addis and zewditu project final (repaired)

Upload: tilahunthm

Post on 03-Apr-2018

232 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    1/43

    1 | P a g e

    I. Executive SummaryEthiopia is endowed with diverse agro-climatic zones that are suitable for beekeeping.

    However, the benefit the country gets from honey and beeswax export is insignificant

    compared to the huge potential it has for earning foreign exchange as well as generating

    income to many smallholder beekeepers and other actors in the subsector. Honey is

    traditionally a very precious product and plays an important role in generating cash income

    for farmers.

    The company establishes for the processing of honey with a capacity of 90 tons per annum.

    The present demand for the proposed product in Ethiopia is estimated at 4,340 tons per

    annum. The demand is expected to reach at 11,257 by the year 2021.

    The plant will create employment opportunities for 19 persons. The total investment

    requirement is estimated at about Birr 6.1million, out of which Birr 3 million is for plant and

    machinery, 1.5 million for building and civil works.

    The project is financially viable with an internal rate of return (IRR) of 30 % and a net

    present value (NPV) of birr7,199,355 birr discounted at 10%.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    2/43

    2 | P a g e

    Brief information about the project

    Name of the Licensee: . Nahom honey processingcompany

    License Type: medium scale honey production License Area: Tigray regional state, Mekele city Total area of the project 600 meter square (20x30) Annual Aggregate Production: ..81 tons Project Life: .10 years Fixed Capital Expenditure: ..... 5,900,000 birr Annual Operational Cost: ... 3,455,523 birr Pre-production Cost: 200,000 birr Depreciation Period: ..10 years for vehicles & 20 years for building Salvage Value: .....5% of Fixed Capital Expenditures Total Sales Revenue for the first year: 6,066,900 birr Income Tax 35% of the profit Net Cumulative Profit, 10 years 18,699,524 birr Pay Back Period ... 4 years Net Present Value ....7,199,355 birr Financial Internal Rate of Return ... 30 % Economic Internal rate of return 62%

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    3/43

    3 | P a g e

    II. Socio Economic and Climatic Condition

    Ethiopia is the largest country in East Africa. As a landlocked country, Ethiopia shares

    boundaries with Eritrea to the north, Kenya to the south, Somalia and Djibouti to the east and

    Sudan to the west. The majority of the population (85 percent) is rural and engaged in

    agricultural production.

    Tigray State is located in the northern part of Ethiopia, with a population of 4.5 million. 80

    percent of the population is lived in rural areas and 20 percent is lived in urban areas.

    Tigray is one of the 11th

    Regional States of the Federal Democratic Republic of Ethiopia and

    situated in the Northern part of the country. The Region has an area of 50,000 Km Square

    divided in to seven zones, Southern, south-eastern, Mekelle, Eastern, Central, South-Western

    and Western zones, and sub divided in to 46 woredas/districts. The region has also a total

    population of 4.5 million.

    Mekelle is the sixth largest city in Ethiopia and the capital of Tigray State. Mekelle enjoys a

    mild highland climate with an average temperature of 25C. The rainy season in the Mekelle

    is from June to September, while the dry season is from October to May. The average annual

    rainfall is approximately 579mm. The total population in the city of Mekelle is estimated at

    215,546. The annual population growth rate is approximately 2.6 percent

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    4/43

    4 | P a g e

    1. Introduction

    1.1 Background of the Study

    In Ethiopia, honey is traditionally a very precious product and plays an important role in

    generating cash income for farmers. It serves as raw material in the production of traditional

    alcoholic beverage, Tej. It is also widely used in different traditional medicament and ritual

    ceremonies.

    There are an estimated 10 million bee colonies in Ethiopia out of which about 7.5 million are

    confined in hives and the remaining exist in the forest and crevices.

    Ethiopia, having the highest number of bee colonies and surplus honey sources of flora, is the

    leading producer of honey and beeswax in Africa. On a world level, Ethiopia is fourth in

    beeswax and 9th

    in honey production. Honey and beeswax also play a big role in the

    economic, cultural and religious life of the people. The annual production of Ethiopian honey

    is estimated at 45,000 tons per annum and that of beeswax 3600 tons per annum. (MORAD,

    Dec. 2008)

    With regard to good opportunity to investment the project will be implemented in Mekele

    town.

    Mekeles annual population growth rate is approximately 2.6 percent per annum. People

    migrate to Mekele for better opportunities like, job, health and education. Tigray honey is

    considered to be of superior quality, and it has a moderate climate due to its highland

    position, which is favorable for honey production. The Mekelle region has a large bee

    population (about 37 thousand bee colonies; 20 percent of the Tigray total). Tigray honey has

    a special aroma that would provide a competitive advantage in niche markets

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    5/43

    5 | P a g e

    1.2 The Owner

    Name of the project; . Maerey honey Processing Company Manager (would be); w/t Addisababa worku Address; Mekele city administration, Kebele. 18, H.No, 832 Business; ..Honey processing company Form Of organization; Private limited company Registration; on progress Business license; on progress Investment permit; .. by Ethiopian investment Authority on first of May 2011

    Status of project; .New

    1.3 Objectives of the Company;

    To maximize profit

    To increase market share

    To produce quality of honey

    To create job opportunities and enable communities improve their income.

    To increase the owners capital

    1.4 Brief information about the Owners

    w/t Addisababa worku and W/ro zewditu hagos solely owns the business. Both of the

    entrepreneurs have an age old experience in the business and can always avail them self on

    fulltime basis to properly run the business. W/rt Addisababa worku is the manager of the

    company, she has enrolled at Addis Ababa University; she gets her first degree in marketing

    management . W/rt Addisababa as manager of the company; she has a well experienced and

    has experienced in managing private business. w/ro zewditu hagos has a BA degree in

    Accounting from Addis Ababa University. She has enrolled at the Addis Ababa University

    he gets her first Degree. Both W/rt Addisababa and w/ro zewditu hagos are well known in

    their respective field of specialization in their vicinity.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    6/43

    6 | P a g e

    1.5 Brief on the project

    The project will be located in Mekele city Kebele 18 in the vicinity commonly called

    Adishindihun

    The project area has suitable infrastructure such as access for transportation, and it is

    assumed that necessary utilities like electric power, water, telephone and accessible road are

    there. The raw materials like crude honey and other inputs for the production process are

    readily available in the Mekele region market.

    1.6 Credit relation

    The company has no credit commitment with Banks and other financial institutions until this

    date of report. Recognizing the importance of having its own building and premises, the

    honey processing company has negotiated and deals to finance the acquisitions from bank

    loan.

