29 july 1996 - virginia tech

226
MANAGEMENT INFORMATION SYSTEM INFRASTRUCTURE FOR A PROPOSED HIGHWAY MANAGEMENT SYSTEM FOR THE VIRGINIA DEPARTMENT OF TRANSPORTATION By Steven T. Smayda Thesis submitted to the Faculty of the Virginia Polytechnic Institute and State University in partial fulfillment of the requirements for the degree of MASTER OF SCIENCE IN CIVIL ENGINEERING APPROVED Jesus M. de la Garza, Ph. D., Chair R. Donald Drew, Ph. D. Michael C. Vorster, Ph. D. 29 July 1996 Blacksburg, Virginia

Upload: others

Post on 22-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

MANAGEMENT INFORMATION SYSTEM INFRASTRUCTURE FOR A PROPOSED HIGHWAY MANAGEMENT SYSTEM FOR THE VIRGINIA

DEPARTMENT OF TRANSPORTATION

By

Steven T. Smayda

Thesis submitted to the Faculty of the

Virginia Polytechnic Institute and State

University in partial fulfillment of the

requirements for the degree of

MASTER OF SCIENCE

IN

CIVIL ENGINEERING

APPROVED

Jesus M. de la Garza, Ph. D., Chair

R. Donald Drew, Ph. D. Michael C. Vorster, Ph. D.

29 July 1996

Blacksburg, Virginia

LD 5655 355 1946

S639 Go

Virginia Polytechnic Institute and State University

Abstract

A MANAGEMENT INFORMATION SYSTEM

INFRASTRUCTURE FOR A PROPOSED HIGHWAY

MANAGEMENT SYSTEM

by Steven T. Smayda

Chairperson of the Supervisory Committee: Professor Jesus M. de la Garza Department of Civil Engineering

The purpose of this work was to develop an infrastructure for a Management

Information Svstem concurrent with the development of a System Dynamics model

for VDOT’s Highway Management System and the Interface between the two.

Specifics include identifying the detailed source for each parameter or developing

recommendations for future data collections. The MIS is to be in both a hard (paper)

and a soft (paperless) format. The soft copy will be based on the hypertext format and

be Windows compatible.

Parameters to be researched were identified from the model simulation code and causal

diagrams. These were then grouped into common themes and/or sources, assigned a

target date for research, and discussed with key personnel at VDOT with regards to

their validity within the model and from a data collection stand-point. Those

parameters identified as not obtainable, due to gaps within VDOT’s database system

were then estimated using engineering judgment in conjunction with key personnel at

VDOT. Obtainable data was gathered from VDOT’s databases and annual reports as

well as other sources. Key VDOT personnel then reviewed all gathered data for its

soundness. Researched parameters were then written-up with any assumptions,

definitions, and sources outlined along with the current value based on the 1995 data.

Although VDOT’s databases were effective in obtaining data for the majority of the

parameters, gaps exist within the system, which required significant input from key

personnel for recommended data collection. VDOT’s personnel proved to be the

most valuable asset in data compilation.

Of particular note is the need for statistical analysis of the data in the form of control

charts to determine the relative validity of each value within the parameter’s

distribution.

TABLE OF CONTENTS

TABLE OF CONTENTS ............cccccsscsscscccscccccccscccsccescecarscscccscceccccccsrsccsccsscccacsccsccccssccsesssesccscesscscsscscoecs iv

LIST OF FIGURES... cc cccscescccccsccnsccscccsccucccscscsvscccceccccccccscesccsccsccssccssccscecessscesosecsscescsccscscescsseees Vill

ACKNOWLEDGMENTS 2............cccccssscvssscsssccscsccssccsssscccscscscccescccsccrscceccnssccccccsscscsccscccscescsscccscccssescees Vill

CHAPTER 1 - INTRODUCTION uuu... cccscccscccsccsccccscnsccscccecccccssccccccccccccsscccecccecescccsccsseccsesescescsacs 1

BACKGROUND 00.0. ccc ccccccccccccccccccucecseeeceuecucuscecseerscueuetseseeesderteneaeasenenersusnsaeeucesascnenerteusrestsetencttrtenteetaeess I

OBJECTIVES 200. occccccccceececcceccececcccceceseecuccuceuucceetaessneesesecectaeeeecencetscensteceveseeecsuerseeesececeesecsecunetieteeetteereens 3

SCOPE AND LIMITATIONS 0000.00. .cccccccccccccececccccccucccesececccceceecueceuseeeecucsceuceecseceeceuseeceecenesectsuerttetverteaneerees 4

CHAPTER 2 - METHODOLOGY 20.0... ccc ecccccccsvcnvscecececcceccccccscescsteccncccsnccnscccscccsscssccssccscsececessosscees 6

INTRODUCTION 0 o.oo c ccc cece cc cccecccccecececrencacaccusecteeteeveusuesteueveneneesceeeeeveveveusteeeveverectetesesteatateretieiteveceneeens 6

IDENTIFICATION OF MODEL PARAMETERS .....c.ccccccccceececccccccecucceceverscuseesteaeeuecesaceusensteseueeesaucecuettteneseceness 7

ANALYSIS AND GROUPING OF PARAMETERS .o..0.0ccccccccceccuscececercecccueececcseeuceescecaesuteucenseueeisenerteartesertreeens 7

INDIVIDUAL PARAMETER RESEARCH. .0...0.0.0cccccccccccceccccesnccecececesececececeeeeseuceensrsteneaeasuceetttnseenertttterererssees 8

DATA ANALYSIS 000. cccccccccccccccecccccccuccucccecececccesuecenerseesesagresessetenenenenseetaectneetetacesetaenesteesnerererstreebenecenens 10

PARAMETER WRITE-UP 0.0.0. co.cc cece cccccceccccecccccccucucecccnsectsestecestcucuceeesesstectetevaneratenes vevevceccevacacaseeectaveeseees 11

STATISTICAL ANALYSIS ISSUES... 00. .0ccccccccccecccccuccecceceecccceececccscuecnceesacrtetersstseueresstertereteteueresettnteneetsenees 13

CHAPTER 3 - THE DEVELOPMENT OF THE MIS HELP FILE~z.w............. cc ececcsccsscescncscccsccccescece 17

THE OBJECTIVE ooo. ccc ccecececcccccccececececcucesccseeccenecencuseuccuerecserscaeeesecueeensneusntutteeeesessteetseuseessessttttteeetenes 17

THE SOFTWARE 2. ..cccccccccccecececcecccccneeececececcucacceeesessesessesageneeesesecaseeseeeteeeaeseseeeteseettesatsteuseesitrtetenseneeees 17

HELP FILE CONSTRUCTION 00000... 0occccccecccccccecccececcessccceseeucs bevececceeeeeeaeaeaececesececteusncnstseeacesssteseettettcterereees I8

CHAPTER 4 - SUMMARY AND RECOMMENDATIONS ..............cccccscscssssccccsccccccscccseccsssceccscscesces 23

ENISTING VDOT DATABASES 00.0.0.0cccccccccccccccceccucecccucccccseceeceesetensaesrsteeeeseettetrstttrtttttitittittsttteteecs 23

THE HUMAN PACTOR 0.0. o ccc cc cece cc ccecece cucu ccccccecececueceressseeueuerevesecneneeserestecnettettttttrtttttittetitretttttttrerss, 23

FUTURE SOURCES OF INFORMATION 00... cccccccccecceccececccuccecceveneteccusesensseettsecttresretscrteteritittittittitttttties. 23

RECOMMENDED DATA COLLECTION 000. ....cccccccccccccccccucccucceceecctecseuceeeuedeeeeeceteseectttittctutecscicististtececeeses 26

REFERENCES 1..........ccccccsscsccsscssccsccsscscssccssceseccescccscsscscscccscccscccccecssacescssccsssccssacccscscoscsssesssesesscansceccoecens 27

APPENDIX A: DATABASE SPREADSHEETS .2............cccccsccscsscssccscccccsscsscsscsccsssssssssccescnssonccnesecscnes 28

EVALUATION SUBSYSTEM ......cccccccccccccccccccccecceeececacessreccsueceeececeeccueceuessesteseretsrsessttuetetestsssereteuescrteeress 28

FINANCIAL SUBSYSTEM... oo... ccccccccccccccceccuccuccuccecencceccusenscecnseeeesaecesareterscueeeestsasenstettstaetescrscessuteserecepens 30

FUNCTION AL SUBSYSTEM... cc ccccccccceccccececencsececcceeeeccscececeneneeeencaceesucreneaeeeesenersnsstesetetatersrsvssatutveveceneens 32

PHYSICAL SUBSYSTEM: BRIDGE MANAGEMENT SYSTEM .......0c.ccccccccccecececcuceuccccuceeseetecscecegesestecusnceecey 3

PHYSICAL SUBSYSTEM: PAVEMENT MANAGEMENT SYSTEM .......c.cccccccececececccceceseucutesstssesesesecsessitcessecs 36

APPENDIX B: PARAMETER WRITE-UPS ...0.............cccecsscccccscsccccsccvcccsconsccscecsccccssescsccccscscsccesescsses 37

AVERAGE ANNUAL DAILY TRAFFIC VOLUME (AADT)....0..00..0.00000000... beccueuercecueesetececuseers vececeeeaversesesces 37

ACCELERATED DETERIORATION TIME OF BRIDGES (ADTB) 0.00.00. 00c ccc oc cece cece cece ccueceeccueteuecetateeessreseass 39

AVERAGE DISTANCE TRAVELED PER GALLON (ADTPG) 000.0... ooc coco ee cc eccc cece ccce cet eteteececesesestetesceeeeees 40

AGING TIME OF HIGHWAY (ATH) 20.00.0000 ccccccccc cece ccc cc cece cc cane cece neces cee eeeeeceeeseceueeesaecsutevreserieecreereneeanees 41

AVERAGE MILES TRAVELED PER VEHICLE (ATM)... 00000000000 ccc ccc cece ccc e cece teetu ee seeeece tee eeta ees cee eee teteeeies 42

AVERAGE VALUE OF A VEHICLE REGISTERED IN VIRGINIA (AVWVYV) ooo cece eee bevceeseeteeteeteeeeeeees 45

BRIDGE BUDGET (BB) 000000. .ooccoe cc ce cc cce ccc ccc cece cence be bebe ence ete be tebe tee beeceeeeeseceeeesseeeeeerins voce c eee eee eens 44

BRIDGES IN FUNCTIONALLY ADEQUATE CRITICAL CONDITION (BFACC) ooo. cccc cc cecc cece ene c ccc neee eens +8

BRIDGES IN FUNCTIONALLY ADEQUATE FAIR CONDITION (BFAFC) 0.o0occ cocci ccc cc cnc ccc ne cece cece ese eee neces 46

BRIDGES IN FUNCTIONALLY ADEQUATE GOOD CONDITION (BFAGC)..00.. ooo cece cece ccc ee cece eee eens 47

BRIDGES IN FUNCTIONALLY ADEQUATE POOR CONDITION (BFAPC) oooo0cocccccccccce cece ce cece cece cece bet ee eeeens 48

BRIDGES IN FUNCTIONALLY ADEQUATE PREFERRED CONDITION (BFAPFC) 00000... cceccccccceccceeccecceneecee ees 49

BRIDGES IN FUNCTIONALLY INADEQUATE CRITICAL CONDITION (BFICC) .o000.000 occ cccc cee ccc cece c ccc ec arcu ees 50

BRIDGES IN FUNCTIONALLY INADEQUATE FAIR CONDITION (BFIFCO) ooo cccc ccc ccceccceeeecceeeseeeseeeeenes 5]

BRIDGES IN FUNCTIONALLY INADEQUATE GOOD CONDITION (BFIGC) ..000. 00 cccccccc cece ec cceece eee eeeseecneseeees JD

BRIDGES IN FUNCTIONALLY INADEQUATE POOR CONDITION (BFIPCO) 00.00. cece 33

BRIDGES IN FUNCTIONALLY INADEQUATE PREFERRED CONDITION (BFIPFC)...0.000..00cccccccccccccc cc eeee eee S4

BIRTH RATE PARAMETER OF VIRGINIA (BRPV) 0000.00.00 ccc ccc cece cece ence cece cede cece ee see etet beeen eeteetecies veces 56

BRIDGE WIDENING BUDGET (BWB)..000000 0. coco ccc cc ccc cece cece cece ecu eet tee eeeeceeseeteeeetceinestitisettettttetttsttcsttteseee D7

BRIDGE WIDENING COST (BWC) ooo... coco ccec cc cccec ccc ccce cece ceccneeccceeneeeceeeeeeeeseteeteseettegieeseeeteteeeeteesscseeeesiaes 38

AVERAGE COST OF BEARING AND ANCHOR BOLT REPLACEMENT (CBAR) .00..o..cccccccceccecc cee cecc eee cceeeeeeeee 59

AVERAGE COST OF CONCRETE BEAM END REPAIR (CCBR)...000. coco ccccc cc cccce cc ccce cece nes cee eeeceteteteeteteeeeeaeees 61

AVERAGE COST OF CONCRETE DIAPHRAGM REPAIR (CCDR) 0000. 0oc coco ccc ccc cccc cece ce eccecevescneeeeseteeceeennenes 63

AVERAGE COST OF CATHODIC PROTECTION (CCP) ooo... 000 coco cc cccccc eee ee cece cca e ee be bebe betes ben beeet ti nbeeeeeenes 65

AVERAGE COST OF DECK EDGE REPAIR (CDER) 0000000000000 coco coco cce cence cee cee cece eee seb seen beeen eet eceeceernenena 67

AVERAGE COST OF DECK REPLACEMENT (CDKR) 000. ooo ooo occ cece cc ce cc ecccececueeceuescueessureeeueteuseessenecaeseeey 69

AVERAGE COST OF DECK OVERLAY (CDO) .....0....... cove ceccececseteeceececeeeseceueeueteeeuesrysntretsecevetetevestetesseeeees 7

AVERAGE COST OF DRAINAGE SYSTEM REPLACEMENT & REPAIR (CDSR).o000.. occ e cece cecc cece eeeec eee 3

AVERAGE COST OF EXPANSION JOINT MAINTENANCE (CEJM) oo o.occcccccccccccccececcceccccescuescaeseneeees coc eeeseeeaee 74

AVERAGE COST OF EXPANSION JOINT REPLACEMENT (CEJP) ooo cc ccccoccccccccccccececccsceeeceesceeueseevessraevevsaes 76

AVERAGE COST OF PATCHING (CPCH) 2000.0. cocoon cece ce etc etc ne cee eteeeseeetneteb esta etciettetenterstetetereereees 78

AVERAGE COST OF PARAPET GUARD RAIL MAINTENANCE (CPGM) ooococccccccceccccccccccececeeeeeeeeceesceseseeeeees 80

AVERAGE COST OF REPAIR OF ABUTMENT (CRA) 0000.0 cocci cccc ccc cce cece ccc eccceeccceecueeseaeereaeserneriestiseecreesens 82

AVERAGE COST OF REPAIR OF COLLISION DAMAGE (CRCD) oo ooo cocci ccccccceecceecccueceseecsreseeeceivececenseeas 84

AVERAGE COST OF REPLACEMENT OF ABUTMENT (CRLAD..00 ooo 0c oocccccccc cece cceeccccecceee rescue reteeseceresiaeesenees 85

AVERAGE COST OF REPLACEMENT OF PIER (CREP)..0 ooo. coco cc cece cece ccc ecceeceueceusceusseuctevenvereeecsuteseaes $7

AVERAGE COST OF REPAIR OF PIER (CRP).......0...... Lecce cece eee c eee e eee eeeteetesueecuueesunesseseestetinecstesnerneenenens 89

AVERAGE COST OF REPAINTING (CRPT ) ooo..0c cocci ccc ccccceccc ccc eccee ese eereve esse veceueeeaessrieeteaestnterecrrerteteeneeees 9]

AVERAGE COST OF SCOUR (CS) oii cccc cece cence cece ce eee ce bette este ceteueteseeeesteripesteaeseetrnetetiieesteecenereas veeeeaee 93

AVERAGE COST OF SEALING DECK/CRACK (CSDCO) o.oo. ooo cece cece ce eee ebb e beet eee bebebeteeeeeteees 95

AVERAGE COST OF STRUCTURAL STEEL SECONDARY MEMBER REPLACEMENT AND REPAIR (CSMR)..... 97

AVERAGE COST OF SPOT PAINTING (CSP) ooo oc ccc cece ccc ccccce cece eeceeccucecevecevvecuveveeeterteseerereneveveresanesaeeeens 99

AVERAGE COST OF SUPERSTRUCTURE REPLACEMENT (CSSR) oo... ccccccccccc cc ccececccneccccueccecuecsseeseevecsevecsane LO]

DETERIORATING TIME OF HIGHWAY (DHT) .00.00. 000 c beet b ete b tebe btte ete eteetnerenteens 104

DEATH RATE PARAMETER OF VIRGINIA (DRPV) 0000000 occ ccc cece cece cee ccecce cece ccc ccevevevcveeesetsinsaeseeeusrterereess 105

DETERIORATION TIME OF BRIDGES (DT TB)... o.oo cece ccc etic c eee b ee eb tee bette tebe stde btn tegetbeeeeeera 106

EXPOSURE TIME OF BRIDGES (ETB) 0.000.000... ccc cc cece ccc cece ccc cence cee e nbc e ceca bbc e tebe b ett etcnetaetaeceeertenteneeaes 107

FEDERAL AID TO VIRGINIA (FAW) ooo cece ccc c cece cent nett be cee eesuretsn seca seseretenesevapersneeaeesrerereaneney 108

FRACTION OF THE BUDGET TO BRIDGE WIDENING (FBBW).oo ooo. c coc c ccc ccc cccccnccececcuccececeevevsseecueeaes 109

FRACTION OF THE BUDGET TO FUNCTIONALLY ADEQUATE MAJOR REPAIRS OF BRIDGES (FBFAJRB)...111

FRACTION OF THE BUDGET TO FUNCTION ALLY ADEQUATE MINOR REPAIRS OF BRIDGES (FBFANRB)..113

FRACTION OF THE BUDGET TO FUNCTIONALLY ADEQUATE PREVENTATIVE MAINTENANCE OF BRIDGES

(FBFAPMB) ooo. c ccc cece cece cece eee e eee e ede se bce ete cee tessa seu setuerensrapereseuessuessrerseesarersesetensentenes 115

FRACTION OF THE BUDGET TO FUNCTION ALLY INADEQUATE MAJOR REPAIRS OF BRIDGES (FBFIJRB)..117

FRACTION OF THE BUDGET TO FUNCTION ALLY INADEQUATE MINOR REPAIRS OF BRIDGES (FBFINRB).119

V

FRACTION OF THE BUDGET TO FUNCTIONALLY INADEQUATE PREVENTATIVE MAINTENANCE OF BRIDGES

(FBFIPMB) 00.0... 0occ cece cence cece ccc ee ccc ne cece teense en eee ee eeeneeeceeeeeennneeceneeeeepeneeeeneeceeneseeneeseteeetieeteseeeneessseeees 121

FRACTION OF THE BUDGET TO HIGHWAY CONSTRUCTION (FBHC)..00000.000 ccc ccc cec cc ecce ce eee ce eeteneseeenees 123

FRACTION OF THE BUDGET TO HIGHWAY MAINTENANCE (FBHM)..0..00 0.00. 0cccccce cece cecce cece eeeeeceerseseuenes 124

FRACTION OF THE BUDGET TO THE REHABILITATION OF BRIDGES (FBRHB)......0000.000..0 ccc cece cece ceeee cee 125

FRACTION OF THE BUDGET TO THE REPLACEMENT OF BRIDGES (FBRPB).......0........00..cc0cececeeeecceeeeteeeeees 126

FRACTION OF THE CONSTRUCTION BUDGET TO THE BRIDGE BUDGET (FCBB) «0.0... .000...ccccccccceeeecceneeeeee 128

FRACTION OF THE CONSTRUCTION BUDGET TO THE SALEM DISTRICT (FCBSD).........00...0cccccceec ccc eeeeeee 129

FRACTION OF THE MAINTENANCE BUDGET TO THE BRIDGE BUDGET (FMBB) ...................500c cece ce eeeeeees 130

FRACTION OF THE MAINTENANCE BUDGET TO THE SALEM DISTRICT (FMBSD) 0.00000... cccccccceeeecceeeeeeeee 131

FRACTION OF MOTOR VEHICLE FUELS TAX TO THE HMO (FMFTH)....00..0. 000.00 ccc cce cece eee eee ccc eceneceese eens 132

FRACTION OF MOTOR VEHICLE FUELS TAX TO THE TTF (FMEFTT) ....000...00.0.00000ccccccceccc eee eeceseeeceeneeenees 133

FRACTION OF MOTOR VEHICLE LICENSE FEE TO THE HMO (FMVLFA))............ 00.0. c0cccceeceeeseseueeceuereeees 134

FRACTION OF MOTOR VEHICLE LICENSE FEE TO THE TTF (FMVLFT) ....0.....0000.000.cccc ccc eccce cece eeeeeeeeeens 135

FRACTION OF MOTOR VEHICLE LICENSE FEE TO THE HMO (FMVSTH)........00.. 00... 0ceccceccceeeccceeccseevesens 136

FRACTION OF MOTOR SALES & USE TAX TO THE TTF (FMVSTT1)...000.... ccc cecc ccc ccc ce ceceeee tte e ee ceecesseneaneeed 137

FRACTION OF THE REVENUE TO THE HIGHWAY BUDGET (FRHWY) 0.000000... 0c coc cec ccc ee cee ce eee eceeceuccuseneeens 138

FRACTION OF STATE SALES TAX TO THE HMO (FSSH) o.oo ccecc cece eeece ccc eeecesceeseeceseseeeeeceeuanesesees 139

FRACTION OF STATE SALES TAN TO THE TTF (FSST) 0000... cccccc ccc ccceccee cece eeeee cece eeseeseeeseessesessueesesraneeseess 140

HIGHWAY CONSTRUCTION BUDGET FOR THE SALEM DISTRICT (HCBSD)......000000. coe cccceccccctecccceeeeeeees 141

HIGHWAY CONSTRUCTION BUDGET IN VIRGINIA (HCBV) 00. .0ccccccccceccccceeecccc ce eeecescuaeeeesteeeesunseeessuaesenes 142

HIGHWAY IN DEFICIENT PAVEMENT CONDITION (HDFPC)........ bbccueceeeceecuseseccuccuessectessteseeaeeaseueeeeeeneres 143

HIGHWAY IN DETERIORATED PAVEMENT CONDITION (HDTPC) ooo. o.oo cccec cc ccceecccccceceeceeeeccteueeceseuseseenes 144

HIGHWAY MAINTENANCE BUDGET FOR THE SALEM DISTRICT (HMB).....00..00.0.00 coco cecccccccescceccaeeceutereees 145

HIGHWAY MAINTENANCE BUDGET IN VIRGINIA CHMBV) ..0... coc cccc ccc cc ccc ccc cccecec nec ceeeseeeeeeeseecusereeeueeees 146

HIGHWAY IN SUFFICIENT PAVEMENT CONDITION (HSFPC) 200000. ocoe cc ccec cc cec ccc ceccceeccccesceeeseseerecaeresenneevens 147

INCOME INCREASING RATE PARAMETER (ERP)... oo... occ cc ccccc cc ccececccceecceneceeeeecceesecueeeeeeeeesescsreveseecenaners 149

IN-MIGRATION PARAMETER OF VIRGINIA (IMRPV) 00. cceccceecceececeeseeeceeeererseeesesceueecsecreeeuseceneecs 150

INFLATION FACTOR (INFLF)....0.. 000.00. 00 cece cece ccc cece eceeecccaeeeeueeeseeeecueseeeeseesteesceesessessescesetetssessecersneraness 151

OUT-MIGRATION PARAMETER OF VIRGINIA (OMRPY) 00.00 coco ccc ccccceccccecesece cee eecseueeesesaeseereaeecseuaeeeeens 152

OBSOLESCENCE TIME OF BRIDGES (OTB) ..000.....000..ccccceccccceeeccccccc ea ecececeuesessencecseneesscressesausececaerereserans 155

PER CAPITA INCOME OF VIRGINIA (PCIV)..00. 000.00. ccccccccccecccceecc cu eccuneceebenseceee eeu ceeesenesseesceetessiecrieesenesens 154

PERSONAL PURCHASE RATE (PPR) 0000... .00.0.ccccccccccccceeeeccceeeeseeeeceececueseseeeeseetecuuesesesseseesessttereeseseaaeresens 155

POPULATION OF SALEM DISTRICT (PS) oo... 00... ccccccccccecccceeccccceescessueccuseeceueecsseesesuaeceueetsneesessaseseseeveveness 156

POPULATION OF VIRGINIA (PY) occ ccc cece ccecc secs cccuccuececsecaveccescecseceueecueceuserecescesevaeceetstecsereensereeerans 157

RATE OF MOTOR FUELS TAN (RMPFT) 000000... occ ccc ccc cc ccc ec ccc ecccceeccceceteecueeensccurecensessesasecseseesaeeseesereneeans 158

RATE OF MOTOR VEHICLE LICENSE FEE (RMVLE) 200... coc cc ccccccccceeccceeecccuccccuececueeccaecserecsucecuevessreveeenes 159

RATE OF MOTOR VEHICLE SALES & USE TAX (RMVSUT)....00. cocci cce cc ceccceecenecee renee bececeecveceuteceueeees 160

RATE FOR STATE SALES TAX (RSST) ooo. ccccc cece cece cccceececcceceevscecececuucreccersececeuceeececaureeventereeeteeeeeeareeecess 161

SERIOUS DETERIORATION TIME OF BRIDGES (SDTB) oo..c cocci cceeccceeccneecccuucceuteceucsenesereneeeteeeeseeee: 162

STATE SALES (SS) oocccccccccc cece cece cececcccceseeeeee cee eeeeecegeseeeeeeeeeeseececesenaeeeseseseesseeeeseseseussessseseseuessecsuceeaaneees 163

TOTAL MILEAGE (TOTMILG) ...000.. ooo ccc cece ccec ccc eeccnenereccceeceseueecceaecceaeetsuuescsseessaesesessuseceureserareeeras 164

TRAVEL TIME ON LINK KL (TITLE L) 000. o coc ce ccc ceeccceeccceeccceeceesecuceeetceessasecaeceusceecsarcerseeeeenanees 165

ANNUAL TRAFFIC VOLUME (TVOL)..00...00occcccec cc ccccccccencececceccuueevececuuuececcueeccessuuvccccnecessseesauteeeeceaaereess 167

TOTAL VALUE OF VEHICLES REGISTERED IN VIRGINIA (TWVV).......0.....cccccccceecececceecessusestccavecseseueenteees 169

VEHICLE AVERAGE ANNUAL GROWTH RATE IN VIRGINIA (VAGR) .0o..o..ccce ccc cccccccceeccccuseececueececeeaneeess 170

VEHICLE INCREASING RATE IN VIRGINIA (VINC) .ooooccccccccccc ccc ccceeecccccaeececceeeccccaeecesseseccssstecccaueeecesaanesss 171

NUMBER OF VEHICLES IN VIRGINIA (VV)....0..00cc ccc ccccccecccecccceescevcecueceeuseesecerssuecsanesusetseccescatecereeensceneees 172

WEIGHTING FACTOR FOR BEARING AND ANCHOR BOLT REPLACEMENT (WFBAR)........0...0..0...ccccceeceeeee 173

WEIGHTING FACTOR FOR BEAM END REPAIR (WFCBR) 0000... .occ ccc cece ccccceceececeeeecencsanecseesecenseeeanseeaes 174

WEIGHTING FACTOR FOR CONCRETE DIAPHRAGM REPAIR (WFCDR) 00... 00.0.oooccee cc ccccecccceeccccuecececeuaeees 175

WEIGHTING FACTOR FOR CATHODIC PROTECTION (WFCP) 0.00.00... 0c cc ccc ccc cece eccccneceeeeceseveseseseeueeseraeeeeenes 176

WEIGHTING FACTOR FOR DECK EDGE REPAIR CWFDER) 0000000000 00o oc ce ccc ccc cecc ccc cee ccueccaesteesereeceereness 177

WEIGHTING FACTOR FOR DECK REPLACEMENT (WFDRR) ..0..00.0 00 coco cee ccc cece ce ccceeccnesesereceutecseneeesaeecsens 178

WEIGHTING FACTOR FOR DECK OVERLAY (WFDO)....0000.00cocccccccccceccceccc ee ccceeceveeccseecsersuescstuueceterenesens 179

WEIGHTING FACTOR FOR DRAINAGE SYSTEM REPLACEMENT AND REPAIR (WFDSR)..000..0 oe 180

WEIGHTING FACTOR FOR EXPANSION JOINT MAINTENANCE (WFEJM).....0..000..... beceeeeeceeecatetenseeteneeeenes 181

WEIGHTING F.ACTOR FOR EXPANSION JOINT RECONSTRUCTION (WFESIR) ooo... oc ccc ccecceccceececenececueeseeueee 182

WEIGHTING FACTOR FOR PATCHING (WFPCH)....0000000000 0. ccc ccccccceccce cece eect cee eeetecesceecusaeeeceseeeeseseeeeeereenes 183

WEIGHTING FACTOR FOR PARAPET GUARD RAIL MAINTENANCE (WFPGM) ....0000.00.coccceccccceeec cee eeecce sees 184

WEIGHTING FACTOR FOR REPAIR OF ABUTMENT (WFERA)..000..occcc cc cc ccc ccc cece cece ec eeseaesesuueseeeneeceseuenestess 185

WEIGHTING FACTOR FOR REPAIR OF COLLISION DAMAGE (WFERCD). 00.00 oococ ccc cccc ec ccccc cece cecececuveceeceeas 186

WEIGHTING FACTOR FOR REPLACEMENT OF ABUTMENT (WFRLA) 0000... occ ccc cceccceeceecccuceccuseccuseseeueseeuees 187

WEIGHTING FACTOR FOR REPLACEMENT OF PIER CWERLP) 0.000.000. 000 occ cece ccc cec ce ee cee eeecneeseneeceaeeesenaess 188

WEIGHTING FACTOR FOR REPAIR OF PIER (WERP).ooo ooo c ccc cccc cece cence ce eee cee ctte cette seeetuenesterateesenes 189

WEIGHTING FACTOR FOR REP.AINTING C(WERPT) 0.00... coco ccecccccccc cece ec ca cece ecae ssa ceeusecneseuecsunsesuaesseneretaaneetaa 190

WLIGHTING FACTOR FOR SCOUR (WES) 2oo0ococccccccccccc cece c cece cece eee beet ene eee enn b eee b eet ce dtd beeebetteeeteeteeesnes 191

WEIGHTING FACTOR FOR SEALING DECK CRACKS (WFSDC) 00000000000 occ c cc cece cece cnet eceteteeeeeeeeeeeenens 192

WEIGHTING FACTOR FOR STRUCTURAL STEEL SECONDARY MEMBER REPLACEMENT AND REPAIR

(WESMR). ooo oo icc ccec cece cc cccc cece ee ecu es nee cueceuccneeee peste esebeesepeseeesceesteesceneesesceetssesieseueesseseesteecsanecesisseseesensase 193

WEIGHTING FACTOR FOR SPOT PAINTING (WESP) 0o.o00. cc ccccc ccc ccc cence cece ccc ee cee eee ncee cn eeceudeeectuseeeeeeeaes 194

WEIGHTING FACTOR FOR SUPERSTRUCTURE REPLACEMENT (WESSR).oo o.oo .occcccccceccceecccecccceeceeteseneceeres [95

APPENDIX C: MODEL CAUSAL DIAGRAMG uu. ccccsssccctsccccsscsncccessscassccsenccctecssscceescceceuescceee 196

EVALUATION SUBSYSTEM 000.0000. 000cccccccccccceeccceecce sees cee beeee ee eeee ee eteeeseteueeeteceeeetedeeetettestetseetitetesrraneceeeens 197

FINANCIAL SUBSYSTEM. ..00. 00.00.00 cccccecc ccc cc cence cee e eee ee bec ee tees eesti cee geeeecettbteessetesesseeeseressenserneeiessanecenesaees 198

FUNCTIONAL SUBSYSTEM. 000.000. ccccccceecccecceeccueeeceuneseeceeseebeeseee este eette sees seseeetieeestsunsesssteetesstesesevneserens 199

PHYSICAL SUBSYSTEM: BRIDGE MANAGEMENT SYSTEM o00... 0000. cccccccceceeeccuceccuececcuvescueresersteeseveneeeeeeaes 200

PHYSICAL SUBSYSTEM: PAVEMENT MANAGEMENT SYSTEM oo..00.c.cccccccccccccccuecccuececeueessuevecssrnneseceueeses 201

APPENDIX D: DYNAMO) CODE oui... cccccssscssccsesscccccessscensescscesesesscoccsceeuceseseuescossseescssseseceeneeeseecs 202

EVALUATION SUBSYSTEM 0.....000.00ccccccecccecceeceseccuesenteseveseessrretinetsnetrrctietesstitteretttvererssressratessteeesrersern 22

FINANCIAL SUBSYSTEM. 2000.00. .cce ccc ccc cee c cece eee ee ee ee cence epee ce bee te eetdeeee eee cceueteessesesestaternresipersresesiettereveseas 205

FUNCTION AL SUBSYSTEM... 00.0. 0cccccccccccecceece cee eeeceeeeee eect se eee cen eee te eeetebeesecetugsecessteeaecseueeetevesserneseecaaereess 208

PHYSICAL SUBSYSTEM: BRIDGE MANAGEMENT SYSTEM o000..0ccccccccccceccccecceveccreeceseuceesuesersanesessteeesserens 211

PHYSICAL SUBSYSTEM: PAVEMENT MANAGEMENT SYSTEM o00..00c0ccccccccccceccccceceecceeceessereeerenstesteeseneseers 214

APPENDIX E: MIS SOFTWARE 1..000........ccssscccnsscccsssscesscscecsscscnscecsscessescesceenssccnesessnscccenscsscesensecesees 215

VITA ,..........ccccccescccscccoscccstsccescescnssoncccesenercnsccescenssessccevccesssanssoneseaesseeseescesnensceneceeesenescenssesceseeceseueceeoeses 216

Vil

LIST OF FIGURES

Number Page

FIGURE | - DATA FLOW WITHIN THE RESEARCH PHASE 000.000.0000 cccccccecccceceeeeceeeeeeeescueseeeesueseeessieseugeseesseaeeeen 6

FIGURE 2 - SAMPLE SPREADSHEET FROM THE BRIDGE SUBSYSTEM FROM APPENDIN Aun... co..0cc.cccccceeceeeeeeeeeees 7

FIGURE 3 - EXAMPLE OF A PARAMETER WRITE-UP FROM APPENDIN Buu... ooo.ccccccce cece ccc ccc ee ceeeceecseueesueseeeeenane 11

FIGURE 4+ - NORMAL DISTRIBUTION 000.000.0000. cccc cece cc ececeecceuccceueceeveceeeceeeccseubeeseueeeetevesereeetiesteseserieesteseneesenes 14

FIGURE S - TIME INDEPENDENT CONTROL CHART 0000.0... c0cccceccccsccecceeeecsseeuesesereretseaneees bocce ecu eee eeesteteeseesenees 15

FIGURE 6 - TIME DEPENDENT CONTROL CHART 00.000. ccccccccccccccceuccceeeeeececeueeeceueeseeeeessea sees ecessetstescesnetereuness 16

Vill

ACKNOWLEDGMENTS

The author wishes to sincerely thank his advisor, Dr. J. M. de la Garza and Major Z.

