agenda2015/11/09 · construction committee 11/9/2015 304 e. grand river ave, conference rm 4a,...
TRANSCRIPT
-
CONSTRUCTION COMMITTEE11/9/2015
304 E. Grand River Ave, Conference Rm 4A, Howell, MI 488436:30 PM
AGENDA
1. CALL TO ORDER2.
APPROVAL OF MINUTES Minutes of Meeting Dated: October 19, 2015
3. APPROVAL OF AGENDA4.
REPORTS A. Budget Report B. Open PCO Log
5. CALL TO THE PUBLIC6.
ACTION ITEMS A. Clark Pay Application #15: $693,407.75 B. PCO 81 - Credit for T&M work: ($12,095.33) C. PCO 82 - Misc. Drywall Extras: $6,341.00 D. PCO 83 - Sallyport Electrical Demolition: $845.00 E. PCO 84 - Added Sprinkler Heads per RFI 121: $896.00 F. PCO 85 - Rework Fire Protection-Sallyport: $1,563.00 G. PCO 86 - Relocate 2 Sprinkler Heads: $1,099.00 H. PCO 88 - Floor to Wall Joint Caulking: $2,712.00 I. PCO 89 - Replacement Door Savings: ($15,207.00)
7. NEW BUSINESS8. ADJOURNMENT
-
Page 1 of 4 Pages
MEETING MINUTES LIVINGSTON COUNTY
OCTOBER 19, 2015 - 6:30 PM
ADMINISTRATION BUILDING - CONFERENCE ROOM 4 304 E. Grand River Avenue, Howell, MI 48843
CONSTRUCTION COMMITTEE
���� COMM. DOLAN � COMM. CHILDS � COMM. VANHOUTEN
OTHERS: MIKE KENNEDY CHAD RIEHL
KEN HINTON HEATHER BRANDENBURG
NATALIE HUNT TOM CREMONTE
1. CALL TO ORDER: Meeting called to order by: COMM. DENNIS DOLAN at 6:30 PM.
2. APPROVAL OF MINUTES: MINUTES OF MEETING DATED SEPTEMBER 14, 2015:
MOTION TO APPROVE THE MINUTES, AS PRESENTED.
MOVED BY: VAN HOUTEN / SECONDED BY: CHILDS
ALL IN FAVOR - MOTION PASSED
3. APPROVAL OF AGENDA:
MOTION TO APPROVE THE AGENDA, AS MODIFIED.
ADD PCO #80 –
NEW BUSINESS – DISCUSS CELL DOORS
MOVED BY: CHILDS / SECONDED BY: VAN HOUTEN
ALL IN FAVOR - MOTION PASSED
4. REPORTS
o STEEL CELL INVOICE RECEIVED LATE, WOULD LIKE TO GET THAT ON THE AGENDA.
o INVOICE WILL BE BROUGHT TO NEXT MEETING ON NOVEMBER 9TH, AGENDA STANDS.
A. BUDGET REPORT:
o BUYOUT BALANCE OF ASPHALT WILL NOT BE SENT AND BE PUT BACK IN CONTINGENCY AND $13,000 IN CHANGE ORDERS ON TODAY’S AGENDA LEAVES A $275,073 CONTINGENCY BALANCE
B. CONSTRUCTION PROGRESS UPDATE: MIKE KENNEDY
o FURNITURE FOR DAY ROOM HAS BEEN DELIVERED, MATTRESSES HAVE ALSO BEEN DELIVERED.
o STARTED FINAL CLEANING IN MECHANICAL CHASE, CELL AREA WILL BE NEXT
-
Page 2 of 4 Pages
o FIXTURES STILL NEED TO BE CAULKED.
o SPRINKLER HEADS TO BE CHANGED IN THE 2ND FLOOR HALLWAY
o EXTERIOR – FINISH PAVING THIS FRIDAY, STRIPING FOR PARKING LOT WILL BE DONE ON MONDAY
o GROUND IS RAKED AND READY FOR SEED, SECURITY FENCES ARE UP, TREES WILL BE PLANTED TOMORROW OR WEDNESDAY
o SALLY PORT (EXISTING) – FOUNDATION IS IN, MASON STARTED TODAY, STEEL WILL BE SET NEXT WEEK
o DISCUSSED HOW TO CONNECT THE SALLY PORT DRAIN TO THE CURRENT PLUMBING
o GLAZING MAY ARRIVE AS SOON AS OCTOBER 30TH
o DOOR RENAMING WILL ESTABLISHED THIS THURSDAY
o SHOULD GET WITH RICH & ROBERTA TO GET FINAL FURNITURE AND IT COSTS.