    2. Security available for loan purpose

    A, Plant building to be constructed & machinery ..3 million birr

    B, Business mortgage... 3.1 million birrTotal Birr6.1 million birr

    3, Technical Assessment

    3.1 Location of the Project

    The honey processing company is situated at Mekele city administration, Kebele 18 in

    vicinity called Adishindihun. According to the resource potential study of the region, the

    raw material is identified in most parts of the Tigray region. The honey producers of the

    region especially the eastern, southern and south eastern zones are well suited for the

    production of quality honey.

    The Tigray region is nationally considered high quality producer of honey (white & butter

    colour) when compared to other Regions of our country, and also based on the availability of

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    7/43

    7 | P a g e

    raw material (crude honey). Mekele region Produces 20% of the Tigray region honey

    production. According to the availability of infrastructure, based on the utility and market

    availability Mekele town is selected and recommended to be the location of the company

    (project).

    3.2 Project Layout

    The plant requires a total area of 600 meter square (20x30) of land out of which 300 meter

    square is built-up area which includes Processing area, raw material stock area, offices etc

    and the remaining will be parking and other areas. This building has 8 classes which are used

    for production process, store house, offices and other purpose.

    3.3, Machinery, Equipment, Furniture and Fixtures

    Maerey honey processing company will fully equip with the standard that it can serve and

    facilitate for production process. Major machineries and equipments would be installed in the

    appropriate rooms. The machinery and equipment required by the project will be procured

    from foreign sources. Fixture, furniture and other necessary office equipments like;

    Liquefier, Filter press, Evaporator, Vacuum pump, Storage/settling tank, Water circulation

    pump, Pre heating tank, Processing tank etc will also be fulfilled.

    3.4. Office Equipment and Material SuppliesThe company would supply processed packed honey and wax for beneficiaries. The

    company would also facilitate uniforms masks, gloves and other necessary materials, for the

    operational workers per need. Raw materials like crude honey and chemicals are sufficiently

    available on time for the purpose of facilitating the production.

    3.5 Other Utilities

    Electricity, water and telephone are already available in the vicinity and will be easily

    installed to the project. The raw materials (inputs) like crude honey and other inputs are

    available in the city market.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    8/43

    8 | P a g e

    3.6 Production Description

    Honey consists essentially of different sugars, predominantly glucose and fructose. Besides,

    honey contains protein, amino acids, enzymes, organic acids, mineral substances etc. The

    colour of honey varies from nearly colorless to dark brown. The flavor and aroma vary but

    are usually derived from its plant origin.

    In Ethiopia, honey is used almost everywhere for the preparation of the favorite national

    drink called Tej and also for food in the form of bread spread or as sweetener in home baking

    and medication.

    3.7 Production Process and Engineering

    3.7.1, Production Process

    Honey contains pollen, dust and air bubbles, which tend to include granulation

    (crystallization). Heating the honey to 45 C0

    to dissolve the crystals present in honey can

    retard the granulation. Filtration then removes part of pollen, foreign particles and wax.

    To prevent fermentation and to destroy yeasts, honey is heated to a temperature of 65 C0

    -70

    C0

    for specified time. Proper temperature and control and heating time is a most important

    factor in honey processing activity.(Profile of honey Processing Project 2007)

    The Process of Honey is Divided in to three Steps

    Filtration to remove wax, foreign particles after heating honey to 45 C0. It may benoted that heating up to 45 C

    0

    (below the melting point of bee wax) is required to

    decrease the viscosity of honey.

    Honey is then heated to 60 C0-65 C0 for 10 to 15 min and passed in to a falling filmevaporator. Vacuum is simultaneously applied to boil the water in honey at a lower

    temperature so that moisture is separated which can be collected separately. This

    procedure also helps in destroying yeasts.

    Cooling the honey to atmospheric temperature and storing in closed vessel for 24-48hours is the next step. Storing honey for period of 24-28 hours is necessary to allow

    air bubbles to go out. Honey is then packed and sealed immediately.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    9/43

    9 | P a g e

    3.7.2, Engineering

    A. Machinery and Equipment

    The machinery and equipment required by the project will be procured from foreign sources.

    The total cost of machinery and equipment is estimated to be Birr 3,000,000. The plant needs

    two vehicles (one pick-up and one minibus) for transportation of raw materials, finished

    products and for office activities. The total cost of the vehicles is estimated at Birr 1,000,000.

    B. Plant Capacity and Production Program

    Plant Capacity; According to the market study, the demand of honey in the year 2012 will

    be 4,774 tones, whereas this demand will grow to 11,257 Tones by the year 2017. The

    envisaged plant will have an annual production capacity of 90 tones of honey will be

    installed. Production capacity is based on a schedule of 300 working days per annum.Production Program; The project is assumed to start operation at 70% of its rated

    capacity, which reaches 90% of the capacity production, will be attained in the fourth year

    and thereafter.

    4. MARKET STUDY

    4.1 General (States Of Other Countries in Producing Honey)

    Ethiopia is 1

    st

    in Africa and 9

    th

    globally in terms of production of honey. It has also thehighest number of bee colonies and surplus honey sources of flora. Likewise, Ethiopia stands

    1st

    in Africa and 4th

    in the world in beeswax production.

    Currently, Ethiopia produces 45,000 tons of honey annually. The country also produces

    3,000 tons of beeswax annually that generated only 1.5 million dollar. Over the 97% of the

    total honey produced is marketed, of which 85% goes to the preparation of local drink Tej.

    (Ministry of rural & agricultural development (MORAD), Dec. 2010)

    Ethiopian honey and other bee products have competitive advantage over other countrys

    products in the following sense. Ethiopia has a diverse ecology and this makes it suitable to

    produce diverse honey plants in different flowering seasons. This, in turn, contributes in the

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    10/43

    10 | P a g e

    production of fresh honey throughout the year. The honey ranges from dark blue to extra

    white, which can meet the demands and preferences of different buyers.

    Its scope for diversification is also phenomenal. One can produce bee products such as table

    honey, honey for Tej, beeswax, pollen, royal jelly, and cream honey.

    The company will buy a total of63 tons of honey from local honey producers starting from

    year 1, and increasing to 81 tons in subsequent year. In the Mekele region the production of

    honey estimates about 400 ton and from the eastern and southern zones their production

    estimates about 780 tones (Bureau of rural and agricultural development 2010).

    In Tigray region there is only one honey processing company. The annual production of the

    region Estimated about 2000 tones; i.e 20 % the countries total production (MOARD,

    2009), so there is no shortage of supply in that region.

    The honey will be processed using internationally accepted modern processing and packing

    equipment all of the processed honey will be bottled and labeled for sale in local markets of

    the country.

    Pro-Poor Potential; - According to information secured from MOARD over 1.5 million

    households in the rural community are involved in beekeeping. In other words, 1 out of 10

    farmers in Ethiopia are involved in beekeeping which would make promoting the Honey and

    other bee products. Records from (MOARD2009 show that, currently, household income

    from honey production is estimated at US 66 million/annum.