Mitchell, USAF, for their patience, advice, and support with this thesis.

Additional thanks go to the rest of my committee, Dr. Vorster and Dr. Drew for their

time and assistance in this endeavor.

Of course any undertaking such as this would be incomplete without thanking those

individuals whose unwavering patience with my endless questions and requests have

made this work possible. Allen Williams, Dean Hackett, John Jones, James Shelor,

and all the others, you have my applause and gratitude for your professionalism and

effort on my behalf.

My greatest thanks goes to my wife Liza for her sacrifice in allowing me to follow my

dream of returning to school to complete this degree. Additionally, I would like to

thank my son, Connor, who has brought such unexpected pleasure into our life and

my parents, Mr. and Mrs. W. A. Smayda, Sr., for their love and support in my

abilities.

1X

CHAPTER 1 - INTRODUCTION

Background

Department of Transportation (DOT) policy makers are faced with an annual decision

concerning what fraction of their budget will be spent on maintenance versus new

construction. Dr. Allan Chasey established in his dissertation (Chasey, 1995), A

Framework for Determining the Impact of Deferred Maintenance and/or Obsolescence of a

Highway System, the need for balancing these expenditures to achieve a desired Level

of Service (LOS) within a specified period of time. Some specific points brought to

light in his dissertation are:

Federal, state, and local governments are reducing construction expenditures

in new infrastructure and in maintenance of existing infrastructure to meet

the growing demand for increased social services. There is greater political

mileage to be gained from these current high profile programs, than from the

customary programs such as infrastructure construction and maintenance are

just as vital. This same mentality is also skewed towards highly visible new

construction than that of routine maintenance.

Design standards have changed, leaving existing structures functionally

obsolete. A prime example is the Woodrow Wilson Bridge, which spans the

Potomac River connecting Northern Virginia with Maryland. Initially it was

designed for a capacity of 75,000 vehicles per day, but now carries over

170,000 (ENR, 1996; p. 9).

Necessary maintenance is deferred, resulting in increased deterioration and a

significant higher cost when the situation is mitigated. Traditionally, this is

due to lack of sufficient funds and is postponed until there is public demand

or sufficient need.

Dr. Chasey’s focus is on the “big picture”. That is, his dissertation and research deals

with the top level policy making for the Department of Transportation and

specifically with the division of monies between maintenance and new construction.

However, Allen Williams, the Maintenance Engineer for VDOT’s Salem District,

narrows this focus to the district level in a paper titled “The Impacts of Deferred

Maintenance - Verbal Description” (Williams, 1995). In this paper, the focus is on the

division of monies between ordinary (preventive) maintenance and maintenance

replacement. This is the result of the money allocated (maintenance versus new

construction) to each district by the State DOT, and is non-transferable from one to

the other.

Ordinary Maintenance is based on historical data and is applied to an element when

deterioration has caused the need for maintenance. It should be noted that it does not

replace the element, rather it extends the life of the element by decreasing the rate

with which it deteriorates. A system begins to deteriorate immediately upon

completion of construction and is dependent on three main factors: the quality of

construction, the traffic (volume and type), and the environmental conditions

(weather, etc.). An important factor of ordinary maintenance is that it not only

directly extends the life of the element, but other interrelated elements within the

system, i.e, the drainage system (gutter and/or camber) have a direct effect on the

entire system, whether it be a roadway or bridge.

In those instances when ordinary maintenance is no longer viable, such as when it has

been deferred to such an extent or the system has reached the end of its functional life,

maintenance replacement is necessary. This is dependent on the three factors outlined

above and the frequency with which ordinary maintenance has been performed.

bo

Elements falling into this category are ranked hierarchically, with those in the worst

condition and/or highest traveled sections receiving priority. The amount of

replacement within the system is based on the amount of funding available, which in

turn is based on the amount of deterioration within the system. However, since funds

are limited, not all of the required maintenance replacement can be accomplished.

This places the burden back to increased amounts of ordinary maintenance performed.

The approach to be used in this model is systems dynamics, using the DYNAMO

software to write the code. System dynamics is a paradigm shift in the manner with

which we attempt to solve problems. Traditionally, problems have been broken

down into their base components, each analyzed for their function. The result ts an

incomplete understanding of the functioning of the system as a whole. The sum of

the parts does not equal the whole. System dynamics takes the stand-point that the

whole is greater than the sum of the parts. It strives to discover the laws affecting the

conversion from input to output for the event being studied.

As with all computer programs, a need exists for the debugging and calibration of the

Highway Management System (HMS) to ensure it functions as intended. The goal is

to not only discover errors in the logic used, but also to ensure it performs as

intended. This can be done through the use of a rough data set, determined through

engineering judgment and global values. However, once the program is functioning as

planned, it ts little more than an academic exercise with little or no utility. It is for

this reason that we intend to calibrate the model using the Salem District as a test bed.

Objectives

The purpose of this thesis is to develop an infrastructure for the Management

Information System concurrent with the development of a System Dynamics Model

for VDOT’s Highway Management System and an intertace between the two. The

specific objectives for this thesis are to detine the step by step process of locating each

parameter value within VDOT’s data bases and annual reports; define all parameter

values (quantitatively) within each subsystem model; and present the findings in a

user-friendly format, both in hard (manual) and soft (software format) copy. The

software will include hypertext links (a windows type format) to allow the user to

navigate through the document. This software will have the global model of the HMS

as the master document providing links to the causal diagrams for each of the

subsystems. Within each of the causal diagrams, each parameter acronym will provide

a link to its corresponding detailed parameter write-up. A pop-up message will

identify to the user those parameters that are either model generated or

user-defined within each of the subsystems, as they are clicked upon.

Scope and Limitations

The primary method of defining each of the parameter values will be to research

relevant VDOT data bases (FMS, HTRIS, and PONTIS) and interview key personnel

such as the District Maintenance Engineer, Alan Williams, and others to include John

Jones, et al. Other sources of information include annual VDOT reports, for instance

their “Average Daily Traffic Volumes on Interstate, Arterial, and Primary Routes”.

It is anticipated there are values for which there has not been any data collected to

date. In these instances, we will rely on the engineering judgment of Alan Williams

and key individuals who are most familiar with the relevant subsystem and parameter.

A method for tracking the identified parameters will then be generated with input

from the key personnel.

The collected data will be entered into a user-friendly format such as an Excel

spreadsheet. The spreadsheet will be broken down into the five subsystems

comprising the Highway Management System. These include the Administrative,

Evaluation, Financial, Functional, and Physical Subsystems. The physical subsystem

can be further broken down into the Bridge Management System (BMS) and the

Pavement Management System (PMS). Within each of these major components, the

parameters will be ordered sequentially as they appear within the computer code for

each of the subsystems.

Upon substantial completion of the data collection, the model, computer code, and

spreadsheet will be put into a hypertext format. The global view of the model will

have links to each of the subsystem models. Within each of the subsystems, each

parameter will have a link detailing the steps necessary to locate the requisite data with

which to define this information. This set up will also be performed with each of the

subsystem source codes and spreadsheets.

Emphasis will not be placed on the quantitative value, but rather on the process one

goes through to define this value. The logic behind this is the model itself will be self-

calibrating and the quantitative values for each parameter will improve over time.

CHAPTER 2 - METHODOLOGY

Introduction

This chapter will provide the fundamental methodology for data collection and the

description of the infrastructure for the Management Information System (MIS).

The five phases which make-up the research phase consist of:

Identification of Model Parameters

Analyzing and Grouping of Parameters

Individual Parameter Research

Data Analysis

roe

wo

p

Parameter Write-Up

Figure 1 is a flow chart depicting the five phases and the thought processes and actions

required upon data collection.

| Model Parameters |

ae

I v

Individual

Paramter

a

Query Databases and/or

Key Personnel

Key Personnel

Estumate

|

1

| | |

| |

: Unsatisfactory Estimate Analy Unsatisfactory Data

Write-up

Results

Figure 1 - Data flow within the Research Phase

Identification of Model Parameters

The Causal Diagrams and the DYNAMO code were the primary sources used to

identify the model parameters for the HMS. Causal Diagrams, which are significantly

easier to identify when compared to the computer code, were used as the primary

source for parameter identification. This code acted as an alternate source --

predominantly used to understand which parameters were to be model generated,

which required user-defined data, and the data required from researching databases.

There are a total of two hundred and fifty-seven (257) parameters within the model.

One hundred and seventeen (117) are to be model generated, seventeen (17) are user

defined, and one hundred and twenty-three (123) are required to be researched.

Analysis and Grouping of Parameters

Once the parameters were identified and cross-referenced with the model and code,

they were analyzed and grouped according to common themes and likely sources, 7.e,

financial, pavement, and bridge. Once accomplished, they were further subdivided

into manageable subgroups and assigned a date (on a weekly basis) in which each

group was to be researched. For ease of maintenance and control purposes, the

parameters were then inputted into a spreadsheet. The spreadsheet was maintained in

two forms: the first separated the parameters by model subsystem, i.e, Evaluation,

Financial, etc.; the second consisted of all parameters sorted in chronological order as

to their assigned research date.

Acronym Name |Units| Value (a) | TIP | TDP Confidence Source Page (s,) | (s,t) Interval Number

TOTMILG | Total mi. 117.91 v VDOT - HTRIS 151

Mileage

Travel Time . See v Average Daily Traffic Volumes on Interstate,

TTLKL On Link KL| ™"- [Spreadsheet Arterial, & Primarv Routes - 1994 152

Figure 2 - Sample spreadsheet from the Bridge Subsystem from Appendix A

The finished spreadsheet has nine main fields for data entry. These fields are the

parameter’s Acronym, Name, Units, Value (x), TIP - Time Independent Parameter

(s-), TDP - Time Dependent Parameter (s-,), Confidence Interval, Source, and Page

Number. The first three fields are self-explanatory. When necessary, the Value (x)

field is further subdivided into three separate fields. This is to facilitate multiple

values for the same parameter, 7.e., Interstate, Primary, and Secondary, when dealing

with parameters specific to the bridge or pavement system. A quick cross-reference

with the parameter’s write-up will alleviate any confusion concerning each value and

the means used to calculate it. The next three columns (TIP, TDP, and Confidence

Interval) will be explained later. In some instances the parameter is not defined by an

equation, but is a constant. This is not to say the parameter never changes in real

time, rather it is constant relative to the simulation model, and should therefore be

updated along with the remainder of the parameters.

The source field contains a bullet description of the data source and when necessary, a

statement advising recommended changes for data collection. A more detailed, step-

by-step description of the source may be obtained in the parameter write-up. The

Page Number refers to the location of the detailed write-up, for a parameter within the

paper form of the user’s copy.

Individual Parameter Research

The parameters were subdivided into four categories according to likely research

avenues. These consist of parameters focusing on the bridge, evaluation, financial, and

pavement aspects of VDOT’s operations. Parameters relating to bridges were

discussed with Dean Hackett, a Senior Structural Engineer for VDOT’s Salem

District. Allan Williams, Salem’s Maintenance Engineer, and Wonkyu Kim, the

simulation modeler, discussed any parameters associated with traffic engineering.

Financial matters were discussed with E. E. Miller, Jr. from VDOT’s Financial

8

Planning and Debt Management department in Richmond, John Jones, Salem’s

Maintenance Manager, and Allan Williams. Finally, any pavement activities were

discussed with Allan Williams, John Jones, and James Shelor, Salem’s Pavement

Management Coordinator.

In the discussion phase with these key individuals, details such as whether specific

parameters were the best measure for achieving the desired end-state were discussed.

In instances where there was a more appropriate method for generating the desired

information, discussions were held with the modeler Wonkyu Kim and implemented

when appropriate.

Data readily obtainable was available in two forms. First, querying of a number of

databases was used. The predominant VDOT databases used in this research were the

Financial Management System (FMS) and the Highway Transportation and Record

Information System (HTRIS). These databases have a limited search capability and in

some instances, i.e, bridge condition ratings, Super Natural was used to perform a

more extensive search. Super Natural is a search engine that overlays VDOT’s

databases allowing the user to perform a search of the database based on any number

of guidelines. The other database predominantly used was the US Census database.

This database was accessed through the Internet. Data used from this database was

obtained from the 1990 census.

The second form consisted of researching various VDOT contracts and the

publications of several agencies; namely, VDOT and the Federal Highway

Administration (FHWA).

For data that was not obtainable, key personnel were asked to provide an estimate

based on their experience and, when necessary, to provide input for a recommended

data collection scheme.

In those instances where the data was unavailable in the needed form and key

personnel were unable to provide a reasonable estimate, the modeler was then

notified. The intent was to take a closer look at the model to find a more applicable

method for modeling the desired outcome. This tended to be an uncommon

occurrence, and in such instances an improved, elementary method was developed.

Data Analysis

Collected data can come in one of two forms. The first form is readily useable and

requires nothing more than verification and a write-up. Examples of this include the

data collected from the 1990 Census (Per Capita Income Level of Virginia (PCIV), etc.)

and certain budgetary items (Highway Construction Budget in Virginia (HCBV), etc.).

The second form of data required numerical manipulation to put it into a useable form

for the HMS model. The numerical manipulation could have been as simple as adding

a series of numbers to achieve the desired input (Highway Maintenance Budget for the

Salem District (HMB), etc.) or a more complicated manipulation, such as the Bureau

of Public Roads’ (BPR) method for determining the travel time between the links

(TTLKL). In such instances, a spreadsheet was used in the data manipulation. Within

each parameter write-up, a detail discussion of the data manipulation is provided.

10

Travel Time on Link KL (TTLKL)

Definition/Assumptions

TTLKL is the average time in minutes spent traveling the full length of each road. Assumed the following values: 2207 vehicles per lane, 65 mph for interstate highways, 55 mph for US highways, 45 mph for state highways, and the predominant number of lanes for one way travel are provided by Allan Williams, the Maintenance Engineer for the Salem District.

Formula

TILKL.K=FFTTLKL*(1-(1-LOSF.K)*(A VBC.K))/(1.0CC1*A VBC.K) Value (min)

See spreadsheet below.

Source

1. Use the Relative Density of Traffic by Route table for the Salem District, found in the Average Daily Traffic Volumes on Interstate, Arterial, and Primary Routes - 1994.

2. Input Route, Mileage, and Average 24-Hour Traffic per Mile of Route into an Excel spreadsheet.

3. Sort by Route Use this equation in the spreadsheet:

“ Ave. 24-hr Traffi Mile of Route’ ae * ra = Ave. Hourly Traffic per Mile of Route

< 4

5. Use the Bureau of Public Roads (BPR) method for determining the new time (Ty) in feet per minute:

/ “47

T. -~0. S- pe oy T, 1-018 =, |= Ty

Where:

sey rs MPH T., = Initial Time... = 60 min

V Volume Ave. Hourly Traffic per Mile of Route

ec apacity ~ {No. of Lanes . 2200)

6. Calculate Total Travel Time by: Ty x Mileage = Time

(mun} Figure 3 - Example of a parameter write-up from Appendix B

The second form of data, once it was manipulated into its required form, was then

turned over to key personnel to be reviewed to ensure it corresponded with their

expectations based on their experience. If the manipulated data did not fall into line

with their expectations, then the data, along with the parameter, was re-evaluated with

the intent to locate its discrepancies. Once the discrepancies were located and

mitigated, the data was manipulated through the process once more.

Parameter Write-up

Once the parameter data has satisfactorily advanced through the first four phases, it

then proceeds to the write-up phase. The write-up’s intent is to provide the layman

11

with a clear, concise method for viewing the results and to provide the methodology

for replication for future updates.

The framework for the write-up consists of the parameter name, with its

corresponding acronym in parenthesis, as the page heading. Immediately following

the page heading is a brief description of the acronym, and if necessary, any

assumptions made during the manipulation of the data.

The value of the parameter, with its units in parenthesis, is then given. Whenever

possible this has been separated into its base components rather than using a weighted

average. The reasoning behind this is that at this point in time the model deals strictly

with the interstate highway system. Therefore, using a weighted average of the entire

road system would skew the results and provide the user with an invalid picture of the

system. Whenever possible values for the primary and secondary systems were

provided in anticipation for the expansion of the model to incorporate these systems.

Following the value is the detailed description of the source for the data. Included in

this section are the steps and formulas used for the manipulation of the data to achieve

the requested results. Whenever necessary, this section also includes the

recommended data collection program for those parameters for which data was

unavailable. Finally, an example of the Excel spreadsheet is given to provide the user

with a clear idea of the data manipulation.

12

Statistical Analysis Issues

All processes have some variation. This is especially true for the transportation and

construction industries, This basic premise must be kept in mind whenever

conducting research within a systems environment. Therefore, the best we can

accomplish is a “snap-shot” of the true picture.

The snapshot used for model calibration with this project is the 1995 data obtained

from VDOT. Exactly where each value is in relation to the overall average for each

parameter value is unknown at this time. If the value is high, it could skew the model

results to the high side. The converse is also true for the values on the low side. But

what is to be done with data that is uncharacteristically high or low, for example the

price of lumber following Hurricane Hugo in 1989 or the price of gasoline in the early

summer of 1996? Do we use this data? What does it do to our results? Are we

deceiving ourselves of the possible results by using this data? At this juncture we have

no statistical knowledge of the data. Relying on the current data to make policy

decisions would be analogous to taking a “shot in the dark”. It is for this reason that

the author recommends a statistical analysis be accomplished for each researched

parameter prior to using this data as a decision making tool. A recommended

statistical tool would be the use of control charts for each of the researched

parameters.

The use of statistical control charts will allow the user to identify whether the desired

value is within acceptable limits of the sample mean. Control charts make use of

upper and lower bounds, centered on the sample mean, called a control limit.

Through these limits, control charts distinguish between the variation that can

normally be expected due to common causes, 2.e., inflation, economic indicators, etc.

and those due to unexpected causes, such as miscalculations in the data manipulation.

13

The sample mean (x) is defined as the arithmetic average of the sample. There are two

instances where a sample set is a normal distribution (Figure 4) with mean u and

variance o-/n; the first is where the data follows a normal distribution, or the data

follows any distribution, but is taken from a sample set of 25 to 30 data points.

Therefore the probability of the sample mean falling between u-*/%5 and u+*%; is

0.9974. Putting this in clearer terms, only 2.5 items out of every hundred will fall

outside these limits, the chances of which are relatively slight. These formulas provide

the lower and upper control limits respectively. However, chances are that we will

not know the population mean (1) and standard deviation (6). Therefore, will have to

use the average of the sample means (x) as our centerline and the sample standard

deviations of the averages (5s) when calculating our control limits, where

x— A.s<x,<x+ 4,8. The constant A, is dependent on the sample size, 7, and can be

found in any statistics book.

20

» < } “O ]-a

sy UY

Figure 4 - Normal Distribution

Of concern when using this particular method is a “spike” in the data used to calculate

the control limit. By its very nature, this spike will skew the control limit and its

corresponding upper and lower limits in the favor of the spike. This in turn will

trickle down through the model with the potential of having major effects on the

results produced by the model. For this reason, a management level decision is

required as to whether or not to delete these spikes from all calculations on a global or

case-by-case basis.

14

There are two types of parameters encountered when working with the VDOT data.

First, a Time Independent Parameter (TIP), the plot of which will have a centerline

with zero slope. The distance of each data point from the centerline is defined as

x - x and the standard error of the mean is defined as s = The value ts

squared to eliminate any possibility of the sum of values equaling zero. The square

root is then taken to normalize the value, 7.e.. return it to the original units. The

smaller the error (the closer the data point to the centerline) the more accurate your

data point is to the overall average (x).

} ut

fm UCch os asa L a > , :

™ a“ \ ao a ee ;

g voy * ” ae a “Center Line -~ eared - ae

= Oda ° LCL ” ”

“ m0 4 Und

om J] 2 3 4 Hl t2 13 14 15 fo oO 7 x ’ 1a

Observation

Figure 5 - Time Independent Control Chart

The second type of parameter is the Time Dependent Parameter (TDP). This value

may vary with time, either increasing, decreasing, or remaining constant. Examples of

this include budgetary items and construction costs. The difference lies in the slope of

the centerline. Aside trom being zero it may also be either positive or negative, with

the slope likely corresponding to one of the cost indices. Figure 6 provides an

example of a time dependent control chart.

2200

UCL 2000 * a *

/ \ \ ff >» >

1800 a id

~ | A P| Li : LN fo / Center Line 51600 f---® NR , \ / 2 SN \ » > \ Ue LCL

1400 | \

1200

1000 0 4 2 3 4 5 6 7 8 9 10 11 12 13 14 #165 16

Observation

Figure 6 - Time Dependent Control Chart

It must be recognized that each parameter value obtained in this research is one value

in a distribution of values associated with each parameter. Where this value lies

within the distribution is unknown at this time. If the value lies in the 95"" percentile

the model will skew towards the upper end. The converse in also true for those values

lving in the 5" percentile. The global effects on the model are also dependent on the

parameter itself. If the parameter is one of the parameters identified as significant in

the sensitivity analysis its effects will have an even greater impact.

Although the time constraints associated with this project precluded any statistical

analvsis of the collected data, it is for these reasons that it 1s highly recommended that

this should be undertaken as soon as possible to begin laying the foundation for future

data collections. Therefore, the Confidence Interval column in the data spreadsheets

has been intentionally left blank as a reminder for this need.

16

CHAPTER 3 - THE DEVELOPMENT OF THE MIS HELP FILE

The Objective

In the development of the “soft” copy of the MIS the intent was to provide VDOT

with the same information conveyed in the “hard” copy, or paper version, which

requires minimal space, and is a stand-alone entity. Bv stand-alone it 1s meant that

VDOT would not have to load a new software package onto their systems in order to

be able to use the soft copy; it should run off their existing systems.

The idea behind the soft copy was to use the developed hard copy as the framework

and establish links in both text and pictures to related topics throughout the

document. Other desired features are to have a searchable index, to be able to print

from the document itself, and to be relatively user-friendlv for updating purposes.

With these items in mind, Web Editors were ruled out since additional software is

necessary, 1.¢., a Web browser such as Netscape, and the lack of several other desired

features. The software accepted tor use in the development of the Help File is a

shareware version of a package called EasvHelp/Web, by Eon Solutions Cheshire,

England. This software was chosen because it met and exceeded the stated

requirements by being able to create a hypertext document tor a Web Homepage with

the click of a button and reprocessing and building the document without losing the

Help tile.

The Software

Easy Help/Web was used in conjunction with two other shareware packages: Shed.exe

and HC505.exe. Shed.exe is a software package that allows the user to map pictures

placing hot spots, or clickable regions, within the picture, which are linked to other

17

areas within the document. HC505.exe is a Microsoft help compiler and is what

actually builds the help file in Windows format.

Help File Construction

The building of the Help file was accomplished in two phases: the creation of the text

document and the mapping of the causal diagrams. However, a few things need to be

accomplished prior to beginning work. Both the EasyHelp and the Shed file need to

be unzipped. Once this is accomplished, the Microsoft Help compiler needs to be

uncompressed and the four files (hc.exe, hcp.exe, hc.err, and hcp.err) must be moved

to the “HC” sub-directory of the EasyHelp directory. Accordingly, each Word

document must have the EasyHelp template attached to it prior to beginning work on

the Word document. This template may also be attached to an existing document,

which is needed to build a Help file. To attach a template, follow the directions in the

Microsoft Word manual.

Building Topics and Links within Text

A Topic is defined as the address for which a Link is told to go. A Link is a “go to”

command function. Any word or phrase within the Word document can be identified

as a Topic or Link.

To create a Topic highlight the word or phrase with the mouse cursor then click on

the “Topic” icon on the button bar at the top of your screen. The pop-up menu will

ask for the topic identifier. Type in the desired Topic name. Click on whether the

Topic is to be a Link or Pop-up topic (the default is Link). For this project, each

parameter write-up heading became a Topic with the parameter’s acronym as the

Topic name, as these needed to correspond with the Link names in the causal

diagrams.

18

Their is a minor difference in the process when creating a Link. The pop-up window

contains a scroll list of all Topic names within the document. To select one of these,

double-click on the desired Topic name and the process 1s complete. The program

ensures the match up between the type of link, z.e, Jump Links correspond to Jump

Topics. If, however, the linked Topic is in a different document then the user needs

to type in the Topic name and click on the corresponding Topic tvpe (Pop-up or

Jump).

Once all necessary items are complete, click on the “Process” icon on the button bar.

It the document is the first to be processed under a new project, click on “New” at the

right side of the pop-up menu. The user will then be asked to provide a Project

Name. Type this in and click “OK”. Next, click on the name of the project just

entered and click the “Edit” button. Click “Add” in the lower right of the menu

followed by “Yes” if the name of the document is the correct one to be added to the

“Project”. Once this is complete, click “OK” on both menus to begin the processing.

Only click on the “Build” button if the current document is to be the master

document for the Help file.

The current numbering and bulleting system organic with MS Word fails during the

compiling of the document. This means the formatting is lost. Because of this the

developers of the EasyHelp program have added “num list (a)” and “num list (b)” for

the user to place numbered lists within the Help file. “Bullet (a)” and “bullet (b)”

provide the same remedy for the bulleting problem. These can be found in the Style

drop-down menu on the button bar at the top of your screen.

Mapping of Causal Diagrams

As previously stated, the Shed software is used to develop the hot-spot areas within

each picture. However, before the picture can be mapped it must be in either a

metafile (*.wmf) or windows bitmap (*.bmp) configuration. Since the bitmap ts more

19

memory efficient it was used in this development. This is essential to keep in mind

since the Microsoft Help compiler will only handle pictures up to 64 kb in size.

Therefore, after creating the hot-spot picture, it is advisable to ensure the picture with

the *.shg (Segmented Hyper Graphics) extension is less than the maximum allowable

SIZe.

To create a hot spot within a picture place the cursor in one corner of the area you

would like mapped. Right-click the mouse and drag the box until it reaches the

desired size. At this time a menu will pop up. Areas to be concerned about within

this menu are the Context String, Type, and Attribute, all of which are found in the

Binding section.

The Context String box is where you place the name of the Topic the mapped section

is to be linked to. For the purposes of this project, the acronym name was used. The

Type box refers to the type of link desired. A jump link physically replaces the

mapped picture screen with the screen from the linked page. A Pop-up will bring up

the linked topic to overlay a section of the existing screen, which remains in the

background. The Attribute box is a drop-down menu with two choices: visible or

invisible; this refers to whether or not the user desires to have a dashed-line box

around the mapped area. All mapped areas in this file have the invisible attribute to

minimize the confusion within the causal diagrams. Once the mapping is complete

for the current picture, click on “File|Save As” and type the name of the current file.

The “Save Location” must be in the Graphics sub-directory of the EasyHelp directory.

Saving the picture in this manner will create the hot-spot picture with the *.shg

extension. The bitmap picture is required to be saved in the same directory. And is

the hot spot and the Topic it is linked to must be of the same type, z.e., jump or pop-

up.

Once the mapping is complete, the bitmap picture 1s required to be inserted into an

MS Word document. This is done with the “Insert! Picture” command of Word.

When inserting the desired picture it is important to remember to click the “Link to

File” box within the menu, otherwise the hot spots will not activate. Due to the size

of each causal diagram, each picture was inserted into a separate Word document (with

the EasyHelp template active) to minimize compilation time. To link each of the

causal diagram documents to the master document (in this project the global picture of

the Highway Management System) a “Heading” was placed in each document. This

was then converted into a Topic link, as outlined earlier. Process each of the causal

diagrams as previously stated, adding each file to the project. Only click “Build” with

the file you desire to have as the master document for the Help file. If for any reason

the picture needs to be edited, delete the picture from the document and edit the

bitmap (*.bmp) and hyper graphic (*.shg) within the graphics directory of EasyHelp

then re-insert it into the document. By double clicking on the picture to use the

Word editor the hot-spot formatting is destroved in the picture.

This chapter is meant to provide the reader with a basic knowledge of the EasyHelp

software. The nature of this document precludes delving into a detailed account of

how to use the software. However, the author has found, through numerous

correspondence, the developer, James Holroyd to be extremely helpful and prompt

with any difficulties encountered.

Appendix E contains the disk containing the compilation software (in an executable

compressed format), the files used to create the MIS help file (in compressed format),

and the MIS help file (uncompressed). Both the EasyHelp and Shed software are

shareware and the user is advised to follow the rules governing it as such.

21

To install the help file onto a computer, follow Microsoft’s directions for copving (or

moving) a file from a floppy disk to a specific directory on a hard drive. The help file

is called sources.hlp.

To run the help file, open Windows and double-click on the file name or use the “run”

command. Use the mouse to navigate through each picture. A link within a picture is

detined when the normal mouse curser (usually an arrow) changes to a pointing hand.

Click once to select the desired item. Green highlighted text is also a clickable item

within the help file.

Other useful teatures include the following:

1. The “Search” button: Allows the user to perform an index or key word search.

ho The “Back” button: Takes the user back to the previous screen.

3. The “Print” button: Prints the current Topic page(s).

4. The “«” button: Allows the user to scroll back in the current document.

5. The “»” button: Allows the user to scroll forward in the current document.

6. “Options|Font”: Allows the user to increase/decrease the size of the text within the help file.

bho

i)

CHAPTER 4 - SUMMARY AND RECOMMENDATIONS

Existing VDOT Databases

The current VDOT database system is very disjointed, with each database unable to

communicate with any other. The existing system has evolved over the past twenty

years into sixteen (16) separate database systems. Each system was designed to fulfill a

specific need in the “current” system with little or no foresight of future needs or of a

unified system for information management.

Financial Management System (FMS)

The Financial Management System is the cornerstone of VDOT’s accounting system

and has been designed for the accounting department. As money is spent, it is

recorded into a coded account for tracking purposes. One of the strengths of the

system is that it allows the user to focus on a specific system, 7.e., interstate, primary,

or secondary.

The principal limitation of the system, from both the model and management

perspective, is the activity codes used are too global to allow the user to go into any

detail within the system. For example, only five codes are used to track money spent

on all maintenance replacement for bridges. The DYNAMO model (Appendix C, p.

193) requires twenty-three distinct activities for the same information. Therefore, time

was spent working with VDOT personnel trom the Bridge division reviewing past

contracts to extract the average unit costs.

Highway Transportation and Record Information System (HTRIS)

HTRIS is currently the database used for both the pavement management system

(PMS) and the bridge management system (BMS) by VDOT. A wealth of information

23

is contained in this database, including traffic counts, road- and bridge physical

conditions, and the inventory for all roads and bridges within the state.

Although this database has proven its utility within the context of this research, some

limitations do exist. Some of the data contained herein is not concrete data, but rather

derived data based on a theoretical growth model. An example of this is the traffic

counts associated with the interstate and primary road systems. The last actual count

was taken in 1988 and, according to VDOT traffic engineers, some of the data 1s

grossly unreliable. Another significant discrepancy is this data is based on the Average

Annual Daily Traffic (AADT). More detailed information such as the peak hourly

traffic counts would provide a clearer, more realistic picture of what is actually

happening within the system.

HTRIS also contains limited information concerning the secondary road system. This

poses a problem regarding future expansion of the DYNAMO model from the

interstate system to the entire system.

Super Natural

Data manipulation and querying capabilities are limited within HTRIS. This limited

query capability has been mitigated to a certain extent with the development of the

“Super Natural” system. This system overlays the Highway Transportation and

Record Information System (HTRIS) and allows the user to query this database for

specific information spanning several parameters individually recorded within the

system, i.e, the number of functionally adequate bridges in good condition on the

Interstate system (BFAGC). Although a powerful search engine, it is extremely user-

unfriendly with the potential for disastrous effects if misused. This search engine will

allow the user to modify the HTRIS database through querying. In order for this

system to be used effectively, the user must have intimate knowledge of the three

major components of the system: an understanding of the information requested, an

24

understanding of the type of information maintained within the HTRIS database, and

finally, the semantics and logical sequence used in querying the system. This last

component is the major limiting factor of the system as it resembles a computer

programming language with three potential outcomes: the information is received, no

response is received from the system, or the system is corrupted. The last is

disastrous, the middle is frustrating as there are no error codes to inform the user

where the query is semantically (and/or logically) incorrect and, if information 1s

received, intimate knowledge of the desired information is necessary to be able to

decide if it is the correct information.

