A13 to A 21

5 Terrace : South Many of the base profile plates to the parapet façade are not level and there are level discrepancies with the terrace paving

6 Terrace : South Seal & make good joint between terrace paving and parapet base profiles including replacing ill cut paviors from A13 to A23

7 Terrace : South Make good seal at top of parapet façade at A13

8 Terrace : South Remove mortar and cement splashes etc. on the base profile to the parapet façade from A13 to A23

Page 186: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 186/407

p p p p ç

9 Terrace : South Make good joint between base parapet façade profile and paviors at A13

10 Terrace : South Remove all mortar/concrete deposits on base profile junction with vertical profiles (7 No.) and make good

11 Terrace : South Remove remaining parts of profile protective covering to base profile of windows to Westfourth/Euroest on South Façade

12 Terrace : East Generally remove mortar stains on window profiles and glass along East Façade A/D 20/21

13 Terrace : East Seal and make good joint between terrace paviors and base profile to windows along East Façade A/D 20/21

14 Terrace : East Remove remaining parts of profile protective covering to base profile of windows to Euroest on East Façade

15 Terrace : East Repair damage to Boiler Flue pipes (damage done in 2005)

16 Terrace : East Remove two (2) badly cut paviors next to Façade Glazing on East Façade

17 Terrace : East Seal & make good joint between terrace paving and parapet base profiles including replacing ill cut paviors A/D 20/21

18 Terrace : East Make good to broken pavior and replace near C 21

19 Terrace : North Finish terrace slabs to Area D 15/16 approx 10/12m2

20 Terrace : North Generally remove mortar stains on window profiles and glass along North Façade D 15/21

21 Terrace : North Seal and make good joint between terrace paviors and base profile to windows along North Façade D 15/21

22 Terrace : North Remove remaining parts of profile protective covering to base profile of windows to Nippon/Euroest on North Façade D 15/21

23 Terrace : North Replace two (2) badly chipped tile paviors on North Façade

24 Terrace : North Remove concrete snots on paviors

25 Terrace : North Seal & make good joint between terrace paving and parapet base profiles including replacing ill cut paviors D 15/21

26 Terrace : Generally Plastic spacers some are left in and some have been removed which is the correct position ?

27 Terrace : Generally Water is gathering at A23 area of terrace and there is no gulley in the area28 Terrace : Generally Remove mortar stains on inner face of parapet to North Terrace

29 Terrace : Generally Remove mortar stains on inner face of parapet to East Terrace

AMERICA HOUSE

Ref. Location Defect R

No. Cl

1 Westfourth Area E2E.02B Refix internal door pull properly to Door No 2 to terrace which came off at the base when opening the door

2 Westfourth Area E2E.02B Remove remaining protective covering to profiles to LH side of Door No 2

Page 187: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 187/407

Page 188: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 188/407

Page 189: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 189/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 3 Lift Lobby E3E.01 Tiling to floor is uneven and not aligned and requires to be re-executed2 Level 3 Lif t Lobby E3E.01 Wall Tiling to West Wall is debonding, uneven, not aligned, pointing is distressed and requires to be re-executed

3 Level 3 Lif t Lobby E3E.01 Wall Tiling to East (Lif t) Wall is uneven, not aligned, pointing is distressed and requires to be re-executed

4 Level 3 Lift Lobby E3E.01 Remove paint on loudspeaker in ceiling and make good

5 Level 3 Lif t Lobby E3E.01 Readjust two (2) small downlighters (North and South) that are not properly aligned and make good

6 Level 3 Lift Lobby E3E.01 Remove paint on ventilation grille large (South)

7 Level 3 Lift Lobby E3E.01 Seal pointing between tiling and lift panelling to PE 09 at head both sides

8 Level 3 Lift Lobby E3E.01 Seal pointing between tiling and lift panelling to PE 08 at head both sides

Page 190: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 190/407

9 Level 3 Lift Lobby E3E.01 Seal pointing between tiling and lift panelling to PE 07 at head both sides

10 Level 3 Lift Lobby E3E.01 Refit stainless steel skirting to Lift PE 09 that show gaps between the skirting and wall panelling both sides

11 Level 3 Lift Lobby E3E.01 Refit stainless steel skirting to Lift PE 08 that show gaps between the skirting and wall panelling both sides

12 Level 3 Lift Lobby E3E.01 Refit stainless steel skirting to Lift PE 07 that show gaps between the skirting and wall panelling both sides

13 Level 3 Lift Lobby E3E.01 Clean threshold of Lift PE 09

14 Level 3 Lift Lobby E3E.01 Clean threshold of Lift PE 08

15 Level 3 Lift Lobby E3E.01 Clean threshold of Lift PE 07

16 Level 3 Lift Lobby E3E.01 Make good to floor covering at RH of lift door frame PE7

17 Level 3 Lift Lobby E3E.01 Make good to floor covering at LH of lift door frame PE7

18 Level 3 Lift Lobby E3E.01 Make good to floor covering at RH of lift door frame PE8

19 Level 3 Lift Lobby E3E.01 Make good to floor covering at LH of lift door frame PE8

20 Level 3 Lift Lobby E3E.01 Make good to floor covering at RH of lift door frame PE9

21 Level 3 Lift Lobby E3E.01 Make good to floor covering at LH of lift door frame PE9

22 Level 3 Lift Lobby E3E.01 Clean all stainless steel skirting to lifts PE07 and PE08

23 Level 3 Lift Lobby E3E.01 Make good pointing between wall tiling and lift panels to LH side of Lift PE09

24 Level 3 Lift Lobby E3E.01 Make good pointing between wall tiling and lift panels to RH side of Lift PE09

25 Level 3 Lift Lobby E3E.01 Make good pointing between wall tiling and lift panels to LH side of Lift PE08

26 Level 3 Lift Lobby E3E.01 Make good pointing between wall tiling and lift panels to LH side of Lift PE07

27 Level 3 Lift Lobby E3E.01 Make good pointing between wall tiling and lift panels to RH side of Lift PE0728 Level 3 Lift Lobby E3E.01 Remove protective covering to lift door frame head LH of Lift PE07

29 Level 3 Lift Lobby E3E.01 Clean stainless steel panel near ceiling on Lift PE09

30 Level 3 Lift Lobby E3E.01 Clean stainless steel panel near ceiling on Lift PE08

31 Level 3 Lift Lobby E3E 01 Clean stainless steel panel near ceiling on Lift PE07

Page 191: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 191/407

AMERICA HOUSE

Ref. Location Defect Ra

No. Cla

1 Corridor Level 3 East (E3E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory B

2 Corridor Level 3 East (E3E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory B

Page 192: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 192/407

Page 193: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 193/407

Page 194: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 194/407

Page 195: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 195/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule E3E 03 Fix lock and handles to door North

35 Stair Vestibule E3E 03 Make good to floor at North and extend terrazzo floor tiling up to door threshold

36 Stair Vestibule E3E 03 North door frames are 6mm above the finished floor level and to be reset

37 Stair Vestibule E3E 03 Remove all remaining parts of protective covering to door

38 Stair Vestibule E3E 03 Remove paint to three (3) sprinkler head in ceiling

39 Stair Vestibule E3E 03 Make good round Fire Damper Grille panel (Upper)

40 Stair Vestibule E3E 03 Clean paint off grille to Fire Damper panel (Upper)

41 Stair Vestibule E3E 03 Provide proper locking device to Upper Fire Damper Grille (Upper)

42 Stair Vestibule E3E 03 Make good round Fire Damper Grille panel (Lower)

Page 196: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 196/407

43 Stair Vestibule E3E 03 Clean paint off grille to Fire Damper panel (Lower)44 Stair Vestibule E3E 03 Provide proper locking device to Upper Fire Damper Grille (Lower)

45 Stair Vestibule E3E 03 Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

46 Stair Vestibule E3E 03 Seal internal around Dry Riser Access Panel and make good

47 Stair Vestibule E3E 03 Make good to skirting to RH of Door North

48 Stair Vestibule E3E 03 Reset H sign above Dry Riser box to be level and make good

49 Stair Vestibule E3E 03 Remove timber batten in Dry Riser box that is obstructing the efficient usage of the Type C Hose Connection

50 Stair Vestibule E3E 03 Terrazzo Skirting is irregular on East Wall and requires to be redone

51 Stair Vestibule E3E 03 terrazzo Skirting is irregular on West Wall and requires to be redone

52 Stair Vestibule E3E 03 Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

Page 197: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 197/407

Page 198: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 198/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule E3E.16 Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

35 Stair Vestibule E3E.16 Seal internal around Dry Riser Access Panel and make good

36 Stair Vestibule E3E.16 Reset H sign above Dry Riser box to be level and make good

37 Stair Vestibule E3E.16 Remove all remaining parts of protective covering to door

38 Stair Vestibule E3E.16 Remove masking tape and paint to three (3) sprinkler head in ceiling

39 Stair Vestibule E3E.16 Make good round Fire Damper Grille panel (Upper)

40 Stair Vestibule E3E.16 Clean paint off grille to Fire Damper panel (Upper)

41 Stair Vestibule E3E.16 Provide proper locking device to Upper Fire Damper Grille (Upper)

42 Stair Vestibule E3E.16 Make good round Fire Damper Grille panel (Lower)

Page 199: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 199/407

43 Stair Vestibule E3E.16 Clean paint off grille to Fire Damper panel (Lower)44 Stair Vestibule E3E.16 Provide proper locking device to Upper Fire Damper Grille (Lower)

45 Stair Vestibule E3E.16 Make good to skirting to LH of Door North

46 Stair Vestibule E3E.16 Make good to skirting to RH of Door South

47 Stair Vestibule E3E.16 Make good around Dry Riser Box with six (6) black screws and repaint

48 Stair Vestibule E3E.16 Make good to wall base to LH side of Door North

49 Stair Vestibule E3E.16 Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair E3E.17 Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair E3E.17 Reset Running Man Sign to be level

3 Egress Stair E3E.17 Remove paint from Access Car Reader and make good

4 Egress Stair E3E.17 Replace strikeplate to door as in distress and damaged

5 Egress Stair E3E.17 Tiled Level 3 floor requires to be polished and sealed and repaired where poor workmanship near divide wall to stair

6 Egress Stair E3E.17 Fixing screws to frame protrude and are to be refixed

7 Egress Stair E3E.17 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair E3E.17 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair E3E.17 Intumescent strip to open door jamb is short at base and to be replaced

Page 200: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 200/407

10 Egress Stair E3E.17 Intumescent strip to hinge door jamb is short at base and head and to be replaced11 Egress Stair E3E.17 Rubber infill strip to door is missing at head

12 Egress Stair E3E.17 Install door stop to Door

13 Egress Stair E3E.17 Screw missing at lock plate on door

14 Egress Stair E3E.17 Remove paint on door frames and make good

15 Egress Stair E3E.17 Fire/Smoke seal threshold required to entry door

16 Egress Stair E3E.17 Door signage

17 Egress Stair E3E.17 Door intruder alarm contacts to be aligned

18 Egress Stair E3E.17 Remove paint etc from door frames to door

19 Egress Stair E3E.17 Remove all remaining protective covering to door

20 Egress Stair E3E.17 Tidy up contact wires to Intruder Alarm at door head

21 Egress Stair E3E.17 Door frames are set 11mm above the finished floor level and require to be reset

22 Egress Stair E3E.17 Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

23 Egress Stair E3E.17 Reset mid Landing light fitting level

24 Egress Stair E3E.17 Make good to open stair stringer to upper stair flight

25 Egress Stair E3E.17 Make good to open stair stringer to lower stair flight

26 Egress Stair E3E.17 Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

27 Egress Stair E3E.17 Clean two (2) stair flights between Levels 3 and 4 of black paint and mortar stains complete28 Egress Stair E3E.17 Replace four (4) chipped stairs to upper flight 3/4

29 Egress Stair E3E.17 Replace two (2) chipped stairs to lower flight 3/4

30 Egress Stair E3E.17 Wall light switch to be reset level

31 Egress Stair E3E 17 Make good to ceiling around smoke detector and repaint

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E3E.05 Remove paint to sprinkler head (south)

2 Vestibule E3E.05 Clean up stains on ceiling loudspeaker

3 Vestibule E3E.05 Remove paint on loudspeaker in ceiling and make good

4 Vestibule E3E.05 Remove paint to South Door Frames

5 Vestibule E3E.05 Fit rubber seal all round door South

6 Vestibule E3E.05 Intumnescent strip is not installed to side or head frames

7 Vestibule E3E.05 Fixing screws to frame protrude and are to be refixed to Door South

8 Vestibule E3E.05 Cover four (4) protruding screw ends in angle plate to top corner to Door South

9 Vestibule E3E.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

Page 201: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 201/407

10 Vestibule E3E.05 Install door stop to Door South11 Vestibule E3E.05 Remove remaining protective covering to Door South

12 Vestibule E3E.05 Install fire/smoke seal threshold plate to Door South

13 Vestibule E3E.05 Screw missing in lock plate to door South

14 Vestibule E3E.05 Install door closer to Door South

15 Vestibule E3E.05 Install edging and recut floor covering to door South threshold

16 Vestibule E3E.05 Clean paint off door frame to Door North

17 Vestibule E3E.05 Intumescent strip is installed to side or head frames of Door North

18 Vestibule E3E.05 Fixing screws to frame protrude and are to be refixed to Door North

19 Vestibule E3E.05 Cover four (4) protruding screw ends in angle plate to top corner to Door North

20 Vestibule E3E.05 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Vestibule E3E.05 Install door stop to Door North

22 Vestibule E3E.05 Fit rubber seal all round door North

23 Vestibule E3E.05 Fire/Smoke Threshold seal is required to door North

24 Vestibule E3E.05 Install door closer to Door North

25 Vestibule E3E.05 Remove all remaining parts of protective covering to door

26 Vestibule E3E.05 Screw missing in lock plate to door North

27 Vestibule E3E.05 Remove paint to light fitting (north) and make good

28 Vestibule E3E.05 Replace missing external skirting corner piece to LH of Door to Toilet E3E.14

29 Vestibule E3E.05 Replace missing external skirting corner piece to LH of Door to Toilet E3E.11

30 Vestibule E3E.05 Replace missing external skirting corner piece to RH of Door to Toilet E3E.11

31 Vestibule E3E 05 Remove paint on skirting to LH side of Door North

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E3E.15 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E3E.15 Clean excess grouting to tiles generally

3 Handicapped Toilet E3E.15 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E3E.15 Make good to floor finish at LH Base Frame of door

5 Handicapped Toilet E3E.15 Make good to floor finish at RH Base Frame of door

6 Handicapped Toilet E3E.15 Remove paint on door frames and make good

7 Handicapped Toilet E3E.15 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E3E.15 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E3E.15 Screw missing to lock plate on door

Page 202: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 202/407

10 Handicapped Toilet E3E.15 Remove all remaining parts of protective covering to door11 Handicapped Toilet E3E.15 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E3E.15 WHB tap is loose and to be reset properly

13 Handicapped Toilet E3E.15 Install plug

14 Handicapped Toilet E3E.15 Overhaul flush to WC as not working properly

15 Handicapped Toilet E3E.15 Install Door stop

16 Handicapped Toilet E3E.15 Install rubber seal around door

17 Handicapped Toilet E3E.15 Replace external grille at door base external as broken

18 Handicapped Toilet E3E.15 No hot water available

19 Handicapped Toilet E3E.15 Install rubber seal around door

20 Handicapped Toilet E3E.15 Clean out at bases to door frames and make good to floor finish

21 Handicapped Toilet E3E.15 Light bulb missing in downlighter and to be replaced

22 Handicapped Toilet E3E.15 Compete activity related to open hole in ceiling with unconnected wires etc.

23 Handicapped Toilet E3E.15 Reconnect open wires or remove from ceiling space

24 Handicapped Toilet E3E.15 Remove masking tape from downlighter in ceiling

25 Handicapped Toilet E3E.15 Repair upper hinge to door that has 'dropped' and make good

26 Handicapped Toilet E3E.15 Install edging strip to PVC floor covering where it abuts the floor tiles in the toilet

27 Handicapped Toilet E3E.15 Wall tiling to be redone on southeast corner of wall near door

28 Handicapped Toilet E3E.15 Remove black screw in South wall and make good

29 Handicapped Toilet E3E.15 Clean general dirt etc in floor pointing and make good

30 Handicapped Toilet E3E.15 Repoint to wall tiling where short or insufficient

31 Handicapped Toilet E3E.15 Remove excess grout on wall tiling

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E3E.14 Make good tile grouting etc around floor gulley

2 Toilet E3E.14 Make good to RH door frame (open) where dented at lock strike plate

3 Toilet E3E.14 Install door stop

4 Toilet E3E.14 Remove paint on door frames and make good

5 Toilet E3E.14 Fixing screws to frame protrude and are to be refixed to door

6 Toilet E3E.14 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Toilet E3E.14 Screw missing to lock plate on door

8 Toilet E3E.14 Remove all remaining parts of protective covering to door

9 Toilet E3E.14 Install rubber seal around door

10 T il t E3E 14 T h hi d i t k t d f

Page 203: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 203/407

10 Toilet E3E.14 Touch up chipped paintwork to door frames11 Toilet E3E.14 Replace door grill screws (Internal) with white headed screws

12 Toilet E3E.14 Generally clean off excess grouting on wall tiles

13 Toilet E3E.14 Clean grout on floor tiles generally

14 Toilet E3E.14 WHB tap is loose and to be reset properly

15 Toilet E3E.14 Install plug

16 Toilet E3E.14 No hot water available

17 Toilet E3E.14 Install edging strip to PVC floor covering where it abuts the ceramic tile floor finish in toilet

18 Toilet E3E.14 Make good to water leak stain to centre and edges of suspended ceiling and repaint

19 Toilet E3E.14 Light (2 No.) bulbs are missing and to be replaced

Page 204: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 204/407

Page 205: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 205/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E3E.11 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E3E.11 Clean excess grouting to tiles generally

3 Handicapped Toilet E3E.11 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E3E.11 Replace distressed strikeplate in open frame

5 Handicapped Toilet E3E.11 Touch up chipped paintwork to door frames

6 Handicapped Toilet E3E.11 Remove paint on door frames and make good

7 Handicapped Toilet E3E.11 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E3E.11 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E3E.11 Screw missing to lock plate on door

10 Handicapped Toilet E3E 11 Remove all remaining parts of protective covering to door

Page 206: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 206/407

10 Handicapped Toilet E3E.11 Remove all remaining parts of protective covering to door11 Handicapped Toilet E3E.11 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E3E.11 WHB tap is loose and to be reset properly

13 Handicapped Toilet E3E.11 Install plug

14 Handicapped Toilet E3E.11 No hot water available

15 Handicapped Toilet E3E.11 Install Door stop

16 Handicapped Toilet E3E.11 Install rubber seal around door

17 Handicapped Toilet E3E.11 Clean out at bases to door frames and make good to floor finish

18 Handicapped Toilet E3E.11 Light bulb missing in downlighter and to be replaced

19 Handicapped Toilet E3E.11 Compete activity related to open hole in ceiling or repair.

20 Handicapped Toilet E3E.11 Fit downlighter in ceiling properly

21 Handicapped Toilet E3E.11 Install edging strip to PVC floor covering where it abuts the floor tiles in the toilet

22 Handicapped Toilet E3E.11 Clean general dirt etc in floor pointing and make good

23 Handicapped Toilet E3E.11 Repoint to wall tiling where short or insufficient

24 Handicapped Toilet E3E.11 Remove excess grout on wall tiling

25 Handicapped Toilet E3E.11 Make good to edge of door damaged near lock plate

26 Handicapped Toilet E3E.11 Make good to joint between wall tiling and floor tiling at North wall

Page 207: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 207/407

Page 208: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 208/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E3E.08 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

2 Vestibule E3E.08 Skirting loose on North Wall at LH return to door to Data Room

3 Vestibule E3E.08 Make good to floor finishes at door frame bases

4 Vestibule E3E.08 Seal hole in hinge door frame at top or fix screw fixing

5 Vestibule E3E.08 Clean light of dirt and paint stains

6 Vestibule E3E.08 Touch up chipped paint on door frames

7 Vestibule E3E.08 Remove paint on door frames and make good

8 Vestibule E3E.08 Fixing screws to frame protrude and are to be refixed to door

9 Vestibule E3E.08 Cover four (4) protruding screw ends in angle plate to top corner to door

10 Vestibule E3E.08 Screw missing to lock plate on door

11 Vestibule E3E 08 Remove all remaining parts of protective covering to door

Page 209: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 209/407

11 Vestibule E3E.08 Remove all remaining parts of protective covering to door

12 Vestibule E3E.08 Install rubber seal around door

13 Vestibule E3E.08 Install door stop

14 Vestibule E3E.08 Remove labels on door and make good

Page 210: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 210/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E3E.09 Paint ceiling

2 Electrical Closet E3E.09 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

3 Electrical Closet E3E.09 Make good to floor level on South Wall near door and refix floor covering

4 Electrical Closet E3E.09 Install skirting to South Wall as missing

5 Electrical Closet E3E.09 Skirting missing at return on East Wall

6 Electrical Closet E3E.09 Skirting loose on northern side of East Wall

7 Electrical Closet E3E.09 Skirting is missing on West wall (North)

8 Electrical Closet E3E.09 Make good to north wall next floor sinking and refix floor covering complete

9 Electrical Closet E3E.09 Infill large hole in southeast of room (fire stopping) Hole at present is a safety issue

10 Electrical Closet E3E.09 Skirting missing at North wall11 Electrical Closet E3E 09 Skirting under Electrical Cabinet TUPS 3E on West wall is short and to be replaced

Page 211: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 211/407

11 Electrical Closet E3E.09 Skirting under Electrical Cabinet TUPS-3E on West wall is short and to be replaced

12 Electrical Closet E3E.09 Paint walls

13 Electrical Closet E3E.09 Connect up exposed wires in light switch and refix light switch plate near door RH side

14 Electrical Closet E3E.09 Remove paint to Door Frames

15 Electrical Closet E3E.09 Fit rubber seal all round door

16 Electrical Closet E3E.09 Intumescent strip is not complete to hinge frame at base of door and to be replaced

17 Electrical Closet E3E.09 Intumescent str ip is not complete to open frame at base and head of door and also loose to be replaced

18 Electrical Closet E3E.09 Fixing screws to frame protrude and are to be refixed to door

19 Electrical Closet E3E.09 Cover four (4) protruding screw ends in angle plate to top corner to Door South

20 Electrical Closet E3E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Electrical Closet E3E.09 Install door stop to door

22 Electrical Closet E3E.09 Remove remaining protective covering to Door South

23 Electrical Closet E3E.09 Install fire/smoke seal threshold plate to Door South

24 Electrical Closet E3E.09 Screw missing in lock plate to door South

25 Electrical Closet E3E.09 Door frames are 5mm above finished floor level and to be reset

26 Electrical Closet E3E.09 Install door closer

27 Electrical Closet E3E.09 Realign intruder alarm door contacts

28 Electrical Closet E3E.09 Door sign

29 Electrical Closet E3E.09 Make good to wall base at return to East wall in middle and repaint

30 Electrical Closet E3E.09 Electrical Cabinet TCT-31 replace damaged top panel cover internally

31 Electrical Closet E3E 09 Screw in the fifteen (15) loose screws to the five (5) control boxes to RH of SBS-7E

Page 212: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 212/407

Page 213: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 213/407

Page 214: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 214/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor North C14/18 (E4E.01) Remove paint on Fire Alarm LH of door to Stair Vestibule E4E.03

2 Corridor North C14/18 (E4E.01) Install operator signage to Fire Alarm Button at South Wall near door to Stair Vestibule E4E.03

3 Corridor North C14/18 (E4E.01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby

4 Corridor North C14/18 (E4E.01) Clean paint off grille to Fire Damper panel (Lower) near Lift Lobby

5 Corridor North C14/18 (E4E.01) Provide proper locking device to Low Fire Damper Grille on South Wall near Lift Lobby

6 Corridor North C14/18 (E4E.01) Tiling to wall at C17 South Wall is uneven, debonding, and not aligned and requires to be re-executed

7 Corridor North C14/18 (E4E.01) Tiling to wall at C16 South Wall is uneven, debonding and not aligned and requires to be re-executed

8 Corridor North C14/18 (E4E.01) Install operator signage to Fire Alarm Button at South Wall RH of Service Elevator Vestibule

9 Corridor North C14/18 (E4E.01) Install operator signage to Door Release Button at South Wall to RH of Service Elevator Vestibule

10 Corridor North C14/18 (E4E.01) Install break glass to Emergency Door Release Button on South Wall to RH of Service Elevator Vestibule

11 Corridor North C14/18 (E4E.01) Remove paint from Running Man Sign above door to Stair Vestibule E4E.16

Page 215: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 215/407

12 Corridor North C14/18 (E4E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby

13 Corridor North C14/18 (E4E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby

14 Corridor North C14/18 (E4E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on South Wall near Lift Lobby

15 Corridor North C14/18 (E4E.01) Make good round Fire Damper Grille panel (Low) on South Wall near to RH side of Service Elevator Lobby

16 Corridor North C14/18 (E4E.01) Clean paint off grille to Fire Damper panel (Lower) to RH side of Service Lift Lobby

17 Corridor North C14/18 (E4E.01) Provide proper locking device to Low Fire Damper Grille on South Wall to RH side of Service Lift Lobby

Page 216: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 216/407

Page 217: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 217/407

Page 218: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 218/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 4 (E4E.03) Remove paint to South Door Frames

2 Stair Vestibule Level 4 (E4E.03) Fit rubber seal all round door South

3 Stair Vestibule Level 4 (E4E.03) Intumescent strip is not complete to open frame and short at base and loose at top and near strike plate to Door South : replace

4 Stair Vestibule Level 4 (E4E.03) Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule Level 4 (E4E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule Level 4 (E4E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule Level 4 (E4E.03) Install door stop to Door South

8 Stair Vestibule Level 4 (E4E.03) Remove remaining protective covering to Door South

9 Stair Vestibule Level 4 (E4E.03) Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule Level 4 (E4E.03) Screw missing in lock plate to door South

11 Stair Vestibule Level 4 (E4E.03) Intumescent strip is not complete to hinge frame as short at base to Door South and to be replaced

12 Stair Vestib le Le el 4 (E4E 03) Int mescent strip on head frame is loose and to be refi ed properl of So th Door

Page 219: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 219/407

12 Stair Vestibule Level 4 (E4E.03) Intumescent strip on head frame is loose and to be refixed properly of South Door

13 Stair Vestibule Level 4 (E4E.03) Remove paint splashes etc on South door surfaces and make good

14 Stair Vestibule Level 4 (E4E.03) Install door closer to South Door

15 Stair Vestibule Level 4 (E4E.03) South door frames are 4mm above the finished floor level and to be reset

16 Stair Vestibule Level 4 (E4E.03) Remove labels on South Door and make good

17 Stair Vestibule Level 4 (E4E.03) Provide operation label to Door Push Button in Romanian and English

18 Stair Vestibule Level 4 (E4E.03) Finish render to wall to LH side of Door North

19 Stair Vestibule Level 4 (E4E.03) Remove paint from top edge of skirting on all walls20 Stair Vestibule Level 4 (E4E.03) North door frames are 6mm above the finished floor level and to be reset

21 Stair Vestibule Level 4 (E4E.03) Clean paint etc from two (2) light fittings

22 Stair Vestibule Level 4 (E4E.03) Clean paint off door frame to Door North

23 Stair Vestibule Level 4 (E4E.03) Clean paint splashes etc on surfaces of Door North

24 Stair Vestibule Level 4 (E4E.03) Intumescent strip is short to head frame and requires to be replaced

25 Stair Vestibule Level 4 (E4E.03) Intumescent strip is not complete to both frame bases of Door North

26 Stair Vestibule Level 4 (E4E.03) Fixing screws to frame protrude and are to be refixed to Door North

27 Stair Vestibule Level 4 (E4E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door North

28 Stair Vestibule Level 4 (E4E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

29 Stair Vestibule Level 4 (E4E.03) Install door stop to Door North

30 Stair Vestibule Level 4 (E4E.03) Fit rubber seal all round door North

31 Stair Vestibule Level 4 (E4E 03) Fire/Smoke Threshold seal is required to door North

Page 220: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 220/407

Page 221: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 221/407

Page 222: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 222/407

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 4 (E4E.16) Reset Door North that has broken out of its frame position and make good

35 Stair Vestibule Level 4 (E4E.16) Replace damaged strikeplate to open frame of Door North

36 Stair Vestibule Level 4 (E4E.16) Make good to hole to LH side of Door north and make good to floor finish complete

37 Stair Vestibule Level 4 (E4E.16) Remove all remaining parts of protective covering to door North

38 Stair Vestibule Level 4 (E4E.16) Remove paint to three (3) sprinkler head in ceiling and make good

39 Stair Vestibule Level 4 (E4E.16) Make good round Fire Damper Grille panel (Upper)

40 Stair Vestibule Level 4 (E4E.16) Clean paint off grille to Fire Damper panel (Upper)

41 Stair Vestibule Level 4 (E4E.16) Provide proper locking device to Upper Fire Damper Grille (Upper)

42 Stair Vestibule Level 4 (E4E.16) Make good round Fire Damper Grille panel (Lower)

43 Stair Vestibule Level 4 (E4E.16) Clean paint off grille to Fire Damper panel (Lower)

44 Stair Vestibule Level 4 (E4E.16) Provide proper locking device to Upper Fire Damper Grille (Lower)

45 Stair Vestibule Level 4 (E4E.16) Make good to skirting to LH of Door South

Page 223: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 223/407

46 Stair Vestibule Level 4 (E4E.16) Make good to skirting to RH of Door South

47 Stair Vestibule Level 4 (E4E.16) Make good to skirting to LH of Door North

48 Stair Vestibule Level 4 (E4E.16) Make good to skirting to RH of Door North

49 Stair Vestibule Level 4 (E4E.16) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

50 Stair Vestibule Level 4 (E4E.16) Remove paint from Running Man Sign and make good

51 Stair Vestibule Level 4 (E4E.16) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

52 Stair Vestibule Level 4 (E4E.16) Seal internally around Dry Riser Access Panel and make good53 Stair Vestibule Level 4 (E4E.16) Fill in gaps around Lower Fire Damper on West Wall and make good all round

54 Stair Vestibule Level 4 (E4E.16) Fill in gaps around Upper Fire Damper on West Wall and make good all round

Page 224: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 224/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule Level 4 (E4E.05) Remove paint to three sprinkler heads

2 Vestibule Level 4 (E4E.05) Make good to floor and finish at frames bases of Door North

3 Vestibule Level 4 (E4E.05) Remove paint to South Door Frames

4 Vestibule Level 4 (E4E.05) Fit rubber seal all round door South

5 Vestibule Level 4 (E4E.05) Intumnescent strip is not installed to side or head frames

6 Vestibule Level 4 (E4E.05) Fixing screws to frame protrude and are to be refixed to Door South

7 Vestibule Level 4 (E4E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door South

8 Vestibule Level 4 (E4E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Vestibule Level 4 (E4E.05) Install door stop to Door South

10 Vestibule Level 4 (E4E.05) Remove remaining protective covering to Door South

11 Vestibule Level 4 (E4E.05) Install fire/smoke seal threshold plate to Door South

12 Vestibule Level 4 (E4E.05) Screw missing in lock plate to door South

Page 225: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 225/407

13 Vestibule Level 4 (E4E.05) Install door closer to Door South

14 Vestibule Level 4 (E4E.05) Install edging and recut floor covering to door South threshold

15 Vestibule Level 4 (E4E.05) Clean paint off door frame to Door North

16 Vestibule Level 4 (E4E.05) Intumescent strip is installed to side or head frames of Door North

17 Vestibule Level 4 (E4E.05) Fixing screws to frame protrude and are to be refixed to Door North

18 Vestibule Level 4 (E4E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door North

19 Vestibule Level 4 (E4E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected 20 Vestibule Level 4 (E4E.05) Install door stop to Door North

21 Vestibule Level 4 (E4E.05) Fit rubber seal all round door North

22 Vestibule Level 4 (E4E.05) Fire/Smoke Threshold seal is required to door North

23 Vestibule Level 4 (E4E.05) Install door closer to Door North

24 Vestibule Level 4 (E4E.05) Remove all remaining parts of protective covering to door

25 Vestibule Level 4 (E4E.05) Screw missing in lock plate to door North

26 Vestibule Level 4 (E4E.05) Replace missing skirting to RH side of Door South

27 Vestibule Level 4 (E4E.05) Replace missing skirting to RH of Door to Handicapped Toilet E4E.15

28 Vestibule Level 4 (E4E.05) Replace missing external angle skirting corner piece and skirting to LH of Door to Handicapped Toilet E3E.15

29 Vestibule Level 4 (E4E.05) Replace missing external angle skirting corner piece and skirting to RH of Door to Handicapped Toilet E3E.15

30 Vestibule Level 4 (E4E.05) Replace missing skirting between Handicapped Toilet E4E.15 and Toilet E4E.14

31 Vestibule Level 4 (E4E 05) Replace missing external skirting corner angle piece to LH side of door to Toilet E4E 14

AMERICA HOUSE

Ref. Location Defect

No.

34 Vestibule Level 4 (E4E.05) Make good to missing floor covering to RH side of Door South

35 Vestibule Level 4 (E4E.05) Make good to hole in wall to RH side of Door to Handicapped Toilet E4E.11 and make good and repaint36 Vestibule Level 4 (E4E.05) Reset double socket outlet near Door South and make level

37 Vestibule Level 4 (E4E.05) Reset double socket outlet near Door North and make level

38 Vestibule Level 4 (E4E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E4E.11

39 Vestibule Level 4 (E4E.05) Install edging strip between PVC f loor covering and ti le f loor f inish to Toilet E4E.12

40 Vestibule Level 4 (E4E.05) Install edging strip between PVC f loor covering and ti le f loor f inish to Toilet E4E.13

41 Vestibule Level 4 (E4E.05) Install edging strip between PVC f loor covering and ti le f loor f inish to Toilet E4E.14

42 Vestibule Level 4 (E4E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E4E.15

43 Vestibule Level 4 (E4E.05) Refix all skirting as attached with panel pins with adhesive or clip-on system

Page 226: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 226/407

Page 227: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 227/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E4E.14 Make good the very poor tile grouting etc around floor gulley

2 Toilet E4E.14 Make good to base of RH door frames to floor finish 3 Toilet E4E.14 Make good to base of LH door frames to floor finish

4 Toilet E4E.14 Install door stop

5 Toilet E4E.14 Remove paint on door frames and make good

6 Toilet E4E.14 Fixing screws to frame protrude and are to be refixed to door

7 Toilet E4E.14 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Toilet E4E.14 Screw missing to lock plate on door

9 Toilet E4E.14 Remove all remaining parts of protective covering to door

10 Toilet E4E.14 Install rubber seal around door

11 Toilet E4E.14 Touch up chipped paintwork to door frames

12 Toilet E4E.14 Replace door grill screws (Internal) with white headed screws

13 Toilet E4E 14 Generally clean off excess grouting on wall tiles

Page 228: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 228/407

13 Toilet E4E.14 Generally clean off excess grouting on wall tiles

14 Toilet E4E.14 Clean grout on floor tiles generally

15 Toilet E4E.14 WHB tap is loose and to be reset properly

16 Toilet E4E.14 Install plug

17 Toilet E4E.14 Make good to joint between wall and floor tiling finish in northwestern corner

Page 229: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 229/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E4E.12 Make good tile grouting etc around floor gulley

2 Toilet E4E.12 Install door stop3 Toilet E4E.12 Remove paint on door frames and make good

4 Toilet E4E.12 Fixing screws to frame protrude and are to be refixed to door

5 Toilet E4E.12 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E4E.12 Screw missing to lock plate on door

7 Toilet E4E.12 Remove all remaining parts of protective covering to door

8 Toilet E4E.12 Install rubber seal around door

9 Toilet E4E.12 Touch up chipped paintwork to door frames

10 Toilet E4E.12 Replace door grill screws (Internal) with white headed screws

11 Toilet E4E.12 Generally clean off excess grouting on wall tiles

12 Toilet E4E.12 Clean grout on floor tiles generally

13 Toilet E4E.12 WHB tap is loose and to be reset properly

Page 230: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 230/407

p p p y

14 Toilet E4E.12 Install plug

15 Toilet E4E.12 Clean out at bases of door frames and make good floor finished complete

16 Toilet E4E.12 Repoint to wall tiling to LH side of door frame for the full length

17 Toilet E4E.12 Repoint wall tiling above hand towel dispenser

18 Toilet E4E.12 Adjust door as it squeaks

19 Toilet E4E.12 Make good at joint between wall tiling and floor tiling on North wall

20 Toilet E4E.12 Make good at joint between wall tiling and floor tiling on West wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E4E.11 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E4E.11 Clean excess grouting to tiles generally3 Handicapped Toilet E4E.11 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E4E.11 Repoint to LH side of door frame

5 Handicapped Toilet E4E.11 Touch up chipped paintwork to door frames

6 Handicapped Toilet E4E.11 Remove paint on door frames and make good

7 Handicapped Toilet E4E.11 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E4E.11 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E4E.11 Screw missing to lock plate on door

10 Handicapped Toilet E4E.11 Remove all remaining parts of protective covering to door

11 Handicapped Toilet E4E.11 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E4E.11 WHB tap is loose and to be reset properly

13 Handicapped Toilet E4E.11 Install plug

Page 231: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 231/407

pp p g

14 Handicapped Toilet E4E.11 Replace defective collar seal to WHB tap

15 Handicapped Toilet E4E.11 Install Door stop

16 Handicapped Toilet E4E.11 Install rubber seal around door

17 Handicapped Toilet E4E.11 Clean out at bases to door frames and make good to floor finish

18 Handicapped Toilet E4E.11 Clean general dirt etc in floor pointing and make good

19 Handicapped Toilet E4E.11 Repoint to wall tiling where short or insufficient

20 Handicapped Toilet E4E.11 Make good to joint between wall tiling and floor tiling at North wall

21 Handicapped Toilet E4E.11 Make good to joint between wall tiling and floor tiling at South wall

22 Handicapped Toilet E4E.11 Make good to joint between wall tiling and floor tiling at West wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Elevator Vestibule (E4E.18) Prepare for and paint ceiling

2 Service Elevator Vestibule (E4E.18) Remove paint on Access Card Reader 3 Service Elevator Vestibule (E4E.18) Remove paint stains on floor covering generally

4 Service Elevator Vestibule (E4E.18) Fill in hole to door head frame

5 Service Elevator Vestibule (E4E.18) Remove paint splashes etc on doors

6 Service Elevator Vestibule (E4E.18) Fixing screws to frame protrude and are to be refixed to Door

7 Service Elevator Vestibule (E4E.18) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Service Elevator Vestibule (E4E.18) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestibule (E4E.18) Intumescent strip is short on both side frames and requires to be replaced

10 Service Elevator Vestibule (E4E.18) Install door stops to Doors

11 Service Elevator Vestibule (E4E.18) Clean paint off Door Frames

12 Service Elevator Vestibule (E4E.18) Door Signage

13 Service Elevator Vestibule (E4E.18) Fire/Smoke Threshold seal is required to door

Page 232: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 232/407

( ) q

14 Service Elevator Vestibule (E4E.18) Install closers with selector on doors

15 Service Elevator Vestibule (E4E.18) Remove all remaining parts of the protective covering to doors

16 Service Elevator Vestibule (E4E.18) Install rubber seal to door

17 Service Elevator Vestibule (E4E.18) Intumescent strip to meeting style is not continuous and missing at door lock

18 Service Elevator Vestibule (E4E.18) Realign door intruder alarm contacts and fix head frame contact which is loose

19 Service Elevator Vestibule (E4E.18) Inner leaf of door has too much play when closed and to be adjusted

20 Service Elevator Vestibule (E4E.18) Tidy up wiring to door intruder contact

21 Service Elevator Vestibule (E4E.18) Screw missing form door locking plate

22 Service Elevator Vestibule (E4E.18) Intumescent strip is short at the prong receiver on the RH door frame

23 Service Elevator Vestibule (E4E.18) Touch up to damaged paintwork to door frames generally

24 Service Elevator Vestibule (E4E.18) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

25 Service Elevator Vestibule (E4E.18) Relay floor covering that is distorted and 'bubbled' and prepare floor screed below

26 Service Elevator Vestibule (E4E.18) Replace missing skirting and external angle corner piece to LH side of lift entrance return

27 Service Elevator Vestibule (E4E.18) Replace missing skirting and external angle corner piece to RH side of lift entrance return

28 Service Elevator Vestibule (E4E.18) Replace missing skirting to RH of Lift entrance 29 Service Elevator Vestibule (E4E.18) Paint sprinkler pipework

30 Service Elevator Vestibule (E4E.18) Tidy up joint at sprinkler head and elbow joints including removing excess joint hemp fibres on sprinkler pipework

31 Service Elevator Vestibule (E4E 18) Replace screws at grille to LH side with white headed screws as elsewhere

AMERICA HOUSE

Ref. Location Defect

No.

