  • ACTIVITY LIST

    KEADUE WWTP UPGRADE WORKS

    KMCF ENGINEERING

    DUBLIN ROAD

    ATHLONE

    2014

  • 1

    1.0 Activity List

    The Following table outlines the Activity list for the project. This document provides a

    comprehensive list of all activities on the project. This list includes a scope of work description

    for each activity, with sufficient detail for a clear understanding of what is required to be

    carried out.

  • 2

    Activity List

    Project: Keadue upgrade Works Date:

    Activity

    ID No.

    Activity Name Description of Work Responsibility

    1 Tendering This activity includes the preparation

    of documents required to be

    included as part of the project

    tender packages

    Contractor

    1.1 Publish Project Details on E-Tenders

    This activity involves summiting

    project details online for relevant

    parties interested

    Contractor

    1.2 Expressions of

    Interest

    This activity involves

    Detailing/document all parties

    interested in the project

    Contractor

    1.3 Review Tender Pack This activity involves reviewing all

    necessary components of tender

    pack

    Contractor

    1.4 Preparation of BoQ This activity involves Preparing a bill

    of quantities for project

    Contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    2 Procurement This activity involves documenting

    project purchasing decisions,

    specifying the approach, and

    identifying potential sellers.

    Contractor

    2.1 Feasibility The feasibility study is an evaluation

    and analysis of the potential of a

    proposed project which is based on

    extensive investigation and research

    to support the process of decision

    making.

    Contractor

  • 3

    2.1.1 WWTP Selection His activity involves selecting an

    appropriate Waste water treatment

    plant(WWTP) based on chosen P.E

    size and cost

    Contractor

    2.1.2 Site Layouts This activity involves preparing site

    layout drawings for project

    Contractor

    2.1.3 Permits This activity involves contacting

    relevant authorities to obtain

    necessary permits i.e. discharge

    permits etc

    Contractor

    2.1.4 Contractor

    Submissions

    This activity involves detailing all

    submissions received from the

    contractor

    Contractor

    2.1.5 Material

    Submissions

    This activity involves detailing all

    relevant material submissions for

    the project

    Contractor

    2.1.6 Plant Submissions This activity involves detailing all

    relevant plant submissions for the

    project

    Contractor

    2.1.7 Health & Safety (H

    & S)Audits

    This activity involves preparing a

    health and safety audit for the

    continued development and

    implementation of H & S throughout

    the project

    Contractor

    2.1.8 Human resources Human resources is required to

    distinguish roles and responsibilities

    for the project and to organize

    organizational charts and a staffing

    Management Plan

    Contractor

    2.1.9 Procurement

    Completion

    This activity involves bringing the

    project procurement to a

    completion

    Contractor

  • 4

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    2.2 Contact Suppliers This activity involves contacting

    suppliers to order materials

    Contractor

    2.2.1 WWTP Supplier This activity involves ordering

    WWTP systems/materials

    Contractor

    2.2.2 Concrete Supplier This activity involves ordering

    concrete supplies.

    Contractor

    2.2.3 Building Materials

    Supplier

    This activity involves ordering

    building materials supplies

    Contractor

    2.2.4 Plant Hire This activity involves hiring plant

    machinery for site

    Contractor

    2.2.5 Submit Tender This activity involves submitting for

    tendering

    Contractor

    2.2.6 Tender Awarded This activity mean rewarding

    successful contractor with project

    Contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    3 Preliminaries Preliminaries is required to

    determine the facts or progress of

    the project

    Contractor

    3.1 Insurance Insurance is the equitable transfer of

    the risk of a loss, from one entity to

    another in exchange for payment. It

    is a form of risk management

    primarily used to hedge against the

    risk of a contingent, uncertain loss.

    Contractor

    3.2 Employers' Liability

    Insurance

    Coverage against common law

    liability of an employer for accidents

    to employees, as distinguished from

    liability imposed by a workers'

    compensation law

    Contractor

  • 5

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4 Construction This activity involves the

    construction for Keadue upgrade

    works

    Relevant sub-

    contractor

    4.1 Commencing on

    site

    Arrive on site to begin construction

    of Keadue upgrade works

    Relevant sub-

    contractor

    4.1.1 Site office This activity involves setting up site

    office on site for duration of the

    project

    Relevant sub-

    contractor

    4.1.2 Office Equipment This activity involves setting up all

    necessary office equipment for

    duration of project

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.2 Mobilization Activation of a contractor's physical

    and manpower resources for

    transfer to a construction site until

    the completion of the contract

    Relevant sub-

    contractor

    4.2.1 Traffic

    Management

    This activity involves setting up a

    traffic management plan to control

    and direct traffic in a safe manner

    during construction of the project

    Relevant sub-

    contractor

    4.2.2 Site Safety

    Induction

    Site induction communicates

    essential information regarding the

    site, the working methods and

    health and safety management.