The Human Factor

The human element proved to be by far the most effective source of information,

both in real time data collection and the knowledge of where to look for seemly

impossible (unquantifiable) data. Examples of this include the average distance

traveled per gallon of fuel (ADTPG) and the average miles traveled per vehicle (ATM).

Future Sources of Information

Future sources of information include both the Integrated Maintenance Management

System (IMMS) and Pontis. The IMMS is in its developmental stage at this time and is

the end result of VDOT’s global review of their maintenance policies, procedures, and

database system. The intent is to integrate VDOT’s existing databases into this new

svstem whereby the current databases will be able to communicate with each other.

This system is also intended to be substantially more user-friendly than the current

database system.

The Pontis system is not a database, rather it is a modeling system for bridge

maintenance. The value to be derived from this model is tts bridge deterioration rates.

Although still in its infancy and the current deterioration rates are based on North

25

Carolina bridges, the model has the potential to provide accurate deterioration rates in

the future once it is calibrated with Virginia bridge data.

Recommended Data Collection

As outlined above, there are a number of changes that are required to improve and

facilitate the data collection, which in turn, will have a significant impact on the

model output. Within the detailed parameter write-ups (Appendix B), in those

instances where changes in the data collection are necessary, recommendations have

been made. These recommendations have been made in context to the current model

and with limited knowledge of the detailed aspects of VDOT’s database system. As

such, they should be viewed as recommendations to be used as a foundation in making

future improvements by someone knowledgeable in both the Highway Management

System and VDOT’s database system.

REFERENCES

Chasey, A.D. (1995); A Framework for Determining the Impact of Deferred Maintenance and/or Obsolescence of a Highway System; Doctoral Dissertation, Virginia Polytechnic Institute and State University.

. Hogg, R. V. and Ledolter, J.; Applied Statistics for Engineers and Physical Scientists; Macmillan Publishing Company, New York, N.Y., 1992.

. Kim, W. (1996); Systems Dynamics Model of a Highway Management System for VDOT; Doctoral Dissertation, Virginia Polytechnic Institute and State University.

. “Potomac Bridge Design Narrowed to Two Finalists.” Engineering News Record, May 20, 1996; p. 9. Williams, A. (1995); Interstate Highway Maintenance Management System; Masters Thesis; Civil Engineering Department, Virginia Polytechnic Institute and State University.

. Wilson, C.; Applied Statistics for Engineers; Applied Science Publishers, Ltd., Essex, England, 1972.

Evaluation Subsystem

APPENDIX A: DATABASE SPREADSHEETS

igen: | Confidence | | Page Acronym | Name Units | Value{x) : TIP (s x ) TDP (s, J Interval | Number

AADT “AVG Annual Daily Traffic; veh | See ¥ Average Daily Traffic Volumes on Interstate, 37

Volume I | Spreadsheet Arterial, & Primary Routes - 1994

Vi ily i ‘ AVG Annual Daily Traffic | wa model-generated

Volume Increasing Rate L ~ 4 I

ADTSD [AVG Distant Traveled per mi | User Defined | User Defined | Trip in Salem District '

AIR | ADT Increasing Ratio dim | User Defined ' User Defined |

icle by Cape ; ; | AVBC JAVG Vehicle by Capacity dim. Wa | model-generated |

‘Ratio | i

Vi Co I . ——

AVCF Annual Volume Conversion dum. User Defined | User Defined Factor |

[BCR Benefit-Cost Ratio dim. wa ' model-generated |

CAP AVG Network Capacity veh User Defined i User Defined |

[Continuous Compound | | CCBCR Benefit Cost Ratio dum. Wa model-generated

CLS Comprehensive Level of i dim | n/a \ | model-generated | Service | ' \

Non-User, | | | DANUBEN Discounted Annual Non User, S/yt | Wa | | model-generated | Benefit | :

to —__ op i ; * —t

DAUBEN (Discounted Annual User Sr Wa | model-generated | | Benefit

—— con Tn DFIO! | Diff in Fraction Industrial Syt wa ! model-generated

| Output to Input

DFTT Diff in Travel Time mim. Wa \ model-generated

DNUBEN [Discounted Non-User Benefit]; $/vr n/a model-generated I i

[DUBEN Discounted User Benefit S/ytr Wa | modei-generated

FFTTLKL | Free Flow Travel Time min. Wa i model-generated |

FSPD Free Flow Speed mph | User Defined User Defined |

HWY Total Construction , HCED Expenditure Discounted S/yr Wa | [rnodel-generated

HCEUD HWY Total Co nstnuction i Myr | n/a | model-generated | Expenditure Undiscounted | :

HEXPD HWY Lane-Mileage In-mi_ | Wa | model-generated | [Expanded i | | |

HWY Total Maintenance i HMED ewe diture Discounted Sy | Wa model-generated

‘HWY Total Maintenance . i HMEUD | F cenditure Undiscounted Siyr | Wa model-generated |

HRV Hourly Volume Wa | model-generated

IR Income Increasing Rate Siy1 nia model-generated

Income Increasing Rate US Census Bureau IIRP e O/yT 1.43 (www.census. gov/ftp/pub/hhes/income/4person.html l49

Parameter )

LHPA Level of Physical Adequacy . dim. nwa model-generated

LOSF [Level of Service Factor dim. Wa model-generated

Maint Expenditure per , MEPEPH Expanded Portion of HWY Sfyr Wa | model-generated

N Economue Life yr User Defined User Defined

NPVB Net Present Value of Benefit $ na | model-generated

NVB Net Value Benefit $ Wa ; model-generated

Per Capita Income of | | US Census Bureau PCIV Virgina S/person| 23,597.00 Vv (www.census.gov/ftp/pub/hhes/income/4person. html 154

_ | ) PLS Physical Level of Service dim. Wa model-generated

i te | Confidence! Page Acronym Name Units Value (x) TIP (s x ) TDP (s,, ) | Interval | Source Number

Total Construction TCED Expenditure Discounted S/yt | wa model-generated

Total Construction CEU ; : ' - TCEUD Expenditure Undiscounted | vy wa model-generated

TLCCD Total Life Cycle Cost $ Wa imodel-generated Discounted

TLCCUD j Total Life Cycle Cost $ Wa | model-generated Undiscounted | ‘ |

. Total Maintenance ' TME . . ~ {ED Expenditure Discounted Myr na | model generated

Total Maintenance ' MEU . , : i | . TMEUD enditure Undiscounted S/yr n/a : i ‘model-generated

TOTMILG | Total Mileage mi 117.91 ¥ L 164

. . . . See | ' Average Daily Traffic Volumes on Interstate. TT : min. : 1 \ ° LKL Travel Time On Link KL Spreadsheet | Y Astenal, & Primary Routes - 1994 165

- See : : ~| Average Daily Traffic Volumes on interstate. v Ann : | . ° 7

TVOL ual Traffic Volume veh Spreadsheet ‘ : Arterial, & Primary Routes - 1995 16

Undiscounted Annual User | IBEN | - UAUBE | Benefit $/yt Wa | model-generated

Undiscounted Annual Non- ANUBEN | - UANUBE} User Benefit S/yt Wa | model-generated

: i Jon- UNUBEN |Undiscounted Non-User S/yr Wa model-generated

Benefit : | [ UUBEN Undiscounted User Benefit S/yr n/a model-generated |

|voRC Vehicle Operating Cost $/veh. Va | | |model-generated |

OT ‘Value of Time $/min | User Defined | ‘User Defined |

WAHR Weighted AVG Hourly dim. | User Defined | | User Defined Volume Ratio \ ' |

Financial Subsystem

: - 1 Confidence Page A N: Units | Val TIP TDP (s, ° cronym ame ni alue (x) (s r) {s, J Interval Source | N er

Available Budget for H $f ! ! - AB Highway yr wa model-generated |

VG Dist Traveled . ADTPG oon ist ‘traveled per mi/gal 19.5 5.5 v FHWA 1994 Highway Stahstics Manual i 40

AT™ oe Miles Traveled per Mile/veh*yr.| —12,$00 100.000 Vv FHWA 1994 Highway Statistics Manual 42

AVG Value of Veh 5 . . AVVV Registered in Virginia $Wveh. 2,146.86 Vv DMV Office of Forecasting & Analysis 43

BB Bridge Budget S/yr 2,833.758.92: $,005,016 08] 3,018,059.80 Vv Six Year Plan & HTRIS 44

US Census Bureau Birth Rate Parameter of ;

BRPV Vir nia © ero persons/yr 001459) V (www.census.gov/ftp/pub/population’ www/statepop. 56

e htmi)

BRYV Birth Rate of Virginia dim wa model-generated

po ' US Census Bureau

Death Rate Parameter of 2 DRPV Vin nia © etero persons/yr | 0 008249 v (www census.gov ftp/pub/population/www/statepop. 105

8 | htm!)

' DRV Death Rate of Virginia dim | wa L model-generated

F | f

FAV Federal Aid to Virginia S/yr | 466,486.400.00 Vv FHWA 1994 High way Statistics Manual 108 1

! FBHC _'Fract Budget to HWY dim 0.8142 ¥ 1 - FBHM 123 Construction | \

FBHM Fract Budget to HW Y Maint. dim : 0.4407 v HTRIS & Data Manipulation | 124

i . 1

FCBB Fract Budget to Bndge dim | 0.0181 0.0189 0.0186 v 1 -FBEUI 128

Fraction of Construction : : . . a 9.969321 5 ‘ Be 2 FCBSD Budget to Salem District im v ix Year Plan & Data Manipulation 129

FMBB mie Budget to! sim 00177 | 90626 =: 0401 ¥ See Recommended Changes 130

Fraction of Maintenance . i . : d ' 009899 j FMBSD Budget to Salem District im | V Six Year Plan & HTRIS | 131

F tor Veh. Fuels T: . . FMFTH ract. Motor Veh. Fuels Tax dim. i 0 838983 Vv Planning & Information Group handout 132

ito HMO | |

|

. Mot . Fuel . ‘ FMFTT Frat Motor Veh. Fuels Tax dim i 0 141243 V Planaing & information Group handout 133

FMVLFH Fract. Motor Veh. License dim. ' 9.603773 v Planning & Information Group handout 134 Fee to HMO

FMVLFT_ [Pract Motor Veb. License dim | 0.113208 ¥ Planoig & Information Group handout | 135 Fee to TTF :

Fract. Motor Veh. Sales & ! d : 0 666667 Pi FMVSTH Use Tax to HMO Im. : v | anning, & Information Group handout 136

Fract. Motor Veh Sales & : ! d ‘ 9.333333 PI FMVSTT |. Tax to im. Vv Janning & Information Group handout 137

Frac of Population of the . : Vv d ‘ a/ v del-generated i

FPS Salem Distnct to VA ‘ m a model-gen i

Fraction of Revenue to . i FRHWY d 0.955 6 Year Pt:

Highway Budget moo v car sven (38

FSSH hae) State Sales Tax to dim. 900 v Planning & Information Group handout 139 po

FSST Fract. State Sales Tax to TTF dim. 0.094444 Vv Planning, & Information Group handout 140

Highway Construction A 82,746,000.00 6 Pi

HCBSD Budget in Salem Distnet syr v Year Plan 141

Hcpy Highway Construction Siyr | 887,666,000 00 V 6 Year Plan 142 Budget in Virginia

HWY Maint Budget for HMB $/ 75 286,472.31 v HTRIS Punt Met Only yr 2 M45

HWY Maint Budget of 7 9,022 2 HMBS ig jam Distnct Syr $289,022 28 Vv HTRIS

HMBV [Highway Maintenance Syr | 760,572.000.00 v 6 Year Plan 146 Budget in Virginia '

HMO HWY : agement and S/yr ‘ n/a model-generated Operation Fund L

IMRPV in-Migrahon Parameter of dim. 0.001168 V US Census Bureau 150

Virginia : (www. census.g ov/fip/pub/population/wwwi/statepop

IMRV [In-migration Rate of Virgini dim Wa model-generated L

I

MFT |Metor Fuels Tax S/yr na modei-generated

MVLF ‘Motor Veh. License Fee S/yt n/a model-generated

MVSUT [Motor Veh. Sales & Use Tax | S/yr wa model-generated i

30

i ' { TIP |rpp(s.)' Confidence t Page Acronym Name Units Value (x) ' (s,) (s;,) Interval | Source Number

| Out-Migration Parameter of . ' US Census Bureau .001737 ‘ : 2

OMRPV Virginia | dim. 0.00173 | (www. census. 0v/fip/pub/population/www/statepop. Is

CMRV Out-migration Rate of dim i n/a model-generated Virginia ‘

: US Census Bureau PPR ai Purchase Rat oo 22,570.47 ‘ ‘ 5

Person rehase Aare S/yr-person | ’ (www.bea doc. gov/bea/statp:. htm#table4 15

PS Population of Salem District person i 662,737 ' N VDOT County maps/1990 Census 156 }

. oo \ 1 US Census Bureau PV Populati f Virginia 0} 6,618,358 . 7 . 157

Opulanon of ee} person (www census. gov/ftp/pub/population/ www statepop. 5

RMFT Rate for Motor Fuels Tax Sgal. : 0.177 Planning & Information Group handout 188

—_ ¢ T RMVLF Rate Motor Veh. License Fee wer 26.50 ” Planning & Information Group handout 159

5 4 t ! RMVSUT Rate for Motor Veh. Sales & dum { 0.03 * . Planning & Information Group handout 160

Use Tax i

RSST Rate for State Sales Tax S/yr. 0.045 1 1 Planning & Information Group handout 161

1 Data Manipulation: Personal Purchase 79,454,500. ! ‘ ' . Loe 385 States Sales Nyr 149,379 500.47 : . |Rate* Population of Virginia 163

SST State Sales Tax S/yr n/a model-generated

TIF Transportation Trust Fund Syr n/a ‘model-generated

TTRV Total Revenue in Virginia Syr n/a 'model-generated

Ve Tvvv _ [Total Value of Veh | $ 353,285,000.00 DMV Office of Forecasting & Analysis 169 Registered in Virginia i

VAGR {Veh AVG Annual Growth dim 00208 0,009 yo DMV Office of Forecasting & Analysis 170 Rate in VA :

VINC vehicle Increasing Rate in vel/yr | 101,551.51 | 5,728.74 og DMV Office of Forecasting & Analysis 171

VMT Vehicle-miles Traveled yveb-myyr wa : + model-generated

VV No. of Vehicles in Virginia veb | 4,982,284 603,028 | ‘ iDMV Office of Forecasting & Analysis 172

31

Functional Subsystem

Acronym | Name Units Value (x) ‘ TIP (s ) TDP (s, J Content Source | wee

Biccp | Bndges Life Cycle Cost $ wa model-generated Discounted : i Bridges Life Cycle Cost :

BLCCUD Undiscounted $ wa model-generated

No. of Bridges Major MOR - B Repaired b/y n/a model-generated

BMNR N°. of Bridges Minor b/y ma ! model-generated Repaired i

No. of Bridges Preventve | BPM to by n/a } model-generated

Maintained ' 2 |

BWC |Bridge Widening Cost $/b $00,000.00 350,000.00 | 200,000.00 | v See Recommended Changes 58

AVG Cost of Beanng & i | [ | ! i 0 0. . CBAR Anchor Bolt Repl ent $/ 7,680.00 3,840.00 | 960.00 v See Recommended Changes 59

AVG Cost of Concrete Beam : | "CBR - RU 5,800.00 | . CCB. End Repair $/ 12,180.00 780! | 1,160.00 See Recommended Changes 63

AVG Cost of Concrete 05.8 . ‘ . \ CCDR ap} Repair $/ | 3,105.81 | 1,505.85 | 15851 v See Recommended Changes 62

1 1

AVG Cost of Cathodic ‘ 739. 20 3.60 ccP Protection $% | 414,739.60 | 260,163.20] 62,23 ’ v See Recommended Changes 65

| CDER | AVG Cost of Deck Edge $b | 399419 | 293214 | 119248 | v See Recommended Changes 67

'Repar i

CDKR AVG Costof Deck $/> | 116,047.82 | 72,795.78 | 17,413.47 | v See Recommended Changes 69 Replacement ! :

cDo AVG Cost of Deck Overlay | $/b | 87,463.41 | 54,865.17 ' 13,124.29 | v See Recommended Changes ; 71 } ; t L !

AVG Cost of Drainage

CDSR System Replacement & $/o 5,000.00 ' v See Recommended Changes 73

Repair | AVG Cost of Expansion ‘ CEJ : 753.4 134. 429.62 v SeeR 74 M Joint tenance $/b 1,753.49 1,134.32 - ee Recommended Changes

t - + ——F

cep AVG Cost of Expansion $/ | 3,562.90 | 230483 | 872.95 v See Recommended Changes 16 iJount Replacement : _

i

CPCH AVG Cost of Patching 8 40,648.67 | 25,498.62 | 6,099 52 v See Recommended Changes 78

| . CPGM jAVG Cost of Parapet Guard $4 2,917.43 2,121.77 393.38 | Vv See Recommended Changes 80

‘Rail Maint.

AVG Cost of Repair of 7,868.4 6,786.75 3,855.71 Vv t CRA Abutment $/ 5 See Recommended Changes 82

L ,

crcp [AVG Cost of Repair of S/o 100,000.00 v See Recommended Changes 84 Collision Damage

AVG Cost of Replacement : ‘ ro) 3. 80 CRLA of Abutment $/b 18,231.42 | 15,725.11 8,933.8 Vv See Recommended Changes 85

crip AVG Costof Replacement | 5 | 94 og746 | 36,702.27 | 0.00 | ¥ See Recommended Changes 87 of Pier

' | CRP AVG Cost of Repar of Pier | $/b 65,122.59 | 28,414.80 | 9.00 v See Recommended Changes 89

CRPT AVG cost of Repainting $/ | 19,930 68 | 10,353.60 | 1,743.76 | v See Recommended Changes 91 i

cs AVG Cost of Scour $/ 311.81 441.45 250.80 v | See Recommended Changes 93

AVG Cost of Seahng | = 656. 994.22 | $,50044 | v See R csDCc DeckiC $/o 36,656.28 | 22, ee Recommended Changes 95

AVG Cost of Structure Steel 302. 7,904.00 832.00 CSMR [oon dary Member $/ | 16,302.00 9 32.0 | N See Recommended Changes 97

| CSP -AVG Cost of Spot Painting | $/> | 5,000.96 | 2597.90 | 43754 | v See Recommended Changes 99

cssr [AVG CostofSuperstructure |g, | 4o4.771.57 | 237,489.77 | 53,908.54 | v See Recommended Changes 101 Replacement

DISR Discount Rate dim. User Defined V User Defined

HLccp [HWY Life Cycle Cost $ wa ¥ model-generated Discounted { | HWY Life Cycle Cost i

HLCCUD | discounted $ n/a ; v model-generated

INFLF Inflation Factor “lyr 2.6 | v www.odci gov/cia/publicationa/95 fact/us.html 151 \ [

TNFLR Inflation Rate dim. User Defined User Defined Maintenance Cost for |

(CDFH - = ni del- ed M Deticient Highway | Sin ™ 2 model- generat

32

| Confidence Page Acronym |Name | Units Value (x) iT IP (s,) TDP (s.,) Interval Source Numbe

Maintenance Cost for . ) . nf - MCDTH Deteriorated Highwa $An-mi ‘a model-generated

MIRCB Major Repair Cost of $f wa | model-generated Bridges

MnRcB_ Minor Repair Cost of sd Wa model-generated Bridges |

péMca [Preventive Maint Costof | ¢,, wa | model-generated Bridges

RHCB R . tation Cost of Sb Wa model-g enerated Bridges

RPCB [Replacement Cost of Bridges! S/b wa ] model-g enerated

Total Bridges Expenditure | - TBED Discounted $Ar n/a model-generated

Total Bridges Expenditure TBEUD Undiscounted SAr wa model-g enerated

TBEXPD | Total Bridges Expenditure SAr n/a model-g enerated

Total HWY Construction el- THCE Expenditure Mr n/a model-g enerated

. FE

THED ‘| Total HWY Expenditure | 4, wa model-generated | Discounted { Total HWY Expenditure | THEUD |, Giscounted Sr n/a model-generated |

THME | Total HWY Maintenance SAyr wa | model-generated |Expenditure , [_

TIME Time yr. User Defined User Defined

Weighting Factor for ] WFBAR |Beanng & Anchor Bolt dim. 0.01 v See Recommended Changes 173

Replacement

wrepr | Weehting Factor for dim 0.13 v | See Recommended Changes 174 Concrete Beam End Repair

| Weighting Factor for 0. R WFCDR Concrete Di Repair dim 03 v See Recommended Changes i75

Weighting Factor for : . : R ed WFCP | cathodic Protection dim 0.01 NV See Recommended Changes 176

WEDER | Weiehtng Factor for Deck | ain, 0.04 v See Recommended Changes 177 Edge Repair

, Weighting Facior for Deck . WFDKR Rep ent dim. 0.65 Vv i See Recommended Changes 178

WFDO Oncay Factor for Deck dim. | 0.17 | Vv | see Recommended Changes | 179

Weightng Factor for

WFDSR_ | Drainage Sys Replace & dim. 0.07 Vv See Recommended Changes 180

| Repair | | Weighting Factor for | |

WFEJM Expansion Joint dim. 0.63 V See Recommended Changes 181 Maintenance

Weightng Factor for . : 0. 2 WFEJR Expansion Joint Recons dim 29 v See Recommended Changes 182

wrpcH | Weighting Factor for dim. 0.21 V See Recommended Changes 183 Patching

| Weighting Factor for Parapet] .. 1

. v ‘ WFPGM Guard Rail Maint ce dim. 0.07 | See Recommended Changes 184

[Weigh f eighting Factor for Repair : . 0.14 See Ri ied WFRA lof Abutment dim N | ee Recommended Changes 185

Weighting Factor for Repair | . 0.14 v See R ded WFRCD of Collision Damage dim ee Recommended Changes 186

Weighting Factor for : WFRL : 0.0 R

[Replacement of Abutment | aim 1 v |see ecommended Changes 187

Weighting Factor for : | WFRL. . . 0.01 v See Recommended Chang

P Replacement of Pier dim « 188

WFRP ee Factor for Repair | ai, 0.70 ty | See Recommended Changes 189

Weighting Factor for | | . 0.14 See R ded WFRPT Repainting dim Vv ee Recommended Changes 190

WFS Weighting Factor for Scour | dim. 0.13 Vv See Recommended Changes i91

WFSDC noeene Factor for Sealing| ai, 0.13 v See Recommended Changes 192

Weighting Factor for | WFSMR_ [Structure Steel Secondary dim. 0.03 v See Recommended Changes 193

Member Replace & Repair

WFSP Weighting Factor for Spot dim. 0.04 v See Recommended Changes 194 Panting

Weighting Factor for Super - . 0.2 R WFSSR g ctureR ent dim ; 2 v See Recommended Changes 195

33

Physical Subsystem: Bridge Management System

Acronym | Name Units Value (x) TIP (s x ) TDP (s; ) Confidene ° Source Never

Accelerated Deterioration : 22 Arte Time of Bridges yt 22 | 28 25 Vv See Recommended Changes 39

BCC Bridges in Critical Condition} b Wa model-generated

Bridges in Func Adequate BFACC | Gitical Condition b i 0 0 | 0 v Super Natural query of HTRIS 45

Bridges in Func Adequate | po BFAFC Fair Condition b | 121 | 277 | 633 v Super Natural query of HTRIS 46

Bnidges in Func Adequate \ | BFAGC |e od Condition b | 100 | 370 | 1031 v Super Natural query of HTRIS 47

FAI Bridges Fune. Adequacy dim. | na modei-generated Index 1

Bridges in Func Adequate ! BFAPC | sor Condition b | 6 16 53 Vv Super Natural query of HTRIS 48

Bridges in Func Adequate 1 i BFAPFC Preferred Condition b 0 0 | 0 v Super Natural query of HTRIS 49

BFC Bridges in Fair Condition b Wa model-generated

Bnidges in Func Inadequate I | BFICC Critical Condition b | 0 0 0 v Super Natural query of HTRIS 50

Bridges in Func inadequate BFIFC Fair Condition b 1 20 89 ¥ Super Natural query of HTRIS | 51

Bridges in Func Inadequate I | BFIGC Good Condition b | 2 4 34 v Super Natural query of HTRIS 52

Bridges in Func Inadequate BFIPC Poor Condition b ! a 36 79 v Super Natural query of HTRIS | 53

Bridges mn Func Inadequate | BFIPFC | 5, ferred Condition | b | ° 0 0 Vv Super Natural query of HTRIS 54

BGC Bridges in Good Condition |b Wa model-generated 1 1 |

BPAI Bridges Physical Adequacy dim. | Wa model-generated Index i

BPC Bridges in Poor Condition bi va model-generated

Bridges in Preferred PF - | - BPFC Condition db wa model-generated

BW Bridge Widerung b/yt | Wa model-generated

BWB Bridge Widening Budget Siyr 150,000.00 | v model-generated 57

DTTB Det erioration Time of yr 21 | 17 ] 19 v See Recommended Changes 106 Bridges | |

. . ! Dean Hackett: Bridges that are new go from

ETB Exposure Time of Bridges yt os y _| preferred to good condition after one winter. 107 F

Func Adequate Accelerated | | AAD . : b/yr | -

F. RB Depreciation Rate of Bridges wr wa | v model-generated

‘Func Adequate Deterioration FADRB pate of Bri dges byt Wa N model-generated

Func Adequate Exposure f | FAERB Rate of Bridges b/yr va v model-generated

Func Adequate Major ; . bs v - FAMJRB Repairs of Bridges ‘yr wa model-generated

Fune Adequate Major FAMJRBB Repairs Budget of Bridges Syr na | Vv model-generated

FAMNRB Func Adequate Minor b/yr | va Vv model-generated Repairs of Bndges |

Func Adequate Minor . . Mv - FAMNRBB) p eairs Budget of Bridges Siyt ‘a N model-generated

Func Adequate Preventive b/ - FAPMB Maint of Bridges ‘yr wa v model-generated

Func Adequate Preventive : FAPMBB |) int Bu dget of Bridges dim Wa v model-generated

Func Adequate Serious FASDRB Depreciation Rate of Bridges b/yr Wa model-generated

FBBW Fract Budget to Bridge dim | 0.5293] 0.0187; — v 6 Year Plan 109 Widening |

Fract Budget to Func |

FBFAIJRB | Adequate Major Repair of dim | 0.4022} 0.1182] 0.1233 v See Recommended Changes 11]

Bridges

Fract Budget to Func

FBFAN RB Adequate Minor Repairs of | dim | 0.0352] 0.0201 | 0.1223 Vv See Recommended Changes | 113

Bridges

: ; Confid , P. Acronym | Name | Unit | Value (x) TIP (s,) | TDP [s; ) ; Interval | Source | Nunther

Ree Bain Cet fanation | FBFAPMB /| Adequate Preventative dim } 0.0321; 0.0370 0.0971 v See Recommended Changes | Ws |

Maintenance of Bridges |

Fract Budget to Func ' j

FBFIJRB | Inadequate Major Repair of | dum | 0.0000| 02660 0.1838 v See Recommended Changes | 117

Bridges _ |

|Fract Budget to Func t ;

FBFINRB {Inadequate Minor Repair of | dir | 9.0003) 0.0015 00172 Vv See Recommended Changes | 119

| Bridges |

Fract Budget to Func | FBFIPMB | Inadequate Preventive dim | 0.0006 | 0.0003 ' 6 0032 v See Recommended Changes | 121

Maintenance of Bridges | |

Fract Budget to . | “aos . 9 0600 a — 2

FBRHB Rehabilitation of Bridges dim 00 a 0182 N | ‘ HTRIS | 12s 4 y 1 ,

FBRPB Fret Budgetto Replacement] | gang) oassa v 6 Year Plan | 126 of Bndges i | |

Func Inadequate Accelerated :

FIADRB Depreciation Rate of Bridges biyr ma : model-generated

Func Inadequate '

FIDRB Deterioration Rate of b/yr va model-generated

\ Bridges ‘

Func Inadequate Exposure i - FIERB Rate of Bridges | b/yr na model-generated

FIMIRB |Punc Inadequate Major b/yr wa model-generated Repairs of Bidges :

Fune Inadequate Major | / FIMIRBB | Repairs Budget of Bridges oy | va model-generated

FIMNRB Func Inadequate Minor b/yr na model-generated Repairs of Bridges | |

Func Inadequate Minor : : - i - FIMNRBB Repairs Budget of Bridges $41 wa model-generated

Func Inadequate |

FIPMB Preventative Maint of b/yr | Iva model-generated

Bnidges | ‘

Func Inadequate |

FIPMBB _ |Preventative Maint Budget S/yr j wa model-generated

| of Bridges |

Func Inadequate Serious : ‘ yt: ' : - FISDRB Depreciation Rate of Bndges b *| wa ; model-generated

ORB Pride Rate of b/yr va model-generated

OTB Brien Fume of yt 20 | v See Recommended Changes 153

habilitats dget of ' PY RHBB re yes on Budget of siyr wa | model-generated

RHRB edges Rate of b/yr na | model-generated |

+ T t

RPBB Baie Budget of $/yt | Wa : model-generated | !

RPRB / Replacement Rate of Bndges| b/yr na J. model-generated } | :

SDTB | Serious Deterioration Time yt 1S | 30 32 N See Recommended Changes 162 [of Bndges

WFCB Bridees Factor for Critical! gi, | User Defined L User Defined

WFGB | Weighting Factor for Good dim User Defined : ; User Defined | Bridges | _|

ty v

WFPB (ages Factor for Poor dim | UserDefined | | User Defined

WEPFR | Weighting Factor for dim | User Defined | User Defined Preferred Bndges | |

Physical Subsystem: Pavement Management System

i | Confidence Page Acronyin Name Units Value (x) | TIP (s x ) TDP (s; J Interval | Source | Number!

, + ARH Aging Rate of Highway In-mi/yr Wa | i model-generated

on ATH Aging Time of Highway yt 6 | Transportation Research Counal 41

Deteriorating Rate of i j ' DRH In-m1y : del-. ted ehway n-mi/yr Iva model-g enerat

DHT Deterio e Time of yr 5 Vv | | Transportation Research Council 104 Highway i | Fract Maint Budget to to FMBDFH dim W | del-generated Deficent HWY a | model-gen

FMBDTH FT¢t Maint Budget to dim na model-generated Deteriorated HWY ' 1 |

HpFpc — Highway in Deficent In-mi | 8.10 45.04 ~ Poy \Pave Tech PCI Ratngs 143 Pavement Condition ! | | ! =

; ' : : ' T HDRM Highway Down Ratio for dim | wa \ i model-generated |

Maintenance : | a Lo

| Highway in Deteriorated : ' | HpTepc | UB MWay in Veetenioral Inm | 22039 | 1.06878; —- foo yw Pave Tech PCI Ratings 144 Pavement Condition . | ‘

Po ee I : ‘

HPAI Highway Physical Adequacy dim wa model-generated Index | * '

__ - : Hsrpc — Haehway im Sufficient inmi | 271.15 | 1,451.91 --- voy |Pave Tech PCI Ratings 147 = Pavement Condition | i

MRDFH Maintenance Rate for In-mrvyr n/a | model-generated Defiaent Highway | a i | ee i]

: ' Maintenance Rate for . :

MRDTH -mi i del- ed Detenorated Highway in-mv/yr wa moder genera

| 4 \

Maintenance Replacement | MRRH . “P In-mi/yr n/a ! : -model-generated

Rate of Highway ' t ' }_____.. + + —_______—. i _________—_——-.

TMH Total Lane-mileage of In-m wa i model-generated Highway ee Po

WEDECH Weighting Factor for dim User Defined ; | User Defined Defiaent Condition of \ Weightng Factor for i ‘ : | WFEDTCH ene | dim User Defined ; User Defined Detenorated Condition of | | :

Oo I [ i i a

36

APPENDIX B: PARAMETER WRITE-UPS

Average Annual Daily Traffic Volume (AADT)

Definition/Assumptions

AADT is the average hourly one-way traffic per mile of route.

Formula

AADT.K=AADTJ+(DT)(ADTINC JK) Value (veh)

See spreadsheet below.

Source

1. Use the “Relative Density of Traffic by Route” table for the Salem District found in the Average Daily Traffic Volumes on Interstate, Arterial, and Primary Routes - 1994. Input Route, Mileage, and Average 24-hour Traffic per Mile of Route into an Excel spreadsheet.