34 Service Elevator Vestibule (E4E.18) Seal and make good to one (1) sprinkler pipe in northeast corner at near ceiling level

35 Service Elevator Vestibule (E4E.18) Replace broken skirting on West Wall

36 Service Elevator Vestibule (E4E.18) Remove remaining parts of protective covering to Lift frames

37 Service Elevator Vestibule (E4E.18) Clean off paint splashes on Lift Door and frames

38 Service Elevator Vestibule (E4E.18) Make good to floor finishes etc at base of LH frame of door

39 Service Elevator Vestibule (E4E.18) Make good to floor finishes etc at base of RH frame of door and fill in sinking to screed

40 Service Elevator Vestibule (E4E.18) Complete conduit to ceiling smoke detector

41 Service Elevator Vestibule (E4E.18) Remove red paint stain on North Wall

Page 233: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 233/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E4E.08 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

2 Vestibule E4E.08 Skirting loose on North Wall at LH return to door to Data Room

3 Vestibule E4E.08 Make good to floor finishes at door frame bases

4 Vestibule E4E.08 Reset light switch plate to level position

5 Vestibule E4E.08 Clean light of dirt and paint stains

6 Vestibule E4E.08 Touch up chipped paint on door frames

7 Vestibule E4E.08 Remove paint on door frames and make good

8 Vestibule E4E.08 Fixing screws to frame protrude and are to be refixed to door

9 Vestibule E4E.08 Cover four (4) protruding screw ends in angle plate to top corner to door

10 Vestibule E4E.08 Screw missing to lock plate on door

11 Vestibule E4E.08 Remove all remaining parts of protective covering to door12 Vestibule E4E.08 Install rubber seal around door

13 Vestibule E4E.08 Install door stop

Page 234: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 234/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Data Room E4E.10 Remove paint on door frames and make good

2 Data Room E4E.10 Fixing screws to frame protrude and are to be refixed to door

3 Data Room E4E.10 Cover four (4) protruding screw ends in angle plate to top corner to door

4 Data Room E4E.10 Screw missing to lock plate on door

5 Data Room E4E.10 Remove all remaining parts of protective covering to door

6 Data Room E4E.10 Install rubber seal around door

7 Data Room E4E.10 Install door stop

8 Data Room E4E.10 Seal North wall to two (2) HVAC pipes and make good all round

Page 235: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 235/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E4E.09 Paint ceiling

2 Electrical Closet E4E.09 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system3 Electrical Closet E4E.09 Make good to floor level on South Wall near door and refix floor covering

4 Electrical Closet E4E.09 Install skirting to South Wall as missing

5 Electrical Closet E4E.09 Skirting missing at return on East Wall

6 Electrical Closet E4E.09 Skirting loose on northern side of East Wall

7 Electrical Closet E4E.09 Skirting is missing on West wall (North)

8 Electrical Closet E4E.09 Make good to north wall next floor sinking and refix floor covering complete

9 Electrical Closet E4E.09 Infill large hole in southeast of room (fire stopping) Hole at present is a safety issue

10 Electrical Closet E4E.09 Skirting missing at North wall

11 Electrical Closet E4E.09 Skirting under Electrical Cabinet TUPS-3E on West wall is short and to be replaced

12 Electrical Closet E4E.09 Paint walls

13 Electrical Closet E4E.09 Make good to door plasterboard ingoings to both door frames and head frame

Page 236: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 236/407

14 Electrical Closet E4E.09 Remove paint to Door Frames

15 Electrical Closet E4E.09 Fit rubber seal all round door

16 Electrical Closet E4E.09 Intumescent strip is short to hinge frame at base of door and to be replaced

17 Electrical Closet E4E.09 Intumescent strip is short to open frame at base and to be replaced

18 Electrical Closet E4E.09 Fixing screws to frame protrude and are to be refixed to door

19 Electrical Closet E4E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

20 Electrical Closet E4E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Electrical Closet E4E.09 Install door stop to door

22 Electrical Closet E4E.09 Remove remaining protective covering to door

23 Electrical Closet E4E.09 Install fire/smoke seal threshold plate to door

24 Electrical Closet E4E.09 Screw missing in lock plate to door

25 Electrical Closet E4E.09 Door frames are 5mm above finished floor level and to be reset

26 Electrical Closet E4E.09 Install door closer

27 Electrical Closet E4E.09 Realign intruder alarm door contacts

28 Electrical Closet E4E.09 Door sign29 Electrical Closet E4E.09 Make good to wall base at return to East wall in middle and repaint

30 Electrical Closet E4E.09 Replace missing skirting to LH side of door

31 Electrical Closet E4E 09 Screw in the twenty (20) missing screws to the five (5) control boxes to RH of SBS-7E

AMERICA HOUSE

Ref. Location Defect

No.

1 Janitor Closet E4E.07 Install protection to water pipe with meter

2 Janitor Closet E4E.07 Replace door grill screws (Internal) with white headed screws3 Janitor Closet E4E.07 Fixing screws to frame protrude and are to be refixed to door

4 Janitor Closet E4E.07 Cover four (4) protruding screw ends in angle plate to top corner to door

5 Janitor Closet E4E.07 Remove all remaining parts of protective covering to door

6 Janitor Closet E4E.07 Remove paint on door frames and make good

7 Janitor Closet E4E.07 Remove wall paint on trims to suspended ceilings and make good

8 Janitor Closet E4E.07 Redo angle edge to vertical corner to LH of door and make good

9 Janitor Closet E4E.07 Redo angle edge to vertical corner southeast and make good

10 Janitor Closet E4E.07 Make good to joint between wall and floor tiling on South Wall

11 Janitor Closet E4E.07 Make good to joint between wall and floor tiling on West Wall12 Janitor Closet E4E.07 Make good ceiling trim at Column B16

13 Janitor Closet E4E.07 Install trough

14 Janitor Closet E4E 07 LH tap in wall is loose and requires to be fixed properly

Page 237: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 237/407

14 Janitor Closet E4E.07 LH tap in wall is loose and requires to be fixed properly

15 Janitor Closet E4E.07 Tidy up loose layout of pipework connected with boiler

16 Janitor Closet E4E.07 RH tap in wall is loose and requires to be fixed properly

17 Janitor Closet E4E.07 Make good untidy suspended ceiling around Column B16

18 Janitor Closet E4E.07 Make good grouting etc to floor gulley

19 Janitor Closet E4E.07 Install door stop

20 Janitor Closet E4E.07 Make good to floor finish (ceramic tiles) to RH door frame

AMERICA HOUSE

Ref. Location Defect

No.

1 Pantry E4E.06 Wall tiling is generally poor workmanship

2 Pantry E4E.06 Make good joint between wall and floor tiling on North Wall3 Pantry E4E.06 Clean off excess grouting throughout

4 Pantry E4E.06 Repair boiler leak and install proper safety valve

5 Pantry E4E.06 Fixing screws to frame protrude and are to be refixed to door

6 Pantry E4E.06 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Pantry E4E.06 Screw missing to lock plate on door

8 Pantry E4E.06 Remove all remaining parts of protective covering to door

9 Pantry E4E.06 Replace door grill screws (Internal) with white headed screws

10 Pantry E4E.06 Install rubber seal to door all round

11 Pantry E4E.06 Touch up chipped paintwork to door frames

12 Pantry E4E.06 Redo angle piece on wall tiling at head of door to Janitor Closet

13 Pantry E4E.06 Redo angle piece on wall tiling at external angle to LH of door to Janitor Closet

14 Pantry E4E 06 Redo angle piece on wall tiling at external angle to RH of door to Janitor Closet

Page 238: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 238/407

14 Pantry E4E.06 Redo angle piece on wall tiling at external angle to RH of door to Janitor Closet

15 Pantry E4E.06 Door frames are set above floor finish by 6mm and require to be reset

16 Pantry E4E.06 Reset RH door to upper cabinet on South Wall

17 Pantry E4E.06 Repair damaged floor base unit (RH) damaged by leaking boiler

18 Pantry E4E.06 Replace damaged suspended ceiling tile

19 Pantry E4E.06 Install plug

20 Pantry E4E.06 Seal floor cabinet units between wall and units LH side and make good (East Wall)

21 Pantry E4E.06 Seal floor cabinet units between wall and units RH side and make good (East Wall)

22 Pantry E4E.06 Make good untidy joint between wall tiling and suspended ceiling on North Wall

23 Pantry E4E.06 Install door stop

24 Pantry E4E.06 Install edging to PVC floor covering at door entrance

25 Pantry E4E.06 Make good to floor finishes at base of LH door frame to Vestibule

26 Pantry E4E.06 Make good to floor finishes at base of RH door frame to Vestibule

27 Pantry E4E.06 Reset to level position for power socket outlet (double) at floor level on North Wall

28 Pantry E4E.06 Are suspended ceiling tiles water resistant (pantry has boiling kettles etc.)29 Pantry E4E.06 Seal floor cabinet units between wall and units LH side and make good (South Wall)

30 Pantry E4E.06 Double bowel sink is shown on drawings - Who authorized change to single bowel sink

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 5 Lift Lobby E5E.01 Tiling to floor is uneven and not aligned and requires to be re-executed

2 Level 5 Lif t Lobby E5E.01 Wall Tiling to West Wall is debonding, uneven, not aligned, pointing is distressed and requires to be re-executed 3 Level 5 Lif t Lobby E5E.01 Wall Tiling to East (Lif t) Wall is uneven, not aligned, pointing is distressed and requires to be re-executed

4 Level 5 Lift Lobby E5E.01 Readjust three (3) small downlighters that are not properly aligned and make good

5 Level 5 Lift Lobby E5E.01 Remove paint on ventilation grille large (South)

6 Level 5 Lift Lobby E5E.01 Seal pointing between lift panelling and ceiling PE 09

7 Level 5 Lift Lobby E5E.01 Seal pointing between lift panelling and ceiling PE 07

8 Level 5 Lift Lobby E5E.01 Refit stainless steel skirting to Lift PE 09 that show gaps between the skirting and wall panelling both sides

9 Level 5 Lift Lobby E5E.01 Refit stainless steel skirting to Lift PE 08 that show gaps between the skirting and wall panelling both sides

10 Level 5 Lift Lobby E5E.01 Refit stainless steel skirting to Lift PE 07 that show gaps between the skirting and wall panelling both sides

11 Level 5 Lift Lobby E5E.01 Clean threshold of Lift PE 09

12 Level 5 Lift Lobby E5E.01 Clean threshold of Lift PE 08

13 Level 5 Lift Lobby E5E.01 Clean threshold of Lift PE 07

14 Level 5 Lift Lobby E5E 01 Make good to floor covering at RH of lift door frame PE7

Page 239: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 239/407

14 Level 5 Lift Lobby E5E.01 Make good to floor covering at RH of lift door frame PE7

15 Level 5 Lift Lobby E5E.01 Make good to floor covering at LH of lift door frame PE7

16 Level 5 Lift Lobby E5E.01 Make good to floor covering at RH of lift door frame PE8

17 Level 5 Lift Lobby E5E.01 Make good to floor covering at LH of lift door frame PE8

18 Level 5 Lift Lobby E5E.01 Make good to floor covering at RH of lift door frame PE9

19 Level 5 Lift Lobby E5E.01 Make good to floor covering at LH of lift door frame PE9

20 Level 5 Lift Lobby E5E.01 Make good pointing between wall tiling and lift panelling to LH side of PE09

21 Level 5 Lift Lobby E5E.01 Make good pointing between wall tiling and lift panelling to LH side of PE07

22 Level 5 Lift Lobby E5E.01 Remove protective covering from base of RH frame to Lift PE08

23 Level 5 Lift Lobby E5E.01 Remove protective covering from base of LH frame to Lift PE09

24 Level 5 Lift Lobby E5E.01 Remove protective covering from base of LH frame to Lift PE08

25 Level 5 Lift Lobby E5E.01 Remove protective covering to lift door frame head LH of Lift PE09

26 Level 5 Lift Lobby E5E.01 Remove protective covering to lift door frame head RH of Lift PE09

27 Level 5 Lift Lobby E5E.01 Remove protective covering to lift door frame head LH of Lift PE08

28 Level 5 Lift Lobby E5E.01 Remove protective covering to lift door frame head LH of Lift PE0729 Level 5 Lift Lobby E5E.01 Clean masking tape off stainless steel panel near ceiling on Lift PE09

30 Level 5 Lift Lobby E5E.01 Reset warped top panel near ceiling on Lift PE08

31 Level 5 Lift Lobby E5E 01 Make good joint at West Wall south end where tiling meets render

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor North C14/18 (E5E.01) Install operator signage to Fire Alarm Button at South Wall near door to Stair Vestibule E5E.03

2 Corridor North C14/18 (E5E.01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby3 Corridor North C14/18 (E5E.01) Clean paint off grille to Fire Damper panel (Lower) near Lift Lobby

4 Corridor North C14/18 (E5E.01) Provide proper locking device to Low Fire Damper Grille on South Wall near Lift Lobby

5 Corridor North C14/18 (E5E.01) Tiling to wall at C17 South Wall is uneven, debonding, and not aligned and requires to be re-executed

6 Corridor North C14/18 (E5E.01) Tiling to wall at C16 South Wall is uneven, debonding and not aligned and requires to be re-executed

7 Corridor North C14/18 (E5E.01) Install operator signage to Fire Alarm Button at South Wall RH of Service Elevator Vestibule

8 Corridor North C14/18 (E5E.01) Install operator signage to Door Release Button at South Wall to RH of Service Elevator Vestibule

9 Corridor North C14/18 (E5E.01) Remove paint from Running Man Sign above door to Stair Vestibule E4E.16

10 Corridor North C14/18 (E5E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby

11 Corridor North C14/18 (E5E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby12 Corridor North C14/18 (E5E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on South Wall near Lift Lobby

13 Corridor North C14/18 (E5E.01) Make good round Fire Damper Grille panel (Low) on South Wall near to RH side of Service Elevator Lobby

14 Corridor North C14/18 (E5E.01) Clean paint off grille to Fire Damper panel (Lower) to RH side of Service Lift Lobby

Page 240: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 240/407

( ) p g p p ( ) y

15 Corridor North C14/18 (E5E.01) Provide proper locking device to Low Fire Damper Grille on South Wall to RH side of Service Lift Lobby

AMERICA HOUSE

Ref. Location Defect Rat

No. Clas

1 Corridor East B/C 18(5E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory B

2 Corridor East B/C 18(5E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory B

Page 241: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 241/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor West B/C 14 (E5E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor West B/C 14 (E5E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor West B/C 14 (E5E.01) Make good round Fire Damper Grille panel B18 East Wall near Fire Hose reel Enclosure (FHE)

4 Corridor West B/C 14 (E5E.01) Clean paint off grille to Fire Damper panel B19 near FHE

5 Corridor West B/C 14 (E5E.01) Provide proper locking device to B18 Fire Damper Grille on East Wall near FHE

6 Corridor West B/C 14 (E5E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box as key is missing

7 Corridor West B/C 14 (E5E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor West B/C 14 (E5E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor West B/C 14 (E5E.01) Build up blockwork below threshold and seal to door

10 Corridor West B/C 14 (E5E.01) Seal to head of door frame with blockwork and make good

11 Corridor West B/C 14 (E5E.01) Divider Wall to LH to be sealed full length to back wall12 Corridor West B/C 14 (E5E.01) Remove one electrical cable (used by Ozer during construction) and make good to holes

13 Corridor West B/C 14 (E5E.01) Seal two holes in ceiling slab within FHE and make good

14 Corridor West B/C 14 (E5E.01) Seal around two (2) pipes in the floor slab and make good

Page 242: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 242/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor South B14/18 (E5E.01) Make good poor tiling above Fire Damper Grille B16 near lift lobby

2 Corridor South B14/18 (E5E.01) Install operator signage to Fire Alarm Button at North Wall near door to Stair Vestibule E5E.03

3 Corridor South B14/18 (E5E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E5E.16

4 Corridor South B14/18 (E5E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E5E.16 North Wall

5 Corridor South B14/18 (E5E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E5E.16

6 Corridor South B14/18 (E5E.01) Install operator signage to Fire Alarm Button at North Wall LH of Stair Vestibule E5E.16

7 Corridor South B14/18 (E5E.01) Tiling to wall at C17 North Wall is uneven, debonding and not aligned and requires to be re-executed

8 Corridor South B14/18 (E5E.01) Tiling to wall at C16 North Wall is uneven, debonding and not aligned and requires to be re-executed

9 Corridor South B14/18 (E5E.01) Make good to large gap between Low Fire Damper Grille and tiling finish on North Wall LH to Stair Vestibule Door E5E.03

10 Corridor South B14/18 (E5E.01) Make good round Fire Damper Grille panel (Upper B 16) on South Wall near Lift Lobby

11 Corridor South B14/18 (E5E.01) Clean paint off grille to Fire Damper panel (Upper B 16) near Lift Lobby12 Corridor South B14/18 (E5E.01) Provide proper locking device to Upper (B 16) Fire Damper Grille on North Wall near Lift Lobby

13 Corridor South B14/18 (E5E.01) Infill to large gap LH side to wall at Fire Damper on North Wall near Lift Lobby

14 Corridor South B14/18 (E5E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E5E.03 LH

Page 243: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 243/407

15 Corridor South B14/18 (E5E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E5E.03 North Wall

16 Corridor South B14/18 (E5E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E5E.03 LH

17 Corridor South B14/18 (E5E.01) Infill to large gap LH side to wall at Fire Damper on North Wall near Stair Vestibule E5E.03

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 5 (E5E.03) Remove paint to South Door Frames

2 Stair Vestibule Level 5 (E5E.03) Fit rubber seal all round door South

3 Stair Vestibule Level 5 (E5E.03) Intumescent strip is not complete to open frame and short at base and head and loose at top to Door South : replace

4 Stair Vestibule Level 5 (E5E.03) Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule Level 5 (E5E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule Level 5 (E5E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule Level 5 (E5E.03) Install door stop to Door South

8 Stair Vestibule Level 5 (E5E.03) Remove remaining protective covering to Door South

9 Stair Vestibule Level 5 (E5E.03) Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule Level 5 (E5E.03) Screw missing in lock plate to door South

11 Stair Vestibule Level 5 (E5E.03) Intumescent strip is not complete at prong receiver to hinge frame and short at base to Door South and to be replaced12 Stair Vestibule Level 5 (E5E.03) Lockset is missing and to be fixed

13 Stair Vestibule Level 5 (E5E.03) Door signage

14 Stair Vestibule Level 5 (E5E.03) South door frames are 8mm above the finished floor level and to be reset

Page 244: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 244/407

15 Stair Vestibule Level 5 (E5E.03) Provide operation label to Door Push Button in Romanian and English

16 Stair Vestibule Level 5 (E5E.03) Make good to skirting that is broken near RH of door to Egress Stair

17 Stair Vestibule Level 5 (E5E.03) Remove paint from top edge of skirting on all walls

18 Stair Vestibule Level 5 (E5E.03) North door frames are 10mm above the finished floor level and to be reset

19 Stair Vestibule Level 5 (E5E.03) Clean paint etc from two (2) light fittings

20 Stair Vestibule Level 5 (E5E.03) Clean paint off door frame to Door North

21 Stair Vestibule Level 5 (E5E.03) Intumescent strip is short to head frame and requires to be replaced

22 Stair Vestibule Level 5 (E5E.03) Intumescent strip is not complete to both frame bases of Door North and to be replaced

23 Stair Vestibule Level 5 (E5E.03) Fixing screws to frame protrude and are to be refixed to Door North

24 Stair Vestibule Level 5 (E5E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door North

25 Stair Vestibule Level 5 (E5E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

26 Stair Vestibule Level 5 (E5E.03) Install door stop to Door North

27 Stair Vestibule Level 5 (E5E.03) Fit rubber seal all round door North

28 Stair Vestibule Level 5 (E5E.03) Fire/Smoke Threshold seal is required to door North29 Stair Vestibule Level 5 (E5E.03) Remove remaining protective covering to Door North

30 Stair Vestibule Level 5 (E5E.03) Remove manufacturer's label on door and adhesive and make good

31 Stair Vestibule Level 5 (E5E 03) Screw missing in lock plate to door North

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 5 (E5E.03) Make good to terrazzo skirting to RH side of Door North

35 Stair Vestibule Level 5 (E5E.03) Remove paint to three (3) sprinkler head in ceiling

36 Stair Vestibule Level 5 (E5E.03) Make good round Fire Damper Grille panel (Upper)

37 Stair Vestibule Level 5 (E5E.03) Clean paint off grille to Fire Damper panel (Upper)

38 Stair Vestibule Level 5 (E5E.03) Provide proper locking device to Upper Fire Damper Grille (Upper)

39 Stair Vestibule Level 5 (E5E.03) Make good round Fire Damper Grille panel (Lower)

40 Stair Vestibule Level 5 (E5E.03) Clean paint off grille to Fire Damper panel (Lower)

41 Stair Vestibule Level 5 (E5E.03) Provide proper locking device to Upper Fire Damper Grille (Lower)

42 Stair Vestibule Level 5 (E5E.03) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

43 Stair Vestibule Level 5 (E5E.03) Seal internal around Dry Riser Access Panel and make good

44 Stair Vestibule Level 5 (E5E.03) Form rounded external corner to terrazzo skirting to LH of door to Egress Stair45 Stair Vestibule Level 5 (E5E.03) Form rounded external corner to terrazzo skirting to RH of door to Egress Stair

Page 245: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 245/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 5 (E5E.04) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 5 (E5E.04) Remove paint from Running Man Sign and make good

3 Egress Stair Level 5 (E5E.04) Reset light fitting on Level 5 Landing wall which is squint

4 Egress Stair Level 5 (E5E.04) Remove paint etc. from ceiling Smoke Detector and make good

5 Egress Stair Level 5 (E5E.04) Tiled Level 3 floor requires to be levelled, polished and sealed and repaired including workmanship near divide wall to stair

6 Egress Stair Level 5 (E5E.04) Fixing screws to frame protrude and are to be refixed

7 Egress Stair Level 5 (E5E.04) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 5 (E5E.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 5 (E5E.04) Intumescent strip to open door jamb is short and to be replaced

10 Egress Stair Level 5 (E5E.04) Intumescent strip to hinge door jamb is short and to be replaced

11 Egress Stair Level 5 (E5E.04) Rubber infill strip to door is loose at head12 Egress Stair Level 5 (E5E.04) Install door stop to Door

13 Egress Stair Level 5 (E5E.04) Screw missing at lock plate on door

14 Egress Stair Level 5 (E5E.04) Remove paint on door frames and make good

15 E St i L l 5 (E5E 04) Fi /S k l th h ld i d t t d

Page 246: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 246/407

15 Egress Stair Level 5 (E5E.04) Fire/Smoke seal threshold required to entry door

16 Egress Stair Level 5 (E5E.04) Door signage

17 Egress Stair Level 5 (E5E.04) Door intruder alarm contacts to be aligned

18 Egress Stair Level 5 (E5E.04) Make good to wall painting where stained by repairs to terrazzo skirting

19 Egress Stair Level 5 (E5E.04) Remove all remaining protective covering to door

20 Egress Stair Level 5 (E5E.04) Replace key sets with correct set

21 Egress Stair Level 5 (E5E.04) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

22 Egress Stair Level 5 (E5E.04) Clean light fitting of paint stains etc. at mid landing

23 Egress Stair Level 5 (E5E.04) Make good to open stair stringer to upper stair flight

24 Egress Stair Level 5 (E5E.04) Make good to open stair stringer to lower stair flight

25 Egress Stair Level 5 (E5E.04) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface and done in bits and pieces

26 Egress Stair Level 5 (E5E.04) Clean two (2) stair flights between Levels 3 and 4 of black paint and mortar stains complete

27 Egress Stair Level 5 (E5E.04) Clean terrazzo tile at mid landing around the two (2) balustrade supports

28 Egress Stair Level 5 (E5E.04) Provide rounded edges to terrazzo skirting to LH of door base

29 Egress Stair Level 5 (E5E.04) Provide rounded edges to terrazzo skirting to RH of door base

30 Egress Stair Level 5 (E5E.04) Replace two (2) chipped steps

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 5 (E5E.16) Remove paint to South Door Frames

2 Stair Vestibule Level 5 (E5E.16) Fit rubber seal all round door South

3 Stair Vestibule Level 5 (E5E.16) Intumescent strip is not complete to both frame base and prong receiver both sides on hinge side of Door South : replace

4 Stair Vestibule Level 5 (E5E.16) Intumescent strip is not complete to base of open frame of Door South and also loose

5 Stair Vestibule Level 5 (E5E.16) Fixing screws to frame protrude and are to be refixed to Door South

6 Stair Vestibule Level 5 (E5E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door South

7 Stair Vestibule Level 5 (E5E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

8 Stair Vestibule Level 5 (E5E.16) Install door stop to Door South

9 Stair Vestibule Level 5 (E5E.16) Remove remaining protective covering to Door South

10 Stair Vestibule Level 5 (E5E.16) Install fire/smoke seal threshold plate to Door South

11 Stair Vestibule Level 5 (E5E.16) Screw missing in lock plate to door South12 Stair Vestibule Level 5 (E5E.16) Intumescent strip is loose and distorted on head frame and to be replaced

13 Stair Vestibule Level 5 (E5E.16) Why are there locks on Stair Egress Doors operated with Card Reader Access and Release Push button ?

14 Stair Vestibule Level 5 (E5E.16) Terrazzo tile floor is uneven and needs to be levelled, polished and resealed

15 Stair Vestibule Level 5 (E5E 16) Terrazzo Skirting at RH wall returns to door to have rounded or pencil arrissed corners to Stair Egress

Page 247: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 247/407

15 Stair Vestibule Level 5 (E5E.16) Terrazzo Skirting at RH wall returns to door to have rounded or pencil arrissed corners to Stair Egress

16 Stair Vestibule Level 5 (E5E.16) Provide operation label to Door Push Button in Romanian and English

17 Stair Vestibule Level 5 (E5E.16) Remove paint etc. from top edge of skirting on all walls

18 Stair Vestibule Level 5 (E5E.16) Reset double power socket outlet near Door North on East wall to be level

19 Stair Vestibule Level 5 (E5E.16) Reset double power socket outlet near Door South on East wall to be level

20 Stair Vestibule Level 5 (E5E.16) Clean paint etc from two (2) light fittings

21 Stair Vestibule Level 5 (E5E.16) Screw missing from door lock plate on Door North

22 Stair Vestibule Level 5 (E5E.16) Clean paint off door frame to Door North

23 Stair Vestibule Level 5 (E5E.16) Touch up chipped paintwork to door frames

24 Stair Vestibule Level 5 (E5E.16) Intumescent strip is short to base of open frame of Door North and to be replaced

25 Stair Vestibule Level 5 (E5E.16) Intumescent strip is short at head and base on the hinge frame and to be re-installed to Door North

26 Stair Vestibule Level 5 (E5E.16) Fixing screws to frame protrude and are to be refixed to Door North

27 Stair Vestibule Level 5 (E5E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door North

28 Stair Vestibule Level 5 (E5E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected 29 Stair Vestibule Level 5 (E5E.16) Install door stop to Door North

30 Stair Vestibule Level 5 (E5E.16) Fit rubber seal all round door North

31 Stair Vestibule Level 5 (E5E 16) Fire/Smoke Threshold seal is required to door North

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 5 (E5E.16) Remove all remaining parts of protective covering to door North

35 Stair Vestibule Level 5 (E5E.16) Remove paint to three (3) sprinkler head in ceiling and make good

36 Stair Vestibule Level 5 (E5E.16) Reset sprinkler head South which is proud of ceiling surface

37 Stair Vestibule Level 5 (E5E.16) Make good round Fire Damper Grille panel (Upper)

38 Stair Vestibule Level 5 (E5E.16) Clean paint off grille to Fire Damper panel (Upper)

39 Stair Vestibule Level 5 (E5E.16) Provide proper locking device to Upper Fire Damper Grille (Upper)

40 Stair Vestibule Level 5 (E5E.16) Make good round Fire Damper Grille panel (Lower)

41 Stair Vestibule Level 5 (E5E.16) Clean paint off grille to Fire Damper panel (Lower)

42 Stair Vestibule Level 5 (E5E.16) Provide proper locking device to Upper Fire Damper Grille (Lower)

43 Stair Vestibule Level 5 (E5E.16) Make good to skirting to LH of Door South

44 Stair Vestibule Level 5 (E5E.16) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required45 Stair Vestibule Level 5 (E5E.16) Remove paint from Running Man Sign and make good

46 Stair Vestibule Level 5 (E5E.16) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

47 Stair Vestibule Level 5 (E5E.16) Seal internally around Dry Riser Access Panel and make good

48 Stair Vestibule Level 5 (E5E.16) Remove piece of timber formwork within Dry Riser enclosure that is obstructing access to Dry Riser coupling

Page 248: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 248/407

48 Stair Vestibule Level 5 (E5E.16) Remove piece of timber formwork within Dry Riser enclosure that is obstructing access to Dry Riser coupling

49 Stair Vestibule Level 5 (E5E.16) Remove pencil mark on terrazzo skirting RH return to Door to Stair Egress

50 Stair Vestibule Level 5 (E5E.16) Make good to skirting terrazzo to East Wall near south end that is in distress

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 5 (E5E.17) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 5 (E5E.17) Remove paint from Running Man Sign and make good

3 Egress Stair Level 5 (E5E.17) Tiled Level 4 floor requires to be levelled, polished and sealed and repaired where poor workmanship near divide wall to stair

4 Egress Stair Level 5 (E5E.17) Intumescent strip is missing from head and frame and requires to be installed

5 Egress Stair Level 5 (E5E.17) Fixing screws to frame protrude and are to be refixed

6 Egress Stair Level 5 (E5E.17) Cover four (4) protruding screw ends in angle plate to top corner to door

7 Egress Stair Level 5 (E5E.17) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

8 Egress Stair Level 5 (E5E.17) Intumescent strip to open door jamb is short at base and to be replaced

9 Egress Stair Level 5 (E5E.17) Intumescent strip to hinge door jamb is short at base and head and to be replaced

10 Egress Stair Level 5 (E5E.17) Intumescent strip is missing from head frame and requires to be replaced

11 Egress Stair Level 5 (E5E.17) Rubber infill strip to door is partly missing at head12 Egress Stair Level 5 (E5E.17) Install door stop to Door

13 Egress Stair Level 5 (E5E.17) Screw missing at lock plate on door

14 Egress Stair Level 5 (E5E.17) Remove paint on door frames and make good

15 Egress Stair Level 5 (E5E 17) Fire/Smoke seal threshold required to entry door

Page 249: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 249/407

15 Egress Stair Level 5 (E5E.17) Fire/Smoke seal threshold required to entry door

16 Egress Stair Level 5 (E5E.17) Door signage

17 Egress Stair Level 5 (E5E.17) Door intruder alarm contacts to be aligned

18 Egress Stair Level 5 (E5E.17) Remove all remaining protective covering to door

19 Egress Stair Level 5 (E5E.17) Tidy up contact wires to door intruder alarm

20 Egress Stair Level 5 (E5E.17) Clean paint etc from Landing 5 light and make good

21 Egress Stair Level 5 (E5E.17) Make good at joint with wall and ceiling above door Landing 5 and repaint

22 Egress Stair Level 5 (E5E.17) Make good to open stair stringer to upper stair flight

23 Egress Stair Level 5 (E5E.17) Make good to open stair stringer to lower stair flight

24 Egress Stair Level 5 (E5E.17) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

25 Egress Stair Level 5 (E5E.17) Clean two (2) stair flights between Levels 5 and 6 of black paint and mortar stains complete

26 Egress Stair Level 5 (E5E.17) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

27 Egress Stair Level 5 (E5E.17) Make good to wall above Door to Landing 5 LH side

28 Egress Stair Level 5 (E5E.17) Replace one (1) chipped stair tread

29 Egress Stair Level 5 (E5E.17) Repoint between wall finish and RH side of door and repaint

30 Egress Stair Level 5 (E5E.17) Clean paint etc from mid landing light

31 Egress Stair Level 5 (E5E 17) Seal joint between tiled floor and terrazzo tile skirting on north wall at mid landing

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Elevator Vestibule (E5E.18) Remove paint stains on floor covering generally

2 Service Elevator Vestibule (E5E.18) Fill in hole to door head frame

3 Service Elevator Vestibule (E5E.18) Fixing screws to frame protrude and are to be refixed to Door

4 Service Elevator Vestibule (E5E.18) Cover four (4) protruding screw ends in angle plate to top corner to door

5 Service Elevator Vestibule (E5E.18) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

6 Service Elevator Vestibule (E5E.18) Intumescent strip is short on both side frames and requires to be replaced

7 Service Elevator Vestibule (E5E.18) Install door stops to Doors

8 Service Elevator Vestibule (E5E.18) Clean paint off Door Frames

9 Service Elevator Vestibule (E5E.18) Door Signage

10 Service Elevator Vestibule (E5E.18) Fire/Smoke Threshold seal is required to door

11 Service Elevator Vestibule (E5E.18) Install closer on inner leaf of doors with selector on doors 12 Service Elevator Vestibule (E5E.18) Remove all remaining parts of the protective covering to doors

13 Service Elevator Vestibule (E5E.18) Install rubber seal to door

14 Service Elevator Vestibule (E5E.18) Intumescent strip to meeting style is not continuous and missing at door lock

15 Service Elevator Vestibule (E5E.18) Realign door intruder alarm contacts and fix head frame contact which is loose

Page 250: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 250/407

( ) g

16 Service Elevator Vestibule (E5E.18) Inner leaf of door has too much play when closed and to be adjusted

17 Service Elevator Vestibule (E5E.18) Tidy up wiring to door intruder contact

18 Service Elevator Vestibule (E5E.18) Screw missing form door locking plate

19 Service Elevator Vestibule (E5E.18) Intumescent strip is short at the prong receiver on the RH door frame

20 Service Elevator Vestibule (E5E.18) Touch up to damaged paintwork to door frames generally

21 Service Elevator Vestibule (E5E.18) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

22 Service Elevator Vestibule (E5E.18) Relay floor covering that is distorted and 'bubbled' and prepare floor screed below

23 Service Elevator Vestibule (E5E.18) Paint sprinkler pipework

24 Service Elevator Vestibule (E5E.18) Tidy up joint at sprinkler head and elbow joints including removing excess joint hemp fibres on sprinkler pipework

25 Service Elevator Vestibule (E5E.18) Replace screws at grille to LH side with white headed screws as elsewhere

26 Service Elevator Vestibule (E5E.18) Seal and make good to conduit at ceiling level (West Wall)

27 Service Elevator Vestibule (E5E.18) Seal and make good to one (1) sprinkler pipe in northeast corner at near ceiling level

28 Service Elevator Vestibule (E5E.18) Clean off paint splashes on Lift Door and frames

29 Service Elevator Vestibule (E5E.18) Make good to floor finishes etc at base of LH frame of door

30 Service Elevator Vestibule (E5E.18) Make good to floor finishes etc at base of RH frame of door and fill in sinking to screed

31 Service Elevator Vestibule (E5E 18) Repair door catch on Inner Door leaf that operate the upper door bolt

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E5E.09 Fix skirting to complete room which is missing

2 Electrical Closet E5E.09 Make good to floor level on South Wall near door and refix floor covering

3 Electrical Closet E5E.09 Make good wall plasterboard on East Wall near bus bar assembly (RH)

4 Electrical Closet E5E.09 Remove paint splashed on door surfaces

5 Electrical Closet E5E.09 Make good to short floor covering on East side of room

6 Electrical Closet E5E.09 Make good to north wall next floor sinking and refix floor covering complete

7 Electrical Closet E5E.09 Infill large hole in southeast of room (fire stopping) Hole at present is a safety issue

8 Electrical Closet E5E.09 Install door closer

9 Electrical Closet E5E.09 Intumescent strip is not provided to head frame of door and to be installed

10 Electrical Closet E5E.09 Intumescent strip is not provided to open frame of door and to be installed

11 Electrical Closet E5E.09 Remove paint to Door Frames12 Electrical Closet E5E.09 Fit rubber seal all round door

13 Electrical Closet E5E.09 Intumescent strip is not provided to hinge frame of door and to be installed

14 Electrical Closet E5E.09 Fixing screws to frame protrude and are to be refixed to door

15 Electrical Closet E5E.09 Cover four (4) protruding screw ends in angle plate to top corner to Door South

Page 251: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 251/407

16 Electrical Closet E5E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be accounted

17 Electrical Closet E5E.09 Install door stop to door

18 Electrical Closet E5E.09 Remove remaining protective covering to Door South

19 Electrical Closet E5E.09 Install fire/smoke seal threshold plate to Door South

20 Electrical Closet E5E.09 Screw missing in lock plate to door South

21 Electrical Closet E5E.09 Door frames are 5mm above finished floor level and to be reset

22 Electrical Closet E5E.09 Install door closer

23 Electrical Closet E5E.09 Intruder alarm door contacts to be fitted

24 Electrical Closet E5E.09 Door sign

25 Electrical Closet E5E.09 Screw in the fifteen (6) loose screws to the five (5) control boxes to RH of SBS-7E

26 Electrical Closet E5E.09 Fit sealing screws to fourteen (14) missing screws to the (5) control boxes to RH of SBS-7E

27 Electrical Closet E5E.09 Replace label to cabinet SBS 9E which is plastic with paper printed sign and install ivorine label

28 Electrical Closet E5E.09 Reconnect three (3) loose wires or remove in electrical box above control boxes No 2 above SBS-7E

29 Electrical Closet E5E.09 Reconnect seven (7) loose wires or remove in electrical box above control boxes No 4 above SBS-7E

30 Electrical Closet E5E.09 Clean dust inside TLE-5E

31 Electrical Closet E5E 09 Clean dust inside TUPS-5E

AMERICA HOUSE

Ref. Location Defect

No.