5. CALL TO THE PUBLIC: None.
6. ACTION ITEMS:
A. ACTION REQUIRED: ................. Clark Construction Jail Roof Invoice:
$7,018.92
REVIEWED AND APPROVED FOR PAYMENT. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: VAN HOUTEN SECONDED BY: CHILDS
B. ACTION REQUIRED: ................. Clark Construction Pay Application 14:
$900,552.95
REVIEWED AND APPROVED FOR PAYMENT. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
C. ACTION REQUIRED: ................. Clark Construction PCO 67 - Delete Mattresses:
($27,430.00)
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
D. ACTION REQUIRED: ................. Clark Construction PCO 68 - Delete VCT:
($875.00)
REVIEWED – APPROVED PCO 67 & 68 ON SEPTEMBER 14TH
APPROVED FOR PAYMENT: MOVED BY: SECONDED BY:
E. ACTION REQUIRED: ................. Clark Construction PCO 70 - I.T. Room:
$15,185.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
-
Page 3 of 4 Pages
F. ACTION REQUIRED: ................. Clark Construction PCO 71 - Data Drop:
$998.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
G. ACTION REQUIRED: ................. Clark Construction PCO 72 - Smoke Dampers:
$1,087.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
H. ACTION REQUIRED: ................. Clark Construction PCO 73 - Asphalt Removal:
$9,700.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
I. ACTION REQUIRED: ................. Clark Construction PCO 74 - Sidewalk
Undercutting:
$3,700.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
J. ACTION REQUIRED: ................. Clark Construction PCO 75 Cut Door:
$886.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
K. ACTION REQUIRED: ................. Clark Construction PCO 76 - Heater:
$888.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
L. ACTION REQUIRED: ................. Clark Construction PCO 77 - Raise DAC 1:
$1,580.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: VAN HOUTEN SECONDED BY: CHILDS
-
Page 4 of 4 Pages
M. ACTION REQUIRED: ................. Clark Construction PCO 78 BR1 PR 5 & 6:
$10,200.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
N. ACTION REQUIRED: ................. Clark Construction PCO 79 Raising RTU:
($2,914.00)
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
O. ACTION REQUIRED: ................. Clark Construction PCO 80 Dimming Switch:
$1,704.00
REVIEWED AND APPROVED PCO. NO OBJECTIONS.
APPROVED FOR PAYMENT: MOVED BY: CHILDS SECONDED BY: VAN HOUTEN
7. NEW BUSINESS:
o DISCUSS CELL DOORS – COMMISSIONER DOLAN AND COMMITTEE MEMBERS RECEIVED DOCUMENTS FROM MIKE KENNEDY IN REGARDS TO CELL DOORS THAT WERE REPLACED.
o NEED DOCUMENTATION THAT CELL DOORS LEFT THE SITE, WHERE, WHEN, AND BY WHOM
o CONFIRMATION THAT GLASS WAS RE-USED WITH THE NEW DOORS.
o LINDHOUT GAVE STEEL CELL THE DIRECTION TO REMOVE DOORS FROM THE SITE WHEN DELIVERING OTHER MATERIALS.
o POTENTIAL CREDIT FROM REICHENBACH COMING
8. ADJOURNMENT:
MOTION TO ADJOURN AT 7:24 PM.
MOVED BY: CHILDS / SECONDED BY: VAN HOUTEN
ALL IN FAVOR - MOTION PASSED
Respectfully Submitted NATALIE HUNT RECORDING SECRETARY
-
Budget Report-Budget and Cost
Summary, Grouped by Sub Project, Cost Items & Bid Pkg
w/ Formulas & Sub Project Filter w/ Contingency Totals
