Project SLOPE1

WP 6 – System integration

Technical Meeting 19-21 Jan 15

Page 2: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Agenda

• Work Package Goals• Tasks and Roles Overview• Timeline• Deliverables• Task Details• Risks and Mitigation Actions• Open Discussion

Page 3: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Work Package Goals

“Achieve a complete integration of the different components that are part of the SLOPE platform”

WP 2 ComponentsForest information

collection and analysisCOA,FLY,GT,ITE,TRE

WP 3 ComponentsIntegration of novel

intelligent harvesting systemsCNR,GRE,KES,ITE,MHG

WP 5 ComponentsForest information

system developmentCNR,TRE,BO

WP6 Integration (All Partners)

SLOPE PLATFORM

Page 4: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Work Package Key aspects

• Build a working system

• Ready for pilots and on the field testing

• Based on 3 integration steps

• Technical and Economical Analysis • Overall solution costs• Social impacts• Environmental impacts

T.6.2

T.6.3

T.6.4

Page 5: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Tasks and Roles

• T.6.1 Definition of integration Steps• Task leader: GRAPHITECH; Participants: MHG, FLY, ITENE

• T.6.2 First Integration - Forest inventory & harvesting systems• Task leader: GRAPHITECH; Participants: MHG, FLY, GRE, TRE, ITENE

• T.6.3 Second integration – Forest management• Task leader: MHG; Participants: CNR, BOKU, GRE, TRE, ITENE

• T.6.4 – Third integration - System validation• Task leader: GRAPHITECH; Participants: KESLA, MHG, BOKU, FLY, GRE, TRE, ITENE

• T.6.5 – Scientific Coordination• Task leader: GRAPHITECH;

Page 6: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Timeline & Deliverable & Milestone & Project Meetings

2014 2015 2016

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36

WP 6 System Integration

T.6.1 Definition of the integration steps

T.6.2 First Integration – Forest inventory & harvesting systems

T.6.3 Second integration – Forest management

T.6.4 Third integration -System validation

T.6.5 Scientific coordination

D.6.01 System Integration and Validation Plan

D.6.021 System Integration Report ID.6.041 SLOPE System Techno-Economic Evaluation Report I

D.6.022 System Integration Report IID.6.042 SLOPE System Techno-Economic Evaluation Report II

D.6.023 System Integration Report IIID.6.043 SLOPE System Techno-Economic Evaluation Report III

MS04 SLOPE System Integration Planning is completed

MS05 Forest Inventory and Intelligent Harvesting system integration

MS07 Forest Management system integrated

MS09 System testing endingD.6.03 SLOPE System Field Trials Readiness Assessment Report

Page 7: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Deliverables

• D. 6.01 System Integration and Validation Plan (M13)• Integration and validation procedures and timeline to validate the SLOPE system• Based on the use cases in WP1

• D.6.03 SLOPE System Field Trials Readiness Assessment Report• Assessment of the initial user experience and recommendations for the field trials

operations. • Guidance and system operation manual for the Field Trials operators

Page 8: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Deliverables

• D. 6.021 System Integration Report I (M23): • Integration test and validation concept procedures results • Assessment of the initial user experience• Recommendations for field trials operations

• D 6.022 System Integration Report II: • Integration test and validation concept procedures results (rev. 2)• Assessment of the initial user experience (rev. 2)• Recommendations for field trials operations (rev. 2)

• D 6.023 System Integration Report III: • Integration test and validation concept procedures results (rev. 3)• Assessment of the initial user experience (rev. 3)• Recommendations for field trials operations (rev. 3)

Page 9: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Deliverables

• D6.041 SLOPE System Techno-Economic Evaluation Report I (M23): • Analysis of technical and economical aspects of SLOPE system • Current practices and the potential known alternatives comparison• Estimation phase

• D6.042 SLOPE System Techno-Economic Evaluation Report II: • Analysis of technical and economical aspects of SLOPE system • Current practices and the potential known alternatives comparison• Preliminary results phase

• D6.043 SLOPE System Techno-Economic Evaluation Report III: • Analysis of technical and economical aspects of SLOPE system • Current practices and the potential known alternatives comparison• Final results phase

Page 10: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Deliverables Progress

40

0 0 0 0 0 0 00

10

20

30

40

50

60

70

80

90

100

D.6.

01 S

yste

min

tegr

atio

n an

dva

lidat

ion

plan

D.6.

021

Syst

emin

tegr

atio

n re

port

1

D.6.

022

Syst

emin

tegr

atio

n re

port

2

D.6.

023

Syst

emin

tegr

atio

n re

port

3

D.6.

3 Sy

stem

fiel

dtr

ials

read

ines

sas

sess

men

t rep

ort

D.6.

041

Tech

no-

econ

omic

eval

uatio

n re

port

1

D.6.

042

Tech

no-

econ

omic

eval

uatio

n re

port

2

D.6.

