aide memoire implementation support mission rw, 15-26 … · a study tour of 167 extension lead...
TRANSCRIPT
Final Draft CONFIDENTIAL
1
AIDE MEMOIRE
Implementation Support Mission
Land Husbandry, Water Harvesting and Hillside Irrigation (LWH) (P114931 IDA Credit No. 4674–RW,
GAFSP Grant TF099108, CIDA Grant TF011435 and USAID Grant TF010953)
15-26 July 2013
A. INTRODUCTION AND ACKNOWLEDGEMENTS
1. From 15 to 26 July 2013, a World Bank team carried out the seventh implementation support mission
for the Land Husbandry, Water Harvesting and Hillside Irrigation (LWH) Project (third joint implementation
support mission with RSSP). The team was coordinated by Valens Mwumvaneza (Rural Development
Specialist) and Mark Austin (Sr. Operations Officer) Co-Task Team Leaders. The team was composed of Meena
Munshi (Senior Economist); Svetlana Khvostova (Safeguards Analyst); Abel Lufafa (Agricultural Officer and
Soil Specialist); Markus Moeller (Water and Irrigation Engineer); Amadou Soumaila (Senior Irrigation
Specialist, FAO); Lazare Hoton (Credit and Rural Finance Officer, FAO); Thierry Lassalle (Institutional
Development and Agribusiness Specialist, FAO Consultant); Pascal Tegwa (Senior Procurement Specialist);
Antoinette Kamanzi (Procurement Assistant); Jasmeen Batra (Economist, DIME); and Belinda Mutesi (Team
Assistant). Lillian Brenda Namutebi (Consultant, FMS) supported the mission remotely. Terhi Majanen and
Vedaste Gatebuka (USAID) participated in the mission. The team worked closely with staff of the LWH/RSSP
Single Project Implementation Unit (SPIU) in the Ministry of Agriculture and Animal Resources (MINAGRI).
Members of the mission team met with Government officials, Project staff and national and local level, service
providers, and Project beneficiaries (see Annex 1). Discussions were held with Dr. Agnes Kalibata (Minister,
MINAGRI) and Mr. Ernest Ruzindaza (Permanent Secretary, MINAGRI). The team expresses its appreciation
for the assistance provided by all those met. The Bank and MINAGRI confirmed their understanding and
agreement to publicly disclose this Aide Memoire at the wrap-up meeting that took place on 26 July 2013 in
Kigali. A separate Technical Annex, referred to herein, forms an integral part of this Aide Memoire.
2. The mission was carried out to provide implementation support to both the LWH and RSSP projects
and was carried out jointly with the Government of Rwanda (GoR) to review: (i) the progress of activities under
the LWH technical components since the MTR mission (in January 2013) and follow up on recommendations
from the MTR mission; (ii) the draft and approve the Annual Work Plan and Budget (AWPB July 2013- June
2014) and the updated Procurement Plan; (iii) the progress of on-going hillside irrigation development and plans
to achieve end of project targets (EOPT); (iv) the progress on all activities related to the Bank's safeguards
policies, including safeguard preparations for Phase 2 sites; (v) the project’s M&E operations, reports, and
update of indicators and develop a one pager on indicators definitions and computation; (vi) early lessons and
progress on DIME impact evaluation; (vii) lessons on South-South partnership on community mobilization and
follow up action; and (viii) the progress and proposed actions to further the nutrition agenda within the project
beneficiaries. Key observations and recommendations of the mission are summarized below, and elaborated in
the annexes.
B. CONTEXT
3. The project development objective (PDO) of LWH is to increase the productivity and commercialization
of hillside agriculture in target areas. The Project has three components: (A) Capacity Development and
Institutional Strengthening for Hillside Intensification; (B) Infrastructure for Hillside Intensification; and (C)
Implementation through the Ministerial SWAp Structure. The Project became effective in June 2010 with USD
34 million IDA financing and additional financing from GAFSP USD50 million; USD7.8 million from CIDA
and up to USD14 million (USD10 million to-date) from USAID bringing the total project financing to
USD105.8 million. A mid-term review (MTR) was conducted in January 2013 which recommended a light
restructuring of the project. The restructuring was finalized and approved on November 8, 2013; at the same time
an additional financing to the project is also being prepared and is expected to be completed by December 2013.
The project will close by 31 December 2015.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
2
C. KEY FINDINGS/PROGRESS OF IMPLEMENTATION
Status of Results and Achievement of Development Objectives
4. For the last fiscal year, which is the third year of implementation since the project effectiveness in
June 2010, LWH implemented 96% of its annual budget and has spent and committed 60% of its total project
budget.
5. LWH has completed land husbandry works on 7,906 ha which is 61% of EOPT, launched irrigation
works in three sites covering 694 ha which is 37% of EOPT and tenders for additional 732 ha of irrigation works
are to be launched in August 2013. Additionally, plans for 3,700 ha land husbandry in hillside are planned for the
current fiscal year. Yields of maize, beans, and Irish potato in treated areas are 30%, 167% and 219%,
respectively above their national average. Sediment yield in four sites reduced by an average of 66% relative to
the time when the land husbandry works were being constructed. The productivity of non-irrigated hillsides has
increased to US$ 2357 per ha; farmers in Cooperatives in LWH sites have commercialized up to 74% which is
above the EOPT of 70%; and the number of project direct beneficiaries has increased to 92,381 of which 49%
are women.
6. Project Rating: LWH is rated satisfactory both in progress towards accomplishing its Project
Development Objectives (PDO) and in Implementation Progress.
Assessment of Implementation Performance
Component A: Capacity Development and Institutional Strengthening for Hillside Intensification
A1: Strengthening Farmer Organizations
7. The main objective of this subcomponent is to build and strengthen farmer organizations,
cooperatives, and Water User Associations (WUAs). The sub-component has made good progress during the last
six months and is rated satisfactory. The field visit interactions with the beneficiaries revealed a high degree of
community enthusiasm and understanding of the project, a strong willingness and commitment to participate and
contribute to watershed development. The key achievements during the last six months have been: (i) adopting of
a harmonized capacity building plan; (ii) fine-tuning of the structure of the farmer/community organizations to
ensure clarity on roles and responsibilities of various levels of community organization and continuity of
leadership; (iii) refining of the monitoring system and initiating a comprehensive database of beneficiaries to
monitor and track results; and (iv) introducing community level reporting and information system. The project
has also recruited local service providers, and launched the capacity building program (training, refreshers,
exposure visits, etc.).
8. The implementation progress on this sub component, key recommendations, and priority actions are
summarized below, and details are included in the Technical Annex 8 on Sub-Component A.1. As of June 30,
2013, the project had implemented most of the recommendations of the MTR mission, and laid a solid
foundation and structure for the community organizations. There are a few areas that would need attention going
forward which are highlighted in the Technical Annex 8. The project has succeeded in formation of 1,067 Self
Help Groups (SHGs) reaching out to 21,180 members in current seven sites, out of which 8,571 (about 40%)
are women. In addition, 77 zonal organizations and five cooperatives have been formed and have started
functioning. 4,866 SHG members have joined the five new cooperatives. There is now better clarity of roles and
responsibilities at the zonal and cooperative level, and four cooperatives have started generating revenues, which
is a positive sign towards financial sustainability. The project has also formed six WUAs which have started
functioning. Phase 1A sites WUAs (in Nyanza 23 and Karongi 12 & 13) have received training in administrative
and financial management, and conflict resolution, and have benefited from exposure visits to good practices. So
far, three WUAs of Phase 1A have acquired district level license certificates which give them recognition to
operate in the district.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
3
9. The following actions have been agreed with the project team: (i) use an improved planning and
reporting format to capture, track, and report progress of key process steps and milestones on community
institutional development by end of December, 2013; (ii) complete grading of SHGs, Zones/Cooperatives, and
WUAs (which have completed one year) by December 31, 2013; (iii) update and finalize the remaining training
modules (including July 2013 South to south training) and train Service providers and TOTs by Oct. 31, 2013;
and (iv) complete legal registration of existing WUAs and set-up three remaining district irrigation committees,
etc.
A2: Extension
10. The objectives of this component are to improve soil fertility and farming skills for intensification and
commercialized rain-fed or irrigated agriculture. The project has adopted a multipronged approach involving
private service providers, farmer based extension and public extension agencies. During the last six months, the
project has strengthened the capacity of grass-root institutions (farmer groups, farmer plat-forms and
cooperatives) as actors in extension support and information dissemination. The project has extended a
partnership agreement with a private extension service provider (TUBURA One Acre Fund) whose field officers
assist project farmers through the season on all the current 7 project sites. TUBURA provides inputs (inorganic
fertilizers and improved seeds) and extension service to project beneficiaries. The project continued to support
the farmer based extension approach through the use of lead farmers within the SHGs and the use of
demonstration plots within the Farmer Field Schools (FFS) model. The extension sub component performance is
rated satisfactory.
11. In the last six month a total of 675 extension lead farmers (38% women and 62% men) received
seasonal training as ToTs on improved agricultural technics and integrated pests management (IPM) practices for
maize, beans and soybeans cropped on treated hillsides. The project also continued mobilization and training for
compost making where 20,258 tons of compost were produced and used in planting 2,077 ha during season B of
2013. The project with support of Rwanda Agriculture Board (RAB) introduced plant clinic workshops whereby
farmers are trained to diagnose, report, and manage pests and diseases to maintain acceptable production
thresholds that do not affect quality and quantity of the produce. So far 226 extension lead farmers (47% women
and 53% men) from all project sites were trained in these workshops.
12. In preparation of intensive horticulture development in irrigated areas, the project has mobilized
different horticulture stakeholders, with the aim of promoting private sector involvement. The project conducted
different workshops and meetings in order to present business opportunities available to the private sector. The
contract farming concept was encouraged in order to guarantee market linkage for horticulture produce. Two
prospective investors are willing to sign tripartite MoUs with the project and farmers by August 2013. The
project continued commercial trials as part of the FFS to develop and increase knowledge for commercial
horticulture. A Study tour of 167 extension lead farmers and change agents from the command area was
conducted where farmers learnt more on quality seed selection, multiplication, and commercial field set up of
some crops like passion fruit, tree tomato, pineapple, and bananas.
13. Key implementation challenges, in last six months, were related to drastic climate changes whereby
severe drought and too much rain have alternatively affected crop productivity in some sites in season B-2013.
The project therefore needs to work more closely with RAB research to find drought resistant varieties.
14. The mission recommends that the SPIU strengthens collaboration with RAB and its different
branches: (i) RAB research to obtain improved varieties and soil testing for fertilizer and lime recommendation;
and (ii) RAB extension for closer collaboration on agronomic extension and for sustainability of project impacts.