    Productivity of beehives; The average yield of the traditional beehive was 12.6 kg in 2008 It

    has increased slightly to 13 kg in 2009 and increased 15 kg in 2010. It was not possible to

    compute the productivity of transitional beehive owing to the presence of only one

    transitional beehive. The productivity of modern beehive has increased from 30 kg in 2008 to

    30.5 kg in 2010.

    Socio economic aspects; The main socio-economic benefits the company is going to

    generate:

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    11/43

    11 | P a g e

    Livelihoods and food security of the area via being source of income/market for thesurrounding farmers and generation of employment,

    Enhancing the productivity of apicultural production in the region by way oftechnology transfer,

    Contributing to the regions income by way of taxes and other payments, Generates profit for the owner of the company Avails employment opportunities to about 19 employees

    4.2. Demand Analysis for honey for honey at national level

    To estimate the current effective demand of natural honey for human consumption the export

    potential and the local consumption estimated through per capita has been added.

    If we take the existing average price of honey globally which is 9 USD - 10USD/kg and if

    Ethiopia could produce its potential which is 500,000 ton per annum (according to MOARD

    documents), this would mean that the country has the potential to generate 1.25 - 1.5 billion

    USD that would make all the more rational to select the Honey and other bee products for

    promotion and development in Ethiopia. And, if we take beeswax the country has the

    potential to produce 50,000 tons (according to MOARD documents) and could generate 225

    million USD if we compute it using the current average global price of honey; i.e. 4500USD/ton. This would clearly mean that the beekeepers will have the significant part of the

    slice of the pie in terms of increasing household income for the poor farmer.

    Demand for processed honey is influenced by population growth, income, and the export

    potential. Population is growing at a rate of 3% and GDP in the past five years has increased

    by 10%.

    Table 4.2 Projected Demands for Honey in Ton at National Level

    Year Quantity

    2012 4,774

    2013 5,251

    2014 5,777

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    12/43

    12 | P a g e

    2015 6.354

    2016 6,990

    2017 7,688

    2018 8,457

    2019 9,303

    2020 10,233

    2021 11,257

    The demand projection shows that a number of plants can be established in various parts of

    our country up to absorb the market.

    At Regional level

    Mekeles annual population growth rate is approximately 2.6 percent per annum. People

    migrate to Mekele for better opportunities like, job, health and education. Tigray honey is

    considered to be of superior quality, and it has a moderate climate due to its highland

    position, which is favorable for honey production. The Mekelle region has a large bee

    population (about 37 thousand bee colonies; 20 percent of the Tigray total). Tigray honey has

    a special aroma that would provide a competitive advantage in niche markets. This means the

    region have an opportunity to invest in honey processing company.

    According to the countries average production of processed honey, currently the region hasthe ability to produceprocessed honey about 2000 tons per annum with increasing 10%

    annually. Still now the region has only one honey processing company which is called DIMA

    honey processing private limited company with the capacity of producing 120 tons/year.

    4.3. Supply Analysis

    The past five years some enterprises have been active to introduce table honey to Super

    markets in Addis Ababa and other regional states.

    The average price of the processed honey was birr 98/k.g. But currently the average price

    increases to 130 birr per kilo gram.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    13/43

    13 | P a g e

    In the past five years Productivity of traditional honeybees is very low and only an average of

    8-10 kg of honey could be cropped per hive per year. However, in areas where improved

    technology and box hives have been introduced, an average of 25 30 kg/hive/harvest has

    been recorded.

    According to CSA (2009), House Hold Income, Consumption and Expenditure survey, the

    per capital consumption of processed honey is about 60 grams. This indicates a national

    consumption of about 4,340 tons.

    The past progress of processed honey production in Ethiopia

    According to ministry of trade and industry, there are only 25 honey producer companies In

    Ethiopia, and only 1 company in Tigray. Tthe annual productivity in average increases 8%

    annually.

    Table 4.1 Number honey processing companies and their volume of production (2007-

    2010)

    Year Number of companies Their volume of Production

    2007 23 3587

    2008 24 3873

    2009 25 4208

    2010 25 4300

    Source, Ministry of Trade and Industry (MTI) 2010

    Export experience of processed honey in Ethiopia

    The price of honey in Ethiopia is increasingly becoming less competitive with that of the

    international price, especially when compared with those of China, and some Latin American

    countries. In the last four years Ethiopia exports an average amount of 321 tons/year.

    Table 6: Export of Honey and value generated (2006-2009)

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    14/43

    14 | P a g e

    Year Quantity Value in birr

    2006 250 7,500,000

    2007 280 8,960,000

    2008 312 10,606,000

    2009 442 14,832,000

    Average 321 10,474,000

    Source: MOARD 2010

    Projected supply for the next 10 Years

    Supply for honey currently estimates about 4730 tons/year, then according to MOARD, 2010

    production honey processing increases by 10% annually.

    Table 4.2 Projected supply of honey in ton

    Year Quantity

    2012 4350

    2013 4,823

    2014 5,360

    2015 5,949

    2016 6,950

    2017 7,660

    2018 8,360

    2019 8,960

    2020 9,980

    2021 11,213

    4.4 Market Prospect

    From the above tables, it can be deducted that there is a growing demand and supply gap

    national level for honey processing company. Hence there is a room and an urgent need to

    open a honey processing company expected to produce 81 tons of honey per year. Thinking

    of the minimum situation, the number of honey processing companies (production capacity

    needed

    Table 4.4 Demand & Supply Gap for Honey Processing Companies

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    15/43

    15 | P a g e

    Year Demand Supply Gap

    2012 4350 4,774 424

    2013 4,823 5,251 428

    2014 5,360 5,777 417

    2015 5,949 6,354 405

    2016 6,950 6,990 40

    2017 7,660 7,688 28

    2018 8,360 8,457 97

    2019 8960 9,303 343

    2020 9980 10,233 253

    2021 11,213 11,257 44

    According to the projection, the number of honey processing company in the country for the

    coming 10 consecutive years cannot satisfying the need of consumers.

    In general, besides the favorable situation to the existing honey processing company, the

    market prospect for honey processing is still wide open for new investors. But the question is

    that demand is one thing and purchasing power of the consumers is the other which is the

    most important factor to maximize profit. Hence accessing market would be important in this

    regard.

