MATTHEW WARR PROFESSIONAL PORTFOLIO PROJECT OVERVIEW No.3 RESUME/PORTFOLIO | CONFIDENTIAL This 80,000 ft2 office space refurbishment project was characterised by an extremely condensed and therefore intense preconstruction phase. From a standing start Trinity had 3 weeks to complete the design and procurement process before commencing works on site. This involved designing the base M&E systems, taking Motorola’s comments on board and making the appropriate adjustments, procuring all the plant and equipment and getting all the subcontractors on board. While classed as a refurbishment project, for Trinity it was effectively a new build because 99% of the building services were new, the exception being some retained perimeter lighting. Project Title MOTOROLA, TRILOGY BUILDING, SWINDON Client HXRUK (KP) Ltd M&E Consultant Wye Solutions Main Contractor Blenheim House Construction Ltd Value M&E Works £2,000,000 Duration February 2010 – July 2010 (6months) Contract Type JCT 05 Design and Build The mechanical works comprised a big VRV air conditioning system with Heat Recovery Units for fresh air ventilation, cooling systems for the Data Centre and Communications room and the usual HCW domestic supply and sanitaryware. Key electrical services included a new MCB distribution board supplying power to the new mechanical plant and small power to the office accommodation. There were data and comms electrical installations together with brand new lighting schemes, a new fire alarm system, security access control, intruder alarms and CCTV and a large UPS system as well. The project was originally programmed over 5 months but due to the requirements of the new tenant, Motorola, the project had to be fasttracked to enable handover 3 weeks earlier than the original targeted completion date.

Upload: matthew-warr

Post on 23-Jan-2018

95 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 3. Brochure Trilogy Swindon

MATTHEW WARR PROFESSIONAL PORTFOLIO PROJECT OVERVIEW No.3 

RESUME/PORTFOLIO | CONFIDENTIAL 

     

 This  80,000  ft2  office  space  refurbishment  project  was  characterised  by  an  extremely  condensed  and  therefore intense pre‐construction phase. From a standing start Trinity had 3 weeks to complete the design and procurement process  before  commencing  works  on  site.  This  involved  designing  the  base  M&E  systems,  taking  Motorola’s comments on board and making the appropriate adjustments, procuring all the plant and equipment and getting all the  sub‐contractors on board.   While  classed  as  a  refurbishment project,  for Trinity  it was effectively  a new build because 99% of the building services were new, the exception being some retained perimeter lighting.     

   

Project Title    MOTOROLA, TRILOGY BUILDING, SWINDON 

Client    HXRUK (KP) Ltd 

M&E Consultant    Wye  Solutions 

Main Contractor    Blenheim House Construction Ltd 

Value M&E Works    £2,000,000 

Duration    February 2010 – July 2010 (6months) 

Contract Type    JCT 05 Design and Build 

The mechanical works comprised a big VRV air conditioning system with Heat Recovery Units  for  fresh  air  ventilation,  cooling systems  for  the  Data  Centre  and Communications  room and  the usual HCW domestic  supply  and  sanitaryware.    Key electrical  services  included  a  new  MCB distribution  board  supplying  power  to  the new mechanical plant  and  small power  to the  office  accommodation.  There  were data  and  comms  electrical  installations together with brand new  lighting schemes, a  new  fire  alarm  system,  security  access control,  intruder  alarms  and  CCTV  and  a large UPS  system as well. The project was originally  programmed  over  5 months  but due to the requirements of the new tenant, Motorola,  the  project  had  to  be  fast‐tracked to enable handover 3 weeks earlier than the original targeted completion date.