The mission also recommends hiring a specialized horticulture specialist with good horticulture
commercialization experience.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
4
Nutrition
15. Two nutrition related indicators were included during the mid-term review. The objective is to
improve dietary intake of nutritional food as well as the nutritional practices among the project beneficiaries.
The two indicators to measure the nutritional outcomes are: (i) % of households with acceptable food
consumption and (ii) number of kitchen gardens constructed. The project has made impressive progress in
launching nutritional activities. During the last six months, three main activities have been carried out: (i)
Nutrition awareness and behavioral change training: in collaboration with the Ministry of Health, the project has
launched a nutrition awareness campaign among the communities, and trained 678 lead farmers (out of which
40% were women) in nutrition and behavior change as of June 2013. These awareness training have been
conducted in six sites to educate the communities on how to improve diet and thus reduce or prevent
malnutrition; (ii) Promotion of Kitchen gardens - the project has promoted kitchen gardens through
demonstration plots and trained communities in construction and management of the kitchen gardens which are
aiming at improving access to nutrition-rich vegetables. In the process, the communities are learning about
production techniques of various vegetables; and (iii) Crop fortification – the project tested bean fortification
with iron and zinc initially on one site in collaboration with the Harvest Plus. Production of fortified beans has
now been scaled up in five LWH sites (all sites where beans are being produced). During the last season, a total
of 1,786 ha of fortified beans were planted, benefiting about 5,866 households. Going forward, the mission
recommends to: (a) use the SHG platform for nutritional awareness among all members; (b) select the poorest
households (especially women headed households) for demonstration of kitchen gardens; and (c) explore
opportunities for testing 1 or 2 community-led nutritional centers hosted in the cooperative premises for pregnant
women and children under two years as well as for increasing overall nutritional awareness and practices among
all HHs within the cooperative area.
A3: Marketing and Rural Finance
Marketing
16. LWH finances investments in marketing infrastructure and building the capacity necessary to address
the challenges surrounding successful horticultural development which are the following: (i) fostering linkages
among entrepreneurs and smallholder organizations; (ii) providing supplementary intensive quality technical
assistance and external certification; and (iii) building post-harvest infrastructure to ensure proper handling of
produce and exploitation of processing potential.
17. Given that LWH has not yet finalized irrigation works, agribusiness activities have focused on
hillsides interventions in rain-fed areas (maize, beans, potatoes, wheat, etc.). In the six rain-fed areas, 5
cooperatives have been formed and 3 are at emerging stage. During the last cropping season 2013A, the coops
and site committees marketed (sold) 2,476 tons equivalent to 77% of produced crops representing 481,056,750
rwf (USD 801,761) gross income. The cooperatives have been successful in fulfilling their economic roles.
18. The mission congratulates the SPIU for the capacity building programmes that associated training and
coaching activities in collaboration with the Post-Harvest Task Force (MINAGRI) for all post-harvest
improvement activities and through the establishment of MoUs with Business Development Centers in the
concerned districts (see appendice 2). Past infrastructure investments were built without involving
beneficiaries/coops. Based on recommendations of MINAGRI Post-Harvest, Handling and Storage Task Force
(see appendice 3) to improve quality (proper drying process, etc.) and increase quantities (half bulk storage) of
marketed agricultural commodities, coops are now involved in the site selection and construction of
infrastructure for their benefit.
19. In the two command areas under development and in two planned ones, production is/will focus on
market oriented horticulture. The mission commends the SPIU for a: (i) the launching of market stakeholders
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
5
network (MSNs) in key areas linking command areas to the urban markets; (ii) contacts established with Rwanda
horticulture inter-professional organization and NAEB; and (iii) linkages with vegetables exporters from the
private sector. The mission recommends that the SPIU continue to accompany MSNs to explore the interest of
developing agri-business centers for horticultural commodities accessible to stakeholders (emerging producers’
cooperatives, off-takers, processors, exporters, etc.).
20. The mission assessed SPIU performances for marketing and agri-business as satisfactory.
Rural Finance
21. The mission notes that significant progress has been made since the mid-term review to implement the
recommendations related to new product development, and capacity building for both participating financial
institutions (PFIs) and farmers through SHGs. Furthermore, the mission appreciates: (i) the adoption of new
products by two new PFIs: Izere Sacco in Gatsibo 8 and Kabare Sacco in Kayonza 4; (ii) the inception of product
development and design study launched by LWH project; and (iii) the pilot of input saving product in close
collaboration with DIME in two LWH sites. In these sites, the project has started piloting new saving products
with the objective of helping farmers to plan and save for agricultural inputs for Seasons 2014A and B. Based on
the progress made, the mission rated the project performance of the Rural finance subcomponent as satisfactory.
22. With respect to the products development: (i) the process to introduce and expand index-based
weather insurance to LWH beneficiaries is on track. The project is working with AFR, Syngenta, and Tubura to
deliver this product to famers in Season 2014B; and (ii) the study for the design and/or refining of 6 financial
products has begun and is on track in accordance with the work plan agreed upon.
23. The capacity development activities resulted in: (i) 86 lead farmers for saving and credit in phase 1A
sites SHGs acquired planning and budgeting skills which enabled them to comply with the financial institutions
requirements to access financial services; (ii) as a result of PFI training on mobilization and saving, savings by
project beneficiaries increased by 59 percent from 10.3 million Rwf in December 2012 to 26.6 million in June
2013. The mission supports the capacity development initiatives and encourages the project to pursue the
partnership with RCA and AMIR to improve the PFI internal control system, loan management and financial
analysis; (iii) training of Saccos on agriculture lending and farmers on loan application process facilitated the
access of 1,022 farmers in different sites to loans amounting 88,318,105 million Rwf. The management of these
loans is facilitated by the tools and knowledge acquired by the loan officers during the training sessions and post-
training coaching organised in partnership with the RCA.
A4: Institutional Strengthening and Capacity Building of MINAGRI and its Agencies
24. Specific objectives of sub-component A4 are to: (i) improve long-term capacity for hillside
intensification and sustainable land management including management of environmental impacts of irrigated
agriculture; (ii) build capacity among MINAGRI staff for community mobilization, participation, and integrated
watershed management approaches; and (iii) strengthen extension and technical backstopping capacity of
government staff at all levels, including filling the identified human resource gaps by financing higher technical
qualifications of appropriate MINAGRI staff, build capacity for phytosanitary implementation and establishing a
GIS based dynamic information framework (DIF) as a decision support system responsive to climate and
proposed water, land and crop uses.
25. Continuing Education for MINAGRI staff to fill critical skills gap. Fifteen candidates from MINAGRI
are proposed for a master degree scholarship program in India for the next academic year.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
6
26. GIS-based dynamic information framework (GIS DIF). The GIS based DIF was established to be a
decision support tool to other sub component technicians in particular and the Ministry at large. Various
activities have been undertaken to support other subcomponents:
Land husbandry: mapping quantitative progress of land husbandry works as a basis for quantifying
completed works and contract payments, mapping 5 new sites to be developed by RSSP and LWH,
physical site guidance of land husbandry works;
Mapping of two sites to resettle affected people (land properties, silt trap zones needing
expropriation);
Water Users associations: mapping of 7 marshlands with list of land users for WUAs to monitor the
use of marshland and calculate water fees;
Hillside irrigation: mapping of terraces to estimate inputs needed and expected productions;
Rural finance: meteorological and spatial information for agro-insurance in every pilot site;
Irrigation: physical delineation guidance of command areas and water reservoir for phase IB and
RSSP3 sites.
27. GIS-DIF also supported other MINAGRI’s agencies and projects such as SPATIII, Rwanda Feeder
Road Development project (RFRDP). The mission congratulates the SPIU for providing client oriented services
to address identified needs with useful decision making tools.
28. The mission recommends that the SPIU pro-actively participate in the preparation of the up-coming
international conference ICT4Ag co-hosted by the Technical Centre for Agricultural and Rural Cooperation
(CTA) and the Rwandan Ministry of Agriculture and Animal Resources (MINAGRI) in Kigali, Rwanda 4-8
November 2013 and use this venue as a unique opportunity to share GIS-DIF learning with an international
audience. The mission also agrees with the proposed GIS training in Hyderabad, India for two persons one in
charge of DIF in the SPIU and the other from MINAGRI GIS unit. The Mission assessed SPIU performances for
institutional development as highly satisfactory.
Component B: Infrastructure for Hillside Intensification
Sub-Component B 1: Land Husbandry Infrastructure
29. The objective of the subcomponent is to improve hillside agricultural management through protection
against soil erosion and enhancing sustained crop productivity. As of June, 2013, a total of 7,906 ha (end of
project target of 12,940 ha) of land had been protected against erosion using various types of land husbandry
practices (terraces, soil bunds, nutrient management, grass strips, and tree planting for details).The sub-
component is rated satisfactory. Overall, this represents a 61 percent level of achievement for the project and a
net increase in area protected against erosion of 2,654 ha since the last mission in January 2013. Yields of
maize, beans and Irish potato in treated areas are 30 percent, 167 percent and 219, respectively above their
national average. Sediment yield (t/ha/yr) in four sites for which complete datasets are available reduced by an
average of 66 percent relative to yield at the time when the land husbandry works were being constructed
reflecting the effectiveness of the land husbandry practices in reducing soil erosion on the hillsides.
30. The mission congratulates the team for the accelerated pace in implementation of the land husbandry
works and concurs with the team’s projection in the AWPB to treat an additional 3,700 ha over the current
financial year (July 13 to June 2014). The mission however notes the delayed progress of land husbandry works
in Karongi 13 (and the effect that this could have on installation of irrigation infrastructure) and concurs with the
team’s proposal to mobilize labor from the neighboring sites to expedite progress. The mission commends the
team’s efforts to closely monitor and manage the escalating land husbandry implementation costs as per the last
mission’s recommendation and recognizes the 12 percent reduction in average unit costs (i.e. from US$ 3,176 at
MTR to US$ 2,800) which was achieved without compromising the quality of works together with the plan to
further reduce the costs to US$ 2,140 as per AWPB.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
7
Sub-Component B2 Water Harvesting Infrastructure and B3 Irrigation Infrastructure
31. The objective of components B2 and B3 is to develop hillside irrigation for the production of high-
value horticultural crops with the strongest marketing potential. Infrastructure investments include dams and
gravity fed irrigation systems with an end-of-project target of 1,868 ha command area. Works are ongoing at one
dam site and three command areas totaling 694 ha. Works for two additional dams and command area of 732 ha
will be tendered in August 2013. Based on available information, Muyanza site (500 ha) was confirmed during
this mission and will be constructed in 2014-2015. The project is preparing to scale-up by carrying out feasibility
and design studies for an additional 6,500 ha new command area, which would be funded through additional
financing and/or a follow-on project. Collection of important data (rainfall, runoff, sediment yield) is ongoing at
ten sites, i.e. water user associations have been established and trained.