Livingston County Jail Expansion Clark Construction CompanyProject # 14-2664
150 S. Highlander Way, Howell, MI 48843 Tel: Fax:
PCO # 089 Ref. Most Recent PCO
PCCO # 014 Ref. Most Recent PCCO
PCCO # Ref. Approved PCCO
A B C=A+B D E F=C+D+E G H I=G+H J K L M=I+J+K+L N=F-M
Line
Item #
line Item
Description
Projected
Budget
Subcontractor Original
Contract
Approved
Change
Orders
Revised
Contract
Amount
Anticipated
Changes
Est Cost at
Completion
Variance
(Over)/Under
Buyout
Balance
Pending
Changes
Current
Budget
Original
Budget
Approved
Budget
Changes
Pending
Budget
Changes
Anticipated
Budget
Changes
2664 A - Additions
03 Building Trade Costs
$28,564.00 $13,991.00 001400 $14,573.00 $0.00 $28,564.00 $0.00 $0.00 G2 Consulting Group, LLC $0.00 $28,564.00 *$28,564.00 $0.00 $28,564.00 $0.00 $0.00 Testing
$8,440.00 $0.00 001500 $8,440.00 $0.00 $8,440.00 $0.00 $0.00 Performance Environmental Services, Inc. $0.00 $8,440.00 *$8,440.00 $0.00 $8,440.00 $0.00 $0.00 Environmental
Remediation
$633,366.00 $165,466.00 003000 $467,900.00 $0.00 $633,366.00 $0.00 $0.00 Albanelli Cement Contractors, Inc. $0.00 $633,366.00 *$633,366.00 $0.00 $633,366.00 $0.00 $0.00 Concrete
Foundations/Flatwork
$427,172.19 $169,172.19 031000 $258,000.00 $0.00 $427,172.19 $0.00 $0.00 Sandborn Construction, Inc. $0.00 $427,172.19 *$427,172.19 $0.00 $427,172.19 $0.00 $0.00 Earthwork & Site
Utilities
$9,850.00 $9,850.00 031500 $0.00 $45,290.00 $55,140.00 $0.00 $0.00 Sandborn Construction, Inc. $0.00 $55,140.00 *$55,140.00 $0.00 $55,140.00 $0.00 $0.00 Landscaping
$46,400.00 $46,400.00 032000 $0.00 $55,950.00 $102,350.00 $0.00 $0.00 Sandborn Construction, Inc. $0.00 $102,350.00 *$102,350.00 $0.00 $102,350.00 $0.00 $0.00 Asphalt Paving
$87,725.00 $87,725.00 032500 $0.00 $0.00 $87,725.00 $0.00 $0.00 Sandborn Construction, Inc. $0.00 $87,725.00 *$87,725.00 $0.00 $87,725.00 $0.00 $0.00 Site Concrete
$660,024.00 $3,252.00 040000 $656,772.00 $0.00 $662,736.00 $2,712.00 $0.00 Davenport Masonry, Inc. $0.00 $660,024.00 *$662,736.00 $0.00 $660,024.00 $0.00 $2,712.00 Masonry
$805,410.00 $4,530.00 050000 $800,880.00 $0.00 $842,669.00 $37,259.00 $0.00 Howard Structural Steel $0.00 $805,410.00 *$842,669.00 $0.00 $805,410.00 $0.00 $37,259.00 Structural Steel
$235,346.00 ($6,170.00)060000 $241,516.00 $0.00 $235,346.00 $0.00 $0.00 Laux Construction, LLC $0.00 $235,346.00 *$235,346.00 $0.00 $235,346.00 $0.00 $0.00 General Trades
$265,650.00 $0.00 074000 $265,650.00 $0.00 $265,650.00 $0.00 $0.00 CEI Michigan LLC $0.00 $265,650.00 *$265,650.00 $0.00 $265,650.00 $0.00 $0.00 Metal Wall Panels
$254,432.00 $13,714.00 075000 $240,718.00 $0.00 $254,432.00 $0.00 $0.00 CEI Michigan LLC $0.00 $254,432.00 *$254,432.00 $0.00 $254,432.00 $0.00 $0.00 Roofing & Sheet
Metal
$48,929.00 $0.00 084000 $48,929.00 $0.00 $48,929.00 $0.00 $0.00 Lansing Glass Company $0.00 $48,929.00 *$48,929.00 $0.00 $48,929.00 $0.00 $0.00 Alum Windows, Non
Secure Glazing
$268,577.00 $68,577.00 092000 $200,000.00 $0.00 $262,822.67 ($5,754.33) $0.00 William Reichenbach Company $0.00 $268,577.00 *$262,822.67 $0.00 $268,577.00 $0.00 ($5,754.33)Drywall, Metal Studs,
Acoust Ceilings
$56,125.00 ($875.00)096000 $57,000.00 $0.00 $56,125.00 $0.00 $0.00 William Reichenbach Company $0.00 $56,125.00 *$56,125.00 $0.00 $56,125.00 $0.00 $0.00 Floor Covering