    4.5 Price Determination

    It would important to examine the possible level of price based on the purchasing power of

    the consumers and competitors action. The price of honey varies according to its colour,

    purity and season. The price of processed table honey at supermarkets in Ethiopia varies

    from Supermarket to supermarket. In this connection, the existing prices of similar hospitals

    are assessed for the benefit of comparison. The price level DIMA, Beza, Tadele and Tesfu

    honey processing companies are presented here;

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    16/43

    16 | P a g e

    Table 4.5 price comparison

    Name of the company Average price /kg

    Dima 130

    Beza 120

    Tadele 125

    Tesfu 110

    Total average price 125/kg

    Marketing Strategies

    Grading, labeling, quality packaging and advertising will be key elements of the marketing

    strategy. The company also wants to have an innovative approach of marketing by displaying

    its quality products at the market. And the price of processed honey will be set at 100 birr/kg

    in order to be competent.

    4.6 Capacity Utilization

    The capacity utilization is predictably assumed, in the first year, it is forecasted to be 70% of

    the full capacity and then increased by 10% each year until it reaches 95% of attainable

    capacity.

    5. Organization, Management and Manpower

    5.1. Organization and Management

    The organizational structure should be in a way that the company able to achieve its

    objectives as well as to the satisfaction of standard requirement.

    Te project will have the following main functional units:

    The major functions of the units in the organizational structure are presented in the nextsections. The detailed job descriptions, qualifications shall be worked of out during

    implementation of the project

    Under the company there will be 3 departments;

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    17/43

    17 | P a g e

    The Administrative staff, which deals in general the company shall undertake planning,

    coordination, and control of the overall activities of the project.

    The Technical staffs will hold responsibilities of running Operations and technique

    Assistant: this unit has responsible for the technical activities, purchasing and collection and

    processing and logistics operations.

    The Finance department is responsible for overall accounting and financial management of

    the company.

    5.2, Man Power

    Maerey s honey processing PLC is in the category of medium scale manufacturing industry

    known in the ministry of trade and industry (TAI) at high standard. Therefore, (TAI) criteria

    have been taken to plan man power requirement of the company. Technical workers arecategorized in their area of study (specialties) and assumed to be 6 in number.

    Administrative staff are considered as supportive personnel and expected to be 8, finance

    staff is also assumed to be 5.Therefore, the total number of workers is assumed to be about

    19 persons. In general the organizational and manpower arrangement is expected to provide

    good working atmosphere in the companys day to day activities.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    18/43

    18 | P a g e

    5.3 Organizational Structure of the company

    6. Financial Analyses

    The financial analysis of the honey processing project is based on the data presented in the

    previous sections and the following assumptions:-

    Construction period 6 month

    Source of finance 51 % equity

    49 % loan

    Bank interest 10%

    Discount cash flow 10%

    Accounts receivable 30 days 30 days

    General Manager

    Secretary

    Technical staff Administration staffFinance staff

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    19/43

    19 | P a g e

    6.1 Investment Costs and Sources of Finance

    TABLE 6.1 Investment Costs and Sources of Finance

    Total Cost Own contribution Bank loan

    No. Cost Items Amount % Amount %

    2 Building and Civil Work 1,500,000 - - 1,500,000 100

    3 Plant Machinery and Equipment 3,000,000 1,500,000 50 1,500,000 50

    4 Office Furniture and Equipment 200,000 200,000 100 - -

    5 Vehicle 1,000,000 1,000,000 100 - -

    Total initial fixed investment 5,700,000 2,700,000 47.36 3,000,000 52.63

    6 Pre-production Expenditure 200,000 200,000 100 - -

    7 Working Capital 215,900 215,900 100 - -

    Total Investment cost 6,115,900 3,115,900 51 3,000,000 49

    6.2 Results of Financial Forecasts

    Profitability

    The projected income statement revels that the project is profitable all throughout its life. The

    annual net profit of about birr932,556 in the first year will steadily increase through time

    and reaches about birr2,893,231 in year 10.

    Financial Position

    A project balance sheet of the corporation with bank additional financing shows quite good

    financial position. The net worth,birr1,032,556 at the end of first year will increase to about

    birr16,724,543 at the end of project years.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    20/43

    20 | P a g e

    Liquidity

    The cash flow projection indicates an overall liquidity of the project. The cumulative cash

    balance at the end of the project years would be about birr18,699,524.

    Financial internal rate of return and net present value

    This indicator measures the power of the project to generate return by comparing the result

    either with opportunity cost of capital or the bank interest rate. The projected discount cash

    flow has resulted in 30 % FIRR and the net present value at 10% discount rate is Birr

    7,199,355 million.

    This result indicates a very attractive rate of return and implies the capacity of the business to

    accommodate any adverse situation.

    Payback Period

    The investment cost and income statement projection are used to project the pay-back period.

    The projects initial investment will be fully recovered within 4 years.

    IRR Sensitivity Analysis

    The sensitivity analysis shows what will happen to the profitability of a project when there

    are changes in the most sensitive parameters that have an influence on the results of the

    project. Hence, it also shows the risks of the investments that have to be done.

    The factors that will cause the highest risks for the profitability of the project are: Reduction

    in Sales, Increase in Cost of Production and increase in Investment cost. The sensitivity

    analysis carried out with the effect of these three parameters on the NPV and the FIRR of the

    project is shown below.

    (1)Reduction in sales: a 5% reduction in sales will make FIRR 25%a10% reduction in sales will make FIRR 16%

    (2)Increase in operating costs: a 10% increase in production costs the FIRR becomes 26%a 20% increase in production costs the FIRR becomes 21%

    (3)Increase in investment cost: a10% increase in investment costs the IRR becomes 28%a20% increase in investment costs the IRR becomes 25%

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    21/43

    21 | P a g e

    7. Risk Analysis

    Based on the type of businesses and the request facility, the following risks are identified and

    the corresponding mitigates are given here under. The risks were drawn from the universally

    accepted lending policies.

    7.1 Characteristics (Personal Risk)

    This is the most important risk, which should be seriously considered. As to this company,

    the owner and the manager have sufficient years of work experience in both government and

    private organizations.

    7.2. Business Risk

    The fate of the business, which is the company production generally found to be dependable.

    The demand-supply analysis exhibits the need of the production of the company. Generally,

    competitors and their pricing will have a direct effect on the potential of firms trade

    opportunities. However, According to the overall demand of honey processing companies in

    Tigray, the effect of competitors in the sector would not be an immediate alarming threat for

    the coming few years.

    7.3 Collateral Risk

    Collateral risk is the second way out in case of any failure in loan repayment. In this regard,

    the company building and the machineries and the business as a whole are dependable

    securities. The debt to register able collateral (building) ratio is found to be above 1:2

    excluding machineries equipments, other fixed assets and the business mortgage part.

    Therefore, there is little risk regarding collateral.

    7.4. Construction Risk

    The construction work of the honey processing company building will be made by phase

    with the owner supervision. Hence, there is no as such serious risk related to construction

    work.