32. Dam construction and irrigation development works at Nyanza-23 (471 ha) were launched in
November 2012 and completion is expected in December 2013. Works progress to date is 25%. Grouting and
embankment filling commenced in the second half of July. The mission estimates that in order to meet the
completion date: (i) provisions should be made to raise the embankment at a rate of 1000 m3 per day while
observing pore water pressure; (ii) the pace of land husbandry works in the command area should be increased
substantially; and (iii) the second consignment of pipes and the entire consignment of valves and fittings should
be ordered and shipped soonest. At Karongi-12 (128 ha) and Karongi-13 (95 ha) the contractor was mobilized in
January 2013. However, the mission notes that actual construction commenced in April 2013 because of a
procurement delay for the supervision firm. Works progress to date is approximately 25% and some design
changes had to be made due to special conditions encountered during construction. If the observed shortage of
manpower for command area terracing and the delay in shipment of pipes and fittings can be overcome,
completion of both schemes is expected for December 2013. At Gatsibo-8 (45 ha), the groundwater study has
been completed with designs and tender documents for stream diversion / groundwater harvesting and a fully
piped command area currently being finalized. Construction is expected to take place from December 2013 to
August 2014.
33. Designs and tender documents are being finalized for Rwamagana-34 (267 ha), Rwamagana-35 (162
ha) and Kayonza-4 (420 ha). The mission confirms the project's proposal not to pursue dam based water storage
at Rwamagana-35 for lack of financial viability. This is also in line with the adaptive LWH approach formalized
during MTR. The project should decide on whether it wishes to pursue a shallow-groundwater irrigation option
at this site. Tendering for civil works for Rwa-34 and Kay-4 should commence in August with works expected
for the November 2013 – October 2014 period.
34. A pre-feasibility, feasibility and design study (2 lots) for new sites totaling 6500 ha has commenced in
May 2013 and is now at inception report stage. Out of these, 500 ha at Muyanza will be brought to detail design
by January 2014 and implemented in this phase of the program. Construction is scheduled for May 2014 – June
2015. Approximately 500 ha will be implemented with the proposed additional financing, with designs and
tender documents ready by May 2014. By February 2015, 5500 ha command area will be ready for
implementation under a follow-on project in support of the hillside irrigation targets set out in the EDPRS2.
35. Based on the overall progress since project effectiveness, sub-components B2 and B3 are rated as
moderately satisfactory. It is anticipated that works will accelerate as the command area currently under
construction has been developed for irrigation. The SPIU should closely monitor on the works implementation
schedule to meet year 4 targets of 850 ha command area developed. With little over two years of project lifetime
remaining, it is important to further accelerate implementation of these two sub-components as agreed in the
updated work plan for the remainder of the project (see Technical Annex 9). Project management should closely
monitor progress against this work plan to avoid any slippage.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
8
Component C: Implementation through the Ministerial SWAp Structure
36. Project Management and coordination is rated satisfactory
Project Management and Staffing
37. At the National Level the SPIU structure comprises both Management and Technical teams numbering
57staff (50 are in place, 3 under recruitment currently and 4 postings need to be filled – the Head of the Irrigation
and Land Husbandry Department, the senior land husbandry specialists and the senior agronomist positions need
to be urgently filled with strong candidates). At the District Level, teams comprise both the District Project
Coordinator and various subject matter specialists (SMS). The average size of a District team is about 6 people
but can vary depending on the number of sites under their direct supervision. To-date 47 staff are in place in 9
Districts and 23 are under recruitment. Depending on the need to create new District teams this number could
increase. The project also managers a number of support staff (drivers, cleaners, messengers) at the central level
and at the district level when required. A number of interns and temporary staff are also managed from the SPIU
office and their number varies with time.
38. Annual Work Plan and Budget (AWPB) for FY14 covering July 2013-June 2014. During the mission
the AWPB was reviewed and modifications suggested. The SPIU had submitted an FY14 AWPB before the
mission started. Mission members reviewed the plans and budget and the final draft will be submitted to IDA for
no object within a week of mission closing.
39. Financial Management. The mission reviewed the status and continuing adequacy of the projects’
financial management (FM) arrangements, including compliance with the legal covenants related to financial
management. The review noted that LWH/RSSP SPIU has an adequate number of finance personnel to manage
both LWH and RSSP project funds. The accounting system works satisfactorily in recording and processing
financial transactions and in preparing regular and reliable financial reports. Functional responsibilities are
adequately segregated and adequate internal control procedures are in place. The mission also made the
following observations in regard to the financial management function of the SPIU;
Overall the disbursement rates for both LWH and RSSP3 have improved compared to the last
implementation support mission and all designated accounts are active.
LWH has 2 trust funds i.e. TF 10953 and TF 11435 with a total allocation of USD 12,990,000. There has
however been no disbursement to date, and both trust funds are scheduled to close on May 14, 2014. We
recommend that urgent action be taken to start utilizing these funds.
Internal audit report for LWH raised a couple of issues that may require follow up.
Following this supervision mission, the overall financial management ISR rating for the project is classified as
satisfactory and the FM risk rating is low.
40. Procurement: the mission assessed the performance of procurement function as satisfactory in
relation to execution of the approved procurement plan of the FY 2012/2013 (July 2012 – June 2013) as well as
cumulative since the project effectiveness. To date, the project has awarded 221 contracts out of 253 planned.
This is equivalent to 87.4% completion compared to 85.98% in January 2013; an increase of 1.42%. Under FY
2012/2013, the project managed to complete the bidding and selection process of 52 out of 70 contracts planned
(approximately 74.3%) in this period. This is equivalent to US$32.5 million in terms of commitments.
41. The project has yet to initiated the procurement process of 18 contracts (approximately 25.7%) broken
down as follows: Works – 3 contracts; Good – 7 contracts; and Consulting Services – 8 contracts. Unless the
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
9
project closing date is extended beyond the revised closing of December 31, 2015, procurement of the pending
works contracts need to be expedited as they are now on the critical path.
Safeguards
42. Overall safeguard compliance is found to be satisfactory. The mission reviewed the Progress Reports
for January – June 2013 and visited project sites at Nyanza-23, Karongi-12 and 13, and Rwamagana-34.
43. Social Safeguards. Income restoration and resettlement/compensation activities are ongoing and
development and implementation of Process Frameworks and RAPs are on schedule, following the availability
of the site designs. Income restoration for Phase 1A sites: Nyanza-23, Karongi 12 and 13 and Gatsibo-8 were
completed for all PAPs at an average rate of 375% of cost of assets. Based on the Implementation Progress
Report for Phase 1B sites, the Project conducted awareness community meetings to inform the communities
about the project. Income restoration process was also completed for Rwamagana-34, 35 and Kayonza-4 sites for
99% of the farmers who have recovered their lost income. The remaining 1% of PAPs, who did not cover their
income loss, are those involved in other activities such as commerce, teaching or government jobs. These PAPs
have indicated their satisfaction with an opportunity to benefit from land husbandry works on their land. Overall
at Phase 1B sites, a total of Rwf 327,046,212 was paid to 2,136 PAPs (on average Rwf153,111 per person), with
an average compensation rate of 457% of the value of estimated income loss. The compensation includes the loss
of crops and calculated loss of income for the duration of construction of the terraces.
44. Resettlement activities at Phase 1B sites were completed in February 2013 with compensation of 235
PAPs in Nyanza and 15 for Karongi, who received an equivalent of Rwf 180,103,512 in land, financial
compensation for crops and property, and additional assistance in the form of seeds and fertilizer. The timing for
preparation of RAPs and Process Frameworks for Phase 2 sites will be guided by completion of site designs.
45. The mission commends the team for maintaining high quality data tracking and detailed progress
reports on implementation of Process Frameworks. The mission also appreciates the innovations in data
collection and monitoring through the use of maps and GIS.
46. Environmental Safeguards. Based on the review of the progress reports and project site visits, the
mission confirmed that environmental management of the project works implemented to-date is in compliance
with the Bank safeguards policies. For Nyanza-23, Karongi-12 and 13, the updated ESIAs have been disclosed
locally and in World Bank InfoShop on January 25, 2013. The updates reflect the latest design changes. Gatsibo-
8, ground water investigations report is expected to be delivered to the LWH team by July 31, 2013. The report
informs the economic and technical feasibility of irrigation at the site. This study will also guide the update of
the ESIA for Gatsibo-8. For Phase 1-B (Rwamagana-34, 35 and Kayonza-4), the EIA studies were commenced
in April 2013. The EIA draft reports for Rwamagana 35 and Kayonza-4 were submitted to the Project for review
and comments. Rwamagana 34 EIA will be informed by the recently completed feasibility study. The final EIA
reports for three sites are expected to be completed by August 31, 2013. The draft study on water quality and
minimum ecological flow for Phase 1-B sites is under development by the National University of Rwanda
(NUR). Final report, incorporating the Project review comments, is expected to be submitted to the Project by
August 15, 2013.
47. Dam Safety. Project compliance with the provisions of OP 4.37 is rated satisfactory. Coinciding
with the mission, the PoE inspected the Nyanza-23 dam construction site. The Panel report and recommendation
is expected in the second half of July. In April 2013, MINAGRI proposed modifications to the dam
instrumentation at Nyanza-23. Prior to Bank confirmation, the design and the supervision consultant team, as
well as the chairman of the PoE had agreed to these modifications. These changes should be reflected in an
update of the Dam Instrumentation Plan, which is contained as a dedicated section in the dams operation and
maintenance plan. The Emergency Preparedness Plan (EPP) for Nyanza-23 requires an update, followed by a
training of local representatives on the content of the EPP. The Mission recommends the safeguards team to
work together with engineers to define an appropriate sensitization program to notify relevant stakeholders of the
necessary safety information. The mission also recommends that the PoE review the updated O&M plan as well
as the EPP. The Panel’s next visit should take place during initial reservoir filling, ideally during spillway
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
10
testing. The feasibility studies for the Kayonza-4, Rwamagana-34 and Rwamagana-35 have been completed. At
present, none of the dams are falling into the large dam category. Some of the upcoming Phase-2 sites can be
expected to contain large dams. Therefore, the mission recommends retaining the Panel of Experts for the
foreseeable future.
48. Following the recommendation of the last Aide Memoire, the Mission recommends that GoR make
institutional arrangements for the establishment and operation of a dam monitoring unit, whose mandate would
be, beyond the lifetime of individual projects, expert supervision and inspection of the increasing number of
dams in the country, including analysis of cumulative environmental impacts of the dams nationwide. The
Mission encourages MINAGRI to analyze the options to increase capacity for dam safety monitoring of GoR.