1 Data Room E5E.10 Remove paint on door frames and make good

2 Data Room E5E.10 Fixing screws to frame protrude and are to be refixed to door

3 Data Room E5E.10 Cover four (4) protruding screw ends in angle plate to top corner to door

4 Data Room E5E.10 Screw missing to lock plate on door

5 Data Room E5E.10 Remove all remaining parts of protective covering to door

6 Data Room E5E.10 Install rubber seal around door

7 Data Room E5E.10 Install door stop

8 Data Room E5E.10 Seal North wall to two (2) HVAC pipes and make good all round

Page 252: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 252/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 5 Schlumberger Space Window No 1 North Repair tighten window handle

2 Level 5 Schlumberger Space Window No 2 North Repair tighten window handle

3 Level 5 Schlumberger Space Window No 3 North Repair tighten window handle

4 Level 5 Schlumberger Space Window No 4 North Repair tighten window handle

5 Level 5 Schlumberger Space Window No 5 North Repair tighten window handle

6 Level 5 Schlumberger Space Window No 6 North Repair tighten window handle

7 Level 5 Schlumberger Space Window No 7 North Repair tighten window handle

8 Level 5 Schlumberger Space Window No 8 Repair defective seal at corner of opening window

9 Level 5 Schlumberger Space Window No 9 North Repair defective seal at corner and refix seal to opening window

10 Level 5 Schlumberger Space Window No 10 tighten window handle

11 Level 5 Schlumberger Space Window No. 11 tighten window handle12 Level 5 Schlumberger Space Window No 12 North install missing window frame seal for full height of opening

13 Level 5 Schlumberger Space Window No 13 North refix seal to opening window at base of sash

14 Level 5 Schlumberger Space Window No 14 North tighten window handle

15 Level 5 Schlumberger Space Window No 3 East Tighten window handle

Page 253: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 253/407

16 Level 5 Schlumberger Space Window No 6 East Repair defective seal at head frame corner and refix seal to opening window

17 Level 5 Schlumberger Space Window Fan No 1 East Repair seal at bottom LH that is under stress and remove excess mastic sealant

18 Level 5 Schlumberger Space Window Fan No 1 East tighten up window handle

19 Level 5 Schlumberger Space Window Fan No 1 East remove all remaining protective covering to window frames etc.

20 Level 5 Schlumberger Space Window Fan No 1 South install inner frame seal which is missing and remove excess mastic sealant

21 Level 5 Schlumberger Space Window Fan No 1 South tighten window handle

22 Level 5 Schlumberger Space Window Fan No 2 South make good to window seal outer and inner at top LH

23 Level 5 Schlumberger Space Window Fan No 2 South make good to window seal in distress at RH which is also broken and needs to be replaced

24 Level 5 Schlumberger Space Window Fan No 2 South tighten window handle

25 Level 5 Schlumberger Space Window Fan No 3 South tighten window handle

26 Level 5 Schlumberger Space Window Fan No 4 South tighten window handle

27 Level 5 Schlumberger Space Window Fan No 5 South tighten window handle

28 Level 5 Schlumberger Space Window Fan No 5 South tighten window handle

29 Level 5 Schlumberger Space Window Fan No 7 South tighten window handle

30 Level 5 Schlumberger Space Window Fan No 2 South Remove excess mastic and sealant

31 Level 5 Schlumberger Space Window Fan No 3 South Remove excess mastic and sealant

AMERICA HOUSE

Ref. Location Defect

No.

35 Level 5 Schlumberger Space Window Fan No 7 South Remove excess mastic and sealant

36 Level 5 Schlumberger Space Window Fan No 3 South replace frame seal that is damaged

37 Level 5 Schlumberger Space Window Fan No 3 South replace window frame seal that is damaged

38 Level 5 Schlumberger Space Window Fan No 4 South Repair window seal (2 No) to LH of window

39 Level 5 Schlumberger Space Window Fan No 5 South repair or replace outer window seal that is distorted at top and damaged at LH end

40 Level 5 Schlumberger Space Window Fan No 6 South Repair or replace outer seal to window that is loose and damaged at RH end

41 Level 5 Schlumberger Space Window Fan No 7 South Repair or replace outer seal to window that is under stress and distorted

42 Level 5 Schlumberger Space Window Fan No 7 South Repair or replace inner seal to window that is damaged at RH end and distorted

43 Level 5 Schlumberger Space Remove labels on all windows generally

44 Level 5 Schlumberger Space Clean general building debris out of runnels to all twenty eight (28) opening sashes

Page 254: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 254/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 6 Lift Lobby E6E.01 Wall Tiling to East (Lift) Wall is uneven, not aligned, pointing is distressed and requires to be re-executed

2 Level 6 Lif t Lobby E6E.01 Readjust two (2) small downlighters (North and South) that are not properly aligned and make good

3 Level 6 Lift Lobby E6E.01 Remove paint on ventilation grille large (South)

4 Level 6 Lift Lobby E6E.01 Seal pointing between lift panelling and ceiling PE 09

5 Level 6 Lift Lobby E6E.01 Refit stainless steel skirting to Lift PE 09 that show gaps between the skirting and wall panelling both sides

6 Level 6 Lift Lobby E6E.01 Refit stainless steel skirting to Lift PE 08 that show gaps between the skirting and wall panelling both sides

7 Level 6 Lift Lobby E6E.01 Refit stainless steel skirting to Lift PE 07 that show gaps between the skirting and wall panelling both sides

8 Level 6 Lift Lobby E6E.01 Clean threshold of Lift PE 09

9 Level 6 Lift Lobby E6E.01 Clean threshold of Lift PE 08

10 Level 6 Lift Lobby E6E.01 Clean threshold of Lift PE 07

11 Level 6 Lift Lobby E6E.01 Make good pointing between wall tiling and lift panelling to LH side of PE0912 Level 6 Lift Lobby E6E.01 Make good pointing between wall tiling and lift panelling to RH side of PE09

13 Level 6 Lift Lobby E6E.01 Make good pointing between wall tiling and lift panelling to LH side of PE08

14 Level 6 Lift Lobby E6E.01 Make good pointing between wall tiling and lift panelling to RH side of PE08

15 Level 6 Lift Lobby E6E.01 Make good pointing between wall tiling and lift panelling to LH side of PE07

16 L l 6 Lift L bb E6E 01 M k d i ti b t ll tili d lift lli t RH id f PE07

Page 255: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 255/407

16 Level 6 Lift Lobby E6E.01 Make good pointing between wall tiling and lift panelling to RH side of PE07

17 Level 6 Lift Lobby E6E.01 Remove protective covering from base of RH frame to Lift PE08

18 Level 6 Lift Lobby E6E.01 Remove protective covering from base of LH frame to Lift PE09

19 Level 6 Lift Lobby E6E.01 Remove protective covering from base of LH frame to Lift PE08

20 Level 6 Lift Lobby E6E.01 Remove protective covering to lift door frame head LH of Lift PE09

21 Level 6 Lift Lobby E6E.01 Remove protective covering to lift door frame head LH of Lift PE08

22 Level 6 Lift Lobby E6E.01 Remove protective covering to lift door frame head LH of Lift PE07

23 Level 6 Lift Lobby E6E.01 Make good to warped joints between head lift panel above door and main panel above lift door PE09

24 Level 6 Lift Lobby E6E.01 Make good to warped joints between head lift panel above door and main panel above lift door PE08

25 Level 6 Lift Lobby E6E.01 Make good to warped joints between head lift panel above door and main panel above lift door PE07

26 Level 6 Lift Lobby E6E.01 Remove paint on three (3) small ceiling downlighters and make good

27 Level 6 Lift Lobby E6E.01 Remove paint on eight (8) sprinkler heads in ceiling

28 Level 6 Lift Lobby E6E.01 Remove paint on smaller grille to North and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor East B/C 18 (E6E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor East B/C 18 (E6E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor East B/C 18 (E6E.01) Make good round Fire Damper Grille panel B18 East Wall near Fire Hose reel Enclosure (FHE)

4 Corridor East B/C 18 (E6E.01) Clean paint off grille to Fire Damper panel B18 near FHE

5 Corridor East B/C 18 (E6E.01) Provide proper locking device to B18 Fire Damper Grille on East Wall near FHE

6 Corridor East B/C 18 (E6E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box as key is missing

7 Corridor East B/C 18 (E6E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor East B/C 18 (E6E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor East B/C 18 (E6E.01) Build up blockwork below threshold and seal to door

10 Corridor East B/C 18 (E6E.01) Seal to head of door frame with blockwork and make good

11 Corridor East B/C 18 (E6E.01) Investigate damp stain within FHE at B18

12 Corridor East B/C 18 (E6E.01) Install two (2) nozzles to hosereels

13 Corridor East B/C 18 (E6E.01) Make good and seal hole in ceiling slab in FHE

14 Corridor East B/C 18 (E6E.01) Seal LH internal divider wall all round at conduit entry

15 Corridor East B/C 18 (E6E.01) Make good slab inside FHE as concrete deposits and debris etc..

16 Corridor East B/C 18 (E6E 01) Seal around two (2) pipes in the floor slab and make good

Page 256: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 256/407

16 Corridor East B/C 18 (E6E.01) Seal around two (2) pipes in the floor slab and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor South B14/18 (E6E.01) Remove paint from Fire Alarm at Stair Vestibule E6E.16

2 Corridor South B14/18 (E6E.01) Install operator signage to Fire Alarm Button at North Wall near door to Stair Vestibule E6E.03

3 Corridor South B14/18 (E6E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E6E.16

4 Corridor South B14/18 (E6E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E6E.16 North Wall

5 Corridor South B14/18 (E6E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E6E.16

6 Corridor South B14/18 (E6E.01) Install operator signage to Fire Alarm Button at North Wall LH of Stair Vestibule E6E.16

7 Corridor South B14/18 (E6E.01) Make good to large gap between Low Fire Damper Grille and tiling finish on North Wall LH to Stair Vestibule Door E6E.03

8 Corridor South B14/18 (E6E.01) Make good round Fire Damper Grille panel (Upper B 16) on South Wall near Lift Lobby

9 Corridor South B14/18 (E6E.01) Clean paint off grille to Fire Damper panel (Upper B 16) near Lift Lobby

10 Corridor South B14/18 (E6E.01) Provide proper locking device to Upper (B 16) Fire Damper Grille on North Wall near Lift Lobby

11 Corridor South B14/18 (E6E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E6E.03 LH

12 Corridor South B14/18 (E6E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E6E.03 North Wall

13 Corridor South B14/18 (E6E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E6E.03 LH

14 Corridor South B14/18 (E6E.01) Remove paint from Running Man Sign near Stair Vestibule E6E.16

15 Corridor South B14/18 (E6E.01) Make good to damaged arris to RH side of Door to Stair Vestibule E6E.16

Page 257: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 257/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 6 (E6E.03) Remove paint to South Door Frames

2 Stair Vestibule Level 6 (E6E.03) Fit rubber seal all round door South

3 Stair Vestibule Level 6 (E6E.03) Intumescent strip is not complete to open frame and short at base and top to Door South : replace

4 Stair Vestibule Level 6 (E6E.03) Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule Level 6 (E6E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule Level 6 (E6E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule Level 6 (E6E.03) Install door stop to Door South

8 Stair Vestibule Level 6 (E6E.03) Remove remaining protective covering to Door South

9 Stair Vestibule Level 6 (E6E.03) Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule Level 6 (E6E.03) Screw missing in lock plate to door South

11 Stair Vestibule Level 6 (E6E.03) Intumescent strip is not complete to hinge frame as missing to lower part, loose in the upper and short at head to Door South12 Stair Vestibule Level 6 (E6E.03) Intumescent strip on head frame is short at sides of South Door : to be replaced

13 Stair Vestibule Level 6 (E6E.03) Remove labels on South door and make good

14 Stair Vestibule Level 6 (E6E.03) Provide operation label to Door Push Button in Romanian and English

15 Stair Vestibule Level 6 (E6E.03) Remove paint from top edge of skirting on all walls

16 Stair Vestibule Level 6 (E6E 03) Clean paint etc from two (2) light fittings

Page 258: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 258/407

16 Stair Vestibule Level 6 (E6E.03) Clean paint etc from two (2) light fittings

17 Stair Vestibule Level 6 (E6E.03) Clean paint off door frame to Door North

18 Stair Vestibule Level 6 (E6E.03) Clean paint splashes etc on surfaces of Door North

19 Stair Vestibule Level 6 (E6E.03) Intumescent strip is short to head frame and requires to be replaced

20 Stair Vestibule Level 6 (E6E.03) Intumescent strip is not complete to both frame bases of Door North

21 Stair Vestibule Level 6 (E6E.03) Fixing screws to frame protrude and are to be refixed to Door North

22 Stair Vestibule Level 6 (E6E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door North

23 Stair Vestibule Level 6 (E6E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

24 Stair Vestibule Level 6 (E6E.03) Install door stop to Door North

25 Stair Vestibule Level 6 (E6E.03) Fit rubber seal all round door North

26 Stair Vestibule Level 6 (E6E.03) Fire/Smoke Threshold seal is required to door North

27 Stair Vestibule Level 6 (E6E.03) Remove remaining protective covering to Door North

28 Stair Vestibule Level 6 (E6E.03) Remove manufacturer's label on door and adhesive and make good

29 Stair Vestibule Level 6 (E6E.03) Screw missing in lock plate to door North

30 Stair Vestibule Level 6 (E6E.03) Make good to terrazzo skirting to RH side of Door South

31 Stair Vestibule Level 6 (E6E 03) Remove paint to three (3) sprinkler head in ceiling

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 6 (E6E.03) Provide proper locking device to Upper Fire Damper Grille (Upper)

35 Stair Vestibule Level 6 (E6E.03) Make good round Fire Damper Grille panel (Lower)

36 Stair Vestibule Level 6 (E6E.03) Clean paint off grille to Fire Damper panel (Lower)

37 Stair Vestibule Level 6 (E6E.03) Provide proper locking device to Upper Fire Damper Grille (Lower)

38 Stair Vestibule Level 6 (E6E.03) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

39 Stair Vestibule Level 6 (E6E.03) Seal internally around Dry Riser Access Panel and make good

40 Stair Vestibule Level 6 (E6E.03) Remove timber batten in Dry Riser box that is obstructing the efficient usage of the Type C Hose Connection

41 Stair Vestibule Level 6 (E6E.03) Form rounded external corner to terrazzo skirting to LH of door to Egress Stair

42 Stair Vestibule Level 6 (E6E.03) Form rounded external corner to terrazzo skirting to RH of door to Egress Stair

43 Stair Vestibule Level 6 (E6E.03) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

44 Stair Vestibule Level 6 (E6E.03) Tile floor is uneven and needs to be levelled, polished and resealed

45 Stair Vestibule Level 6 (E6E.03) Make good split joint at arris to LH side of door to Egress Stair and repaint

Page 259: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 259/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 6 (E6E.04) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 6 (E6E.04) Remove paint from Running Man Sign and make good

3 Egress Stair Level 6 (E6E.04) Remove paint from Access Car Reader and make good

4 Egress Stair Level 6 (E6E.04) Remove paint etc. from ceiling Smoke Detector and make good

5 Egress Stair Level 6 (E6E.04) Tiled Level 6 Landing floor requires to be levelled, polished and sealed and repair near divide wall to stair

6 Egress Stair Level 6 (E6E.04) Fixing screws to frame protrude and are to be refixed

7 Egress Stair Level 6 (E6E.04) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 6 (E6E.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 6 (E6E.04) Intumescent strip to open door jamb is short and to be replaced

10 Egress Stair Level 6 (E6E.04) Intumescent strip to hinge door jamb is short and to be replaced

11 Egress Stair Level 6 (E6E.04) Rubber infill strip to door is loose at head

12 Egress Stair Level 6 (E6E.04) Install door stop to Door

13 Egress Stair Level 6 (E6E.04) Screw missing at lock plate on door

14 Egress Stair Level 6 (E6E.04) Remove paint on door frames and make good

15 Egress Stair Level 6 (E6E.04) Fire/Smoke seal threshold required to entry door

16 Egress Stair Level 6 (E6E.04) Door signage

Page 260: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 260/407

g ( ) g g

17 Egress Stair Level 6 (E6E.04) Door frame set 12mm above finished floor level and to be reset

18 Egress Stair Level 6 (E6E.04) Door intruder alarm contact wiring to be tidied up

19 Egress Stair Level 6 (E6E.04) Remove all remaining protective covering to door

20 Egress Stair Level 6 (E6E.04) Clean paint etc off light at Landing 621 Egress Stair Level 6 (E6E.04) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

22 Egress Stair Level 6 (E6E.04) Clean light fitting of paint stains etc. at mid landing

23 Egress Stair Level 6 (E6E.04) Make good to open stair stringer to upper stair flight

24 Egress Stair Level 6 (E6E.04) Make good to open stair stringer to lower stair flight

25 Egress Stair Level 6 (E6E.04) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

26 Egress Stair Level 6 (E6E.04) Clean two (2) stair flights between Levels 3 and 4 of black paint and mortar stains complete

27 Egress Stair Level 6 (E6E.04) Clean terrazzo tile at mid landing around the two (2) balustrade supports

28 Egress Stair Level 6 (E6E.04) Reset light fitting at mid landing to level position

29 Egress Stair Level 6 (E6E.04) Clean main landing light of paint splashes etc

30 Egress Stair Level 6 (E6E.04) Replace one (1) chipped step tread

31 Egress Stair Level 6 (E6E 04) Make good to wall paint where repairs carried out to stair skirting

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 6 (E6E.17) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 6 (E6E.17) Remove paint from Running Man Sign and make good

3 Egress Stair Level 6 (E6E.17) Remove paint from Access Car Reader and make good

4 Egress Stair Level 6 (E6E.17) Remove paint on Smoke Detector and make good

5 Egress Stair Level 6 (E6E.17) Tiled Level 4 floor requires to be polished and sealed and repaired where poor workmanship near divide wall to stair

6 Egress Stair Level 6 (E6E.17) Fixing screws to frame protrude and are to be refixed

7 Egress Stair Level 6 (E6E.17) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 6 (E6E.17) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 6 (E6E.17) Intumescent strip to open door jamb is short at base and head and to be replaced

10 Egress Stair Level 6 (E6E.17) Intumescent strip to hinge door jamb is short at base and head and to be replaced

11 Egress Stair Level 6 (E6E.17) Intumescent strip is missing from head frame and requires to be replaced

12 Egress Stair Level 6 (E6E.17) Rubber infill strip to door is missing all round

13 Egress Stair Level 6 (E6E.17) Install door stop to Door

14 Egress Stair Level 6 (E6E.17) Screw missing at lock plate on door

15 Egress Stair Level 6 (E6E.17) Remove paint on door frames and make good

16 Egress Stair Level 6 (E6E.17) Fire/Smoke seal threshold required to entry door

Page 261: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 261/407

17 Egress Stair Level 6 (E6E.17) Door signage

18 Egress Stair Level 6 (E6E.17) Door intruder alarm contacts to be aligned

19 Egress Stair Level 6 (E6E.17) Remove all remaining protective covering to door

20 Egress Stair Level 6 (E6E.17) Tidy up contact wires to door intruder alarm21 Egress Stair Level 6 (E6E.17) Align contacts of door intruder alarm

22 Egress Stair Level 6 (E6E.17) Make good to open stair stringer to upper stair flight

23 Egress Stair Level 6 (E6E.17) Make good to open stair stringer to lower stair flight

24 Egress Stair Level 6 (E6E.17) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

25 Egress Stair Level 6 (E6E.17) Clean two (2) stair flights between Levels 6 and 7 of black paint and mortar stains complete

26 Egress Stair Level 6 (E6E.17) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

27 Egress Stair Level 6 (E6E.17) Door lock is not working properly and to be overhauled

28 Egress Stair Level 6 (E6E.17) Make good to wall finish at LH side of door and repaint

29 Egress Stair Level 6 (E6E.17) Reset Mid landing light so that it is level

30 Egress Stair Level 6 (E6E.17) Clean paint from mid landing light

31 Egress Stair Level 6 (E6E 17) Touch up damaged paintwork to door frames

AMERICA HOUSE

Ref. Location Defect

No.

34 Egress Stair Level 6 (E6E.17) Repoint between floor tiling to mid landing and west wall

35 Egress Stair Level 6 (E6E.17) Clean Landing 6 light of paint etc

36 Egress Stair Level 6 (E6E.17) Re-fix intruder alarm contact to door frame as loose37 Egress Stair Level 6 (E6E.17) Terrazzo skirting is missing to LH of door and to be replaced

38 Egress Stair Level 6 (E6E.17) Repoint to tiles skirting to Lower Stair flight on West Wall

39 Egress Stair Level 6 (E6E.17) Repoint to tiles skirting to Upper Stair flight on East Wall

40 Egress Stair Level 6 (E6E.17) Re-execute skirting to LH side of door as poor workmanship with rounded corners

41 Egress Stair Level 6 (E6E.17) Re-execute skirting to RH side of door as poor workmanship with rounded corners

Page 262: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 262/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E6E.14 Make good the very poor tile grouting etc around floor gulley

2 Toilet E6E.14 Make good to base of RH door frames to floor finish

3 Toilet E6E.14 Make good to base of LH door frames to floor finish 4 Toilet E6E.14 Install door stop

5 Toilet E6E.14 Remove paint on door frames and make good

6 Toilet E6E.14 Fixing screws to frame protrude and are to be refixed to door

7 Toilet E6E.14 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Toilet E6E.14 Screw missing to lock plate on door

9 Toilet E6E.14 Remove all remaining parts of protective covering to door

10 Toilet E6E.14 Install rubber seal around door

11 Toilet E6E.14 Touch up chipped paintwork to door frames

12 Toilet E6E.14 Replace door grill screws (Internal) with white headed screws

13 Toilet E6E.14 Generally clean off excess grouting on wall tiles

14 Toilet E6E.14 Clean grout on floor tiles generally

15 Toilet E6E.14 WHB tap is loose and to be reset properly

16 Toilet E6E.14 Install plug

Page 263: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 263/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E6E.13 Make good tile grouting etc around floor gulley

2 Toilet E6E.13 Install door stop

3 Toilet E6E.13 Remove paint on door frames and make good

4 Toilet E6E.13 Fixing screws to frame protrude and are to be refixed to door

5 Toilet E6E.13 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E6E.13 Screw missing to lock plate on door

7 Toilet E6E.13 Remove all remaining parts of protective covering to door

8 Toilet E6E.13 Install rubber seal around door

9 Toilet E6E.13 Touch up chipped paintwork to door frames

10 Toilet E6E.13 Replace door grill screws (Internal) with white headed screws

11 Toilet E6E.13 Generally clean off excess grouting on wall tiles

12 Toilet E6E.13 Clean grout on floor tiles generally

13 Toilet E6E.13 WHB tap is loose and to be reset properly

14 Toilet E6E.13 Install plug

15 Toilet E6E.13 Touch up missing parts of grouting to wall tiling generally

16 Toilet E6E.13 Clean out at bases of door frames and make good floor finished complete

17 Toilet E6E 13 Make good at joint between wall tiling and floor tiling on south wall

Page 264: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 264/407

17 Toilet E6E.13 Make good at joint between wall tiling and floor tiling on south wall

18 Toilet E6E.13 Make good at joint between wall tiling and floor tiling on west wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E6E.12 Make good tile grouting etc around floor gulley

2 Toilet E6E.12 Install door stop

3 Toilet E6E.12 Remove paint on door frames and make good4 Toilet E6E.12 Fixing screws to frame protrude and are to be refixed to door

5 Toilet E6E.12 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E6E.12 Screw missing to lock plate on door

7 Toilet E6E.12 Remove all remaining parts of protective covering to door

8 Toilet E6E.12 Install rubber seal around door

9 Toilet E6E.12 Touch up chipped paintwork to door frames

10 Toilet E6E.12 Replace door grill screws (Internal) with white headed screws

11 Toilet E6E.12 Generally clean off excess grouting on wall tiles

12 Toilet E6E.12 Clean grout on floor tiles generally

13 Toilet E6E.12 WHB tap is loose and to be reset properly

14 Toilet E6E.12 Install plug

15 Toilet E6E.12 Clean out at bases of door frames and make good floor finished complete

16 Toilet E6E.12 Make good at joint between wall tiling and floor tiling on North wall

17 Toilet E6E.12 Make good at joint between wall tiling and floor tiling on West wall

Page 265: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 265/407

17 Toilet E6E.12 Make good at joint between wall tiling and floor tiling on West wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E6E.11 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E6E.11 Clean excess grouting to tiles generally

3 Handicapped Toilet E6E.11 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E6E.11 Touch up chipped paintwork to door frames

5 Handicapped Toilet E6E.11 Remove paint on door frames and make good

6 Handicapped Toilet E6E.11 Fixing screws to frame protrude and are to be refixed to door

7 Handicapped Toilet E6E.11 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Handicapped Toilet E6E.11 Screw missing to lock plate on door

9 Handicapped Toilet E6E.11 Remove all remaining parts of protective covering to door

10 Handicapped Toilet E6E.11 Clean fan outlet in ceiling of dirt/dust etc.

11 Handicapped Toilet E6E.11 WHB tap is loose and to be reset properly

12 Handicapped Toilet E6E.11 Install plug

13 Handicapped Toilet E6E.11 Replace defective collar seal to WHB tap

14 Handicapped Toilet E6E.11 Install Door stop

15 Handicapped Toilet E6E.11 Install rubber seal around door

16 Handicapped Toilet E6E.11 Clean out at bases to door frames and make good to floor finish

17 Handicapped Toilet E6E 11 Clean general dirt etc in floor pointing and make good

Page 266: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 266/407

17 Handicapped Toilet E6E.11 Clean general dirt etc in floor pointing and make good

18 Handicapped Toilet E6E.11 Repoint to wall tiling where short or insufficient

19 Handicapped Toilet E6E.11 Make good to joint between wall tiling and floor tiling at North wall

20 Handicapped Toilet E6E.11 Make good to joint between wall tiling and floor tiling at South wall21 Handicapped Toilet E6E.11 Make good to joint between wall tiling and floor tiling at West wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Janitor Closet E6E.07 Install protection to water pipe with meter

2 Janitor Closet E6E.07 Replace door grill screws (Internal) with white headed screws

3 Janitor Closet E6E.07 Fixing screws to frame protrude and are to be refixed to door

4 Janitor Closet E6E.07 Cover four (4) protruding screw ends in angle plate to top corner to door

5 Janitor Closet E6E.07 Remove all remaining parts of protective covering to door

6 Janitor Closet E6E.07 Remove paint on door frames and make good

7 Janitor Closet E6E.07 Remove wall paint on trims to suspended ceilings and make good

8 Janitor Closet E6E.07 Redo angle edge to vertical corner to LH of door and make good

9 Janitor Closet E6E.07 Redo angle edge to vertical corner southeast and make good

10 Janitor Closet E6E.07 Make good to joint between wall and floor tiling on South Wall

11 Janitor Closet E6E.07 Make good to joint between wall and floor tiling on West Wall

12 Janitor Closet E6E.07 Make good ceiling trim at Column B16

13 Janitor Closet E6E.07 Install trough

14 Janitor Closet E6E.07 LH tap in wall is loose and requires to be fixed properly

15 Janitor Closet E6E.07 Tidy up loose layout of pipework connected with boiler

16 Janitor Closet E6E.07 RH tap in wall is loose and requires to be fixed properly

17 Janitor Closet E6E.07 Replace two (2) damaged ceiling tiles

Page 267: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 267/407

17 Janitor Closet E6E.07 Replace two (2) damaged ceiling tiles

18 Janitor Closet E6E.07 Make good grouting etc to floor gulley

19 Janitor Closet E6E.07 Install door stop

20 Janitor Closet E6E.07 Make good to floor finish (ceramic tiles) to RH door frame21 Janitor Closet E6E.07 Make good to floor finish (ceramic tiles) to LH door frame

22 Janitor Closet E6E.07 Make good joint between LH side of door and wall finish

23 Janitor Closet E6E.07 Make good joint between RH side of door and wall finish

AMERICA HOUSE

Ref. Location Defect

No.