3. Sort by Route.

ho

37

Spreadsheet

Route Mileage Ave. 24 Hr. Traffic per Mile of Route

1-581 6.75 60,725

1-77 24,29 25,171

I-81 86.87 33,201 US 11 68.57 12,392

US 219 1.73 4,900 US 220 108.43 20,126

US 220 BUS 0.27 30,000 US 221 89.87 6,951

US 460 99.91 15,308 US 460 BUS 3.46 6,542 US 501 14.29 2,459

US 52 27.44 3,638

US 58 83.96 6,856 US 58 BUS 6.71 15.417

VA 100 48.54 Jat VA 103 13.43 2,468

VA 108 4.24 3,300 VA 112 0.21 1,100

VA 114 8.25 10,139

VA 115 3.14 12,210 VA 116 12.78 3,670

VA 117 1.35 21,000 VA 118 0.20 13,000

VA 122 50.14 4,012 VA 148 0.87 3,900

VA 174 4.29 3,900 VA 177 2.33 3,800

VA 18 5.12 300 VA 220 ALT 6.83 16,357

VA 232 0.58 5,800 VA 24 34.36 5,315

VA 311 40.24 3,899

VA 320 1.75 300 VA 40 47.79 5,680 VA 419 6.97 28.014

VA 42 51.50 2,449 VA 43 48.86 1,420

VA 43 Y 0.11 763

VA 457 2.62 4,800 VA 57 38.22 5,693

VA 57 ALT 4.09 10,000

VA 61 13.63 775 VA 69 0.25 3,400

VA 8 55.14 3,475 VA 87 4.10 8,229

VA 94 9.20 1,100 VA 97 8.27 1,100

VA 99 1.35 5,800

38

Accelerated Deterioration Time of Bridges (ADTB)

Definition/Assumptions

ADTB is defined, as the time required for a bridge condition rating to go from “Fair” to “Poor”.

Formula

Constant.

Value (yr.)

Interstate 22

Primary 28 Secondary 25

Source (see Recommended Changes)

Current

1. This type of information is unavailable at this time, as it is not collected. 2. Dean Hackett, Salem District Bridge Engineer, with a Super Natural query

of HTRIS, obtained data used for this parameter.

3. Values were obtained by subtracting the “Year Built” from the “Year Improved” for each of the Road and Bridge classifications.

Recommended

1. For new structures, time begins subsequent to the completed structure’s first winter, as ordinary maintenance is performed to mitigate the effects of that winter, thereby placing the bridge in the “Good” condition.

2. For existing structures, time begins subsequent to any upgrade or downgrade to its existing condition.

3. Deterioration Times are then calculated by finding the difference between the date of classification for the older (higher) condition and the date for the newer (lower) condition.

Spreadsheet

N/A

39

Average Distance Traveled per Gallon (ADTPG)

Definition/Assumptions

Passenger vehicles include pickup and panel trucks (with a registered gross weight of 27,500 lb.), as well as passenger vehicles.

Formula

Constant.

Value (mi./gal)

Passenger 19.5 Other 5.5

Source

1. Federal Highway Administration’s (FHWA) Highway Statistics Manual - Table VM1.

2. An alternate source is the Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis. Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

40

Aging Time of Highway (ATH)

Definition/Assumptions

Is the time for pavement to decline from a “Good” rating to a “Fair” rating.

Formula

Constant.

Value (yr.)

6

Source

1. This data is unavailable at this time due to the Transportation Research Council (TRC) upgrading their database system. It is estimated the new system will be in place in January 1997.

2. Mr. Tom Freeman of the TRC provided this estimate. (804) 293-1957.

Spreadsheet

N/A

41

Average Miles Traveled per Vehicle (ATM)

Definition/Assumptions

Formula

Constant.

Value (mi./veh*yr)

Passenger 12,500 Other 100,000

Source

1. Federal Highway Administration’s (FHWA) Highway Statistics Manual - Table VM1.

2. An alternate source is the Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis. Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

42

Average Value of a Vehicle Registered in Virginia (AVVV)

Definition/Assumptions

Formula

Constant.

Value ($/veb)

2,146.86

Source

1. This value was calculated from data obtained from the Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis. Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473. The total amount of money collected from the Motor Vehicle Sales & Use Tax (MVSUT) is $353,285,000.00. By definition, a vehicle is either taxed at 3.0% of its total worth or $35.00, whichever is greater.

3. The value was calculated with the following formulas: MVSUT - ($35.00 x 360,000) = $340,685,000.00

Vehicles in Virginia (VV) - 360,000 = 5,125,309

$340,285,000 ——_——"___ = $2. 215.70 (5,125,309 x 3%)

a

ho

5

= $1,166.67 3% [($1.166.67 x 360,000) +($2.215.70 x 5,125,309)|

| = $2146.86 5,485,309 4. Numerical calculations of this sort are expedited through the use of a

spreadsheet.

Spreadsheet

N/A

43

Bridge Budget (BB)

Definition/Assumptions

The Bridge Budget consists of the ordinary, maintenance replacement, widening, and replacement expenditures. For 1995 data, there was not any money budgeted for bridge replacement.

Formula

BB.K=clip(clip(1.49E6*K, 1.49E6, TIME.K,5)FMBP.K*HMBS.K, TIME.K,0)

Value ($/yr.)

Interstate $2,833,758.92

Primary $8,005,016.08

Secondary $3,018,059.80

SOUrCE

1. In HTRIS, run an inquiry for the 220 (Ordinary Maintenance), 460 (Maintenance Replacement), and 404 (Bridge Inspections). Separate the inquiries by System: 3 (Primary), 4 (Secondary), and 5 (Interstate).

3. In Excel, for each of the categories, use this equation:

Bridge Widening = BWC

Act 221+ Act 222 + Act 223 + Act 224+ Act 404 = Ordinary Maintenance

Act 461+ Act 462 + Act 463 + Act 464+ Act 465 + Act 466+

Act 467 = Maintenance Replacement

bo

Bridge Widening + Ordinary Maintenance + Maintenance Replacement = BB

Spreadsheet

Maintenance Construction Total

Interstate $1,333 ,758.92 $1,500,000.00 $2,833,758.92

Primary $4,710,016.08 $3 295,000.00 $8,005,016.08

Secondary $3 018,059.80 --- $3,018,059.80

44

Bridges in Functionally Adequate Critical Condition (BFACC)

Definition/Assumptions

BFACC is detined as those bridges whose design still meets the federal specifications, but has advanced deterioration of one or more of its primary structural elements, z.e., fatigue cracks in steel or shear cracks in concrete.

Formula

BFACC.K =BFACC J+ (DT)(FASDRB JK-RHRB,JK)

Value (b)

Interstate Q

Primary 0 Secondary 0

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”.

2. Break the data down into the three systems (3, 4, & 5). 3. For each of the sufficiency ratings, multiply the respective percentages by

its respective items (bridge or culvert) and total the two values, z.e.,

[ Bridges!" x Bridges" | +(Culvertsinews x Culverts" = BFACC o Adequate & Critical] Number (%e Adequate & Critical) sumber

Spreadsheet

See spreadsheet on page 55.

45

Bridges in Functionally Adequate Fair Condition (BFAFC)

Definition/Assumptions

BFAFC is defined as those bridges whose design still meets the federal specifications. All primary structural elements are sound but may have minor section loss, cracking, spalling or scour.

Formula

BFAFC.K =BFAFC,] + (DT) (FADRB.JK-FAMNRB.JK-FAADRB. JK)

Value (b)

Interstate 121

Primary 277 Secondary 633

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”. Break the data down into the three systems (3, 4, & 5).

3. For each of the sufficiency ratings, multiply the respective percentages by its respective items (bridge or culvert) and total the two values, z.e., (Bridgestts x Bridges |. (cutverts'#** se Culverts ~ BFAFC

a Adequate & Fur } i Number) %9 Adequate & Farr] (Number 3

ho

Spreadsheet

See spreadsheet on page 55.

46

Bridges in Functionally Adequate Good Condition (BFAGC)

Definition/Assumptions

BFAGC is defined as those bridges whose design still meets the federal specifications, but there may be some minor problems.

Formula

BFAGC.K =BFAGC,] + (DT)(FAERB.JK-FAPMB.JK-FADRB.JK)

Value (b)

Interstate 100

Primary 370

Secondary 1031

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”.

2. Break the data down into the three systems (3, 4, & 5). 3. For each of the sufficiency ratings, multiply the respective percentages by

its respective items (bridge or culvert) and total the two values, z.e.,

(Bridgesit= x Bridges tn | +4 [Culverts x Culverts" _ BFAGC

(°o Adequate & Good) (9° Adequate & Good {Number |

Spreadsheet

See spreadsheet on page 55.

47

Bridges in Functionally Adequate Poor Condition (BFAPC)

Definition/Assumptions

BFAPC is defined as those bridges whose design still meets the federal specifications. Poor condition is defined as advanced section loss, deterioration, spalling or scour, with local failures possible.

Formula

BFAPC.K =BFAPC,] +(DT)(FAPMB.JK +FAMNRB.JK +FAMJRB.JK+RHRBJ K+RPRB.JK +BW.JK-ORB.JK-FAERB JK)

Value (b)

Interstate 6

Primary 16 Secondary 53

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural querv: “Breakdown of Structures by Sufficiency Ratings”. Break the data down into the three systems (3, 4, & 5).

3. For each of the sufficiency ratings, multiply the respective percentages by its respective items (bridge or culvert) and total the two values, z.e.,

(Bridges! x Bridges) | + (Culverts x Culverts" = BFAPC i%> Adequate & Poor ! 1% Adequate & Poor | {Number |

bho

Spreadsheet

See spreadsheet on page 55.

48

Bridges in Functionally Adequate Preferred Condition (BFAPFC)

Definition/Assumptions

Bridges in this category are assumed to need ordinary maintenance after one winter and therefore, are considered “Adequate Good Condition”.

Formula

BFAPFC.K=BFAPFC_] +(DT)(FAPMB.JK +FAMNRB.JK+FAMJRBJK+RH

RB.JK+RPRB.JK+VW.JK-ORB.JK-FAERB.JK)

Value (b)

Interstate 0

Primary 0 Secondary 0

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”.

2. Break the data down into the three systems (3, 4, & 5). 3. For each of the sufficiency ratings, multiply the respective percentages by

its respective items (bridge or culvert) and total the two values, z.e, . Interstate : Interstate . Interstate ” Interstate Ie x J r —_ 2 A : ( Bridges" adewuate & Preferea’i * DIdges, =: | +(con CTS. Adequate & Prefered) * Culverts,. xe | = BFAPFC

Spreadsheet

See spreadsheet on page 55.

49

Bridges in Functionally Inadequate Critical Condition (BFICC)

Definition/Assumptions

BFICC is defined as those bridges whose design does not meet the federal specifications, but has advanced deterioration of one or more of its primary structural elements, 7.¢e., fatigue cracks in steel or shear cracks in concrete.

Formula

BFICC.K-BFICC,] + (DT)(FISDRB.JK-RPRB.JK)

Value (b)

Interstate 0 Primary 0 Secondary 0

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings’.

2. Break the data down into the three systems (3, 4, & 5). 3. For each of the sufficiency ratings, multiply the respective percentages by

its respective items (bridge or culvert) and total the two values, 2.e.,

(Bridges x Bridges "2" J+ (c ulverts re x Culverts 2" = BFICC % Inadequate & Cnitical } (Number } o Inadequate & Cntical} {Number }

Spreadsheet

See spreadsheet on page 55.

50

Bridges in Functionally Inadequate Fair Condition (BFIFC)

Definition/Assumptions

BFIFC is defined as those bridges whose design does not meet the federal specifications. All primary structural elements are sound but may have minor section loss, cracking, spalling or scour.

Formula

BFIFC.K = BFIFC J + (DT)(FIDRB.JK-FIMNRB.JK-FIADRB.JK)

Value (b)

Interstate 1

Primary 20 Secondary 89

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”.

2. Break the data down into the three systems (3, 4, & 5).

3. For each of the sufficiency ratings, multiply the respective percentages by its respective items (bridge or culvert) and total the two values, i.e.,

(Bridges x Bridgesynre | + (Cutvertsit"= x Culverts" ] = BFIFC (° Inadequate & Fair | ( Number (% Inadequate & Fair | {Number )

Spreadsheet

See spreadsheet on page 55.

51

Bridges in Functionally Inadequate Good Condition (BFIGC)

Definition/Assumptions

BFIGC is defined as those bridges whose design does not meet the federal specifications, but there may be some minor problems.

Formula

BFIGC.K =BFIGC,] + (DT)(FIERB.JK-FIPMB .JK-FIDRB JK)

Value (b)

Interstate 2

Primary 4 Secondary 34

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”. Break the data down into the three systems (3, 4, 8& 5).

3. For each of the sufficiency ratings, multiply the respective percentages by its respective items (bridge or culvert) and total the two values, 7.e., (Bridges Interstate x Bridges" + (Cutversi x Culverts" —_ BFIGC

(9 Inadequate & Good! ! Number i (°o Inadequate & Good} Sumber

ho

Spreadsheet

See spreadsheet on page 55.

nn bo

Bridges in Functionally Inadequate Poor Condition (BFIPC)

Definition/Assumptions

BFIPC is defined as those bridges whose design does not meet the federal specifications. Poor condition 1s defined as advanced section loss, deterioration,

spalling or scour, with local failures possible.

Formula

BFIPC.K =BFIPC,J + (DT)(FIADRB.JK-FIMNJRB.JK-FISDRB.JK)

Value (b)

Interstate 0

Primary 36 Secondary 79

SOUrCE

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”. Break the data down into the three systems (3, 4, & 5).

3. For each of the sufficiency ratings, multiply the respective percentages by its respective items (bridge or culvert) and total the two values, .e., [Bridgos'*" x Bridges + (Culverts x Culverts _ BFI PC

(°o Imaidequate & Poor! (Number | (%> Inadequate & Poor | Number !

bho

Spreadsheet

See spreadsheet on page 55.

Bridges in Functionally Inadequate Preferred Condition (BFIPFC)

Definition/Assumptions

Bridges in this category are assumed to need ordinary maintenance after one winter and therefore, are considered “Inadequate Good Condition”.

Formula

BFIPFC.K =FBIPFC J + (DT)(FIPMB.JK +FIMNRB.JK + FIMJRB.JK + ORB.JK- BW.JK-FIERB.JK)

Value (b)

Interstate 0

Primary 0 Secondary 0

Source

1. Dean Hackett, Salem District Bridge Engineer, Super Natural query: “Breakdown of Structures by Sufficiency Ratings”. Break the data down into the three systems (3, 4, & 5).

3. For each of the sufficiency ratings, multiply the respective percentages by its respective items (bridge or culvert) and total the two values, i.e,

[Bridges x Bridges ee Js [Culverts x Culverts 8" = BFIPFC o Inadequate & Preferred ! ‘Number } (°o Inadequate & Preferred ! i Number}

bo

Spreadsheet

See spreadsheet on page 55.

54

SYSTEM TOTALS

Bridges Culverts Total Interstate 120 110 230

Primary +05 318 723

Secondary 1435 485 1920

INTERSTATE SYSTEM

Suff = 50 Suff < 50 Bridges Culverts Total Bridges Culverts Total

Good 22.5% 27 66.4% 73 100 1.7% 2 0.0% 0 2

Fair 71.7% 86 31.8% 35 121 0.8% | 0.0% 9 1

Poor 3.3% + 1.8% 2 6 0.0% 0 0.0% 90 0

Critical 0.0% Q 0.0% Q 0 0.0% 90 0.0% 0 Q

Total 97.5% 117 100.0% 110 227 2.5% = 3 0.0% 0 3

PRIMARY SYSTEM

Sulf = 50 Sulf < 50

Bridges Culverts Total Bridges Culverts Total

Good 34.7% 141 72.2% 230 370 1.0% + 0.0% QO 4

Fair 48.0% 194 25.9% 82 277 5.0% 20 0.0% 0 20

Poor 2.5% 10 1.9% 6 16 8.9% 36 0.0% 0 36

Critical 0.0% Q 0.0% 0 Q 0.0% 0 0.0% 9 0

Total 85.2% = 345 100.0% 318 663 14.9% 60 0.0% 90 60

SECONDARY SYSTEM

Sulf = 50 Suff < 50

Bridges Culverts Total Bridges Culverts Total Good 49.6% 712 65.8% 319 1031 2.4% 34 0.0% 0 34

Fair 34.5% 495 28.5% 138 633 6.2% 89 0.0% 9 89

Poor 1.8% 26 3.7% 28 53 5.5% 79 0.0% 0 79

Critical 0.0% 0 0.0% 0 Q 0.0% Q 0.0% 0 0

Total 85.9% 1233 100.0% 485 1718 14.1% 202 0.0% 90 202

Note: A structure with a sufficiency rating less than 50 is considered by the FHWA as being eligible

for Federal funding tor replacement because it is functionally obsolete.

mn mn

Birth Rate Parameter of Virginia (BRPV)

Definition/Assumptions

BRPV is the rate at which the population of Virginia is growing each year.

Formula

Constant.

Value (persons/yr.)

0.014591

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.census.gov/ftp/pub/population/www/statepop.btml

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

56

Bridge Widening Budget (BWB)

Definition/Assumptions

This value is a “seed” number to provide the model a starting reference point from which to begin its calculations. Currentlv there is no bridge-widening budget in place.

Formula

BWB.K = BB* FBBW

Value ($/yr.)

150,000.00

Source

1. John Jones.

Spreadsheet

N/A

57

Bridge Widening Cost (BWC)

Definition/Assumptions

At this time there is no recording system for this data. Dean Hackett, Salem District Bridge Engineer, provided the current values to act as a reference point.

Formula

Constant.

Value ($/yr.)

Interstate $500,000.00

Primary $350,000.00 Secondary $200,000.00

Source

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

« Activity Name » Activity Code » System

» Bridge Identification Number » Cost

« Date

» Budget (Construction or Maintenance) » Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

Average Cost of Bearing and Anchor Bolt Replacement (CBAR)

Definition/Assumptions

CBAR 1s based on the average size bridge for each of the road categories. It has been assumed that 10 percent are in need of replacement.

Formula

Constant.

Value ($/b)

Interstate $7,680.00

Primary $3,840.00 Secondary $ 960.00

Source (see Recommended Changes)

Current

1. The value of $3,200.00 per bearing is an average cost based on past contracts. 2. In Excel, for each of the categories, use this equation:

(Spans + 1) x (Beams per Span) x Cost per Bearing x 0.1 = CBAR

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code - System

- Bridge Identification Number

+ Cost » Date + Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Nn NO

Spreadsheet

Length (ft) Width (ft) Spans Beams per Span Cost per Bridge Interstate 209 45.1 3 7 $ 7,680.00

Primary 152 38.9 2 5 $ 3,840.00

Secondary 6+ 22.1 1 2 $ 960.00

$ 3,200.00 Cost per Bearing

Note: Assumed a value of 10 percent in need of repair.

60

Average Cost of Concrete Beam End Repair (CCBR)

Definition/Assumptions

CCBR is based on the average size bridge for each of the road categories. It has been assumed that 20 percent are in need of repair.

Formula

Constant.

Value ($/b)

Interstate $12,180.00

Primary $ 5,800.00 Secondary $ 1,160.00

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group.

2. Locate the item “Concrete Beam End Repair” under the major heading of “Superstructure Widening/Repair”.

3. In Excel, for each of the categories, use this equation:

(Spans + 1) x Beams per Span x Cost per Beam End « 0.2 = CCBR

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code + System - Bridge Identification Number + Cost + Date

- Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

61

Spreadsheet

Length (fi) Width (ft) Spans Beams per Span Cost per Bridge

Interstate 209 45.1 3 7 $ 12,180.00

Primary 152 38.9 2 5 $ 5,800.00

Secondary 64 22.1 1 2 $ 1,160.00

Cost per Beam End $ 1,450.00

Note: Assumed a value of 20 percent in need of repair.

62

Average Cost of Concrete Diaphragm Repair (CCDR)

Definition/Assumptions

CCDR is based on the average size bridge for each of the road categories. It has been assumed the diaphragms are spaced at 25 foot intervals and that 10 percent ts in need of repair.

Formula

Constant.

Value ($/b)

Interstate $3,105.81

Primary $1,505.85

Secondary $ 158.51

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Concrete Diaphragm Repair” under the major heading of

“Superstructure Widening/Repair”. 3. Use the Average Price. 4. In Excel, for each of the categories, use this equation:

[ Length

25 x (Beams per Span - 1) x Cost per Diaphragm ~ 0.1 = CCDR

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System » Bridge Identification Number ~ Cost - Date + Budget (Construction or Maintenance) + Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Note: Assumed a value of 10 percent in need of repair.

Length (ft) Width (ft) Spans Beams per Cost per Bridge Span

Interstate 209 45.1 3 7 $ 3,105.81 Primary 152 38.9 2 5 $ 1,505.85

Secondary 6+ 22.1 1 2 $ 158.51

Cost per Diaphragm S$ 619.18

64

Average Cost of Cathodic Protection (CCP)

Definition/Assumptions

CCP is based on the average size bridge for each of the road categories. The protection will cover the entire span of each of the bridge categories.

Formula

Constant.

Value ($/b)

Interstate $414,739.60

Primary $260,163.20 Secondary $ 62,233.60

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. Locate the item “Anode System” under the major heading of “Superstructure Widening/Repair”.

3. Use the Average Price. 4. In Excel, for each of the categories, use this equation:

Length x Width x Cathodic Protection = CCP

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code + System + Bridge Identification Number « Cost » Date - Budget (Construction or Maintenance) - Bridge Condition Rating

» Bridge Condition Rating Date 3. Activity costs are to be recorded on a “per bridge” basis using contract

lump sums.

Spreadsheet

Length (ft) Width (ft) Spans Beams per Span Cost per Bridge

Interstate 209 45.1 3 7 $ 414,739.60

Primary 152 38.9 2 5 $ 260,163.20

Secondary 64 22.1 1 2 $ 62,233.60

Cathodic Protection $ 44.00

66

Average Cost of Deck Edge Repair (CDER)

Definition/Assumptions

CDER 1s based on the average size bridge for each of the road categories. It has been assumed that 10 percent is in need of repair.

Formula

Constant.

Value ($/b)

Interstate $3,894.19

Primary $2,832.14 Secondary $1,192.48

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Deck Edge Repair” under the major heading of

“Superstructure Widening/Repair”. 3. Use the Average Price. +. In Excel, for each of the categories, use this equation:

Length x Deck Edge Repair x 0.25 = CDER

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System » Bridge Identification Number - Cost - Date + Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

67

Spreadsheet

Length (ft) Width (ft) Spans Cost per Bridge

Interstate 209 45.1 3 $ 2,336.52

Primary 152 38.9 2 $ 1,699.28

Secondary 64 22.1 1 $ 715.49

Deck Edge Repair (If) $ 74.53

Note: Assumed a value of 15 percent in need of repair.

68

Average Cost of Deck Replacement (CDKR)

Definition/Assumptions

CDKR is based on the average size bridge tor each of the road categories. An 8-% inch deck and 170 pounds per cubic yard of concrete for reinforcing steel are assumed.

Formula

Constant.

Value ($/b)

Interstate $116,047.52

Primary $ 72,795.78 Secondary $ 17,413.47

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the items “Concrete (Class A4)”, “Epoxy Coated Reinforcing Steel”, and

“Bridge Deck Grooving” under the major heading of “Superstructure Widening/Repair”.

3. In Excel, for each of the categories, use these equations:

Length x Width x (**),)

27

Concrete - A4 (sy) x 170 = Epoxy Rein Steel (Ibs)

Length x Width — >. J Deck Groove (sy)

(Concrete - A4 (cy) x Concrete - A4 (%)) +

(Epoxy Rein Steel (lbs) x Epoxy Rein Steel (%)) +

(Deck Groove (sy) x Deck Groove ( 4) = CDKR

Recommended

|- Concrete - A4 (sy)

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System » Bridge Identification Number - Cost

69

+ Date

- Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract

lump sums.

Spreadsheet

Length (ft) Width Spans Concrete Epoxy Rein Steel Deck Groove (sy) | Cost per Bridge

(fy - A4 (cy) (Ib.) Interstate 209 $5.1 3 247.28 42038.35 1047.32 $ 116,047.52

Primary 152 38.9 2 155.12 26370.36 656.98 $ 72,795.78

Secondary 64 22.1 i 37.11 6308.05 157.16 $ 17,413.47

Concrete - § 325.57 A4 (cy)

Epoxy Rein $ 0.60

Steel (Ib.) Deck § 9.85

Groove (sy)

70

Average Cost of Deck Overlay (CDO)

Definition/Assumptions

CDO is based on the average size bridge for each of the road categories. It has been assumed that 100 percent is in need of repair and the applied layer is 1 4 inch thick.

Formula

Constant.

Value ($/b)

Interstate $87,463.41

Primary $54,865.17 Secondary $13,124.29

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Latex Hydraulic Cement Concrete” under the major heading

of “Superstructure Widening/Repair”. 3. In Excel, for each of the categories, use this equation:

[tenes x Width x (17512) 27 x Hyd. Cement Conc (cy) = CDO

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code + System + Bridge Identification Number + Cost - Date + Budget (Construction or Maintenance) - Bridge Condition Rating + Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

71

Spreadsheet

Length (fi) Width (ft) Spans Cost per Bridge Interstate 209 45.1 3 $ 87,463.41

Primary 152 38.9 2 $ 54,865.17

Secondary 64 22.1 1 $ 13,124.29

Hyd Cement Conc. (cy) $ 801.71

Note: Assumed a value of 100 percent in need of repair.

72

Average Cost of Drainage System Replacement & Repair (CDSR)

Definition/Assumptions

CDSR is based on the average size bridge for each of the road categories. It has been assumed that 100 percent is in need of repair.

Formula

Constant.

Value ($/b)

$5,000.00

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code + System » Bridge Identification Number » Cost » Date + Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

73

Average Cost of Expansion Joint Maintenance (CEJM)

Definition/Assumptions

CEJM is based on the average size bridge for each of the road categories. It has been assumed that 25 percent is in need of repair.

Formula

Constant.

Value ($/b)

Interstate $1,753.49

Primary $1,134.32 Secondary $ 429.62

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Expansion Joint Reconstruction” under the major heading of

“Superstructure Widening/Repair”. 3. Use the Average Price. 4. In Excel, for each of the categories, use this equation:

Width x (Spans + 1) « Expansion Joint (If) « 0.25 = CEJR Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code + System + Bridge Identification Number « Cost - Date + Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

5. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

74

Spreadsheet

Length (ft) Width (ft) Spans Cost per Bridge

Expansion Joint (if)

Interstate 209 45.1 3 $ 1,753.49

Primary 152 38.9 2 $ 1,134.32

Secondary 64+ 22.1 1 $ 429.62

S 38.88

Note: Assumed a value of 25 percent in need of repair.

75

Average Cost of Expansion Joint Replacement (CEJP)

Definition/Assumptions

CEJP is based on the average size bridge for each of the road categories. It has been assumed that 100 percent is in need of repair.

Formula

Constant.

Value (S/b)

Interstate $3,562.90 Primary $2,304.83 Secondary $ 872.95

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Performed Elastomeric Joint Sealer (2 % inch)” under the

major heading of “Superstructure Widening/Repair”. 3. Use the Average Price. 4. In Excel, for each of the categories, use this equation:

Width « (Spans + 1) x Expansion Joint (lf) = CEJP

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code - System

» Bridge Identification Number

» Cost

+ Date

» Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

(ad

76

Spreadsheet

Length (ft) Width (ft) Spans Cost per Bridge

Expansion Joint (If)

Interstate 209 $5.1 3 $ 3,562.90

Primary 152 38.9 2 $ 2,304.83

Secondary 64 22.1 1 $ 872.95

$ 19.75

Note: Assumed a value of 100 percent in need of repair.

77

Average Cost of Patching (CPCH)

Definition/Assumptions

CPCH is based on the average size bridge for each of the road categories. It has been assumed that 20 percent is in need of repair.

Formula

Constant.

Value ($/b)

Interstate $40,648.67

Primary $25,498.62 Secondary $ 6,099.52

Source (see Recommended Changes)

Current

Obtain the latest “Unit Price Listing - Salem District” trom the Bridge Group. Locate the item “Type Y Patching” under the major heading of “Superstructure Widening/Repair”.

3. Find the numerical average of the four types using the Average Price. 4. In Excel, for each of the categories, use this equation:

Length « Width

9

Recommended

Noe

x Ave. Patching (sy) x 0.2 = CPCH

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code + System - Bridge Identification Number + Cost » Date - Budget (Construction or Maintenance) + Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

78

Spreadsheet

Length (fi) Width (fj) Spans Cost per Bridge

Interstate 209 45.1 3 $ 71,135.17

Primary 152 38.9 2 $ 44,622.59

Secondary 6+ 22.1 1 $ 10,674.16

Ave. Patching (sy) S$ 194.06

Note: Assumed a value of 35 percent in need of repair.

79

Average Cost of Parapet Guard Rail Maintenance (CPGM)

Definition/Assumptions

CPGM is based on the average size bridge for each of the road categories. It has been assumed that 15 percent is in need of maintenance. The equation takes into consideration that both sides of the bridge are in need of repair (the factor of 2 in the equation).

Formula

Constant.

Value ($/b)

Interstate $2,917.43

Primary $2,121.77 Secondary $ 893.38

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Concrete Parapet” under the major heading of

“Superstructure Widening/Repair”. 3. In Excel, for each of the categories, use this equation:

Length x Concrete Parapet (If) x 2 x 0.15=CPGM

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code + System » Bridge Identification Number - Cost » Date - Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

80

Spreadsheet

Length (ft) Width (ft) Spans Cost per Bridge

Concrete Parapet (If)

Note: Assumed a value of 10 percent in need of repair.

Interstate 209 45.1 3 $ 1,944.95

Primary 152 38.9 2 $ 1,414.51

Secondary 64 22.1 1 $ 595.58

$ 46.53

81

Average Cost of Repair of Abutment (CRA)

Definition/Assumptions

CRA is based on the average size bridge for each of the road categories. It is assumed 15 percent of the surface is in need of repair.

Formula

Constant.

Value ($/b)

Interstate $7,868.45

Primary $6,786.75

Secondary $3,855.71

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. Locate the items “Conc. Substructure Surface Repair” under the major heading of “Substructure Widening/Repair”.

3. In Excel, for each of the categories, use these equations: Width x Height . on. Conc Substructure Surface Repair x 0.15=CRA

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code - System » Bridge Identification Number » Cost » Date

- Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Length (ft} Width (ft) Height Cost per Bridge

Interstate 209 45.1 10 $ 7,868.45

Primary 152 38.9 10 $ 6,786.75

Secondary 64 22.1 10 $ 3,855.71

Conc. Substructure Surface Repair $ 523.40

Note: Assumed a value of 15 percent in need of repair.

83

Average Cost of Repair of Collision Damage (CRCD)

Definition/Assumptions

CRCD is based on the average size bridge for each of the road categories.

Formula

Constant.

Value ($/b)

$100,000.00

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code - System » Bridge Identification Number

« Cost

+ Date - Budget (Construction or Maintenance) - Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

84

Average Cost of Replacement of Abutment (CRLA)

Definition/Assumptions

CRLA 1s based on the average size bridge for each of the road categories. It is assumed that only one abutment is replaced and the average thickness of the abutment is three feet. Rebar is placed at 170 pounds per cubic yard.

Formula

Constant.

Value ($/b)

Interstate $18,231.42

Primary $15,725.11 Secondary $ 8,933.80

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the items “Concrete (A3)” and “Epoxy Coated Reinforcing Steel” under

the major heading of “Substructure”. 3. In Excel, for each of the categories, use these equations: Width x Height « Thickness

Q7% os

Concrete (A3) x 170'%, = Rein Steel

(Concrete (A3) x Cost of Concrete) + (Rein Steel x Cost of Rein Steel) = CRLA Recommended

= Concrete (A3)

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code

- System - Bridge Identification Number - Cost + Date » Budget (Construction or Maintenance) » Bridge Condition Rating - Bridge Condition Rating Date

3, Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

85

Spreadsheet

Length (ft) Width (ft) Height Cost per Bridge

Interstate 209 45.1 1¢ $ 18,231.42

Primary 152 38.9 10 $ 15,725.11

Secondary 64 22.1 10 $ 8,933.80

Concrete (A3) S$ 263.52

Epoxy Rein Steel S 0.59

Average Cost of Replacement of Pier (CRLP)

Definition/Assumptions

CRLP is based on the average size bridge for each of the road categories. It has been assumed that 100 percent is in need of maintenance. Assuming a worst case scenario, a solid hammerhead pier was used with a pier cap three feet wider than the bridge deck. The pier is assumed to be three feet thick and twenty feet high. Reinforcing is assumed to be at 170 lb. per cubic yard of concrete.

Formula

Constant.

Value ($/b)

Interstate $84,987.46

Primary $36,702.27

Secondary $ 0.00

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. Locate the items “Concrete (A3)” and “Epoxy Coated Reinforcing Steel” under the major heading of “Substructure”.

3. In Excel, for each of the categories, use these equations:

(Width ~ 3 x 20) +|(Width +3) x 3 x 3]

27

Concrete _, x 170 bs’ = Rein Steel

= Concrete, ‘|

(ibs!

- ; ; . . (Concrete, x Concrete, J + (Rein Steel... x Rein Steel 1 x Piers per Bridge = CRLI

(Sis)

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System - Bridge Identification Number - Cost - Date » Budget (Construction or Maintenance)

87

- Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Length (ft) Width Spans Piersper Councret Rein Steel Cost per Bridge (ft) Bridge e

Interstate 209 45.1 3 2 116.26 19763.44 $ 84,987.46

Primary 152 38.9 2 l 100.41 17069 .89 $ 36,702.27

Secondary 6+ 22.1 1 0 57.48 9771.22 $

Concrete - A3 (cy) $ 263.52

Epoxy Rein Steel (Ib.) $ 0.60

Note: It is assumed that all the piers will be replaced.

88

Average Cost of Repair of Pier (CRP)

Definition/Assumptions

CRP is based on the average size bridge for each of the road categories. It has been assumed that 25 percent is in need of maintenance. Assuming a worst case scenario, a solid hammerhead pier was used with a pier cap three feet wider than the bridge deck. The pier is assumed to be three feet thick and twenty feet high.