49. Implementation of Project’s M&E Functions. The mission found the M&E arrangement of the
SPIU to be satisfactory with a core M&E team at the national level and in all Districts where both LWH and
RSSP activities are carried out. The team is implementing a unified M&E system for both Projects which
integrate farmers at the different levels of their organizations structures, from SHGs to the cooperative level. In
addition, the M&E team has successfully updated both LWH and RSSP Results Frameworks (see Annex 3).
50. During the last mission in January 2013, the mission recommended that the SPIU prepare a detailed
description including critical assumptions, methods of data collection, frequency of data collection, calculation
and analysis for each indicator in the Results Framework for RSSP and LWH Projects so that all those within the
project and others can refer to the description to understand what each indicator means, exactly how and what is
being measured. The detailed description for both LWH and RSSP Results Framework were reviewed during
the mission and agreed upon and can be found in Annex 7.
DIME
51. LWH and DIME tested a first round of rural finance innovations in Karongi starting in Season A
2013, and will test a second round of rural finance innovations in Rwamagana starting in Season A 2014. In
Karongi a pilot and rigorous test of 2 new rural financial products – targeted savings accounts & pre-
commitment savings accounts will be conducted. In Rwamagana, LWH & DIME are testing the introduction of 4
new pre-commitment products –fixed withdrawal penalty, health shock exemption, agricultural shock exemption
and no withdrawal penalty.
52. LWH is collaborating with DIME and TUBURA are testing three extension performance feedback
tools: scorecards; advocacy groups; and a free client hotline. Data is available from the first two rounds of
scorecards, fielded in November 2012 and March 2013. Farmers report high levels of satisfaction with fertilizer
delivery and all extension services. Nearly all farmers received the trainings on planting and urea application, but
less than half of the farmers received the trainings on any of the other topics, i.e. nurseries, disease identification,
and safe use of pesticide. The data from the logbooks and hotline is currently being collected, and analysis will
be presented along with the third round of scorecard data in September.
53. Project Communications. The mission reviewed the work of the communications team and found
that improvements in overall project communications is improving and that the recommendations made in the
January 2013 mission are being implemented. Additional agreements were reached to continue to refine the
communications function of the SPIU and particularly how the SPIU could both support and draw upon the
expertise of the communications team within CICA. Please see Annex 6 for specifics.
54. The proposed next joint implementation support mission for LWH & RSSP3 will take place from
March 24 to April 4, 2014.
55. The Bank and MINAGRI confirm their understanding and agreement to publicly disclose this Aide
Memoire. The disclosure of this Aide Memoire was discussed and agreed to with the Project and Ministry
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
11
counterparts led by Honorable Minister of MINAGRI, Mrs. Agnes Kalibata at the wrap-up meeting that took
place on July 26, 2013 in Kigali.
D. RECOMMENDATIONS AND PENDING ACTIONS/NEXT STEPS
Recommended Action Responsible Entity Deadline
1 complete grading of SHGs. Zones/Cooperatives and WUAs
(which have completed one year)
LWH team 30 December
2013
2 Hiring a specialized horticulture technical assistance (TA) with
good horticulture commercialization experience.
LWH team 30 December
2013
3 Launch civil works at Rwamagana-34, Kayonza-4 and Gatsibo-8 LWH team 30 December
2013
4 Complete construction of Nyanza-23, Karongi-12 and Karongi-13
irrigation systems
LWH team 31 December
2013
5 Update Nyanza-23 dam operation and maintenance (O&M) plan
and emergency preparedness (EPP) plan and conduct training of
local representatives on EPP
LWH team 31 December
2013
6 Finalize EIA reports for Phase 1B sites. LWH team/ Consultant Upon
availability of
the site design
studies.
7 Finalize the preparation and implementation of RAPs for phase 1B
sites.
LWH team Upon
availability of
the site design
and other
supporting
studies.
8 Package the contracts for procurement of limestone based on site
location and capacity of suppliers.
LWH team On going
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
12
Annex 1: List of People Met
S/N Name Position Organisation contact
1 Dr Agnes Kalibata Minister MINAGRI
2 Ernest Ruzindaza Permanent
Secretary
MINAGRI
3 Jolly Dusabe LWH/RSSP
coordinator
MINAGRI
4 SPIU staff MINAGRI
5 KOTUDUABURWA
trader cooperative
Steering
commitee
Karenge centre 0788307930
6 Rebecca RUZIBUKA Manager Africa Business Consultant
(BDC)
7 Alfred Willem ARTELIA
SOMEAH
Team Leader, Construction
Supervision Firm, Nyanza-23
site
0787552014
8 Toky Ratsima ARTELIA
SOMEAH
Irrigation Expert, Construction
Supervision Firm, Nyanza-23
site
250 786991261
9 Fernamet Mwrenzi JV
RCE&ECAM
Technical Director,
Contractor- Karongi-12 and
Karongi-13 site
+250 788358911
10 Augustin Butera JV
RCE&ECAM
Assistant contract manager,
Contractor- K-12 and K-13 site
+250 788401249
11 Ameur Bahri Comet
International /
Tunisia
Resident engineer,
Construction Supervision
Firm, K-12 and K-13
0784576505
12 Mohamed Gossa Comet
International /
Tunisia
Resident engineer,
Construction Supervision
Firm, K-12 and K-13
0787844226
13 Ashok Raut SMEC
International
Team leader, Phase 1B sites
feasibility and construction
supervision firm
0787831147
14 Kiprotich Tirgeito SMEC
International
Dam Engineer, Phase 1B sites
feasibility and construction
supervision firm
0787 450600
15 Janet Kanyambo BDF Fund Manager
16 Agathe
Nyinawinkindi
BNR Principal Inspector
17 Jean-Damascène
Serugero
BNR Inspector
18 Gérard Nsabimana BNR Inspector
19 Francesca
Mukayirangwa
RCA Head of Capacity development
Unit
20 Judith Aguga Acon AFR Technical Director
21 Frank Bakx
Triodos
Facet/Rabobank Technical Advisor
22 Jean Tibouto WOCCU Project Manager
23 Alexy Maniragaba SACCO
Umugisha
Manger
24 Gad Niyigada SACCO Manager
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
13
Ubumwe Mwa
Nyakariro
25 Marie Grace
MUNEZERO
Business
development
advisor
Business Development Centre,
Huye
26 Rita MUKABALISA Secretary Electromax Milling Company,
Huye
27 Alexandre
MUKUNDABANTU
Chairperson KOAIRWA rice cooperative,
Rwasave
28 Damascène
NIYIRINGIYIMANA
Chairperson WUA, Rwasave
29 LeoPaul
NTIBARASHYIRA-
AMAKYENJA
Chairperson KOAKIRWA Hillside,
Rwasave cooperative
30 Jean Claude
BIHIBINDI
Chairperson Rice Cooperative
IDIREMUHINZI, Agasasa
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
14
Annex 2: Progress on MTR(January 2013) recommendations
Recommended Action Responsible Entity Deadline Progress july 2013
Adopt a consolidated, harmonized
and agreed capacity building strategy
Project Capacity
Building Team
February 21st,
2013
Implemented
Recruit Service Providers and ensure
that their work plans reflect the
agreed capacity building strategy
Project Capacity
Building Team
March 30th, 2013 implemented
Based on results of pre-feasibility
study for Phase-2 sites, select
remaining irrigation sites needed to
achieve project target
LWH team May 31st, 2013 Prefeasibility studies
launched and sites to be
selected Mid- July 2013
after the inception report.
Support to PFIs MIS to be
implemented in close partnership
with RCA.
Project team May 31st ,2013 Under discussion between
RCA and BNR
Prepare ToRs for O&M services at
Nyanza-23 and Karongi-12 and
Karongi-13 irrigation schemes.
LWH team with
assistance of
irrigation task force
May 31st, 2013 Implemented
Provide training of WUAs on their
principal functions at all phase 1A
sites, including O&M fees based on a
realistic costing of O&M plans
LWH team June 30th, 2013 Implemented, while O&M
await the completion of
infrastructures
Start formation of WUA in Phase 1B
sites.
Project Capacity
Building Team
July 31st, 2013 Implemented
Complete legal registration of
existing three WUAs
Project Capacity
Building Team
July 31st, 2013 Implemented
Set up and build capacity of district
irrigation committees
Project Capacity
Building Team
July 31st, 2013 Implemented
Work with RAB and NAEB to
strengthen IPM trainings and
establish on plant clinics
Project agronomist July 31st, 2013 Implemented.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
15
Annex3 : Updated LWH Results Framework (July 2013)
1 New baseline following LWH site specific survey, the PAD baseline of US$ 1000 was based on a national average. 2 New baseline following LWH site specific survey, the 2009 PAD baseline of US$1000 was based on national average for irrigated perimeters.
Indicators
Core
Unit of
Measure
Baseline
(2009)
Cumulative Target Values** Comments
Dec
2010
Dec
2011
Dec
2012
Progress
July
2013
Dec
2013 Dec 2014
Dec
2015
Indicator One:
Productivity of target
irrigated command area
($/ha)
Amt
US$ 492
1 - -
N/A
1400 2000 2700
No irrigation yet.
Indicator Two:
Productivity of targeted
non-irrigated hillside
($/ha)
Amt
US$ 469
2 - 1900 2100
2,357
2300 2350 2400
Indicator Three: Share
of commercialized
products from target
areas (%)
% 35 45 50 60
74 65 70 70
Indicator Four: Direct
project beneficiaries-
individuals (of which
female)
# 0 5000
(2250)
18000
(8100)
21000
(9450)
92,381
( 45,417)
94000
(46,000)
97,000
(52,500)
100,000
(55,000)
Intermediate Result
indicator one : Number
of cooperatives which
have increased their net
revenues by 50% relative
to the baseline
% 0 0 3 4 3 6 8 10
Coops that have
increased their net
revenues by 50%
compared to the
baseline 1st season
after one year
existence
Intermediate Result
indicator Two: Cost
recovery ratio for
operation and
% 0 - - -
N/A
40 60 90
No irrigation yet.
