Download - Activity List
-
ACTIVITY LIST
KEADUE WWTP UPGRADE WORKS
KMCF ENGINEERING
DUBLIN ROAD
ATHLONE
2014
-
1
1.0 Activity List
The Following table outlines the Activity list for the project. This document provides a
comprehensive list of all activities on the project. This list includes a scope of work description
for each activity, with sufficient detail for a clear understanding of what is required to be
carried out.
-
2
Activity List
Project: Keadue upgrade Works Date:
Activity
ID No.
Activity Name Description of Work Responsibility
1 Tendering This activity includes the preparation
of documents required to be
included as part of the project
tender packages
Contractor
1.1 Publish Project Details on E-Tenders
This activity involves summiting
project details online for relevant
parties interested
Contractor
1.2 Expressions of
Interest
This activity involves
Detailing/document all parties
interested in the project
Contractor
1.3 Review Tender Pack This activity involves reviewing all
necessary components of tender
pack
Contractor
1.4 Preparation of BoQ This activity involves Preparing a bill
of quantities for project
Contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
2 Procurement This activity involves documenting
project purchasing decisions,
specifying the approach, and
identifying potential sellers.
Contractor
2.1 Feasibility The feasibility study is an evaluation
and analysis of the potential of a
proposed project which is based on
extensive investigation and research
to support the process of decision
making.
Contractor
-
3
2.1.1 WWTP Selection His activity involves selecting an
appropriate Waste water treatment
plant(WWTP) based on chosen P.E
size and cost
Contractor
2.1.2 Site Layouts This activity involves preparing site
layout drawings for project
Contractor
2.1.3 Permits This activity involves contacting
relevant authorities to obtain
necessary permits i.e. discharge
permits etc
Contractor
2.1.4 Contractor
Submissions
This activity involves detailing all
submissions received from the
contractor
Contractor
2.1.5 Material
Submissions
This activity involves detailing all
relevant material submissions for
the project
Contractor
2.1.6 Plant Submissions This activity involves detailing all
relevant plant submissions for the
project
Contractor
2.1.7 Health & Safety (H
& S)Audits
This activity involves preparing a
health and safety audit for the
continued development and
implementation of H & S throughout
the project
Contractor
2.1.8 Human resources Human resources is required to
distinguish roles and responsibilities
for the project and to organize
organizational charts and a staffing
Management Plan
Contractor
2.1.9 Procurement
Completion
This activity involves bringing the
project procurement to a
completion
Contractor
-
4
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
2.2 Contact Suppliers This activity involves contacting
suppliers to order materials
Contractor
2.2.1 WWTP Supplier This activity involves ordering
WWTP systems/materials
Contractor
2.2.2 Concrete Supplier This activity involves ordering
concrete supplies.
Contractor
2.2.3 Building Materials
Supplier
This activity involves ordering
building materials supplies
Contractor
2.2.4 Plant Hire This activity involves hiring plant
machinery for site
Contractor
2.2.5 Submit Tender This activity involves submitting for
tendering
Contractor
2.2.6 Tender Awarded This activity mean rewarding
successful contractor with project
Contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
3 Preliminaries Preliminaries is required to
determine the facts or progress of
the project
Contractor
3.1 Insurance Insurance is the equitable transfer of
the risk of a loss, from one entity to
another in exchange for payment. It
is a form of risk management
primarily used to hedge against the
risk of a contingent, uncertain loss.
Contractor
3.2 Employers' Liability
Insurance
Coverage against common law
liability of an employer for accidents
to employees, as distinguished from
liability imposed by a workers'
compensation law
Contractor
-
5
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4 Construction This activity involves the
construction for Keadue upgrade
works
Relevant sub-
contractor
4.1 Commencing on
site
Arrive on site to begin construction
of Keadue upgrade works
Relevant sub-
contractor
4.1.1 Site office This activity involves setting up site
office on site for duration of the
project
Relevant sub-
contractor
4.1.2 Office Equipment This activity involves setting up all
necessary office equipment for
duration of project
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.2 Mobilization Activation of a contractor's physical
and manpower resources for
transfer to a construction site until
the completion of the contract
Relevant sub-
contractor
4.2.1 Traffic
Management
This activity involves setting up a
traffic management plan to control
and direct traffic in a safe manner
during construction of the project
Relevant sub-
contractor
4.2.2 Site Safety
Induction
Site induction communicates
essential information regarding the
site, the working methods and
health and safety management.