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    22/43

    22 | P a g e

    All the identified risks which are related to the university accepted lending policies, are to the

    acceptable level that keeps the lenders interest in a safe position. In addition, the quality of

    the assets of the company is dependable and the projected financial reports imply a good

    leverage condition that the company will have a capacity to pay the principal and interest

    without any problem.

    8. Summary, Conclusion

    Maerey honey processing PLC is a business organization at medium scale processing

    industry level. It is located in Tigray region in Mekele city, Kebele 18. It is registered with a

    capital of birr6.1 million

    The owners of the company are W/rt Addisababa worku and w/ro Zewditu Hagos. W/rt

    Addisababa worku is the manager of the company. She is well experienced and capable of

    running the company without any problem.

    The owners the company contributed 3.1 million birr. Now they intended to construct

    through external financing. They have agreed to borrow birr 3 million.

    The project area has suitable infrastructure such as access for transportation, and it is

    assumed that necessary utilities like electric power, water, telephone and accessible road are

    there. The raw materials like crude honey and other inputs for the production process are

    readily available in the Mekele region market.

    According to the resource potential study of the region, the raw material is identified in most

    parts of the Tigray region. The Tigray region is nationally considered high quality producer

    of honey (white & butter colour) when compared to other Regions of our country, and also

    based on the availability of raw material (crude honey).

    The company would supply processed packed honey and wax for beneficiaries. Raw

    materials like crude honey and chemicals are sufficiently available on time for the purpose of

    facilitating the production.

    One of the Social benefits of the project is creates job opportunities. The planed manpower of

    the project amounts to 19.these will create jobs that will contribute to the reducing of

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    23/43

    23 | P a g e

    alarming unemployment growth rate in the country. The employees will benefit from salaries

    and wages, while the project owner and Gov.ts shall gain revenue from the project.

    Cross cutting issues: The project has given high emphasis for the HIV/ADIS, Gender issues

    mainstreams. The project gives attention for to protecting the diseases and creates the

    awareness of gender mainstreaming by giving the chance to discuss monthly within the

    employees.

    The company establishes for the processing of honey with a capacity of 90 tons per annum.

    The present demand for the proposed product in Ethiopia is estimated at 4,340 tons per

    annum. The demand is expected to reach at 11,257 by the year 2020.

    The plant will create employment opportunities for 19 persons. The total investment

    requirement is estimated at about Birr 6.1million, out of which Birr 3 million is for plant and

    machinery, 1.5 million for building and civil works.

    The projected income statement reveals that the annual profit that the annual profit will

    increase from birr932,556 in 2005 E.C to birr 2,893,231 at the end in year 2014E.C. The

    average net income will be 1,888,952.The net worth will be about birr717,556 at the end of

    2005 E.C and reaches birr 18,584,524 at the end of projected years. The cash flow forfinancial planning indicates that the project will not face any liquidity problem. The project is

    financially viable with financial internal rate of return (FIRR) of30 % & its benefit cost ratio

    is1.298.

    Moreover, the sensitivity analysis for financial analysis exhibited that the business will be

    safe to the Extent of more than 20 % decrease of sales or20 % increase in fixed assets or

    operating costs. The initial investment can safely be recovered until the end of 4th

    year. In

    general, the projected financial results justify the acceptance of the intended business.

    The project economic analysis shows that it has a great contribution in generating national

    income. The Economic internal rate of return (EIRR) is 62% & its present value is birr

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    24/43

    24 | P a g e

    18,129,023. the benefit cost ratio is 1.589.This shows high contribution to the national

    economy besides its financial viability.

    The economic impact of project in terms of the main socio-economic benefits that company

    is going to generate Livelihoods and food security of the area via being source of

    income/market for the surrounding farmers and generation of employment, enhancing the

    productivity of honey production in the region ,can be considered as elements of contribution

    as a whole.

    Loan Needed

    Based on the overall assessments of the project, the medium processing industry requires a

    loan of birr 3,000,000 from external sources to half cover for the machineries and fully cover

    the building construction that would be located in Tigray region in Mekele city, Kebele 18.

    As the detail assessment results shows the Loan will be settled without any problem.

    Terms of Loan

    Disbursement: The loan is proposed to be transferred to the account of the companyin three phases (installment).

    Loan repaymentA, principal repayment

    The principal amount of birr 3,000,000 shall be repaid in 60 equal monthly installments.

    B, interest payment: 10 % of the loan per annum on the outstanding balance is payable on

    monthly basis together with the principal repayment amount.

    C, other bank charges: 0.5 % of the loan per annum outstanding balance payable on

    monthly basis.

    D, Grace period: 1 year from the date of loan disbursement.

    9. Assumptions Employed in the Project Financial Analysis

    9.1 Operating Costs

    Salaries . 266,640

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    25/43

    25 | P a g e

    Repair and maintenance 2 % of the fixed assets

    UTILITIES:

    Electric power and water are the two basic utilities required by the plant. When the plant

    operates at full capacity, it will require 18,025 kWh of electric power and 10,500 litter

    Furnace oil. Likewise, the plant is expected to consume 180 m3

    of water per annum.

    Estimated annual Utility cost

    Fuel and lubricant 450 liters x12x21113,400 birr Supplies 10,000 birr Insurance 1% of the fixed investment 57,000 birr and

    No. Cost Items Value in birr Repair and maintenance

    1 Building and Civil Work 1,500,000 30,0000

    2 Plant Machinery and Equipment 3,000,000 60,000

    3 Furniture and fixture 200,000 4,000

    4 Vehicles 1,000,000 20,000

    Total fixed Investment cost 5,700,000 114,000

    Annual Cost

    No. Description Measure Consumptio

    n

    Unit

    cost

    Total cost

    1 Electric power kWh 18,025 1 18,025

    2 Water M 1,800 10,800

    3 Communication 6,000

    4 Furnace oil Liter 10,500 6.5 68,250

    Total 103,075

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    26/43

    26 | P a g e

    2 % of the salaries of the employees . 4,848 birr

    Uniform and Gowns 10 gowns x 100 =100 birr and 4 uniforms for two

    guards x 300 = 1200 birr

    Annual Depreciation Straight Line Method

    Interest rate .. 10% the loan Sales tax 15% Corporate tax . 35% of net income Miscellaneous expenses6,000

    9 .2 Capacity Utilization

    Production is assumed to be commence at 70 % of installed capacity and increased by 10 %

    each year until it reaches the assumed attainable capacity, 90 %

    No. Cost Items Original values Depreciation

    rate

    Depreciated

    value per year

    1 Building and Civil Work 1,500,000 5 75,000

    2 Plant Machinery and Equipment 3,000,000 5 150,000

    3 Office Furniture and fixture 200,000 10 20,000

    4 Vehicle 1,000,000 20 50,000

    5 Pre-production Expenditure 200,000 20 40,000

    Total Investment cost 5,900,000 385,000

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    27/43

    27 | P a g e

    9.3. Revenue

    9.4 Disbursement

    At the time of building construction starts = birr 1,500,000

    At the purchasing period of the fixed assets = birr 1,500,000

    3,000,000

    Equity contribution: . Birr 3,115,900 Repayment is assumed to begin a year later as it began Grace period would be one year after first disbursement. Number of repayments 60 equal monthly repayments.