$123,307.00 $0.00 099000 $123,307.00 $0.00 $123,307.00 $0.00 $0.00 Classic Painting Co., Inc. $0.00 $123,307.00 *$123,307.00 $0.00 $123,307.00 $0.00 $0.00 Painting
$1,158,769.00 $147,769.00 110000 $1,011,000.00 $0.00 $1,158,769.00 $0.00 $0.00 Pauly Jail Building Company Inc $0.00 $1,158,769.00 *$1,158,769.00 $0.00 $1,158,769.00 $0.00 $0.00 Detention Equipment
$1,912,715.00 $70,450.00 130000 $1,842,265.00 $0.00 $1,897,508.00 ($15,207.00) $0.00 SteelCell of North America Inc. $0.00 $1,912,715.00 *$1,897,508.00 $0.00 $1,912,715.00 $0.00 ($15,207.00)Manu. Steel Mod
Cells
$183,268.00 $1,200.00 210000 $182,068.00 $0.00 $186,826.00 $3,558.00 $0.00 John E. Green Company $0.00 $183,268.00 *$186,826.00 $0.00 $183,268.00 $0.00 $3,558.00 Fire Suppressions
Systems
$1,325,049.50 $29,849.50 230000 $1,295,200.00 $0.00 $1,325,049.50 $0.00 $0.00 William E. Walter, Inc. $0.00 $1,325,049.50 *$1,325,049.50 $0.00 $1,325,049.50 $0.00 $0.00 Plumbing/HVAC
Systems
$77,440.00 $0.00 231000 $77,440.00 $0.00 $77,440.00 $0.00 $0.00 Technical Energy Solutions $0.00 $77,440.00 *$77,440.00 $0.00 $77,440.00 $0.00 $0.00 Control Systems
$1,631,015.23 $77,115.23 260000 $1,553,900.00 $0.00 $1,631,860.23 $845.00 $0.00 Superior Electric of Lansing, Inc. $0.00 $1,631,015.23 *$1,631,860.23 $0.00 $1,631,015.23 $0.00 $845.00 Electrical & Electr
Safety/Security
-
Budget Report-Budget and Cost
Summary, Grouped by Sub Project, Cost Items & Bid Pkg
w/ Formulas & Sub Project Filter w/ Contingency Totals
PCO # 089 Ref. Most Recent PCO
PCCO # 014 Ref. Most Recent PCCO
PCCO # Ref. Approved PCCO
A B C=A+B D E F=C+D+E G H I=G+H J K L M=I+J+K+L N=F-M
Line
Item #
line Item
Description
Projected
Budget
Subcontractor Original
Contract
Approved
Change
Orders
Revised
Contract
Amount
Anticipated
Changes
Est Cost at
Completion
Variance
(Over)/Under
Buyout
Balance
Pending
Changes
Current
Budget
Original
Budget
Approved
Budget
Changes
Pending
Budget
Changes
Anticipated
Budget
Changes
$9,345,558.00 $902,015.92 $101,240.00 $10,247,573.92 Subtotals for Building Trade Costs: $10,372,226.59 $23,412.67 $0.00 $0.00 $10,348,813.92 $10,372,226.59 $0.00 $10,348,813.92 $0.00 $23,412.67
06 Contractor Soft Cost
$0.00 $0.00 000900 $0.00 $20,721.00 $20,721.00 $0.00 $0.00 $0.00 $20,721.00 $20,721.00 $20,721.00 $0.00 $0.00 $0.00 Preconstruction
$0.00 $0.00 000980 $0.00 $47,840.00 $47,840.00 $0.00 $0.00 $0.00 $47,840.00 *$47,840.00 $0.00 $47,840.00 $0.00 $0.00 Insurance
$0.00 $0.00 000990 $0.00 $57,600.00 $57,600.00 $0.00 $0.00 $0.00 $57,600.00 *$57,600.00 $0.00 $57,600.00 $0.00 $0.00 Bonds
$0.00 $0.00 001000 $0.00 $94,370.58 $94,370.58 $0.00 $0.00 $0.00 $94,370.58 *$94,370.58 $0.00 $94,370.58 $0.00 $0.00 General Conditions
$0.00 $0.00 001050 $0.00 $52,679.00 $52,679.00 $0.00 $0.00 $0.00 $52,679.00 *$52,679.00 $0.00 $52,679.00 $0.00 $0.00 Building Permit
$0.00 $0.00 001100 $0.00 $246,611.00 $246,611.00 $0.00 $0.00 $0.00 $246,611.00 *$246,611.00 $0.00 $246,611.00 $0.00 $0.00 CM Labor
$0.00 $0.00 001200 $0.00 $194,165.10 $194,165.10 $0.00 $0.00 $0.00 $194,165.10 *$194,165.10 $0.00 $194,165.10 $0.00 $0.00 CM Fee