Formula

Constant.

Value ($/b)

Interstate $65,122.59

Primary $28,414.80 Secondary $ 0.00

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. Locate the item “Conc. Substructure Surface Repair” under the major heading of “Substructure Widening/Repair”.

3. In Excel, for each of the categories, use these equations: (2 20 Widthe-[2 3 (Width-3-12 15-3 —— = Surface Area per Pier, .

\

Piers per Bridge Surface Area, , x Conc Sub Surf Repair, x 0.25= CRP

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name - Activity Code + System + Bridge Identification Number + Cost - Date + Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

89

Spreadsheet

Length (ft) Width Spans Piers per Surface Area Cost per Bridge

fy

Bridge (sy) Interstate 209 $5.1 3 2 248.84 $ 65,122.59

Primary 152 38.9 2 i 217.16 $ 28,414.80

Secondary 64 22.1 1 0 131.29 $ :

Conc. Sub Surf Repair (sy) S 523.40 Note: Assumed a value of 25 percent of the surface area is in need of repair.

90

Average Cost of Repainting (CRPT)

Definition/Assumptions

CRPT is based on the average size bridge for each of the road categories. It is assumed that 100 percent of the bridge will be repainted and the steel beams are W33x118.

Formula

Constant.

Value ($/b)

Interstate $19,930.68

Primary $10,353.60 Secondary $ 1,743.76

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Repaint Existing Structure” under the major heading of

“Superstructure Widening/Repair”. 3. In Excel, for each of the categories, use this equation:

Length « Spans x Prep & Paint x 118":

2000", = CRPT

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code - System + Bridge Identification Number

« Cost

» Date

» Budget (Construction or Maintenance) » Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

91

Spreadsheet

Length (ft) Width (ft) Spans Beams per Cost per Bridge Span

Interstate 209 45.1 3 7 $ 19,930.68

Primary {a2 38.9 2 5 $ 10,353.60

Secondary ot 22.1 1 2 $ 1,743.76

Prep & Paint (ton) $ 209.91 Note: Assumed a value of 100 percent in need of repainting.

Average Cost of Scour (CS)

Definition/Assumptions

CS is based on the average size bridge for each of the road categories. It 1s assumed Class II Rip Rap is placed four feet in front of the abutment.

Formula

Constant.

Value ($/b)

Interstate $1,023.57

Primary $ 882.86 Secondary $ 501.57

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. Locate the item “Rip Rap Class II” under the major heading of “Substructure Widening/Repair”.

3. In Excel, for each of the categories, use this equation: Width x Rip Rap (Class II) x 4x 2.111"™% =CS

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code » System

- Bridge Identification Number + Cost - Date - Budget (Construction or Maintenance) - Bridge Condition Rating « Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

93

Spreadsheet

Length (ft) Width (ft) Spans Cost per Bridge

Interstate 209 $5.1 4 $ 1,023.57

Primary 152 38.9 + $ 882.86

Secondary 64 22.1 + $ 501.57

Rip Rap Class II $ 24.19

Note: 2.111 tons of Rip Rap Class II = 1 sv.

94

Average Cost of Sealing Deck/Crack (CSDC)

Definition/Assumptions

CSDC is based on the average size bridge for each of the road categories. It is assumed 100 percent of the deck will be resealed.

Formula

Constant.

Value ($/b)

Interstate $36,656.28

Primary $22,994.22 Secondary $ 5,500.44

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Crack Repair” under the major heading of “Superstructure

Widening/Repair”. 3. In Excel, for each of the categories, use this equation:

( Length x Width 9 * Deck Sealing = CSDC

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code - System + Bridge Identification Number + Cost

» Date » Budget (Construction or Maintenance) + Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

95

Spreadsheet

Length (ft) Width (ft) Spans Cost per Bridge Interstate 209 45.1 3 $ 36,656.28

Primary 152 38.9 2 $ 22,994.22

Secondary 6+ 22.1 1 $ 5,500.44

Deck Sealing (sy) § 35.00

Note: Assumed a value of 100 percent in need of repair.

96

Average Cost of Structural Steel Secondary Member Replacement and Repair (CSMR)

Definition/Assumptions

CSMR is based on the average size bridge for each of the road categories. It has been assumed the diaphragms are spaced at 25-foot intervals and that 25 percent is in need of repair.

Formula

Constant.

Value ($/b)

Interstate $16,302.00

Primary $ 7,904.00 Secondary $ 832.00

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. 2. In Excel, for each of the categories, use this equation:

[ Length

25

Recommended

x (Beams per Span - 1) x Cost per Diaphragm x 0.25= CSMR

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code - System

+ Bridge Identification Number - Cost + Date - Budget (Construction or Maintenance) » Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

97

Spreadsheet

Length (ft) Width (ft) Spans Beams per Span Cost per Bridge

Interstate 209 45.1 3 7 $ 16,302.00

Primary 152 38.9 2 ) $ 7,904.00

Secondary 6+ 22.1 1 2 $ 832.00

Cost per Diaphragm $ 1,300.00

Note: Assumed a value of 25 percent in need of repair.

98

Average Cost of Spot Painting (CSP)

Definition/Assumptions

CSP is based on the average size bridge for each of the road categories. It is assumed that 10 percent of the total surface area of the beams is in need of spot painting. The surface area per lineal foot of the W33x118 beams is calculated from the Manual of Steel Construction; Load & Resistance Factor Design, Volume I

Second Edition, pp. 1-28.

Formula

Constant.

Value ($/b)

Interstate $5,000.96

Primary $2,597.90 Secondary $ 437.64

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the item “Prepare & Spot Paint Existing Structure” under the major

heading of “Superstructure Widening/Repair”. 3. In Excel, for each of the categories, use these equations:

11.48+[2 x (115—055)]+ (2 x 29.75) + (4 x 0.74)

125, x 1 ft = Surface Area

Length x Beams per Span x Spot Painting x Surface Area per Lineal Foot x 0.1= CSP

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name « Activity Code + System » Bridge Identification Number « Cost + Date + Budget (Construction or Maintenance) » Bridge Condition Rating « Bridge Condition Rating Date

99

3. Activity costs are to be recorded on a “per bridge” basis using contract

lump sums.

Spreadsheet

Length (ft) Width (ft) Spans Beams per Cost per Bridge Span

Interstate 209 45.1 3 7 $ 5,000.96

Primary 152 38.9 2 5 $ 2,597.90

Secondary 6+ 22.1 1 2 $ 437.54

Spot Painting (sf) S 4.28

Surface Area per Lineal Foot (sf) 7.99

Note: Assumed a value of 10 percent in need of painting.

100

Average Cost of Superstructure Replacement (CSSR)

Definition/Assumptions

CSSR is based on the average size bridge for each of the road categories. Joints are placed every 7 feet across the width and every 18 feet along the length of the bridge; concrete is placed at a depth of 8% inches; reinforcing steel is placed at 170 '"/., of concrete; and structural steel is W33x118.

Formula

Constant.

Value ($/b)

Interstate $404,771.57

Primary $237,489.77 Secondary $ 53,908.54

Source (see Recommended Changes)

Current

1. Obtain the latest “Unit Price Listing - Salem District” from the Bridge Group. 2. Locate the items “Concrete (Class A4)”, “Epoxy Coated Reinforcing Steel”,

“Kansas Corral Railing”, “Bridge Deck Grooving”, “Performed Elastomeric Joint Sealer (4-in)”, “Asphalt Concrete (SM-2A)”, “Flexible Pavement Planing”, and “Structural Steel (Rolled)”.

101

tye In Excel, for each of the categories, use these equations:

Length - Width (84,5 } 7 = Concrete,

Concrete x 170%. = Rein Steel...

2 x Length = Railing,

Length Width a Groove, ..,

Leneth Width Length Width : <= tS = Joint Sealer, ,

Length Width 110

o D000 = Asph

Length Width : —,_— = Planing |

Isv]

| ton]

Length x Beams x 118 = Struc Steel,

Concrete, x Concrete, + Rein Steel

Groove, \* Groove, _., + Joint Sealer, \* Joint Sealer,,.. + Asph., ay Asph, + {tont

is) < Rein Steel. + Railing... x Railing, ., + Ibs saps if aa

Planing x Planing,,., + Struc Steel, , « Struc Steel... = CSSR (S. ibs

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code + System - Bridge Identification Number - Cost - Date

+ Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

102

Spreadsheet

Length Width Beam Concret Rein Railin Groov Joint Aspb Planing Struc Cost per Bridge

s € Steel g e Sealer Steel

Interstate 209 45.1 7 247.23 42238.3 418 1047.3 1870.22 57.60 1047.32 172634 § 404,771.57

5 2

Primary 152 38.9 5 155.12 26372.3 304 656.98 1173.17 36.13 656.98 89682 $ 237,489.77

6

Secondary 64 22.1 2 37.11 6328.05 128 157.16 280.63 8.64 157.16 15104 $ 53,908.54

Concrete - A4 $ 325.57

(cy) Epoxv Rein S$ 2.40 Steel (Ib.) Kansas Railing $§ 65.80

(If) Deck Groove $ 9.85

(sy) Elast. Joint S$ 34.41 Sealer 4" (If) Asph Conc. - § 242.21 SM-2A (ton) Flex Pyvmt S 4.87 Planing (sv) Structural Steel $ 123 - Rolled

Note: It is assumed that asphalt concrete will be applied at a rate of 125 pounds per square vard.

103

Deteriorating Time of Highway (DHT)

Definition/Assumptions

Is the time for pavement to decline from a “Fair” rating to a “Poor” rating.

Formula

Constant.

Value (yr.)

5

Source

1. This data is unavailable at this time due to the Transportation Research Council (TRC) upgrading their database svstem. It is estimated the new system will be in place in January 1997.

2. Mr. Tom Freeman of the TRC provided the estimate. (804) 293-1957.

Spreadsheet

N/A

104

Death Rate Parameter of Virginia (DRPV)

Definition/Assumptions

DRPV is the rate at which the population of Virginia is declining each year.

Formula

Constant.

Value (persons/yr.)

0.008249

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.census.zov/ftp/pub/population/www/statepop.ptml

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

Deterioration Time of Bridges (DTTB)

Definition/Assumptions

DTTB is defined, as the time required for a bridge condition rating to go from “Good “to” Fair”.

Formula

Constant.

Value (yr.)

Interstate 21 Primary 17 Secondary 19

Source (see Recommended Changes)

Current

1. This type of information is unavailable at this time, as it is not collected. 2. Dean Hackett, Salem District Bridge Engineer, with a Super Natural query

of HTRIS, obtained data used for this parameter.

3. Values were obtained by subtracting the “Year Built” from the “Year Improved” for each of the Road and Bridge classifications.

Recommended

1. For new structures, time begins subsequent to the completed structure’s first winter, as ordinarv maintenance 1s performed to mitigate the effects of that winter, thereby placing the bridge in the “Good” condition.

2. For existing structures, time begins subsequent to any upgrade or downgrade to its existing condition.

3. Deterioration Times are then calculated by finding the difference between the date of classification for the older (higher) condition and the date for the newer (lower) condition.

Spreadsheet

N/A

106

Exposure Time of Bridges (ETB)

Definition/Assumptions

ETB is the time for bridges in “Preferred” condition to fall to “Good” condition. Bridges undergo ordinary (preventive) maintenance after their first winter to remove the salts and mitigate the effects of winter on the structure.

Formula

Constant.

Value (yr.)

0.5

Soitrce

1. Dean Hackett, Salem District Bridge Engineer.

Spreadsheet

N/A

107

Federal Aid to Virginia (FAV)

Definition/Assumptions

FAV is the subsidized amount of money allocated to the state of Virginia for its transportation budget.

Formula

Constant.

Value ($/yr.)

466,486,400.00

Source

1. Federal Highway Administration’s 1995 Highway Statistics Manual (HPM-40), Table FA-4.

Spreadsheet

N/A

108

Fraction of the Budget to Bridge Widening (FBBW)

Definition/Assumptions

FBBW is the fraction of the total bridge budget (BB) used for the widening of bridges.

Formula

Constant.

Value (dim)

Interstate 0.5293 Primary 0.0187 Secondary N/A

Source

Current

1. Construction data was obtained from VDOT’s Six-Year Plan. 2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404. 3. Identify all bridge data in the Six-Year Plan. Sum widening and

replacement funds. 4. Separate and sum the maintenance codes, by system, into the following

categories: Minor Major Preventative Replacement Rehabilitation

221 +61 225 465 551 222 462 226 552 224 +66 40+ 553 565 368 463 556 566 467 557 569 354 561

555 562 567 563

364

Each category was then summed by system to determine the total amount for each category and system.

nA

Sum these totals with the construction data for the total expenditures.

Divide the construction total (widening) for each system by the overall total to determine the fraction.

Widening Expenditure : = FBBW

Total Expenditure

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

109

Activity Name Activity Code System Bridge Identification Number Cost Date Budget (Construction or Maintenance) Bridge Condition Rating Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

110

Fraction of the Budget to Functionally Adequate Major Repairs of Bridges (FBFAJRB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on performing major repairs to functionally adequate bridges.

Formula

FBFAJRB.K = AFBAJRB.K/TFBBM.K

Value (dim)

Interstate 0.4022 Primary 0.1182 Secondary 0.1233

Source (see Recommended Changes)

Current

1. Construction data was obtained from VDOT’s Six-Year Plan. 2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404. 3. Identify all bridge data in the Six-Year Plan. Sum widening and

replacement funds. 4, With a Super Natural query of HTRIS, determine the number good, fair,

poor, and critical functionally adequate and inadequate bridges by system. Good bridges correspond with preventive maintenance. Fair bridges correspond with minor maintenance. Poor bridges correspond with major maintenance. Determine the fraction of functionally adequate and inadequate good bridges, i.e., Number of Functionally Adequate Good

Or

AwN

= Fraction of Functionally Adequate Good Total Good Bridges

1-Fraction of Func Adequate Good = Fraction of Functionally Inadeq Good

9. Repeat for fair and poor bridges. 10. Separate and sum the maintenance codes, by system, into the following

categories:

111

il,

Minor Major Preventative Replacement Rehabilitation

221 461 225 +65 551 222 462 226 552 224 466 404 353 565 568 463 556 566 467 557 569 554 561

555 562 567 563

564

Each category was then summed by system to determine the total amount for each category and system.

12. Determine the fraction of money spent on minor, major, and preventive maintenance.

13. Multiply each maintenance fraction with each of the bridge functional adequacy fractions to determine the fraction of money spent on each of the bridge functional classifications.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code » System - Bridge Identification Number - Cost « Date

- Budget (Construction or Maintenance) - Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Interstate Primary Secondary

FBBW 0.5293 0.0187 -

FBFAJRB 0.4022 0.1182 0.1233

FBFANRB 0.0352 0.0201 0.1223

FBFAPMB 0.0321 0.0370 0.0971

FBFIJRB 0.0000 0.2660 0.1838

FBFINRB 0.0003 0.0015 0.0172

FBFIPMB 0.0006 0.0003 0.0032

FBRHP 0.0001 0.1827 ---

FBRPB 0.0001 0.3554 ---

112

Fraction of the Budget to Functionally Adequate Minor Repairs of Bridges (FBFANRB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on performing minor repairs to functionally adequate bridges.

Formula

FBFANRB.K = AFBANRB.K/TFBBM.K

Value (dim)

Interstate 0.0352 Primary 0.0201 Secondary 0.1223

Source (see Recommended Changes)

Current

1. Construction data was obtained from VDOT’s Six-Year Plan. 2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404. 3. Identify all bridge data in the Six-Year Plan. Sum widening and

replacement funds. 4, With a Super Natural query of HTRIS, determine the number good, fair,

poor, and critical functionally adequate and inadequate bridges by system. A good bridge corresponds with preventive maintenance. Fair bridges correspond with minor maintenance. Poor bridges correspond with major maintenance. Determine the fraction of functionally adequate and inadequate good bridges, 1.€., Number of Functionally Adequate Good

Total Good Bridges = Fraction of Functionally Adequate Good

ON DW

|-Fraction of Func Adequate Good = Fraction of Functionally Inadeq Good

9. Repeat for fair and poor bridges. 10. Separate and sum the maintenance codes, by system, into the following

cat egories:

Minor Major Preventative Replacement Rehabilitation

221 461 225 465 551 222 462 226 552

224 466 404 553

5365 568 +63 556

566 467 557

569 554 561

355 562

567 563

564

113

11. Each category was then summed by system to determine the total amount for each category and system.

12. Determine the fraction of money spent on minor, major, and preventive

maintenance.

13. Multiply each maintenance fraction with each of the bridge functional adequacy fractions to determine the fraction of money spent on each of the bridge functional classifications.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name - Activity Code + System

- Bridge Identification Number + Cost + Date - Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Interstate Primary Secondary

FBBW 0.5293 0.0187 --

FBFAJRB 0.4022 0.1182 0.1233

FBFANRB 0.0352 0.0201 0.1223

FBFAPMB 0.0321 0.0370 0.0971

FBFIJRB 0.0000 0.2660 0.1838

FBFINRB 0.0003 0.0015 0.0172

FBFIPMB 0.0006 0.0003 ¢.0032

FBRHP 0.0001 0.1827 ~-

FBRPB 0.0001 0.3554 ---

114

Fraction of the Budget to Functionally Adequate Preventative Maintenance of Bridges (FBFAPMB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on performing preventive maintenance to functionally adequate bridges.

Formula

FBFAPRB.K = AFBAPRB.K/TFBBM.K

Value (dim)

Interstate 0.0321

Primary 0.0370 Secondary 0.0971

Source (see Recommended Changes)

Current

1. Construction data was obtained trom VDOT’s Six-Year Plan. 2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404. 3. Identify all bridge data in the Six-Year Plan. Sum widening and

replacement funds. 4. With a Super Natural query of HTRIS, determine the number good, fair,

poor, and critical functionally adequate and inadequate bridges by system. Good bridges correspond with preventive maintenance. Fair bridges correspond with minor maintenance. Poor bridges correspond with major maintenance. Determine the fraction of functionally adequate and inadequate good bridges, 1.€., Number of Functionally Adequate Good

Total Good Brdzes = Fraction of Functionally Adequate Good

ON Dn

1-Fraction of Func Adequate Good = Fraction of Functionally Inadeq Good

9. Repeat for fair and poor bridges. 10. Separate and sum the maintenance codes, by system, into the following

categories:

115

Minor Major Preventative Replacement Rehabilitation 221 461 225 465 551 222 462 226 552 224 +66 404 553 565 568 463 556 566 +67 557 569 354 561

355 562 367 563

364+

11. Each category was then summed by system to determine the total amount for each category and system.

12. Determine the fraction of money spent on minor, major, and preventive maintenance.

13. Multiply each maintenance fraction with each of the bridge functional adequacy fractions to determine the fraction of money spent on each of the bridge functional classifications.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System » Bridge Identification Number

+ Cost - Date + Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract

lump sums.

Spreadsheet

Interstate Primary Secondary

EBBW 0.5293 0.0187 = FBFAJRB 0.4022 0.1182 0.1233

FBFANRB 0.0352 0.0201 0.1223

FBFAPMB 0.0321 0.0370 0.0971

FBFIJRB 0.0000 0.2660 0.1838

FBFINRB 0.0003 0.0015 0.0172

FBFIPMB 0.0006 0.0003 0.0032

FBRHP 0.0001 0.1827 --

FBRPB 0.0001 0.3554 ---

116

Fraction of the Budget to Functionally Inadequate Major Repairs of Bridges (FBFIJRB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on performing major repairs to functionally inadequate bridges.

Formula

FBFIJRB.K = AFBIJRB.K/TFBBM.K

Value (dim)

Interstate 0.0000 Primary 0.2660 Secondary 0.1838

Source (see Recommended Changes)

Current

1. Construction data was obtained from VDOT’s Six-Year Plan.

2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404.

3. Identify all bridge data in the Six-Year Plan. Sum widening and replacement funds.

4, With a Super Natural query of HTRIS, determine the number good, fair, poor, and critical functionally adequate and inadequate bridges by system.

5. Good bridges correspond with preventive maintenance. 6. Fair bridges correspond with minor maintenance. 7. Poor bridges correspond with major maintenance. 8. Determine the fraction of functionally adequate and inadequate good

bridges, 1.€.,

eS = Fraction of Functionally Adequate Good

1-Fraction of Func Adequate Good = Fraction of Functionally Inadeq Good

9. Repeat for fair and poor bridges. 10. Separate and sum the maintenance codes, by system, into the following

categories:

117

Minor Major Preventative Replacement — Rebabilitation 221 +61 225 465 551 222 +62 226 552 224 +66 +04 553 565 568 +63 556 366 +67 55/7 569 554 561

555 562 367 363

364

11. Each category was then summed by system to determine the total amount for each category and system.

12. Determine the fraction of money spent on minor, major, and preventive maintenance.

13. Multiply each maintenance fraction with each of the bridge functional adequacy fractions to determine the fraction of money spent on each of the bridge functional classifications.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

>

+

+

¢

¢

Activity Name Activity Code System

Bridge Identification Number Cost Date Budget (Construction or Maintenance) Bridge Condition Rating Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Interstate Primary Secondary

FBBW 0.5293 0.0187 --

FBFAJRB 0.4022 0.1182 0.1233

FBFANRB 0.0352 0.0201 0.1223

FBFAPMB 0.0321 0.0370 0.097 1

FBFIJRB 0.0000 0.2660 0.1838

FBFINRB 0.0003 0.0015 0.0172

FBFIPMB 0.0006 0.0003 0.0032

FBRHP 0.0001 0.1827 --

FBRPB 0.0001 0.3554 ---

118

Fraction of the Budget to Functionally Inadequate Minor Repairs of Bridges (FBFINRB)

Definition/Assumptions

Is the traction of the bridge budget (BB) spent on performing minor repairs to functionally inadequate bridges.

Formula

FBFINRB.K = AFBINRB.K/TFBBM.K

Value (dim)

Interstate 0.0000 Primary 0.2660 Secondary 0.1838

Source (see Recommended Changes)

Current

1. Construction data was obtained from VDOT’s Six-Year Plan. 2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404. 3. Identify all bridge data in the Six-Year Plan. Sum widening and

replacement funds. 4. With a Super Natural query of HTRIS, determine the number good, fair,

poor, and critical functionally adequate and inadequate bridges by system. Good bridges correspond with preventive maintenance. Fair bridges correspond with minor maintenance. Poor bridges correspond with major maintenance. Determine the fraction of functionally adequate and inadequate good bridges, i.e., Number ot Functionally Adequate Good

Total Good Bridges = Fraction of Functionally Adequate Good

ON AU

1-Fraction of Func Adequate Good = Fraction of Functionally Inadeq Good

9. Repeat for fair and poor bridges.

10. Separate and sum the maintenance codes, by system, into the following categories:

119

Minor Major Preventative Replacement Rehabilitation 221 461 225 465 551 222 462 226 552 224 466 404 553 565 568 +63 556 566 +67 357 569 554 561

355 362 567 563

So+

11. Each category was then summed by system to determine the total amount for each category and system.

12. Determine the fraction of money spent on minor, major, and preventive maintenance.

13. Multiply each maintenance fraction with each of the bridge functional adequacy fractions to determine the fraction of money spent on each of the bridge functional classifications.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name « Activity Code

» Bridge Identification Number » System

« Cost

+ Date

» Budget (Construction or Maintenance) - Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract

lump sums.

Spreadsheet

Interstate Primary Secondary

FBBW 0.5293 0.0187 _. FBFAJRB 0.4022 0.1182 0.1233

FBFANRB 0.0352 0.0201 0.1223

FBFAPMB 0.0321 0.0370 0.0971

FBFIJRB 0.0000 0.2660 0.1838

FBFINRB 0.0003 0.0015 0.0172

FBFIPMB 0.0006 0.0003 0.0032

FBRHP 0.0001 0.1827 —

FBRPB 0.0001 0.3554 _

120

Fraction of the Budget to Functionally Inadequate Preventative Maintenance of Bridges (FBFIPMB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on performing preventive maintenance to functionally inadequate bridges.

Formula

FBFIPRB.K = AFBIPRB.K/TFBBM.K

Value (dim)

Interstate 0.0006

Primary 0.0003

Secondary 0.0032

Source (see Recommended Changes)

Current

1. Construction data was obtained from VDOT’s Six-Year Plan. 2. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404.

3. Identify all bridge data in the Six-Year Plan. Sum widening and replacement funds.

4, With a Super Natural query of HTRIS, determine the number good, fair, poor, and critical functionally adequate and inadequate bridges by system. Good bridges correspond with preventive maintenance. Fair bridges correspond with minor maintenance. Poor bridges correspond with major maintenance. Determine the fraction of functionally adequate and inadequate good bridges, z.e., Number of Functionally Adequate Good

Tolal Good Brides = Fraction of Functionally Adequate Good

CON DN

1-Fraction of Func Adequate Good = Fraction of Functionally Inadeq Good

9. Repeat for fair and poor bridges. 10. Separate and sum the maintenance codes, by system, into the following

categories:

121

Minor Major Preventative Replacement — Rebabilitation

221 tol 225 465 351 222 462 226 552 224 466 404 553 565 368 463 556 566 467 557 569 354 561

555 562 567 563

264

11. Each category was then summed by system to determine the total amount for each category and system.

12. Determine the fraction of money spent on minor, major, and preventive maintenance.

13. Multiply each maintenance fraction with each of the bridge functional adequacy fractions to determine the fraction of money spent on each of the bridge functional classifications.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

¢

+

a

¢

¢

Activity Name Activity Code System Bridge Identification Number Cost Date Budget (Construction or Maintenance) Bridge Condition Rating Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

Interstate Primary Secondary

FBBW 0.5293 0.0187 -

FBFAJRB 0.4022 0.1182 0.1233

FBFANRB 0.0352 0.0201 0.1223

FBFAPMB 0.0321 0.0370 0.0971

FBFYRB 0.0000 0.2660 0.1838

FBFINRB 0.0003 0.0015 0.0172

FBFIPMB 0.0006 0.0003 0.0032

FBRHP 0.0001 0.1827 --

FBRPB 0.0001 0.3554 ---

122

Fraction of the Budget to Highway Construction (FBHC)

Definition/Assumptions

Is the fraction of the total Salem District budget allocated to construction.

Formula

FBHC.K = 1-FBHM

Value (dim)

0.5593

Source

1. This is determined by summing the Salem construction and maintenance budgets, then dividing the construction budget by the total budget.

Spreadsheet

N/A

123

Fraction of the Budget to Highway Maintenance (FBHM)

Definition/Assumptions

Is the fraction of the total Salem District budget allocated to maintenance.

Formula

Constant.

Value (dim)

0.4407

Source

1. This is determined by summing the Salem construction and maintenance budgets, then dividing the maintenance budget by the total budget.

Spreadsheet

N/A

124

Fraction of the Budget to the Rehabilitation of Bridges (FBRHB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on bridge rehabilitation.

Formutla

FBRHB.K = AFBRHB.K/TFBBM.K

Value (dim)

Interstate 0.0001

Primary 0.1827 Secondary N/A

Source

1. This is determined by subtracting the sum of all other bridge fractions from one.

|— » (Bridge Budget Fractions) = FBRHB

Spreadsheet

N/A

Fraction of the Budget to the Replacement of Bridges (FBRPB)

Definition/Assumptions

Is the fraction of the bridge budget (BB) spent on bridge replacement.

Formula

FBRPB.K =AFBRPB.K/TFBBM.K

Value (dim)

Interstate 0.0001

Primary 0.3554 Secondary N/A

Source

Current

1. Construction data was obtained from VDOT’s Six-Year Plan. Maintenance data was obtained from HTRIS. Activity series: 220, 460, 550,

and 560; activity 404. 3. Identify all bridge data in the Six-Year Plan. Sum widening and

replacement funds. 4, Separate and sum the maintenance codes, by system, into the following

categories: Minor Major Preventative Replacement _Rebabilitation

221 tol 225 465 551 222 +62 226 352 22+ +66 404 553 365 368 463 5356 366 467 357 569 554 561

555 362 56/7 363

364

5. Each category was then summed by system to determine the total amount for each category and system.

6. Sum these totals with the construction data for the total expenditures.

7. Divide the construction total (replacement) for each system by the overall total to determine the fraction.

Replacement Expenditure ; = FBRHB

Total Expenditure

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

126

+

*

Activity Name Activity Code System Bridge Identification Number Cost Date Budget (Construction or Maintenance) Bridge Condition Rating Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

127

Fraction of the Construction Budget to the Bridge Budget (FCBB)

Definition/Assumptions

Formula

Constant.

Value (dim)

Interstate 0.0181

Primary 0.0189 Secondary 0.0186

Source (see Recommended Changes)

Current

1. Data obtained from the Commonwealth Transportation Board Six-Year

Plan. 2. For each of the road classifications (Interstate and Primary), sum the total

dollars allocated to bridgework for the Salem District. 3. Divide the total allocated funds for each of the classifications by the

construction budget for the Salem District (HCBSD), i.e., Bridge Total —HcBsp FCBB verse

Recommended

Interstate

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System - Bridge Identification Number

« Cost + Date

- Budget (Construction or Maintenance) » Bridge Condition Rating + Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

128

Fraction of the Construction Budget to the Salem District (FCBSD)

Definition/Assumptions

Formula

Constant.

Value (dim)

0.09321

Source

1. Data obtained from the Commonwealth Transportation Board Six-Year

Plan. 2. Divide allocated money to Salem District by the state wide allocation, i.e.,

HCBS HCBSD _ecRsp HCBV

Spreadsheet

N/A

129

Fraction of the Maintenance Budget to the Bridge Budget (FMBB)

Definition/Assumptions

This is the fraction of the money from the maintenance budget that is applied to the bridge budget

Formula

Constant.

Value (dim)

Interstate 0.0177

Primary 0.0626 Secondary N/A

Source

Current

1. Divide allocated money to Salem District by the state wide allocation, i.e., HMB

HMBV

Recommended

= FMBSD

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code «+ System

» Bridge Identification Number + Cost - Date - Budget (Construction or Maintenance) » Bridge Condition Rating + Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

Fraction of the Maintenance Budget to the Salem District (FMBSD)

Definition/Assumptions

Formula

Constant.

Value (dim)

0.09899

Source

1. Divide allocated money to Salem District by the state wide allocation, 7.e.,

HIB -= FMBSD

HMBV

Spreadsheet

N/A

131

Fraction of Motor Vehicle Fuels Tax to the HMO (FMFTH)

Definition/Assumptions

FMFTH is the portion of the Motor Vehicle License Fee that is allotted to the Highway Maintenance and Operating Fund (HMO).

Formula

Highway Maintenance and Oreraung Fund < FMFTH = Motor Vehicle License Fee, <,

Value (dim)

0.838983

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: - Federal Highway Admuinistration’s (FHWA) Highway Statistics Manual. - Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerrv Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

132

Fraction of Motor Vehicle Fuels Tax to the TTF (FMFTT)

Definition/Assumptions

FMFTT is the portion of the Motor Vehicle Fuels Tax allotted to the Transportation Trust Fund (TTF).

Formula

Transportation Trust Fund, ¢,

FMEFTT = Motor Vehic le Fuels Tax, ¢,

Value (dim)

0.141243

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: » Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Diviston of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

133

Fraction of Motor Vehicle License Fee to the HMO (FMVLFH)

Definition/Assumptions

FMVLFH is the portion of the Motor Vehicle License Fee allotted to the Highway Maintenance and Operating Fund (HMO).

Formula

Highway Mamtenance and Operating Fund, ., FMVLFH = Motor Vehicle License Fee,<,

Value (dim)

0.603773

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: » Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chiet Economist. (804) 367-6473.

Spreadsheet

N/A

134

Fraction of Motor Vehicle License Fee to the TTF (FMVLFT)

Definition/Assumptions

FMVLFT is the portion of the Motor Vehicle License Fee allotted to the Transportation Trust Fund (TTF).

Formula

Transportation Trust Fund, ¢,

FMVLFT = Moter Vehicle License Fee, ¢,

Value (dim)

0.113208

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning

Information Group Handout, by E.E. Miller, Jr. 2. Alternate Sources are:

» Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

135

Fraction of Motor Vehicle License Fee to the HMO (FMVSTH)

Definition/Assumptions

FMVSTH is the portion of the Motor Vehicle Sales & Use Tax allotted to the Highway Maintenance and Operating Fund (HMO).

Formula

Highway Maintenance and Operating Fur. .,,

FMVSTH = Motor Vehicle License Fee,,,

Value (dim)

0.666667

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: » Federal Highway Admuinistration’s (FHWA) Highway Statistics Manual. - Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact 1s Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

136

Fraction of Motor Sales & Use Tax to the TTF (FMVSTT)

Definition/Assumptions

FMVSTT is the portion of the Motor Vehicle Sales & Use Tax allotted to the Transportation Trust Fund (TTF).

Formula

Transportation Trust Fund,.,;

FMVSTT ™~ Motor Vehicle Sales & Use Tax, o,;

Value (dim)

0.333

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: » Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

137

Fraction of the Revenue to the Highway Budget (FRHWY)

Definition/Assumptions

FRHWY is the fraction of the total state budget that is actually spent on the highway system, z.e., excludes the fraction of the budget that is applied to the Public Transit.

Formula

Constant.

Value (dim)

0.955

Source

1. Data obtained from the Commonwealth Transportation Board Six-Year

Plan, p. 3.

2. Subtract the “Public Transit” allocation from the “Total” allocation. 3. Divide this figure by the “Total” allocation, i.e.,

(Total - Public Transit)

Total = FRHWY

Spreadsheet

N/A

138

Fraction of State Sales Tax to the HMO (FSSH)

Definition/Assumptions

FSSH is the portion of the Motor Vehicle License Fee that is allotted to the Highway Maintenance and Operating Fund (HMO).