1 Pantry E6E.06 Wall tiling is generally poor workmanship

2 Pantry E6E.06 Make good joint between wall and floor tiling on North Wall

3 Pantry E6E.06 Clean off excess grouting throughout

4 Pantry E6E.06 Repair boiler leak and install proper safety valve

5 Pantry E6E.06 Fixing screws to frame protrude and are to be refixed to door

6 Pantry E6E.06 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Pantry E6E.06 Screw missing to lock plate on door

8 Pantry E6E.06 Remove all remaining parts of protective covering to door

9 Pantry E6E.06 Replace door grill screws (Internal) with white headed screws

10 Pantry E6E.06 Install rubber seal to door all round

11 Pantry E6E.06 Touch up chipped paintwork to door frames

12 Pantry E6E.06 Redo angle piece on wall tiling at head of door to Janitor Closet

13 Pantry E6E.06 Redo angle piece on wall tiling at external angle to LH of door to Janitor Closet

14 Pantry E6E.06 Redo angle piece on wall tiling at external angle to RH of door to Janitor Closet

15 Pantry E6E.06 Redo angle piece on wall tiling at external angle to soffit of door to Janitor Closet

16 Pantry E6E.06 Reset RH door to upper cabinet on South Wall

17 Pantry E6E.06 Repair damaged floor base unit (RH) damaged by leaking boiler

Page 268: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 268/407

17 Pantry E6E.06 Repair damaged floor base unit (RH) damaged by leaking boiler

18 Pantry E6E.06 Replace damaged suspended ceiling tile

19 Pantry E6E.06 Install plug to sink

20 Pantry E6E.06 Seal floor cabinet units between wall and units LH side and make good (East Wall)21 Pantry E6E.06 Seal floor cabinet units between wall and units RH side and make good (East Wall)

22 Pantry E6E.06 Make good untidy joint between wall tiling and suspended ceiling on North Wall

23 Pantry E6E.06 Install door stop

24 Pantry E6E.06 Install edging to PVC floor covering at door entrance

25 Pantry E6E.06 Make good to floor finishes at base of LH door frame to Vestibule

26 Pantry E6E.06 Make good to floor finishes at base of RH door frame to Vestibule

27 Pantry E6E.06 Reset to level position for power socket outlet (double) at floor level on North Wall

28 Pantry E6E.06 Are suspended ceiling tiles water resistant (pantry has boiling kettles etc.)

29 Pantry E6E.06 Seal floor cabinet units between wall and units LH side and make good (South Wall)

30 Pantry E6E.06 Redo angle piece on wall tiling at external angle between cupboard units in southeast room corner

31 Pantry E6E 06 ]Make good to wall at joint with tiling at southeast corner near wall tiling and just above floor cupboard units

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 7 Lift Lobby E7E.01 Reset Large Grille in ceiling and make good to screw holes etc to the north and repaint

2 Level 7 Lif t Lobby E7E.01 Wall Tiling to East (Lif t) Wall is uneven, not aligned, pointing is distressed and requires to be re-executed

3 Level 7 Lift Lobby E7E.01 Readjust three (3) small downlighters that are not properly aligned and make good

4 Level 7 Lift Lobby E7E.01 Remove paint on ventilation grille large (South)

5 Level 7 Lift Lobby E7E.01 Seal pointing between lift panelling and ceiling PE 09

6 Level 7 Lift Lobby E7E.01 Refit stainless steel skirting to Lift PE 09 that show gaps between the skirting and wall panelling both sides

7 Level 7 Lift Lobby E7E.01 Refit stainless steel skirting to Lift PE 08 that show gaps between the skirting and wall panelling both sides

8 Level 7 Lift Lobby E7E.01 Refit stainless steel skirting to Lift PE 07 that show gaps between the skirting and wall panelling both sides

9 Level 7 Lift Lobby E7E.01 Clean threshold of Lift PE 09

10 Level 7 Lift Lobby E7E.01 Clean threshold of Lift PE 08

11 Level 7 Lift Lobby E7E.01 Clean threshold of Lift PE 07

12 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to LH side of PE09

13 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to RH side of PE09

14 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to LH side of PE08

15 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to RH side of PE08

16 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to LH side of PE07

17 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to LH side of PE09

Page 269: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 269/407

y g p g g p g

18 Level 7 Lift Lobby E7E.01 Make good pointing between wall tiling and lift panelling to RH side of PE07

19 Level 7 Lift Lobby E7E.01 Remove protective covering from base of RH frame to Lift PE08

20 Level 7 Lift Lobby E7E.01 Remove protective covering from base of LH frame to Lift PE09 21 Level 7 Lift Lobby E7E.01 Remove protective covering from base of LH frame to Lift PE08

22 Level 7 Lift Lobby E7E.01 Remove protective covering to lift door frame head LH of Lift PE09

23 Level 7 Lift Lobby E7E.01 Remove protective covering to lift door frame head LH of Lift PE08

24 Level 7 Lift Lobby E7E.01 Remove protective covering to lift door frame head LH of Lift PE07

25 Level 7 Lift Lobby E7E.01 Remove paint on three (3) small ceiling downlighters and make good

26 Level 7 Lift Lobby E7E.01 Remove paint on eight (8) sprinkler heads in ceiling

27 Level 7 Lift Lobby E7E.01 Infill gap at head of lift panel lining to Lift PE08

28 Level 7 Lift Lobby E7E.01 Infill gap at head of lift panel lining to Lift PE07

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor North C14/18 (E7E.01) Remove paint on Fire Alarm LH of door to Stair Vestibule E7E.03

2 Corridor North C14/18 (E7E.01) Install operator signage to Fire Alarm Button at South Wall near door to Stair Vestibule E7E.03

3 Corridor North C14/18 (E7E.01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby4 Corridor North C14/18 (E7E.01) Clean paint off grille to Fire Damper panel (Lower) near Lift Lobby

5 Corridor North C14/18 (E7E.01) Provide proper locking device to Low Fire Damper Grille on South Wall near Lift Lobby

6 Corridor North C14/18 (E7E.01) Install operator signage to Fire Alarm Button at South Wall RH of Service Elevator Vestibule

7 Corridor North C14/18 (E7E.01) Install operator signage to Door Release Button at South Wall to RH of Service Elevator Vestibule

8 Corridor North C14/18 (E7E.01) Install break glass to Emergency Door Release Button on South Wall to RH of Service Elevator Vestibule

9 Corridor North C14/18 (E7E.01) Remove paint from Running Man Sign above door to Stair Vestibule E7E.16

10 Corridor North C14/18 (E7E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby

11 Corridor North C14/18 (E7E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby

12 Corridor North C14/18 (E7E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on South Wall near Lift Lobby

13 Corridor North C14/18 (E7E.01) Make good round Fire Damper Grille panel (Low) on South Wall near to RH side of Service Elevator Lobby

14 Corridor North C14/18 (E7E.01) Clean paint off grille to Fire Damper panel (Lower) to RH side of Service Lift Lobby

15 Corridor North C14/18 (E7E.01) Provide proper locking device to Low Fire Damper Grille on South Wall to RH side of Service Lift Lobby

16 Corridor North C14/18 (E7E.01) point ceiling finish around Running Man Sign near Stair Vestibule E7E.16

Page 270: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 270/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor East B/C 18(E7E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor East B/C 18(E7E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor East B/C 18(E7E.01) Make good round Fire Damper Grille panel C14 East Wall near Fire Hose reel Enclosure (FHE)4 Corridor East B/C 18(E7E.01) Clean paint off grille to Fire Damper panel C14 near FHE

5 Corridor East B/C 18(E7E.01) Provide proper locking device to C14 Fire Damper Grille on East Wall near FHE

6 Corridor East B/C 18(E7E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box

7 Corridor East B/C 18(E7E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor East B/C 18(E7E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor East B/C 18(E7E.01) Build up blockwork below threshold and seal to door

10 Corridor East B/C 18(E7E.01) Seal to head of door frame with blockwork and make good

11 Corridor East B/C 18(E7E.01) Divider Wall to RH to be sealed full length to back wall

12 Corridor East B/C 18(E7E.01) Seal wall at RH side of enclosure for waste pipe and make good

13 Corridor East B/C 18(E7E.01) Seal two holes in ceiling slab within FHE and make good

14 Corridor East B/C 18(E7E.01) Seal around conduit to RH side of FHE internally on LH Divider wall

15 Corridor East B/C 18(E7E.01) Make good to wall below Fire Damper Grill near Door to Stair Vestibule E7E.03

16 Corridor East B/C 18(E7E.01) Renew defective lock to Fire Hose reel Enclosure (FHE)

17 Corridor East B/C 18(E7E.01) Fit two (2) nozzles to hosereels

Page 271: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 271/407

18 Corridor East B/C 18(E7E.01) Remove hardboard shim to LH side of FHE door frame

19 Corridor East B/C 18(E7E.01) Divider Wall to RH to be sealed at top and made good

20 Corridor East B/C 18(E7E.01) Seal and make good to void for pipes in ceiling slab21 Corridor East B/C 18(E7E.01) Seal and make good to large pipe above FHE Door on RH side inside

22 Corridor East B/C 18(E7E.01) Seal ends of RH Divider wall in FHE and make good

23 Corridor East B/C 18(E7E.01) Remove loose frame fixing metal fastener to LH side frame and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor West B/C 14 (E7E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor West B/C 14 (E7E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor West B/C 14 (E7E.01) Make good round Fire Damper Grille panel B18 East Wall near Fire Hose reel Enclosure (FHE)4 Corridor West B/C 14 (E7E.01) Clean paint off grille to Fire Damper panel B19 near FHE

5 Corridor West B/C 14 (E7E.01) Provide proper locking device to B18 Fire Damper Grille on East Wall near FHE

6 Corridor West B/C 14 (E7E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box as key is missing

7 Corridor West B/C 14 (E7E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor West B/C 14 (E7E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor West B/C 14 (E7E.01) Build up blockwork below threshold and seal to door

10 Corridor West B/C 14 (E7E.01) Seal to head of door frame with blockwork and make good

11 Corridor West B/C 14 (E7E.01) Divider Wall to LH to be sealed full length to back wall

12 Corridor West B/C 14 (E7E.01) Remove three electrical cables (used by Ozer during construction) and make good to all holes

13 Corridor West B/C 14 (E7E.01) Seal two holes in ceiling slab within FHE and make good

14 Corridor West B/C 14 (E7E.01) Seal around hole to RH side of FHE internally near concrete beam

15 Corridor West B/C 14 (E7E.01) Make good slab inside FHE as concrete deposits and debris etc..

16 Corridor West B/C 14 (E7E.01) Seal around two (2) pipes in the floor slab and make good

17 Corridor West B/C 14 (E7E.01) Fit two (2) nozzles to hosereels

Page 272: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 272/407

18 Corridor West B/C 14 (E7E.01) Remove small electrical cable used by Ozer during construction and make good to floor and ceiling slab when removed

19 Corridor West B/C 14 (E7E.01) Make good to blockwork above door on RH side of front wall

20 Corridor West B/C 14 (E7E.01) Seal sides of RH Divider wall at back and front and make good21 Corridor West B/C 14 (E7E.01) Seal LH Divider wall at top and make good

22 Corridor West B/C 14 (E7E.01) Make good to wall plaster finish to LH side of external door frames to FHE

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor South B14/18 (E7E.01) Install operator signage to Fire Alarm Button at North Wall near door to Stair Vestibule E7E.03

2 Corridor South B14/18 (E7E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E7E.16

3 Corridor South B14/18 (E7E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E7E.16 North Wall4 Corridor South B14/18 (E7E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E7E.16

5 Corridor South B14/18 (E7E.01) Install operator signage to Fire Alarm Button at North Wall LH of Stair Vestibule E7E.16

6 Corridor South B14/18 (E7E.01) Install operator signage to Fire Alarm Button at North Wall LH of Stair Vestibule E7E.16

7 Corridor South B14/18 (E7E.01) Make good to large gap between Low Fire Damper Grille and tiling finish on North Wall LH to Stair Vestibule Door E7E.03

8 Corridor South B14/18 (E7E.01) Make good round Fire Damper Grille panel (Upper B 16) on South Wall near Lift Lobby

9 Corridor South B14/18 (E7E.01) Clean paint off grille to Fire Damper panel (Upper B 16) near Lift Lobby

10 Corridor South B14/18 (E7E.01) Provide proper locking device to Upper (B 16) Fire Damper Grille on North Wall near Lift Lobby

11 Corridor South B14/18 (E7E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E7E.03 LH

12 Corridor South B14/18 (E7E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E7E.03 North Wall

13 Corridor South B14/18 (E7E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E74E.03 LH

Page 273: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 273/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 7 (E7E.03) Remove paint to South Door Frames

2 Stair Vestibule Level 7 (E7E.03) Fit rubber seal all round door South

3 Stair Vestibule Level 7 (E7E.03) Intumescent strip to open frame is short to both head and base to Door South : to be replaced4 Stair Vestibule Level 7 (E7E.03) Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule Level 7 (E7E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule Level 7 (E7E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule Level 7 (E7E.03) Install door stop to Door South

8 Stair Vestibule Level 7 (E7E.03) Remove remaining protective covering to Door South

9 Stair Vestibule Level 7 (E7E.03) Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule Level 7 (E7E.03) Screw missing in lock plate to door South

11 Stair Vestibule Level 7 (E7E.03) Intumescent strip is not complete to hinge frame as short at base to Door South and to be replaced

12 Stair Vestibule Level 7 (E7E.03) Intumescent strip to hinge frame is missing below the prong receiver

13 Stair Vestibule Level 7 (E7E.03) Change to permanent lockset

14 Stair Vestibule Level 7 (E7E.03) Tiled floor is uneven and discoloured and required to be levelled, polished and sealed

15 Stair Vestibule Level 7 (E7E.03) Floor tiling at Door South is incomplete

16 Stair Vestibule Level 7 (E7E.03) South light is not working and to be repaired

17 Stair Vestibule Level 7 (E7E.03) Provide operation label to Door Push Button in Romanian and English

18 St i V tib l L l 7 (E7E 03) R i t f t d f ki ti ll ll

Page 274: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 274/407

18 Stair Vestibule Level 7 (E7E.03) Remove paint from top edge of skirting on all walls

19 Stair Vestibule Level 7 (E7E.03) Clean paint etc from two (2) light fittings

20 Stair Vestibule Level 7 (E7E.03) Clean paint off door frame to Door North21 Stair Vestibule Level 7 (E7E.03) Clean paint splashes etc on surfaces of Door North

22 Stair Vestibule Level 7 (E7E.03) Intumescent strip is short to head frame and requires to be replaced

23 Stair Vestibule Level 7 (E7E.03) Intumescent strip is not complete to both frame bases of Door North

24 Stair Vestibule Level 7 (E7E.03) Fixing screws to frame protrude and are to be refixed to Door North

25 Stair Vestibule Level 7 (E7E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door North

26 Stair Vestibule Level 7 (E7E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

27 Stair Vestibule Level 7 (E7E.03) Install door stop to Door North

28 Stair Vestibule Level 7 (E7E.03) Fit rubber seal all round door North

29 Stair Vestibule Level 7 (E7E.03) Fire/Smoke Threshold seal is required to door North

30 Stair Vestibule Level 7 (E7E.03) Remove remaining protective covering to Door North

31 Stair Vestibule Level 7 (E7E 03) Form rounded external corner to terrazzo skirting to RH of door to Egress Stair

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 7 (E7E.03) Screw missing in lock plate to door North

35 Stair Vestibule Level 7 (E7E.03) Make good to terrazzo skirting to RH side of Door South

36 Stair Vestibule Level 7 (E7E.03) Remove paint to three (3) sprinkler head in ceiling37 Stair Vestibule Level 7 (E7E.03) Make good round Fire Damper Grille panel (Upper)

38 Stair Vestibule Level 7 (E7E.03) Clean paint off grille to Fire Damper panel (Upper)

39 Stair Vestibule Level 7 (E7E.03) Provide proper locking device to Upper Fire Damper Grille (Upper)

40 Stair Vestibule Level 7 (E7E.03) Make good round Fire Damper Grille panel (Lower)

41 Stair Vestibule Level 7 (E7E.03) Clean paint off grille to Fire Damper panel (Lower)

42 Stair Vestibule Level 7 (E7E.03) Provide proper locking device to Upper Fire Damper Grille (Lower)

43 Stair Vestibule Level 7 (E7E.03) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

44 Stair Vestibule Level 7 (E7E.03) Seal internally around Dry Riser Access Panel and make good

45 Stair Vestibule Level 7 (E7E.03) Door to Dry Riser hatch is missing and to be replaced

46 Stair Vestibule Level 7 (E7E.03) Seal internally around Dry Riser Access Panel and make good

47 Stair Vestibule Level 7 (E7E.03) Form rounded external corner to terrazzo skirting to LH of door to Egress Stair

48 Stair Vestibule Level 7 (E7E.03) Make good to poor workmanship to terrazzo tiling at RH of North Door

Page 275: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 275/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 7 (E7E.04) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 7 (E7E.04) Remove paint etc. from ceiling Smoke Detector and make good

3 Egress Stair Level 7 (E7E.04) Tiled Level 3 floor requires to be levelled, polished and sealed and repaired including workmanship near divide wall to stair4 Egress Stair Level 7 (E7E.04) Door to be adjusted as squeaks badly

5 Egress Stair Level 7 (E7E.04) Closer not really strong enough to close the door

6 Egress Stair Level 7 (E7E.04) Fixing screws to frame protrude and are to be refixed

7 Egress Stair Level 7 (E7E.04) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 7 (E7E.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 7 (E7E.04) Intumescent strip to open door jamb is short at head and base and to be replaced

10 Egress Stair Level 7 (E7E.04) Intumescent strip to hinge door jamb is short at head and base and to be replaced

11 Egress Stair Level 7 (E7E.04) Rubber infill strip to door is loose at head

12 Egress Stair Level 7 (E7E.04) Install door stop to Door

13 Egress Stair Level 7 (E7E.04) Screw missing at lock plate on door

14 Egress Stair Level 7 (E7E.04) Remove paint on door frames and make good

15 Egress Stair Level 7 (E7E.04) Fire/Smoke seal threshold required to entry door

16 Egress Stair Level 7 (E7E.04) Door signage

17 Egress Stair Level 7 (E7E.04) Door intruder alarm contacts to be aligned

18 Egress Stair Level 7 (E7E 04) Door intruder alarm contact wiring to be tidied up

Page 276: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 276/407

18 Egress Stair Level 7 (E7E.04) Door intruder alarm contact wiring to be tidied up

19 Egress Stair Level 7 (E7E.04) Remove all remaining protective covering to door

20 Egress Stair Level 7 (E7E.04) Replace key sets with correct set

21 Egress Stair Level 7 (E7E.04) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

22 Egress Stair Level 7 (E7E.04) Clean light fitting of paint stains etc. at mid landing

23 Egress Stair Level 7 (E7E.04) Make good to open stair stringer to upper stair flight

24 Egress Stair Level 7 (E7E.04) Make good to open stair stringer to lower stair flight

25 Egress Stair Level 7 (E7E.04) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

26 Egress Stair Level 7 (E7E.04) Clean two (2) stair flights between Levels 3 and 4 of black paint and mortar stains complete

27 Egress Stair Level 7 (E7E.04) Clean terrazzo tile at mid landing around the two (2) balustrade supports

28 Egress Stair Level 7 (E7E.04) Reset light fitting at mid landing to level position

29 Egress Stair Level 7 (E7E.04) Clean main landing light of paint splashes etc30 Egress Stair Level 7 (E7E.04) Reset Light to Landing & and make level

31 Egress Stair Level 7 (E7E 04) Make good to hole repair on South wall to LH of Loudspeaker

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 7 (E7E.16) Remove paint to South Door Frames

2 Stair Vestibule Level 7 (E7E.16) Fit rubber seal all round door South

3 Stair Vestibule Level 7 (E7E.16) Intumescent strip is short to both frame bases to Door South : replace4 Stair Vestibule Level 7 (E7E.16) Intumescent strip is not complete to base of open frame of Door South

5 Stair Vestibule Level 7 (E7E.16) Fixing screws to frame protrude and are to be refixed to Door South

6 Stair Vestibule Level 7 (E7E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door South

7 Stair Vestibule Level 7 (E7E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

8 Stair Vestibule Level 7 (E7E.16) Install door stop to Door South

9 Stair Vestibule Level 7 (E7E.16) Remove remaining protective covering to Door South

10 Stair Vestibule Level 7 (E7E.16) Install fire/smoke seal threshold plate to Door South

11 Stair Vestibule Level 7 (E7E.16) Screw missing in lock plate to door South

12 Stair Vestibule Level 7 (E7E.16) Install door closer to Door South

13 Stair Vestibule Level 7 (E7E.16) W hy are there locks on Stair Egress Doors operated with Card Reader Access and Release Push button ?

14 Stair Vestibule Level 7 (E7E.16) Terrazzo tile floor is uneven and needs to be levelled, polished and resealed

15 Stair Vestibule Level 7 (E7E.16) Make good to LH return of terrazzo skirting at Egress Stair door with rounded external angle

16 Stair Vestibule Level 7 (E7E.16) Provide operation label to Door Push Button in Romanian and English

17 Stair Vestibule Level 7 (E7E.16) Remove paint etc. from top edge of skirting on all walls

18 Stair Vestibule Level 7 (E7E 16) Replace damaged strike plate to Door South

Page 277: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 277/407

18 Stair Vestibule Level 7 (E7E.16) Replace damaged strike plate to Door South

19 Stair Vestibule Level 7 (E7E.16) Reset double power socket outlet near Door South on East wall to be level

20 Stair Vestibule Level 7 (E7E.16) Clean paint etc from two (2) light fittings

21 Stair Vestibule Level 7 (E7E.16) Screw missing from door lock plate on Door North

22 Stair Vestibule Level 7 (E7E.16) Clean paint off door frame to Door North

23 Stair Vestibule Level 7 (E7E.16) Touch up chipped paintwork to door frames Door North

24 Stair Vestibule Level 7 (E7E.16) Intumescent strip is not complete to both frame bases of Door North

25 Stair Vestibule Level 7 (E7E.16) Intumescent strip is loose at the prong receiver on the hinge frame and to be re-installed to Door North

26 Stair Vestibule Level 7 (E7E.16) Fixing screws to frame protrude and are to be refixed to Door North

27 Stair Vestibule Level 7 (E7E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door North

28 Stair Vestibule Level 7 (E7E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

29 Stair Vestibule Level 7 (E7E.16) Install door stop to Door North30 Stair Vestibule Level 7 (E7E.16) Fit rubber seal all round door North

31 Stair Vestibule Level 7 (E7E 16) Fire/Smoke Threshold seal is required to door North

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 7 (E7E.16) Touch up damaged paintwork to door frames of Door South

35 Stair Vestibule Level 7 (E7E.16) Make good to floor and finish to LH Side frame of Door South

36 Stair Vestibule Level 7 (E7E.16) Remove all remaining parts of protective covering to door North37 Stair Vestibule Level 7 (E7E.16) Remove paint to three (3) sprinkler head in ceiling and make good

38 Stair Vestibule Level 7 (E7E.16) Make good round Fire Damper Grille panel (Upper)

39 Stair Vestibule Level 7 (E7E.16) Clean paint off grille to Fire Damper panel (Upper)

40 Stair Vestibule Level 7 (E7E.16) Provide proper locking device to Upper Fire Damper Grille (Upper)

41 Stair Vestibule Level 7 (E7E.16) Make good round Fire Damper Grille panel (Lower)

42 Stair Vestibule Level 7 (E7E.16) Clean paint off grille to Fire Damper panel (Lower)

43 Stair Vestibule Level 7 (E7E.16) Provide proper locking device to Upper Fire Damper Grille (Lower)

44 Stair Vestibule Level 7 (E7E.16) Make good to skirting to LH of Door South

45 Stair Vestibule Level 7 (E7E.16) Make good to skirting to LH of Door North

46 Stair Vestibule Level 7 (E7E.16) Make good to skirting to RH of Door North

47 Stair Vestibule Level 7 (E7E.16) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

48 Stair Vestibule Level 7 (E7E.16) Remove paint from Running Man Sign and make good

49 Stair Vestibule Level 7 (E7E.16) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

50 Stair Vestibule Level 7 (E7E.16) Seal internally around Dry Riser Access Panel and make good

51 Stair Vestibule Level 7 (E7E.16) Replace missing hatch door to Dry Riser

Page 278: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 278/407

52 Stair Vestibule Level 7 (E7E.16) Make good to damaged skirting to LH side of door to Egress Stair and repaint as required

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 7 (E7E.17) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 7 (E7E.17) Remove paint from Running Man Sign and make good

3 Egress Stair Level 7 (E7E.17) Align Access Car Reader level and make good4 Egress Stair Level 7 (E7E.17) Remove paint on Smoke Detector and make good

5 Egress Stair Level 7 (E7E.17) Tiled Level 7 floor requires to be polished and sealed and repaired and where poor workmanship near divide wall to stair

6 Egress Stair Level 7 (E7E.17) Fixing screws to f rame protrude and are to be refixed

7 Egress Stair Level 7 (E7E.17) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 7 (E7E.17) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 7 (E7E.17) Intumescent strip to open door jamb is short at base and strike plate, also loose and to be replaced

10 Egress Stair Level 7 (E7E.17) Intumescent strip to hinge door jamb is short at base and head and to be replaced

11 Egress Stair Level 7 (E7E.17) Door catches on Egress Stair landing floor : adjust so that it does not catch

12 Egress Stair Level 7 (E7E.17) Rubber infill strip to door is loose at head

13 Egress Stair Level 7 (E7E.17) Install door stop to Door

14 Egress Stair Level 7 (E7E.17) Screw missing at lock plate on door

15 Egress Stair Level 7 (E7E.17) Remove paint on door frames and make good

16 Egress Stair Level 7 (E7E.17) Fire/Smoke seal threshold required to entry door

17 Egress Stair Level 7 (E7E.17) Door signage

18 Egress Stair Level 7 (E7E.17) Door intruder alarm contacts to be aligned

Page 279: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 279/407

g ( ) g

19 Egress Stair Level 7 (E7E.17) Remove all remaining protective covering to door

20 Egress Stair Level 7 (E7E.17) Tidy up contact wires to door intruder alarm

21 Egress Stair Level 7 (E7E.17) Align contacts of door intruder alarm

22 Egress Stair Level 7 (E7E.17) Make good to open stair stringer to upper stair flight

23 Egress Stair Level 7 (E7E.17) Make good to open stair stringer to lower stair flight

24 Egress Stair Level 7 (E7E.17) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

25 Egress Stair Level 7 (E7E.17) Clean two (2) stair flights between Levels 3 and 4 of black paint and mortar stains complete

26 Egress Stair Level 7 (E7E.17) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

27 Egress Stair Level 7 (E7E.17) Fix contact plate for Access Control on door to door more tightly

28 Egress Stair Level 7 (E7E.17) Make good to terrazzo skirting damaged to LH side of Door and repaint as required

29 Egress Stair Level 7 (E7E.17) Repoint between wall finish and LH side of door and repaint30 Egress Stair Level 7 (E7E.17) Clean paint from mid landing light

31 Egress Stair Level 7 (E7E 17) Clean paint from light on Landing 7

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule Level 7 (E7E.05) Remove paint to three sprinkler heads

2 Vestibule Level 7 (E7E.05) Make good to floor and finish at frames bases of Door South

3 Vestibule Level 7 (E7E.05) Remove paint to South Door Frames4 Vestibule Level 7 (E7E.05) Fit rubber seal all round door South

5 Vestibule Level 7 (E7E.05) Intumnescent strip is not installed to side or head frames

6 Vestibule Level 7 (E7E.05) Fixing screws to frame protrude and are to be refixed to Door South

7 Vestibule Level 7 (E7E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door South

8 Vestibule Level 7 (E7E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Vestibule Level 7 (E7E.05) Install door stop to Door South

10 Vestibule Level 7 (E7E.05) Remove remaining protective covering to Door South

11 Vestibule Level 7 (E7E.05) Install fire/smoke seal threshold plate to Door South

12 Vestibule Level 7 (E7E.05) Screw missing in lock plate to door South

13 Vestibule Level 7 (E7E.05) Install door closer to Door South

14 Vestibule Level 7 (E7E.05) Install edging and recut floor covering to door South threshold

15 Vestibule Level 7 (E7E.05) Clean paint off door frame to Door North

16 Vestibule Level 7 (E7E.05) Intumescent strip is installed to side or head frames of Door North

17 Vestibule Level 7 (E7E.05) Fixing screws to frame protrude and are to be refixed to Door North

18 Vestibule Level 7 (E7E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door North

Page 280: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 280/407

19 Vestibule Level 7 (E7E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

20 Vestibule Level 7 (E7E.05) Install door stop to Door North

21 Vestibule Level 7 (E7E.05) Fit rubber seal all round door North

22 Vestibule Level 7 (E7E.05) Fire/Smoke Threshold seal is required to door North

23 Vestibule Level 7 (E7E.05) Install door closer to Door North

24 Vestibule Level 7 (E7E.05) Remove all remaining parts of protective covering to door

25 Vestibule Level 7 (E7E.05) Screw missing in lock plate to door North

26 Vestibule Level 7 (E7E.05) Replace missing external angle skirting corner piece to LH of Door to Handicapped Toilet E7E.15

27 Vestibule Level 7 (E7E.05) Replace missing external angle skirting corner piece to LH of Door to Pantry

28 Vestibule Level 7 (E7E.05) Replace missing external angle skirting corner piece to RH of Door to Pantry

29 Vestibule Level 7 (E7E.05) Replace missing external angle skirting corner piece to RH of Door to Vestibule E7E.0830 Vestibule Level 7 (E7E.05) Replace missing skirting to LH side return to Pantry Door

31 Vestibule Level 7 (E7E 05) Refix skirting on East Wall South End

AMERICA HOUSE

Ref. Location Defect

No.

34 Vestibule Level 7 (E7E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet 74E.11

35 Vestibule Level 7 (E7E.05) Install edging strip between PVC floor covering and ti le f loor f inish to Toilet E7E.12

36 Vestibule Level 7 (E7E.05) Install edging strip between PVC floor covering and ti le f loor f inish to Toilet E7E.13

37 Vestibule Level 7 (E7E.05) Install edging strip between PVC floor covering and ti le f loor f inish to Toilet E7E.14

38 Vestibule Level 7 (E7E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E7E.15

39 Vestibule Level 7 (E7E.05) Refix all skirting as attached with panel pins with adhesive or clip-on system

40 Vestibule Level 7 (E7E.05) Clean paint and dirt on Smoke Detector

Page 281: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 281/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E7E.15 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E7E.15 Clean excess grouting to wall tiles generally

3 Handicapped Toilet E7E.15 Replace door grill screws (Internal) with white headed screws4 Handicapped Toilet E7E.15 Make good to floor finish at LH Base Frame of door

5 Handicapped Toilet E7E.15 Make good to floor finish at RH Base Frame of door

6 Handicapped Toilet E7E.15 Remove paint on door frames and make good

7 Handicapped Toilet E7E.15 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E7E.15 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E7E.15 Screw missing to lock plate on door

10 Handicapped Toilet E7E.15 Remove all remaining parts of protective covering to door

11 Handicapped Toilet E7E.15 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E7E.15 WHB tap is loose and to be reset properly13 Handicapped Toilet E7E.15 Install plug

14 Handicapped Toilet E7E.15 Install Door stop

15 Handicapped Toilet E7E.15 Install rubber seal around door

16 Handicapped Toilet E7E.15 Clean general dirt etc in floor pointing and make good

17 Handicapped Toilet E7E.15 Repoint to wall tiling where short or insufficient

18 Handicapped Toilet E7E.15 Make good to tiled floor finish to door frame bases LH

19 Handicapped Toilet E7E 15 Make good to tiled floor finish to door frame bases RH

Page 282: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 282/407

19 Handicapped Toilet E7E.15 Make good to tiled floor finish to door frame bases RH

20 Handicapped Toilet E7E.15 Make good to joint between wall and floor tiling on South Wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E7E.14 Make good the poor tile grouting etc around floor gulley

2 Toilet E7E.14 Make good to base of RH door frames to floor finish

3 Toilet E7E.14 Make good to base of LH door frames to floor finish

4 Toilet E7E.14 Install door stop

5 Toilet E7E.14 Remove paint on door frames and make good

6 Toilet E7E.14 Fixing screws to frame protrude and are to be refixed to door

7 Toilet E7E.14 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Toilet E7E.14 Screw missing to lock plate on door

9 Toilet E7E.14 Remove all remaining parts of protective covering to door

10 Toilet E7E.14 Install rubber seal around door

11 Toilet E7E.14 Touch up chipped paintwork to door frames

12 Toilet E7E.14 Replace door grill screws (Internal) with white headed screws13 Toilet E7E.14 Generally clean off excess grouting on wall tiles

14 Toilet E7E.14 Clean grout on floor tiles generally

15 Toilet E7E.14 WHB tap is loose and to be reset properly

16 Toilet E7E.14 Install plug

17 Toilet E7E.14 Make good to joint between wall and floor tiling finish on West wall

Page 283: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 283/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E7E.13 Make good tile grouting etc around floor gulley

2 Toilet E7E.13 Install door stop

3 Toilet E7E.13 Remove paint on door frames and make good

4 Toilet E7E.13 Fixing screws to frame protrude and are to be refixed to door

5 Toilet E7E.13 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E7E.13 Screw missing to lock plate on door

7 Toilet E7E.13 Remove all remaining parts of protective covering to door

8 Toilet E7E.13 Install rubber seal around door

9 Toilet E7E.13 Touch up chipped paintwork to door frames

10 Toilet E7E.13 Replace door grill screws (Internal) with white headed screws

11 Toilet E7E.13 Generally clean off excess grouting on wall tiles

12 Toilet E7E.13 Clean grout on floor tiles generally13 Toilet E7E.13 WHB tap is loose and to be reset properly

14 Toilet E7E.13 Install plug

15 Toilet E7E.13 Touch up missing parts of grouting to wall tiling generally

16 Toilet E7E.13 Clean out at bases of door frame LH and make good floor finished complete

17 Toilet E7E.13 Clean out at bases of door frame RH and make good floor finished complete

18 Toilet E7E.13 Make good at joint between wall tiling and floor tiling on south wall

19 Toilet E7E.13 Make good at joint between wall tiling and floor tiling on west wall

Page 284: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 284/407

19 Toilet E7E.13 Make good at joint between wall tiling and floor tiling on west wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E7E.12 Make good tile grouting etc around floor gulley

2 Toilet E7E.12 Install door stop

3 Toilet E7E.12 Remove paint on door frames and make good

4 Toilet E7E.12 Fixing screws to frame protrude and are to be refixed to door

5 Toilet E7E.12 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E7E.12 Screw missing to lock plate on door

7 Toilet E7E.12 Remove all remaining parts of protective covering to door

8 Toilet E7E.12 Install rubber seal around door

9 Toilet E7E.12 Touch up chipped paintwork to door frames

10 Toilet E7E.12 Replace door grill screws (Internal) with white headed screws

11 Toilet E7E.12 Generally clean off excess grouting on wall tiles

12 Toilet E7E.12 Clean grout on floor tiles generally13 Toilet E7E.12 WHB tap is loose and to be reset properly

14 Toilet E7E.12 Install plug

15 Toilet E7E.12 Clean out at bases of door frame LH and make good floor finished complete

16 Toilet E7E.12 Clean out at bases of door frame RH and make good floor finished complete

17 Toilet E7E.12 Make good at joint between wall tiling and floor tiling on North wall

18 Toilet E7E.12 Make good at joint between wall tiling and floor tiling on South wall

Page 285: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 285/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E7E.11 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E7E.11 Clean excess grouting to tiles generally

3 Handicapped Toilet E7E.11 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E7E.11 Touch up chipped paintwork to door frames

5 Handicapped Toilet E7E.11 Remove paint on door frames and make good

6 Handicapped Toilet E7E.11 Fixing screws to frame protrude and are to be refixed to door

7 Handicapped Toilet E7E.11 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Handicapped Toilet E7E.11 Screw missing to lock plate on door

9 Handicapped Toilet E7E.11 Remove all remaining parts of protective covering to door

10 Handicapped Toilet E7E.11 WHB tap is loose and to be reset properly

11 Handicapped Toilet E7E.11 Install plug to sink

12 Handicapped Toilet E7E.11 Install Door stop13 Handicapped Toilet E7E.11 Install rubber seal around door

14 Handicapped Toilet E7E.11 Clean out at bases to door frames and make good to floor finish

15 Handicapped Toilet E7E.11 Clean general dirt etc in floor pointing and make good

16 Handicapped Toilet E7E.11 Repoint to wall tiling where short or insufficient

17 Handicapped Toilet E7E.11 Make good to joint between wall tiling and floor tiling at North wall

18 Handicapped Toilet E7E.11 Make good to joint between wall tiling and floor tiling at South wall

19 Handicapped Toilet E7E.11 Make good to joint between wall tiling and floor tiling at West wall

Page 286: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 286/407

pp g j g g

20 Handicapped Toilet E7E.11 Make good to joint between wall tiling and floor tiling at East wall

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Elevator Vestibule (E7E.18) Prepare for and paint ceiling

2 Service Elevator Vestibule (E7E.18) Remove paint on Access Card Reader

3 Service Elevator Vestibule (E7E.18) Remove paint stains on floor covering generally 4 Service Elevator Vestibule (E7E.18) Fill in hole to door head frame

5 Service Elevator Vestibule (E7E.18) Remove paint splashes etc on doors

6 Service Elevator Vestibule (E7E.18) Fixing screws to frame protrude and are to be refixed to Door

7 Service Elevator Vestibule (E7E.18) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Service Elevator Vestibule (E7E.18) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestibule (E7E.18) Intumescent strip is short on both side frames and requires to be replaced

10 Service Elevator Vestibule (E7E.18) Install door stops to Doors

11 Service Elevator Vestibule (E7E.18) Clean paint off Door Frames

12 Service Elevator Vestibule (E7E.18) Door Signage

13 Service Elevator Vestibule (E7E.18) Fire/Smoke Threshold seal is required to door

14 Service Elevator Vestibule (E7E.18) Install closers with selector on doors

15 Service Elevator Vestibule (E7E.18) Remove all remaining parts of the protective covering to doors

16 Service Elevator Vestibule (E7E.18) Install rubber seal to door

17 Service Elevator Vestibule (E7E.18) Intumescent strip to meeting style is not continuous and missing at door lock

18 Service Elevator Vestibule (E7E.18) Realign door intruder alarm contacts and fix head frame contact which is loose

19 Service Elevator Vestibule (E7E.18) Inner leaf of door has too much play when closed and to be adjusted

Page 287: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 287/407

9 Se ce e ato est bu e ( 8) e ea o doo as too uc p ay e c osed a d to be adjusted

20 Service Elevator Vestibule (E7E.18) Tidy up wiring to door intruder contact

21 Service Elevator Vestibule (E7E.18) Screw missing form door locking plate

22 Service Elevator Vestibule (E7E.18) Reconnect outer leaf door closer

23 Service Elevator Vestibule (E7E.18) Touch up to damaged paintwork to door frames generally

24 Service Elevator Vestibule (E7E.18) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

25 Service Elevator Vestibule (E7E.18) Relay floor covering that is distorted and 'bubbled' and prepare floor screed below

26 Service Elevator Vestibule (E7E.18) Replace external angle skirting corner piece to LH side of lift entrance return

27 Service Elevator Vestibule (E7E.18) Replace missing skirting and external angle corner piece to RH side of lift entrance return

28 Service Elevator Vestibule (E7E.18) Replace inner leaf bolt insert to head frame that has been damaged by the door operation

29 Service Elevator Vestibule (E7E.18) Paint sprinkler pipework30 Service Elevator Vestibule (E7E.18) Tidy up joint at sprinkler head and elbow joints including removing excess joint hemp fibres on sprinkler pipework

31 Service Elevator Vestibule (E7E 18) Replace screws at grille to LH side with white headed screws as elsewhere

AMERICA HOUSE

Ref. Location Defect

No.