$0.00 $0.00 $713,986.68 $0.00 Subtotals for Contractor Soft Cost: $713,986.68 $0.00 $0.00 $0.00 $713,986.68 $713,986.68 $20,721.00 $693,265.68 $0.00 $0.00
07 Contingency
$0.00 $0.00 999999 $0.00 $142,402.69 $142,402.69 $0.00 $0.00 $0.00 $142,402.69 *$142,402.69 $0.00 $142,402.69 $0.00 $0.00 Contingency
$0.00 $0.00 $142,402.69 $0.00 Subtotals for Contingency: $142,402.69 $0.00 $0.00 $0.00 $142,402.69 $142,402.69 $0.00 $142,402.69 $0.00 $0.00
$9,345,558.00 $902,015.92 $957,629.37$10,247,573.92 $11,228,615.96$23,412.67 $0.00Subtotals for Additions: $0.00$11,205,203.29 $11,228,615.96$20,721.00 $11,184,482.29 $0.00 $23,412.67
2664 R - Renovations
03 Building Trade Costs
$1,620.00 $0.00 001400 $1,620.00 $4,817.00 $6,437.00 $0.00 $0.00 G2 Consulting Group, LLC $0.00 $6,437.00 *$6,437.00 $0.00 $6,437.00 $0.00 $0.00 Testing
$6,685.00 $0.00 001500 $6,685.00 $0.00 $6,685.00 $0.00 $0.00 Performance Environmental Services, Inc. $0.00 $6,685.00 *$6,685.00 $0.00 $6,685.00 $0.00 $0.00 Environmental
Survey
$124,000.00 $0.00 040000 $124,000.00 $0.00 $124,000.00 $0.00 $0.00 Davenport Masonry, Inc. $0.00 $124,000.00 *$124,000.00 $0.00 $124,000.00 $0.00 $0.00 Masonry
$50,422.00 $0.00 050000 $50,422.00 $0.00 $50,422.00 $0.00 $0.00 Howard Structural Steel $0.00 $50,422.00 *$50,422.00 $0.00 $50,422.00 $0.00 $0.00 Structural Steel
$498,984.00 $0.00 060000 $498,984.00 $0.00 $498,984.00 $0.00 $0.00 Laux Construction, LLC $0.00 $498,984.00 *$498,984.00 $0.00 $498,984.00 $0.00 $0.00 General Trades
$1,982.00 $0.00 075000 $1,982.00 $0.00 $1,982.00 $0.00 $0.00 CEI Michigan LLC $0.00 $1,982.00 *$1,982.00 $0.00 $1,982.00 $0.00 $0.00 Roofing & Sheet
Metal
$74,000.00 $0.00 092000 $74,000.00 $0.00 $74,000.00 $0.00 $0.00 William Reichenbach Company $0.00 $74,000.00 *$74,000.00 $0.00 $74,000.00 $0.00 $0.00 Drywall, Metal Studs,
Acoust Ceilings
$103,000.00 $0.00 096000 $103,000.00 $0.00 $103,000.00 $0.00 $0.00 William Reichenbach Company $0.00 $103,000.00 *$103,000.00 $0.00 $103,000.00 $0.00 $0.00 Floor Covering
$26,179.00 $0.00 099000 $26,179.00 $0.00 $26,179.00 $0.00 $0.00 Classic Painting Co., Inc. $0.00 $26,179.00 *$26,179.00 $0.00 $26,179.00 $0.00 $0.00 Painting
$571,116.00 $13,116.00 110000 $558,000.00 $0.00 $571,116.00 $0.00 $0.00 Pauly Jail Building Company Inc $0.00 $571,116.00 *$571,116.00 $0.00 $571,116.00 $0.00 $0.00 Detention Equipment
$29,456.00 $0.00 210000 $29,456.00 $0.00 $29,456.00 $0.00 $0.00 John E. Green Company $0.00 $29,456.00 *$29,456.00 $0.00 $29,456.00 $0.00 $0.00 Fire Suppressions
Systems
$530,700.00 $0.00 230000 $530,700.00 $0.00 $530,700.00 $0.00 $0.00 William E. Walter, Inc. $0.00 $530,700.00 *$530,700.00 $0.00 $530,700.00 $0.00 $0.00 Plumbing/HVAC
Systems
$3,610.00 $0.00 231000 $3,610.00 $0.00 $3,610.00 $0.00 $0.00 Technical Energy Solutions $0.00 $3,610.00 *$3,610.00 $0.00 $3,610.00 $0.00 $0.00 Control Systems
-
Budget Report-Budget and Cost
Summary, Grouped by Sub Project, Cost Items & Bid Pkg
w/ Formulas & Sub Project Filter w/ Contingency Totals
PCO # 089 Ref. Most Recent PCO
PCCO # 014 Ref. Most Recent PCCO
PCCO # Ref. Approved PCCO
A B C=A+B D E F=C+D+E G H I=G+H J K L M=I+J+K+L N=F-M
Line
Item #
line Item
Description
Projected
Budget
Subcontractor Original
Contract
Approved
Change
Orders
Revised
