2017 treeo - approval and type ii assemblies and type ii detector assemblies paul h. schwartz, usc...

17
Approval and Type II Detector Assemblies Paul H. Schwartz, USC FCCCHR UF TREEO Conference 1516 February 2017 1 Paul H. Schwartz, P.E. Chief Engineer USC Approval and Type II Detector Assemblies What’s New at USC What’s New at USC? One-day s eminars / webinars What’s “Old News” at USC? What’s “Old ” at UF TREEO? The USC Foundation Approval Program

Upload: vanque

Post on 27-May-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 1

Paul H. Schwartz, P.E.Chief Engineer

USC Approval and Type II Detector Assemblies

What’s New at USC

What’s New at USC?

• One-day seminars / webinars

What’s “Old News” at USC?

What’s “Old ” at UF TREEO?

The USC FoundationApproval Program

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 2

What Does Approval Mean?

• Product complies with performancebased standard

- Standard defines what a product is supposed to do

- Standard defines a procedure for testing or evaluating

- Standard defines cause for failure or rejection

Approval Program• Not a rating system

• Product meets minimum standard

Standard

Approval Program• USC - Two Part Process

- Laboratory Evaluation

- Field Evaluation

Approval ProgramLaboratory

• All testing conducted by trained USC Staff at USC Foundation Laboratory

- Third party laboratories not used

• Manufacturers may witness, but not participate in the testing

Approval ProgramLaboratory

• Submission of Working Drawings

• Hydrostatic

• Pressure (Head) Loss vs. Flow Rate

• Elastomer / Spring Documentation

• Backsiphonage and Backpressure Test

• Thermal Loop

• Cycle test

Approval ProgramLaboratory

• Submission of Working Drawings

- Design Requirements

- Material Requirements

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 3

Approval ProgramLaboratory

• Submission of Working Drawings

- Failure to comply with Design Requirements

Approval ProgramLaboratory

• Submission of Working Drawings

- Failure to comply with Design Requirements

Approval ProgramLaboratory

• Submission of Working Drawings

- Failure to comply with Material Requirements

Approval ProgramLaboratory

• Hydrostatic Tests – Structural Integrity

- Twice (2X) maximum rated working water pressure (MWWP) – 10 min

- Failure criteria

• Leakage

• Damage

• Permanent deformation

2 x MWWP; typically 2 x 175psi = 350 psi

Approval ProgramLaboratory

Approval ProgramLaboratory

- Body leak or rupture

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 4

Approval ProgramLaboratory

Backpressure each check valve

Approval ProgramLaboratory

Backpressure each check valve

Approval ProgramLaboratory

• Dislodged parts that leak

Approval ProgramLaboratory

• Broken parts that leak

New Part-- Flat --

Tested Part-- Bent --

• Permanent deformation / damage

Approval ProgramLaboratory

Approval ProgramLaboratory

• Pressure (Head) Loss vs. Flow Rate

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 5

P r essu r e L o ssInlet Outlet

Approval ProgramLaboratory

• Pressure Loss vs Flow Rate Protocol

- NOT only a single point

• At rated flow

Approval ProgramLaboratory

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 6

Approval ProgramLaboratory

Approval ProgramLaboratory

(200%)

Approval ProgramLaboratory

Approval ProgramLaboratory

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 7

Approval ProgramLaboratory

• Elastomer Documentation

- Durometer (hardness)

• 9th Edition Std.

- Check: 35-45 Shore A

- RV: 55-65 Shore A

Approval ProgramLaboratory

• Elastomer Specifications

- Durometer (hardness)

• 10th Edition Std.

- No restrictions

BackpressureVacuum

Approval ProgramLaboratory

RP – Backsiphonage / Backpressure Test

• Vertical up (VU) orientation

Approval ProgramLaboratory

Thermal Loop

• Thermal Loop Performance Test- Assembly must function at rated Temperature (MWWT)

and Pressure (MWWP) for 100 hours- Maximum Rated Working Temperature

• Minimum of 140o F - Based upon real-world field measurements

- Maximum Rated Working Pressure• Typically 175 psi

Approval ProgramLaboratory

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 8

Approval ProgramLaboratory

Approval ProgramLaboratory

Cycle test

• Cycle Test includes 5,000 cycles:

- Various flow rates

• 25%, 50%, 75%, 100% of rated flow

- Depressurize upstream

- Apply backpressure

Approval ProgramLaboratory

• Cycle Test Criteria

- Damage vs Performance

Approval ProgramLaboratory

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 9

Approval ProgramLaboratory

• Failure to comply with any laboratory test is cause for failure

• Damage or permanent deformationto the assembly is cause for failure

Approval ProgramLaboratory

• Over 50% of the assemblies which were listed by other listing agencies and submitted to USC from 2009 to 2012 failed the USC Foundation Laboratory evaluation initially

• USC – FCCCHR

- No Laboratory Approval

- Released to Field Evaluation

• Only Listing/Approval Agency that requires successful completion of a Field Evaluation

Approval ProgramLaboratory

• USC – FCCCHR

- Staff may not release evaluation status updates to public

- Official contact list

• Provided by each Manufacturer

Approval ProgramLaboratory

Approval ProgramField

Field Evaluation

• Manufacturer responsible for finding field sites

- Anywhere in North America

• DO YOU HAVE POTENTIAL FIELD TEST SITES?

- Generally installed within 500 mile radius of L.A.

