addendum 2018 transmission capability assessment for ... · the aeso will publish a new...
TRANSCRIPT
The Alberta Electric System Operator (AESO) is committed to providing guidance to market participants and stakeholders on where transmission capability is available, and optimal areas to seek connection to Alberta’s grid. In 2018, the first comprehensive Transmission Capability Assessment for Renewables Integration report (2018 Assessment) was published, along with a complementary interactive map, to help address these specific information needs.
This report is an Addendum to the 2018 Assessment. It provides an update on where transmission system capability is available in central east and southern Alberta, subsequent to the December 2018 announcement of the results of the most recent Renewable Electricity Program (REP) auctions. A total of 763 megawatts (MW) of wind generation was acquired through REP Rounds 2 and 3, with projects from both Rounds scheduled to be in commercial operation by June 30, 2021.
The Addendum to the 2018 Transmission Capability Assessment for Renewables Integration report is an update on the transmission system’s integration capability following the allocation of generation through Rounds 2 and 3 of the Renewable Electricity Program.
1.0 Executive summary
11.0 Executive summary
Addendum - 2018 Transmission Capability Assessment for Renewables Integration
HIGHLIGHTS
�� If the transmission system is optimized, there is an upper limit of 470 MW of remaining integration capability in the south.
�� Optimal distribution of the 470 MW of integration capability in the south is 340 MW in the southwest and 130 MW in the southeast.
�� To optimize the use of the existing transmission system through southwest and southeast Alberta, the AESO assumes the connection of new generation to 240 kilovolt (kV) collector systems.
�� When the transmission system is optimized, capability in the central east area is zero; however, a small amount of generation can still be integrated into this area, recognizing this could decrease overall system capability.
�� The 2019 Transmission Capability Assessment for Renewables Integration report will be published by the end of the first quarter (Q1) of 2019. The 2019 Assessment will include the impact of the near-term transmission system developments for renewables integration, in addition to the REP Rounds 2 and 3 generation allocations included in this Addendum.
22.0 Study overview
REP Rounds 2 and 3 built off the tremendous success of Round 1 by demonstrating significant competitive interest from local and international investors eager to develop renewable generation projects in Alberta.
2.0 Study overview
Addendum - 2018 Transmission Capability Assessment for Renewables Integration
BACKGROUND
Renewable Electricity Program
The Alberta electric system’s capability to integrate new generation is evolving as REP competitions progress. This initiative is successfully encouraging the development of large-scale renewable electricity generation to meet the province’s target of having 30 per cent of electricity produced by renewable generation by 2030 (the 30 by 30 target).
The 30 per cent target requires the addition of approximately 5,000 MW of electricity generation from renewable resources, and assumes that wind and solar are the most economical resources that will develop. Emissions from coal-generated electricity will also be phased out by 2030.
The results of REP Round 1 were announced in December 2017, exceeding the original 400 MW target, with nearly 600 MW of renewable generation scheduled to come online by the end of 2019. The next two REP Rounds also exceeded expectations, with a December 2018 announcement confirming that an additional 763 MW of wind generation will be delivered through Rounds 2 and 3 (363 MW and 400 MW respectively). Projects from both Rounds are scheduled to come online by June 30, 2021.
Capability Assessment
The inaugural Transmission Capability Assessment for Renewables Integration report was published in June 2018, providing an update to the Renewable Generation Integration Plan included in the AESO’s 2017 Long-term Transmission Plan (2017 LTP). It looks forward to 2021 and identifies transmission system capability following the REP Round 1 announcement.
The 2018 Assessment and subsequent integration capability studies are specific to central east and southern Alberta because it is anticipated that the majority of renewable generation will continue to develop in these wind and solar resource-rich areas.
ADDENDUM OBJECTIVE AND SCOPE
This report is an Addendum to the 2018 Assessment, and provides an update on transmission system integration capability following the allocation of generation awarded through REP Rounds 2 and 3.
The scope includes an evaluation of the overall renewables integration capability in the central east and southern Alberta study region (Figure 1) in 2021, when all projects from the contracts awarded in REP Rounds 1 through 3 are in service.
�� REP Round 1: 600 MW of renewable energy is scheduled to come online by the end of 2019.
�� REP Rounds 2 and 3: approximately 763 MW of renewable energy is scheduled to come online by June 30, 2021.
Figure 1: Study region
Addendum - 2018 Transmission Capability Assessment for Renewables Integration
Calgary
Lethbridge
MedicineHat
EdmontonLloydminster
WINDYFLATS138S
BIGSTONE86S
SAUNDERSLAKE 289S
NEWELL2075S
WESTBROOKS
28S
WAREJUNCTION
132S
BATTLERIVER757S
EASTCROSSFIELD 64S
SHEERNESS807S
JENNER275S
BOWMANTON244S
LANFINE959S
PEMUKAN932S
HANSMANLAKE 650S
CYPRESS562S
ALBERTANEWSPRINT
122S
BRAZEAU62S
CHERHILL338S
NORTHBARRHEAD69S
WOLFCREEK288S
NEVIS766S
CASSILS324S
LANGDON102S
PEIGAN59S
CLOVER BAR987S
HALKIRK615S
CASTLE ROCKRIDGE 205S
JANET74S
REDDEER
63S
TRAVERS554S
COYOTELAKE 963S
CORDEL755S
WILLESDENGREEN68S
SC1266S
HAZELWOOD287S
LETHBRIDGENORTH 370S
BLACKSPRINGRIDGE 485S
MILO356S
DEERLAND13S
OAKLAND946S
AMOCOEMPRESS
163S
SAGITAWAH77S
BENALTO17S
BEDDINGTONSS-162
NORTHCALDER
37S
PICTUREBUTTE 120S
WHITLA251S
SUNDANCE310P
FIDLER312S
SS-65
FOOTHILLS237S
GAETZ87S
HEARTLAND12S
TINCHEBRAY972S
PAINTEARTH863S
NILREM574S
METISKOW648S
ANDERSON801S
KEEPHILLS320P
SARCEE42S
WABAMUN19S
CROSSINGS511S
EASTCALGARY 5S
ELLERSLIE89S
GOOSELAKE 103S
BENNETT520S
SHEPARDSS-25
EDP Renewables Canada Ltd.Sharp Hills Wind Farm
248.4 MW
Enel Green PowerCanada, Inc.
