2017 treeo - approval and type ii assemblies and type ii detector assemblies paul h. schwartz, usc...
TRANSCRIPT
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 1
Paul H. Schwartz, P.E.Chief Engineer
USC Approval and Type II Detector Assemblies
What’s New at USC
What’s New at USC?
• One-day seminars / webinars
What’s “Old News” at USC?
What’s “Old ” at UF TREEO?
The USC FoundationApproval Program
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 2
What Does Approval Mean?
• Product complies with performancebased standard
- Standard defines what a product is supposed to do
- Standard defines a procedure for testing or evaluating
- Standard defines cause for failure or rejection
Approval Program• Not a rating system
• Product meets minimum standard
Standard
Approval Program• USC - Two Part Process
- Laboratory Evaluation
- Field Evaluation
Approval ProgramLaboratory
• All testing conducted by trained USC Staff at USC Foundation Laboratory
- Third party laboratories not used
• Manufacturers may witness, but not participate in the testing
Approval ProgramLaboratory
• Submission of Working Drawings
• Hydrostatic
• Pressure (Head) Loss vs. Flow Rate
• Elastomer / Spring Documentation
• Backsiphonage and Backpressure Test
• Thermal Loop
• Cycle test
Approval ProgramLaboratory
• Submission of Working Drawings
- Design Requirements
- Material Requirements
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 3
Approval ProgramLaboratory
• Submission of Working Drawings
- Failure to comply with Design Requirements
Approval ProgramLaboratory
• Submission of Working Drawings
- Failure to comply with Design Requirements
Approval ProgramLaboratory
• Submission of Working Drawings
- Failure to comply with Material Requirements
Approval ProgramLaboratory
• Hydrostatic Tests – Structural Integrity
- Twice (2X) maximum rated working water pressure (MWWP) – 10 min
- Failure criteria
• Leakage
• Damage
• Permanent deformation
2 x MWWP; typically 2 x 175psi = 350 psi
Approval ProgramLaboratory
Approval ProgramLaboratory
- Body leak or rupture
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 4
Approval ProgramLaboratory
Backpressure each check valve
Approval ProgramLaboratory
Backpressure each check valve
Approval ProgramLaboratory
• Dislodged parts that leak
Approval ProgramLaboratory
• Broken parts that leak
New Part-- Flat --
Tested Part-- Bent --
• Permanent deformation / damage
Approval ProgramLaboratory
Approval ProgramLaboratory
• Pressure (Head) Loss vs. Flow Rate
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 5
P r essu r e L o ssInlet Outlet
Approval ProgramLaboratory
• Pressure Loss vs Flow Rate Protocol
- NOT only a single point
• At rated flow
Approval ProgramLaboratory
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 6
Approval ProgramLaboratory
Approval ProgramLaboratory
(200%)
Approval ProgramLaboratory
Approval ProgramLaboratory
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 7
Approval ProgramLaboratory
• Elastomer Documentation
- Durometer (hardness)
• 9th Edition Std.
- Check: 35-45 Shore A
- RV: 55-65 Shore A
Approval ProgramLaboratory
• Elastomer Specifications
- Durometer (hardness)
• 10th Edition Std.
- No restrictions
BackpressureVacuum
Approval ProgramLaboratory
RP – Backsiphonage / Backpressure Test
• Vertical up (VU) orientation
Approval ProgramLaboratory
Thermal Loop
• Thermal Loop Performance Test- Assembly must function at rated Temperature (MWWT)
and Pressure (MWWP) for 100 hours- Maximum Rated Working Temperature
• Minimum of 140o F - Based upon real-world field measurements
- Maximum Rated Working Pressure• Typically 175 psi
Approval ProgramLaboratory
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 8
Approval ProgramLaboratory
Approval ProgramLaboratory
Cycle test
• Cycle Test includes 5,000 cycles:
- Various flow rates
• 25%, 50%, 75%, 100% of rated flow
- Depressurize upstream
- Apply backpressure
Approval ProgramLaboratory
• Cycle Test Criteria
- Damage vs Performance
Approval ProgramLaboratory
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 9
Approval ProgramLaboratory
• Failure to comply with any laboratory test is cause for failure
• Damage or permanent deformationto the assembly is cause for failure
Approval ProgramLaboratory
• Over 50% of the assemblies which were listed by other listing agencies and submitted to USC from 2009 to 2012 failed the USC Foundation Laboratory evaluation initially
• USC – FCCCHR
- No Laboratory Approval
- Released to Field Evaluation
• Only Listing/Approval Agency that requires successful completion of a Field Evaluation
Approval ProgramLaboratory
• USC – FCCCHR
- Staff may not release evaluation status updates to public
- Official contact list
• Provided by each Manufacturer
Approval ProgramLaboratory
Approval ProgramField
Field Evaluation
• Manufacturer responsible for finding field sites
- Anywhere in North America
• DO YOU HAVE POTENTIAL FIELD TEST SITES?
- Generally installed within 500 mile radius of L.A.
• Manufacturer is encouraged to locate field test sites
as Laboratory Evaluation is being conducted
Approval ProgramField
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 10
• Field Site Criteria
- Non hazardous location
- Accessible
- Acceptable to administrative authorities and owner
- Variety of applications
- Different pressures
- High flowing site (50%-100% of rated flow)
Approval ProgramField
• Field Evaluation “clock” starts once three (3) assemblies have been initial field tested.