Relevant sub-
contractor
4.2.3 Road Brushing This activity involves removal of
necessary brush from roadside
ditches for the safety of the
traveling public
Relevant sub-
contractor
-
6
4.2.4 Site Clearing Plant
& Equipment
This activity involves hiring of
necessary plant equipment for
clearing of construction site
Relevant sub-
contractor
4.2.5 Excavation
Equipment
This activity involves hiring of
necessary excavation equipment for
clearing of construction site
Relevant sub-
contractor
4.2.6 Paving Equipment This activity involves hiring of
necessary paving equipment for
clearing of construction site
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.3 Temporary Works This activity involves setting up of
temporary works
Relevant sub-
contractor
4.3.1 Site Security
Fencing
This activity involves setting up of
fencing around the site for public
safety
Relevant sub-
contractor
4.3.2 Car Parking This activity involves construction of
temporary car park for onsite for
duration of project
Relevant sub-
contractor
4.3.3 Site Entrance /
Access
This activity involves providing site
entrance/access for to construction
site
Relevant sub-
contractor
4.3.4 Temporary Site
Services
This activity involves setting site up
temporary site services for duration
of project i.e. plumbing and electrics
Relevant sub-
contractor
-
7
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.4 Ground Works This activity involves setting up of Ground Works
Relevant sub-contractor
4.4.1 Site Clearing This activity involves clearing the
site and getting it ready for
construction
Relevant sub-
contractor
4.4.2 Strip Top Soil This activity involves the stripping
back of top soil
Relevant sub-
contractor
4.4.3 Top Soil Storage This activity involves the storing of
the top soil removed
Relevant sub-
contractor
4.4.4 Trial Holes This activity involves trial holes been
dug to determine the geology and
water table of the site
Relevant sub-
contractor
4.4.5 Set Out Site This activity involves setting out the
site is to stake out reference points
and markers that will guide the
construction of new structures such
as roads or buildings
Relevant sub-
contractor
4.4.6 Place Access Road
Sub-Base
This activity involves laying the sub
base and providing and access road
to the site
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.5 Control room This activity involves setting up of control room
Relevant sub-contractor
4.5.1 Setting out This activity involves setting out the
site to stake out reference points
and markers that will guide the
construction of the Control room
Relevant sub-
contractor
-
8
4.5.2 Excavate for
Foundations/Services
This activity involves excavating for
foundations/ services for the
control room
Relevant sub-
contractor
4.5.3 Poor Foundations The activity involves the pouring of
concrete for the foundations
Relevant sub-
contractor
4.5.4 Block Work This activity involves the laying of
blocks by a competent builder
Relevant sub-
contractor
4.5.5 Roof This activity involves the building of
the roof by a competent carpenter
Relevant sub-
contractor
4.5.6 Finishing This activity involves the finishing
of the control room
Relevant sub-
contractor
4.5.7 Wiring This activity involves the wiring of
the control room by a competent
electrician
Relevant sub-
contractor
4.5.8 Control Panels (ICS) This activity involves the installing
of control panels for the WWTP
Relevant sub-
contractor
4.5.9 Re - Furbish This activity involves the
refurbishing of the control room
Relevant sub-
contractor
4.5.10 Windows This activity involves the
placing/fitting of the windows
Relevant sub-
contractor
4.5.11 Painting This activity involves the painting of
the control room
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6 New WWTP
infrastructure
4.6.1 Preliminary
4.6.1.1 Excavate for Sub-
base
This activity involves the excavating
the sub base for the new WWTP
Relevant sub-
contractor
4.6.1.2 Place Hardcore
Sub-base
The activity involves the placing of