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
16
maintenance of WUA in
project areas
Intermediate Result
indicator Three:
Proportion of beneficiary
farmers in project
affected areas using
improved farm methods
(disaggregated by
gender)
% Male=30
Female=25
M=50
F=50
M=60
F=60
M=70
F=70
M=72.66
F=70.32 M=75
F=75
M=80
F=80
M=90
F=90
Intermediate Result
indicator Four:
Percentage of adult
project beneficiaries in
the project areas
which have access to the
services of formal
financial
institutions(disaggregated
by gender)
% Male=22
Female=18
M=50
F=50
M=70
F=65
M=90
F=80
M=91.9
F=82.5
M=92
F=85
M=94
F=87
M=95
F=90
Intermediate Result
indicator Five: # of
project participating
financial institutions
(PFIs) offering new
products
# 0 - 3 6 8 12 18 24
Intermediate Result
indicator Six: Percentage
of Cooperatives and their
Self Help Groups (SHGs)
ranked and graded high
(A & B)
%
%
-
-
-
-
-
-
-
-
N/A
N/A
60
60
70
70
80
80
The guidelines are
being developed
during the mission,
after which grading
will be
implemented. The
update on grading
to be reported in
December 2013
Intermediate Result % 79% - - 82% 79% 83% 84% 85%
LWH Implementation Support Mission July 2013—Draft AIDE MEMOIRE
17
indicator Seven:
Percentage of households
with acceptable food
consumption
Number of kitchen
gardens constructed
#
-
-
-
3,975
5,910
6,000
9,500
15,000
Intermediate Result
indicator One: Proportion
of land protected against
soil erosion in project
areas (ongoing
assessment each year)
% 26 43 60 75 61.1 80 85 90 Phase IA &B sites
WC ,CAC and CA
Intermediate Result
indicator Two: Area
developed for Irrigation
in project (ha) # ha 0 - -
NA
350 850 1,868
Works in progress
for an area of 694
Ha in three sites(K-
12,K-13 and Ny-
23).
Intermediate Result
indicator Four: Reduced
sediment yield (volume
or weight per unit area of
catchment (T/ha/yr) in
the project areas
% - - - 65.7 10 30 50
Sediment yield in
phase IA sites End
2012 : K-12(29), K-
13 (23); Ny-23(15)
and
G-8(7.12). The
calculation is based
on the FY2012 end
values compared to
2011 values taken
as baseline: K-
12(69), K-13(57),
Ny-23(48) and G-
8(53).
18
Annex 4: Procurement
Rwanda
Implementation Support for Land Husbandry, Water Harvesting and Hillside IrrigationProject (LWH)
July 17, 2013
Procurement Inputs
Introduction
1. The World Bank procurement team consisting of Pascal Tegwa and Antoinette Kamanzi met with the
project procurement team to discuss the progress of procurement management as a follow up on the
recommendations made during the January 2013 mission and last Post Procurement Review (PPR) exercise. The
procurement unit is well staffed. Currently, it has 7 procurement experts including the head of procurement unit.
A list of procurement team is attached as Annex A. The report summarizes the achievement to date, challenges,
the status of implementation of previous recommendations and the agreed action plan.
Achievement to date
2. The mission assessed the performance of procurement function as satisfactory in relation to
execution of the approved procurement plan of the FY 2012/2013 (July 2012 – June 2013) as well as
cumulative since the project effectiveness. To date, the project has awarded 221 contracts out of 253 planned.
This is equivalent to 87.4% completion compared to 85.98% in January 2013; an increase of 1.42%. Under FY
2012/2013, the project managed to complete the bidding and selection process of 52 out of 70 contracts planned
(approximately 74.3%) in this period. This is equivalent to US$32.5 million in terms of commitments.
3. The project has not initiated the procurement process of 18 contracts (approximately 25.7%) broken
down as follows: Works – 3 contracts; Good – 7 contracts; and Consulting Services – 8 contracts. Unless the
project closing date is extended beyond the revised closing of December 31, 2015, procurement of the pending
works contracts need to be expedited as they are now on the critical path.
4. The mission was informed that the project has already received the final design reports for the 3 works
contracts. They will advertise all 3 contracts by the first week of August 2013. The three contracts consist of
construction of Hillside dams at Rwamagana 34 and 35 and Kayonza 4. The average cost estimate is US$12
million. However, there is a risk of not receiving responsive bids because of low capacity of the local contractors
because construction of hillside dams is a new technology in Rwanda. Currently, the project is executing one
contract of the same technology that was awarded to the Chinese firm, China New Era International Engineering
Corporation (CNME). It is unlikely that these contracts will attract foreign bidders given the cost estimate of
about US$12 million. It was noted that even the previous bid did not attract many bidders.
4. Regarding procurement of goods, they are usually operating costs and are requested depending on the
levels of stock remaining, procurement unit is still awaiting requests from the user departments to enable them to
initiate the procurement process. The selection process of the remaining 8 contracts for consultancy services
include 1 contract for the development of extension materials and training modules; 2 contracts for horticulture
(likely to be cancelled); and 3 contracts for communication strategy, development of water points, translation and
the last one for supervision of small scale irrigation infrastructures in Gatsibo of which the design studies are not
yet completed. The project has advertised the expression of interests for communication strategy and translation
services.
Procurement Challenges
5. The procurement unit has been encountering various challenges, a few highlighted as follows:
(i) Considerable delays in completion of design studies for planned works. This has been attributed
by technical departments.
(ii) Too many contracts in pipeline to be processed at the same time. This has been attributed by the
fact that the procurement plan is always prepared to respond on activities of the Annual Work Plan and
Budget (AWPB) and seasonality due to type of activities, which depend on rain season.
(iii) At the time RSSP3 became effective, there were too much workload compared to capacity of the
procurement unit in terms of staff numbers at that time. By then, the procurement unit had only 3
procurement staff at the head office compared to the current number of 6.
19
(iv) Low technical and financial capacity of local contractors to absorb the planned contracts for
construction of dams and marshlands. Due to challenges related to national geographical setting of the
country, packaging of these contracts attract mainly local contractors, although, are normally processed
using International Competitive Bidding (ICB) procedures because of the set threshold. The mission
learnt that the supply side for these types of contracts is high - the Ministry of Agriculture also has the
same type of contracts financed by other donors and its own budget. There are few local contractors that
have experience, capacity and capability to execute these types of technologies. The mission strongly
recommended to the project management to conduct a quick assessment in order to establish the
actual local capacity to feed in future strategic procurement planning This assessment can be done
by an individual consultant and should cover the two different technologies, one for construction of
hillside dams (LWH Project) and second for construction of marshlands and dams (RSSP).
(v) Sometimes the project advertises contracts of the same nature at the same time for RSSP3 and
LWH projects. While bidders are not restricted to bid for contracts which belong to only one project, the
challenge has been to award the contract if the bidder has submitted the same qualification information.
It was recommended to make cross reference of the two bidding documents to inform the bidders that
bids for RSSP3 are being advertised at the same time with LWH bids and that bidders who wish to
submit bids for RSSP3 and LWH should provide proof of resources (financial, equipment and personnel)
to execute multiple contracts concurrently.
Status of implementation of previous recommendations
6. The following table shows status of implementation of major recommendations of the implementation
support mission conducted in January 2013. The table shows that the project has implemented all major previous
recommendations.
Recommendation Planned
date for
execution
Current Status
Design and implementation of the
contract management monitoring system
Immediately System is in place and it is working. In addition, the
Project recruited a Procurement Specialist with
Engineering background in charge of contract
management
Provide residual capacity of the technical
department in case the selection of
consultants is delayed.
April 2013 Procurement unit is now working closely with the
technical team. The project has recruited a
procurement staff with engineering background.
Revised Procurement Plan
7. The procurement team is still waiting for the project action plan and budget in order to revise the
procurement plan for FY13/14. It was agreed that the revised procurement plan will be submitted to the Bank
for review and approval before being implemented.
Agreed Actions
8. Following is a table of the actions agreed. This table includes also the actions that have not been
implemented as a result of the last implementation support mission conducted in July 2012.
Action Responsible Planned
Date
Status and Remarks
Design a strategy for rebidding of the
construction ofKilimbi marshland to attack
bidders this timebefore embarking on the
rebidding process.
Procurement
Unit and
Technical
Department
First week
of August
2013
Bidding document ready for
publication
Conduct a quick assessment to establish the
actual local capacity for construction of
dams and marshland to feed in future
strategic procurement planning.
Project
Coordinator,
Procurement
Unit and
Technical
Immediately
20
department
Revised procurement plan Procurement
unit
? Procurement team awaiting for the
project action plan and budget for
FY13-14
Package the contracts for procurement of
limestone based on site location and
capacity of suppliers.
Prepared by,
Pascal Tegwa and
Antoinette Kamanzi
July 18, 2013.
Appendix to Annex4
Procurement Team
1. Innocent Kamugisha - Head of Procurement Unit
2. NkakaTheogene - Procurement Specialist
3. Ngenganyi Maurice - Procurement Specialist
4. Shingiro Laurent - Procurement Specialist
5. Ruzibiza Stephen - Procurement Specialist
6. Agnes Tuyishimire - Procurement Officer (on annual leave)
7. Jeanne d’Arc Umunezero - Procurement Assistant (based in Southern Province)
21
Annex 5: Financial Management
Project Name: Land Husbandry, Water Harvesting and Hillside Irrigation (LWH)
& Third Rural Sector Support Program (RSSP3)
Project ID: P114931 / P124785 / P126440
IDA Credit/Grant No.: IDA Credit IDA-46740, TF-99108, IDA 50640
Implementing Agency: Ministry of Agriculture and Animal Resources:
SPIU for LWH and RSSP
Effectiveness Date: IDA-46740 02 June 2010; TF-99108 14 May 2012;
IDA 50640 June 20, 2012
Closing Date: IDA-46740 31 December 2015; TF-99108 31 December 2015;
IDA 50640 October 30, 2017
Credit/Grant Amount: IDA-46740 = USD32.89 M; TF-99108= USD 50.0M; IDA 50640=80M
Plus estimated contributions from USAID $14m and CIDA $7.8 CAD
Remaining Period to Closing IDA 46740 2.5 Years; TF 099108 2.5 Years;
IDA 50640 4.8 Years
Disbursed Amount
IDA-46740 = USD18.30M; TF-99108= USD 25.72 M;
IDA50640=USD 21.03M
Cancelled Amount -
Previous Supervision July 2012 – January 2013
Period Covered by Review: February 2013 – July 2013
Previous FM ISR Rating: Satisfactory Current FM ISR Rating: Satisfactory
Previous Residual FM Risk
Rating: Low
Current Residual FM Risk
Rating: Low
EXECUTIVE SUMMARY
The mission reviewed the status and continuing adequacy of the projects’ financial management (FM)
arrangements, including compliance with the legal covenants related to financial management. The review noted
that LWH/RSSP SPIU has an adequate number of finance personnel to manage both LWH and RSSP project
funds. The accounting system works satisfactorily in recording and processing financial transactions and in
preparing regular and reliable financial reports. Functional responsibilities are adequately segregated and
adequate internal control procedures are in place. The mission also made the following observations in regard to
the financial management function of the SPIU;
1. The final audit report for RSSP 2 was submitted to the bank on March 27 2013. The audit opinion
rendered by the auditor was unqualified (clean) opinion. However a number of weaknesses wear noted in
the management letter. Although these did not lead to a qualification however they’re issues that still
warrant follow up and implementation. An audit action plan was prepared and implementation of actions
in progress although the action plan was not timely shared with IDA. As recommendation going forward
the action plan should be time bound, the one shared does not include timeframes when
recommendations such as those in progress will be finalized.