    Relevant sub-

    contractor

    4.2.3 Road Brushing This activity involves removal of

    necessary brush from roadside

    ditches for the safety of the

    traveling public

    Relevant sub-

    contractor

  • 6

    4.2.4 Site Clearing Plant

    & Equipment

    This activity involves hiring of

    necessary plant equipment for

    clearing of construction site

    Relevant sub-

    contractor

    4.2.5 Excavation

    Equipment

    This activity involves hiring of

    necessary excavation equipment for

    clearing of construction site

    Relevant sub-

    contractor

    4.2.6 Paving Equipment This activity involves hiring of

    necessary paving equipment for

    clearing of construction site

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.3 Temporary Works This activity involves setting up of

    temporary works

    Relevant sub-

    contractor

    4.3.1 Site Security

    Fencing

    This activity involves setting up of

    fencing around the site for public

    safety

    Relevant sub-

    contractor

    4.3.2 Car Parking This activity involves construction of

    temporary car park for onsite for

    duration of project

    Relevant sub-

    contractor

    4.3.3 Site Entrance /

    Access

    This activity involves providing site

    entrance/access for to construction

    site

    Relevant sub-

    contractor

    4.3.4 Temporary Site

    Services

    This activity involves setting site up

    temporary site services for duration

    of project i.e. plumbing and electrics

    Relevant sub-

    contractor

  • 7

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.4 Ground Works This activity involves setting up of Ground Works

    Relevant sub-contractor

    4.4.1 Site Clearing This activity involves clearing the

    site and getting it ready for

    construction

    Relevant sub-

    contractor

    4.4.2 Strip Top Soil This activity involves the stripping

    back of top soil

    Relevant sub-

    contractor

    4.4.3 Top Soil Storage This activity involves the storing of

    the top soil removed

    Relevant sub-

    contractor

    4.4.4 Trial Holes This activity involves trial holes been

    dug to determine the geology and

    water table of the site

    Relevant sub-

    contractor

    4.4.5 Set Out Site This activity involves setting out the

    site is to stake out reference points

    and markers that will guide the

    construction of new structures such

    as roads or buildings

    Relevant sub-

    contractor

    4.4.6 Place Access Road

    Sub-Base

    This activity involves laying the sub

    base and providing and access road

    to the site

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.5 Control room This activity involves setting up of control room