    Initial working capital 1 month salaries 22, 220 Raw material and inputs 176,610 Supplies .. 830 Utilities5,690 Fuel and lubricant .9,450 Uniforms and gowns.. 1,100

    Total. 215,900

    Man power requirement

    The proposed project will require 16 employees of whom 10 are direct production workers

    and 6 are administrative workers. The annual labour cost of the project is estimated to be

    No. Types of goods sold Income at

    100 %

    Income at 70

    %

    Income at

    80%

    Income at

    90 %

    1 Processed honey 8,100,000 5,670,000 6,480,000 7,290,000

    2 Wax 567,000 396,900 453,600 510,300

    Total 8,667,000 6,066,900 6,933,600 7,800,300

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    28/43

    28 | P a g e

    266,640 Birr. The list of employees together with the corresponding salary cost is presented

    in

    Table 9.1.10 Technical, Administrative accounting and finance staffs salaries

    Machinery, office equipments, furniture and medical equipment

    No. of persons

    Salary ( Birr)

    No. Position Monthly Annual

    1 Plant manager 1 2500 30,000

    2 Personnel 1 1200 14,400

    3 Chemist 1 1500 18,000

    4 Secretary 1 1000 12,000

    5 Purchaser 2 2*1000 24,000

    6 Sales man 1 800 9,600

    7 Casher 1 1000 12,000

    8 Quality controller 1 1200 14,400

    9 Accountant 1 1400 16,800

    10 Operator-mechanics 1 1400 16,800

    11 Production workers 3 3*1000 36,000

    12 Guards 2 2*400 9,600

    13 Cleaner 1 400 4,800

    14 Drivers 2 2*1000 24,000

    Sub Total 20,200 242,400

    Workers benefit (10% of Basic

    salary)

    19 2,020 24,240

    Grand total - 22,220 266,640

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    29/43

    29 | P a g e

    A. Machinery & Office Equipments

    No. Description

    1 Liquefier

    2 Filter press

    3 Falling film Evaporator

    4 Vacuum pump

    5 Storage/settling tank

    6 Water circulation pump

    7 Pre heating tank

    8 Processing tank

    9 Cooling tank/condenser

    10 Moisture condensing tank

    11 Honey circulation SS gear pump

    12 Insulation (Optional)

    13 Control panel, Level indicators, pressure gauges, temperature

    gauges, SS pipes and fittings.

    14 Computers and printers

    B, furniture and Fixture

    No. Description

    1 Furniture

    2 Chairs and table tables

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    30/43

    30 | P a g e

    C, Annual raw material and input requirement

    D. Building and Civil Works

    The plant requires a total of 600 m2 area of land out of which 300 m2 is built-up area which

    includes Processing area, raw material stock area, offices etc. The total cost of construction is

    estimated to be Birr1,452,000. The total cost, for a period of80 years with cost of Birr 1 per

    m2

    , is estimated at Birr 48,000. The total investment cost for land, building and civil works is

    estimated at Birr1,500,000.

    No. Description Unit of

    measure

    Qty Unit Cost in

    Birr

    Total Cost in

    Birr

    1 Crude honey kg 45,000 50 2,250,000

    2 Sanitary chemicals kg 1,200 9 10,800

    4 Glass jars pc 63,000 1 63,000

    5 Plastic containers pc 50 200 10,0008 Cartons pc 4,340 5 21,700

    10 Labels pc 45,000 0.1 4,500

    Total 2,344,400

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    31/43

    31 | P a g e

    10. Annexes for financial and economic analysis

    10.1 Financial analysis projections

    10.1.1 Total investment costs

    Description/year 0 1 2 3 4 5 6 7 8 9 10

    Total fixed investment costs 5,700,000 0 0 0 0 0 0 0 0 0 0

    Total pre production expenditures 200,000 0 0 0 0 0 0 0 0 0 0

    Increase in net working capital 0 215,900 21,590 23,749 26,124 28,736 31,610 34,771 38,248 42,073 46,2

    Total investment costs 5,900,000 215,900 21,590 23,749 26,124 28,736 31,610 34,771 38,248 42,073 46,2

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    32/43

    32 | P a g e

    10.1.2 Operating costs projection

    Description/year 1 2 3 4 5 6 7 8 9 10

    Salary and wages 266,640 293,304 322,634 354,898 390,388 409,907 430,402 451,922 474,519 498

    Cost of Goods sold 2,250,000 2,475,000 2,722,500 2,994,750 3,294,225 3,623,648 3,986,012 4,384,613 4,823,075 5,3

    Supplies 10,000 11,000 12,100 13,310 14,641 16,105 17,716 19,487 21,436 23,

    Repair and

    maintenance

    114,000 125,400 137,940 151,734 166,907 166,907 166,907 166,907 166,907 166

    Utilities 103,075 113,383 124,721 137,193 150,912 150,912 150,912 150,912 150,912 150

    Fuel and lubricant 113,400 124,740 137,214 150,935 166,029 166,029 166,029 166,029 166,029 166

    Insurance 61,848 61,848 61,848 61,848 61,848 61,848 61,848 61,848 61,848 61,

    Gowns and uniforms 2,200 2,420 2,662 2,928 3,221 3,221 3,221 3,221 3,221 3,22

    Miscellaneous 6,000 6,300 6,615 6,946 7,293 7,293 7,293 7,293 7,293 7,29

    Depreciation 385,000 385,000 385,000 385,000 385,000 345,000 345,000 345,000 345,000 345

    Financial costs 300,000 240,000 180,000 120,000 60,000 0 0 0 0 0

    Package costs 110,000 121,000 133,100 146,410 161,051 161,051 161,051 161,051 161,051 161

    Total operating costs 3,455,523 3,666,091 3,903,700 4,171,054 4,471,128 4,702,014 5,065,989 5,466,362 5,906,772 6,3