2. Overall the disbursement rates for both LWH and RSSP3 have improved compared to the last
implementation support mission and all designated accounts are active.
3. LWH has 2 trust funds i.e. TF 10953 and TF 11435 with a total allocation of USD 12,990,000. There has
however been no disbursement to date, and both trust funds are scheduled to close on May 14, 2014. We
recommend that urgent action be taken to start utilizing these funds.
4. Internal audit report for LWH raised a couple of issues that may require follow up.
22
ISR FM RATING
Following this supervision mission, the overall financial management ISR rating for the project is classified as.
The findings underlining such rating are provided in the FM ISR report.
FM RISK RATING
The overall financial management risk for the project is Low. The detailed risk ratings are provided in Appendix
1.
FM REVIEW: FINDINGS AND ACTION PLAN
Budgeting; the annual work plan and budget for FY 13/14 are under discussion and review by the technical
team, this process is part of this mission, the outcome of which will determine the inputs for the final budget to
be approved by the steering committee. The annual expenditure performance by IDA category for LWH is
38.05% and 19% for RSSP3
Accounting; the accounting system for the SPIU remains adequate, the information system Tompro adequately
records and produces financial reports sufficient for the project requirements. There is still a need to train the
accountants that have not been trained within the SPIU so that there is continuity should the need arise,
especially given the market trend of staff turnover.
Internal Controls.
The internal control system for the SPIU is adequate however there were weaknesses observed by the external
auditor during the audit of RSSP 2/3. Since the SPIU is one, we deem that these affect both projects. Some of the
weaknesses found during the RSSP 2 audit included the following weaknesses; Non-compliance with assets
management and stock management procedures, Weaknesses in IT internal controls, Physical verification;
irregularities were noted on works under phase II, 17% of the previous year audit recommendations were not
fully implemented, hence weaknesses not addressed
Internal audit; internal audit for the SPIU is active, produces reports, and time bound action plans and follows
up on audit recommendations. Most recent report is for LWH (July 2012 – March 2013), carried out to ascertain
whether all payments were properly authorized and sufficiently supported by relevant documents, assess the
adequacy of internal controls, to ensure the adherence to procedures and accounting policies, ascertain the
economy, efficiency and effectiveness on all payments made, whether tenders were awarded in transparency,
compliance to World Bank and RPPA procedures were followed in tendering process e.t.c. The audit report also
highlighted a number of weaknesses but one recurrent concern is the delay by districts to account for transfers.
Our recommendation overall is to strengthen the internal control system and follow up with the accountability
issue so that it does not reoccur.
Funds Flow:
RSSP3 has since project commencement disbursed 26.66% on IDA 50640. There is a marked improvement
in the disbursement compared to the 12.51% in January 2013.
23
RSSP3 – IDA50640
Category Category Description
Allocated Disbursed Undisbursed
Historical
Category
Disbursed
USD USD USD USD
Total 78,885,684.00 21,034,467.15 57,851,216.85
1
gds,wks,non
cs,cs,train,,oc,pt1cd 70,800,657.00 12,276,122.89 58,524,534.11 12,221,098.42
2
gds,wks,serv fin by subgrants
pt 1c 4,987,026.00 1,529,424.25 3,457,601.75 1,521,907.29
3 PPF REFINANCING 1,133,415.00 442,106.69 691,308.31 442,879.02
4 UNALLOCATED 1,964,586.00 0.00 1,964,586.00 0.00
DA-A Designated Account 0.00 7,492.01 -7,492.01
DA-B Designated Account 0.00 6,779,321.31 -6,779,321.31
LWH has since project commencement disbursed 56.60% on IDA 46740 and 51.45% on TF 99108
including initial advance. The project still has 2 years of implementation however there’s a need to scale up on
disbursement. On the other hand the project has 2 trust funds that is, TF 10953 and TF 11435 with a total
allocation of USD 12,990,000 with no disbursement to date. The project is in the process of obtaining signatory
approvals from both MINAGRI and MINECOFIN there is however an urgent need to speed up the process and
start using these funds since both trust funds will close on May 14, 2014. The new revised plan for disbursement
is as below and in accordance to this plan the project is below the forecasted disbursement targets.
LWH – IDA 46740
Category Category Description
Allocated Disbursed Undisbursed
Historical
Category
Disbursed
USD USD USD USD
Total 32,340,108.00 18,303,791.08 14,036,316.92
1 DISB - GOODS 3,022,440.00 2,589,508.04 432,931.96 2,632,204.79
2 DISB - CIVIL WORKS 13,147,614.00 9,740,952.16 3,406,661.84 9,842,758.58
3 DISB - CONSULTING 8,311,710.00 2,928,019.75 5,383,690.25 2,981,020.54
4 DISB - TRAINING 3,929,172.00 258,431.16 3,670,740.84 263,468.96
5 PPF REFINANCING 211,570.80 333,999.58 -122,428.78 323,976.63
6 UNALLOCATED 3,113,113.20 0.00 3,113,113.20 0.00
7 DISB - OPERATING COSTS 604,488.00 103,441.74 501,046.26 104,158.35
DA-A Designated Account 0.00 2,335,229.48 -2,335,229.48
DA-Q Designated Account 0.00 14,209.17 -14,209.17
24
LWH – TF 99108
Category Category Description
Allocated Disbursed Undisbursed
Funds
Available
Historical
Category
Disbursed
USD USD USD USD USD
Total 50,000,000.00 25,723,716.04 24,276,283.96 24,276,283.96
1 TF99108 - GOODS 4,300,000.00 3,552,988.88 747,011.12 747,011.12 3,552,988.88
2
TF99108 - CIVIL
WORKS 22,100,000.00 14,661,949.45 7,438,050.55 7,438,050.55 14,661,949.45
3
TF99108 -
CONSULTING 13,800,000.00 2,897,141.01 10,902,858.99 10,902,858.99 2,897,141.01
4 TF99108 - TRAINING 6,800,000.00 294,081.01 6,505,918.99 6,505,918.99 294,081.01
5
TF99108 -
OPERATING COSTS 800,000.00 177,350.72 622,649.28 622,649.28 177,350.72
6 UNALLOCATED 2,200,000.00 0.00 2,200,000.00 2,200,000.00 0.00
DA-A Designated Account 0.00 4,140,204.97 -4,140,204.97 -4,140,204.97
Financial Reporting; IFRs are submitted timely with an acceptable quality. The 2nd
semi-annual IFR is
currently being prepared and is expected to be received within the due deadline.
External Audit. The final audit report for RSSP 2 was submitted to the bank on March 27 2013. The audit
opinion rendered by the auditor was unqualified (clean) opinion. However a number of weaknesses wear
noted in the management letter. Although these did not lead to a qualification however they’re issues that
still warrant follow up and implementation. An audit action plan was prepared and implementation of actions
in progress although the action plan was not timely shared with IDA. As recommendation going forward the
action plan should be time bound, the one shared does not include timeframes when recommendations such
as those in progress will be finalized.
Transactions (including SOE/interim report) Reviews. No transaction review undertaken given work of
Internal Audit and low risk allocated to the project.
GAC – Fraud and Corruption. No issues identified.
FM Action Plan - Status of previous Action Plan
Issues Agreed Actions By Whom By When Status
1. RSSP II outstanding
audit.
Audit on going- project team
to follow up to ensure audit is
finalized by February 2013
Project finance
team
February 28,
2013
Done
2. LWH audit findings Implement audit
recommendations
Project Finance
Team
February 28,
2013
3. AFR issue of
documentation
Follow up with disbursement
and the team leader
TTL/WB, Project
finance team
March 30, 2013 Done
4. CIDA/USAID Funds Activate the trust fund TTL WB March 30, 2013 Done
25
FM New Action Plan
Issues Agreed Actions By Whom By When
5. RSSP 2 Audit findings Follow up as per submitted
action plan
SPIU September 30,
2013
6. Disbursement Accelerate disbursement on the 2
TFs for LWH
SPIU September 30,
2013
7. Accounting Training for the accountants that
have not been trained
SPIU September 30,
2013
8. Internal control Follow up on audit
recommendations especially on
accountability of transfers to
district
SPIU September 30,
2013
9. Audit and IFR IFRs are due on August 15,
Close accounts for Audit of both
projects
SPIU September 30,
2013 (for Audit)
August 15,2013
(for IFR)
Appendix 1: Updated FM Risk Assessment
Updated FM Risk Assessment LWH/RSSP3 - SPIU
Type of Risk Residual Risk Rating Brief Explanation of Changes and any New
Mitigation Measures Previous Current
INHERENT RISK
Country Level M M
Entity Level M M
Program Level M M
OVERALL INHERENT RISK M M
CONTROL RISK
Budgeting L L
Accounting L L
Internal controls M M
Funds Flow M M
Financial Reporting L L
Auditing L L
OVERALL CONTROL RISK L L
TOTAL RISK L L
26
Annex 6: Communication
The mission noted that the communications team implemented most of the recommendations of the January
2013mission. The SPIU has created a database which houses and organizes pictures, videos and testimonies of
the beneficiaries and landscape transformation showcasing how RSSP and LWH projects have impacted both
landscapes and changes in beneficiaries’ livelihoods. The communication team has also developed a
documentary slideshow of the achievements and other realizations made during the last six months. Giving voice
to beneficiaries experiences by providing brief write-ups by mission members from the field visits was started
last mission and included as an annex in the aide memoire. The plan is to continue this practice in future aide
memoires. The mission has also noted that the SPIU was in process of upgrading its website which will cover
both LWH and RSSP activities and communications. The mission has recommended the following:
(1) The SPIU will work with CICA to explore the feasibility of the partnership in producing radio and
video/documentary programs to communicate Project activities and for the purpose of extension services
to targeted farmers, the SPIU to support the needed equipment to design and print extension materials
and communication documents. Both institutions will also explore how the postharvest facilities
constructed by the SPIU in different sites can also become innovation centers, where farmers can get
extension services and materials.
(2) Baseline and transformation capture – the Project to document for each site the baseline condition via
photos and videos as well as written document and from time to time how the sites and beneficiaries
where the Project operates are being transformed.
(3) To further enhance the 6 month mission preparation documentary, the SPIU might consider archiving
each month photos, videos, news articles, posting from the MINAGRI website and other
communications of interest into the communication database. Then for the 6 month documentary, the
team would just compile the previous 6 monthly archives.