• Manufacturer is encouraged to locate field test sites

as Laboratory Evaluation is being conducted

Approval ProgramField

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 10

• Field Site Criteria

- Non hazardous location

- Accessible

- Acceptable to administrative authorities and owner

- Variety of applications

- Different pressures

- High flowing site (50%-100% of rated flow)

Approval ProgramField

• Field Evaluation “clock” starts once three (3) assemblies have been initial field tested.

• Manufacturer may install more than 3

• Foundation Staff conducts all field tests

• Requires twelve (12) consecutive months of simultaneous trouble-free service

Approval ProgramField

Approval ProgramField

• Twelve (12) Months Trouble-free Service

- Three sites for each make, model, size, and orientation

• Initial field test and inspection

• Monthly field tests

• Final field test and inspection

Approval ProgramField

• Failure to pass field test is cause for rejection

- However, Dirt / Debris not cause for failure

Approval ProgramField

• Design or material failure is cause for rejection- Manufacturer immediately notified

• Field Evaluation Stopped- Redesign / Modify- Resubmit for Laboratory Evaluation- Change out Assemblies / components

• Restart Field Evaluation “clock” at zero

Approval ProgramField

• Approximately 30% of the assemblies passing the USC laboratory evaluation do not pass the field evaluation the first time

• Of those that fail the field evaluation, approximately 70% fail in the last three months

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 11

The USC FoundationUSC Approval

USC Approval

• USC List of Approved Backflow Prevention Assemblies

USC List on Mobile Devicesusclist.com

Approval of Backflow Preventers

• Performance Standards- Double Check Valve Assemblies (DC)- Reduced Pressure Principle

Assemblies (RP)- Vacuum Breakers

• PVB, SVB, AVB- Detector Assemblies

• DCDA, DCDA-II• RPDA, RPDA-II

Approval of Backflow Preventers

• Performance Standards- Double Check Valve Assemblies (DC)- Reduced Pressure Principle

Assemblies (RP)- Vacuum Breakers

• PVB, SVB, AVB- Detector Assemblies

• DCDA, DCDA-II• RPDA, RPDA-II

Fire Sprinkler Systems

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 12

Fire Sprinkler Systems

• Manual – 10th Edition- Non-potable water piping- Fire department connection- Auxiliary water systems- Additives

AWWA Manual M-14

AwwaRF Study ~1998

• Impact of Wet-Pipe Fire Sprinkler Systems on Drinking Water Quality

- Wet based fire sprinkler systems

• Primarily exceed secondary water quality standards

Fire Sprinkler Systems

• Detector Assemblies- Prevent backflow and detect

unauthorized use of water• DCDA• DCDA-II• RPDA• RPDA-II

QUIZ QUESTIONIn which Edition of the USC Manual was the new Standard added for Double Check Detector Assemblies (DCDA)?

A. 4th Edition - 1969B. 6th Edition – 1979C. 8th Edition – 1988D. 9th Edition – 1993E. 10th Edition - 2009

Standards

QUIZ QUESTIONIn which Edition of the USC Manual was the new Standard added for Double Check Detector Assemblies (DCDA)?

A. 4th Edition - 1969B. 6th Edition – 1979C. 8th Edition – 1988D. 9th Edition – 1993E. 10th Edition - 2009

Standards

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 13

“Detector” Assemblies

Unauthorized use?

“Detector” Assemblies

Which way to go?

“Detector” Assemblies

Path of less resistance

2.5 psid 2.5 psid

5.0 psid

“Detector” Assemblies

Path of less resistance

2.5 psid 2.5 psid

5.0 psid

First 3 gpm

“Detector” Assemblies

Path of less resistance

1.5 psid 3.5 psid

5.0 psid

“Detector” Assemblies

1.2 psid 4.5 psid

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 14

DCDA – Main Line Assembly

• Sometimes “standard” DC springs

• Sometimes two “stronger” springs

• Sometimes one “stronger” spring

- 1st Check Valve, or

- 2nd Check Valve

USC Manual – 10th Edition MRC

• Chapter 10 – DCDA / RPDA- BPMA requested lowering of bypass flow

• 3 gpm to 2 gpm- BPMA requested new concept

• Bypass only one mainline check valve

• Goal? Lower overall pressure loss

USC Manual – 10th Edition Standard

• Chapter 10 – DCDA / RPDA- Reduced bypass flow from 3 gpm to

2 gpm

- New DCDA-II and RPDA-II- Only bypasses one mainline check

valve

“Detector” Assemblies

Path of less resistance

First 2 GPMinstead of

3 GPM

Manual - 10th Edition

• Chapter 10 - New AssembliesType II Detectors Assemblies -DCDA-II /RPDA-II

Type II Detector

1.2 psid 2.5 psid

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 15

Type II Detector

• Bypass Assembly– Basically a double

check valve without a second check valve.

– SOV’s– TC’s

• NOT A SEPARATELY APPROVED ASSEMBLY

Manual - 10th Edition

• Chapter 10 - DCDA vs DCDA-II- Detect low flows – unauthorized use- Flow through path of least resistance

Manual - 10th Edition

• Lower overall pressure loss

Field Testing – Field Test Form

• DCDA-II / RPDA-II- How are these assemblies reported?

• Two forms?• Modify existing forms?

- Add new “box” for bypass check valve

Field Testing – Field Test Form(s)

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 16

Field Testing – Field Test Form(s) Field Testing – Field Test Form(s)

Field Testing – Field Test Form Field Testing – Field Test Form

Contact Information

• Email – [email protected]

• Toll Free – 866.545.6340

• Web – fccchr.usc.edu

Social Media

• @uscfccchr

• facebook.com/uscfccchr

• youtube.com/uscfccchr

Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR

UF TREEO Conference15‐16 February 2017 17

Questions?