the hard core
Relevant sub-
contractor
4.6.1.3 Erect Formwork This activity involves the erecting of
the formwork for the WWTP
Relevant sub-
contractor
-
9
4.6.1.4 Place
Reinforcement
This activity involves the placing of
steel reinforcement
Relevant sub-
contractor
4.6.1.5 Pour Concrete Base This activity involves the pouring of
the concrete for the base
Relevant sub-
contractor
4.6.1.6 Install Screens This activity involves the installing of
the screen for the new WWTP
Relevant sub-
contractor
4.6.1.7 Install Venturi Flow
Meter
This activity involves the installing of
the venture meter for the WWTP
Relevant sub-
contractor
4.6.1.8 Install Automatic
Sampler
This activity involves the installing of
the sampler for the new WWTP
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6.2 Primary Relevant sub-
contractor
4.6.2.1 Clarifier This activity involves the placing of
the clarifier on site
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6.3 Secondary Relevant sub-
contractor
4.6.3.1 Aerator This activity involves the placing of
the Aerator on site
Relevant sub-
contractor
4.6.3.2 Clarifier This activity involves the placing of
the Clarifier on site
Relevant sub-
contractor
4.6.3.3 Chemical This activity involves the introducing
of the chemical dosage
Relevant sub-
contractor
-
10
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6.4 Tertiary Relevant sub-
contractor
4.6.4.1 Inspection of Reed
Beds
This activity involves the inspection
of the reed beds on site
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6.5 Storm Tank Relevant sub-contractor
4.6.5.1 Preparation of Sub-base
This activity involves the preparing he sub base for the pouring of concrete
Relevant sub-contractor
4.6.5.2 Pouring Concrete Base
This activity involves the pouring of the concrete base
Relevant sub-contractor
4.6.5.3 Tank Installation This activity involves instillation the
storm tank
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6.6 Package System Relevant sub-
contractor
4.6.6.1 Excavate for Sub-
base
This activity involves the excavating
of the sub base
Relevant sub-
contractor
4.6.6.2 Place Hardcore
Sub-base
This activity involves the placing of
the hardcore base
Relevant sub-
contractor
4.6.6.3 Erect Formwork This activity involves the erecting of
the formwork
Relevant sub-
contractor
-
11
4.6.6.4 Place
Reinforcement
This activity involves the placing of
the steel reinforcement
Relevant sub-
contractor
4.6.6.5 Pour Concrete Sub-
Base
This activity involves the pouring of
the concrete
Relevant sub-
contractor
4.6.6.6 Strike Formwork His activity involves the striking of
the formwork
Relevant sub-
contractor
4.6.6.7 Install BMS units This activity involves the installing of
the new package WWTP
Relevant sub-
contractor
4.6.6.8 Connect new
infrastructure
This activity involves the connecting
of all pipes into the package WWTP
Relevant sub-
contractor
4.6.6.9 Commission This activity involves the
commissioning of the new package
WWTP
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.6.7 Reinstatement Relevant sub-
contractor
4.6.7.1 Placing Concrete
Kerbs
This activity involves the placing of
the concrete kerbs around the site
Relevant sub-
contractor
4.6.7.2 Pedestrian Paths This activity involves the placing
/laying out of pedestrian foot paths
Relevant sub-
contractor
4.6.7.3 Replacing Top Soil
This activity involves the replacing of
the top soil around the site
Relevant sub-
contractor
4.6.7.4 Seeding This activity involves the reseeding
of trees and plants around the site
Relevant sub-
contractor
4.6.7.5 Bitumen layer to
Road
This activity involves the laying of
the bitumen layer for the road
Relevant sub-
contractor
-
12
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.7 Sewer Connection Relevant sub-
contractor
4.7.1 Set Out Proposed
Pipe Network
This activity involves the setting out
of the proposed pipe network
Relevant sub-
contractor
4.7.2 Excavate for, and
Construct Manhole
1
