24 Road (Lake Cushman) Reconstruction Project
Interagency partnership and funding
Funding
• Total project funds available:
~ $4.6 million
• Funding sources: • Federal Lands Transportation
Program • Tacoma Power • US Forest Service • National Park Service
24 Road (Lake Cushman)
Project goals:
• Meet FERC requirements • Permanent dust abatement • Improved road surface • Reduced traffic congestion • Safety features • Improve Olympic NP utility
infrastructure
Project scope
It’s happening…!
•February 2020: Engineering design finalized
~ Contract and award ~
•Summer 2020 (July – Sept): Road closure / construction
Date: May 2019 Subject: Utility Installation ONP
Separate phase, pending future funding: Bear Gulch
(Storm Damage – 2017)