• Manufacturer may install more than 3
• Foundation Staff conducts all field tests
• Requires twelve (12) consecutive months of simultaneous trouble-free service
Approval ProgramField
Approval ProgramField
• Twelve (12) Months Trouble-free Service
- Three sites for each make, model, size, and orientation
• Initial field test and inspection
• Monthly field tests
• Final field test and inspection
Approval ProgramField
• Failure to pass field test is cause for rejection
- However, Dirt / Debris not cause for failure
Approval ProgramField
• Design or material failure is cause for rejection- Manufacturer immediately notified
• Field Evaluation Stopped- Redesign / Modify- Resubmit for Laboratory Evaluation- Change out Assemblies / components
• Restart Field Evaluation “clock” at zero
Approval ProgramField
• Approximately 30% of the assemblies passing the USC laboratory evaluation do not pass the field evaluation the first time
• Of those that fail the field evaluation, approximately 70% fail in the last three months
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 11
The USC FoundationUSC Approval
USC Approval
• USC List of Approved Backflow Prevention Assemblies
USC List on Mobile Devicesusclist.com
Approval of Backflow Preventers
• Performance Standards- Double Check Valve Assemblies (DC)- Reduced Pressure Principle
Assemblies (RP)- Vacuum Breakers
• PVB, SVB, AVB- Detector Assemblies
• DCDA, DCDA-II• RPDA, RPDA-II
Approval of Backflow Preventers
• Performance Standards- Double Check Valve Assemblies (DC)- Reduced Pressure Principle
Assemblies (RP)- Vacuum Breakers
• PVB, SVB, AVB- Detector Assemblies
• DCDA, DCDA-II• RPDA, RPDA-II
Fire Sprinkler Systems
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 12
Fire Sprinkler Systems
• Manual – 10th Edition- Non-potable water piping- Fire department connection- Auxiliary water systems- Additives
AWWA Manual M-14
AwwaRF Study ~1998
• Impact of Wet-Pipe Fire Sprinkler Systems on Drinking Water Quality
- Wet based fire sprinkler systems
• Primarily exceed secondary water quality standards
Fire Sprinkler Systems
• Detector Assemblies- Prevent backflow and detect
unauthorized use of water• DCDA• DCDA-II• RPDA• RPDA-II
QUIZ QUESTIONIn which Edition of the USC Manual was the new Standard added for Double Check Detector Assemblies (DCDA)?
A. 4th Edition - 1969B. 6th Edition – 1979C. 8th Edition – 1988D. 9th Edition – 1993E. 10th Edition - 2009
Standards
QUIZ QUESTIONIn which Edition of the USC Manual was the new Standard added for Double Check Detector Assemblies (DCDA)?
A. 4th Edition - 1969B. 6th Edition – 1979C. 8th Edition – 1988D. 9th Edition – 1993E. 10th Edition - 2009
Standards
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 13
“Detector” Assemblies
Unauthorized use?
“Detector” Assemblies
Which way to go?
“Detector” Assemblies
Path of less resistance
2.5 psid 2.5 psid
5.0 psid
“Detector” Assemblies
Path of less resistance
2.5 psid 2.5 psid
5.0 psid
First 3 gpm
“Detector” Assemblies
Path of less resistance
1.5 psid 3.5 psid
5.0 psid
“Detector” Assemblies
1.2 psid 4.5 psid
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 14
DCDA – Main Line Assembly
• Sometimes “standard” DC springs
• Sometimes two “stronger” springs
• Sometimes one “stronger” spring
- 1st Check Valve, or
- 2nd Check Valve
USC Manual – 10th Edition MRC
• Chapter 10 – DCDA / RPDA- BPMA requested lowering of bypass flow
• 3 gpm to 2 gpm- BPMA requested new concept
• Bypass only one mainline check valve
• Goal? Lower overall pressure loss
USC Manual – 10th Edition Standard
• Chapter 10 – DCDA / RPDA- Reduced bypass flow from 3 gpm to
2 gpm
- New DCDA-II and RPDA-II- Only bypasses one mainline check
valve
“Detector” Assemblies
Path of less resistance
First 2 GPMinstead of
3 GPM
Manual - 10th Edition
• Chapter 10 - New AssembliesType II Detectors Assemblies -DCDA-II /RPDA-II
Type II Detector
1.2 psid 2.5 psid
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 15
Type II Detector
• Bypass Assembly– Basically a double
check valve without a second check valve.
– SOV’s– TC’s
• NOT A SEPARATELY APPROVED ASSEMBLY
Manual - 10th Edition
• Chapter 10 - DCDA vs DCDA-II- Detect low flows – unauthorized use- Flow through path of least resistance
Manual - 10th Edition
• Lower overall pressure loss
Field Testing – Field Test Form
• DCDA-II / RPDA-II- How are these assemblies reported?
• Two forms?• Modify existing forms?
- Add new “box” for bypass check valve
Field Testing – Field Test Form(s)
Approval and Type II Detector AssembliesPaul H. Schwartz, USC FCCCHR
UF TREEO Conference15‐16 February 2017 16
Field Testing – Field Test Form(s) Field Testing – Field Test Form(s)
Field Testing – Field Test Form Field Testing – Field Test Form
Contact Information
• Email – [email protected]
• Toll Free – 866.545.6340
• Web – fccchr.usc.edu
Social Media
• @uscfccchr
• facebook.com/uscfccchr
• youtube.com/uscfccchr