Contract
Amount
Anticipated
Changes
Est Cost at
Completion
Variance
(Over)/Under
Buyout
Balance
Pending
Changes
Current
Budget
Original
Budget
Approved
Budget
Changes
Pending
Budget
Changes
Anticipated
Budget
Changes
$500,675.18 $3,675.18 260000 $497,000.00 $0.00 $500,675.18 $0.00 $0.00 Superior Electric of Lansing, Inc. $0.00 $500,675.18 *$500,675.18 $0.00 $500,675.18 $0.00 $0.00 Electrical & Electr
Safety/Security
$2,505,638.00 $16,791.18 $4,817.00 $2,522,429.18 Subtotals for Building Trade Costs: $2,527,246.18 $0.00 $0.00 $0.00 $2,527,246.18 $2,527,246.18 $0.00 $2,527,246.18 $0.00 $0.00
06 Contractor Soft Cost
$0.00 $0.00 000900 $0.00 $5,180.00 $5,180.00 $0.00 $0.00 $0.00 $5,180.00 $5,180.00 $5,180.00 $0.00 $0.00 $0.00 Preconstruction
$0.00 $0.00 000980 $0.00 $11,960.00 $11,960.00 $0.00 $0.00 $0.00 $11,960.00 *$11,960.00 $0.00 $11,960.00 $0.00 $0.00 Insurance
$0.00 $0.00 000990 $0.00 $14,400.00 $14,400.00 $0.00 $0.00 $0.00 $14,400.00 *$14,400.00 $0.00 $14,400.00 $0.00 $0.00 Bonds
$0.00 $0.00 001000 $0.00 $16,299.00 $16,299.00 $0.00 $0.00 $0.00 $16,299.00 *$16,299.00 $0.00 $16,299.00 $0.00 $0.00 General Conditions
$0.00 $0.00 001050 $0.00 $13,170.00 $13,170.00 $0.00 $0.00 $0.00 $13,170.00 *$13,170.00 $0.00 $13,170.00 $0.00 $0.00 Building Permit
$0.00 $0.00 001100 $0.00 $78,520.00 $78,520.00 $0.00 $0.00 $0.00 $78,520.00 *$78,520.00 $0.00 $78,520.00 $0.00 $0.00 CM Labor
$0.00 $0.00 001200 $0.00 $50,821.00 $50,821.00 $0.00 $0.00 $0.00 $50,821.00 *$50,821.00 $0.00 $50,821.00 $0.00 $0.00 CM Fee
$0.00 $0.00 $190,350.00 $0.00 Subtotals for Contractor Soft Cost: $190,350.00 $0.00 $0.00 $0.00 $190,350.00 $190,350.00 $5,180.00 $185,170.00 $0.00 $0.00
07 Contingency
$0.00 $0.00 999999 $0.00 $225,486.82 $225,486.82 $0.00 $0.00 $0.00 $225,486.82 *$225,486.82 $0.00 $225,486.82 $0.00 $0.00 Contingency
$0.00 $0.00 $225,486.82 $0.00 Subtotals for Contingency: $225,486.82 $0.00 $0.00 $0.00 $225,486.82 $225,486.82 $0.00 $225,486.82 $0.00 $0.00
$2,505,638.00 $16,791.18 $420,653.82$2,522,429.18 $2,943,083.00$0.00 $0.00Subtotals for Renovations: $0.00$2,943,083.00 $2,943,083.00$5,180.00 $2,937,903.00 $0.00 $0.00
$11,851,196.00 $918,807.10 $1,378,283.19Totals For Project # 14-2664: $12,770,003.10 $14,171,698.96$23,412.67 $0.00$0.00$14,148,286.29 $14,171,698.96$25,901.00 $14,122,385.29 $0.00 $23,412.67
Contingency Summary: $0.00 $367,889.51 $367,889.51 $0.00 $0.00 $367,889.51 $0.00 $367,889.51 $367,889.51$0.00 $0.00 $0.00 $367,889.51 $0.00
-
Potential Change Order
Summary Log
Livingston County Jail Expansion Clark Construction CompanyProject # 14-2664
150 S. Highlander Way, Howell, MI 48843 Tel: Fax:
Budget Cost
Number Description PCCO No Approximate
(Anticipated)
Pending Approved Approximate
(Anticipated)
Pending Approved Contingency
Funds
013 Open cut and form North Foundation wall $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
023 Cellular Decking per RFI 39 $12,738.00 $0.00 $0.00 $12,738.00 $0.00 $0.00 $0.00
032 Work overtime on steel erection $4,411.00 $0.00 $0.00 $4,411.00 $0.00 $0.00 $0.00
036 Girt changes for the NE corner windows $4,868.00 $0.00 $0.00 $4,868.00 $0.00 $0.00 $0.00
060 Overhead door steel modification and misc siding
support modifications.