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    33/43

    33 | P a g e

    10.1.3 Revenue projection

    Description/Year 1 2 3 4 5 6 7 8 9 10

    Gross Revenue

    6,066,90

    0

    6,933,6

    00

    7,800,3

    00

    8,190,3

    15

    8,599,8

    31

    9,029,8

    22

    9,481,3

    13

    9,955,3

    79

    10,453,

    148

    10,975,

    805

    Less Sales Tax (15%) 910,035

    1,040,0

    40

    1,170,0

    45

    1,228,5

    47

    1,289,9

    75

    1,354,4

    73

    1,422,1

    97

    1,493,3

    07

    1,567,9

    72

    1,646,3

    71

    Net Revenue

    5,156,86

    5

    5,893,5

    60

    6,630,2

    55

    6,961,7

    68

    7,309,8

    56

    7,675,3

    49

    8,059,1

    16

    8,462,0

    72

    8,885,1

    76

    9,329,4

    35

    10.1.4 Cash flow for financial planning

    Description/Year

    0 1 2 3 4 5 6 7 8 9 10 Scrap 11

    Total cash inflow 6,115,900 5,372,765 5,915,150 6,654,004 6,987,892 7,338,592 7,706,959 8,093,887 8,500,320 8,927,249 9,375,715 2,250,000

    Inflow funds 6,115,900 215,900 21,590 23,749 26,124 28,736 31,610 34,771 38,248 42,073 46,280

    Inflow operation 5,156,865 5,893,560 6,630,255 6,961,768 7,309,856 7,675,349 8,059,116 8,462,072 8,885,176 9,329,435

    salvage value 2,250,000

    Total cash outflow 6,115,900 4,655,209 4,872,943 5,306,455 5,619,612 5,962,170 6,081,606 6,233,454 6,393,106 6,560,970 6,737,484 0

    Increased in fixed assets 5,900,000

    Increased in current assets 215,900 215,900 21,590 23,749 26,124 28,736 31,610 34,771 38,248 42,073 46,280

    Operating costs 3,037,163 3,334,395 3,661,334 4,020,952 4,416,515 4,437,498 4,459,604 4,482,896 4,507,440 4,533,310

    Income corporate tax 502,146 676,958 841,372 852,536 856,919 1,012,498 1,139,079 1,271,962 1,411,457 1,557,894

    financial costs 300,000 240,000 180,000 120,000 60,000 0 0 0 0 0

    loan repayment 600,000 600,000 600,000 600,000 600,000 600,000 600,000 600,000 600,000 600,000

    Surplus 717,556 1,042,208 1,347,549 1,368,280 1,376,422 1,625,353 1,860,433 2,107,215 2,366,278 2,638,231 2,250,000

    Cumulative cash balance 717,556 1,759,764 3,107,312 4,475,592 5,852,014 7,477,367 9,337,800 11,445,015 13,811,293 16,449,524 18,699,524

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    34/43

    34 | P a g e

    10.1.5 Income Statement Projection

    Description/Year 1 2 3 4 5 6 7 8 9 10

    Revenue 5,156,865 5,893,560 6,630,255 6,961,768 7,309,856 7,675,349 8,059,116 8,462,072 8,885,176 9,32

    Less Operating

    costs 3,422,163 3,719,395 4,046,334 4,405,952 4,801,515 4,782,498 4,804,604 4,827,896 4,852,440 4,87

    Operational

    margin 1,734,702 2,174,166 2,583,921 2,555,816 2,508,341 2,892,851 3,254,512 3,634,177 4,032,735 4,45

    In % of Revenue 34 37 39 37 34 38 40 43 45 48

    Financial Cost 300,000 240,000 180,000 120,000 60,000 0 0 0 0 0

    Gross Profit from

    Operation 1,434,702 1,934,166 2,403,921 2,435,816 2,448,341 2,892,851 3,254,512 3,634,177 4,032,735 4,45

    In % of Revenue 28 33 36 35 33 38 40 43 45 48

    Income (Corporate

    Tax) 502,146 676,958 841,372 852,536 856,919 1,012,498 1,139,079 1,271,962 1,411,457 1,55

    Net Profit 932,556 1,257,208 1,562,549 1,583,280 1,591,422 1,880,353 2,115,433 2,362,215 2,621,278 2,893

    Net worth 717,556 1,974,764 3,537,312 5,120,592 6,712,014 8,592,367 10,707,800 13,070,015 15,691,293 18,58

    In % of Revenue 18 21 24 23 22 24 26 28 30 31

    Ratios (%):

    Net Profit to equity 30 31 36 34 34 40 42 45 48 50

    Net profit to Net

    Worth 130 64 44 31 24 22 20 18 17 16

    Net Profit +

    Interest to

    Investment 20 24 28 28 27 30 34 37 41 45

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    35/43

    35 | P a g e

    10.1.6 Cash Flow Projection for Discounting

    Description/Year 0 1 2 3 4 5 6 7 8 9 10 Scr

    otal cash inflow 0 5,156,865 5,893,560 6,630,255 6,961,768 7,309,856 7,675,349 8,059,116 8,462,072 8,885,176 9,329,435 2,25

    nflow operation 0 5,156,865 5,893,560 6,630,255 6,961,768 7,309,856 7,675,349 8,059,116 8,462,072 8,885,176 9,329,435

    alvage value 0 0 0 0 0 0 0 0 0 0 0 2,25

    otal cash outflow 6,115,900 3,755,209 4,032,943 4,526,455 4,899,612 5,302,170 5,481,606 5,633,454 5,793,106 5,960,970 6,137,484

    ncreased in fixedssets 6,115,900 0 0 0 0 0 0 0 0 0 0

    ncreased in net work

    apital

    215,900

    21,590 23,749 26,124 28,736 31,610 34,771 38,248 42,073 46,280

    Operating costs 0 3,037,163 3,334,395 3,661,334 4,020,952 4,416,515 4,437,498 4,459,604 4,482,896 4,507,440 4,533,310

    ncome (corporate)

    ax 0 502,146 676,958 841,372 852,536 856,919 1,012,498 1,139,079 1,271,962 1,411,457 1,557,894

    Net Cash Flow 6,115,900 1,401,656 1,860,618 2,103,800 2,062,156 2,007,686 2,193,743 2,425,663 2,668,967 2,924,206 3,191,951 2,25

    umulative net cash

    ow 6,115,900 4,714,244 2,853,627 -749,827 1,312,329 3,320,015 5,513,758 7,939,421 10,608,387 13,532,593 16,724,543 18,9