    Relevant sub-contractor

    4.5.1 Setting out This activity involves setting out the

    site to stake out reference points

    and markers that will guide the

    construction of the Control room

    Relevant sub-

    contractor

  • 8

    4.5.2 Excavate for

    Foundations/Services

    This activity involves excavating for

    foundations/ services for the

    control room

    Relevant sub-

    contractor

    4.5.3 Poor Foundations The activity involves the pouring of

    concrete for the foundations

    Relevant sub-

    contractor

    4.5.4 Block Work This activity involves the laying of

    blocks by a competent builder

    Relevant sub-

    contractor

    4.5.5 Roof This activity involves the building of

    the roof by a competent carpenter

    Relevant sub-

    contractor

    4.5.6 Finishing This activity involves the finishing

    of the control room

    Relevant sub-

    contractor

    4.5.7 Wiring This activity involves the wiring of

    the control room by a competent

    electrician

    Relevant sub-

    contractor

    4.5.8 Control Panels (ICS) This activity involves the installing

    of control panels for the WWTP

    Relevant sub-

    contractor

    4.5.9 Re - Furbish This activity involves the

    refurbishing of the control room

    Relevant sub-

    contractor

    4.5.10 Windows This activity involves the

    placing/fitting of the windows

    Relevant sub-

    contractor

    4.5.11 Painting This activity involves the painting of

    the control room

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6 New WWTP

    infrastructure

    4.6.1 Preliminary

    4.6.1.1 Excavate for Sub-

    base

    This activity involves the excavating

    the sub base for the new WWTP

    Relevant sub-

    contractor

    4.6.1.2 Place Hardcore

    Sub-base

    The activity involves the placing of

    the hard core

    Relevant sub-

    contractor

    4.6.1.3 Erect Formwork This activity involves the erecting of

    the formwork for the WWTP

    Relevant sub-

    contractor

  • 9

    4.6.1.4 Place

    Reinforcement

    This activity involves the placing of

    steel reinforcement

    Relevant sub-

    contractor

    4.6.1.5 Pour Concrete Base This activity involves the pouring of

    the concrete for the base

    Relevant sub-

    contractor

    4.6.1.6 Install Screens This activity involves the installing of

    the screen for the new WWTP

    Relevant sub-

    contractor

    4.6.1.7 Install Venturi Flow

    Meter

    This activity involves the installing of

    the venture meter for the WWTP

    Relevant sub-

    contractor

    4.6.1.8 Install Automatic

    Sampler

    This activity involves the installing of

    the sampler for the new WWTP

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6.2 Primary Relevant sub-

    contractor

    4.6.2.1 Clarifier This activity involves the placing of

    the clarifier on site

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6.3 Secondary Relevant sub-

    contractor

    4.6.3.1 Aerator This activity involves the placing of

    the Aerator on site

    Relevant sub-

    contractor

    4.6.3.2 Clarifier This activity involves the placing of

    the Clarifier on site

    Relevant sub-

    contractor

    4.6.3.3 Chemical This activity involves the introducing

    of the chemical dosage

    Relevant sub-

    contractor

  • 10

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6.4 Tertiary Relevant sub-

    contractor

    4.6.4.1 Inspection of Reed

    Beds

    This activity involves the inspection

    of the reed beds on site

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6.5 Storm Tank Relevant sub-contractor

    4.6.5.1 Preparation of Sub-base

    This activity involves the preparing he sub base for the pouring of concrete

    Relevant sub-contractor

    4.6.5.2 Pouring Concrete Base

    This activity involves the pouring of the concrete base

    Relevant sub-contractor

    4.6.5.3 Tank Installation This activity involves instillation the

    storm tank

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6.6 Package System Relevant sub-

    contractor

    4.6.6.1 Excavate for Sub-

    base

    This activity involves the excavating

    of the sub base

    Relevant sub-

    contractor

    4.6.6.2 Place Hardcore

    Sub-base

    This activity involves the placing of

    the hardcore base

    Relevant sub-

    contractor

    4.6.6.3 Erect Formwork This activity involves the erecting of

    the formwork

    Relevant sub-

    contractor

  • 11

    4.6.6.4 Place

    Reinforcement

    This activity involves the placing of

    the steel reinforcement

    Relevant sub-

    contractor

    4.6.6.5 Pour Concrete Sub-

    Base

    This activity involves the pouring of

    the concrete

    Relevant sub-

    contractor

    4.6.6.6 Strike Formwork His activity involves the striking of

    the formwork

    Relevant sub-

    contractor

    4.6.6.7 Install BMS units This activity involves the installing of

    the new package WWTP

    Relevant sub-

    contractor

    4.6.6.8 Connect new

    infrastructure

    This activity involves the connecting

    of all pipes into the package WWTP

    Relevant sub-

    contractor

    4.6.6.9 Commission This activity involves the

    commissioning of the new package

    WWTP

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.6.7 Reinstatement Relevant sub-

    contractor

    4.6.7.1 Placing Concrete

    Kerbs

    This activity involves the placing of

    the concrete kerbs around the site

    Relevant sub-

    contractor

    4.6.7.2 Pedestrian Paths This activity involves the placing

    /laying out of pedestrian foot paths

    Relevant sub-

    contractor

    4.6.7.3 Replacing Top Soil

    This activity involves the replacing of

    the top soil around the site

    Relevant sub-

    contractor

    4.6.7.4 Seeding This activity involves the reseeding

    of trees and plants around the site

    Relevant sub-

    contractor

    4.6.7.5 Bitumen layer to

    Road

    This activity involves the laying of

    the bitumen layer for the road

    Relevant sub-

    contractor

  • 12

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.7 Sewer Connection Relevant sub-

    contractor

    4.7.1 Set Out Proposed

    Pipe Network

    This activity involves the setting out

    of the proposed pipe network

    Relevant sub-

    contractor

    4.7.2 Excavate for, and

    Construct Manhole

    1

    This activity involves the

    constructing for a new manhole

    (MH1)