043

Tech

no-

econ

omic

eval

uatio

n re

port

3

Deliverables Status

Page 11: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Tasks Details

Page 12: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Task 6.1

Definition of the Integration Steps• Leader: Graphitech• Participants: MHG, FLY, ITENE

Objectives• Define the integration steps• Define validation concepts

• Functionalities• Communication

Page 13: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Integration StrategyWaterfall + agile like approach• 3 major loops of integration and lab validation• Agile works well with small groups for specific tasks• 3 big integration steps and 3-4 loops of iterative evolution• Bug fixing and integration at high frequency• Parallel support for real use case pilots

T.6.2

T.6.3

T.6.4

Page 14: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Integration strategy - 2For each main integration step:• Definition of the involved components• Timeline with integration steps, milestones, telcos, days for

testing• One testing scenario based on the use case• Involved actors recognition• Definition of HW and SW• Functional requirements• Non-functional requirements• Testing approach

Page 15: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Involved Components

GeoServer<<infrastructure>>

PostGIS DB<<datastore>>XML

File System<<datastore>>

JDBC

<<requires>>

HTTP

Preprocessing Server<<infrastructure>>

<<requires>>

<<requires>>

HTTP

2D Renderer

3D Renderer

Network System

Network System

2D Monitoring planning

3D Harvesting Planning

Menu Interface<<GUI>>

Menu Interface<<GUI>>

Interface

Interface

Interface

Interface

Graphitech Services

WebServer<<infrastructure>>

PostGIS DB<<datastore>>

<<requires>>

REST

FlyBy Services

FTP Server<<infrastructure>>

FTP

<<requires>>

Treemetrics Services

SLOPE FIS <<LifeRay>>

Tracking Clients

Web Service<<infrastructure>>

Forest information DB<<datastore>>

JDBC<<requires>>

REST

XML

Handheld RFID UHF Reader

<<Device>>

Android Phone / Tablet

<<Device>>

BT

Truck with control unit <<Device>>

DB Forest model View

<<GUI>>

2D Portlet<<GUI>>

3D Portlet<<GUI>>

Interface

Interface

Biomass Manager<<GUI>>

WSRP

Interface

MHG Services

Web Service<<infrastructure>>

Biomass DB<<datastore>>

JDBC<<requires>>REST

XML

Surveys Clients <<PCs>>

Aerial Imageries Client

On-Field Lidar Scan Client

HTTP

FTP

Web Service<<infrastructure>>

Forest Information Model DB

<<datastore>>

JDBC <<requires>>

REST

XML

SLOPE FIS (Hosted By MHG)

Cable Crane / Hervester Head<<Device>>

Page 16: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Timeline

Tentative integration timeline drafted• Defines integration steps at high level• One Telco every 2 weeks (eventually increased or reduced)• One/two testing days per month (incremental report writing)• One/two days for the reporting of the results

Page 17: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Testing scenario definition

• Testing scenario based on the use case

• Involved actors

• HW & SW Requirements

• Functional Requirements

• Non-functional Requirements

• Define a threshold to be reached

Page 18: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Testing

• Execute the testing scenario• Evaluate the functional requirements• Evaluate the non-functional requirements• Check the results against a threshold• Fill a report

• Bugs and other issues to be notified to the partners in charge

Page 19: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Deliverables and Expectations

Reports:• D.6.01 System Integration and Validation Plan (M13)

• Contribution from the involved partners for:• functional and non functional requirements• Testing scenarios revision• Draft reports as deliverable annexes

Page 20: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Task 6.2

First Integration: forest inventory & harvesting systems• Leader: Graphitech• Participants: MHG, FLY, TRE, GRE, ITENE

Page 21: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Objectives

• Integration between HW providers and SW developer

• Collected data available among HW and SW providers (FIM)

• Communication between HW sensors and RFID tracking

• Estimation of• Components and operations costs• Productivity and reliability

Page 22: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Deliverables and Expectations

Reports:• D.6.021 System Integration report 1 (M23)

• Preliminary layout as annex of D.6.01• D.6.041 System techno economic evaluation report 1

• Preliminary layout as annex of D.6.01

• Integrated working prototype ready to be shown at mid-termproject review

• Collaboration from CNR for a first schema of a system techno-economic evaluation report

• Regular Telcos on a Monthly basis• First Telco at Task’s start

Page 23: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Risks

• Data Formats • DB Model (T.1.5 and T.5.1)• Reduce Harmonization/adaptation• Images and other data formats

• Unreliable Services• Hardware interfaces with software

• RFID• BT

• Inability to reproduce planned test field/conditions

• Component testing takes time!

Page 24: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Mitigating Actions

• Exhaustive System Architecture• T.1.5 and Parallel Session of Tomorrow

• Exhaustive Requirement analysis• D.1.1 and D.1.2

• Common data model• T.1.4

• Communication• Skype (Small Group, no desktop sharing)• WebEx (up to 25 persons with desktop sharing)• Monthly Basis

Page 25: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Open Discussion

Page 26: 2nd Technical Meeting - WP6

Technical Meeting 19-21 Jan 15

Thank you for your attention