34 Service Elevator Vestibule (E7E.18) Seal and make good to one (1) sprinkler pipe in northeast corner at near ceiling level

35 Service Elevator Vestibule (E7E.18) Refix loose skirting on West Wall

36 Service Elevator Vestibule (E7E.18) Remove remaining parts of protective covering to Lift frames and Lift Doors

37 Service Elevator Vestibule (E7E.18) Clean off paint splashes on Lift Door and frames

38 Service Elevator Vestibule (E7E.18) Provide edge strip to Lift threshold for good finish to floor covering

39 Service Elevator Vestibule (E7E.18) Complete conduit to ceiling smoke detector properly and not a bit of black take and flexible conduit

40 Service Elevator Vestibule (E7E.18) Remove red paint stain on North Wall

41 Service Elevator Vestibule (E7E.18) Remove labels etc from door and make good

42 Service Elevator Vestibule (E7E.18) Relocate door contacts for intruder alarm as they interfere with the closure of the outer door leaf

43 Service Elevator Vestibule (E7E.18) Seal and make good to conduit at ceiling level on North Wall (middle)

Page 288: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 288/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E7E.08 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

2 Vestibule E7E.08 Skirting loose on North Wall to Data Room

3 Vestibule E7E.08 Make good to floor finishes at door frame bases

4 Vestibule E7E.08 Reset light switch plate to level position

5 Vestibule E7E.08 Clean light of dirt and paint stains

6 Vestibule E7E.08 Touch up chipped paint on door frames

7 Vestibule E7E.08 Remove paint on door frames and make good

8 Vestibule E7E.08 Fixing screws to frame protrude and are to be refixed to door

9 Vestibule E7E.08 Cover four (4) protruding screw ends in angle plate to top corner to door

10 Vestibule E7E.08 Screw missing to lock plate on door

11 Vestibule E7E.08 Remove all remaining parts of protective covering to door

12 Vestibule E7E.08 Install rubber seal around door13 Vestibule E7E.08 Install door stop

14 Vestibule E7E.08 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

Page 289: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 289/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Data Room E7E.10 Remove paint on door frames and make good

2 Data Room E7E.10 Fixing screws to frame protrude and are to be refixed to door

3 Data Room E7E.10 Cover four (4) protruding screw ends in angle plate to top corner to door

4 Data Room E7E.10 Screw missing to lock plate on door

5 Data Room E7E.10 Remove all remaining parts of protective covering to door

6 Data Room E7E.10 Install rubber seal around door

7 Data Room E7E.10 Install door stop

8 Data Room E7E.10 Seal North wall to two (2) HVAC pipes and make good all round

9 Data Room E7E.10 Paint ceiling and beams

10 Data Room E7E.10 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

11 Data Room E7E.10 Replace missing skirting to Column C16 including external angle corner piece

12 Data Room E7E.10 Remove formwork between beam and floor slab on East Wall and make good all the length13 Data Room E7E.10 Double floor socket on West wall to be set level

14 Data Room E7E.10 Seal South wall for conduit at ceiling level and make good

15 Data Room E7E.10 Seal West wall for conduit at ceiling level and make good

Page 290: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 290/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E7E.09 Paint ceiling

2 Electrical Closet E7E.09 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

3 Electrical Closet E7E.09 Make good to floor level on South Wall near door and refix floor covering

4 Electrical Closet E7E.09 Install skirting to South Wall as missing

5 Electrical Closet E7E.09 Remove two (2) wall fixing on East Wall near Bus Bars and make good

6 Electrical Closet E7E.09 Make good to taped wire joint on electrical cable in southeast corner at ceiling level

7 Electrical Closet E7E.09 Skirting is missing on West wall (North)

8 Electrical Closet E7E.09 Make good to north wall next floor sinking and refix floor covering complete

9 Electrical Closet E7E.09 Infill large hole in southeast of room (fire stopping) Hole at present is a safety issue

10 Electrical Closet E7E.09 Skirting missing at North wall

11 Electrical Closet E7E.09 Skirting under Electrical Cabinet TUPS-3E on West wall is short and to be replaced

12 Electrical Closet E7E.09 Paint walls13 Electrical Closet E7E.09 Make good to door plasterboard ingoings to both door frames and head frame

14 Electrical Closet E7E.09 Remove paint to Door Frames

15 Electrical Closet E7E.09 Fit rubber seal all round door

16 Electrical Closet E7E.09 Intumescent strip is short to hinge frame at base of door and to be replaced

17 Electrical Closet E7E.09 Intumescent strip is short to open frame at base and head and to be replaced

18 Electrical Closet E7E.09 Fixing screws to frame protrude and are to be refixed to door

19 Electrical Closet E7E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

Page 291: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 291/407

20 Electrical Closet E7E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Electrical Closet E7E.09 Install door stop to door

22 Electrical Closet E7E.09 Remove remaining protective covering to door

23 Electrical Closet E7E.09 Install fire/smoke seal threshold plate to door

24 Electrical Closet E7E.09 Screw missing in lock plate to door

25 Electrical Closet E7E.09 Door frames are 5mm above finished floor level and to be reset

26 Electrical Closet E7E.09 Install door closer

27 Electrical Closet E7E.09 Realign intruder alarm door contacts

28 Electrical Closet E7E.09 Door sign

29 Electrical Closet E7E.09 Make good to wall base at return to East wall in middle and repaint30 Electrical Closet E7E.09 Plasterboard lining including repair to return on East Wall near Bus bars and make good

31 Electrical Closet E7E 09 Screw in the twenty (20) missing screws to the five (5) control boxes to RH of SB11-7E

AMERICA HOUSE

Ref. Location Defect

No.

37 Electrical Closet E7E.09 Reconnect or remove two (2) wires in Box 3 above SBS 11E

38 Electrical Closet E7E.09 Reconnect or remove five (5) wires in Box 4 above SBS 11E

39 Electrical Closet E7E.09 Reinstall five (5) missing internal panels to Electrical Cabinet TL7-E

40 Electrical Closet E7E.09 Reinstall two (2) missing internal panels to Electrical Cabinet TLS7-E

41 Electrical Closet E7E.09 Refix upper panel firmly to Electrical Cabinet TCT7-E

Page 292: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 292/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Janitor Closet E7E.07 Install protection to water pipe with meter

2 Janitor Closet E7E.07 Replace door grill screws (Internal) with white headed screws

3 Janitor Closet E7E.07 Fixing screws to frame protrude and are to be refixed to door

4 Janitor Closet E7E.07 Cover four (4) protruding screw ends in angle plate to top corner to door

5 Janitor Closet E7E.07 Remove all remaining parts of protective covering to door

6 Janitor Closet E7E.07 Remove paint on door frames and make good

7 Janitor Closet E7E.07 Remove wall paint on trims to suspended ceilings and make good

8 Janitor Closet E7E.07 Redo angle edge to vertical corner to LH of door and make good

9 Janitor Closet E7E.07 Redo angle edge to vertical corner southeast and make good

10 Janitor Closet E7E.07 Make good to joint between wall and floor tiling on South Wall

11 Janitor Closet E7E.07 Make good to joint between wall and floor tiling on West Wall

12 Janitor Closet E7E.07 Make good ceiling trim at Column B1613 Janitor Closet E7E.07 Install trough

14 Janitor Closet E7E.07 LH tap in wall is loose and requires to be fixed properly

15 Janitor Closet E7E.07 Tidy up loose layout of pipework connected with boiler

16 Janitor Closet E7E.07 RH tap in wall is loose and requires to be fixed properly

17 Janitor Closet E7E.07 Make good untidy suspended ceiling around Column B16

18 Janitor Closet E7E.07 Make good grouting etc to floor gulley

19 Janitor Closet E7E.07 Install door stop

20 Janitor Closet E7E 07 Make good to floor finish (ceramic tiles) to RH door frame

Page 293: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 293/407

20 Janitor Closet E7E.07 Make good to floor finish (ceramic tiles) to RH door frame

21 Janitor Closet E7E.07 Make good to floor finish (ceramic tiles) to he door frame

22 Janitor Closet E7E.07 Replace water stained suspended ceiling tile

23 Janitor Closet E7E.07 Make good wall tiling around water pipe on East wall which is unsatisfactory

24 Janitor Closet E7E.07 Make good poor finish to top of wall tiling at Column B 16

AMERICA HOUSE

Ref. Location Defect

No.

1 Pantry E7E.06 Wall tiling is generally poor workmanship

2 Pantry E7E.06 Make good joint between wall and floor tiling on North Wall

3 Pantry E7E.06 Clean off excess grouting throughout

4 Pantry E7E.06 Repair boiler leak and install proper safety valve

5 Pantry E7E.06 Fixing screws to frame protrude and are to be refixed to door

6 Pantry E7E.06 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Pantry E7E.06 Screw missing to lock plate on door

8 Pantry E7E.06 Remove all remaining parts of protective covering to door

9 Pantry E7E.06 Replace door grill screws (Internal) with white headed screws

10 Pantry E7E.06 Install rubber seal to door all round

11 Pantry E7E.06 Touch up chipped paintwork to door frames

12 Pantry E7E.06 Redo angle piece on wall tiling at head of door to Janitor Closet13 Pantry E7E.06 Redo angle piece on wall tiling at external angle to LH of door to Janitor Closet

14 Pantry E7E.06 Redo angle piece on wall tiling at external angle to RH of door to Janitor Closet

15 Pantry E7E.06 Make good to reveal above wall tiling at door to Vestibule and repaint

16 Pantry E7E.06 Reset RH door to upper cabinet on South Wall

17 Pantry E7E.06 Make good reveal at top of wall tiling along North wall and repaint

18 Pantry E7E.06 Replace damaged one (1) suspended ceiling tile

19 Pantry E7E.06 Install plug to sink

20 Pantry E7E 06 Seal floor cabinet units between wall and units LH side and make good (East Wall)

Page 294: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 294/407

20 Pantry E7E.06 Seal floor cabinet units between wall and units LH side and make good (East Wall)

21 Pantry E7E.06 Seal floor cabinet units between wall and units RH side and make good (East Wall)

22 Pantry E7E.06 Make good untidy joint between wall tiling and suspended ceiling on North Wall

23 Pantry E7E.06 Install door stop

24 Pantry E7E.06 Install edging to PVC floor covering at door entrance

25 Pantry E7E.06 Make good to floor finishes at base of LH door frame to Vestibule

26 Pantry E7E.06 Make good to floor finishes at base of RH door frame to Vestibule

27 Pantry E7E.06 Reset to level position for power socket outlet (double) at floor level on North Wall

28 Pantry E7E.06 Are suspended ceiling tiles water resistant (pantry has boiling kettles etc.)

29 Pantry E7E.06 Seal floor cabinet units between wall and units LH side and make good (South Wall)

30 Pantry E7E.06 Redo angle piece on wall tiling at external angle to head of door to Janitor Closet

31 Pantry E7E.06 Redo angle near sink/floor cabinets in Southeast corner and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 7 S&T General Area Window No 1 North Repair tighten window handle

2 Level 7 S&T General Area Window No 2 North Repair tighten window handle

3 Level 7 S&T General Area Window No 3 North Repair tighten window handle

4 Level 7 S&T General Area Window No 4 North Repair tighten window handle

5 Level 7 S&T General Area Window No 5 North Repair tighten window handle

6 Level 7 S&T General Area Window No 6 North Repair tighten window handle

7 Level 7 S&T General Area Window No 7 North Repair tighten window handle

8 Level 7 S&T General Area Window No 8 North Repair defective seal at corner of opening window

9 Level 7 S&T General Area Window No 9 North Repair defective seal at corner and refix seal to opening window

10 Level 7 S&T General Area Window No 10 North tighten window handle

11 Level 7 S&T General Area Window No. 11 North tighten window handle

12 Level 7 S&T General Area Window No 12 North repair defective angle seal at bottom13 Level 7 S&T General Area Window No 13 North refix seal to opening window at base of sash

14 Level 7 S&T General Area Window No 14 North tighten window handle

15 Level 7 S&T General Area Window No 3 East Tighten window handle

16 Level 7 S&T General Area Window No 6 East Repair defective seal at head frame corner and refix seal to opening window

17 Level 7 S&T General Area Window Fan No 1 East Repair seal at top LH and RH that is under stress and remove excess mastic sealant

18 Level 7 S&T General Area Window Fan No 1 East tighten up window handle and does not make the full 180o turn

19 Level 7 S&T General Area Window Fan No 1 East remove all remaining protective covering to window frames etc.

20 Level 7 S&T General Area Window Fan No 1 South Repair seal at LH and RH to top of opening sash frame

Page 295: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 295/407

20 Level 7 S&T General Area Window Fan No 1 South Repair seal at LH and RH to top of opening sash frame

21 Level 7 S&T General Area W indow Fan No 1 South tighten window handle

22 Level 7 S&T General Area Window Fan No 2 South make good to window frame seal which is damaged and distorted

23 Level 7 S&T General Area W indow Fan No 2 South make good to window seal in distress at RH and LH which is also broken and needs to be replaced

24 Level 7 S&T General Area W indow Fan No 2 South tighten window handle

25 Level 7 S&T General Area W indow Fan No 3 South tighten window handle

26 Level 7 S&T General Area W indow Fan No 3 South make good to window seal in distress at RH and LH which is also broken and needs to be replaced

27 Level 7 S&T General Area W indow Fan No 3 South tighten window handle

28 Level 7 S&T General Area Window Fan No 3 South Make good to frame seal that is damaged and distorted at bottom both ends

29 Level 7 S&T General Area Window Fan No 1 South Remove excess mastic and sealant

30 Level 7 S&T General Area Window Fan No 2 South Remove excess mastic and sealant

31 Level 7 S&T General Area Window Fan No 3 South Remove excess mastic and sealant

AMERICA HOUSE

Ref. Location Defect

No.

35 Level 7 S&T General Area Window Fan No 4 South Make good to outer seal of opening sash where damaged at both ends at top

36 Level 7 S&T General Area Window Fan No 4 South Make good to inner opening sash seal where damaged at RH top

37 Level 7 S&T General Area Window Fan No 5 South Make good to outer seal of opening sash where damaged at both ends at top

38 Level 7 S&T General Area Window Fan No 5 South Make good to inner opening sash seal where damaged at LH top

39 Level 7 S&T General Area Window Fan No 6 South Repair damaged sole plate to window frame

40 Level 7 S&T General Area Window Fan No 6 South Make good to outer seal of opening sash where damaged at RH at top

41 Level 7 S&T General Area Window Fan No 6 South Make good to inner opening sash seal where damaged at LH top

42 Level 7 S&T General Area Window Fan No 7 South Make good to outer seal of opening sash where damaged at both RH and LH at top

43 Level 7 S&T General Area Window Fan No 7 South Make good to inner opening sash seal where damaged at LH and RH at top

44 Level 7 S&T General Area Remove paint in ceiling edge trim throughout

45 Level 7 S&T General Area Remove paint on ceiling diffusers on North Façade

46 Level 7 S&T General Area Remove paint on ceiling diffusers on South Façade47 Level 7 S&T General Area Remove paint on ceiling diffusers on East Façade

48 Level 7 S&T General Area Window No 1 North repair to bottom angle seal in frame

49 Level 7 S&T General Area Window No 2 North repair to bottom angle seal in frame

50 Level 7 S&T General Area Window No 5 North repair to bottom angle seal in frame

51 Level 7 S&T General Area Window No 6 North repair to bottom angle seal in frame

52 Level 7 S&T General Area Window No 7 North repair bottom frame seal as distorted

53 Level 7 S&T General Area Window No 13 North repair to bottom angle seal in frame

54 Level 7 S&T General Area Window No 14 North repair bottom frame seal as distorted

Page 296: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 296/407

p

55 Level 7 S&T General Area Window No 1 East repair bottom frame seal as distorted

56 Level 7 S&T General Area Window No 2 East repair opening sash seal which is in distress

57 Level 7 S&T General Area Window No 3 East repair opening sash seal which is in distress

58 Level 7 S&T General Area Window No 3 East repair to bottom angle seal in frame

59 Level 7 S&T General Area Window No 4 East repair to bottom angle seal in frame

60 Level 7 S&T General Area Remove labels on all windows generally

61 Level 7 S&T General Area Clean general building debris out of runnels to all twenty eight (28) opening sashes

Page 297: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 297/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor North C14/18 (E8E.01) Remove paint on Fire Alarm LH of door to Stair Vestibule E8E.03

2 Corridor North C14/18 (E8E.01) Install operator signage to Fire Alarm Button at South Wall near door to Stair Vestibule E8E.03

3 Corridor North C14/18 (E8E.01) Make good round Fire Damper Grille panel (Low) on South Wall near Lift Lobby

4 Corridor North C14/18 (E8E.01) Clean paint off grille to Fire Damper panel (Lower) near Lift Lobby

5 Corridor North C14/18 (E8E.01) Provide proper locking device to Low Fire Damper Grille on South Wall near Lift Lobby

6 Corridor North C14/18 (E8E.01) Tiling to wall at C17 South Wall is uneven, debonding, and not aligned and requires to be re-executed

7 Corridor North C14/18 (E8E.01) Tiling to wall at C16 South Wall is uneven, debonding and not aligned and requires to be re-executed

8 Corridor North C14/18 (E8E.01) Install operator signage to Fire Alarm Button at South Wall RH of Service Elevator Vestibule

9 Corridor North C14/18 (E8E.01) Install operator signage to Door Release Button at South Wall to RH of Service Elevator Vestibule

10 Corridor North C14/18 (E8E.01) Install break glass to Emergency Door Release Button on South Wall to RH of Service Elevator Vestibule

11 Corridor North C14/18 (E8E.01) Remove paint from Running Man Sign above door to Stair Vestibule E8E.16

12 Corridor North C14/18 (E8E.01) Make good round Fire Damper Grille panel (Upper C 16) on South Wall near Lift Lobby13 Corridor North C14/18 (E8E.01) Clean paint off grille to Fire Damper panel (Upper C 16) near Lift Lobby

14 Corridor North C14/18 (E8E.01) Provide proper locking device to Upper (C/16) Fire Damper Grille on South Wall near Lift Lobby

15 Corridor North C14/18 (E8E.01) Make good round Fire Damper Grille panel (Low) on South Wall near to RH side of Service Elevator Lobby

16 Corridor North C14/18 (E8E.01) Clean paint off grille to Fire Damper panel (Lower) to RH side of Service Lift Lobby

17 Corridor North C14/18 (E8E.01) Provide proper locking device to Low Fire Damper Grille on South Wall to RH side of Service Lift Lobby

18 Corridor North C14/18 (E8E.01) Refix five (5) sprinkler heads flush with ceiling

19 Corridor North C14/18 (E8E.01) Make good poor lining above Fire Damper near Lift Lobby on South Wall

20 Corridor North C14/18 (E8E.01) Straighten Fire Damper and Frame which is out of alignment on South Wall near lift lobby

Page 298: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 298/407

21 Corridor North C14/18 (E8E.01) Realign Running Man Sign above door to Stair Vestibule E8E.16

22 Corridor North C14/18 (E8E.01) Remove paint on Fire Alarm LH of door to Stair Vestibule E8E.16

23 Corridor North C14/18 (E8E.01) Remove paint on wall tiling at wall return near door to Stair Vestibule E8E.03

24 Corridor North C14/18 (E8E.01) Make good joint between wall tiling return and plastered wall near door to Stair Vestibule E8E.03

25 Corridor North C14/18 (E8E.01) Make good large gap joint between RJ side of Fire Damper near door to Stair Vestibule E8E.03

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor East B/C 18(E8E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor East B/C 18(E8E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor East B/C 18(E8E.01) Make good round Fire Damper Grille panel C14 East Wall near Fire Hose reel Enclosure (FHE)

4 Corridor East B/C 18(E8E.01) Clean paint off grille to Fire Damper panel C14 near FHE

5 Corridor East B/C 18(E8E.01) Provide proper locking device to C14 Fire Damper Grille on East Wall near FHE

6 Corridor East B/C 18(E8E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box

7 Corridor East B/C 18(E8E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor East B/C 18(E8E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor East B/C 18(E8E.01) Build up blockwork below threshold and seal to door

10 Corridor East B/C 18(E8E.01) Seal to head of door frame with blockwork and make good

11 Corridor East B/C 18(E8E.01) Divider Wall to LH to be sealed full length to back wall and front wall

12 Corridor East B/C 18(E8E.01) Seal wall at RH side of enclosure for two (2) conduits and make good13 Corridor East B/C 18(E8E.01) Seal two holes in ceiling slab within FHE and make good

14 Corridor East B/C 18(E8E.01) Seal around conduit to RH side of FHE internally near concrete beam

15 Corridor East B/C 18(E8E.01) Seal LH divider wall for two (2) pipes and make good

16 Corridor East B/C 18(E8E.01) Tidy up loose blockwork to RH divider wall in FHE

17 Corridor East B/C 18(E8E.01) Seal LH Divider wall at plasterboard joints and edges throughout and make good

18 Corridor East B/C 18(E8E.01) Refix door as not fitting properly

19 Corridor East B/C 18(E8E.01) Remove metal and hardboard shims to LH side of door frame

Page 299: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 299/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor West B/C 14 (E8E.01) Make good edge trim to Ceiling Access Panel (North) as workmanship is unsatisfactory

2 Corridor West B/C 14 (E8E.01) Make good edge trim to Ceiling Access Panel (South) as workmanship is unsatisfactory

3 Corridor West B/C 14 (E8E.01) Make good round Fire Damper Grille panel B18 East Wall near Fire Hose reel Enclosure (FHE)

4 Corridor West B/C 14 (E8E.01) Clean paint off grille to Fire Damper panel B19 near FHE

5 Corridor West B/C 14 (E8E.01) Provide proper locking device to B18 Fire Damper Grille on East Wall near FHE

6 Corridor West B/C 14 (E8E.01) Glass Key Box to Fire Hose reel box the glass is loose and should re replaced with a Break Glass Key Box as key is missing

7 Corridor West B/C 14 (E8E.01) Bed Glazing to Fire Hose reel box in neoprene gasket to prevent rattle and worse

8 Corridor West B/C 14 (E8E.01) Seal LH and RH openings between Fire Hose reel (FHE) door frame and blockwork

9 Corridor West B/C 14 (E8E.01) Build up blockwork below threshold and seal to door

10 Corridor West B/C 14 (E8E.01) Seal to head of door frame with blockwork and make good

11 Corridor West B/C 14 (E8E.01) Divider Wall to LH to be sealed full length to back wall

12 Corridor West B/C 14 (E8E.01) Remove one (1) electrical cable (used by Ozer during construction) and make good to all holes13 Corridor West B/C 14 (E8E.01) Seal two holes in ceiling slab within FHE and make good

14 Corridor West B/C 14 (E8E.01) Remove paint on H Sign and make good

15 Corridor West B/C 14 (E8E.01) Make good slab inside FHE as concrete deposits and debris etc..

16 Corridor West B/C 14 (E8E.01) Seal around two (2) pipes in the floor slab and make good

17 Corridor West B/C 14 (E8E.01) Remove metal shim to LH side frame

18 Corridor West B/C 14 (E8E.01) Finish missing parts of RH divider wall and make good

19 Corridor West B/C 14 (E8E.01) Seal RH divider wall for drain pipe and make good

20 Corridor West B/C 14 (E8E.01) Seal RH divider wall for one (1) large diameter pipe and make good

Page 300: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 300/407

21 Corridor West B/C 14 (E8E.01) Seal RH divider wall for two (2) small diameter pipes and make good

22 Corridor West B/C 14 (E8E.01) Seal RH divider wall for one (1) conduit and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Corridor South B14/18 (E8E.01) Make good poor tiling above Fire Damper Grille B16 near lift lobby

2 Corridor South B14/18 (E8E.01) Install operator signage to Fire Alarm Button at North Wall near door to Stair Vestibule E8E.03

3 Corridor South B14/18 (E8E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E8E.16

4 Corridor South B14/18 (E8E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E8E.16 North Wall

5 Corridor South B14/18 (E8E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E8E.16

6 Corridor South B14/18 (E8E.01) Install operator signage to Fire Alarm Button at North Wall LH of Stair Vestibule E8E.16

7 Corridor South B14/18 (E8E.01) Tiling to wall at C17 North Wall is uneven, debonding and not aligned and requires to be re-executed

8 Corridor South B14/18 (E8E.01) Tiling to wall at C16 North Wall is uneven, debonding and not aligned and requires to be re-executed

9 Corridor South B14/18 (E8E.01) Make good to large gap between Low Fire Damper Grille and tiling finish on North Wall LH to Stair Vestibule Door E8E.03

10 Corridor South B14/18 (E8E.01) Make good round Fire Damper Grille panel (Upper B 16) on South Wall near Lift Lobby

11 Corridor South B14/18 (E8E.01) Clean paint off grille to Fire Damper panel (Upper B 16) near Lift Lobby

12 Corridor South B14/18 (E8E.01) Provide proper locking device to Upper (B 16) Fire Damper Grille on North Wall near Lift Lobby13 Corridor South B14/18 (E8E.01) Make good round Fire Damper Grille panel (Low) on North Wall near Stair Vestibule E8E.03 LH

14 Corridor South B14/18 (E8E.01) Clean paint off grille to Fire Damper panel (Low) near Stair Vestibule E8E.03 North Wall

15 Corridor South B14/18 (E8E.01) Provide proper locking device to Low Fire Damper Grille on North Wall near Stair Vestibule E8E.03 LH

16 Corridor South B14/18 (E8E.01) Replace broken 'break' glass to Fire Alarm Button at North Wall near to Stair Vestibule E8E.03

17 Corridor South B14/18 (E8E.01) Remove paint on Fire Alarm near door to Stair Vestibule E8E.16

18 Corridor South B14/18 (E8E.01) Remove paint on Running Man Sign near door to Stair Vestibule E8E.16

19 Corridor South B14/18 (E8E.01) Refix loose fire damper frame and door near Lift Lobby on North Wall

20 Corridor South B14/18 (E8E.01) Remove paint on Running Man Sign near door to Stair Vestibule E8E.03

Page 301: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 301/407

21 Corridor South B14/18 (E8E.01) Make good to large gap between Fire Damper near door to Stair Vestibule E8E.16 at RH side

22 Corridor South B14/18 (E8E.01) Make good to large gap between Fire Damper near door to Stair Vestibule E8E.036 at LH side

23 Corridor South B14/18 (E8E.01) Remove paint to Running Man Sign at Lift Lobby

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 8 (E8E.03) Remove paint to South Door Frames

2 Stair Vestibule Level 8 (E8E.03) Fit rubber seal all round door South

3 Stair Vestibule Level 8 (E8E.03) Intumescent strip is short to open frame at base to Door South : replace

4 Stair Vestibule Level 8 (E8E.03) Fixing screws to frame protrude and are to be refixed to Door South

5 Stair Vestibule Level 8 (E8E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door South

6 Stair Vestibule Level 8 (E8E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

7 Stair Vestibule Level 8 (E8E.03) Install door stop to Door South

8 Stair Vestibule Level 8 (E8E.03) Remove remaining protective covering to Door South

9 Stair Vestibule Level 8 (E8E.03) Install fire/smoke seal threshold plate to Door South

10 Stair Vestibule Level 8 (E8E.03) Screw missing in lock plate to door South

11 Stair Vestibule Level 8 (E8E.03) Intumescent strip is short to hinge frame at base to Door South and to be replaced

12 Stair Vestibule Level 8 (E8E.03) Complete terrazzo tiling up to door frames at Door South13 Stair Vestibule Level 8 (E8E.03) Make good to terrazzo skirting in northwest corner

14 Stair Vestibule Level 8 (E8E.03) South door frames are 4mm above the finished floor level and to be reset

15 Stair Vestibule Level 8 (E8E.03) Provide operation label to Door Push Button in Romanian and English

16 Stair Vestibule Level 8 (E8E.03) Remove paint from top edge of skirting on all walls

17 Stair Vestibule Level 8 (E8E.03) North door frames are 6mm above the finished floor level and to be reset

18 Stair Vestibule Level 8 (E8E.03) Clean paint etc from two (2) light fittings

19 Stair Vestibule Level 8 (E8E.03) Clean paint off door frame to Door North

20 Stair Vestibule Level 8 (E8E.03) Intumescent strip is short to open frame at base to Door North : replace

Page 302: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 302/407

21 Stair Vestibule Level 8 (E8E.03) Intumescent strip is short to hinge frame at base to Door North and to be replaced

22 Stair Vestibule Level 8 (E8E.03) Fixing screws to frame protrude and are to be refixed to Door North

23 Stair Vestibule Level 8 (E8E.03) Cover four (4) protruding screw ends in angle plate to top corner to Door North

24 Stair Vestibule Level 8 (E8E.03) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

25 Stair Vestibule Level 8 (E8E.03) Install door stop to Door North

26 Stair Vestibule Level 8 (E8E.03) Fit rubber seal all round door North

27 Stair Vestibule Level 8 (E8E.03) Fire/Smoke Threshold seal is required to door North

28 Stair Vestibule Level 8 (E8E.03) Remove remaining protective covering to Door North

29 Stair Vestibule Level 8 (E8E.03) Screw missing in lock plate to door North

30 Stair Vestibule Level 8 (E8E.03) Make good to terrazzo skirting to RH side of Door South

31 Stair Vestibule Level 8 (E8E 03) Remove paint to three (3) sprinkler head in ceiling

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 8 (E8E.03) Provide proper locking device to Upper Fire Damper Grille (Upper)

35 Stair Vestibule Level 8 (E8E.03) Make good round Fire Damper Grille panel (Lower)

36 Stair Vestibule Level 8 (E8E.03) Clean paint off grille to Fire Damper panel (Lower)

37 Stair Vestibule Level 8 (E8E.03) Provide proper locking device to Upper Fire Damper Grille (Lower)

38 Stair Vestibule Level 8 (E8E.03) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

39 Stair Vestibule Level 8 (E8E.03) Seal internally around Dry Riser Access Panel and make good

40 Stair Vestibule Level 8 (E8E.03) Door to Dry Riser Fire Hatch is missing and to be replaced

41 Stair Vestibule Level 8 (E8E.03) Divider Wall in Dry Riser RH side is missing and to be installed

42 Stair Vestibule Level 8 (E8E.03) Form rounded external corner to terrazzo skirting to LH of door to Egress Stair

43 Stair Vestibule Level 8 (E8E.03) Form rounded external corner to terrazzo skirting to RH of door to Egress Stair

44 Stair Vestibule Level 8 (E8E.03) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

45 Stair Vestibule Level 8 (E8E.03) Tile floor is uneven and needs to be levelled, polished and resealed

46 Stair Vestibule Level 8 (E8E.03) Remove paint etc from top edge of skirting all round

Page 303: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 303/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 8 (E8E.04) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 8 (E8E.04) Remove paint from Running Man Sign and make good

3 Egress Stair Level 8 (E8E.04) Remove paint from Access Car Reader and make good

4 Egress Stair Level 8 (E8E.04) Remove paint etc. from ceiling Smoke Detector and make good

5 Egress Stair Level 8 (E8E.04) Tiled Level 8 floor requires to be levelled, polished and sealed and repaired including workmanship near divide wall to stair

6 Egress Stair Level 8 (E8E.04) Fixing screws to frame protrude and are to be refixed

7 Egress Stair Level 8 (E8E.04) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 8 (E8E.04) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 8 (E8E.04) Intumescent strip to open door jamb is short and to be replaced

10 Egress Stair Level 8 (E8E.04) Intumescent strip to hinge door jamb is short and to be replaced

11 Egress Stair Level 8 (E8E.04) Rubber infill strip to door is missing at head

12 Egress Stair Level 8 (E8E.04) Install door stop to Door 13 Egress Stair Level 8 (E8E.04) Screw missing at lock plate on door

14 Egress Stair Level 8 (E8E.04) Remove paint on door frames and make good

15 Egress Stair Level 8 (E8E.04) Fire/Smoke seal threshold required to entry door

16 Egress Stair Level 8 (E8E.04) Door signage

17 Egress Stair Level 8 (E8E.04) Door intruder alarm contacts to be aligned

18 Egress Stair Level 8 (E8E.04) Door intruder alarm contact wiring to be tidied up

19 Egress Stair Level 8 (E8E.04) Remove all remaining protective covering to door

20 Egress Stair Level 8 (E8E.04) Replace key sets with correct set

21 E St i L l 8 (E8E 04) Mid l di tili i d 'b d' d i t b l id li h d d l d

Page 304: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 304/407

21 Egress Stair Level 8 (E8E.04) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

22 Egress Stair Level 8 (E8E.04) Clean light fitting of paint stains etc. at mid landing

23 Egress Stair Level 8 (E8E.04) Make good to open stair stringer to upper stair flight

24 Egress Stair Level 8 (E8E.04) Make good to open stair stringer to lower stair flight

25 Egress Stair Level 8 (E8E.04) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

26 Egress Stair Level 8 (E8E.04) Clean two (2) stair flights between Levels 3 and 4 of black paint and mortar stains complete

27 Egress Stair Level 8 (E8E.04) Clean terrazzo tile at mid landing around the two (2) balustrade supports

28 Egress Stair Level 8 (E8E.04) Reset light fitting at mid landing to level position

29 Egress Stair Level 8 (E8E.04) Clean main landing light of paint splashes etc

30 Egress Stair Level 8 (E8E.04) Replace one (1) chipped step

31 Egress Stair Level 8 (E8E 04) Touch up damaged paintwork to door frames

AMERICA HOUSE

Ref. Location Defect

No.

1 Stair Vestibule Level 8 (E8E.16) Remove paint to South Door Frames and make good

2 Stair Vestibule Level 8 (E8E.16) Fit rubber seal all round door South

3 Stair Vestibule Level 8 (E8E.16) Intumescent strip is short to open frame base of Door South : replace

4 Stair Vestibule Level 8 (E8E.16) Intumescent strip is not complete to base of open frame of Door South

5 Stair Vestibule Level 8 (E8E.16) Fixing screws to frame protrude and are to be refixed to Door South

6 Stair Vestibule Level 8 (E8E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door South

7 Stair Vestibule Level 8 (E8E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

8 Stair Vestibule Level 8 (E8E.16) Install door stop to Door South

9 Stair Vestibule Level 8 (E8E.16) Remove remaining protective covering to Door South

10 Stair Vestibule Level 8 (E8E.16) Install fire/smoke seal threshold plate to Door South

11 Stair Vestibule Level 8 (E8E.16) Screw missing in lock plate to door South

12 Stair Vestibule Level 8 (E8E.16) Intumescent strip is short to hinge frame base of Door South : replace13 Stair Vestibule Level 8 (E8E.16) W hy are there locks on Stair Egress Doors operated with Card Reader Access and Release Push button ?

14 Stair Vestibule Level 8 (E8E.16) Terrazzo tile floor is uneven and needs to be levelled, polished and resealed

15 Stair Vestibule Level 8 (E8E.16) Terrazzo Skirting at both wall returns to doors to have rounded or pencil arrissed corners to Stair Egress Door

16 Stair Vestibule Level 8 (E8E.16) Provide operation label to Door Push Button in Romanian and English

17 Stair Vestibule Level 8 (E8E.16) Remove paint etc. from top edge of skirting on all walls

18 Stair Vestibule Level 8 (E8E.16) Reset double power socket outlet near Door North on East wall to be level

19 Stair Vestibule Level 8 (E8E.16) Reset double power socket outlet near Door South on East wall to be level

20 Stair Vestibule Level 8 (E8E.16) Clean paint etc from two (2) light fittings

21 Stair Vestibule Level 8 (E8E 16) Screw missing from door lock plate on Door North

Page 305: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 305/407

21 Stair Vestibule Level 8 (E8E.16) Screw missing from door lock plate on Door North

22 Stair Vestibule Level 8 (E8E.16) Clean paint off door frame to Door North

23 Stair Vestibule Level 8 (E8E.16) Touch up chipped paintwork to door frames (north)

24 Stair Vestibule Level 8 (E8E.16) Intumescent strip is not complete to base of open frame of Door North

25 Stair Vestibule Level 8 (E8E.16) Intumescent strip is short to hinge frame base of Door North : replace

26 Stair Vestibule Level 8 (E8E.16) Fixing screws to frame protrude and are to be refixed to Door North

27 Stair Vestibule Level 8 (E8E.16) Cover four (4) protruding screw ends in angle plate to top corner to Door North

28 Stair Vestibule Level 8 (E8E.16) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

29 Stair Vestibule Level 8 (E8E.16) Install door stop to Door North

30 Stair Vestibule Level 8 (E8E.16) Fit rubber seal all round door North

31 Stair Vestibule Level 8 (E8E 16) Fire/Smoke Threshold seal is required to door North

AMERICA HOUSE

Ref. Location Defect

No.

34 Stair Vestibule Level 8 (E8E.16) Touch up damaged paintwork to frames of Door South

35 Stair Vestibule Level 8 (E8E.16) Make good to damaged skirting to LH of Stair door

36 Stair Vestibule Level 8 (E8E.16) Make good skirting broken at door reveal LH of Stair Door

37 Stair Vestibule Level 8 (E8E.16) Remove all remaining parts of protective covering to door North

38 Stair Vestibule Level 8 (E8E.16) Remove paint to three (3) sprinkler head in ceiling and make good

39 Stair Vestibule Level 8 (E8E.16) Make good round Fire Damper Grille panel (Upper)

40 Stair Vestibule Level 8 (E8E.16) Clean paint off grille to Fire Damper panel (Upper)

41 Stair Vestibule Level 8 (E8E.16) Provide proper locking device to Upper Fire Damper Grille (Upper)

42 Stair Vestibule Level 8 (E8E.16) Make good round Fire Damper Grille panel (Lower)

43 Stair Vestibule Level 8 (E8E.16) Clean paint off grille to Fire Damper panel (Lower)

44 Stair Vestibule Level 8 (E8E.16) Provide proper locking device to Upper Fire Damper Grille (Lower)

45 Stair Vestibule Level 8 (E8E.16) Terrazzo skirting poorly executed at East Wall (South) and to be redone

46 Stair Vestibule Level 8 (E8E.16) Make good to arris RH side of door to stair that has been damaged

47 Stair Vestibule Level 8 (E8E.16) Make good to finish to LH of Door North

48 Stair Vestibule Level 8 (E8E.16) Make good to floor finish to RH of Door North

49 Stair Vestibule Level 8 (E8E.16) Running Man Sign obstructs the efficient operation of the South sprinkler and solution is required

50 Stair Vestibule Level 8 (E8E.16) Remove paint from Running Man Sign and make good

51 Stair Vestibule Level 8 (E8E.16) Realign Dry Riser outlet so that ease of connection by Fire Brigade is provided

52 Stair Vestibule Level 8 (E8E.16) Seal internally around Dry Riser Access Panel and make good

53 Stair Vestibule Level 8 (E8E.16) Seal holes in ceil ing at ends of Running Man Sign

54 Stair Vestibule Level 8 (E8E 16) Replace broken light bulb in H Sign above Dry Riser Inlet

Page 306: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 306/407

54 Stair Vestibule Level 8 (E8E.16) Replace broken light bulb in H Sign above Dry Riser Inlet55 Stair Vestibule Level 8 (E8E.16) Make good to skirting at northeast corner which is poorly executed

AMERICA HOUSE

Ref. Location Defect

No.