    Net Present Value

    At 10% 7,199,355

    nternal Rate Of

    eturn 30%

    ay Back Period 4 years

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    36/43

    36 | P a g e

    10.1.7 Sensitive analysis

    Description IRR

    Sales Decreased by 5 % 25

    Sales Decreased by 10% 16

    Operating Costs increased by

    10 % 26

    Operating Costs increased by

    20% 21

    Fixed Assets Increased by

    10 % 28

    Fixed Assets Increased by 25

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    37/43

    37 | P a g e

    10.2 Economic analysis

    10.2.1 Initial investment costs

    Description financial costs Conversion factor economic price

    Building and Civil Work 1,500,000 0.610 915,000

    Plant Machinery and Equipment 3,000,000 1.019 3,057,000

    Office Furniture and Equipment 200,000 1.000 200,000

    Vehicle 1,000,000 0.824 824,000

    Total fixed investment costs 5,700,000 4,996,000

    Pre-production Expenditure 200,000 1.000 200,000

    Working Capital

    Salaries

    For skilled labour 20,900 0.810 16,929

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    38/43

    38 | P a g e

    For unskilled labour 1,320 0.390 515

    Raw material and inputs 176,610 1.000 176,610

    Supplies 830 0.880 730

    Utilities 1,897 1.430 2,713

    Fuel oil 3,793 0.866 3,285

    Fuel and lubricant 9,450 1.050 9,923

    Uniforms and gowns 1,100 0.698 768

    Total working capital 215,900 211,472

    Grand total investment costs 6,115,900 5,407,472

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    39/43

    39 | P a g e

    10.2.2 Operating Costs

    Description Financial costs

    Conversion

    factor economic price

    Salaries

    For skilled labour 250,800 0.810 203,148

    For unskilled labour 15,840 0.390 6,178

    Cost of Goods sold(crude honey) 2,250,000 1.00 2,250,00

    Supplies 10,000 1.00 10,000

    Repair and maintenance 114,000 1.000 114,000

    Utility 34,825 1.430 49,800

    Fuel oil 68,250 0.866 59,105

    Fuel and lubricant 113,400 1.050 119,070

    Uniform and Gowns 2,200 0.698 1,536

    Miscellaneous 6,000 1.000 6,000

    Sanitary Chemicals 10,800 0.88 9,504

    Plastic & Glass jars 63,000 0.863 54,369

    Plastic Containers 10,000 0.863 8,630

    Cartons 21,700 0.883 19,161

    Labels 4,500 0.883 3,974

    Total operating costs 2,975,315 2,914,473

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    40/43

    40 | P a g e

    10.2.3 Revenue projection

    Types of goods

    sold 1 2 3

    4 5 6 7 8 9

    Processed

    honey and bee

    wax

    6,066,900 6,673,590 7,340,949 8,075,044 8,478,796.10 8,902,735.90 9,347,872.69 9,815,266.33 10,306,029.65 10,82

    10.2.4 Operating cost projection

    Salaries 1 2 3 4 5 6 7 8 9 1

    For skilled labour 203,148 223,463 245,809 270,390 283,909 298,105 313,010 328,661 345,094 3

    For unskilled labour 6,178 6,796 7,475 8,223 8,634 9,066 9,519 9,995 10,495 1

    Cost of Goods sold 2,250,000 2,475,000 2,722,500 2,994,750 3,144,488 3,301,712 3,466,797 3,640,137 3,822,144 4

    Supplies 10,000 10,000 10,000 10,000 10,500 11,025 11,576 12,155 12,763 1

    Repair and maintenance 114,000 125,400 137,940 151,734 159,321 167,287 175,651 184,434 193,655 2

    Utility 49,800 49,800 54,780 60,258 63,271 66,434 69,756 73,244 76,906 8

    Fuel oil 59,105 65,016 71,517 78,669 82,602 86,732 91,069 95,622 100,403 1

    Fuel and lubricant 119,070 130,977 144,075 158,482 166,406 174,727 183,463 192,636 202,268 2

    Uniform and Gowns 1,534 1,687 1,856 2,042 2,144 2,251 2,364 2,482 2,606 2

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    41/43

    41 | P a g e

    Miscellaneous 6,000 6,600 7,260 7,986 8,385 8,805 9,245 9,707 10,192 1

    Sanitary chemicals 9,504 10,454 11,500 12,650 13,282 13,946 14,644 15,376 16,145 1

    Plastic & glass jars 54,369 59,806 65,786 72,365 75,983 79,783 83,772 87,960 92,358 9

    Plastic containers 8,630 9,493 10,442 11,487 12,061 12,664 13,297 13,962 14,660 1

    Cartons 19,161 21,077 23,185 25,503 26,778 28,117 29,523 30,999 32,549 3

    Labels 3,974 4,371 4,809 5,289 5,554 5,832 6,123 6,429 6,751 7

    Total operating costs 2,914,473 3,199,940 3,518,934 3,869,828 4,063,319 4,266,485 4,479,809 4,703,800 4,938,990 5

    10.2.5 Cash Flow Projection for Discounting

    Description/Ye

    ar 0 1 2 3 4 5 6 7 8 9 10 11

    Total cash

    inflow

    0 6,066,90

    0

    6,673,5

    90

    7,340,9

    49

    8,075,0

    44

    8,478,796 8,902,73

    6

    9,347,8

    73

    9,815,2

    66

    10,306,0

    30

    10,821,

    331

    2

    Inflow

    operation

    0 6,066,90

    0

    6,673,5

    90

    7,340,9

    49

    8,075,0

    44

    8,478,796 8,902,73

    6

    9,347,8

    73

    9,815,2

    66

    10,306,0

    30

    10,821,

    331

    Salvage value 0 0 0 0 0 0 0 0 0 0 0 2,

    Total cash

    outflow

    5,407,472 3,125,94

    5

    3,497,3

    68

    3,847,1

    04

    4,231,8

    15

    4,267,080 4,480,43

    4

    4,704,4

    56

    4,939,6

    78

    5,186,66

    2

    5,445,9

    96

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    42/43

    42 | P a g e

    Increased in

    fixed assets

    5,407,472 0 0 0 0 0 0 0 0 0 0

    Increased in net

    working capital

    0 211,472 291,44

    7

    320,59

    2

    352,65

    1

    193,958 203,656 213,839 224,531 235,757 247,54

    5

    Operating costs 0 2,914,47

    3

    3,205,9

    20

    3,526,5

    12

    3,879,1

    64

    4,073,122 4,276,77

    8

    4,490,6

    17

    4,715,1

    48

    4,950,90

    5

    5,185,9

    39

    Net Cash Flow (5,407,472) 2,940,95

    5

    3,176,2

    22

    3,493,8

    45

    3,843,2

    29

    4,211,716 4,422,30

    2

    4,643,4

    17

    4,875,5

    88

    5,119,36

    7

    5,375,3

    36

    2,

    cumulative net

    cash flow

    (5,407,472) (2,466,5

    17)

    709,70

    5

    4,203,5

    50

    8,046,7

    79

    12,258,49

    5

    16,680,7

    97

    21,324,

    214

    26,199,

    802

    31,319,1

    69

    36,694,

    505

    38

    Net Present

    Value At 10%

    18,129,0

    23

    Internal Rate

    Of return

    62%

    Pay Back

    Period

  • 7/28/2019 Addis and Zewditu Project Final (Repaired)

    43/43