Riverview Wind Farm115 MW
Capital Power CorporationWhitla Wind
201.6 MW
Enel Green Power Canada, Inc.Phase 2 of Castle RockRidge Wind Power Plant30.6 MW
EDF Renewables Canada Inc.Cypress Wind Power Project
201.6 MW
Potentia Renewables Inc.Stirling Wind Project113 MW
Potentia Renewables Inc.Jenner Wind Power Project 271.4 MW
TransAlta CorporationWindrise Wind207 MW
Potentia Renewables Inc.Jenner Wind Power Project122.4 MW
Capstone InfrastructureCorporationBuffalo Atlee 1/2/348.3 MW
Substation
REP Round1 ProjectsREP Round2 ProjectsREP Round3 Projects
240 kV Line
Central East0 MW CapabilitySoutheast130 MW CapabilitySouthwest340 MW Capability
Capability shown for each study arearepresents the optimal scenario forrenewable generation integration.
Optimal project connections will be viathe 240 kV system shown in the map.
32.0 Study overview
43.0 Assumptions
If the transmission system is optimized, renewable generation integration capability in southern Alberta is 470 MW, with 340 MW in the southwest and 130 MW in the southeast.
3.0 Assumptions
Addendum - 2018 Transmission Capability Assessment for Renewables Integration
STUDY ASSUMPTIONS
The following system model and assumptions were used to assess the capability of the existing transmission system:
�� Central east, southwest and southeast areas were studied.
�� Limiting scenarios identified in the 2018 Assessment were assumed to remain unchanged.
�� The same base cases from the 2018 Assessment were used, with the system topology updated to include REP Rounds 2 and 3.
�� Future renewable generation:
- is assumed not to be located in central east Alberta, based on the conclusion in the 2018 Assessment that this is not the optimal location for new generation integration (the findings are still considered to be valid)
- is assumed to be connected to 240 kV substations in order to efficiently use existing transmission capability and minimize impact on local constraints
COMPARISON WITH 2018 ASSESSMENT
�� The 2018 Assessment identified 1,200 MW of remaining capability in the south and central east areas after the addition of capability awarded in REP Round 1, based on transmission system optimization.
�� After integrating REP Rounds 2 and 3, there is 470 MW of remaining capability in southwest and southeast Alberta (340 MW and 130 MW respectively).
�� Figure 2 shows the remaining capability identified in the 2018 Assessment compared to this Addendum.
Addendum - 2018 Transmission Capability Assessment for Renewables Integration
53.0 Assumptions
INTERACTIVE MAP
The Optimal Integration Capability interactive map that was published with the 2018 Assessment has been updated. Features on the map include:
�� A customizable basemap, allowing the user to choose between multiple map backgrounds including satellite imagery.
�� A measuring tool allowing the user to calculate distances or areas on the map, such as the distance from a potential project location to the nearest transmission infrastructure.
�� The study region (central east, southwest and southeast areas) and updated capability for each area.
�� 240 kV transmission lines and substations.
�� The location of projects selected for REP Rounds 1, 2 and 3.
The interactive map can be found at aeso.ca following the path: Grid > Long-term Transmission Plan.
Figure 2: Comparison of remaining capability between 2018 Assessment and 2019 Addendum
64.0 Next Steps
Transmission Capability Assessment for Renewables Integration reports and the complementary interactive map are key resources for current and prospective market participants, providing direction on where capability is available, and optimal areas to site projects and connect to the system.
4.0 Next Steps
Addendum - 2018 Transmission Capability Assessment for Renewables Integration
The AESO will publish a new Transmission Capability Assessment for Renewables Integration report by the end of Q1 2019. The updated 2019 Assessment will include the impact of the near-term transmission system developments for renewables integration, in addition to the generation allocations through REP Rounds 2 and 3 included in this Addendum.
The three projects identified in the AESO’s 2017 LTP to enable Alberta’s 30 by 30 renewables target include:
�� The Provost−to−Edgerton and Nilrem−to−Vermilion transmission development in the central east area is anticipated to be in service by 2022. This project’s addition of incremental capability to the transmission system is planned to follow the June 2021 commencement of commercial operation from REP Rounds 2 and 3.
�� The planned Central East Transfer-out and Chapel Rock–Pincher Creek transmission developments, in the central east and southwest areas respectively, are the most effective transfer-out transmission development projects. Both projects will be staged with milestones that introduce flexibility to enable the addition of incremental transfer capability as renewables generation development evolves.