1 Egress Stair Level 8 (E8E.17) Remove paint etc to top edge of skirting throughout and make good

2 Egress Stair Level 8 (E8E.17) Remove paint from Running Man Sign and make good

3 Egress Stair Level 8 (E8E.17) Remove paint from Access Car Reader and make good

4 Egress Stair Level 8 (E8E.17) Remove paint on Smoke Detector and make good

5 Egress Stair Level 8 (E8E.17) Tiled Level 8 floor requires to be polished and sealed and repaired where poor workmanship near divide wall to stair

6 Egress Stair Level 8 (E8E.17) Fixing screws to frame protrude and are to be refixed

7 Egress Stair Level 8 (E8E.17) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Egress Stair Level 8 (E8E.17) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Egress Stair Level 8 (E8E.17) Intumescent strip to open door jamb is short at base and to be replaced

10 Egress Stair Level 8 (E8E.17) Intumescent strip to hinge door jamb is short at base and head and to be replaced

11 Egress Stair Level 8 (E8E.17) Intumescent strip is loose on head frame and requires to be replaced

12 Egress Stair Level 8 (E8E.17) Rubber infill strip to door is missing at head

13 Egress Stair Level 8 (E8E.17) Install door stop to Door

14 Egress Stair Level 8 (E8E.17) Screw missing at lock plate on door

15 Egress Stair Level 8 (E8E.17) Remove paint on door frames and make good

16 Egress Stair Level 8 (E8E.17) Fire/Smoke seal threshold required to entry door

17 Egress Stair Level 8 (E8E.17) Door signage

18 Egress Stair Level 8 (E8E.17) Door intruder alarm contacts to be aligned

19 Egress Stair Level 8 (E8E.17) Remove all remaining protective covering to door

20 Egress Stair Level 8 (E8E.17) Tidy up contact wires to door intruder alarm

21 Egress Stair Level 8 (E8E 17) Align contacts of door intruder alarm

Page 307: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 307/407

21 Egress Stair Level 8 (E8E.17) Align contacts of door intruder alarm22 Egress Stair Level 8 (E8E.17) Make good to open stair stringer to upper stair flight

23 Egress Stair Level 8 (E8E.17) Make good to open stair stringer to lower stair flight

24 Egress Stair Level 8 (E8E.17) Make good at stair landing head for handrails where black marks etc are on the tiled floor surface

25 Egress Stair Level 8 (E8E.17) Clean two (2) stair flights between Levels 8 and Roof of black paint and mortar stains complete

26 Egress Stair Level 8 (E8E.17) Mid landing tiling is uneven and 'bossed' and requires to be relaid, polished and resealed

27 Egress Stair Level 8 (E8E.17) Door frame is set 9mm above the finished floor level and requires to be reset properly

28 Egress Stair Level 8 (E8E.17) Clean Landing 8 light of paint stains etc.

29 Egress Stair Level 8 (E8E.17) Reset Landing 8 light properly level

30 Egress Stair Level 8 (E8E.17) Clean paint from mid landing light

31 Egress Stair Level 8 (E8E 17) Remove paint stains on door surfaces

AMERICA HOUSE

Ref. Location Defect

No.

34 Egress Stair Level 8 (E8E.17) Replace missing light switch near door to Door as wires are exposed

35 Egress Stair Level 8 (E8E.17) Running Man Sign to be reset properly level and make good

36 Egress Stair Level 8 (E8E.17) Mid landing wall light to be reset properly level

37 Egress Stair Level 8 (E8E.17) Repair to terrazzo skirting broken at RH side of door and repaint as required38 Egress Stair Level 8 (E8E.17) Make good wall paint where terrazzo tile to upper flight was repaired

39 Egress Stair Level 8 (E8E.17) Make good wall paint where terrazzo tile to lower flight was repaired

40 Egress Stair Level 8 (E8E.17) Replace five (5) chipped stair treads

41 Egress Stair Level 8 (E8E.17) Make good pointing to stair skirting on East Wall Upper flight

42 Egress Stair Level 8 (E8E.17) Make good pointing to stair skirting on West Wall Lower flight

Page 308: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 308/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule Level 8 (E8E.05) Remove paint to three sprinkler heads

2 Vestibule Level 8 (E8E.05) Make good floor finish to RH side of Door South Frame

3 Vestibule Level 8 (E8E.05) Remove paint to South Door Frames

4 Vestibule Level 8 (E8E.05) Fit rubber seal all round door South

5 Vestibule Level 8 (E8E.05) Intumnescent strip is not installed to side or head frames

6 Vestibule Level 8 (E8E.05) Fixing screws to frame protrude and are to be refixed to Door South

7 Vestibule Level 8 (E8E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door South

8 Vestibule Level 8 (E8E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Vestibule Level 8 (E8E.05) Install door stop to Door South

10 Vestibule Level 8 (E8E.05) Remove remaining protective covering to Door South

11 Vestibule Level 8 (E8E.05) Install fire/smoke seal threshold plate to Door South

12 Vestibule Level 8 (E8E.05) Screw missing in lock plate to door South

13 Vestibule Level 8 (E8E.05) Install door closer to Door South

14 Vestibule Level 8 (E8E.05) Install edging and recut floor covering to door South threshold which is short

15 Vestibule Level 8 (E8E.05) Clean paint off door frame to Door North

16 Vestibule Level 8 (E8E.05) Intumescent strip is installed to side or head frames of Door North

17 Vestibule Level 8 (E8E.05) Fixing screws to frame protrude and are to be refixed to Door North

18 Vestibule Level 8 (E8E.05) Cover four (4) protruding screw ends in angle plate to top corner to Door North

19 Vestibule Level 8 (E8E.05) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

20 Vestibule Level 8 (E8E.05) Install door stop to Door North

21 Vestibule Level 8 (E8E.05) Fit rubber seal all round door North

Page 309: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 309/407

( )22 Vestibule Level 8 (E8E.05) Fire/Smoke Threshold seal is required to door North

23 Vestibule Level 8 (E8E.05) Install door closer to Door North

24 Vestibule Level 8 (E8E.05) Remove all remaining parts of protective covering to door

25 Vestibule Level 8 (E8E.05) Screw missing in lock plate to door North

26 Vestibule Level 8 (E8E.05) Replace missing skirting and external angle skirting pieces both end between doors to Pantry and Vestibule E8E.08

27 Vestibule Level 8 (E8E.05) Why is floor covering a different colour ? Who authorised the change

28 Vestibule Level 8 (E8E.05) Replace missing external angle skirting corner piece and skirting to RH of Door to Pantry

29 Vestibule Level 8 (E8E.05) Why is skirting a different colour ? Who authorised the colour change and type ?

30 Vestibule Level 8 (E8E.05) Remove timber packer to RH top of door frame to door South

31 Vestibule Level 8 (E8E 05) Seal and point up RH side of door frame to Door South

AMERICA HOUSE

Ref. Location Defect

No.

34 Vestibule Level 8 (E8E.05) Plastic skirting loose to RH side of door to Handicapped Toilet Door E8E.11

35 Vestibule Level 8 (E8E.05) Reset double socket outlet near Door South and make level

36 Vestibule Level 8 (E8E.05) Reset double socket outlet near Door North and make level

37 Vestibule Level 8 (E8E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E8E.1138 Vestibule Level 8 (E8E.05) Install edging strip between PVC f loor covering and tile f loor f inish to Toilet E8E.12

39 Vestibule Level 8 (E8E.05) Install edging strip between PVC f loor covering and tile f loor f inish to Toilet E8E.13

40 Vestibule Level 8 (E8E.05) Install edging strip between PVC f loor covering and tile f loor f inish to Toilet E8E.14

41 Vestibule Level 8 (E8E.05) Install edging strip between PVC floor covering and tile floor finish to Handicapped Toilet E8E.15

42 Vestibule Level 8 (E8E.05) Refix all skirting as attached with panel pins with adhesive or clip-on system

43 Vestibule Level 8 (E8E.05) Make good floor finish to LH side of Door South Frame

Page 310: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 310/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E8E.15 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E8E.15 Clean excess grouting to tiles generally

3 Handicapped Toilet E8E.15 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E8E.15 Make good to floor finish at LH Base Frame of door

5 Handicapped Toilet E8E.15 Make good to floor finish at RH Base Frame of door

6 Handicapped Toilet E8E.15 Remove paint on door frames and make good

7 Handicapped Toilet E8E.15 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E8E.15 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E8E.15 Screw missing to lock plate on door

10 Handicapped Toilet E8E.15 Remove all remaining parts of protective covering to door

11 Handicapped Toilet E8E.15 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E8E.15 WHB tap is loose and to be reset properly

13 Handicapped Toilet E8E.15 Install plug to sink

14 Handicapped Toilet E8E.15 Install rubber seal around door

15 Handicapped Toilet E8E.15 Install Door stop

16 Handicapped Toilet E8E.15 Toilet does not flush as there is no water supply

17 Handicapped Toilet E8E.15 Clean general dirt etc in floor pointing and make good

18 Handicapped Toilet E8E.15 Repoint to wall tiling where short or insufficient

19 Handicapped Toilet E8E.15 Make good to tiled floor finish to door frame bases LH

20 Handicapped Toilet E8E.15 Make good to tiled floor finish to door frame bases RH

21 Handicapped Toilet E8E.15 Make good to wall tiling at north east corner 22 Handicapped Toilet E8E 15 Make good to joint between wall and floor tiling on West Wall

Page 311: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 311/407

22 Handicapped Toilet E8E.15 Make good to joint between wall and floor tiling on West Wall

23 Handicapped Toilet E8E.15 Make good to joint between wall and floor tiling on South Wall

24 Handicapped Toilet E8E.15 Make good to poor tiling at base of West Wall

25 Handicapped Toilet E8E.15 Refix soap dispenser straight

26 Handicapped Toilet E8E.15 No water in sink tap supply

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E8E.14 Make good the very poor tile grouting etc around floor gulley

2 Toilet E8E.14 Make good to base of RH door frames to floor finish

3 Toilet E8E.14 Make good to base of LH door frames to floor finish

4 Toilet E8E.14 Install door stop5 Toilet E8E.14 Remove paint on door frames and make good

6 Toilet E8E.14 Fixing screws to frame protrude and are to be refixed to door

7 Toilet E8E.14 Cover four (4) protruding screw ends in angle plate to top corner to door

8 Toilet E8E.14 Screw missing to lock plate on door

9 Toilet E8E.14 Remove all remaining parts of protective covering to door

10 Toilet E8E.14 Install rubber seal around door

11 Toilet E8E.14 Touch up chipped paintwork to door frames

12 Toilet E8E.14 Replace door grill screws (Internal) with white headed screws

13 Toilet E8E.14 Generally clean off excess grouting on wall tiles

14 Toilet E8E.14 Clean grout on floor tiles generally

15 Toilet E8E.14 WHB tap is loose and to be reset properly

16 Toilet E8E.14 Install plug to sink

17 Toilet E8E.14 Make good to joint between wall and floor tiling finish in north wall

18 Toilet E8E.14 No water supply so toilet does not flush

19 Toilet E8E.14 No water supply to sink

Page 312: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 312/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E8E.13 Make good tile grouting etc around floor gulley

2 Toilet E8E.13 Install door stop

3 Toilet E8E.13 Remove paint on door frames and make good

4 Toilet E8E.13 Fixing screws to frame protrude and are to be refixed to door5 Toilet E8E.13 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E8E.13 Screw missing to lock plate on door

7 Toilet E8E.13 Remove all remaining parts of protective covering to door

8 Toilet E8E.13 Install rubber seal around door

9 Toilet E8E.13 Touch up chipped paintwork to door frames

10 Toilet E8E.13 Replace door grill screws (Internal) with white headed screws

11 Toilet E8E.13 Generally clean off excess grouting on wall tiles

12 Toilet E8E.13 Clean grout on floor tiles generally

13 Toilet E8E.13 WHB tap is loose and to be reset properly

14 Toilet E8E.13 Install plug

15 Toilet E8E.13 Touch up missing parts of grouting to wall tiling generally

16 Toilet E8E.13 Make good to defective wall tiling in South West Corner

17 Toilet E8E.13 Make good to defective wall tiling in South East Corner

18 Toilet E8E.13 Clean out at bases of door frame RH and make good floor finishes complete

19 Toilet E8E.13 Clean out at bases of door frame LH and make good floor finishes complete

20 Toilet E8E.13 Make good at joint between wall tiling and floor tiling on West wall

21 Toilet E8E.13 No water supply so toilet does not flush

22 Toilet E8E.13 No water supply to sink

Page 313: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 313/407

pp y

AMERICA HOUSE

Ref. Location Defect

No.

1 Toilet E8E.12 Make good tile grouting etc around floor gulley

2 Toilet E8E.12 Install door stop

3 Toilet E8E.12 Remove paint on door frames and make good

4 Toilet E8E.12 Fixing screws to frame protrude and are to be refixed to door5 Toilet E8E.12 Cover four (4) protruding screw ends in angle plate to top corner to door

6 Toilet E8E.12 Screw missing to lock plate on door

7 Toilet E8E.12 Remove all remaining parts of protective covering to door

8 Toilet E8E.12 Install rubber seal around door

9 Toilet E8E.12 Touch up chipped paintwork to door frames

10 Toilet E8E.12 Replace door grill screws (Internal) with white headed screws

11 Toilet E8E.12 Generally clean off excess grouting on wall tiles

12 Toilet E8E.12 Clean grout on floor tiles generally

13 Toilet E8E.12 WHB tap is loose and to be reset properly

14 Toilet E8E.12 Install plug

15 Toilet E8E.12 Clean out at bases of door frame RH and make good floor finishes complete

16 Toilet E8E.12 Clean out at bases of door frame LH and make good floor finishes complete

17 Toilet E8E.12 Make good at joint between wall tiling and floor tiling on North wall

18 Toilet E8E.12 Make good at joint between wall tiling and floor tiling on West wall

19 Toilet E8E.12 No water supply so toilet does not flush

20 Toilet E8E.12 No water supply to sink

Page 314: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 314/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Handicapped Toilet E8E.11 Make good to floor tiling around floor gulley and regrout

2 Handicapped Toilet E8E.11 Clean excess grouting to tiles generally

3 Handicapped Toilet E8E.11 Replace door grill screws (Internal) with white headed screws

4 Handicapped Toilet E8E.11 Repoint to LH side of door frame

5 Handicapped Toilet E8E.11 Touch up chipped paintwork to door frames

6 Handicapped Toilet E8E.11 Remove paint on door frames and make good

7 Handicapped Toilet E8E.11 Fixing screws to frame protrude and are to be refixed to door

8 Handicapped Toilet E8E.11 Cover four (4) protruding screw ends in angle plate to top corner to door

9 Handicapped Toilet E8E.11 Screw missing to lock plate on door

10 Handicapped Toilet E8E.11 Remove all remaining parts of protective covering to door

11 Handicapped Toilet E8E.11 Clean fan outlet in ceiling of dirt/dust etc.

12 Handicapped Toilet E8E.11 WHB tap is loose and to be reset properly

13 Handicapped Toilet E8E.11 Install plug

14 Handicapped Toilet E8E.11 Install Door stop

15 Handicapped Toilet E8E.11 Install rubber seal around door

16 Handicapped Toilet E8E.11 Clean out at bases to door frames and make good to floor finish

17 Handicapped Toilet E8E.11 Clean general dirt etc in floor pointing and make good

18 Handicapped Toilet E8E.11 Repoint to wall tiling where short or insufficient

19 Handicapped Toilet E8E.11 Make good to joint between wall tiling and floor tiling at North wall

20 Handicapped Toilet E8E.11 Make good to joint between wall tiling and floor tiling at South wall

21 Handicapped Toilet E8E.11 Make good to joint between wall tiling and floor tiling at West wall22 Handicapped Toilet E8E.11 No water supply so toilet does not flush

Page 315: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 315/407

23 Handicapped Toilet E8E.11 No water supply to sink

24 Handicapped Toilet E8E.11 Remove screw to LH head of door frame and make good

25 Handicapped Toilet E8E.11 Remove screw to head of LH door head frame and make good

26 Handicapped Toilet E8E.11 Replace missing gulley grating to floor

27 Handicapped Toilet E8E.11 Fix loudspeaker in ceiling and wire up complete

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Elevator Vestibule (E8E.18) Prepare for and paint ceiling

2 Service Elevator Vestibule (E8E.18) Align Access Card Reader which is not level

3 Service Elevator Vestibule (E8E.18) Remove paint stains on floor covering generally

4 Service Elevator Vestibule (E8E.18) Fill in hole to door head frame

5 Service Elevator Vestibule (E8E.18) Remove paint splashes etc on doors

6 Service Elevator Vestibule (E8E.18) Fixing screws to frame protrude and are to be refixed to Door

7 Service Elevator Vestibule (E8E.18) Cover four (4) protruding screw ends in angle plate to top corner to door

8 Service Elevator Vestibule (E8E.18) Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

9 Service Elevator Vestibule (E8E.18) Intumescent strip is short on both side frames and requires to be replaced

10 Service Elevator Vestibule (E8E.18) Install door stops to Doors

11 Service Elevator Vestibule (E8E.18) Clean paint off Door Frames

12 Service Elevator Vestibule (E8E.18) Door Signage

13 Service Elevator Vestibule (E8E.18) Fire/Smoke Threshold seal is required to door

14 Service Elevator Vestibule (E8E.18) Install closers with selector on doors

15 Service Elevator Vestibule (E8E.18) Remove all remaining parts of the protective covering to doors

16 Service Elevator Vestibule (E8E.18) Install rubber seal to door

17 Service Elevator Vestibule (E8E.18) Intumescent strip to meeting style is not continuous and missing at door lock

18 Service Elevator Vestibule (E8E.18) Inner leaf of door has too much play when closed and to be adjusted

19 Service Elevator Vestibule (E8E.18) Tidy up wiring to door intruder contact

20 Service Elevator Vestibule (E8E.18) Screw missing form door locking plate

21 Service Elevator Vestibule (E8E.18) Touch up to damaged paintwork to door frames generally22 Service Elevator Vestibule (E8E.18) Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

Page 316: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 316/407

( ) g g y

23 Service Elevator Vestibule (E8E.18) Relay floor covering that is distorted and 'bubbled' and prepare floor screed below

24 Service Elevator Vestibule (E8E.18) Replace skirting external angle corner piece to LH side of lift entrance return

25 Service Elevator Vestibule (E8E.18) Replace missing skirting and external angle corner piece to RH side of lift entrance return

26 Service Elevator Vestibule (E8E.18) Skirting missing to RH side of entrance to Service Elevator Lobby

27 Service Elevator Vestibule (E8E.18) Skirting missing to LH side of entrance to Service Elevator Lobby

28 Service Elevator Vestibule (E8E.18) Seal and make good to conduit at ceiling level (East Wall)

29 Service Elevator Vestibule (E8E.18) Paint sprinkler pipework

30 Service Elevator Vestibule (E8E.18) Tidy up joint at sprinkler head and elbow joints including removing excess joint hemp fibres on sprinkler pipework

31 Service Elevator Vestibule (E8E 18) Replace screws at grille to LH side with white headed screws as elsewhere

AMERICA HOUSE

Ref. Location Defect

No.

34 Service Elevator Vestibule (E8E.18) Seal and make good to one (1) sprinkler pipe in northeast corner at near ceiling level

35 Service Elevator Vestibule (E8E.18) Refix loose skirting on West Wall

36 Service Elevator Vestibule (E8E.18) Remove remaining parts of protective covering to Lift frames

37 Service Elevator Vestibule (E8E.18) Clean off paint splashes on Lift Door and frames38 Service Elevator Vestibule (E8E.18) Edging strip required to floor covering at Lift threshold

39 Service Elevator Vestibule (E8E.18) Complete conduit to ceiling smoke detector

40 Service Elevator Vestibule (E8E.18) Remove red paint stain on North Wall

41 Service Elevator Vestibule (E8E.18) Floor covering missing at entrance to Service Elevator Lobby

Page 317: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 317/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule E8E.08 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

2 Vestibule E8E.08 Make good to floor finishes at door frame base RH

3 Vestibule E8E.08 Make good to floor finishes at door frame base LH

4 Vestibule E8E.08 Remove polythene cover to ceiling light5 Vestibule E8E.08 Clean light of dirt and paint stains

6 Vestibule E8E.08 Touch up chipped paint on door frames

7 Vestibule E8E.08 Remove paint on door frames and make good

8 Vestibule E8E.08 Fixing screws to frame protrude and are to be refixed to door

9 Vestibule E8E.08 Cover four (4) protruding screw ends in angle plate to top corner to door

10 Vestibule E8E.08 Two (2) screws missing to lock plate on door

11 Vestibule E8E.08 Remove all remaining parts of protective covering to door

12 Vestibule E8E.08 Install rubber seal around door

13 Vestibule E8E.08 Install door stop

14 Vestibule E8E.08 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

Page 318: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 318/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Data Room E8E.10 Remove paint on door frames and make good

2 Data Room E8E.10 Fixing screws to frame protrude and are to be refixed to door

3 Data Room E8E.10 Cover four (4) protruding screw ends in angle plate to top corner to door

4 Data Room E8E.10 Screw missing to lock plate on door5 Data Room E8E.10 Remove all remaining parts of protective covering to door

6 Data Room E8E.10 Install rubber seal around door

7 Data Room E8E.10 Install door stop

8 Data Room E8E.10 Seal North wall to two (2) HVAC pipes and make good all round

9 Data Room E8E.10 Refix all plastic skirting as fixed with panel pins and make good with adhesive or clip-on system

10 Data Room E8E.10 Paint ceiling and beams

11 Data Room E8E.10 Seal conduit at ceiling level on East Wall and make good

12 Data Room E8E.10 Seal conduit at ceiling level on South Wall and make good

13 Data Room E8E.10 Complete conduit to Smoke Detector (done to two different types of conduit)

14 Data Room E8E.10 Remove timber formwork on East Wall between beam and slab and make good

Page 319: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 319/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Electrical Closet E8E.09 Paint ceiling

2 Electrical Closet E8E.09 Skirting fixed with panel pins and to be re-fixed with adhesive or clip-on system

3 Electrical Closet E8E.09 Make good to floor level on South Wall near door and refix floor covering

4 Electrical Closet E8E.09 Install skirting to South Wall as missing5 Electrical Closet E8E.09 Door dented at lock plate and to be made good as may inhibit the door closing

6 Electrical Closet E8E.09 Skirting loose on northern side of East Wall

7 Electrical Closet E8E.09 Skirting is missing on West wall (North)

8 Electrical Closet E8E.09 Make good to north wall next floor sinking and refix floor covering complete

9 Electrical Closet E8E.09 Infill large hole in southeast of room (fire stopping) Hole at present is a safety issue

10 Electrical Closet E8E.09 Skirting missing at North wall

11 Electrical Closet E8E.09 Skirting under Electrical Cabinet TUPS-8E on West wall is short and to be replaced

12 Electrical Closet E8E.09 Paint walls

13 Electrical Closet E8E.09 Make good to door plasterboard ingoings to both door frames and head frame

14 Electrical Closet E8E.09 Remove paint to Door Frames

15 Electrical Closet E8E.09 Fit rubber seal all round door

16 Electrical Closet E8E.09 Intumescent strip is short to hinge frame at base of door and to be replaced

17 Electrical Closet E8E.09 Intumescent strip is short to open frame at base and to be replaced

18 Electrical Closet E8E.09 Fixing screws to frame protrude and are to be refixed to door

19 Electrical Closet E8E.09 Cover four (4) protruding screw ends in angle plate to top corner to door

20 Electrical Closet E8E.09 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

21 Electrical Closet E8E.09 Install door stop to door 22 Electrical Closet E8E.09 Remove remaining protective covering to door

23 El t i l Cl t E8E 09 I t ll fi / k l th h ld l t t d

Page 320: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 320/407

23 Electrical Closet E8E.09 Install fire/smoke seal threshold plate to door

24 Electrical Closet E8E.09 Screw missing in lock plate to door

25 Electrical Closet E8E.09 Make good to floor covering cut short in front of Electrical Cabinet TL8-E

26 Electrical Closet E8E.09 Install door closer

27 Electrical Closet E8E.09 Door LH to Electrical Cabinet TL8-E is not fixed to head hinge and will fall out when opened

28 Electrical Closet E8E.09 Door sign

29 Electrical Closet E8E.09 Make good to wall base at return to East wall in middle and repaint

30 Electrical Closet E8E.09 Replace upper panel to RH of Electrical Cabinet TL8-E which is damaged

31 Electrical Closet E8E 09 Screw in the twenty eight (28) missing screws to the seven (7) control boxes to RH of SBS-12E

AMERICA HOUSE

Ref. Location Defect

No.

1 Janitor Closet E8E.07 Install protection to water pipe with meter

2 Janitor Closet E8E.07 Replace door grill screws (Internal) with white headed screws

3 Janitor Closet E8E.07 Fixing screws to frame protrude and are to be refixed to door

4 Janitor Closet E8E.07 Cover four (4) protruding screw ends in angle plate to top corner to door5 Janitor Closet E8E.07 Remove all remaining parts of protective covering to door

6 Janitor Closet E8E.07 Remove paint on door frames and make good

7 Janitor Closet E8E.07 Remove wall paint on trims to suspended ceilings and make good

8 Janitor Closet E8E.07 Redo angle edge to vertical corner to LH of door and make good

9 Janitor Closet E8E.07 Redo angle edge to vertical corner southeast and make good

10 Janitor Closet E8E.07 Make good to joint between wall and floor tiling on South Wall

11 Janitor Closet E8E.07 Make good to joint between wall and floor tiling on West Wall

12 Janitor Closet E8E.07 Make good ceiling trim at Column B16

13 Janitor Closet E8E.07 Install trough

14 Janitor Closet E8E.07 LH tap in wall is loose and requires to be fixed properly

15 Janitor Closet E8E.07 Tidy up loose layout of pipework connected with boiler

16 Janitor Closet E8E.07 RH tap in wall is loose and requires to be fixed properly

17 Janitor Closet E8E.07 Make good to VERY untidy suspended ceiling around Column B16

18 Janitor Closet E8E.07 Make good grouting etc to floor gulley

19 Janitor Closet E8E.07 Install door stop

20 Janitor Closet E8E.07 Make good to floor finish (ceramic tiles) to RH door frame

21 Janitor Closet E8E.07 Remove plastic protection from gulley grating

22 Janitor Closet E8E.07 Make good to floor finish (ceramic tiles) to LH door frame

23 Janitor Closet E8E 07 Make good to wall around conduit and four pipes to Boiler Unit and repaint

Page 321: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 321/407

23 Janitor Closet E8E.07 Make good to wall around conduit and four pipes to Boiler Unit and repaint

24 Janitor Closet E8E.07 Make good to hole in wall at corner behind boiler and repaint

25 Janitor Closet E8E.07 Paint behind Boiler which is missing

26 Janitor Closet E8E.07 Repair ceiling trim at North wall to RH side of door

27 Janitor Closet E8E.07 Make good to hole around water pipe on North Wall tiling

28 Janitor Closet E8E.07 Make good to hole around water pipe on East Wall tiling

29 Janitor Closet E8E.07 Make good to tile external angle at Column B 16

30 Janitor Closet E8E.07 Touch up damaged and chipped paintwork to door frames31 Janitor Closet E8E.07 Remove paint on Smoke Detector and make good

AMERICA HOUSE

Ref. Location Defect

No.

1 Pantry E8E.06 Wall tiling is generally poor workmanship

2 Pantry E8E.06 Make good joint between wall and floor tiling on North Wall

3 Pantry E8E.06 Clean off excess grouting throughout

4 Pantry E8E.06 Repair boiler leak and install proper safety valve5 Pantry E8E.06 Fixing screws to frame protrude and are to be refixed to door

6 Pantry E8E.06 Cover four (4) protruding screw ends in angle plate to top corner to door

7 Pantry E8E.06 Screw missing to lock plate on door

8 Pantry E8E.06 Remove all remaining parts of protective covering to door

9 Pantry E8E.06 Replace door grill screws (Internal) with white headed screws

10 Pantry E8E.06 Install rubber seal to door all round

11 Pantry E8E.06 Touch up chipped paintwork to door frames

12 Pantry E8E.06 Redo angle piece on wall tiling at head of door to Janitor Closet

13 Pantry E8E.06 Redo angle piece on wall tiling at external angle to LH of door to Janitor Closet

14 Pantry E8E.06 Redo angle piece on wall tiling at external angle to RH of door to Janitor Closet

15 Pantry E8E.06 Door frames are set above floor finish by 5mm and require to be reset

16 Pantry E8E.06 Redo seal at worktop at North Wall

17 Pantry E8E.06 Replace wall tiling angle piece to duct in southeast corner and make good all round

18 Pantry E8E.06 Install skirting at base of duct in southeast corner between base cabinets

19 Pantry E8E.06 Install plug to sink

20 Pantry E8E.06 Seal floor cabinet units between wall and units LH side and make good (East Wall)

21 Pantry E8E.06 Seal floor cabinet units between wall and units RH side and make good (East Wall)

22 Pantry E8E.06 Make good untidy joint between wall tiling and suspended ceiling on North Wall

23 Pantry E8E 06 Install door stop

Page 322: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 322/407

23 Pantry E8E.06 Install door stop

24 Pantry E8E.06 Install edging to PVC floor covering at door entrance

25 Pantry E8E.06 Make good to floor finishes at base of LH door frame to Vestibule

26 Pantry E8E.06 Make good to floor finishes at base of RH door frame to Vestibule

27 Pantry E8E.06 Reset to level position for power socket outlet (double) at floor level on North Wall

28 Pantry E8E.06 Are suspended ceiling tiles water resistant (pantry has boiling kettles etc.)

29 Pantry E8E.06 Seal floor cabinet units between wall and units LH side and make good (South Wall)

30 Pantry E8E.06 Double Sink shown on plans - who authorised change ?31 Pantry E8E.06 Wall cabinets on South wall are not level : reset

AMERICA HOUSE

Ref. Location Defect R

No. C

34 Pantry E8E.06 Make good tiling around door top Janitor Closet

35 Pantry E8E.06 Make good to ceiling trim along North Wall

36 Pantry E8E.06 Make good to wall finish to RH side of wall cabinets South Wall to reveal

37 Pantry E8E.06 Make good messy repair to LH door of Wall Cabinets on South Wall

Page 323: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 323/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Level 8 Japanese Embassy Window No 1 North Repair tighten window handle

2 Level 8 Japanese Embassy Window No 2 North Repair tighten window handle

3 Level 8 Japanese Embassy Window No 3 North Repair tighten window handle

4 Level 8 Japanese Embassy Window No 4 North Repair tighten window handle5 Level 8 Japanese Embassy Window No 5 North Repair tighten window handle

6 Level 8 Japanese Embassy Window No 6 North Repair tighten window handle

7 Level 8 Japanese Embassy Window No 7 North Repair tighten window handle

8 Level 8 Japanese Embassy Window No 8 North Repair tighten window handle

9 Level 8 Japanese Embassy Window No 9 North Repair tighten window handle

10 Level 8 Japanese Embassy Window No 10 North tighten window handle

11 Level 8 Japanese Embassy Window No. 11 North tighten window handle

12 Level 8 Japanese Embassy Window No 12 North repair defective angle seal at bottom

13 Level 8 Japanese Embassy Window No 13 North tighten window handle

14 Level 8 Japanese Embassy Window No 14 North tighten window handle

15 Level 8 Japanese Embassy Window No 2 East Tighten window handle

16 Level 8 Japanese Embassy Window No 4 East make good to angle piece seal at bottom

17 Level 8 Japanese Embassy Window Fan No 1 East tighten window handle

18 Level 8 Japanese Embassy Window Fan No 1 East upper seal to window sash is missing

19 Level 8 Japanese Embassy Window Fan No 1 East remove excess mastic and sealant.

20 Level 8 Japanese Embassy Window Fan No 1 South Repair seal at LH and RH to top of opening sash frame

21 Level 8 Japanese Embassy W indow Fan No 1 South tighten window handle

22 Level 8 Japanese Embassy Window Fan No 2 South make good to two (2) holes in cill frame and replace

23 Level 8 Japanese Embassy Window Fan No 2 South make good to window seal in distress at LH which is also broken and needs to be replaced

Page 324: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 324/407

p y g p

24 Level 8 Japanese Embassy W indow Fan No 2 South tighten window handle

25 Level 8 Japanese Embassy W indow Fan No 3 South tighten window handle

26 Level 8 Japanese Embassy Window Fan No 3 South make good to window seal in distress at LH which is also broken and needs to be replaced

27 Level 8 Japanese Embassy W indow Fan No 3 South tighten window handle

28 Level 8 Japanese Embassy Window Fan No 3 South Make good to frame seal that is loose and distorted at bottom both ends

29 Level 8 Japanese Embassy Window Fan No 1 South Remove excess mastic and sealant

30 Level 8 Japanese Embassy Window Fan No 2 South Remove excess mastic and sealant31 Level 8 Japanese Embassy Window Fan No 3 South Remove excess mastic and sealant

AMERICA HOUSE

Ref. Location Defect

No.

35 Level 8 Japanese Embassy Window Fan No 4 South Make good to damaged cill frame and replace

36 Level 8 Japanese Embassy Window Fan No 4 South Make good to inner opening sash seal where damaged at RH top

37 Level 8 Japanese Embassy Window Fan No 5 South Make good to outer seal of opening sash seal upper LH and RH where damaged at top

38 Level 8 Japanese Embassy Window Fan No 5 South tighten window handle39 Level 8 Japanese Embassy Window Fan No 6 South Repair make good to inner window sash seal damaged at bottom RH side

40 Level 8 Japanese Embassy Window Fan No 6 South tighten window handle

41 Level 8 Japanese Embassy Window Fan No 6 South adjust as difficult to close opening sash

42 Level 8 Japanese Embassy Window Fan No 7 South Make good to outer seal of opening sash where damaged at LH at top

43 Level 8 Japanese Embassy Window Fan No 7 South tighten window handle

44 Level 8 Japanese Embassy Remove paint in ceiling edge trim throughout

45 Level 8 Japanese Embassy Remove paint on ceiling diffusers on North Façade

46 Level 8 Japanese Embassy Remove paint on ceiling diffusers on South Façade

47 Level 8 Japanese Embassy Remove paint on ceiling diffusers on East Façade

48 Level 8 Japanese Embassy Window No 3 North repair to bottom angle seal in frame

49 Level 8 Japanese Embassy Window No 6 North repair to bottom angle seal in frame and distressed bottom seal

50 Level 8 Japanese Embassy Window No 7 North repair to bottom angle seal in frame

51 Level 8 Japanese Embassy Window No 5 East repair bottom angle seal and bottom seal in distress

52 Level 8 Japanese Embassy Make good pointing to Window at Boiler flue

53 Level 8 Japanese Embassy Replace broken glass at window return (South)

54 Level 8 Japanese Embassy Window Fan No 2 South adjust window as difficult to close

55 Level 8 Japanese Embassy Window Fan No 7 South remove excess mastic and sealant

56 Level 8 Japanese Embassy Replace suspended ceiling U bar where broken mid-span AB 14/15

57 Level 8 Japanese Embassy Replace dirty suspended ceiling tile in AB 14/15

Page 325: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 325/407

y y g

58 Level 8 Japanese Embassy Remove labels on all windows generally

59 Level 8 Japanese Embassy Clean general building debris out of runnels to all twenty eight (28) opening sashes

60 Level 8 Japanese Embassy W indow No 1 North repair broken restrainer

61 Level 8 Japanese Embassy Window No 2 North repair broken restrainer

62 Level 8 Japanese Embassy Window No 12 North repair broken restrainer

63 Level 8 Japanese Embassy Tidy up ceiling trims generally

64 Level 8 Japanese Embassy Replace water stained suspended ceiling tile AB 15/1665 Level 8 Japanese Embassy Replace damaged ceiling suspension system at AB 19/20

AMERICA HOUSE

Ref. Location Defect

No.

68 Level 8 Japanese Embassy Make good to suspended ceiling at Area B/C 19 where the ceiling dips and requires adjustment

69 Level 8 Japanese Embassy Replace two (2) dirty suspended ceiling tiles in CD 17/18

70 Level 8 Japanese Embassy Replace two (2) dirty suspended ceiling tiles in CD 15/16

71 Level 8 Japanese Embassy Replace damage U bar of the suspended ceiling system in CD 15/1672 Level 8 Japanese Embassy Replace two (2) dirty suspended ceiling tiles in CD 13/14

73 Level 8 Japanese Embassy Replace damage U bar of the suspended ceiling system in CD 13/14

74 Level 8 Japanese Embassy Remove paint on two HVAC controller on Column A13

75 Level 8 Japanese Embassy Remove paint on two HVAC controller on Column D13

76 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A14

77 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D14

78 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A15

79 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D15

80 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A16

81 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D16

82 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A17

83 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D17

84 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A18

85 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D18

86 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A19

87 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D19

88 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column A20

89 Level 8 Japanese Embassy Remove paint on three HVAC controller on Column D20

90 Level 8 Japanese Embassy Remove paint stains on ceiling diffusers on North Elevation

Page 326: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 326/407

91 Level 8 Japanese Embassy Remove paint stains on ceiling diffusers on South Elevation

92 Level 8 Japanese Embassy Remove paint stains on ceiling diffusers on East Elevation

AMERICA HOUSE

Ref. Location Defect

No.