Formula

_ 0.85 Highway Maintenance and Operating Fund, .«,

FSSH = Motor Vehicle License Fee,,,

Value (dim)

0.00

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: « Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

139

Fraction of State Sales Tax to the TTF (FSST)

Definition/Assumptions

FSST is the portion of the State Sales Tax allotted to the Transportation Trust Fund (TTF).

Formula

0.85 Transportation Trust Fund,.,,

FMVLFT = Motor Vehicle License Fee, ,,

Value (dim)

0.094444

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are:

» Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

140

Highway Construction Budget for the Salem District (HCBSD)

Definition/Assumptions

Formula

HCBSD.K =FCBSD.K*HCBCV.K

Value ($/yr.)

82,740,000.00

Value ($/yr.)

1. Commonwealth Transportation Board’s Six-Year Improvement Program - Fiscal Year 1995-96, p. 174.

Spreadsheet

N/A

141

Highway Construction Budget in Virginia (HCBV)

Definition/Assumptions

Formula

HCBV.K =FBHC.K*ABH.K

Value ($/yr.)

887 ,666,000.00

Value ($/yr.)

1. Commonwealth Transportation Board’s Six-Year Improvement Program - Fiscal Year 1995-96, p. 3.

Spreadsheet

N/A

Highway in Deficient Pavement Condition (HDFPC)

Definition/Assumptions

With the new PCI rating svstem there is no definitive point which separates highway in deteriorated (fair) from deficient (poor) and sufficient (good) conditions. For the purposes of this model, a deteriorated condition has been defined as: 79 > PCI=50 for the primary system and 84 >PCI=50 for the interstate system. Data for the secondary highway system was unavailable at the time of collection.

Formula

HDFPC.K = HDFPC,] + (DT)(ARH.JK-MRDFH.JK-DRH.JK)

Value (In-m1)

Interstate 220.39 Primary 1068.78 Secondary 0.00

Source

1.

in se Ww

Obtain the “Salem Flexible Ratings (Pavement Condition Index) - 1995” for each of the systems. In Excel, input the “PCI” and “Lane Miles” columns for each of the systems, sort the data in ascending order by “PCI”, and sum the “Lane Miles” for each system for the PCI defined earlier. Add the columns: “Rating”, “Percentage” and “Mileage”. In the “Rating” column enter the rating of “Poor”. The “Percentage” column is the percentage of total mileage of deteriorated roadway of the system, as compared to the total mileage recorded for the system. Total Mileage

' Detenorated ! =P t Total Mileage cree

(System)

Multiply this percentage by the actual mileage to determine the adjusted mileage in the deteriorated category.

Spreadsheets

See spreadsheet on page 148.

143

Highway in Deteriorated Pavement Condition (HDTPC)

Definition/Assumptions

With the new PCI rating system there is no definitive point which separates highway in deficient (poor) condition from deteriorated (fair). For the purposes of this model, a cut-off value of 50 has been assumed for each of the highway categories. Data for the secondary highway system was unavailable at the time of collection.

Formula

HDTPC.K=HDTPC,J +(DT)(DRH.JK-MRDTH_JK)

Value

Interstate 8.10

Primary 45.04 Secondary 0.00

SOuUrce

1. Obtain the “Salem Flexible Ratings (Pavement Condition Index) - 1995” for each of the systems.

2. In Excel, input the “PCI” and “Lane Miles” columns for each of the systems, sort the data in ascending order by “PCI”, and sum the “Lane Miles” with a PCI of less than 50.

3. Add the columns: “Rating”, “Percentage” and “Mileage”. In the “Rating” column enter the rating of “Poor”.

5. The “Percentage” column is the percentage of total mileage of deficient roadway of the system, as compared to the total mileage recorded for the system. Total Mileage,

i Deficient?

*

; = Percentage Total Mileage. ”

(Svstem!

6. Multiply this percentage by the actual mileage to determine the adjusted mileage in the deficient category.

Spreadsheets

See spreadsheet on page 148.

144

Highway Maintenance Budget for the Salem District (HMB)

Definition/Assumptions

Formula

HMB.K =clip(clip(6.2E6*K,6.2E6, TIME.K,5)FMBP.K*HMBS.K, TIME.K,0)

Value ($/yr.)

75,286,472.31

Source

1. Sum the ordinary maintenance, maintenance replacement, and incidental construction totals for each of the systems obtained from the A-17 report.

Spreadsheet

N/A

Highway Maintenance Budget in Virginia (HMBV)

Definition/Assumptions

Formula

HMBV.K =FBHM.K*HMBV.K

Value ($/yr.)

760,572,000.00

Source

1. Commonwealth Transportation Board’s Six-Year Improvement Program - Fiscal Year 1995-96, p. 3.

Spreadsheet

N/A

146

Highway in Sufficient Pavement Condition (HSFPC)

Definition/Assumptions

With the new PCI rating system there is no definitive point which separates highway in deficient (poor) condition from deteriorated (fair). For the purposes of this model a cut-off value of >78 for primary and > 83 for interstate, has been assumed for each of the highway categories. Data tor the secondary highway system was unavailable at the time of collection.

Formula

HSFPC.K =HSFPC,J +(DT)\(MRDTH.JK + ERH.JK + MRDFH JK-ARH_JK)

Value

Interstate 271.15 Primary 1451.91 Secondary 0.00

Source

1. Obtain the “Salem Flexible Ratings (Pavement Condition Index) - 1995” tor each of the systems.

2. In Excel, input the “PCI” and “Lane Miles” columns for each of the systems,

sort the data in ascending order by “PCI”, and sum the “Lane Miles” for each system for the PCI defined earlier.

3. Add the columns: “Rating”, “Percentage” and “Mileage”. 4. Inthe “Rating” column enter the rating of “Poor”. 5. The “Percentage” column is the percentage of total mileage of sufficient

roadway of the system, as compared to the total mileage recorded for the system. Total Mileage... sscsenr p

= t Total Mileage... “eee

6. Multiply this percentage by the actual mileage to determine the adjusted mileage in the sufficient category.

Spreadsheets

See spreadsheet on page 148.

147

Spreadsheets - Sufficiency Ratings

Interstate

PCI Rating Percentage Mileage

TOTAL GOOD 54.27% 271.15

TOTAL FAIR 44.11% 220.39

TOTAL POOR 1.62% 8.10

Lane Mileage 499.64

Primary

Pcl Rating Percentage Mileage

TOTAL GOOD 56.59% 1451.91

TOTAL FAIR 41.66% 1068.78

TOTAL POOR 1.76% 45.04

Lane Mileage 2565.74

148

Income Increasing Rate Parameter (IIRP)

Definition/Assumptions

IIRP is the rate at which the per capita income 1s growing each year.

Formula

Constant.

Value (%/yr.)

1.43

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.census.gov/ftp/pub/bhes/income/4person.ptml

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

149

In-Migration Parameter of Virginia (IMRPV)

Definition/Assumptions

IMRPV is the rate at which the population of Virginia is growing each year through immigration.

Formula

Constant.

Value (dim)

0.001168

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.census.gov/ftp/pub/population/www/statepop.btml

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

15C

Inflation Factor (INFLF)

Definition/Assumptions

Formula

INFLF.K = (INFLR + 1)**TIME.K

Value (%/yr.)

2.6

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.odc.gov/ca/pubulications/95fact/us.btml

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

151

Out-Migration Parameter of Virginia (OMRPV)

Definition/Assumptions

OMRPYV is the rate at which the population of Virginia is decreasing each vear through emigration.

Formula

Constant.

Value (dim)

0.001737

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.census.gov/ftp/pub/population/www/statepop.btml

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

152

Obsolescence Time of Bridges (OTB)

Definition/Assumptions

Obsolescence is a function of Policy Makers decision processes. It deals with the bridge’s ability to satisfy the current Bridge Specifications vice its structural soundness with regards to loading.

Formula

Constant

Value (yr.)

20

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code - System - Bridge Identification Number + Cost «+ Date

+ Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

153

Per Capita Income of Virginia (PCIV)

Definition/Assumptions

Formula

PCIV.K=PCIV.J+(DT)(IIR.JK)

Value ($/person)

$23,597.00

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.bea.doc.gou/bea/statepi.btm#tabele# under the “Per capita personal income, by State and region, 1995”.

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

154

Personal Purchase Rate (PPR)

Definition/Assumptions

Formula

Constant.

Value ($/yr.-person)

22,570.47

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: wuw.bea.doc.gov/bea/statepi.htm#table.

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

Population of Salem District (PS)

Definition/Assumptions

Formula

Constant.

Value (person)

662,737

Source

1. This data was obtained by summing the 1990 Population Census totals found in the legend of each of the VDOT General Highway maps for each of the thirteen counties in the Salem District.

Spreadsheet

N/A

156

Population of Virginia (PV)

Definition/Assumptions

Formula

Constant.

Value (person)

6,618,358

Source

1. Using the Internet, this can be found in the US Census Bureau’s homepage at: www.census.zov/ftp/pub/population/www/statepop.html

2. It should be noted for those individuals not familiar with the mechanics of the web, addresses (URL) are case sensitive and should be typed as shown above.

Spreadsheet

N/A

157

Rate of Motor Fuels Tax (RMFT)

Definition/Assumptions

RMFT is the tax assessed each time fuel is purchased at a filling station.

Formula

Constant.

Value ($/gal)

0.177

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: » Federal Highway Administration’s (FHWA) Highway Statistics Manual. + Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

158

Rate of Motor Vehicle License Fee (RMVLF)

Definition/Assumptions

RMVLF 1s the fee associated with registering a motor vehicle with the Division of Motor Vehicles (DMV).

Formula

Constant.

Value ($/veh)

26.50

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: + Federal Highway Administration’s (FHWA) Highway Statistics Manual. » Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

159

Rate of Motor Vehicle Sales & Use Tax (RMVSUT)

Definition/Assumptions

All vehicles are taxed at 3.0 percent of their total value or $35.00 whichever 1s greater.

Formula

Constant.

Value (dim)

0.03

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning

Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: » Federal Highway Administration’s (FHWA) Highway Statistics Manual. + Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

160

Rate for State Sales Tax (RSST)

Definition/Assumptions

The state sales tax for Virginia.

Formula

Constant.

Value ($/yr.)

0.045

Source

1. Obtained from the “Allocation Formula - A Quick Look”, Planning Information Group Handout, by E.E. Miller, Jr.

2. Alternate Sources are: + Federal Highway Administration’s (FHWA) Highway Statistics Manual. + Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis.

Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

161

Serious Deterioration Time of Bridges (SDTB)

Definition/Assumptions

SDTB is defined as the time required for a bridge condition rating to go from “Poor” to “Critical”.

Formula

Constant

Value (yr.)

Interstate 15

Primary 30 Secondary 32

Source

Current

1. This type of information is unavailable at this time as it is not collected. 2. Data used for this parameter was obtained by Dean Hackett, Salem District

Bridge Engineer, with a Super Natural query of HTRIS. 3. Values were obtained by subtracting the “Year Built” from the “Year

Improved” for each of the Road and Bridge classifications. Recommended

1. For new structures, time begins subsequent to the completed structure’s first winter, as ordinary maintenance is performed to mitigate the effects of that winter, thereby placing the bridge in the “Good” condition.

2. For existing structures, time begins subsequent to any upgrade or downgrade to its existing condition.

3. Deterioration Times are then calculated by finding the difference between the date of classification for the older (higher) condition and the date for the newer (lower) condition.

Spreadsheet

N/A

162

State Sales (SS)

Definition/Assumptions

The estimated dollar amount of sales in the state of Virginia.

Formula

SST. K=PPR*PV.K

Value ($/yr.)

149,379,454,500.47

Source

1. Obtained by multiplying the personal purchase rate (PPR) with the population of Virginia (PV).

Spreadsheet

N/A

163

Total Mileage (TOTMILG)

Definition/Assumptions

The total road mileage in the system.

Formula

Constant

Value (mi.)

Interstate 117.91 Primary 1035.39 Secondary 7077.03

Source

1. HTRIS query

Spreadsheet

N/A

164

Travel Time on Link KL (TTLKL)

Definition/Assumptions

TTLKL is the average time in minutes spent traveling the full length of each road. Assumed the following values: 2200 vehicles per land, 65 mph for interstate highways, 55 mph for US highways, 45 mph for state highways, and the predominant number of lanes for one way travel are provided by Alan Williams, the Maintenance Engineer for the Salem District.

Formula

TTLKL.K =FFTTLKL*(1-(1-LOSF.K)*(AVBC.K))/(1.0001*A VBC.K)

Value (min)

See spreadsheet below

Source

1. Use the Relative Density of Traffic by Route table tor the Salem District, found in the Average Daily Traffic Volumes on Interstate, Arterial, and Primary Routes - 1994. Input Route, Mileage, and Average 24-Hour Trattfic per Mile of Route into an Excel spreadsheet.

3. Sort by Route 4. Use this equation in the spreadsheet:

f Ave. 24-hr Traffic per Mile of Route \ | x4 y= Ave. Hourly Traffic per Mile of Route

5. Use the Bureau of Public Roads (BPR) method tor determining the new time (Tx) in feet per minute:

Vv) T, +013 =| =T,

Where:

No

Doe MPH T,, = Initial Time,,,,,, = G0 min

V Volume’ Ave. Hourly Traffic per Mile of Route

fom Capacity ~ (No. of Lanes x 2200}

6. Calculate Total Travel Time by: T.. x Mileage = Time (min)

Spreadsheet

Route Mileage Ave. 24 Hr. Ave. Hourly No. of Ave. Hourly V/C MPH To IN (min) Traffic per Trafficper Lanes Traffic per (min)

Mile of Route Mile of One-Way Route En-Mi

1-581 6.75 60,725 2,532.21 6 421.70 ©.192 65 6,23 6.23

1-77 24.29 25,171 1,048.79 4 262.20 0.119 65 22.42 22.42

I-81 86.87 33,201 1,383.38 4 345.84 0.157 65 80.19 8C.22

US 11 68.57 12,392 516.33 4 129.08 0.059 55 74.80 74.80

US 219 1.73 4,900 224.17 2 102.08 0.046 55 1.89 1.89

US 220 108.43 20,126 338.58 4 09.65 9.095 35 118.29 118.29

US 220 BUS 0.27 30,000 1,252.00 4 312.50 9.142 55 v.29 0.29

US 221 89.87 6,951 289.63 2 144.81 0.066 55 98.04 98.04

US 460 99.91 15,308 637.33 4 159.46 0.072 55 108.99 128.99

US 460 BUS 3.46 6,542 272.58 4 68.15 0.031 55 3.77 3.77

US 501 14.29 2,459 122.46 2 51.23 0.023 55 15.59 15.59

US 52 27.44 3,638 151.58 2 75.79 3.034 55 29.93 29.93

US 58 83.96 6,856 285.67 2 142.83 0.C65 55 91.59 91.59

US 58 BUS 6.71 15,417 642.33 4 160.59 2.073 55 7.32 7.32

VA 100 48.54 8,734 363.92 2 181.96 0.083 45 64.72 64.72

VA 103 13.43 2,468 102.83 2 51.42 9.023 45 17.91 17.91

VA 108 4.24 3,300 137.52 2 68.75 0.031 45 5.65 3.65

VA 112 c.21 1,100 45.83 4 11.46 9.005 45 2.28 0.28

VA 114 8.25 10,139 422.46 4 105.61 0.048 45 11.00 11.¢¢

VA 115 3.14 12,212 528.75 4 127.19 0.058 45 4.19 4.19

VA 116 12.78 3,670 152.92 2 76.46 9.035 45 17.04 17.24

VA 117 1.35 21,000 875.20 4 218.75 o.C99 45 1.8¢ 1.82

VA 118 C.20 13,000 541.67 2 270.83 0.123 45 0.27 0.27

VA 122 50.14 4,012 167.17 2 83.58 0.038 45 66.85 66.85

VA 148 0.87 5,900 245.83 2 122.92 0.056 45 1.16 1.16

VA 174 4.29 5,900 245.83 4 61.46 0.028 45 5.72 5.72

VA177 2.33 5,802 241.67 2 120.83 9.055 45 3.11 3.11

VA 18 5.12 30¢ 12.5¢ 2 6.25 2.00 45 6.83 6.83

VA 220 6.83 16,357 681.54 4 170.39 9.077 45 9.11 9.11

VA 232 c.58 5,80C 241.67 2 120.83 0.055 45 0.77 c.77

VA 24 34.36 5,315 221.46 2 110.73 0.050 45 45.81 45.31

VA 311 40.24 3,899 162.46 2 $1.23 9.037 45 53.65 53.65

VA 320 1.75 Bcc 20.83 2 10.42 0.005 45 2.33 2.33

VA 40 47.79 5,68¢ 236.67 2 118.33 0.054 45 63.72 63.72

VA 419 6.97 28,014 1,167.25 4 291.81 0.133 45 9.29 9.29

VA 42 51.50 2,449 102.04 2 51.02 0.023 45 68.67 68.67

VA 43 48.86 1,42¢ 59.17 2 29.58 0.013 45 65.15 65.15

VA43 Y v.11 763 31.79 2 15.90 ¢.007 45 v.15 0.15

VA 457 2.62 4,800 COneS 2 100.co 0.045 45 3.49 3.49

VA 57 38.22 5,693 237.21 2 118.60 0.054 45 50.96 50.96

VA 57 ALT 4.09 O,000 416.67 2 208.33 0.095 45 5.45 5.45

VA 61 13.63 775 32.29 2 16.15 0.0C7 45 18.17 18.17

VA 69 0.25 3,400 141.67 2 70.83 0.032 45 0.33 0.33

VAS8 55.14 3,475 144.79 2 72.40 0.033 45 73.52 73.52

VA 87 4.12 8,229 342.88 2 171.44 0.078 45 5.47 5.47

VA 94 9.20 1,102 45.33 2 22.92 9.010 45 12.27 12.27

VA 97 8.27 1,100 45.33 2 22.92 0.010 45 11.03 11.03

VA 99 1.35 5,800 241.67 2 120.83 0.055 45 1.80 1.80

NOTE: Used the BPR Method for TN.

No. of Lanes from Alan Williams

166

Annual Traffic Volume (TVOL)

Definition/Assumptions

AADT is the estimated annual one-way tratfic volume per mile of route.

Formula

TVOL.K=AADT.K*220

Value (veh)

See spreadsheet below

Source

1. Use the “Relative Density of Traffic by Route” table for the Salem District found in the Average Daily Traffic Volumes_on Interstate, Arterial, and Primary Routes - 1994. Input Route, Mileage, and Average 24-hour Traffic per Mile of Route into an Excel spreadsheet. Sort by Route. Multiply the “Average 24-hour Traftic per Mile of Route” by 365 days to obtain the desired value.

167

Spreadsheet

Route Mileage Ave. 24 Hr. Traffic per Ave. Annual Traffic per 1-581 6.75 60,725 22,164,625 1-77 24.29 25,171 9,187,415 1-81 86.87 33,201 12,118,365 US 11 68.57 12,392 4,523,08C US 219 1.73 4,900 1,788,500 US 220 168.43 20,126 7,345,990 US 220 BUS 2.27 3,000 10,950,006 US 221 89.87 6,951 2,537,115 US 460 99.91 15,308 5,587,420 US 460 BUS 3.46 6,542 2,387,83¢ US 501 14.29 2,459 897,535 US 52 27.44 3,638 1,327,879 US 58 83.96 6,856 2,502,440 US 58 BUS 6.71 15,417 5,627,205 VA 100 48.54 8,734 3,187,910 VA 103 13.43 2,468 900,820 VA 108 4.24 3,300 1,204,500

VA 112 2.21 1,100 401,500 VA 114 8.25 10,139 3,700,735 VA 115 3.14 12.210 4,456,650 VA 116 12.78 3,670 1,339,552 VA 117 1.35 21,000 7,665,000 VA 118 2.20 13,000 4,745,000 VA 122 52.14 4,012 1,464,38¢ VA 148 2.87 5,900 2,153,500 VA 174 4.29 5,900 2,153,500 VA 177 2.33 5,800 2,117,000 VA 18 5.12 oo 109,500 VA 220 ALT 6.83 16,357 5,979,305 VA 232 2.58 5,800 2,117,000 VA 24 34.36 5,315 1,939,975 VA311 40.24 3,899 1,423,135 VA 320 1.75 500 182,500 VA 40 47.79 5,680 2,073,200 VA 419 6.97 28,014 12,225,11° VA 42 51.50 2,449 893,885 VA 43 48.86 1,420 518,300 VA43Y o.11 763 278,495 VA 457 2.62 4,800 1,752,000

VA 57 38.22 5,693 2,077,945 VA 57 ALT 4.09 c,000 3,650,000

VA 61 13.63 775 282,875 VA 69 2.25 3,400 1,241,000 VA8 55.14 3,475 1,268,375 VA 87 4.10 8,229 3,003,585 VA 94 9.20 1,100 401,500 VA97 8.27 1,100 401,502 VA 99 1.35 5,800 2,117,000

168

Total Value of Vehicles Registered in Virginia (TVVV)

Definition/Assumptions

Formula

TVVV.K=AVVV*VV.K

Value ($)

353,285,000.00

Source

1. This amount is estimated by a regression model at the Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis. Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473.

Spreadsheet

N/A

169

Vehicle Average Annual Growth Rate in Virginia (VAGR)

Definition/Assumptions

The estimated rate at which the number of registered vehicles in Virginia increases (decreases).

Formula

Constant.

Value ($/yr.)

Passenger 0.0208 Other 0.0095

Source

i. Data from 1989 to 1995 was obtained from Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis. Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473. The data was record as Passenger and Other until 1993. Therefore, this has been maintained to obtain a truer

mean for the value. 2. The growth rate was determined by first determining the growth rates between

each of the years by dividing the succeeding year by the preceding year then subtracting one.

Passer, 1 = 00202

Passenger, 5.

3. The final growth rate (VAGR) was determined by finding the arithmetic mean for these intermediate growth rates.

Spreadsheet

Vehicle Registration for Virginia

1989 1990 1991 1992 1993 1994 1995 Average

Passenger 4,402,077 4,440,868 4,531,770 4,678,685 4,799,366 4,882,284 4,315,016

Other 583,361 582,811 593,146 551,324 584,156 603,025

572,591 Growth Rate (Pass.) 2.02% 0.88% 2.05% 3.24% 2.58% 1.73% 2.08%

Growth Rate (Other) 1.88% -C.09% 1.77% -7 05% 5.96% 3.23% 0.95%

Note: Passenger vehicles include trucks with a registered gross weight of 7,500 Ib. or less.

Vehicle Increasing Rate in Virginia (VINC)

Definition/Assumptions

The estimated number of increased (decreased) registered vehicles in Virginia.

Formula

VINC.KL=VV.K*VAGR

Value ($/yr.)

Passenger 101,552

Other 5,729

Source

1. These estimates were obtained bv multiplying the number of registered vehicles in 1995 (VV) by their growth rate (VAGR).

Spreadsheet

N/A

171

Number of Vehicles in Virginia (VV)

Definition/Assumptions

The number of registered vehicles in Virginia.

Formula

VV.K=VV.J+(DT)(VINC JK)

Value ($/yr.)

Passenger 4,882,284

Other 603,025

Source

1. Data from 1989 to 1995 was obtained from Division of Motor Vehicle’s (DMV) Office of Forecasting and Analysis. Point of Contact is Ms. Gerry Turner, Chief Economist. (804) 367-6473. The data was record as Passenger and Other until 1993. Therefore, this has been maintained to obtain a truer

mean for the value.

Spreadsheet

Vehicle Registration for Virginia

1989 1990 1991 1992 1993 1994 1995 Average

Passenger 4,402,077 4,440,868 4,531,770 4,678,685 4,799,366 4,882.284 4,315,016

Other 583,361 582,811 593,146 551,324 584,156 03,025

572,591 Growth Rate (Pass.) 2.02% c.88% 2.05% 3.24% 2.58% 1.73% 2.08%

Growth Rate (Other) 1.88% <.09% 1.77% -7 05% 5.96% 3.23% 0.95%

Note: Passenger vehicles include trucks with a registered gross weight of 7,500 Ib. or less.

172

Weighting Factor for Bearing and Anchor Bolt Replacement (WFBAR)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.01

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code - System « Bridge Identification Number

- Cost - Date - Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

173

Weighting Factor for Beam End Repair (WFCBR)

Definition/Assumptions

Is the fraction of the total money spent on Major Repair Cost of Bridges (MJRCB). Other elements include average costs of deck replacement {CDKR) and superstructure replacement (CSSR). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.13

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name Activity Code

- System Bridge Identification Number

» Cost - Date

- Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

174

Weighting Factor for Concrete Diaphragm Repair (WFCDR)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), bearing and anchor bolt replacement (CBAR), and deck edge repair (CDER). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.03

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

« Activity Name » Activity Code » System » Bridge Identification Number - Cost » Date « Budget (Construction or Maintenance) - Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

175

Weighting Factor for Cathodic Protection (WFCP)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), bearing and anchor bolt replacement (CBAR), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.01

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System » Bridge Identification Number - Cost - Date + Budget (Construction or Maintenance) + Bridge Condition Rating + Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

176

Weighting Factor for Deck Edge Repair (WFDER)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and bearing and anchor bolt replacement (CBAR). The sum of which ts equal to one.

Formula

Constant.

Value (dim)

0.04

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

« Activity Name - Activity Code - System » Bridge Identification Number - Cost - Date - Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

177

Weighting Factor for Deck Replacement (WFDKR)

Definition/Assumptions

Is the fraction of the total money spent on Major Repair Cost of Bridges (MJRCB). Other elements include average costs of concrete beam end repair (CCBR) and superstructure replacement (CSSR). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.65

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code + System » Bridge Identification Number » Cost - Date » Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

178

Weighting Factor for Deck Overlay (WFDO)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: bearing and anchor bolt replacement (CBAR), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which ts equal to one.

Formula

Constant.

Value (dim)

0.17

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

« Activity Name + Activity Code » System » Bridge Identification Number

+ Cost

+ Date

+ Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

179

Weighting Factor for Drainage System Replacement and Repair (WFDSR)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), bearing and anchor bolt replacement (CBAR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which 1s equal to one.

Formula

Constant.

Value (dim)

0.07

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System » Bridge Identification Number + Cost + Date + Budget (Construction or Maintenance) « Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

180

Weighting Factor for Expansion Joint Maintenance (WFEJM)

Definition/Assumptions

Is the fraction of the total money spent on Preventive Maintenance Cost of Bridges (PMCB). Other elements include average costs of parapet guard rail maintenance (CPGM), scour (CS), sealing deck cracks (CSDC), and spot painting (CSP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.63

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code - System » Bridge Identification Number + Cost - Date » Budget (Construction or Maintenance) + Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

181

Weighting Factor for Expansion Joint Reconstruction (WFEJR)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), patching (CPCH), bearing and anchor bolt replacement (CBAR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which ts equal to one.

Formula

Constant.

Value (dim)

0.29

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code + System » Bridge Identification Number «+ Cost - Date - Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

182

Weighting Factor for Patching (WFPCH)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), bearing and anchor bolt replacement (CBAR), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which 1s equal to one.

Formula

Constant.

Value (dim)

0.21

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code - System

» Bridge Identification Number - Cost + Date » Budget (Construction or Maintenance) - Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

183

Weighting Factor for Parapet Guard Rail Maintenance (WFPGM)

Definition/Assumptions

Is the fraction of the total money spent on Preventive Maintenance Cost of Bridges (PMCB). Other elements include average costs of expansion joint maintenance (CEJM), scour (CS), sealing deck cracks (CSDC), and spot painting (CSP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.07

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name « Activity Code - System + Bridge Identification Number » Cost + Date « Budget (Construction or Maintenance) » Bridge Condition Rating + Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

184

Weighting Factor for Repair of Abutment (WFRA)

Definition/Assumptions

Is the fraction of the total money spent on Rehabilitation Cost of Bridges (RHCB). Other elements include average costs of repair of collision damage (CRCD), abutment replacement (CRLA), pier replacement (CRLP), and pier repairs (CRP). The sum of which ts equal to one.

Formula

Constant.

Value (dim)

0.14

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System + Bridge Identification Number + Cost » Date - Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

185

Weighting Factor for Repair of Collision Damage (WFRCD)

Definition/Assumptions

Is the fraction of the total money spent on Rehabilitation Cost of Bridges (RHCB). Other elements include average costs of abutment repairs (CRA), abutment replacement (CRLA), pier replacement (CRLP), and pier repairs (CRP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.14

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code - System

» Bridge Identification Number - Cost

«+ Date + Budget (Construction or Maintenance) » Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

186

Weighting Factor for Replacement of Abutment (WFRLA)

Definition/Assumptions

Is the fraction of the total money spent on Rehabilitation Cost of Bridges (RHCB). Other elements include average costs of abutment repairs (CRA), repair of collision damage (CRCD), pier replacement (CRLP), and pier repairs (CRP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.01

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code + System « Bridge Identification Number + Cost + Date

- Budget (Construction or Maintenance) - Bridge Condition Rating + Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

187

Weighting Factor for Replacement of Pier (WFRLP)

Definition/Assumptions

Is the fraction of the total money spent on Rehabilitation Cost of Bridges (RHCB). Other elements include average costs of abutment repairs (CRA), repair of collision damage (CRCD), abutment replacement (CRLA), and pier repairs (CRP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.01

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer.

Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code + System

« Bridge Identification Number + Cost » Date - Budget (Construction or Maintenance) - Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

188

Weighting Factor for Repair of Pier (WFRP)

Definition/Assumptions

Is the fraction of the total money spent on Rehabilitation Cost of Bridges (RHCB). Other elements include average costs of abutment repairs (CRA), repair of collision damage (CRCD), abutment replacement (CRLA), and pier replacement (CRLP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.70

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name - Activity Code + System » Bridge Identification Number + Cost ~ Date - Budget (Construction or Maintenance) + Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

189

Weighting Factor for Repainting (WFRPT)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of deck overlay (CDO), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), bearing and anchor bolt replacement (CBAR), drainage system replacement and repair (CDSR), structural steel secondary member replacement and repair (CSMR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.14

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name « Activity Code + System » Bridge Identification Number » Cost - Date + Budget (Construction or Maintenance) - Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

190

Weighting Factor for Scour (WFS)

Definition/Assumptions

Is the fraction of the total money spent on Preventive Maintenance Cost of Bridges (PMCB). Other elements include average costs of expansion joint maintenance (CEJM), parapet guard rail maintenance (CPGM), sealing deck cracks (CSDC), and spot painting (CSP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.13

Source (see Recommended Changes)

Current

{. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

» Activity Name » Activity Code » System » Bridge Identification Number + Cost - Date + Budget (Construction or Maintenance) + Bridge Condition Rating » Bridge Condition Rating Date

3, Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

191

Weighting Factor for Sealing Deck Cracks (WFSDC)

Definition/Assumptions

Is the fraction of the total money spent on Preventive Maintenance Cost of Bridges (PMCB). Other elements include average costs of expansion joint maintenance (CEJM), parapet guardrail maintenance (CPGM), scour (CS), and spot painting (CSP). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.13

Source (see Recommended Changes)

Current

{. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name + Activity Code - System

+ Bridge Identification Number + Cost

« Date

- Budget (Construction or Maintenance) « Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

Weighting Factor for Structural Steel Secondary Member Replacement and Repair (WFSMR)

Definition/Assumptions

Is the fraction of the total money spent on Minor Repair Cost of Bridges (MNRCB). Other elements include average costs of: deck overlay (CDO), cathodic protection (CCP), patching (CPCH), expansion joint reconstruction (CEJR), repainting (CRPT), drainage system replacement and repair (CDSR), bearing and anchor bolt replacement (CBAR), concrete diaphragm (CCDR), and deck edge repair (CDER). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.03

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

« Activity Name « Activity Code + System + Bridge Identification Number

+ Cost - Date + Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

193

Weighting Factor for Spot Painting (WFSP)

Definition/Assumptions

Is the fraction of the total money spent on Preventive Maintenance Cost of Bridges (PMCB). Other elements include average costs of: expansion joint maintenance (CEJM), parapet guardrail maintenance (CPGM), scour (CS), and sealing deck cracks (CSDC). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.04

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

+ Activity Name » Activity Code + System « Bridge Identification Number » Cost - Date + Budget (Construction or Maintenance) + Bridge Condition Rating - Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

194

Weighting Factor for Superstructure Replacement (WFSSR)

Definition/Assumptions

Is the fraction of the total money spent on Major Repair Cost of Bridges (MJRCB). Other elements include average costs of concrete beam end repair (CCBR) and deck replacement (CDKR). The sum of which is equal to one.

Formula

Constant.

Value (dim)

0.22

Source (see Recommended Changes)

Current

1. Dean Hackett, Salem District Bridge Engineer. Recommended

1. Establish new activity codes for each of the parameters. 2. Establish a data base with the following fields:

- Activity Name » Activity Code - System » Bridge Identification Number + Cost » Date - Budget (Construction or Maintenance) » Bridge Condition Rating » Bridge Condition Rating Date

3. Activity costs are to be recorded on a “per bridge” basis using contract lump sums.

Spreadsheet

N/A

195

APPENDIX C: MODEL CAUSAL DIAGRAMS

196

Evaluation Subsystem

Widt-SSHd

S .¢ Worf

SWiod-SSHdt »

(ores n

Se ee

wns

y TH ud

apurd~ Neanee red

. One)

AGI wal

Manabi ntragyy

ues agate

eo LS

T .

- .