27
Annex 7: M&E Plan for LWH
PDO: To increase the productivity and commercialization of hillside agriculture in target areas.
PDO Level Indicators
INDICATOR 1:Increased Productivity of targeted irrigated command area ($/ha)3
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
492 - - - 1400
BR+200%
2000 BR+300%
2700 BR+450%
Variable definition: Total value($) of production in the project irrigated command area(ha)
Unit of Measure: USD per ha
Method of analysis/calculation: Total production ($) over total area cropped.
Critical Assumptions: Adoption of new technologies by beneficiary cooperatives leads to increased
production.
Method of data collection : Post season survey and cooperative reports. The calculation is based on
Season B and A (January), then season A and B of the previous season (July); a weighted average is
calculated on annual basis.
Frequency : Seasonal (Coop reports) , reported on annual basis
Responsibility : SPIU M&E Specialist, District M&E Assistants, Agri-business officer
INDICATOR 2: Increased Productivity of targeted non-irrigated hillsides ($/ha)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015 469 - 1900
BR+283%
2100
BR+323%
2300
BR+364%
2350
BR+374%
2400
BR+384%
Variable definition: Total value($) of production over total cropped area
Unit of Measure: USD per ha
Method of analysis/calculation: Total production over total area cropped.
Critical Assumptions: Adoption of new technologies by beneficiary cooperatives leads to increased
production.
Method of data collection : Post season survey and cooperative reports ;The calculation is based on
Season B and A (January), then season A and B of the previous season (July), after which a weighted
average is calculated on annual basis.
Frequency : Seasonal (Coop reports) , reported on annual basis
Responsibility : SPIU M&E Specialist, District M&E Officers, Agri-business, and Agronomists
3 Exchange rate : 1USD=565 RFW as mentioned in LWH PAD Document
28
INDICATOR 3: Increased in share of commercialized products from target areas (%)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
35 45 50 60 65 70 70
Variable definition: Total production sold disaggregated by the rain fed and command area over the
total production
Unit of Measure: Percentage
Method of analysis/calculation: Sum of sold production($) of season B and A(July)or A and B(January)
over the total production for season of both season B and A (July) and A and B(January)
Critical Assumptions: The project induces higher production, thus increase in production marketed.
Method of data collection : Post survey Cooperative reports, District Agri-business report and post
seasonal survey twice a year
Frequency: Annually
Responsibility: SPIU M&E Specialist, Marketing Officer , M&E Assistants, Agri-business officer
INDICATOR 4: Project beneficiaries(individual )of which female ( beneficiaries)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015 0 5000
(2250)
18000
(8100)
21000
(9450)
94000
(46000)
97000
(47000)
100000
(48000)
Variable definition: Total number of SHGs members and their HH members receiving support for
productivity and commercialization in the project intervention areas ( farmers in SHGs4 + family
members)
Unit of Measure: Number
Method of analysis/calculation: Total number of SHG members + family members + Any other farmer
doing any activity financed/supported by the project.
Critical Assumptions: Farmers in the project areas are grouped for common interest and receives income
and other benefits as a result of project activities.
Method of data collection : Census of beneficiary farmers
Frequency: Launch of site, seasonal census
Responsibility: Chain Formation Specialist, Capacity Building Specialist, Community District
Development Officer, District M&E Officers
4 SHG members are representatives of the HH in the project area with land or doing other activities supported by the
project whose income is as a result of project interventions;
29
Intermediate Result (Component One): Improved hillside land husbandry technologies and techniques,
strengthened value chains for agricultural products, and expanded access to rural finance.
INDICATOR 1: Number of Cooperatives which have increased their net revenues by 50% relative to the
baseline(Number)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
0 0 3 4 6 8 10
Variable definition: Net revenues of each coop relative to the Baseline. The baseline value is the net
revenue of the coop after one year existence
Unit of Measure: number
Method of analysis/calculation: Total revenue per year less Total Costs per year compared to the coop
net revenue at the first year existence.
Critical Assumptions: Cooperatives receiving technical support in agri-business
Method of data collection: Financial statements of cooperatives prepared annually & collected by
District Agri-business Officers and M&E assistants through Cooperative managers.
Frequency : Collected every season (A&B) & reported annually
INDICATOR 2: Cost recovery and maintenance of WUA in project area (%)
Baseline Targets
2010 2011 2012 2013 2014 2015
0 - - - 40 60 90
Variable definition: Cost recovery and maintenance of WUA in project area
Unit of Measure: Percentage
Method of analysis/calculation: Total contribution of WUA / Total operational/running costs in the
Financial Year.
Critical Assumptions: WUAs formed and cover their share of running costs in the reporting period
Method of data collection : WUA reports , Contractor's/Operator financial reports,
Frequency: seasonal and reported Annually
Responsible: WUAs, Irrigation Engineers
INDICATOR 3: Proportion of farmer in project affected areas using improved farm methods (disaggregated
by gender)
Baseline Targets
2010 2011 2012 2013 2014 2015 M=30
F=25
50
50
60
60
70
70
75
75
80
80
90
90
Variable definition: Total number of farmers using improved farm methods / total number of farmers in
the project area disaggregated by gender)
Unit of Measure: Percentage
Method of analysis/calculation: Total No of farmers using at least 3 improved farm methods / Total No
of farmers in the project area disaggregated by gender) these are: improved planting materials, IPM, soil
fertility management, conservation tillage, agro-forestry interventions, intercropping with plant cover
and green manuring, compost & mulching, liming
30
Critical Assumptions : Farmers adopt improved farming methods
Method of data collection : Post Seasonal Surveys ( twice a year) and reported annually
Frequency: Annually ;
Responsible: SPIU M&E Specialist, Senior Agronomist, District agronomists, M&E Officers
INDICATOR 4: Percentage of adult project beneficiaries in the project areas which have access to the
services of formal financial institutions(disaggregated by gender)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
M=22
F= 18
50
50
70
65
90
80
92
85 94
87
95
90
Variable definition: Total number of adult project beneficiaries having accounts in formal financial
Institutions / total number of beneficiaries in the project area disaggregated by gender)
Unit of Measure: Percentage
Method of analysis/calculation: Number of adult beneficiaries having accounts in formal financial
institutions /total adult beneficiaries in the project targeted area ( disaggregated by gender)
Critical Assumptions : Financial institutions are decentralized and accessible to farmers adoption of
financial services
Method of data collection: Surveys twice a yr and reported on annual basis.
Frequency: Annually
INDICATOR 5: # of participating financial institutions (PFIs) in the project areas offering new products.
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
0 - 3 6 12 18 24
Variable definition: Number of financial institutions offering new products
Unit of Measure: Number of PFIs
Method of analysis/calculation: Counting Participating Financial Institutions(PFIs)
Critical Assumptions: Financial institutions offer new products.
Method of data collection : LWH progress reports
Frequency: Bi-annual ( Jan and July every year)
INDICATOR 6: % of Coops and their SHGs ranked high and graded high (A&B)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015 0
0
-
-
-
-
-
-
60
60
70
70
80
80
Variable definition: Total number SHGs fulfilling the criteria of being in category of A&B over Total
SHGs in the Project sites
Unit of Measure: percentage
Method of analysis/calculation: Total number SHGs fulfilling the criteria of being in category of A&B
after one year existence / Total SHGs in the Project sites: i.e grading of SHGs as per categorization
criteria
Critical Assumptions : SHGs are strengthened to become strong groups and fulfilling the criteria put in
place
Method of data collection: Use of guidelines established for grading in E each SHGs on regular basis.
Frequency: Annually
Responsible: Chain Formation Specialist , District CDOs
31
INDICATOR 7: % of Households with acceptable food consumption
Number of Kitchen gardens constructed5
Baseline Targets
2009 2010 2011 2012 2013 2014 2015 79
0
-
-
-
-
82
3975
83
6000
84
9500
85
15000
Variable definition:
Total number HH with acceptable food consumption ( as mentioned in the food ranges module of
nutrition) /Total HH in the Project sites
Constructed Kitchen gardens in the HH the project site /total HH in the project site
Unit of Measure:
Percentage
Number
Method of analysis/calculation
Total number HH with acceptable food consumption ( as mentioned in the food ranges module of
nutrition) /Total HH in the Project sites
Constructed Kitchen gardens in the HH the project site /total HH in the project site
Critical Assumptions: Farmers trained on nutrition and kitchen gardens constructed in all HH in the
project site.
Method of data collection: Post seasonal Surveys on food consumption and District report on
kitchen gardens ;
Frequency:Bi-annual
Responsible: Horticulture, Agronomist, M&E Assistants.
5
32
Intermediate Result (Component Two): Improved infrastructure for hillsides
INDICATOR 1: Proportion of land in the project protected against soil erosion in project areas
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
266 43 60 75 80 85 90
Variable definition: Land Protected against erosion upon total land in the project area
Unit of Measure: Percentage
Method of analysis/calculation: Land Protected against erosion upon total land in the project area
Critical Assumptions : Soil erosion protection measures are adequately implemented and sustainable
Method of data collection : District progress reports
Frequency: Bi-annual
Responsible: Watersheds, Agroforestry , M&E Officers
INDICATOR 2 : Area developed for Irrigation in the project (Ha)
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
0 - - - 350 850 1868
Variable definition: Total area under irrigation
Unit of Measure: number of ha
Method of analysis/calculation: Total area under irrigation
Critical Assumptions Continuous supply of water
Method of data collection : District project reports
Frequency: Bi-annual
Responsible: Watershed Officers; Irrigation Officers, ,M&E Officers
INDICATOR 3 : Reduced sediment yield(volume or weight per unit area of catchment(T/ha/yr)in the
project area
Baseline Targets
2009 2010 2011 2012 2013 2014 2015
0 - - - -10 -30 -50
Variable definition: Amount of sediment yield in the project area.
Unit of Measure: Percentage
Method of analysis/calculation: Amount of sediment in the project area T/ha/yr)
Critical Assumptions : Soil loss is controlled through land management
Method of data collection : rain gauges, sediment loads equipment installed in the downstream of the
watershed
Frequency: Annual
6 : The baseline was established based on the weighted average of 7 sites ranged as follows: Karongi-12 (14 %); Karongi-
13(13%), Nyanza-23(12.5%);Gatsibo-8(19.6%), Rwamagana-34 (56%) , Rwamagana-35 (39.3%); Kayonza-4(24.9%).