$15,242.00 $0.00 $0.00 $15,242.00 $0.00 $0.00 $0.00
081 Credit for T&M work completed in PCO's 53 and 65. -$12,095.33 $0.00 $0.00 -$12,095.33 $0.00 $0.00 $0.00
082 Misc. Drywall Extras $6,341.00 $0.00 $0.00 $6,341.00 $0.00 $0.00 $0.00
083 Sallyport electrical demolitioin $845.00 $0.00 $0.00 $845.00 $0.00 $0.00 $0.00
084 Added spriinkler heads per RFI 121 $896.00 $0.00 $0.00 $896.00 $0.00 $0.00 $0.00
085 Rework Fire Protection main in Sallyport $1,563.00 $0.00 $0.00 $1,563.00 $0.00 $0.00 $0.00
086 Relocate 2 sprinkler heads out of door swing $1,099.00 $0.00 $0.00 $1,099.00 $0.00 $0.00 $0.00
088 Floor to wall joint caulking $2,712.00 $0.00 $0.00 $2,712.00 $0.00 $0.00 $0.00
089 Replacement door savings -$15,207.00 $0.00 $0.00 -$15,207.00 $0.00 $0.00 $0.00
Project Totals: $23,412.67 $0.00 $0.00 $23,412.67 $0.00 $0.00 $0.00
Prolog Converge Printed on: 11/4/2015 Prolog_Converge Page 1
-
Lindhout Associates architects aia pc
Our Mission
Integrity in architecture and design in client relationships in employee relationships in community relationships advancement in all these efforts
10465 citation drive, brighton, michigan 48116
www.lindhout.com
810-227-5668 (fax) 810-227-5855
william p. lindhout frank l. pierron piet w. lindhout robert j. king michael j. kennedy david a. richardsonmichael j. o’leary bradley m. alvord john w. eckstein d. jason mcintyre holly a. osterhout
November 5, 2015
Livingston County Jail150 S. Highlander Way Howell, MI 48855
Attn: Lt. Tom Cremonte, Jail Administrator
Re: Application and Certificate for Payment No.15
Dear Lt. Cremonte:
Attached please find the application and certificate for payment No.15 from Clark Construction Company. We find this work to be in general compliance with the requirements of the contract documents and the level of completeness to be equal to or greater than the amount indicated in the attached application.
If this action meets with your approval, please proceed with payment to Clark Construction Company in the amount indicated on the application.
Feel free to contact our office if you have any questions or comments regarding this application for payment.
Michael J. Kennedy, PresidentLindhout Associates architects aia pc
c.c. Chad Riehl, Clark Construction Company
-
(Through PCCO #14)
-
Page 1 of 1
10/21/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 081Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 081 for the following extra work: Credit for T&M work completed in PCO's 53 and 65.. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 092000 01000 S
Credit for T&M per PR#4 ($1,561.33) William Reichenbach Co.
002 2664 A 03 092000 01000 S
Drywall, Metal Studs, Acoust Ceilings
($10,534.00) William Reichenbach Co.
Total Amount ($12,095.33)
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad RiehlProject Director
Livingston County/Date
-
Page 1 of 1
10/21/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 082Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 082 for the following extra work: Misc. Drywall Extras. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 092000 01000 S
Build Chase to cover sprinkler pipe $635.00 William Reichenbach Co.
002 2664 A 03 092000 01000 S
Frame wall on lower roof along C line
$656.00 William Reichenbach Co.
003 2664 A 03 092000 01000 S
Build chase around plumbing room 696
$507.00 William Reichenbach Co.
004 2664 A 03 092000 01000 S
Install 2hr shaft ceiling in janitor closet
$2,476.00 William Reichenbach Co.
005 2664 A 03 092000 01000 S
Cut roof decking back at skylight locations
$2,067.00 William Reichenbach Co.
Total Amount $6,341.00
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad RiehlProject Director
Livingston County/Date
-
Page 1 of 1
10/21/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 083Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 083 for the following extra work: Sallyport electrical demolitioin. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 260000 01000 S
Sallyport electrical Demolition $845.00 Superior Electric
Total Amount $845.00
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad Riehl
Project Director
Livingston County/Date
-
PROPOSED CHANGE ORDER
SUPERIOR ELECTRIC OF LANSING212 W. SHERIDAN ROAD
LANSING, MICHIGAN 48906
CCN # PCO-023 SALLY PORT DEMODate: 10/16/2015
Project Name: LIVINGSTON COUNTY JAIL ADDITION
Project Number: 18000
Page Number: 1
Client Address:
CLARK CONSTRUCTION COMPANYContact: CHAD RIEHL
3535 MOORES RIVER DRIVE
LANSING, MICHIGAN 48911
Work Description
PER LIVINGSTON COUNTY/ CLARK CONSTRUCTION REQUEST, DEMO ELECTRICAL IN EXISTING SALLY PORT NOT
SHOWN IN DRAWINGS TIME AND MATERIAL
We reserve the right to correct this quote for errors and omissions.