, OdXTaL

‘ “A

pewnosspuny Pngrneds

a fr

(wt

ANH vane

3Shid

4a -

weniney

PASRUPIOL

AM Sy zon

HWE

ddXx- oH

HZ

“---

SWG-Mu014

a *

GnGW

ws, ,o

ag ‘

: -"

napisy "y

Ae cant

(uma) 7"

- sourvat

pewnosagq sungppuad»

3 t

é

$9 WORICY

FOI

aE lena]

+ =

e Jy

Ailey

a Inypuady: WERE IEIOL

AAH papuedxy

iad Weistyg

7 =

Dmog Tenuds,

. ny

<3—_—_____>

aingpeadxy IEW

(ur q)

e wen

ined GaWLH

Hada Sd

qt foerbpy

=! WHOH

cws-ssd '

a =

QGsW1

TL

yroshug ope

we 8

ld ’

way genes

Ba,

s Ass)

' =

“« ;

¥ ~

4 prions sn

- 4

WdHT ot

woes .

asig

moe

Pawns sipun

ean pueds

3 y,

v

! TOTP SP

at

SSN wor?

-@ i

aingpuadx3, ampnyno}

(ug)

HYP g S05 YUN

Wa ~

sETBODY &

->

Sait

=se Arense3

inn

HELO) LAH

punodun 9

ss unued

$909 Bune

ad au A

ae

ie

%. mom

ONaol UNSOH*

TTT?

89099 wan

AOA iva

VM Hayes

47 ‘

- a

LR Wal

twoueey .

. .

T

(va) .-

N :

bk

popinooag '

. (gr

! eit

‘ >

: a?

. 1

NM peu An

amy nner

ime

+ Wyop

ARH

OMY bUOIa

ID + (amang

” aAN

ere

qyq° ‘

AN & 77 TTT

tyr -

gare rt aoL

Q39H uso

A dnoou

<7" SSNg

woL4 ‘

’ +

'

. a

t “.

4 Paynes

qiso 7

2 .

ay mL

oS

trae

SSNs ators

' “Gnoo 1a

wos

ww-e

nee Rew

' ssast

ig i

+ QD0TL

BAAN

wee

eee ee

“bs

ig 2

r ae?

vse,

Pahoa.

a 1*

wm

Mee .

1 -

a

en ¢

a GOTH

rece

° * TT

te me

wn ig

. ea)

Soak

widu9g

WSN

UON

ARG

Ie sy

pownetacun

_ pPawnesse

an payinor

ag *

4 alf

= =

a Nagi WO

NSAI

NT

! NAAN

(onuyg) ea areca

Naann

4 .

+ a

LOM,

' Toren

+ Tal

. -

PHY CAD

cd wc?

“.

; Ysid

¥. Jf

SRaTEmBENG >.

| .

a YS!

¥

.

Cw)

Cutyg$) ‘

-. *

peu

deal UeN [Poul €or ece

.! —

<€~ ssid wor

auaAg masala a

+.

. “.

repriceag wee

SANS

ee es annonspur

Ra me

= ssn

wos

I 7

‘ ?

f owe

ot

SW

. a

og

JASN’

4 « 27 4 NSN a Beeee

eon tenga

© wer

ypuag

s9sn fenauy

t.

x 7

1 Dead

pewnes 4q)

‘ ma

7 Paynes

spur ™.

~ :

(Han) 09905

7 -

‘ se

’ MO 4 BANG

Nadi wid

4 eioraey

cer Nagano

wee Pas

Cd *.-

(MID =

eS ~ ii.”

tl”

“..

: ag

ULE [BAIL

~m,

TIN

we”

~ =.

. Cap

ROESIEY EOL ye

VOLS FAS

Tw.

? x

i .

. Sa

oo” we olitee

we. SUAIOL

MILs

+ aie

eee

aot

- --

: 7.

’ 1

’ mh

~ ;

. ‘

Cupey an)

pears gs Fas,

joer, \

l ‘

7 Tas

ard) Leg

1 rang)

dul ‘a

eounioud +.

ee

ee

tea

UTD

A Haug)

enna po ee

waias ul

dal] 1344

warty) PHF

pa ee

+ ee

LLdO

IM LA agnastenin

inzy openienuy

Ow

Lianne painariiweiy

sn PUI!

FBAE UO

Rey TITER

% tae.

‘ an

+ st

LOA

TS LOY

. ~y

SHETOD

earstaad fay Done y

aur

oe '@ra

OWALOL

7€ Le

a

. s

sR

BY .

£ )

. Sd

(Ops a

pagytiaan 1U9

[BATT {

* ony fuse ari

de ‘

os —

~ WANT

Fe Ona

' A

"yan Launop Amon -

dl AA

. 45 O71

ryan awnycn MCL

+} ss

~ #

, Al

ayy bs eau

awed! {

t AHS s wer wert ene

, a---- yh ------

Aue

qienuny ony

+f oe

4 -~

a ;

GAIA) Wolom

y UctssanuU)

JAll

' wae)

. *

.

hurd

LIV

6 GAMER?

pun

peniaiy

wae Br

Ouse 104)

SSH

urorg awrtes

Chea

ones Qiedeg

inpey «

DUM IP OELL

JoOAY ome

OAW eoee SAA

REP

eat

de feed a-- SHVGASSHa

¥

=_

71

fenucg ony

dv °

DAY

SWdSSHgMorg +

bY LA

3sOm

(SSAZ) tiajsAsqns

uoRnenjeaq

197

Financial Subsystem

(wi! BOP.

oF paBpng

jumpy pry

wo}:

fswa)

Qylyd=

| sAsgns jeshy

Of «

. ae

(unig ~s

we TOME T

E

Sct ah

pig *

rugey ‘

=anu

OUT

Lys ee

a

jeden ToD

GHVH *

SSHkd O4

tpnq

sycvoqd ply

TO”

wo:

me

ee ee

CVTIAL

t

4Aao4d A

' se

‘ wou

fungt wee

~~ .

Wal TWP

ES 0}

FA

WES

OF ¢

; Se

wg

waAe sw

ator PAR

awe mt

~. 3

Istorg WPI

erS jobpng

Neves Red

Waly Wale,

yelp pAUpUE

SLAM ~

a pera

rn

mH gg Lk

TVeqey

Se ee

ae m

\ STA

OS

%

rt

Gea

{ SAWH

Y.

+ fay)

1 yg)

- ~

aot

7 ,

Yes

ly gy

era I<

- 7

epg atid

Pruiduyy ui petpng

yonsjqe4 J ARH

eng ae

Hs

ted 2)

| ~

~ wee

ee ee eee

a i

eee

‘Wye eee

ee eee

\Oyyu<«ae2

ct crc

AHa4

7 PADI

<5 bie

>! AIH

<4

fag

CANH "TPL

(eq

(uigy

wae weg

pet, OTS

fewybiy .

dP epee

Noe

_

span Naku

sais -

DIRS AFIS

Ped

Del

Why

‘ 1

ads

WAH

A ¢

WHOL

‘ TT

reds

7 PopP

EG

4 7”

A” ~

. y

Sang CMW

PE.

HLS ort

, *-

pecs ua

ve ;

“A, '

Hays “Ou OR

1 ae

CHYd

= '

- "

PA SHR

SIPS, t

pur. uo ered

PUR Lae CeUEK

Amal] Cad

pur ysnuy

uowuedt ey

' PRIME

Ld yap

1opyE PE!

1 ratty

er ony

. +

l El so 7

aes

MASAI 7777

geocttt o>

OW oan

ns wy

dll fier

rete

Bebe: eh

. -

' -

(ang) eT

fv

ee

v4

’ Lis

AR

DINH

Cp may acuacy

’ vs

own

‘ tug

WADE

PRY Lo”

a

-* ‘

dhs bag

BsuRCTy “

- 4.6

ARK HATA

eee

rcrcccccc wire

e ee wee LLL

UBA JO~RY

Red

Lae ;

~enne Ls

IAW -?

' swan

a

7

‘ '

7

- cal

’ Cat

‘ vend)

' Gp)

-

oun, meee

rays) <w]

9904 Cate)

| aS

“ey Ory

(a. Je Guneygs

Wy, yy

wey

«BL vie.

2S

TOP

191 848

y YE L

AaNY 10,0

FL NG eGo we

OF THES

BRA Be

pervert) o8

f vauet|

B3u----> 199

isms coca

Oa oe

myn wen mine, — oo = en LTA

+ IN

Vo

ALS a

A ane

LS AW

LISAWA tog

AW

WAAR °

' \

. +1

.7 '

' -

' ‘|

~~

t ’

‘ Bon

' .

Larw a4)

‘ ‘\

ruta ‘ne

‘ ,

muita: Patina

at raid

yeu eee);

ahd mea

t ’

pase! Ta

Peony y

ey pa bepate yg

tay ’

uo gereyg ui

uo eit 4)

riaBin espe

ied

oie '

; potore,

id

" . SP,

sO aTNe

Ong >”

YING

KUL ’

A MAI

f 4 4

youu

et

ccnp Pap

pty

. "ses

AL “sce

. .

\de

i ‘

7 OIWA

AAAY

; ANAL

a ‘

ae AMMO

AddINO

I '

j ‘

A.

' *

4

a fintg)

+s

_ A

ye, we

=?

[DLPSe TEST

SE Stare] “Tevet

. +

cuban jo

a ;

«ft +

eoeyer 4

Cae) uo

‘ ‘

sour nideg e

Ce em

WUesI3 4

wale obeys

tad payanery

‘. t

aypnyag Tana

-. riba

we

Yee

7 TR

ae tag

ea .

‘ ,

wes be

Patt

a

Tucneinde aeded

+ 39

CVA Ny

. '

a woupinde.;

WOE Dg

> A

-

A ¢

i \

, ’

went,

Bae a

+ y

Acd

: ——

+4 wa

. :

’ AS44727

Sd "os

4 :

e

' BIW

WU

vai Lament

wan

‘ :

et!

' YRteld

[en T

RIGA

ot a cuba

‘wit -!

7 Caste),

t) Otw

YEP IH PTI

3A

perepatws yeris

un .

va erat

A, yo 7.

' 4

PUB fb

YALE 4

' HonvA

see eo

o> oh Al!

frves Fund

sey ured

-" '

"w+

OF ede

ay uA

. Te

. !

H y

. A

es nar

ert

1 al

. my

a AdMI

Ad >

ASE Ada

’ wal

o?* ‘

¥

1 é

, =~

ae +

} ,

ee a ie

ewe me mee

ee

wee

me ee ee ee

° www

eeweew

wee

ew ew

ew ew “EF

FP

ew were ee eee

a

A

(SSid) WarsAsqns jeoueuiy

198

1d WE AT) LAE?

IO (atins

so . Fe

yuma Krag?

(abp sey)

CoSprmyeg) COANE

tang) s9beg 20 Id)

sobre. I

4 jo 1a

ngie ree MAIO

WEG ay

wr dn 36) =e

.oley ow

Saige

Sueray mid

4 sSWwY-

1 SNidi4

narca

ie yO

usu

MORITA

aomday

oy acday

pp |

e Ow

oar

7 aFime

ed

“1 SSHd

Korg

t ope

dang a

aseidey jo HOD

one MRE SMT

azo aay

HEL ONC

T, aN

ata. ——L

a /

- | GMM

«SSH OE NM,

_ iaucctng

VIMO

le iy

GF IMIAA

da

detom 4

STKE AISIEER

AI an

' BP.

IG Aw

- RATA

Sig eM.

me BETS

; oe

an TSIRSB A

B) 2b

& oa

, 4

eee,

( wa,

vila

‘ !

: :

2 fe

Swrg-

z -

. we

ET ee 8

‘ VERSES

eee "

t -

(bola

, BuNGId

8 Stamper

trig .

SSH

tory Burwis

. BYNMIZ

“y J

Wd de RS

' a!

ardoylo jo"

how SujeauneS)

TG gb

wt ‘

ny ’

3

5 eee

sacnna Sat

_iayesseua! —*

Mepopua) GARB PLA)

AAyabpuA) Dou RUEKY

for 1 Sum eam

’ Wao

Balun i

abe

SAGA 5

Ate, SABPBIOATPY

paurday sore

pevedmy icuyy

anuans ig ADAM

« 7

Ma

aH

fuses ce

oR mopyqio

on mipugya

ay ROplai2

ON -

: Vie!

- -

-

. H

Gudd rw

YNKIa Va

“deo nA

peurie’s '

7 ween

ae

= '

' '

' wee

° jonedon

Toqauwavyay ~ s 1OPTT j OuyyBs aan

TT eae

4 Jopoenc

ner”

W909 DAW GOH

Lag

VaIM 5

es i

Joyo 5

pep ant meena

peninos spun ty

: SSHd

O4 q nyac 19

—_—

enupundyg Bee ee

ee wo HQ

ALAS

_ é

wid) Iho

+ .?

sol png

[FOL '

oe Oy

4 MN

.

oe

oe Brug

pdg

104

a? ansel

ee" OdxX38L

ir

* ;

Kee Payday

~ 7

.

wy SSAq of

af

wer"

: or

“oy

rome

‘ (@Opeagrg)

dSaM

payinorn qisen

. og)

a

¥ Gnas nedaypug

ae

fy Tr

sll, meee

buyued spA

cu peprcoaty

” Print rerros]

7.

- Odd

Hngg P

apr un

85g <_<"

amapusda &

+ SSAZ

OL soprowe

{Cuba

_ “a

GOdH

1.--- 1509

Sav OIA

+ #

stOpug iol

. ‘

t (red!

we

‘ ‘

' 1’

dSO

IY pens

44

| '

° !

, eon

my wor

, '

on

¥ 1

1020R

4 Bu Bang

227 oe

‘ pot

OO WIM

- ~

(wid) ah

“yaqiiase 4 Cunt)

Bae ay \

' we

. swe

' Capra)

ary wnot4q

ayy >

> YRC

ag NORE WA

wor onw

og |

-. SSHd

04 1

huew SIO

+ eyry

1 ~

Tey PRE

SI. SAU

SaNE + ON

yago7 "4

4 [|

tmgpm ‘

‘ é

cry '

; h--

= $509

OAV Gata)

wawaneyde

1 1

“~. sOUPU

AEE

PY BOT

\ |

: ampnys

a ane

' a8

1 A

Oe ie)

uuisugdx4 m4

' '

u .

10g Ope

J Ouro aan

4 pe

I wipe

4 Bu

bang .

~ 4

“ edeg

n ao.

--

1 .

crcsctcct

5.

; 1

Qe woiais fears

‘ YSSAaM

‘ '

.. :

Cotpuars) ASM

‘ ‘

rd »

‘ ’

| t

*. '

UE USRULEWY

. '

3 +)

-_ ’

CaBpugess '

’ ~

' ‘et

: - We

. watia verlag

\ +.

‘ .

oy oe

a

Jussyeo

JayFEOD) 8

. au

pone ‘

Py .

1 ‘

I? Bam pues»

~- SHER

™ \

wang fo

' pom

.. I-

- wwia)

‘ 4

aa SSuevaviegy

ge HACOY

-~ x

1509 ony

1 1

*.

4 Peg

pag

Wy et

~ ‘Miitol

“ay HGQr)

---4

' *.

wm

em

Purrag 5 ‘3

wag) on

SWHLe

we

IEDR SDED

wo.

' t

. sow 4

Capi Deon, popnoran

iso rpeaseg

tn yok

teat SAGSSHd

Of '

' a

OOS IM

aK eb haus

4 <add

on BEERS

7 He vata}

' ,

= NV

QacqH

SAGA PIE

' '

' ‘

Bau

ay

a

jue uas

rr day Ag

3 i

‘. eon

wk

ren «

CSHL ¥e

\ ‘

. HiOGuw

\

op ope y Buy

ean '

J .

losiqor |

mot

, ‘

~ |!

HMA

---+

[ a’

7 Taber

7 77

Bumabizan ‘

. igo

see o

4 he) 4

i ‘

‘ Tre

“a (abpagegs

i Tao

— —»

SAND e_sne2s

#6 SAA

ts04 payne

aun oe,

* ‘

‘ i

wauiaceysay on

ae> SSH

Of y

159 OF

paunoo apy riise4

wingpowd <4

a ‘

YOST

TOT RY

34

wan

t “

goarw

Ss .

a)

ADI

MH piel

Eg

DOTNUE g

BASSHid gPIP

2 =

: ‘

e wi

oe we

PTS T TTT

“ss

- me

TNIOH

€ SASHL

. :

HICH

’ aor y

AMD

2 owe eee

; rcs

r“ro.

\: c

--F ro

ee

| Osea tt

ager to x,

+ ae

(ate ass

i He dB

sb atbuaygy

§ sBprag ‘

o ‘

we a

' Wourgondey bewarnds

Won jouzue

' (tie 4

yd SPrgLE

CoOpryrgy |

yoyoapag |

Agee

Puig

sag Aguieday

P poisedug

of Fd

mipowed eon

PSO

Functional Subsystem

SSAB OL

---- Sat

x

PART Arges

\. _

aR GEL qo.

te page)

(afin

a7

1 1

ab

8 uenderq

ed ta ' i) ‘

AR PUOdES .

buyers paBeine rg

rt "09 ‘aN

yso9 aay

HOD OfMy

br OA

E500 SAY

EIST D ene

ft ' a

t tos

mney ir

“yaays BINjON AS 10

t \

, "

” Oy eee

e Bony

Wr

Ory | Met

aya

' tddry

ra

| (adit 4

\ Odo

' =~

YCboo

’ Oy,

Aye

1 I

1 4505

i 7

AAS

4 1

a 5)

} >

' cad

1 wea

t wid

Wd,

ty wid

trae

(ed

dyad vig

duedan edey

sp ede ey

wmuvredey —

Ougueday into

Agperg weg

peda Ur ded |

MRE MO

NLT duahad

wines med

coed OE

abpg ad

aye m0

7 LPAI

Fe DUC

8S be oe,

eee

SHAT aun

tops]

Boa He

Guy braan,

THETA

eo

plrghamene

ye

4 yer

oon LUMA

Susutom es

Ogd4n

FT

OR

ee NS

pupitroan AEA

yp gag Hodas dod

Hash HID

AAISAM

ying ns

/

(SSNa) warsAsqns jeuonoun4

199

4

foro tp A

FB cbr

ep ;

woe

ye ys hasaanugl

BAT AEP

E a 1599

: 4 gousriee’

tA £

aye

. >

G5

ut soln

sadaig

70 ary

n Ae Oy

_ deedbe as ey

= gerbe,

buy sunny

- tu

i Lote

8odY---->

sate

nn. o aay

a ——

” Gud

sz SR

(14h $3800 Je

, 7 Bana

<

“7 aot

* woe”

% TTA

ybonrg '

cried

1 .

~ anuned

7

\ +

‘4 1

” e

weer,

' *

-~

- qeewesh sey

,

u Tse

t gcrtias

4

\ ern Sd

As

- wl

daddy

.

, '

~ “ye eg 7

Csetpig) '

a

~we

= 7)

.

’ 1

cA HIG

In AP y

worpYOD

Cow) “

s meee

~eaer”

- 1:

.

3 .

: yea

bpog Uefa

ds 38.9 sn

OM aS urse

ees

Tat eset

pig) Set pug

» ey

a

; !

ryan

7 snd

ape ung

eS

SSHH

OF} dni

aide tna

' '

' vetpngeery

oft aucsv44- 37525 2+--

wee spy

oll

Jac hbapeu wa

c /

AHA

; (abqa)

Tae SPATS

ciintene rg ‘

‘ UoRIPLE>

j09, ‘

5

1 {

L oe

Ui sao e

mg

| '

dHddW4

\

’ :

‘ ‘

*, 7

meee

el -

=

' S23 tpg

onterg ‘

vow wep

ie) w

“4

“TTS

ae ee,

(xP pag) ?

‘ —

- ~~

me

. f

Jeers

)

’ sted]

y to(E Wl

‘1 aEnbapyoury

oe Tass0b Bug

car Sm

UUIBPUO JeUy

1a. 4)

rg

I!

1 -_>~

aT Dapy

oun

. UL

Sa Bot ge

aenbep ‘

wo 19651 @

>

; ary

. eh 4a

Ll --

REWBSEE

Tay '

. wieder

wwleya ‘

~ °

\ -

c l

"BOY

ee

_ >

a wwe

apeu FY

‘ ry

oo

sOd ID

-* é_

\

Ms.

t.

! Barna

Gaarvig S77.

4

See

=.

hk vay

' rf

~--gsdepiayt oor”

SSI tory

ssityos --

t peace”

q

4 enBpug

10 BUY

' SSNS

OL Gg

7: Cas

waka capa) Py

4 .

‘ ’

wv '

Uni a) sata

90 FORREST

8 PRLPIBA

Ty '

sal pug anf

wget. Sas

gposie ne

' ‘

a“ oenbepy 2)

ioe (Rrbope

ras

sone. 2usyas] Maritain

uiey Toy

Garg) ep gon

'

i a

aoe EL

8 Di

rg ew eh

ee ee

eee eee ee

eee wd

co 1

oy Eph

g werd OAR Ys

' (saB pug)

Bee Fg

Ivis ‘

niephapeul ‘

' ase

44

i t

vu ppuun my

Hirty

* lpn

iaeng '

Y

: i

PTT

if tte

ip wee

. ‘

sy

I

uu ig

--.._-_J ‘

441s '

on

' seBpuig

go gs Spng

\ UuMmpHuny

wey 5

; (

'

e

' ar day

OURY genbamy aur 4

_, bITU7888

78) S8bpg jd

— *

eratiprgycaruss uy

’ Cy A$)

2060138 Jo

! =>

murnbapey > ing

". ul sebrna

| a

Seng

OORT BTR? Te)

ar nbapry) 254

rebpng '

Soy

ee"

gaan

-.. O4v4a

—— Pe

eee

wnsmteg 4”

nestor ‘sn

, ae

GuNWVd g

BUNWId —

, chaciy 20h

i —

- _

@ ty

Ae bot

. SYN

aaa +

UNNI e+.

>

7 ~

t i

“ene

ord

‘ ‘

Vv tA

nas

“+

wee

~ f

7 re

sae 4

Utot em

wae”

V+

' trig \*tes@

9 qeday

Oi asseBpri

ve Dpary a

! SSasCd

S54

q SSA TOL

To Renee

re ‘

Y

t aye ribo

ny ver a

Senge

au 9fe 1

ye 0

Ob gaadp

np '

1

sung ony

Hpr@ peg

ap Hr bepy

aw

Ko

- seins. ey

Myer ete]

t 7

*

feeb 4

IKAET saépriq

po ’

on :

a uhv4a4 ahd

aerbenvar sag

ot My den nary

“so

1 ‘

\ UqpoUd) DoOS

awnbapruy vu y

1

~

1 '

; UF

SABpLG se

op boom eed

1

° wo ’

— gunida

aabicu

!

' fasi¢ratppa

yo potpn

< Ww

ca

1 qUER

Dae em

i “

“Sy itauy aneg

° ty ag

iy

i ae

BeNbape ony

ay aig

ob dg

atpugie ytorg

1

ee

1 .-

1 i

; aU

UIEBY PANINI

1 ’

* Gale fe

aay 4d €—_1___

i f

ayenbapeu; oung

4 1

EG iy

mae -

: aad

Sos ie

FOpING ay

ows TUsERY

4 +

.

i '

oe “ft

Y

303 3.1914

arnbamy ?

Neay

na

-7

“ '

-? a.

‘%

oun

gj .4 RopAK

pet mee

meow

ew eH”

ston

oopsgo

we

1

.

-

a |

NEVIS ong

ou MELTS

1 Panel

7. Ssnaes

' .

(wag) wig?

aye y

ain sods: weer ewe eww

we

l Vsate

sy

ma

7 cwiqi saba.gt-20!

pg

epg

fabpg ' F

die nbagy oun

_—

(1A) #8

one

jo aie:

a 40

atta eee

|

“5

@ poog

Panasarg at

1 auRL

cng

an

anguarasy Mend

speu ,

A

' feed eae

seu Ries

; GtAwde

4 -- got

A

‘ ‘

aenbapeul ound

Wet our gop

Opn WED

4 '

Q

f Ff

\ 1

= -~s-wee

4

1 aay,

gk

Boa aaa

: 7

¥ >

Gels s

adidas

:

=

\ ..

\ .

‘ 4

patie

ber ‘sy

1 8

e wid

'

~ was

t uepria © Op

iy wuspuip

ou '

SP) ‘

eet”

“Ssqaen _-.

oe

' Seren

nen ele

er ------

epnaisert ’

dc

““a

pa, ‘

—_— ‘

(28g Eg

éabpud /

Ber bapy tatue

ant rat

W Whecna

uae so

> pantyig |

MOGI

,

a

‘ «

itvdd

.

. Ut

saben

+ I

. menbapre;

vung |

Hy

OF ,

5 *

~ .

ns em

Pic

ad

cee wes!

“tego

mal Og,

RB Pg) eaGpug

jo SevjGg~

. af

. om

aficug #

;

=

: '

ah y

asua 1-8

ayy .

=Alsg

'

7) .

W1O--- =e

Ayn ;

_

ee ;

s \

SM Le

wee eee

ee ef ee ee

ee

ETRY pa

,

(gsod ee

Cap aeeEs

a! we

c

Me ee

ee eee

eee

’ TSCM

BE PUBL

Eee Prod ‘

wet

te rw ee

ee eee

eH >

SSATOL

4-

> Fg

* wm et

rw wr

eee

ee ee eee eee ee

.f*

Cy (Ss

m7 ab

SiINa- SsHa}

asds juawabeuey

sbplig (WazsAsqns

[eB atSAUd

200

Physical Subsystem: Pavement Management System

Pha ed

mae et

ee

ee

ee een

re eee

ee eee

eee

a

é

e

é a f ’ 4 '

Catyy-s ea)

f sewyounae

' cc

la yowua

neue

d

ruil, Cu ieee

' ar

JAP brsypargy

in Aer ang

‘ .

7 Jd

LOH

( -

’ ~

Hid ts}

z *

~ )

‘ |

‘ /

1%

o

rn ’

' ‘

' .,

'

CU rant Btpy

yo |

. ~

é

vompua9 '

- POpes

of 898 qh ICh '

“f,

hope 4 Buns

Frey '

aon,

1 ’

.

HOLOAM

' '

“. TA V

E au

t .

+ ay

AeronyB

th 10

' '

t ae

Y Bue 10129339

; Had

' '

t '

t t

‘ \

1 +’

‘ 1

f] t

' !

‘ ‘

SSAFOL '

I .

¥ ¥

* '

! ‘

~

1 :

yang) FR;

' \

‘ -

stowaway

qee eed Ll

s AMEE

+ '

' ‘

° (and

auED T¥,

! '

‘ Vopugn

wewaw{

* H

1 |

s ,

UWI

Us Awnaytit

‘ -_

a

a

a”

* eae ert

, te.

SdH

1 (apy DUET

ME mYB IH LC ran

I! .

1 feomy

eeutine, Ao

ft +44

' HWE

te 4

1 a4

(Mayoryg BNET)

funigMenmgfiiy jo

¥ ’

Aeneu H te

uappucsy (AS O

IA

Ot pPapoouLe

D) '

. ae

Ww

{ue 7yw qiuj

‘ ¥

\ Wyse g Aisnp

| fhe ay

SSATO!

~*

Hay

Hoda

_

- -

-

e ”

7

.

HL

(ayy -ouer,

UdIyDUE> pavarE gy

yao Ss

ui sey

ayy

3d 4SH

+ _

=» SSAT'SSNIO}

7s

-

= ’ , t 1 t ' _

‘ -

1 .*%

a.” "7

"ht -"

'

-”

i .7

‘ +

="

1 [ETA

ae

a

‘ Tene Lk

e 1

TRIES

~ J

, '

, Hea

7, a

I “ea

'

& '

- I

SSNS

OL .

ve t

SSAZO1~~_!

ema

ne yea

+ ea

(ura) Agnnyftiyg

pap tiajag

uyetpeg mew pe

Pe

2’) HLGSW

| i

u

Taare

eo ! SS

Js tong

em ew eee hee ~ se bee eee

'

fu!

Seenutiy waisued

” ee we

guts ew ped

HIG

— .

- 4

1 4 ~

¥ ~\

Ssnsot u

HAAWH

(SWd-S SHd)

Wal SAG

juatAabeUuey TUsulaAeg

:WuaRSASGNS jesIsAug

201

APPENDIX D: DYNAMO CODE

Evaluation Subsystem

L PCIV.K=PCIV,J + (DT)(HR.JK) N PCIV=PCIN C PCIN=11933

* PCIV - AVG INCOME LEVEL OF VIRGINIA ($/MAN.YR)

R UR.KL=PCIV.K*IIRP

* TTR - INCOME INCREASING RATE ($/YR) C IIRP=0.00143

* IIRP - INCOME INCREASING RATE PARAMETER (DIM) L HTMED.K = HTMED.]+(DT)(TMED. JK) N HTMED=0 * HTMED - HIGHWAY TOTAL MAINTENANCE EXPENDITURE DISCOUNTED

L HMEUD.K=HMEUD,J+(DT)(TMEUD JK) N HMEUD=0

* HMEUD - HIGHWAY TOTAL MAINTENANCE EXPENDITURE UNDISCOUNTED

L HCEUD.K =HCEUD.J+ (DT)(TCEUD. JK) N HCEUD=0

* HCEUD - HIGHWAY TOTAL CONSTRUCTION EXPENDITURE UNDISCOUNTED R TCEUD.KL=INFLF.K*THCE.K

* TCEUD - TOTAL CONSTRUCTION EXPENDITURE UNDISCOUNTED L HCED.K=HCED.]+(DT)(TCED.JK) N HCED=0 * HCED - HIGHWAY TOTAL CONSTRUCTION EXPENDITURE UNDISCOUNTED

R TCED.KL = (INFLF.K*THCE.K)/(1+ DISR)**TIME.K

* TCEUD - TOTAL CONSTRUCTION EXPENDITURE UNDISCOUNTED R TMED.KL=(INFLF.K*(TBEXPD.K + THME.&))/(1 + DISR)** TIME.K

* THED - TOTAL HWY & Bridge Maint EXPENDITURE DISCOUNTED ($/YR) R TMEUD.KL=INFLF.K*(TBEXPD.K + THME.K)

* TMEUD - TOTAL HWY & Bridge Maint EXPENDITURE DISCOUNTED ($/YR) A WLOSF.K = ((0.8*(1* Ahstpc.k + 2* Ahdtpce.k + 4* Ahdtpc.k)/TOTALH.K)*

+(0.2*(1*BPFC.K+2*BGC.K+4*BFC.K + 8*BPC.K + 16*BCC.K)/TOTALB.K))

* JFCTOR - J FACTOR N WLOSFEN = ((0.8*(1*hstpcN + 2*hdfpcN + 4*hdtpcN)/TOTALHN)*

+ (0.2*(1* BPFCN + 2*BGCN + 4*BFCN +8*BPCN + 16*BCCN)/TOTALBN)) A LOSF.K=TABLE(LOSFT, WLOSF.K.1,6.1) T LOSFT=0.1/0.2/0.3/0.4/0.6/1 * LOSF-LEVEL OF SERVICE FACTOR (DIM) N LOSFN = TABLE(LOSFTN, WLOSEN, 1,6, 1)

T LOSFTN=0.1/0.2/0.3/0.4/0.6/1 A LHPA.K=HPALK*(1-HDRM.K) * LHPA - LEVEL OF HWY PHYSICAL SUFFICIENCY (DIM)

A PLS.K=LHPA.K*BPALK

bo oO bho

* PLS - PHYSICAL LEVEL OF SERVICE OF BRIDGE (DIM) A VOPC.K=(TABLE(VOPCT,PLS.K.0,1,0.2))*tvol.k*totmilg T VOPCT=0.4/0.3/0.22/0.18/0.16/0.15 N VOPCN=TABLE(VOPCNT,PLSN,O,1,0.2) T VOPCNT =0.4,0.3,0.22,0.18,0.16,0.15 * VOPC - VEHICLE OPERATING COST ($/MI) * # ADDING CAPACITY FOR EXPANSION A CAP.K =CLIP(658.88*2000/(117.91*2),485.14*2000/(117.91*2), TIME. K,5) N CAPN=485.14*2000/(117.91*2) * CAP - NETWORK CAPACITY A AVBC.K=MIN(HRV.K/CAP.K,1) N AVBCN=MIN(HRVN/CAPN,1) L AADT.K=AADT.J+(DT)(ADTINC JK) N AADT=AADTN N AADTN= ((60725.*0.3*2 + 60275*0.7)*6.75-+ (25171*0.3*2+25171*0.7)*24.29*

+ (33201*0.3*2 +33201*0.7)*86.87)/(117.91) *A ADT - AVERAGE ANNUAL DAILY TRAFFIC (VEH) A HRV.K=AADT.K*WAHR N HRVN=AADTN*WAHR * HRV - HOURLY VOLUME C WAHR=0.0417 * WAHR - WEIGHTED AVERAGE HOURLY VOLUME RATIO (DIM) R ADTINC.KL=AADT.K*0.001 * ADTINC - AADT INCREASING RATE (VEH/YR) A TVOL.K=(AADT.K*220) * TVOL - ANNUAL TRAFFIC VOLUME (VEH) N TVOLN=AADTN N PLSN=LHPAN*BPAIN N LHPAN=HPAIN N HPAIN=(HSEPCN + HDFPCN*WFDFCH + HDTPCN*WFDTCH)/TMHN N TMHN=HSFPCN+HDFPCN+HDTPCN A TTLKL.K=FFTTLKL.K*(1-(1-LOSF.K)*(A VBC.K))/(1.0001-A VBC.K) * TTLKL- TRAVEL TIME (MIN) A SPD.K=MIN(TOTMILG/(TTLKL.K/60),FSPD) N TTLKLN=FFTTLKL*(1-(1-LOSFN)*(A VBCN))/(1.0001-A VBCN) A FFTTLKL.K =(TOTMILG/FSPD)*60 * FFTTLKL - FREE FLOW TRAVEL TIME ON LINK KL (MIN) C FSPD=80 * FSPD - FREE FLOW SPEED(MI/HR) A DFTT.K=(TTLKLN-TTLKL.K)/TTLKL.K A DFIOLK=TABLE(DFIOIT,DFTT.K,-.5,.5,.1) T DFIOIT =-.001/-.0008/-.0006/-.0004/-.0002/0/.0002/.0004/.0006/.0008/.001 R UAUBEN.KL=((TTLKLN-TTLKL.K)*VOT*INFLF.K)** ((TVOL.K+ TVOLN)/2))*(ADTSD/TOTMILG)