1 East Triangle : East Elevation Install sixteen (16) black bolt caps to elevation of corrugated sheeting

2 East Triangle : East Elevation Make good poor joint near Car Park Entry on south east between short width of sheeting near corner

3 East Triangle : East Elevation Edge of corrugated sheeting is not fully masked by angle at southeast corner near Car Park entry

4 East Triangle : East Elevation Remove cement stains to base of corrugated sheeting5 East Triangle : East Elevation Remove coil of wire on corrugated sheeting

6 East Triangle : East Elevation Seal East Wall where it joins soffit of First Floor level which has not been properly addressed

7 East Triangle : East Elevation Corrugated sheeting is badly cut at First Floor Level next to glazing return and needs to be sealed and made good

8 East Triangle : East Elevation Angle mask is required at First floor level where corrugated sheeting meets the glazing panels

9 East Triangle : East Elevation Refit loose rubber seal to glazed are on LH side of East Elevation

10 East Triangle : East Elevation Make good to several uneven panel joins to corrugated sheeting on East Elevation at higher levels

11 East Triangle : East Elevation Replace two (2) damaged soffit panels at end of East Building on East Elevation near angle

12 East Triangle : East Elevation Seal corrugated sheeting where it is in distress near glazed area

13 East Triangle : East Elevation Make good the window seal in middle of glazed area that is debonding

14 East Triangle : East Elevation Make good mastic seal to glazed panels as required

15 East Triangle : East Elevation Seal to glazing next to corrugated sheeting on return is in distress and to be made good

16 East Triangle : East Elevation Mastic at RH side at angle with glazed return requires to be made good

17 East Triangle : East Elevation Seal joint of underside steel plating to corrugated sheeting above black rendered wall to car park ramp

18 East Triangle : East Elevation Seal open joint at bottom RH of East Elevation which also requires to be aligned

19 East Triangle : East Elevation Make good to badly cut sheets on RH side of East Elevation at base

20 East Triangle : East Elevation Make good to badly cut sheets on RH side of East Elevation above base

21 East Triangle : East Elevation Make good to badly cut sheets on RH side of East Elevation at upper level

22 East Triangle : East Elevation Angle piece (vertical) on RH side of East Elevation is not straight and to be refixed

23 East Triangle : East Elevation Refix seal in middle of glazed area East Elevation LH side

Page 327: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 327/407

24 East Triangle : East Elevation Refit top sheet as badly fitted to RH side of East Elevation at Level 2 Terrace

25 East Triangle : East Elevation Install two (2) black bolt caps to elevation of corrugated sheeting at Level 2 Terrace

26 East Triangle : East Elevation Make good gap and seal between corrugated sheeting and parapet wall Level 2 Terrace

27 East Triangle : East Elevation Make good and seal gap at top of parapet rail at Level 2 Terrace

28 East Triangle : East Elevation Make good angle joint with corrugated cladding to RH side at upper part of Level 2 Terrace

AMERICA HOUSE

Ref. Location Defect

No.

1 East Triangle : West Elevation Provide threshold plate seal to single leaf entry door

2 East Triangle : West Elevation Replace thirty two (32) screws fixing corrugated sheeting with standard fixing bolts and black cover caps

3 East Triangle : West Elevation Install twenty (20) black bolt caps to elevation of corrugated sheeting

4 East Triangle : West Elevation Make good seal between base profile and adjoining paviors

5 East Triangle : West Elevation Make good seal between corrugated sheeting and wall glazing to LH side of Glass Wall

6 East Triangle : West Elevation Remove labels on glass panels

7 East Triangle : West Elevation Fit missing seal to glazed panel above door

8 East Triangle : West Elevation Refix uneven corrugated panels above glazed wall with especial reference to joints

9 East Triangle : West Elevation Form base skirting to area of cladding at Level 2 Terrace

10 East Triangle : West Elevation Make good to joint between main sheeting and short cut panels on RH side at Level 2 Terrace

11 East Triangle : West Elevation Reset capping to top of wall on West Elevation as uneven

12 East Triangle : West Elevation Seal hole at bottom LH near parapet at Level 2 Terrace

Page 328: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 328/407

AMERICA HOUSE

Ref. Location Defect Rat

No. Clas

1 North Elevation to East Bridge Remove labels and make good

2 North Elevation to East Bridge Remove excess mastic on glass

3

4

56

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

Page 329: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 329/407

26

27

28

29

30

31

32

33

AMERICA HOUSE

Ref. Location Defect

No.

1 East Elevation Main Building Capping to white corrugated wall is uneven and distorted and to make level and proper at Level 2 terrace

2 East Elevation Main Building Install eighty one (81) white bolt caps to elevation of corrugated sheeting First Floor level

3 East Elevation Main Building Remove red vertical 'builder' lines three (3) no on white corrugated sheeting and make good at First Floor level

4 East Elevation Main Building Provide joint seal to corrugated sheeting to RH side at first floor level5 East Elevation Main Building Repair distorted and bulging white corrugated sheeting at First Floor level to South side of elevation and make good

6 East Elevation Main Building Replace angle seal at lower part of white corrugated sheeting at northern end at junction with Ground Floor soffit

7 East Elevation Main Building Review siting of two (2) CCTV cameras which seem to cover the same area

8 East Elevation Main Building Five downlighters have been placed out of line in soffit ceiling to Ground level and to be reset properly

9 East Elevation Main Building Soffit ceiling lining has been poorly cut round both boiler flues and requires to be recut or a trim made and fitted

10 East Elevation Main Building Double door requires a threshold plate and seal

11 East Elevation Main Building Remove labels to shopfront glazing

12 East Elevation Main Building Door intruder alarm white cable is set in black mastic window joint

13 East Elevation Main Building Remove wire fastening in window joint Ground Floor shopfront in second glazed panel from boiler flues RH

14 East Elevation Main Building Remove wire fastening in window joint Ground Floor shopfront in third glazed panel from boiler flues RH

15 East Elevation Main Building Seal glazed panel at base to LH side of double entry door

16 East Elevation Main Building Make good to poor joint at Ground Floor level to black corrugated sheeting at Northern end where it meets soffit lining

17 East Elevation Main Building Install twelve (12) black bolt caps to elevation of corrugated sheeting

18 East Elevation Main Building Make good to poor joint at Ground Floor level to black corrugated sheeting at Northern end where it meets paviors at base

Page 330: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 330/407

AMERICA HOUSE

No.

1 South Elevation Grd to Level 2 Realign irregular gaps between soffit panels under First Floor mall corridor to walkway at South Elevation

2 South Elevation Grd to Level 2 Remove builder's marks for downlighters to nine (9) mostly at eastern end

3 South Elevation Grd to Level 2 CCTV camera set at Main Office Entrance is obstructed by wing fang and should be positioned for clear view

4 South Elevation Grd to Level 2 Clean soffit lining to walkway (GF) as area BA 12/13 as very dirty and make good

5 South Elevation Grd to Level 2 Clean soffit panel at southern edge between A 12/23 and make good

6 South Elevation Grd to Level 2 Remove several pieces of protective covering and masking tape in gaps to soffit panels along GF walkway A12/23

7 South Elevation Grd to Level 2 Remove buckled soffit panel in Area A22/.23 and replace at GF walkway

8 South Elevation Grd to Level 2 Repair beige coloured reveal at edge of ceiling soffit to GF walkway between A13/14 that should match the rest and be black

9 South Elevation Grd to Level 2 Make good to ceiling trim around Column A 17 which is in distress

10 South Elevation Grd to Level 2 Remove paint splashes to ceiling trim at columns A13 to 19

Page 331: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 331/407

AMERICA HOUSE

1 Roof Landing B/C 14 Terrazzo tiling to floor is uneven and discoloured and requires to be replaced or evened, polished and resealed

2 Roof Landing B/C 14 Remove paint etc to top of terrazzo skirting throughout

3 Roof Landing B/C 14 Make good to terrazzo skirting damage at stairhead near door

4 Roof Landing B/C 14 Make good to joint with wall head just above landing floor level at northeast corner of landing slab

5 Roof Landing B/C 14 Make good to lining to smoke ventilation roof opening on South side

6 Roof Landing B/C 14 Clean wall mounted light of paint and dirt etc. and make good

7 Roof Landing B/C 14 Reset wall mounted light so that it is level

8 Roof Landing B/C 14 Make good terrazzo skirting to door at LH side and rounded arris at edge

9 Roof Landing B/C 14 Make good terrazzo skirting to door at RH side and rounded arris at edge

10 Roof Landing B/C 14 Door frames are set 6mm above floor and are to be set level

11 Roof Landing B/C 14 Remove paint to Door Frames

12 Roof Landing B/C 14 Fit rubber seal all round door

13 Roof Landing B/C 14 Intumescent strip is short to hinge frame at base of door and to be replaced

14 Roof Landing B/C 14 Intumescent strip is short to open frame at base of door and to be replaced

15 Roof Landing B/C 14 Fixing screws to frame protrude and are to be refixed to door 16 Roof Landing B/C 14 Cover four (4) protruding screw ends in angle plate to top corner to door

17 Roof Landing B/C 14 Intumescent str ip not continuous to side frames due to incorrect placement of str ike plate & security prong and to be corrected

18 Roof Landing B/C 14 Install door stop to door

19 Roof Landing B/C 14 Remove remaining protective covering to door

20 Roof Landing B/C 14 Install fire/smoke seal threshold plate to door

21 Roof Landing B/C 14 Screw missing in lock plate to door

22 Roof Landing B/C 14 Install door closer

23 Roof Landing B/C 14 Replace missing lock and handles

24 Roof Landing B/C 14 Door signage

25 Roof Landing B/C 14 Make good pointing to LH side of door to plaster and repaint

26 Roof Landing B/C 14 Make good pointing to RH side of door to plaster and repaint

Page 332: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 332/407

26 Roof Landing B/C 14 Make good pointing to RH side of door to plaster and repaint

27 Roof Landing B/C 14 Light switch plate is missing and bare wires are unprotected and exposed

28 Roof Landing B/C 14 Remove paint splashes etc on door surfaces

29 Roof Landing B/C 14 Running Man Sign to be reset level

AMERICA HOUSE

2 Roof Corridor B/C 14/15 Remove paint etc to top of terrazzo skirting throughout

3 Roof Corridor B/C 14/15 Terrazzo floor in lieu of cement screed in front of Electrical Cabinets

4 Roof Corridor B/C 14/15 Install Terrazzo skirting to three side of ingoing to Electrical cabinets

5 Roof Corridor B/C 14/15 Terrazzo skirting is missing to the RH of Electrical Cabinets on main wall

6 Roof Corridor B/C 14/15 Terrazzo skirting is missing to the LH of Electrical Cabinets on main wall

7 Roof Corridor B/C 14/15 Terrazzo skirting is uneven to northern end of East wall and to be made good

8 Roof Corridor B/C 14/15 Terrazzo skirting is broken to RH side of Egress Stair Door and to be repaired

9 Roof Corridor B/C 14/15 Terrazzo skirting to West Wall is poor workmanship and to be made good

10 Roof Corridor B/C 14/15 Terrazzo skirting is broken to RH side of West Wall towards Door North and to be repaired

11 Roof Corridor B/C 14/15 Terrazzo skirting is of poor workmanship at North Wall and to be made good

12 Roof Corridor B/C 14/15 Terrazzo skirting is damaged on West Wall and to be made good

13 Roof Corridor B/C 14/15 Redo RH return of terrazzo skirting to Egress Stair door and provide rounded arris on angle

14 Roof Corridor B/C 14/15 Redo LH return of terrazzo skirting to Egress Stair door and provide rounded arris on angle

15 Roof Corridor B/C 14/15 Install operator sign on Fire Alarm Bell Point to LH side of door

16 Roof Corridor B/C 14/15 Replace broken 'break' glass to Fire Alarm Bell Point17 Roof Corridor B/C 14/15 Install operator sign on Door Maglock release to RH side of door

18 Roof Corridor B/C 14/15 Install Door Emergency release Break Glass to LH side of door

19 Roof Corridor B/C 14/15 Remove paint from Fire Alarm Bell to LH side of Egress Stair Door

20 Roof Corridor B/C 14/15 Repair damaged edge arris to LH side of door to Egress Stair and repaint

21 Roof Corridor B/C 14/15 Realign conduit to light switch to LH side of door to Egress Stair which is not straight

22 Roof Corridor B/C 14/15 Consider repositioning light switch so as not to be so near Fire Alarm Bell Point

23 Roof Corridor B/C 14/15 Clean paint splashes etc from two (2) light fittings

24 Roof Corridor B/C 14/15 Seal North Wall to Rah side at junction with East Wall

25 Roof Corridor B/C 14/15 Provide Handrail to North Door Stair

26 Roof Corridor B/C 14/15 Mage good joint between door frame and wall at LH side of door vertically

27 Roof Corridor B/C 14/15 Make good to wall below threshold of Door North and repaint

Page 333: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 333/407

g p

28 Roof Corridor B/C 14/15 Seal Wall to North Wall at junction with West Wall just below the threshold of Door North

29 Roof Corridor B/C 14/15 Make good cable to North door contact intruder alarm which is very untidy

30 Roof Corridor B/C 14/15 Make good cable to South door contact intruder alarm which is very untidy

31 Roof Corridor B/C 14/15 Remove steel reinforcement rod to RH side of East Wall and make good

32 Roof Corridor B/C 14/15 Repoint to Electrical cabinets which is crazed and cracked all round

33 Roof Corridor B/C 14/15 Seal wall to LH side of Electrical cabinets and repaint

AMERICA HOUSE

36 Roof Corridor B/C 14/15 Provide handrail for Door South Stair

37 Roof Corridor B/C 14/15 Make good to wall below Door South threshold and repaint

38 Roof Corridor B/C 14/15 Make good damaged wall to RH side of South Wall blow door opening

39 Roof Corridor B/C 14/15 Make good patch of damaged wall to LH side at low level

40 Roof Corridor B/C 14/15 Seal for one (1) conduit near ceiling on South Wall and make good

41 Roof Corridor B/C 14/15 Seal for six (6) conduits near ceiling on East Wall and make good

42 Roof Corridor B/C 14/15 Seal for three (3) conduits near ceiling on East Wall and make good

43 Roof Corridor B/C 14/15 Seal hole near ceiling on West Wall and make good

44 Roof Corridor B/C 14/15 Seal for one (1) conduit near ceiling on North Wall and make good

45 Roof Corridor B/C 14/15 Seal hole to LH side of West Wall for flexible conduit (intruder alarm) and make good

46 Roof Corridor B/C 14/15 Seal hole to RH side of West Wall for flexible conduit (intruder alarm) and make good

47 Roof Corridor B/C 14/15 Door Frame to South Door is set at an angle in the opening and to be reset

48 Roof Corridor B/C 14/15 Remove paint to South Door Frames

49 Roof Corridor B/C 14/15 Fit rubber seal all round South door

50 Roof Corridor B/C 14/15 Intumescent strip is short to hinge frame at base of South door and to be replaced51 Roof Corridor B/C 14/15 Intumescent strip is short to open frame at base of South door and to be replaced

52 Roof Corridor B/C 14/15 Fixing screws to frame protrude and are to be refixed to South door

53 Roof Corridor B/C 14/15 Cover four (4) protruding screw ends in angle plate to top corner to South door

54 Roof Corridor B/C 14/15 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

55 Roof Corridor B/C 14/15 Install door stop to South door

56 Roof Corridor B/C 14/15 Remove remaining protective covering to South door

57 Roof Corridor B/C 14/15 Install fire/smoke seal threshold plate to South door

58 Roof Corridor B/C 14/15 Screw missing in lock plate to South door

59 Roof Corridor B/C 14/15 Install door closer to South Door

60 Roof Corridor B/C 14/15 Remove paint splashes to South door surfaces and make good

61 Roof Corridor B/C 14/15 Door signage to South Door

Page 334: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 334/407

62 Roof Corridor B/C 14/15 Replace damaged prong receiver on hinge frame of door South

63 Roof Corridor B/C 14/15 Install permanent handles to door South

64 Roof Corridor B/C 14/15 Install permanent lockset to Door South

65 Roof Corridor B/C 14/15 Remove paint to North Door Frames

66 Roof Corridor B/C 14/15 Fit rubber seal all round North door

AMERICA HOUSE

70 Roof Corridor B/C 14/15 Cover four (4) protruding screw ends in angle plate to top corner to North door

71 Roof Corridor B/C 14/15 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

72 Roof Corridor B/C 14/15 Install door stop to North door

73 Roof Corridor B/C 14/15 Remove remaining protective covering to North door

74 Roof Corridor B/C 14/15 Install fire/smoke seal threshold plate to North door

75 Roof Corridor B/C 14/15 Screw missing in lock plate to North door

76 Roof Corridor B/C 14/15 Install door closer to North Door

77 Roof Corridor B/C 14/15 Remove paint splashes to North door surfaces and make good

78 Roof Corridor B/C 14/15 Door signage to North Door

79 Roof Corridor B/C 14/15 Install permanent handles to door North

80 Roof Corridor B/C 14/15 Install permanent lockset to Door South

Page 335: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 335/407

AMERICA HOUSE

5 North Elevation Grd. D 16/20 Inverted L Vent No 1 RH make good to loose vertical ingoing lining and refix

6 North Elevation Grd. D 16/20 Inverted L shaped Vent No 1 LH make good to loose vertical ingoing lining and refix

7 North Elevation Grd. D 16/20 Inverted L shaped Vent No 1 LH make good to poor mitred joint at top.

8 North Elevation Grd. D 16/20 Inverted L shaped Vent No 1 remove mortar cement drippings in ventilator

9 North Elevation Grd. D 16/20 Realign ceiling soffit panel near rectangular Vent No 2 D 20

10 North Elevation Grd. D 16/20 Inverted L shaped Vent No 3 RH make good to loose vertical ingoing lining and refix

11 North Elevation Grd. D 16/20 Inverted L shaped Vent No 3 LH make good to loose vertical ingoing lining and refix

12 North Elevation Grd. D 16/20 Inverted L shaped Vent No 32 LH make good to poor mitred joint at top.

13 North Elevation Grd. D 16/20 Inverted L shaped Vent No 3 remove mortar cement drippings in ventilator

14 North Elevation Grd. D 16/20 Elongated rectangular Vent No 4 LH make good to loose vertical ingoing lining and refix

15 North Elevation Grd. D 16/20 Elongated rectangular Vent No 4 RH make good to loose vertical ingoing lining and refix

16 North Elevation Grd. D 16/20 Elongated rectangular Vent No 4 replace bent louvre towards the top

17 North Elevation Grd. D 16/20 Redo lining ingoing at cill to Elongated rectangular Vent No 4 as uneven and poor workmanship

18 North Elevation Grd. D 16/20 Install eighty six (86) black bolt caps to elevation of corrugated sheeting

19 North Elevation Grd. D 16/20 Refix loose ingoing lining to Fire Escape Door LH side D18/1920 North Elevation Grd. D 16/20 Refix loose ingoing lining to Fire Escape Door RH side D18/19

21 North Elevation Grd. D 16/20 Make good to floor base at Fire Escape Door at D 18/19

22 North Elevation Grd. D 16/20 Remove protective covering from door frames etc to Fire Escape Door D 18/19

23 North Elevation Grd. D 16/20 Remove all mortar and paint splashes from door frames to Fire Escape Door D 18/19

24 North Elevation Grd. D 16/20 Door seal loose at door base of Fire Escape Door and refix

25 North Elevation Grd. D 16/20 Make good to three (3) holes in hinge frame of Fire Escape Door D 18/19

26 North Elevation Grd. D 16/20 Remove all mortar and paint splashes from door to Fire Escape Door D 18/19

27 North Elevation Grd. D 16/20 Provide door threshold to Fire Escape Door D18/19

28 North Elevation Grd. D 16/20 Make good sinking in floor to LH side of door frame to Fire Escape Door D18/19

29 North Elevation Grd. D 16/20 Make good sinking in floor to RH side of door frame to Fire Escape Door D18/19

30 North Elevation Grd. D 16/20 Make good to LH side of Door Plinth 1 joint between corrugated cladding and concrete and repaint to Transformer Room

Page 336: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 336/407

31 North Elevation Grd. D 16/20 Make good to RH side of Door Plinth 1 joint between corrugated cladding and concrete and repaint to Transformer Room

32 North Elevation Grd. D 16/20 Make good to LH side of Door Plinth 2 joint between corrugated cladding and concrete and repaint to Transformer Room

33 North Elevation Grd. D 16/20 Make good to RH side of Door Plinth 2 joint between corrugated cladding and concrete and repaint to Transformer Room

AMERICA HOUSE

39 North Elevation Grd. D 16/20 Remove remaining parts of protective covering to doors and frames to Transformer Door No 2

40 North Elevation Grd. D 16/20 Remove remaining parts of protective covering to doors and frames to Transformer Door No 3

41 North Elevation Grd. D 16/20 Make good open mitred joint to top LH of Fire Escape Door side and head frame D 18/19

42 North Elevation Grd. D 16/20 Refix loose ingoing lining to Transformer Door No 1 LH side and make good all round

43 North Elevation Grd. D 16/20 Refix loose ingoing lining to Transformer Door No 1 RH side and make good all round

44 North Elevation Grd. D 16/20 Refix loose ingoing lining to Transformer Door No 2 LH side and make good all round

45 North Elevation Grd. D 16/20 Refix loose ingoing lining to Transformer Door No 2 RH side and make good all round

46 North Elevation Grd. D 16/20 Refix loose ingoing lining to Transformer Door No 3 LH side and make good all round

47 North Elevation Grd. D 16/20 Refix loose ingoing lining to Transformer Door No 3 RH side and make good all round

48 North Elevation Grd. D 16/20 Remove paint etc. from frames to Transformer Room Door No 1 and make good

49 North Elevation Grd. D 16/20 Remove paint etc. from frames to Transformer Room Door No 2 and make good

50 North Elevation Grd. D 16/20 Remove paint etc. from frames to Transformer Room Door No 3 and make good

51 North Elevation Grd. D 16/20 Remove paint etc from door surfaces of Transformer Door No 1 and make good

52 North Elevation Grd. D 16/20 Remove paint etc from door surfaces of Transformer Door No 2 and make good

53 North Elevation Grd. D 16/20 Remove paint etc from door surfaces of Transformer Door No 3 and make good54 North Elevation Grd. D 16/20 Install seal between lining and door frame to Transformer Door No 1 on RH side which is missing

55 North Elevation Grd. D 16/20 Reset angle piece at top between Transformer Doors 1 and 2 and make good

56 North Elevation Grd. D 16/20 Reset angle piece at top between Transformer Doors 2 and 3 and make good

57 North Elevation Grd. D 16/20 Reset angle piece at top between Transformer Door 3 and Vent Panel No 5 and make good

58 North Elevation Grd. D 16/20 Seal base profile end which is open to LH of Transformer Door No 1 at ground level and make good

59 North Elevation Grd. D 16/20 Seal base profile end which is open to RH of Transformer Door No 1 at ground level and make good

60 North Elevation Grd. D 16/20 Seal base profile end which is open to LH of Transformer Door No 2 at ground level and make good

61 North Elevation Grd. D 16/20 Seal base profile end which is open to RH of Transformer Door No 2 at ground level and make good

62 North Elevation Grd. D 16/20 Corrugated sheet lining between Transformer Doors 1 and 2 is short to base profile and requires to be redone

63 North Elevation Grd. D 16/20 Seal base profile end which is open to LH of Generator Door No 1 at ground level and make good

64 North Elevation Grd. D 16/20 Seal base profile end which is open to RH of Generator Door No 1 at ground level and make good

Page 337: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 337/407

65 North Elevation Grd. D 16/20 Seal base profile end which is open to LH of Generator Door No 2 at ground level and make good

66 North Elevation Grd. D 16/20 Seal base profile end which is open to RH of Generator Door No 2 at ground level and make good

AMERICA HOUSE

73 North Elevation Grd. D 16/20 Refix loose ingoing lining to Main Switch Room Door No 1 LH side and make good all round

74 North Elevation Grd. D 16/20 Refix loose ingoing lining to Main Switch Room Door No 1 RH side and make good all round

75 North Elevation Grd. D 16/20 Refix loose ingoing lining to Generator Room Door No 1 RH side and make good all round

76 North Elevation Grd. D 16/20 Refix loose ingoing lining to Generator Room Door No 1 LH side and make good all round

77 North Elevation Grd. D 16/20 Refix loose ingoing lining to Generator Room Door No 2 RH side and make good all round

78 North Elevation Grd. D 16/20 Refix loose ingoing lining to Generator Room Door No 2 LH side and make good all round

79 North Elevation Grd. D 16/20 Refix loose ingoing lining to Generator Room Door No 3 RH side and make good all round

80 North Elevation Grd. D 16/20 Refix loose ingoing lining to Generator Room Door No 3 LH side and make good all round

81 North Elevation Grd. D 16/20 Remove protective covering from frames to Generator Room Door No 1 and make good

82 North Elevation Grd. D 16/20 Remove protective covering from frames to Generator Room Door No 2 and make good

83 North Elevation Grd. D 16/20 Remove protective covering from frames to Generator Room Door No 3 and make good

84 North Elevation Grd. D 16/20 Remove paint and mortar splashes from door frames to Generator Room Door No 1 and make good

85 North Elevation Grd. D 16/20 Remove paint and mortar splashes from door frames to Generator Room Door No 2 and make good

86 North Elevation Grd. D 16/20 Remove paint and mortar splashes from door frames to Generator Room Door No 3 and make good

87 North Elevation Grd. D 16/20 Remove paint and mortar splashes to door surfaces to Generator Room Door No 1 and make good88 North Elevation Grd. D 16/20 Remove paint and mortar splashes to door surfaces to Generator Room Door No 2 and make good

89 North Elevation Grd. D 16/20 Remove paint and mortar splashes to door surfaces to Generator Room Door No 3 and make good

90 North Elevation Grd. D 16/20 Remove paint and mortar splashes from door frames to Main Switch Room Door No 1 and make good

91 North Elevation Grd. D 16/20 Remove paint and mortar splashes to door surfaces to Main Switch Room Door No 1 and make good

92 North Elevation Grd. D 16/20 Make good dent at end of Generator Exhaust No 1

93 North Elevation Grd. D 16/20 Make good dent at end of Generator Exhaust No 2

94 North Elevation Grd. D 16/20 Seal and make good poorly cut corrugated sheeting around exhaust duct No 1 to generators or install circular trim

95 North Elevation Grd. D 16/20 Seal and make good poorly cut corrugated sheeting around exhaust duct No 2 to generators or install circular trim

96 North Elevation Grd. D 16/20 Make good to frame base to Main Switch Room Door No 1 at LH side

97 North Elevation Grd. D 16/20 Change fuel pipe filling points to coupling type to Generator No 1

98 North Elevation Grd. D 16/20 Change fuel pipe filling points to coupling type to Generator No 2

G / f f G

Page 338: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 338/407

99 North Elevation Grd. D 16/20 Make good to corrugated wall covering around fuel filling point to Generator No 1

AMERICA HOUSE

107 North Elevation Grd. D 16/20 Install vertical angle piece to corrugated sheeting wall at return to Docking Bay and make good all round

108 North Elevation Grd. D 16/20 Corrugated sheeting at Docking Bay return is short at base and to be replaced

109 North Elevation Grd. D 16/20 Redo base profile at return to Docking Bay and make good

Page 339: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 339/407

R f L ti D f t

AMERICA HOUSE

Page 340: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 340/407

Ref. Location Defect

AMERICA HOUSE

10 North Elevation G to 2 D 13/16 Refix loose ingoing linings RH to Security Room Window

11 North Elevation G to 2 D 13/16 Make good to bottom LH mitred joint to Security Room window

12 North Elevation G to 2 D 13/16 Make good to corrugated sheeting under Security Room window where short to base profile and replace

13 North Elevation G to 2 D 13/16 Supply and fit missing bolt fixing at base of corrugated sheeting under Security Room window

14 North Elevation G to 2 D 13/16 Align base profile near Security Room window and to the right side of it and make good

15 North Elevation G to 2 D 13/16 Corrugated sheeting has been cut short to base profile under Security Room window and to be replaced

16 North Elevation G to 2 D 13/16 Remove all paint and mortar splashes on corrugated wall sheeting

17 North Elevation G to 2 D 13/16 Refix RH ingoing linings to Vertical rectangular Vent No 6 and make good

18 North Elevation G to 2 D 13/16 Refix LH ingoing linings to Vertical rectangular Vent No 6 and make good

19 North Elevation G to 2 D 13/16 Refix RH ingoing linings to Vertical rectangular Vent No 7 and make good

20 North Elevation G to 2 D 13/16 Refix LH ingoing linings to Vertical rectangular Vent No 7 and make good

21 North Elevation G to 2 D 13/16 Refix RH ingoing linings to Vertical rectangular Vent No 8 and make good

22 North Elevation G to 2 D 13/16 Refix LH ingoing linings to Vertical rectangular Vent No 8 and make good

23 North Elevation G to 2 D 13/16 Make good at bottom LH mitred joint to ingoing linings to Vent Rectangular No 6

24 North Elevation G to 2 D 13/16 Make good at bottom RH mitred joint to ingoing linings to Vent Rectangular No 7 25 North Elevation G to 2 D 13/16 Make good at bottom LH mitred joint to ingoing linings to Vent Rectangular No 8

26 North Elevation G to 2 D 13/16 Install seventy nine (79) black bolt caps to elevation of corrugated sheeting on North Elevation Grd to 2nd D 13/16

27 North Elevation G to 2 D 13/16 Remove mortar to louvres and frame of rectangular ventilator No 6 and make good

28 North Elevation G to 2 D 13/16 Remove mortar to louvres and frame of rectangular ventilator No 7 and make good

29 North Elevation G to 2 D 13/16 Remove mortar to louvres and frame of rectangular ventilator No 8 and make good

30 North Elevation G to 2 D 13/16 Ref it Ventilator No 7 as badly fitted complete

31 North Elevation G to 2 D 13/16 Replace forty (40) silver coloured headed screws to ventilation panel at First Floor ceiling level to match black frame

32 North Elevation G to 2 D 13/16 Replace damaged louvre in rectangular Vent No 9

33 North Elevation G to 2 D 13/16 Corrugated sheeting is badly cut to expansion joint and is damaged in parts and to be made good and angle inserted

Page 341: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 341/407

Ref. Location DefectNo

AMERICA HOUSE

11 North Elevation First Floor D20/18 Refix joint between corrugated sheet 4 and sheet 5 to RH side of Panel 6

12 North Elevation First Floor D20/18 Refix joint between corrugated sheet 5 and bottom sheet RH side of Panel 6

13 North Elevation First Floor D20/18 Make good to distorted Sheet 2 in Panel 6 at LH side that has lifted

14 North Elevation First Floor D20/18 Make good to poor fitting of bottom sheet in Panel 6 to base profile angle

15 North Elevation First Floor D20/18 Remove wire cable coming out of building above ventilator grille in panel 4 and make good to sheeting etc.

16 North Elevation First Floor D20/18 Refix joint between top corrugated sheet and sheet 2 to LH side of Panel 5

17 North Elevation First Floor D20/18 Refix joint between corrugated sheet 2 and sheet 3 to full width side of Panel 5

18 North Elevation First Floor D20/18 Refix joint between corrugated sheet 3 and sheet 4 to RH side of Panel 6

19 North Elevation First Floor D20/18 Refix joint between corrugated sheet 4 and bottom sheet RH side of Panel 6

20 North Elevation First Floor D20/18 Refix joint between top corrugated sheet and sheet 2 at LH side of Panel 4

21 North Elevation First Floor D20/18 Refix joint between corrugated sheet 2 and sheet 3 at LH side of Panel 4

22 North Elevation First Floor D20/18 Refix joint between corrugated sheet 3 and sheet 4 at LH side of Panel 4

23 North Elevation First Floor D20/18 Refix joint between corrugated sheet 4 and sheet 5 at LH side of Panel 4

24 North Elevation First Floor D20/18 Make good to distorted Sheet 5 in Panel 2 at RH side that has lifted

25 North Elevation First Floor D20/18 Make good to distorted Sheet 5 in Panel 1 at RH side that has lifted 26 North Elevation First Floor D20/18 Refix joint between top corrugated sheet and sheet 2 to RH side of Panel 2

27 North Elevation First Floor D20/18 Refix joint between corrugated sheet 2 and sheet 3 to RH side of Panel 2

28 North Elevation First Floor D20/18 Refix joint between corrugated sheet 3 and sheet 4 to RH side of Panel 2

29 North Elevation First Floor D20/18 Refix joint between corrugated sheet 4 and sheet 5 to RH side of Panel 2

30 North Elevation First Floor D20/18 Install seventy nine (79) white bolt caps to elevation of corrugated sheeting First Floor level

31 North Elevation First Floor D20/18 Refix warped and irregular capping to return at D18 at Level 2 Terrace

32 North Elevation First Floor D20/18 Make good to angle between return and main elevation at D 18 where angle is short at the base

Page 342: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 342/407

Ref. Location Defect

No.

1 Soffit Grd Flr D16/20 Remove pencil marks on soffit lining to eleven (11) light fittings and make good

AMERICA HOUSE

Page 343: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 343/407

Ref. Location Defect

No.

1 South Elevation 2 to 8 Make good to Joint lining panels between East and West which are not aligned or properly installed

2 South Elevation 2 to 8 Cap ends of ALL profiles at joint between East and West buildings and make good including mastic excess removal

AMERICA HOUSE

13 South Elevation 2 to 8 Refix loose outer soffit panel near Door West to Euroest Invest Area

14 South Elevation 2 to 8 Profile frame at base on main façade Level 2/3 is short near Column A 18 LH and to be replaced

15 South Elevation 2 to 8 Remove paint splashes to underside of soffit to Terrace Level 2

Page 344: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 344/407

Ref. Location Defect

No.

1 East Elevation 2 to 8 Make good to profile frame damage Level 2/3 on LH side of elevation East

2 East Elevation 2 to 8 Seal hole to left of Boiler Flue at base of 3rd Floor vertical profile

3 East Elevation 2 to 8 Repaint to rusty part of frame holdfasts to Boiler Flue from Level 2 through to Level 8

AMERICA HOUSE

R f L ti D f t

Page 345: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 345/407

Ref. Location Defect

No.

1 North Elevation Level 2 to 8 Make good to exposed padding at soffit joint between Panels 1 and 2

2 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 2 and 3

3 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 3 and 4

4 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 4 and 5

AMERICA HOUSE

15 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 15 and 16

16 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 16 and 17

17 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 17 and 18

18 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 18 and 19

19 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 19 and 20

20 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 20 and 21

21 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 21 and 22

22 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 22 and 23

23 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 23 and 24

24 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 24 and 25

25 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 25 and 26

26 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 26 and 27

27 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 27 and 28

28 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 28 and 29

29 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 29 and 30 30 North Elevation Level 2 to 8 Make good open joint at soffit between Panel 30 and 31

31 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 1

32 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 2

33 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 3

Ref. Location Defect

Page 346: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 346/407

No.

34 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 W indow 4

35 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 5

36 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 6

37 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 7

38 North Elevation Level 2 to 8 Capping to windows between D16 and D15 at Terrace Level 2 Window 8

AMERICA HOUSE

Ref. Location Defect

No.

1 Lifts Provide fixing to stop 'wobble' of call button panel in Service Elevator

Page 347: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 347/407

1 Lifts Provide fixing to stop wobble of call button panel in Service Elevator

2 Lifts Remove all protective covering to handrail in Service lift/elevator

3 Lifts Realign gap between Car ceiling and top of mirror wall which is uneven to Lift PE 09

4 Lifts Refix skirting to back wall of lift car to Lift PE 09 which is loose

5 Lifts Refix front skirting to RH side of Lift Car which is loose to Lift PE 09

6 Lifts Clean plastic head piece to call button panel and refix to PE 09

AMERICA HOUSE

Ref. Location Defect

No.

1 Service Lift Motor Room BC 14/15 Paint ceiling

2 Ser ice Lift Motor Room BC 14/15 Paint floor incl ding steps

Page 348: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 348/407

2 Service Lift Motor Room BC 14/15 Paint floor including steps

3 Service Lift Motor Room BC 14/15 Paint walls

4 Service Lift Motor Room BC 14/15 Cover up exposed reinforcement to LH lower of East Wall and make good

5 Service Lift Motor Room BC 14/15 Seal to duct on LH side of East wall near North wall and make good all round

6 Service Lift Motor Room BC 14/15 Seal hole above duct to LH side of East Wall near North Wall and make good

7 Service Lift Motor Room BC 14/15 Make good to two (2) formwork fixing holes and seal to East Wall

AMERICA HOUSE

18 Service Lift Motor Room BC 14/15 Make good to eight (8) formwork fixing holes and seal to South Wall

19 Service Lift Motor Room BC 14/15 Remove nail in lower part of South Wall and make good to wall

20 Service Lift Motor Room BC 14/15 Make good to honeycombed wall to left part repaint complete to West Wall

21 Service Lift Motor Room BC 14/15 Seal and make good to conduit on West Wall (South)

22 Service Lift Motor Room BC 14/15 Seal and make good to conduit on West Wall (Centre)

23 Service Lift Motor Room BC 14/15 Remove two conduit holdfasts (obsolete) on West Wall to right of near North Wall and make good

24 Service Lift Motor Room BC 14/15 Seal large hole with two ventilation ducts to West Wall and make good all round

25 Service Lift Motor Room BC 14/15 Make good to six (6) formwork fixing holes and seal to West Wall

26 Service Lift Motor Room BC 14/15 Remove two (2) steel bolt fixings at West Wall lower in middle and make good

27 Service Lift Motor Room BC 14/15 Remove one conduit holdfast (obsolete) on West Wall (Centre) and make good

28 Service Lift Motor Room BC 14/15 Remove polystyrene to North Door as this is a fire door and polystyrene is combustible

29 Service Lift Motor Room BC 14/15 Make good to wall above door top frame and repaint

30 Service Lift Motor Room BC 14/15 Clean conduit of paint to RH side of door for full height

31 Service Lift Motor Room BC 14/15 Concrete steps are very rough and need to be properly levelled and shaped

32 Service Lift Motor Room BC 14/15 Provide handrail to stair33 Service Lift Motor Room BC 14/15 Remove steel reinforcement rod to LH side of North Wall at lower level and make good

Ref. Location Defect

No.