This quote covers direct costs only and we reserve the right to claim for impact and consequential costs.
This price is good for acceptance within 10 days from the date of receipt.
We request a time extension of 3 days.
We will supply and install all materials, labor, and equipment as per your instructions on CCN # PCO-023 SALLY PORT DEMO.
Itemized Breakdown
Description Qty Total Mat.
MISC DEMO 10 0.00
Totals 10 0.00
Summary
ELECTRICAN (10.00 Hrs @ $73.50) 735.00
Subtotal 735.00
Markup 15% 110.25
Subtotal 845.25
Final Amount $845.25
CONTRACTOR CERTIFICATION
Name:
Date:
Signature:I hereby certify that this quotation is complete and accurate based on the information provided.
CLIENT ACCEPTANCE
ORIGINAL
-
PROPOSED CHANGE ORDER
SUPERIOR ELECTRIC OF LANSING212 W. SHERIDAN ROAD
LANSING, MICHIGAN 48906
CCN # PCO-023 SALLY PORT DEMODate: 10/16/2015
Project Name: LIVINGSTON COUNTY JAIL ADDITION
Project Number: 18000
Page Number: 2
Client Address:
CLARK CONSTRUCTION COMPANY3535 MOORES RIVER DRIVE
LANSING, MICHIGAN 48911
CCN #: PCO-023 SALLY PORT DEMO
Final Amount:$845.25
Name:
Date:
Signature:
Change Order #:I hereby accept this quotation and authorize the contractor to complete the above described work.
ORIGINAL
-
Page 1 of 1
10/21/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 084Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 084 for the following extra work: Added spriinkler heads per RFI 121. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 210000 01000 S
Added sprinkler heads per RFI 121 $896.00 John E. Green Co
Total Amount $896.00
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad RiehlProject Director
Livingston County/Date
-
Page 1 of 1
10/21/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 085Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 085 for the following extra work: Rework Fire Protection main in Sallyport. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 210000 01000 S
Rework Fire Protection main in Sallyport
$1,563.00 John E. Green
Total Amount $1,563.00
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad RiehlProject Director
Livingston County/Date
-
Page 1 of 1
10/21/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 086Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 086 for the following extra work: Relocate 2 sprinkler heads out of door swing. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 210000 01000 S
Relocate 2 sprinkler heads out of door swing
$1,099.00 John E. Green
Total Amount $1,099.00
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad Riehl
Project Director
Livingston County/Date
-
Page 1 of 1
11/4/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 088Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 088 for the following extra work: Floor to wall joint caulking. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 040000 01000 S
Floor to wall joint caulking $2,712.00 Davenport Masonry
Total Amount $2,712.00
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad RiehlProject Director
Livingston County/Date
-
ATTN: Greg Deuel Clark Construction Company
RE: Livingston County Jail
We propose to furnish labor, material, and equipment for the following work:
Install Dyna Flex SC sealant at the floor to wall conditions were expansion exist
Approx 450 LF
Clarifications:
This quote is for work to be preformed as straight time
For the sum of: 2,712.00$
If you should have any questions, please feel free to contact me at any time.
Sincerely,
Rick Benner
517-927-9020
P.O. Box 188 · 1445 Edgar Rd. · Holt, MI 48842-0188 · Phone: 517.699.4279 · Fax: 517.699.6141 · www.davenpo
EQUAL OPPORTUNITY EMPLOYER
-
ortmasonry.com
-
Page 1 of 1
11/4/2015
Mike Kennedy Lindhout Associates Architects10465 Citation DriveBrighton, MI 48116
RE: PCO No. 089Livingston County Jail Expansion -14-2664
Dear Mike Kennedy,
We have finalized gathering all the required quotations for PCO No. 089 for the following extra work:Replacement door savings. We have reviewed the scopes of work and have verified that all extra work items are in compliance with the Contract Documents.
The following is a detailed itemization of all extra costs:
Item Budget Code Description Amount Proposed
Contractor
001 2664 A 03 130000 01000 S
Replacement door savings ($15,207.00) Steel Cell
Total Amount ($15,207.00)
This change will require 0 days extension to the contract completion date. This quote is void after 30 days.
If you have any questions regarding this Potential Change Order Request, please call me at your earliest convenience.
If the above item(s) meet with your approval, please sign a copy of this letter and send back to me.
Respectfully,
CLARK CONSTRUCTION COMPANY
Chad Riehl
Project Director
Livingston County/Date