* UAUBEN - UNDISCOUNTED ANNUAL USER BENEFIT ($/YR) C ADTSD=67 * ADTSD - AVERAGE DISTANCE TRAVELED IN SALEM DISTRICT (MI) L UUBEN.K=UUBEN.]+(DT)(UAUBEN. JK) * UUBEN - UNDISCOUNTED USER BENEFIT ($/YR) N UUBEN=0 R DAUBEN.KL=((TTLKLN-TTLKL.K)*VOT*INFLF.K)**

Ko

Oo Cand

((TVOL.K + TVOLN)/2))/(1 + DISR)**TIME.K * DAUBEN - DISCOUNTED ANNUAL USER BENEEIT ($/YR) C VOT=0.15 * VOT - VALUE OF TIME ($/MIM) L DUBEN.K=DUBEN.]+(DT)(DAUBEN. JK) * DUBEN - DISCOUNTED USER BENEFIT ($/YR) N DUBEN=0 R UANUBEN.KL=(PV.K*0.17*PCIV.K*DFIOLK) * UANUBEN - UNDISCOUNTED ANNUAL NON-USER BENEFIT ($/YR) L UNUBEN.K=UNUBEN,] + (DT)(UANUBEN JK) * UNUBEN - UNDISCOUNTED NON-USER BENEFIT ($/YR) N UNUBEN=0 R DANUBEN.KL= (PV.K*PCIV.K*DFIOLK)/(1+DISR)**TIME.K * DANUBEN - DISCOUNTED ANNUAL NON-USER BENEFIT ($/YR) L DNUBEN.K=DNUBEN.] + (DT)(DANUBEN JK) * DNUBEN - DISCOUNTED NON-USER BENEFIT ($/YR) N DNUBEN=0 A TLCCUD.K=BLCCUD.K + HLCCUD.K * TLCCUD - TOTAL LIFE-CYCLE COST UNDISCOUNTED A NVB.K=UUBEN.K+ UNUBEN.K-TLCCUD.K * NVB - NET VALUE OF BENEFIT UNDISCOUNTED($) A TLCCD.K=clip((BLCCD.K + HLCCD.K),1,TIME.K,1) * TLCCD - TOTAL LIFE-CYCLE COST DISCOUNTED A NPVB.K=DUBEN.K + DNUBEN.K-TLCCD.K * NVB - NET PRESENT VALUE OF BENEFIT DISCOUNTED(3) A HCEUDE.K =CLIP(HCEUD.K,1,TIME.K,1) * HCEUDE - HIGHWAY TOTAL CONSTRUCTION EXPENDITURE ENUMERATOR L HEXPD.K =HEXPD.J+(DT)(ERH.JK) N HEXPD=HEXPDN C HEXPDN=0 A CCBCR.K =((UUBEN.K + UNUBEN.K-(HMEUD.K*HEXPD.K/TOTALH.K))* /(HCEUDE.K*DISR))*(1-EXP(-DISR*N))

* CCBCR - CONTINUOUS COMPOUND BENEFIT COST RATIO (DIM) C N=40 * N - PROJECT LIFE (YRS) A DRE.K=UUBEN.K + UNUBEN.K-HMEUD.K * DRE.K - DIFFERENCE BET. EXPENDITURE AND REVENUE A GTRMBR.K=(TVOL.K*TOTMILG*RMFT.K)/((HMB.K + BB.K)*ADTPG.K) * GTRMBR - GASOLINE TAX REVENUE MAINT. BUDGET RATIO (DIM) C TOTMILG=117.91 * TOTMILG - TOTAL MILAGE IN SALEM DISTRICT

204

Financial Subsystem eb Bb 9 Oh Ob Of 9 DECISION VARIABLES 2h 9G Of oh 9 9 oh Of OG of

C FBHM=0.5 * FBHM - FRACTION BUDGET TO HWY MAINT. (DIM) A FBHC.K=1-FBHM * FBHC - FRACTION BUDGET TO HWY CONSTRUCTION (DIM) C FCBB=0.5 * FRACTION CONSTRUCT. BUDGET TO BRIDGE (DIM) C FMBB=0.5 * FRACTION MAINT. BUDGET TO BRIDGE (DIM) A FMBP.K=1-FMBB * FRACTION MAINT. BUDGET TO PAVEMENT (DIM) CR ee oe a a a

L PV.K=PV.J+(DT)(BRV.JK+IMRV.JK-DRV.JK-OMRV.JK) N PV=PVN * PV-POPULATION OF VIRGINIA (PERSONS) C PVN= 6618358 R BRV.KL=BRPV*PV.K * BRV-BIRTH RATE OF VIRGINIA (DIM) C BRPV=0.014591 * BRPV-BIRTH RATE PARAMETER OF VIRGINIA (PERSONS/YR) R DRV.KL=DRPV*PV.K * DRV-DEATH RATE OF VIRGINIA (PERSONS/YR) C DRPV=0.008249 * DRPV-DEATH RATE PARAMETER OF VIRGINIA (DIM) R IMRV.KL=IMRPV*PV.K * IMRV - IN-MIGRATION RATE OF VIRGINIA (PERSONS/YR) C IMRPV=0.001168 * IMRPV - IN-MIGRATION RATE PARAMETER OF VIRGINIA (DIM) R OMRV.KL=OMRPV*PV.K * OMRV - OUT-MIGRATION RATE OF VIRGINIA (PERSONS/YR) C OMRPV =0.001737 * OMRPV-OUT-MIGRATION RATE PARAMETER OF VIRGINIA (DIM) L VV.K=VV.J+(DT)(VVINC.JK) * VV - NO. OF VEHS IN VIRGINIA (VEHS) N VV=0 R VVINC.KL=VV.K*VAGR * VVINC - VEH. INCREASING RATE (VEH/YR) C VAGR=0.01 * VAGR - AVG ANNUAL GROWTH RATE OF VEH. IN VIRGINIA (DIM) A VMT.K=ATMV*VV.K * VMT - VEHICLE MILE TRAVELED (VEH-NI/YR) C ATMV=12500 * ATM - AVG TRAVELED MILE PER VEH. (MILE/YR) A SS.K=PPR*PV.K * SS - STATE SALES ($/YR) C PPR=1000 * PPR - PERSONAL PERCHASE RATE ($/YR-PERSONS)

205

A MVLF.K=VV.K*RMVLF * MVLF - MOTOR VEHICLE LICENSE FEE ($/YR) C RMVLF=26.5 * RMVLE - RATE FOR MOTOR VEHICLE LICENSE FEE ($/VEH) A TVVV.K=AVVV*VV.K * TVVV - TOTAL VALUE OF VEH. REGISTERED IN VIRGINIA ($) C AVVV=20000 * AVVV - AVG. VALUE OF VEH. REGISTERED IN VIRGINIA ($/VEH.) A MVSUT.K=RMVSUT*TVVV.K * MVSUT- MOTOR VEHICLE SALES AND USE TAX ($/YR) C RMVSUT=0.03 * RMVSUT- RATE FOR MOTOR VEHICLE SALES AND USE TAX (DIM) A MFT.K=RMFT.K*VMT.K * MFT - MOTOR FUEL TAX ($/YR) A RMFT.K=0.177 * RMFT - RATE FOR MOTOR FUEL TAX ($/GAL) A ADTPG.K=TABLE(ADTPGT,SPD.K,40,80,10) T ADTPGT =40/35/30/25/18 * ADTPG - AVG DISTANCE TRAVELED PER GALLON (GAL/MI) * A ADTPG=20 A SST.K=RSST*SS.K * SST - STATE SALES TAX ($/YR) C RSST =0.045 * RSST - RATE FOR STATE SALES TAX A TTF.K =FMVLFT.K*MVLF.K + FMVSTT.K*MVSUT.K+ FMEFTT.K** MFT.K +FSST.K*SST.K * TTF - TRANSPORTATION TRSUT FUND ($/YR) A FMVLFT.K =3/26.5 * FMVLFT - FRACTION MOTOR VEHICLE LICENSE FEE TO TTF (DIM) A FMVSTT.K=1/3 * FMVSTT- FRACTION MOTOR VEHICLE SALES AND USE TAX TO TTF (DIM) A FMFTT.K=2.5/17.7 * FMETT - FRACTION MOTOR FUEL TAX TO TTF (DIM) A FSST.K=0.85"(0.5/4.5) * ESST - FRACTION STATE SALES TAX TO TTF (DIM) A HMO.K=FMVLFH.K*MVLF.K + FMVSTH.K*MVSUT.K + FMETH.K** MFT.K+ FSSH.K*SST.K * HMO - HIGHWAY MANAGEMENT AND OPERATION FUND ($/YR) A FMVLFH.K = 16/26.5 * FMVLFH - FRACTION MOTOR VEHICLE LICENSE FEE TO HMO (DIM) A FMVSTH.K =2/3 * FMVSTH- FRACTION MOTOR VEHICLE SALES AND USE TAX TO HMO (DIM) A FMFTH.K = 14.85/17.7 * FMFTH - FRACTION MOTOR FUEL TAX TO HMO (DIM) A FSSH.K=0.85*(0/4.5) * FSSH - FRACTION STATE SALES TAX TO HMO (DIM) A TTRV.K=clip(1.7e9,(TTF.K + HMO.K + FAV.K),time.k,0) * TTRV - TOTAL TRANSPORTATION REVENUE IN VIRGINIA ($/YR) A FAV.K=500000 * FAV - FEDERAL AIDS FOR VIRGINIA A ABH.K=FRHWY*TTRV.K

* ABH - AVAILABLE BUDGET FOR HIGHWAY ($/YR) C FRHWY =0.8 * FRHWY - FRACTION REVENUE TO HWY (DIM) A HMBV.K=FBHM*ABH.K * HMBV - HIGHWAY MAINT. BUDGET IN VIRGINIA ($/YR) A HMBS.K=FMBSD*HMBV.K * HMBS - HIGHWAY MAINT. BUDGET IN SALEM DISTRICT ($/YR) C FMBSD=0.15 * FMBSD - FRACTION MAINT. BUDGET TO SALEM DISTRICT (DIM)

A HCBV.K=FBHC.K*ABH.K * HCBV - HWY CONSTRUCTION BUDGET IN VIRGINIA ($/YR)

A HCBS.K=FCBSD*HCBV.K * HCB - HIGHWAY CONSTRUCT. BUDGET IN SALEM DISTRICT ($/YR) C FCBSD=0.15 * FCBSD - FRACTION CONSTRUCT. BUDGET TO SALEM DISTRICT (DIM) A BB.K =clip(clip(1.49e6*k,1.49e6,time.k.5),FCBB*HCBS.K + FMBB*HMBS.K.time.k,0) * BB - BRIDGE BUDGET ($/YR) A HMB.K =clip(clip(6.2E6*K,6.2E6,time.k.5), FMBP.K*HMBS.K.time.k.0) * HMB - HWY MAINT. BUDGET FOR PAVEMENT MANAGEMENT ONLY ($/YR)

cK=1 * K -Budget Multiplier

Functional Subsystem

* ***Expansion increase bridge cost 50%**** C TEST1=0.9015

C TEST2=0.10035

C TEST3=0.043919

C TEST4 =0.173385 A MCDFH.K=29000

*A MCDFH.K=TABLE(MCDFHT.HDFPC.K,0,600, 100)

*T MCDFHT = 1500/4500/10000/24000/33000/39000/43000

* MCDFH-ORDINARY MAINTENANCE COST OF HIGHWAY ($/LANE-MI)

A MCDTH.K=73000 *A MCDTH.K=TABLE(MCDTHT.HDTPC.K,0,600,100)

*T MCDTHT = 43000/55000/62500/97000/12500/14500/150000 * MCDTH-MAINTENANCE REPLACEMENT COST OF HIGHWAY ($/LANE-MI)

A ECH.K=1E6

* ECH - EXPANSION COST OF HIGHWAY ($/LN-MI) *AEP.K=1

A EP.K=clip(1.5,1,time.k,5)

* EP - COST EXPANSION PARAMETER

A PMCB.K =EP.K*(CS*ARS.K+ CSDC*ARSDC.K + CEJM*AREJM.K+ CBM*ARBM.K-+ *

CPGM*ARPGM.K+CSP*ARSP.K)

* PMCB.K - PREVENTIVE MINTENANCE COST OF BRIDGES ($/BRIDGE) A MNRCB.K=EP.K*(CDO*ARDO.K + CCP* ARCP.K + CPCH*ARPCH.K + CEJR** AREJR.K+CRPT*ARRPT.K+CBAR*ARBAR.K + CDSR*ARDSR.K + CSMR*ARSMR.K +*

CCDR*ARCDR.K +CDER*ARDER.K) * MNRCB - MINOR REPAIR COST OF BRIDGES ($/BRIDGE)

A MJRCB.K=EP.K*(CDKR*ARDKR.K + CSSR*ARSSR.K+ CCBR*ARCBR.K)

* MJRCB - MAJOR REPAIR COST OF BRIDGE ($/BRIDGE)

A RHCB.K=EP.K*(CRA*ARRA.K+CRP*ARRP.K+CRLP*ARRLP.K+CRLA*ARRLA.K +* CRCD*ARCD.K)*1.5

* RHCB - REHABILITAION COST OF BRIDGE ($/BRIDGE)

A BWC.K = 500000

* BWC - BRIDGE WIDENING COST

A RPCB.K=EP.K*1500000 C CS=8316 * CSV - AVG. COST OF SCOUR ($/BRIDGE) A ARS.K=TEST1

* ARS - AVERAGE ANNUAL APPYING RATE OF SCOUR (DIM) C CSDC = 36656.28

* CSDC - AVG. COST OF SEALING DECK CRACKS ($/BRIDGE) A ARSDC.K=TEST1

* ACP - AVERAGE ANNUAL APPYING RATE OF SEALING DECK CRACKS (DIM) C CEJM= 1753.49 * CEJM - AVG. COST OF EXPANSION JOINT MAINTENANCE ($/BRIDGE) A AREJM.K=TEST1

* AREJM - AVERAGE ANNUAL APPYING RATE OF EXPANSION JOINT MAINTENANCE

(DIM) C CBM=825

208

* CBM - AVG. COST OF BEARING MAINTENANCE ($/BRIDGE) A ARBM.K=TEST1 * ARBM - AVERAGE ANNUAL APPYING RATE OF BEARING MAINTENANCE (DIM) C CPGM=2917.43 * CPGM - AVG. COST OF PARAPET GUARD RAIL MAINTENANCE ($/BRIDGE) A ARPGM.K=TEST1 * ARPGM - AVERAGE ANNUAL APPYING RATE OF PARAPET GUARD RAIL MAINTENANCE (DIM) C CSP =5000.96 * CSP - AVG. COST OF SPOT PAINTING ($/BRIDGE) A ARSP.K=TEST1 * ARSP - AVERAGE ANNUAL APPYING RATE OF SPOT PAINTING (DIM)

C CDO=87463.41 * CDO - AVG. COST OF DECK OVERLAY ($/BRIDGE) A ARDO.K=TEST2 * ARDO - AVERAGE ANNUAL APPYING RATE OF DECK OVERLAY (DIM) C CCP =414739.60 * CCP - AVG. COST OF CATHODIC PROTECTION ($/BRIDGE) A ARCP.K=TEST2 * ARCP - AVERAGE ANNUAL APPYING RATE OF CATHODIC PROTECTION (DIM) C CPCH=71135.17 * CPCH - AVG. COST OF PATCHING ($/BRIDGE) A ARPCH.K=TEST2 * ARPCH - AVERAGE ANNUAL APPYING RATE OF PATCHING (DIM) C CEJR=1753.49 * CEJR - AVG. COST OF EXPANSION JOINT REPLACEMENT ($/BRIDGE) A AREJR.K=TEST2 * AREJR - AVERAGE ANNUAL APPYING RATE OF EXPANSION JOINT REPLACEMENT (DIM) C CRPT=19930.68 * CRPT - AVG. COST OF REPAINTING A ARRPT.K=TEST2 * ARRPT - AVERAGE ANNUAL APPYING RATE OF REPAINTING (DIM) C CBAR= 1680 * CBAR - AVG. COST OF BEARING (& ANCHOR BOLT) REPLACEMENT ($/BRIDGE) A ARBAR.K=TEST2 * ARBAR - AVERAGE ANNUAL APPYING RATE OF BEARING (& ANCHOR BOLT) REPLACEMENT (DIM) C CDSR = 100000 A ARDSR.K=TEST2 C CSMR = 100000 A ARSMR.K=TEST2 C CCDR=100000 A ARCDR.K=TEST2 C CDER = 100000 A ARDER.K=TEST2

C CDKR= 116047 * CDKR - AVG. COST OF DECK REPLACEMENT ($/BRIDGE)

209

A ARDKR.K=TEST3 C CSSR = 2288661 * CSSR - AVG. COST OF SUPER STRUCTURE REPLACEMENT ($/BRIDGE) A ARSSR.K=TEST3 C CCBR = 100000 A ARCBR.K=TEST3 %

of

C CRA =291096 * CRA - AVG. COST OF REPAIR OF ABUTMENT ($/BRIDGE) A ARRA.K=TEST4 C CRP =32561 * CRP - AVG. COST OF REPAIR OF PIER ($/BRIDGE) A ARRP.K=TEST4 C CRLA =356492 * CRA - AVG. COST OF REPLACEMENT OF ABUTMENT ($/BRIDGE) A ARRLA.K=TEST4 C CRLP =84987.46 * CRP - AVG. COST OF REPLACEMENT OF PIER ($/BRIDGE) A ARRLP.K=TEST4 C CRCD = 100000 A ARCD.K=TEST4

A TBEXPD.K =PMCB.K*BPM.K + MNRCB.K*BMNR.K + MJRCB.K*BMJR.K + BWC.k** BW.KL+RPCB.k*RPRB.KL+RHCB.K*RHRB.KL

* TBEXPD - TOTAL BRIDGE EXPENDITURE ($/YR) A BPM.K=FAPMB.KL+FIPMB.KL * BPM - NO. OF BRIDGES PREVENTIVELY MAINTAINED (BRIDGES/YR) A BMNR.K=FIMNRB.KL+FAMNRB.KL * BMNR - NO. OF BRIDGES MINOR REPAIRED (BRIDGES/YR) A BMJR.K=FIMJRB.KL+FAMJRB.KL * BMJR - NO. OF BRIDGES MAJOR REPAIRED (BRIDGES/YR) L BLCCD.K =BLCCD.]+(DT)(TBED.JK) * BLCCD - BRIDGE LIFE CYCLE COST DISCOUNTED ($) N BLCCD=0 R TBED.KL=(INFLF.K*TBEXPD.K)/(1 + DISR)**TIME.K * TBED - TOTLA BRIDGE EXPENDITURE DISCOUNTED ($/YR) A INFLF.K=(INFLR+1)**TIME.K * INFLF - INFLATION FACTOR (DIM) C INFLR=0.0 * INFLR - INFLATION RATE (DIM) C DISR=0.06 * DISR - DISCOUNT RATE (DIM) L BLCCUD.K =BLCCUD.]+(DT)(TBEUD. JK) * BLCCUD - BRIDGE LIFE CYCLE COST UNDISCOUNTED ($) N BLCCUD=0 R TBEUD.KL=(INFLF.K*TBEXPD.K) * TBEUD - TOTLA BRIDGE EXPENDITURE UNDISCOUNTED ($/YR) A THCE.K=ERH.KL*ECH.K * THCE - TOTAL HWY CONSTRUCTION EXPENDITURE ($/YR) A THME.K = MRDFH.KL*MCDFH.K+ MRDTH.KL*MCDTH.K

210

* THME - TOTAL HWY MAINTENANCE EXPENDITURE ($/YR) L HLCCUD.K=HLCCUD.]+(DT)(THEUD. JK) * HLCCUD - HWY LIFE CYCLE COST UNDISOUNTED N HLCCUD=0 R THEUD.KL=INFLF.K*(THCE.K+THME.K) * THEUD - TOTAL HWY EXPENDITURE UNDISCOUNTED ($/YR) L HLCCD.K=HLCCD.] + (DT)(THED.JK) * HLCCD - HWY LIFE CYCLE COST DISOUNTED N HLCCD=0 R THED.KL=(INFLF.K*{THCE.K + THME.K))/(1+ DISR)**TIME.K * THED - TOTAL HWY EXPENDITURE DISCOUNTED ($/YR)

Physical Subsystem: Bridge Management System

* C FBFAPMB=0.5

NOTE FBFANRB - Fract Budget to Func Adequate Preventive Maintenance of Bridges (Dim) A FBFANRB.K=(1-FBFAPMB)/3 NOTE FBFANRB.- Fract Budget to Func Adequate Minor Repairs of Bridges (Dim) A FBFAJRB.K =(1-FBEFAPMB)/3 NOTE FBFAJRB - Fract Budget to Func Adequate Major Repairs ot Bridges (Dim) c FBBW =0.0 NOTE FBBW - Fract Budget to Bridge Widening (Dim) a FBRHB.k=(1-FBFAPMB)/3 NOTE FBRHB - Fract Budget to Rehabilitation of Bridges (Dim) C FBFIPMB=0.0 NOTE FBFIPMB - Fract Budget to Func Inadequate Preventive Maintenance of Bridges (Dim) C FBFINRB=0.0 NOTE FBFINRB - Fract Budget to Func Inadequate Minor Repair of Bridges (Dim) C FBFIJRB=0.0 NOTE FBFIJRB -Fract Budget to Func Inadequate Major Repair of Bridges (Dim) C FBRPB=0.0 NOTE FBRPB - Fract Budget to Replacement ot Bridges (Dim) A ABFAPFC.K=MAX(BFAPFC.K,0) A ABFAGC.K=MAX(BFAGC.K.0)

A ABFAFC.K=MAX(BFAFC.K,0) A ABFAPC.K=MAX(BFAPC.K,0) A ABFIPFC.K =MAX(BFIPFC.K,0) A ABFIGC.K=MAX(BFIGC.K,0)

A ABFIFC.K=MAX(BFIFC.K,0) A ABFIPC.K=MAX(BFIPC.K,0) A ABFACC.K=MAX(BFACC.K.0) A ABFICC.K =MAX(BFICC.K,0) L BFAPFC.K=BFAPFC,] + (DT)(FAPMB.JK + FAMNRB.JK + FAMJRB.JK +*

RHRB.JK +RPRB.JK + BW.JK-ORB.JK-FAERB.]K) N BFAPFC=BFAPFCN C BFAPFCN=31 : NOTE FASC - Bridges in Functionally Adequate Superior Condition (Bridges) R FAERB.KL = max(BFAPFC.K/ETB,0) NOTE FAER - Functionally Adequate Exposure Rate of Bridges (Bridges/YR) C ETB=1.5

211

NOTE ET - Exposure Time of the Bridges (YR) R FAPMB.KL=FAPMBB.K/PMCB.K NOTE FAPMB-Functionallvy Adequate Preventive Maintenance of Bridges (Bridges/YR) A FAPMBB.K = BB.K*FBFAPMB NOTE FAPMBB - Functionally Adequate Preventive Maintenance Budget of Bridges ($/YR) L BFAGC.K=BFAGC._] + (DT)(FAERB.JK-FAPMB.JK-FADRB.JK) N BFAGC =BFAGCN C BFAGCN =87 NOTE FAGC - Bridges in Functionally Adequate Good Condition (Bridges) R FADRB.KL=max(BFAGC.K/DTTB,0) NOTE FADRB.- Functionally Adequate Deterioration Rate of Bridges (Bridges/YR) C DTTB=15 NOTE DTT - Deterioration Time of Bridges (YR) R FAMNRB.KL=FAMNRBB.k/MNRCB.K NOTE FAMNR - Functionally Adequate Minor Repair Budget of Bridges ($/YR) A FAMNRBB.K = BB.K*FBFANRB.K NOTE FAMNRBB - Functionally Adequete Minor Repair Budget of Bridges ($/YR) L BFAFC.K=BFAFC.]+(DT)(FADRB.JK-FAMNRB.JK-FAADRB.JK) N BFAFC=BFAFCN

C BFAFCN=49 R FAADRB.KL=max(BFAFC.K/ADTB,0)

C ADTB=15 R FAMJRB.KL=FAMJRBB.K/MJRCB.K A FAMJRBB.K=BB.K*FBFAJRB.K L BFAPC.K =BFAPC.J+(DT)(FAADRB JK-FAMJRB.JK-FASDRB.JK) N BFAPC=BFAPCN C BFAPCN =27 R FASDRB.KL=max(BFAPC.K/SDTB,0) C SDTB=26 R RHRB.KL=RHBB.K/RHCB.K A RHBB.K=BB.K*FBRHB.k R ORB.KL=max(BFAPFC.K/OTB,0) C OTB=50 R BW.KL=BWB.K/BWC.k

A BWB.K=BB.K*FBBW L BFIPFC.K = BFIPFC.] + (DT)(FIPMB.JK + FIMNRB. JK + FIMJRB.JK +*

ORB.JK-BW.JK*-FIERB.JK) N BFIPFC=BFIPFCN C BFIPFCN=1 R FIERB.KL=max(BFIPFC.K/ETB,0) R FIPMB.KL=FIPMBB.K/PMCB.K

A FIPMBB.K =BB.K*FBFIPMB L BFIGC.K = BFIGC.J+ (DT)(FIERB.JK-FIPMB. JK-FIDRB.JK) N BFIGC =BFIGCN C BFIGCN =9 R FIDRB.KL= max(BFIGC.K/DTTB,0) R FIMNRB.KL=FIMNRBB.K/MNRCB.K A FIMNRBB.K = BB.K*FBFINRB L BFIFC.K = BFIFC.J+(DT)(FIDRB.JK-FIMNRB,JK-FIADRB.JK) N BFIFC=BFIFCN C BFIFCN =10

212

R FIADRB.KL=max(BFIFC.K/ADTB,0) R FIMJRB.KL=FIMJRBB.K/MJRCB.K A FIMJRBB.K =BB.K*FBFIJRB L BFIPC.K =BFIPC.J+(DT)(FIADRB.JK-FIMJRB.JK-FISDRB.]K) N BFIPC=BFIPCN C BFIPCN=16 R FISDRB.KL=max(BFIPC.K/SDTB,0) R RPRB.KL=RPBB.K/RPCB.k A RPBB.K =BB.K*FBRPB L BFACC.K = BFACC.] + (DT)(FASDRB.JK-RHRB.JK) N BEACC=BFACCN C BFACCN=0 L BFICC.K=BFICC.] + (DT)(FISDRB.JK-RPRB.]K) N BFICC=BFICCN C BFICCN=0 A TBFAC.K=BFAPFC.K + BEFAGC.K + BFAFC.K+ BFAPC.K N TBFACN=BFAPFCN+BFAGCN + BFAFCN + BFAPCN+BFACCN A TBFIC.K = BFIPFC.K + BFIGC.K + BFIFC.K + BFIPC.K + BCC.K N TBFICN = BFIPFCN + BFIGCN + BFIFCN + BFIPCN + BFICCN A BFALK =(TBFAC.K*WFFAB+ TBFIC.K*WFFIB)/(TBFAC.K + TBFIC.K) N BFAIN=(TBFACN*WEFFAB+ TBFICN*WFEIB)/(TBFACN + TBFICN) A BPFC.K = ABFIPFC.K + ABFAPFC.K A BGC.K=ABFIGC.K+ ABFAGC.K A BFC.K=ABFIFC.K + ABFAFC.K A BPC.K=ABFIPC.K+ ABFAPC.K A BCC.K = ABFICC.K + ABFACC.K A BPALK=(BPFC.K*WFPFB + BGC.K*WFGB+ BFC.K*WFFB+ BPC.K*

WEPB+BCC.K*WECB)/(BPFC.K + BGC.K+ BFC.K + BPC.K + BCC.K) N BPFCN=BFIPFCN+BFAPFCN N BGCN = BFIGCN + BFAGCN N BFCN=BFIFCN + BFAFCN N BPCN=BFIPCN+BFAPCN N BCCN=BFICCN+BFACCN N BPAIN=(BPFCN*WEPFB+BGCN*WFGB+BFCN*W/FFB + BPCN*

WFPB+BCCN*WECB)/(BPFCN + BGCN + BECN + BPCN + BCCN) C WFFAB=1 C WFFIB=0.5 C WFPFB=1 C WFGB=1 C WFFB=0.9 C WFPB=0.7 C WFCB=0.4

213

Physical Subsystem: Pavement Management System

C FBFAPMB=0.5 C FBOMH=0.5 A FBMRH.K = 1-FBOMH A AHSFPC.K=MAX(HSFPC.K,0) A AHDFPC.K=MAX(HDFPC.K,0) A AHDTPC.K=MAX(HDTPC.K,0) L HSFPC.K = HSFPC.]+(DT)(MRDTH.JK + ERH JK + MRDFH.JK-ARH.JK) N HSFPC=HSFPCN C HSFPCN = 149.36 * HSFPC-HIGHWAY IN SUFFICIENT PAVEMENT CONDITION (LANE-MI) R MRDFH.KL=HMB.K*FBOMH/MCDFH.K * MRDFH-ORDINARY MAINTEANACE RATE OF HIGHWAY (LANE-MI/YR) R MRDTH.KL=HMB.K*FBMRH.K/MCDTH.K * MRDTH-MAINTENANCE REPLACEMENT RATE OF HIGHWAY (LANE-MI/YR) R ARH.KL=HSFPC.K/ATH * ARH-AGING RATE OF HIGHWAY (LANE-MI/YR) C ATH=1 * ATH-AGING TIME OF HIGHWAY (YR) L HDFPC.K =HDFPC.]+(DT)(ARH.JK-MRDFH JK-DRH JK) N HDFPC =HDFPCN C HDFPCN = 127.39 *HDFPC-HIGHWAY IN DEFICIENT PAVEMENT CONDITION (LANE-MI) L HDTPC.K=HDTPC.J+(DT)(DRH.JK-MRDTH JK) N HDTPC=HDTPCN C HDTPCN = 208.38 * HDTPC-HIGHWAY IN DETERIORATED PAVEMENT CONDITION (LANE-MI) R DRH.KL=HDFPC.K/DTH * DRH-DETERIORATING RATE OF HIGHWAY (LANE-MI/YR) C DTH=4.2 * DHT-DETERIORATING TIME OF HIGHWAY (YR) A HDRM.K=(MRDFH.KL+MRDTH.KL)/(HSFPC.K + HDFPC.K+HDTPC.K) * HDRM-HIGHWAY DOWN RATIO FOR MAINTENANCE (DIM) A HPALK=(HSFPC.K+ HDFPC.K*WFDFCH + HDTPC.K*WFDTCH)* /(HSFPC.K +HDFPC.K + HDTPC.K)

* HPAI - HIGHWAY PHYSICAL ADEQUACY INDEX (DIM) C WEDFCH=0.5 * WFDFCH-WEIGHTING FACTOR FOR DEFICIENT CONDITION OF HIGHWAY (DIM) C WFDTCH=0 * WFDTCH-WEIGHTING FACTOR FOR DETERIORATED CONDITION OF HIGHWAY (DIM)

oh ob oh af 2b ab ab 9b 2b ab of ah ob ab af 26 ab of ah ab

* Expansion Rate tor * * Adding lane on I-81 * 3G BG a Ob Sh 96 2G 9b 9b Be 2h of Ob 26 9b OG ab 9f Be oh

R ERH.KL=CLIP(0,((86.87)*2)/5, TIME.K,5) * ERH-EXPANSION RATE OF HIGHWAY (LANE-MI/YR)

A TMH.K=HSFPC.K+HDFPC.K+HDTPC.K

* TMH - TOTAL LANE MILEAGE OF HIGHWAY (LANE-MI)

214

APPENDIX E: MIS SOFTWARE

215

VITA

Steve Smayda was born September 1, 1965 in Bad Constatt, Stuttgart, Germany. He

graduated from Park View High School in Sterling, Virginia in June 1983. In January

1984 he enlisted into the Marines Corps Reserve, earning the title of U. S. Marine in

August of that same year. He graduated with a Bachelors of Science Degree in

Psychology in July 1988 from Virginia Tech and was subsequently commissioned a

Second Lieutenant of Marines. He has served as a Naval Aviator as a Light Attack

pilot as well as a Combat Engineering Officer specializing in demolitions. He

returned to school in 1992, completing the majority of a Bachelors of Science Degree

in Civil Engineering at Virginia Tech prior to entering the Masters program. He is

currently a Captain of Marines with the Reserves and will be working for Kiewit

Construction upon graduation.

He is an active member of several professional organizations to include the American

Society of Civil Engineers, the Society of American Military Engineers, and the

Marine Corps Reserve Officers Association. He is married to his wife, Liza, of three

years and has a six-month-old son, Connor.

216