34 Service Lift Motor Room BC 14/15 Remove two (2) steel reinforcement rods to RH side of North Wall at lower level and make good

35 Service Lift Motor Room BC 14/15 Remove paint etc. from conduit to RH side of North Wall door

36 S i Lift M t R BC 14/15 M k d t i (6) f k fi i h l d l t N th W ll

Page 349: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 349/407

36 Service Lift Motor Room BC 14/15 Make good to six (6) formwork fixing holes and seal to North Wall

37 Service Lift Motor Room BC 14/15 Tidy up wires to Door intruder alarm contact

38 Service Lift Motor Room BC 14/15 Seal ventilator duct in northeast corner of room to floor and make good all round

39 Service Lift Motor Room BC 14/15 Complete blockwork housing and capping to ventilation duct in northeast corner of room

40 Service Lift Motor Room BC 14/15 Seal and make good to hole in floor slab at southeast corner

41 Service Lift Motor Room BC 14/15 Remove paint to North Door Frames

AMERICA HOUSE

52 Service Lift Motor Room BC 14/15 Door is fouling on lightning protection system which requires to be relocated

53 Service Lift Motor Room BC 14/15 Remove paint splashes to North door surfaces and make good

54 Service Lift Motor Room BC 14/15 Door signage to North Door

55 Service Lift Motor Room BC 14/15 Install permanent handles to door North

56 Service Lift Motor Room BC 14/15 Intumescent strip is partly missing on head frame and to be replaced

57 Service Lift Motor Room BC 14/15 Lockset is missing and to be installed

58 Service Lift Motor Room BC 14/15 Replace damaged strike plate to Door North

59 Service Lift Motor Room BC 14/15 Make good to rust on door head and repaint

60 Service Lift Motor Room BC 14/15 Touch up chipped/damaged paintwork to frames

61 Service Lift Motor Room BC 14/15 Remove manufacturer's labels on door and make good

62 Service Lift Motor Room BC 14/15 Install door closer to North Door

Ref. Location Defect

No.

1 Lift Motor Room BC 16/17 Paint ceiling

2 Lift Motor Room BC 16/17 Paint floor including steps

3 Lift Motor Room BC 16/17 Paint walls not yet properly painted

4 Lift Motor Room BC 16/17 Make good to concrete steps and make necessary remedial works

Page 350: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 350/407

4 Lift Motor Room BC 16/17 Make good to concrete steps and make necessary remedial works

5 Lift Motor Room BC 16/17 Install handrail to stairs

6 Lift Motor Room BC 16/17 Make good wall around Fan on North Wall and repaint

7 Lift Motor Room BC 16/17 Remove paint on wall telephone on North Wall

8 Lift Motor Room BC 16/17 Make good hole to RH of steps on North Wall and repaint as required

9 Lift Motor Room BC 16/17 Light switch to LH side of door to be set at a more workable height

AMERICA HOUSE

20 Lift Motor Room BC 16/17 Remove paint on conduit on West Wall especially near ceiling

21 Lift Motor Room BC 16/17 Make good to wall where two (2) conduits pass through to West Wall and seal

22 Lift Motor Room BC 16/17 Make good all round to ventilator opening on South Wall at head and repaint as required

23 Lift Motor Room BC 16/17 Set Running Man Sign level

24 Lift Motor Room BC 16/17 Complete conduit to ceiling mounted Smoke Detector

25 Lift Motor Room BC 16/17 Remove paint to North Door Frames

26 Lift Motor Room BC 16/17 Fit rubber seal all round North door  

27 Lift Motor Room BC 16/17 Intumescent strip is short to hinge frame at base and head of North door and to be replaced

28 Lift Motor Room BC 16/17 Intumescent strip is short to open frame at base and head of North door and to be replaced

29 Lift Motor Room BC 16/17 Fixing screws to frame protrude and are to be refixed to North door  

30 Lif t Motor Room BC 16/17 Cover four (4) protruding screw ends in angle plate to top corner to North door 

31 Lift Motor Room BC 16/17 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

32 Lift Motor Room BC 16/17 Install door stop to North door  

33 Lift Motor Room BC 16/17 Remove remaining protective covering to North door  

Ref. Location Defect

No.

34 Lift Motor Room BC 16/17 Install fire/smoke seal threshold plate to North door

35 Lift Motor Room BC 16/17 Screw missing in lock plate to North door

36 Lift Motor Room BC 16/17 Replace lockset with permanent locks

37 Lift Motor Room BC 16/17 Remove paint splashes to North door surfaces and make good

38 Lift Motor Room BC 16/17 Door signage to North Door

Page 351: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 351/407

38 Lift Motor Room BC 16/17 Door signage to North Door

39 Lift Motor Room BC 16/17 Install permanent handles to door North

40 Lift Motor Room BC 16/17 Intumescent strip is missing on head frame and to be replaced

41 Lift Motor Room BC 16/17 Replace temporary door handles with permanent ones

42 Lift Motor Room BC 16/17 Install door closer to North Door

43 Lift Motor Room BC 16/17 Make good to holes in floor near door north

AMERICA HOUSE

Ref. Location Defect

No.

1 Mechanical Room : Roof BC 17/18 Paint ceiling

2 Mechanical Room : Roof BC 17/18 Paint walls3 Mechanical Room : Roof BC 17/18 Paint floor including steps

4 Mechanical Room : Roof BC 17/18 Fit rubber seal all round North door

5 Mechanical Room : Roof BC 17/18 Intumescent strip is missing to hinge frame North door and to be replaced

6 Mechanical Room : Roof BC 17/18 Intumescent strip is missing to open frame of North door and to be replaced

Page 352: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 352/407

p g p p

7 Mechanical Room : Roof BC 17/18 Fixing screws to frame protrude and are to be refixed to North door

8 Mechanical Room : Roof BC 17/18 Cover four (4) protruding screw ends in angle plate to top corner to North door

9 Mechanical Room : Roof BC 17/18 Intumescent strip not continuous to side frames due to incorrect placement of strike plate & security prong and to be corrected

10 Mechanical Room : Roof BC 17/18 Install door stop to North door

11 Mechanical Room : Roof BC 17/18 Remove remaining protective covering to North door

AMERICA HOUSE

22 Mechanical Room : Roof BC 17/18 Touch up chipped/damaged paintwork to frames

23 Mechanical Room : Roof BC 17/18 Remove manufacturer's labels on door and make good

24 Mechanical Room : Roof BC 17/18 Make good to rough steps and level and carry out required remedial works

25 Mechanical Room : Roof BC 17/18 Install stair handrail

26 Mechanical Room : Roof BC 17/18 Make good to poor concrete on North wall

27 Mechanical Room : Roof BC 17/18 Cap or cut four bolts to floor plate near door

28 Mechanical Room : Roof BC 17/18 Provide protection at eye level to steel channel near door

29 Mechanical Room : Roof BC 17/18 Change Panel label SBS 13E which is a plastic holder with paper sign with Ivorine label

30 Mechanical Room : Roof BC 17/18 In southwest corner, cap or cut four (4) bolts to four (4) stanchion base plates at floor level

31 Mechanical Room : Roof BC 17/18 Seal wall in southeast corner at duct

32 Mechanical Room : Roof BC 17/18 Make good render to wall at blockwork ventilation enclosure in southeast corner

33 Mechanical Room : Roof BC 17/18 Remove general snots of concrete on floor (before painting)

Ref. Location Defect

No.

34 Mechanical Room : Roof BC 17/18 On East Wall cap or cut four (4) bolts to three (3) stanchion plates at floor level

35 Mechanical Room : Roof BC 17/18 In middle of room, cap or cut four (4) bolts to three (3) stanchions at floor level

36 Mechanical Room : Roof BC 17/18 Tidy up and gully and reset gulley grating in recessed frame complete37 Mechanical Room : Roof BC 17/18 Pipe insulation to pipework to gulley is poor workmanship and the copious usage of tape in a probably water filled area is bad

38 Mechanical Room : Roof BC 17/18 Finish block work to ventilator duct on West Wall (South)

39 Mechanical Room : Roof BC 17/18 Repair blockwork on South Wall near duct exit and make good and seal to duct and pipes

40 Mechanical Room : Roof BC 17/18 Make good missing blockwork at wall return on West Wall High level) and seal all round

Page 353: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 353/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Roof Housing BC 14/15 External Fix lightning strip on LH side to South wall and make good

2 Roof Housing BC 14/15 External Fix lightning strip on RH side to South wall and make good

3 Roof Housing BC 14/15 External Paint patch repair above door on South wall

4 Roof Housing BC 14/15 External Paint patch repair to LH side of door on South Wall5 Roof Housing BC 14/15 External Paint two (2) repair patches to Left of Door at base of South wall

6 Roof Housing BC 14/15 External Paint two (2) repair patches to Left Door at South

7 Roof Housing BC 14/15 External Paint LH ingoing of door on South Wall

8 Roof Housing BC 14/15 External Paint RH ingoing of door on South Wall

Page 354: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 354/407

9 Roof Housing BC 14/15 External Paint head ingoing of door to South Wall

10 Roof Housing BC 14/15 External Seal around duct to RH of door on South Wall and paint all round

11 Roof Housing BC 14/15 External Make good to chipped threshold step

12 Roof Housing BC 14/15 External Paint to patch near and around patch to ventilator fan

13 Roof Housing BC 14/15 External Patch and paint to LH duct at low level near roof duct channel

AMERICA HOUSE

24 Roof Housing BC 14/15 External Level and fix capping to South Wall

25 Roof Housing BC 14/15 External Level and fix capping to East Wall

26 Roof Housing BC 14/15 External Level and fix capping to North Wall

27 Roof Housing BC 14/15 External Level and fix capping to West Wall

28 Roof Housing BC 14/15 External Fix lightning strip on LH side to North wall and make good

29 Roof Housing BC 14/15 External Fix lightning strip on RH side to North wall and make good

30 Roof Housing BC 14/15 External Reconnect or remove cable on North Wall that is open

31 Roof Housing BC 14/15 External Remove paint on conduit to light on North Wall

32 Roof Housing BC 14/15 External Seal hole for conduit and make good and paint at north wall above door to Roof Corridor

33 Roof Housing BC 14/15 External Seal wall at four (4) access ladder fixing points at North Wall

Ref. Location Defect

No.

34 Roof Housing BC 14/15 External Make good to damaged step to Roof Corridor and seal

35 Roof Housing BC 14/15 External Seal to Upper Duct between doors on North Wall, make good and paint all round

36 Roof Housing BC 14/15 External Seal to Lower Duct between doors on North Wall, make good and paint all round

37 Roof Housing BC 14/15 External Repaint to LH side of Door to Service Elevator Motor Room

38 Roof Housing BC 14/15 External Repaint to RH side of Door to Service Elevator Motor Room

39 Roof Housing BC 14/15 External Repaint to head of Door to Service Elevator Motor Room

40 Roof Housing BC 14/15 External Paint LH ingoing of door on North Wall to Roof Corridor

41 Roof Housing BC 14/15 External Paint RH ingoing of door on North Wall to Roof Corridor

42 Roof Housing BC 14/15 External Paint head ingoing of door on North Wall to Roof Corridor

Page 355: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 355/407

43 Roof Housing BC 14/15 External Plastic roof cover to smoke ventilation is damaged on northeast corner and to be replaced

44 Roof Housing BC 14/15 External Smoke Ventilator is inoperable as broken

45 Roof Housing BC 14/15 External Access Ladder is made of reinforcement steel (backstreet) and should be replaced

46 Roof Housing BC 14/15 External Access Ladder to be repainted as it is rusting in several places with external weather resistant paint

47 Roof Housing BC 14/15 External Access Ladder to be fixed to parapet as the top guide handle are 'shaking' and unstable

AMERICA HOUSE

58 Roof Housing BC 14/15 External Make good to two large duct pipes and paint all round to East Lower Wall

59 Roof Housing BC 14/15 External Make good to top of plasterboard linings to smoke vent shaft in roof

Ref. Location Defect

No.

1 Roof Housing External BC 16/18 Remove three (3) supports to cable tray built into West Wall (Lower), reset and make good to wall complete

2 Roof Housing External BC 16/18 Seal at base of West Wall Lower and repaint along full length

3 Roof Housing External BC 16/18 Seal to conduit tray and cables to LH side of West Lower Wall and make good all round and repaint

4 Roof Housing External BC 16/18 Seal to conduit tray and cables to middle of West Lower Wall and make good all round and repaint

5 Roof Housing External BC 16/18 Make good to poor workman ship to cable tray along full length of West Wall Lower

6 Roof Housing External BC 16/18 Make good painting to two (2) areas on West Wall Lower that were repaired but not painted

7 Roof Housing External BC 16/18 Seal and make good to vent duct to LH side of West Wall Lower and repaint all round

8 Roof Housing External BC 16/18 Seal and make good to vent duct to RH side of West Wall Lower and repaint all round

9 Roof Housing External BC 16/18 Seal and make good to circular vent duct to RH side of West Wall Lower and repaint all round

10 Roof Housing External BC 16/18 Make good to edge with walkway and repaint for full length of West Wall Lower

Page 356: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 356/407

11 Roof Housing External BC 16/18 Make good to edge of LH return to West Wall Lower at walkway at North End

12 Roof Housing External BC 16/18 Make good to edge of RH return to West Wall Lower at walkway at South End

13 Roof Housing External BC 16/18 Seal and make good around Vent pipe with proper collar piece on West Wall walkway

14 Roof Housing External BC 16/18 Remove three (3) adhesive/glue fixings to flexible conduit and fix to wall with proper fixings

15 Roof Housing External BC 16/18 Point and paint to West Wall just below capping and make good for full length of wall

AMERICA HOUSE

26 Roof Housing External BC 16/18 Seal and make good to one (1) conduit to South Wall and repaint towards the middle

27 Roof Housing External BC 16/18 Seal and make good to upper vent duct on South Wall (middle) and repaint all round

28 Roof Housing External BC 16/18 Seal and make good to lower vent duct on South Wall (middle) and repaint all round

29 Roof Housing External BC 16/18 Make good rough wall around two circular duct pipes and seal and make good and repaint all round

30 Roof Housing External BC 16/18 Repair damaged capping on East Wall and make good and repaint to wall surface

31 Roof Housing External BC 16/18 Seal and make good to one (1) conduit to East Wall and repaint towards the middle

32 Roof Housing External BC 16/18 Repaint return wall south at East Wall

33 Roof Housing External BC 16/18 Repaint edge to east facing upper part of enclosure on East Wall and make good

Ref. Location Defect

No.

34 Roof Housing External BC 16/18 Seal and make good to LH ventilator duct to East Wall and repaint all round

35 Roof Housing External BC 16/18 Seal and make good to RH ventilator duct to East Wall and repaint all round

36 Roof Housing External BC 16/18 Make good to northern return to East Wall and repaint at upper walkway

37 Roof Housing External BC 16/18 Seal and make good around Vent pipe with proper collar piece on East Wall walkway (North)

38 Roof Housing External BC 16/18 Repaint wall where repaired at former opening for ventilator duct to LH side of North Wall

39 Roof Housing External BC 16/18 Seal and make good to LH ventilator duct on LH side of North Wall and repaint all round

40 Roof Housing External BC 16/18 Seal and make good to RH ventilator duct on LH side of North Wall and repaint all round

41 Roof Housing External BC 16/18 Make good step to Mechanical Room and paint

42 Roof Housing External BC 16/18 Make good to hole at base of RH door frame to Mechanical Room and seal and paint

43 Roof Housing External BC 16/18 Make good to hole at base of LH door frame to Mechanical Room and seal and paint

44 Roof Housing External BC 16/18 Repaint repair above door to Mechanical Room on North Wall

Page 357: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 357/407

45 Roof Housing External BC 16/18 Seal and make good to ventilator duct to RH of door to mechanical Room on North Wall and repaint all round

46 Roof Housing External BC 16/18 Seal and make good to ventilator fan to Lift Motor Room on North Wall in infill hole at top and paint all round

47 Roof Housing External BC 16/18 Seal and make good to one (1) conduit on North Wall and paint

48 Roof Housing External BC 16/18 Repair wall where damaged by door handle of door to Lift Motor Room North Wall and repaint

49 Roof Housing External BC 16/18 Repaint wall to LH side of Door to Lift Motor Room North Wall

AMERICA HOUSE

60 Roof Housing External BC 16/18 Access Ladder to be fixed to parapet as the top guide handle are 'shaking' and unstable

61 Roof Housing External BC 16/18 Make good to top of plasterboard linings to smoke vent shaft in roof

62 Roof Housing External BC 16/18 Smoke Ventilator is inoperable as broken

63 Roof Housing External BC 16/18 Make good to gulley opening and form good receptor

64 Roof Housing External BC 16/18 Fit missing dome grating to roof gulley

65 Roof Housing External BC 16/18 Screed expansion strips are generally becoming loose and missing and requires to be repaired and replaced

66 Roof Housing External BC 16/18 Make good to Lift Motor Room door that id damaged on the hinge edge

Ref. Location Defect

No.

1 Roof Well BC 15/17 Seal and make good to four (4) ladder fixings to wall at North Wall

2 Roof Well BC 15/17 Seal and make good to four (4) ladder fixings to wall at South Wall

3 Roof Well BC 15/17 Access Ladder to North Wall is made of reinforcement steel (backstreet) and should be replaced

4 Roof Well BC 15/17 Access Ladder to South Wall is made of reinforcement steel (backstreet) and should be replaced

5 Roof Well BC 15/17 Access Ladder to South Wall to be repainted as it is rusting in several places with external weather resistant paint

6 Roof Well BC 15/17 Access Ladder to North Wall to be repainted as it is rusting in several places with external weather resistant paint

7 Roof Well BC 15/17 Refix top RH ladder fixing on North Wall that is loose and make good

8 Roof Well BC 15/17 Fix lightning rod strip LH properly to North wall as at present it has no fixings9 Roof Well BC 15/17 Fix lightning rod strip RH properly to North wall as at present it has no fixings

10 Roof Well BC 15/17 Fix lightning rod strip LH properly to South wall as at present it has no fixings

11 Roof Well BC 15/17 Fix lightning rod strip RH properly to South wall as at present it has no fixings

12 Roof Well BC 15/17 Access Ladder upper above duct is not stable and requires stay support on North Side

13 R f W ll BC 15/17 A L dd b d t i t t bl d i t t S th Sid

Page 358: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 358/407

13 Roof Well BC 15/17 Access Ladder upper above duct is not stable and requires stay support on South Side

14 Roof Well BC 15/17 Make good to North Wall at base in middle and repaint

15 Roof Well BC 15/17 Make good to roof gulley and refix dome grating complete

16 Roof Well BC 15/17 Ventilation WC Unit is not properly set on roof with absorbers etc.

AMERICA HOUSE

Ref. Location Defect

No.

1 Roof Well BC 13/14 Seal and make good to four (4) ladder fixings to wall at North Wall

2 Roof Well BC 13/14 Seal and make good to four (4) ladder fixings to wall at South Wall

3 Roof Well BC 13/14 Access Ladder to North Wall is made of reinforcement steel (backstreet) and should be replaced

4 Roof Well BC 13/14 Access Ladder to South Wall is made of reinforcement steel (backstreet) and should be replaced

5 Roof Well BC 13/14 Access Ladder to South Wall to be repainted as it is rusting in several places with external weather resistant paint

6 Roof Well BC 13/14 Access Ladder to North Wall to be repainted as it is rusting in several places with external weather resistant paint

7 Roof Well BC 13/14 Refix top RH ladder fixing on North Wall that is loose and make good

8 Roof Well BC 13/14 Access Ladder upper above duct is not stable and requires stay support on North Side

9 Roof Well BC 13/14 Access Ladder upper above duct is not stable and requires stay support on South Side10 Roof Well BC 13/14 Make good to roof gulley and refix dome grating complete

11 Roof Well BC 13/14 Fix lightning rod strip LH properly to North wall as at present it has no fixings

12 Roof Well BC 13/14 Fix lightning rod strip LH properly to South wall as at present it has no fixings

13 Roof Well BC 13/14 Seal and make good to South Wall LH side to cable tray and two (2) conduits and repaint

14 Roof Well BC 13/14 Seal at wall base for full length and repaint to South Wall

Page 359: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 359/407

14 Roof Well BC 13/14 Seal at wall base for full length and repaint to South Wall

15 Roof Well BC 13/14 Repaint repair to top of RH of South Wall and make good

16 Roof Well BC 13/14 Make good to edge of roof and divider wall and repaint along full length

17 Roof Well BC 13/14 Make good to edge of roof and Wall to Roof Housing BC 14/15 East

18 Roof Well BC 13/14 Make good to return wall at Divider Wall on North Wall and repaint

AMERICA HOUSE

Ref. Location Defect

No.

1 Roof Duct BC 13/19 Seal to wall to Roof Housing BC 14/15 near roof duct and make good and repaint wall (South)

2 Roof Duct BC 13/19 Generally tidy up lightning strip installation and cover plates and brick anchors in area B 13/19

3 Roof Duct BC 13/19 Generally tidy up lightning strip installation and cover plates and brick anchors in area C 13/19

4 Roof Duct BC 13/19 Generally tidy up lightning strip installation and cover plates and brick anchors in area B/C 19

5 Roof Duct BC 13/19 AHU near Roof Housing BC 14/15 is set on Roof Duct and not the design position and blocks walkway roof duct

6 Roof Duct BC 13/19 Roof duct screed in area C 13/17 is badly cracked and crazed and to be repaired and made good

7 Roof Duct BC 13/19 Screed expansion strips are generally becoming loose and missing and requires to be repaired and replaced

8 Roof Duct BC 13/19 Make good to hose clips used to join flexible conduits to steel conduits near BC 14/15 housing (2 No.)

9 Roof Duct BC 13/19 Change rusty plug caps to Glycol Tank (2 No)

10 Roof Duct BC 13/19 Seal and make good to four (4) ladder fixings to wall at South Wall of duct at B 1311 Roof Duct BC 13/19 Seal and make good to four (4) ladder fixings to wall at South Wall of duct at B 16

12 Roof Duct BC 13/19 Seal and make good to two (2) ladder fixings to wall at South Wall of duct at B 16

13 Roof Duct BC 13/19 Access Ladder to South Duct Wall (B 13) is made of reinforcement steel (backstreet) and should be replaced

14 Roof Duct BC 13/19 Access Ladder to South Duct Wall (B 16) is made of reinforcement steel (backstreet) and should be replaced

15 Roof Duct BC 13/19 Sloping Access ladder to South Duct wall at B16 requires to be painted in external weather resistant paint as rusting

Page 360: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 360/407

15 Roof Duct BC 13/19 Sloping Access ladder to South Duct wall at B16 requires to be painted in external weather resistant paint as rusting

16 Roof Duct BC 13/19 Access Ladder to South Duct W all (B13) to be repainted as it is rusting in several places with external weather resistant paint

17 Roof Duct BC 13/19 Access Ladder to South Duct W all (B16) to be repainted as it is rusting in several places with external weather resistant paint

18 Roof Duct BC 13/19 Remove steel reinforcement rod near B15 in South Duct wall and make good and repaint

19 Roof Duct BC 13/19 Remove three (3) steel reinforcement rods near B16 in South Duct Wall and make good and repaint

AMERICA HOUSE

30 Roof Duct BC 13/19 Seal and make good to conduit on South Duct Wall B 17/18 and repaint

31 Roof Duct BC 13/19 Make good damaged wall lining to South Duct Wall at B13 and repaint

32 Roof Duct BC 13/19 Make good damaged wall lining to South Duct Wall at B14 and repaint

33 Roof Duct BC 13/19 Make good damaged wall lining to South Duct Wall at B15 and repaint

Ref. Location Defect

No.

34 Roof Duct BC 13/19 Make good damaged wall lining to South Duct Wall at B16 and repaint

35 Roof Duct BC 13/19 Make good damaged wall lining to South Duct Wall at B17 and repaint

36 Roof Duct BC 13/19 Make good to three (3) areas of damaged wall lining to South Duct Wall at B18 and repaint

37 Roof Duct BC 13/19 Make good to three (3) areas of damaged wall lining to South Duct Wall at B19 and repaint

38 Roof Duct BC 13/19 Make good damaged wall lining to East Duct Wall at B19 and repaint

39 Roof Duct BC 13/19 Repaint repair to East Duct Wall at LH end

40 Roof Duct BC 13/19 Make good to walkway edge for full length and repaint East Duct Wall upper

41 Roof Duct BC 13/19 Remove steel plate and two (2) fixing bolts on LH side of East Duct Wall and make good and repaint

42 Roof Duct BC 13/19 Remove six (6) steel reinforcement rods in East Duct Wall and make good and repaint

43 Roof Duct BC 13/19 Fix lightning rod strip at LH side of East Duct wall as at present it has no fixings

44 Roof Duct BC 13/19 Fix lightning rod strip at RH side of East Duct wall as at present it has no fixings45 Roof Duct BC 13/19 Repaint repairs to RH side at end of East Duct Wall and make good

46 Roof Duct BC 13/19 Seal East Duct Wall at base with main roof and repaint

47 Roof Duct BC 13/19 Repaint repair area on East Duct Wall to left of three circular ducts

48 Roof Duct BC 13/19 Seal and make good to cable tray on LH side of East Duct Wall and repaint

49 Roof Duct BC 13/19 Seal and make good to cable tray on RH side of East Duct Wall and repaint

Page 361: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 361/407

49 Roof Duct BC 13/19 Seal and make good to cable tray on RH side of East Duct Wall and repaint

50 Roof Duct BC 13/19 Seal and make good to circular ducts (3 No ) and make good and repaint

51 Roof Duct BC 13/19 Make good edges to concrete base for AHU on Roof Duct

52 Roof Duct BC 13/19 Repaint repair to North Duct Wall at C 19

53 Roof Duct BC 13/19 Repair wall at edge to North Duct Wall at C 18 make good and repaint

AMERICA HOUSE

64 Roof Duct BC 13/19 Fix two (2) steel conduit properly to roof duct at C14/15

65 Roof Duct BC 13/19 Repaint three repairs to RH side of North Duct Wall C 13/14 for pipes

66 Roof Duct BC 13/19 Seal and Make good to two pipes to RH side of North Duct Wall C 13 and repaint

Ref. Location Defect

No.

67 Roof Duct BC 13/19 Seal and make good to four (4) ladder fixings to wall at South Wall of duct at C 13

68 Roof Duct BC 13/19 Seal and make good to four (4) ladder fixings to wall at South Wall of duct at C 16

69 Roof Duct BC 13/19 Seal and make good to two (2) ladder fixings to wall at South Wall of duct at C 16

70 Roof Duct BC 13/19 Access Ladder to South Duct Wall (C 13) is made of reinforcement steel (backstreet) and should be replaced

71 Roof Duct BC 13/19 Access Ladder to South Duct Wall (C 16) is made of reinforcement steel (backstreet) and should be replaced

72 Roof Duct BC 13/19 Sloping Access ladder to South Duct wall at C16 requires to be painted in external weather resistant paint as rusting

73 Roof Duct BC 13/19 Access Ladder to South Duct Wall (C13) to be repainted as it is rusting in several places with external weather resistant paint

74 Roof Duct BC 13/19 Access Ladder to South Duct Wall (C16) to be repainted as it is rusting in several places with external weather resistant paint

75 Roof Duct BC 13/19 Seal and make good to two (2) circular duct at pipes at C 17 on North Duct wall and repaint

76 Roof Duct BC 13/19 Seal and make good to cable tray and cables at C 17 on North Duct Wall and repaint

77 Roof Duct BC 13/19 Seal and make good to one (1) conduit at C 16 on North Duct Wall and repaint

78 Roof Duct BC 13/19 Seal and make good to two (2) conduits at C 15/16 on North Duct Wall and repaint79 Roof Duct BC 13/19 Seal and make good to hole in North Duct Wall at C 14/16 and repaint

80 Roof Duct BC 13/19 Repaint repair at RH end of North Duct wall and on part return to divider wall

Page 362: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 362/407

AMERICA HOUSE

Ref. Location Defect

No.

1 Main Roof AD 13/20 Remove adhesive and remnants of polystyrene panels to upstand of parapet on North Wall D 13/20 and make good

2 Main Roof AD 13/20 Remove adhesive and remnants of polystyrene panels to upstand of parapet on South Wall A 13/20 and make good

3 Main Roof AD 13/20 Remove adhesive and remnants of polystyrene panels to upstand of parapet on East Wall A/D 20 and make good

4 Main Roof AD 13/20 Remove timber battens left in screed in area CD 14/18 and make good

5 Main Roof AD 13/20 Remove timber battens left in screed in area B/d 18/20 and make good

6 Main Roof AD 13/20 Make good to roof gulley at C14

7 Main Roof AD 13/20 Fix dome grating to roof gulley C 14

8 Main Roof AD 13/20 Make good to roof gulley at C16

9 Main Roof AD 13/20 Fix dome grating to roof gulley C 16

10 Main Roof AD 13/20 Make good to roof gulley at C18

11 Main Roof AD 13/20 Fix dome grating to roof gulley C 18

12 Main Roof AD 13/20 Make good to roof gulley at C19

13 Main Roof AD 13/20 Fix dome grating to roof gulley C 19 14 Main Roof AD 13/20 Make good to roof gulley at B14

15 Main Roof AD 13/20 Fix dome grating to roof gulley B 14

16 Main Roof AD 13/20 Make good to roof gulley at B 16

17 Main Roof AD 13/20 Fix dome grating to roof gulley B 16

18 Main Roof AD 13/20 Make good to roof gulley at B 18

Page 363: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 363/407

19 Main Roof AD 13/20 Fix dome grating to roof gulley B 18

20 Main Roof AD 13/20 Make good to roof gulley at B 19

21 Main Roof AD 13/20 Fix dome grating to roof gulley B 19

22 Main Roof AD 13/20 Make good to area of 'ponding' to roof screed in area CD 15/16

AMERICA HOUSE

Ref. Location Defect

No.

1 Valve Room S1E 14 Level -1 Remove polystyrene foam around door and replace with inert and acceptable filler to the approval of W4A

2 Valve Room S1E 14 Level -1 Make good to render above door on outside face and repaint

3 Valve Room S1E 14 Level -1 Fixing screws to frame protrude and are to be refixed to North door

4 Valve Room S1E 14 Level -1 Cover four (4) protruding screw ends in angle plate to top corner to North door

5 Valve Room S1E 14 Level -1 Remove paint to Door Frames

6 Valve Room S1E 14 Level -1 Fit rubber seal all round door

7 Valve Room S1E 14 Level -1 Touch up chipped paint on door frames

8 Valve Room S1E 14 Level -1 Install door stop

9 Valve Room S1E 14 Level -1 Replace plastic door handles with anodised handles

10 Valve Room S1E 14 Level -1 Remove remaining protective covering from door etc and make good

11 Valve Room S1E 14 Level -1 Remove paint stains etc on door frames and make good

12 Valve Room S1E 14 Level -1 Replace strikeplate to door frame as showing signs of distress

13 Valve Room S1E 14 Level -1 Remove wood block spacer between door frame of blockwork RH side (open)

14 Valve Room S1E 14 Level -1 Remove twelve (12) screw fixings to Southwest wall and make good and repaint15 Valve Room S1E 14 Level -1 Remove three (3) reinforcement rods near ceiling on Southwest Wall and make good and repaint

16 Valve Room S1E 14 Level -1 Fill in hole left behind after formwork fixings removed and make good and repaint wall

17 Valve Room S1E 14 Level -1 Remove cementitious deposits on sprinkler pipe and repaint

18 Valve Room S1E 14 Level -1 Render to door returns to sides and head has not been done and to be executed includiong paint finish

19 Valve Room S1E 14 Level -1 Repaint fllor that is damaged and poor workmanship

Page 364: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 364/407

20 Valve Room S1E 14 Level -1 Paint wall

21 Valve Room S1E 14 Level -1 Paint ceiling

AMERICA HOUSE

Ref. Location Defect

No.

1 Vestibule Level -1 (SE1 15) Door and Frame to be installed

2 Vestibule Level -1 (SE1 15) Repaint floor as damaged and poor quality

3 Vestibule Level -1 (SE1 15) Paint ceiling

4 Vestibule Level -1 (SE1 15) Remove paint on conduit drop to light switch

5 Vestibule Level -1 (SE1 15) Make good holes in Northeast wall and make good and repaint wall

Page 365: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 365/407

AMERICA HOUSE

Ref. Location DefectNo.

1 Storage Area Level -1 S1E 016 Install door

2 Storage Area Level -1 S1E 016 Clean floor

3 Storage Area Level -1 S1E 016 Clear out general builder's debris etc

4 Storage Area Level -1 S1E 016 Make good to square hole in floor slab in southwest corner and make good including floor paint

5 Storage Area Level -1 S1E 016 Level floor near East Wall BC 23 where concrete snots and depositis were not removed before floor paint application

6 Storage Area Level -1 S1E 016 Remove paint on conduit drop near door and make good

7 Storage Area Level -1 S1E 016 Remove paint to conduit drop to telephone outlet on Northeast wall and make good

8 Storage Area Level -1 S1E 016 Make good to render above door on Northwest wall at D22 and repaint

9 Storage Area Level -1 S1E 016 Seal wall near ceiling on northwest corner of room at D22 and make good around two (2) electrical conduits

10 Storage Area Level -1 S1E 016 Remove cementitious deposits on sprinkler pipework and repaint

11 Storage Area Level -1 S1E 016 Install missing smoke detector in Area AB 22/23 in Storage Area

12 Storage Area Level -1 S1E 016 Realign hangers to sprinkler pipework that are not vertical

13 Storage Area Level -1 S1E 016 Clean three (3) ceiling light fittings

14 Storage Area Level -1 S1E 016 Paint ceiling

15 Storage Area Level -1 S1E 016 Make good to honeycombed area to Southwaest wall and repaint as required

Page 366: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 366/407

AMERICA HOUSE

Ref. Location Defect

No.1 Storage under Ramp Level -1 Make good to uneven concrete finish to sloping ceiling

2 Storage under Ramp Level -1 Remove formwork left at base on ramp to low wall and returns and repaint wall

3 Storage under Ramp Level -1 Paint ceiling

4 Storage under Ramp Level -1 Make good to very rough area of sloping ceiling near southwest wall and cover up exposed reinforcement etc.

5 Storage under Ramp Level -1 Remove formwork left in opening to Southwest wall B23 and make good

6 Storage under Ramp Level -1 Fill in hole at B23 in wall and seal completely and repaint

7 Storage under Ramp Level -1 Remove metal coverplate on East Wall at B23 including ten (10) reinforcement rod retainers and replace with proper hatch

8 Storage under Ramp Level -1 Remove formwork left at southeast corner of area B23 and make good to ceiling

9 Storage under Ramp Level -1 Remove reinforcement rod left in southwest wall and make good

10 Storage under Ramp Level -1 Fill in three (3) holes left behind after formwork fixings removed and make good and repaint wall

11 Storage under Ramp Level -1 Repaint walls

12 Storage under Ramp Level -1 Clean floor paint finish which is very dirty and stained

Page 367: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 367/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 368

Page 368: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 368/407

4/10/2013 368

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 369

Page 369: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 369/407

4/10/2013 369

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 370

Page 370: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 370/407

4/10/2013 370

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 371

Page 371: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 371/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 372

Page 372: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 372/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 373

Page 373: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 373/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 374

Page 374: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 374/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 375

Page 375: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 375/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 376

Page 376: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 376/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 377

Page 377: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 377/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 378

Page 378: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 378/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 379

Page 379: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 379/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 380

Page 380: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 380/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 381

Page 381: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 381/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 382

Page 382: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 382/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 383

Page 383: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 383/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 384

Page 384: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 384/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 385

Page 385: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 385/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 386

Page 386: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 386/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 387

Page 387: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 387/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 388

Page 388: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 388/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 389

Page 389: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 389/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 390

Page 390: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 390/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 391

Page 391: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 391/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 392

Page 392: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 392/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 393

Page 393: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 393/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 394

Page 394: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 394/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 395

Page 395: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 395/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 396

Page 396: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 396/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 397

Page 397: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 397/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 398

Page 398: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 398/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 399

Page 399: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 399/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 400

Page 400: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 400/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 401

Page 401: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 401/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 402

Page 402: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 402/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 403

Page 403: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 403/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 404

Page 404: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 404/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 405

Page 405: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 405/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 406

Page 406: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 406/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 407

Page 407: America House Snagging List 25.05.06 (East)

7/28/2019 America House Snagging List 25.05.06 (East)

http://slidepdf.com/reader/full/america-house-snagging-list-250506-east 407/407

AMERICA HOUSE SNAGGING LIST (EAST)

4/10/2013 408