This activity involves the
constructing for a new manhole
(MH1)
Relevant sub-
contractor
4.7.3 Excavate & Lay
Sewer Pipe A - B
This activity involves the excavating
and the laying of pipe work from A -
B
Relevant sub-
contractor
4.7.4 Excavate for, and
Construct Manhole
2
This activity involves the
constructing for a new manhole
(MH2)
Relevant sub-
contractor
4.7.5 Excavate & Lay
Sewer Pipe B - C
This activity involves the excavating
and the laying of pipe work from B -
C
Relevant sub-
contractor
4.7.6 Excavate for, and
Construct Manhole
3
This activity involves the
constructing for a new manhole
(MH3)
Relevant sub-
contractor
4.7.7 Excavate & Lay
Sewer Pipe C - D
This activity involves the excavating
and the laying of pipe work from C -
D
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.8 Pump Chamber Relevant sub-
contractor
4.8.1 Excavate for Sub-
base
This activity involves the excavating
of the sub base
Relevant sub-
contractor
4.8.2 Place Hardcore
Sub-base
This activity involves the placing of
the hard core sub base
Relevant sub-
contractor
-
13
4.8.3 Erect Formwork This activity involves the erecting of
the formwork
Relevant sub-
contractor
4.8.4 Place
Reinforcement
This activity involves the placing of
the steel reinforcement
Relevant sub-
contractor
4.8.5 Pour Concrete Sub-
Base
This activity involves the pouring of
the concrete sub base
Relevant sub-
contractor
4.8.6 Strike Formwork This activity involves the striking of
the formwork
Relevant sub-
contractor
4.8.7 Backfill Surrounds This activity involves the backfilling
in the surrounds of the pump
chamber
Relevant sub-
contractor
4.8.8 Install Pump This activity involves the installing of
the pump
Relevant sub-
contractor
4.8.9 Commission This activity involves the
commissioning of the pump house
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.9. Demolition Works Relevant sub-
contractor
4.9.1 Demolish Existing This activity involves the
demolishing of the existing WWTP
Relevant sub-
contractor
4.9.2 Remove from Site This activity involves the removing
of the old WWTP off site
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
4.10 Site Finishing Relevant sub-
contractor
4.10.1 landscaping This activity involves the landscaping
of the site
Relevant sub-
contractor
-
14
4.10.2 Planting This activity involves the planting of
new plants on the site
Relevant sub-
contractor
4.10.3 Fencing This activity involves the fencing
around the site
Relevant sub-
contractor
4.10.4 Painting This activity involves the painting of
facilities around the site
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
5 Testing Relevant sub-
contractor
5.1 Air Testing Sewer
Network
This activity involves the testing of
the sewer network to ensure all
connections pipes are working
Relevant sub-
contractor
5.2 Testing BMS Unit This activity involves the testing of
the Package BMS system to insure
its working
Relevant sub-
contractor
5.3 Testing Pump This activity involves the testing of
the pumps to insure there in
working order
Relevant sub-
contractor
Activity List
Project: Keadue upgrade Works Date:
Activity ID No.
Activity Name Description of Work Responsibility
6 Completion Relevant sub-
contractor
6.1 Final Inspection This activity involves the final
inspection of all work carried out
onsite
Relevant sub-
contractor
6.2 Condition Survey of
Roads and Paths
This activity involves a survey of all
roads and paths to insure there up
to required standard
Relevant sub-
contractor
-
15
6.3 CCTV Survey of
Pipework
This activity involves the testing of
the pipework to insure there in
working order
Relevant sub-
contractor
6.4 Demobilisation of
Site
This activity involves the removing
of site offices and plant machinery
off site
Relevant sub-
contractor
6.5 As Constructed
Drawings
This activity involves insuring site is
of drawings specified
Relevant sub-
contractor
6.6 Safety File
Handover
This activity involves the handing
over of all files
Relevant sub-
Contractor