    Relevant sub-

    contractor

    4.7.3 Excavate & Lay

    Sewer Pipe A - B

    This activity involves the excavating

    and the laying of pipe work from A -

    B

    Relevant sub-

    contractor

    4.7.4 Excavate for, and

    Construct Manhole

    2

    This activity involves the

    constructing for a new manhole

    (MH2)

    Relevant sub-

    contractor

    4.7.5 Excavate & Lay

    Sewer Pipe B - C

    This activity involves the excavating

    and the laying of pipe work from B -

    C

    Relevant sub-

    contractor

    4.7.6 Excavate for, and

    Construct Manhole

    3

    This activity involves the

    constructing for a new manhole

    (MH3)

    Relevant sub-

    contractor

    4.7.7 Excavate & Lay

    Sewer Pipe C - D

    This activity involves the excavating

    and the laying of pipe work from C -

    D

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.8 Pump Chamber Relevant sub-

    contractor

    4.8.1 Excavate for Sub-

    base

    This activity involves the excavating

    of the sub base

    Relevant sub-

    contractor

    4.8.2 Place Hardcore

    Sub-base

    This activity involves the placing of

    the hard core sub base

    Relevant sub-

    contractor

  • 13

    4.8.3 Erect Formwork This activity involves the erecting of

    the formwork

    Relevant sub-

    contractor

    4.8.4 Place

    Reinforcement

    This activity involves the placing of

    the steel reinforcement

    Relevant sub-

    contractor

    4.8.5 Pour Concrete Sub-

    Base

    This activity involves the pouring of

    the concrete sub base

    Relevant sub-

    contractor

    4.8.6 Strike Formwork This activity involves the striking of

    the formwork

    Relevant sub-

    contractor

    4.8.7 Backfill Surrounds This activity involves the backfilling

    in the surrounds of the pump

    chamber

    Relevant sub-

    contractor

    4.8.8 Install Pump This activity involves the installing of

    the pump

    Relevant sub-

    contractor

    4.8.9 Commission This activity involves the

    commissioning of the pump house

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.9. Demolition Works Relevant sub-

    contractor

    4.9.1 Demolish Existing This activity involves the

    demolishing of the existing WWTP

    Relevant sub-

    contractor

    4.9.2 Remove from Site This activity involves the removing

    of the old WWTP off site

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    4.10 Site Finishing Relevant sub-

    contractor

    4.10.1 landscaping This activity involves the landscaping

    of the site

    Relevant sub-

    contractor

  • 14

    4.10.2 Planting This activity involves the planting of

    new plants on the site

    Relevant sub-

    contractor

    4.10.3 Fencing This activity involves the fencing

    around the site

    Relevant sub-

    contractor

    4.10.4 Painting This activity involves the painting of

    facilities around the site

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    5 Testing Relevant sub-

    contractor

    5.1 Air Testing Sewer

    Network

    This activity involves the testing of

    the sewer network to ensure all

    connections pipes are working

    Relevant sub-

    contractor

    5.2 Testing BMS Unit This activity involves the testing of

    the Package BMS system to insure

    its working

    Relevant sub-

    contractor

    5.3 Testing Pump This activity involves the testing of

    the pumps to insure there in

    working order

    Relevant sub-

    contractor

    Activity List

    Project: Keadue upgrade Works Date:

    Activity ID No.

    Activity Name Description of Work Responsibility

    6 Completion Relevant sub-

    contractor

    6.1 Final Inspection This activity involves the final

    inspection of all work carried out

    onsite

    Relevant sub-

    contractor

    6.2 Condition Survey of

    Roads and Paths

    This activity involves a survey of all

    roads and paths to insure there up

    to required standard

    Relevant sub-

    contractor

  • 15

    6.3 CCTV Survey of

    Pipework

    This activity involves the testing of

    the pipework to insure there in

    working order

    Relevant sub-

    contractor

    6.4 Demobilisation of

    Site

    This activity involves the removing

    of site offices and plant machinery

    off site

    Relevant sub-

    contractor

    6.5 As Constructed

    Drawings

    This activity involves insuring site is

    of drawings specified

    Relevant sub-

    contractor

    6.6 Safety File

    Handover

    This activity involves the handing

    over of all files

    Relevant sub-

    Contractor