33
Annex 8 : Summary of Component A.1 : Strengthening Farmer Organizations
The main objective of this subcomponent is to build and strengthen farmer organizations, cooperatives and
Water User Associations (WUAs). The sub-component has made good progress during the last six months, and
is rated satisfactory. The field visit interactions with the beneficiaries revealed a very high degree of community
enthusiasm and understanding of the project; and a strong willingness and commitment to participate and
contribute to their watershed development. In most communities visited, the mission heard several testimonials
from the beneficiaries about increased benefits from the group formation, new techniques of land improvement,
better marketing facilities, and improved access to knowledge, financial resources, etc. The key achievements
during the last six months have been: (i) adopting of a harmonized capacity building plan; (ii) fine-tuning of the
structure of the farmer/community organizations to ensure clarity on roles and responsibilities of various levels
of community organization and continuity of leadership; (iii) refining of the monitoring system and initiating a
comprehensive database of beneficiaries to monitor and track results; and (iv) introducing community level
reporting and information system. The project has also recruited the local service providers, and launched the
capacity building program (training, refreshers, exposure visits, etc).
The implementation progress, key recommendations and priority actions are summarized below, and details are
included in the Technical Annex on Sub-Component A.1. As of June 30, 2013, the project has succeeded in
formation of 1067 SHGs reaching out to 21,180 members in current seven sites, out of which 8571 (about
40%) are women. In addition, 77 Zonal organizations and five cooperatives have been formed and have started
functioning. Out of total SHG members, 4866 members have joined the five cooperatives. There is now better
clarity of roles and responsibilities at the zonal and cooperative level, and four cooperatives have started
generating revenues, which is an excellent sign towards financial sustainability. The project has also formed six
WUAs, which have started functioning. Phase 1A WUAs (in Nyanza 23 and Karonji 12 & 13) have received
training in administrative and financial management, and conflict resolution, and have benefited from exposure
visits to good practices. So far, three WUAs of Phase 1A have acquired district licences certificates which give
them recognition to operate in the district.
While the project has implemented most of the recommendations of the MTR mission, and laid a solid
foundation and structure for the community organizations, there are a few areas that would need attention going
forward. These are as follows: (i) adopting and mainstreaming of an improved reporting and monitoring format
to track progress of implementation targets and milestones including tracking of inclusion of the most vulnerable
including vulnerable women and youth; (ii) tracking performance of SHGs, WUAs and cooperatives on a regular
basis to ensure continuity of their performance, and motivation; (iii) further streamlining of capacity building
activities, and ensuring that key capacity building activities are carried out on a continuous basis and in a cost-
effective way, and as per agreed capacity building plan; (iv) ensuring that each level of community institutions –
SHGs, Zones and site committees, WUAs and Cooperatives perform their functions effectively – there is no
duplication of functions, and adequate technical assistance is provided to the higher level institutions
(cooperatives and WUAs) to perform their functions; (v) improved community level monitoring and learning
system (including reporting formats, database and learning and sharing forums); and (vi) developing an exit
strategy so that the institutions are sustainable in the long run.
The following actions have been agreed with the project team: (i) mainstream and use an improved planning and
reporting format (as part of AWPB) to capture, track and report progress of key process steps and milestones on
community institutional development by Sept.30, 2013; (ii) complete grading of SHGs. Zones/Cooperatives and
WUAs (which have completed one year) by December 31, 2013; (iii) update and finalize the remaining training
modules (including July 2013 South to south training) and train Service providers and TOTs in those training
modules by Oct. 31, 2013; and (iv) complete legal registration of remaining WUAs and set-up remaining
Irrigation District Committees etc.
34
Annex 9: Technical annex for sub-components B2 and B3: Water harvesting and hillside irrigation
The mission visited a total of nine sites (Nyanza-23, Karongi-12, Karongi-13, Rwamagana-34, Nyamukana,
Muyanza, Base, Rugabano, Mwange), had walk-throughs in potential reservoir and command areas and engaged
in discussions with WUA members and inhabitants of the respective areas.
A breakdown of the implementation progress by site and activity is given in the table below.
Table: Summary of implementation progress
Activities Sites Total Area
(ha)
Ongoing works Nyanza-23 (471ha); Karongi-12 (128 ha);
Karongi-13 (95 ha) 694
Sites being readied for
tendering
Rwamagana-34 (267 ha); Kayonza-4 (420 ha),
Gatsibo-8 (45 ha), 732
Ongoing studies Muyanza (442 ha) and three other fast-track
sites (1500 ha) 442
Total 1868
At Nyanza-23, the mission noted that the silt trap zone has not yet been established. These land husbandry works
should commence soonest as they are critical to control siltation of the reservoir and are expected to reach their
full effectiveness only after one or two seasons.
Also at Nyanza-23, the contract for the construction supervision firm (Artelia/Someah) should be amended from
the current nine months to twelve months, in order to cover the entire construction period through to December
2013.
The mission reviewed phase 1B sites feasibility studies and is pleased to find that efficient storage sites have
been identified, especially at Kayonza-4 and other cost saving features (alternative lining method, cropping plan)
are being proposed. The reports show economic viability of the water harvesting and irrigation infrastructure at
both Kay-4 and Rwa-5. Using a 100 year return period for spillway sizing is considered the absolute minimum,
and it is recommended to rather use 200 years routed flood instead. While the cost increases of such a change are
considered minor, the hydrological risk during the 50 year design life of the dam is reduced from 39 % to 22 %.
The project should also determine the return period for a zero freeboard, i.e. water level at dam crest. Prior to
tendering, the project should submit detailed designs for Bank concurrence. The mission discussed and agreed on
tender structure for both sites and discussed ways to increase tender outreach and encourage more competition
(e-mail alerts to existing long-list of construction firms, notifications of embassies in Kigali, encouragement of
joint ventures).
The mission acknowledges the significant challenges experienced by LWH and RSSP projects in retaining
contractors for dam construction - only two national firms with relevant prior experience and very limited
interest from foreign firms so far. Hiring road construction firms without prior experience in dam construction
would be conditioned on them partnering up (joint venture or sub-contractor) with firms experienced and well
documented references in this field as well as daily earthworks commensurate with the specifications of each
site.
The mission reviewed all available data for phase 1-C fast-track sites of Base, Muyanza, Nyamukana and
Nyarubogo. Based on the information provided, Muyanza and Nyarubogo appear to be the most promising and
with least constraints or possible conflicts. However, it is recommended to (i) check and re-calculate
embankment volume at Muyanza site as it appears to be too high for a 12-14 m dam (ii) keep both dam locations
at Nyamukana in parallel through the feasibility stage, as embankment volume and command area for site 33a do
look promising while the new dam site in a narrow valley section 2 km downstream has some interesting
features as well, (iii) decelerate Nyarubogo site from fast-track to part B because of apparent water quantity
issues (extremely low baseflow) and possible competition with an existing RSSP scheme downstream, all of
which merits more careful investigation, (iv) decelerate Base site from fast-track to part B because of apparent
35
flooding issues which need to be studied carefully by the consultant and the possible impact on the downstream
hydropower project (Base 1 and Base 2) needs to be fully quantified. It was also agreed to bring the Rugabano
site to feasibility study.
If the project wishes to proceed with approx. 800 - 1000 ha per consultant team for part-A fast-track (designs
ready early next year), it might be advisable to retain one or two promising stream diversion sites. This carries
the advantage of being able to top up, at a relatively lower unit cost, whatever dam based command area will be
financed from the additional financing once the exact amount of available resources become known and actual
construction costs for upcoming tenders are locked up in contracts. It also allows to respond flexibly in case of
unexpected cost increases at Muyanza during feasibility and design studies.
Data collection (rainfall, runoff, sediment yield) is ongoing at a total of 10 sites. The data collected so far
provides important information needed for system design as well as for monitoring of soil erosion. The sediment
yield data presented to the mission is encouraging and it is recommended to continue the exercise in order to
establish a long-term trend. With the plan to establish data collection at ten additional sites, procurement of
equipment and construction should be expedited.
To date, WUAs have been established at six sites and 60 farmers have been trained on key WUA functions prior
to scheme commissioning, which is good practice. The Karongi District Irrigation Steering Committee has been
formed, N-23, K-12 and K-13 WUAs have been registered with their respective districts and registration with
RGB is ongoing. For WUAs in schemes currently under construction, more O&M training is needed according
to the O&M plans already developed.
Following a study of different management models for hillside irrigation, MINAGRIs concluded that in the
short-term, service provider O&M carries the least risk of failure at new hillside schemes. The project has
prepared ToRs for O&M services. While the TORs cover most relevant aspects of irrigation service provision,
the mission is concerned that bunching irrigation services under one contract with extension and marketing
services. This carries the risk of replicating the phased-out coop-model for irrigation O&M, which was found to
put most emphasis on marketing activities and lead to a neglect of irrigation infrastructure. After reviewing the
TORs, the O&M services should be tendered.
3 year work plan for sub-components B2 and B3 until end of project The overall work plan for sub-components B2 and B3 for the remainder of the project was updated during this
mission. It is important to track progress against this work plan, detect slippage and take remedial action if
necessary.
36
Follow-up on recommendations from the January 2013 MTR
MTR recommendation No. 1
Project should decide on the re-allocation amount to component B, by 15 February 2013.
Mission follow-up Re-allocation has been formalized in the restructuring paper.
MTR recommendation No. 2
Based on results of pre-feasibility study for Phase-2 sites, select remaining irrigation sites needed to achieve end
of project target on area developed for irrigation by May 2013.
Mission follow-up Remaining site (Muyanza) pre-selected and confirmed during this mission.
MTR recommendation No. 3
Provide training of WUAs on their principal functions at all phase 1A sites, including O&M fees based on a
realistic costing of O&M plans, by June 2013.
Mission follow-up Project staff conducted extensive training of WUA members on organizational and financial management, roles
and responsibilities of WUA officials as well as conflict resolution. Training on water management and system
operation and maintenance still needs to be conducted.
MTR recommendation No. 4
Prepare terms of reference for O&M services at Nyanza-23 and Karongi-12 and Karongi-13 irrigation schemes,
by May 2013.
Mission follow-up Terms of reference have been prepared by June 2013 but require revision and updating.
37
MTR recommendation No. 5
Complete studies and tender documents for Gatsibo-8, Rwamagana-34, Rwamagana-35 and Kayonza-4, by July
2013.
Mission follow-up Feasibility studies were completed in June, and detailed designs and tender documents are expected in
July/August 2013. This work is six months behind schedule due to delays during procurement and
implementation.
July 2012 recommendation No. 4
Finalize procurement of contractor and supervision firm for Karongi-12 and Karongi-13 by November and
commence construction by December 2012.
Mission follow-up The civil works contract was signed on 24 December 2012, and mobilization and site installation commenced on
7 January 2013. Works started only in April 2013 with the arrival of the construction supervision firm.
July 2012 recommendation No. 7
Recruit additional experienced irrigation engineer by October 2012.
Mission follow-up The selected candidate has reported for work in February 2013, and is currently posted at Karongi command area
construction site.