Page 1: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 1ISO Public

2017 Budget and Grid Management ChargeInitial Stakeholder Meeting

June 16, 2016

Page 2: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 2ISO Public

Agenda

Topic Presenter(s)

2017 Budget Process & GMC Rate Outlook Ryan Seghesio &April Gordon

Managing Employee Compensation Doreen Fender

2016 - 2017 Project Release Plans Janet Morris

2015 & 2016 Project Summaries Jan Cogdill

2015 & Q1 2016 Financial Summaries Denise Walsh

2017 Budget Calendar & Next Steps April Gordon

Stakeholder Feedback & Discussion Group

Page 3: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 3ISO Public

Budget Process and Rate Outlook

Ryan SeghesioCFO and Treasurer

April GordonManager, Financial Planning and Procurement

Page 4: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 4ISO Public

Budget Principles and Highlights

• Principles:

– Provide transparency into the budget process

– Enhance stakeholder understanding of the budget

– Deliver a revenue requirement under the $202 million cap

• Highlights:

– Consider the cost internal campaign

– Lincoln backup site

– EIM revenue

Page 5: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 5ISO Public

Annual Revenue Requirement projected to remain under $202M cap.

$100

$120

$140

$160

$180

$200

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019O&M All Other Components

ProjectedActualMillions

Page 6: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 6ISO Public

Grid management charge rates remain stable.

$0.0850

$0.2979

$0.0049$0.00

$0.05

$0.10

$0.15

$0.20

$0.25

$0.30

$0.35

2012 2013 2014 2015 2016

Market Service Charge Systems Operations Charge CRR Services Charge

Page 7: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 7ISO Public

Managing Employee Compensation

Doreen FenderManager, Total Rewards

Page 8: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 8ISO Public

Managing employee compensation reflects ISO philosophy to attract, train, motivate and retain top talent.

• Competitive Pay – Market pay practices– Bi-annual salary surveys covering 100% of ISO positions

• Pay for Performance Philosophy– High Performance Goals aligned to meet annual Corporate objectives– Year-end evaluation of performance results against objectives– Differentiation of merit dollars based on performance

• Strong Performance Management Program– Individual performance plans– Stretch objectives– Ongoing feedback, coaching and support

• 3% Budgeted Merit – Optimal utilization of available merit dollars– Not all employees receive pay increases

Page 9: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 9ISO Public

2016 - 2017 Project Release Plans

Janet MorrisDirector, Program Office

Page 10: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 10ISO Public

Release planning information is updated and discussed regularly throughout the year.

Release planning page: http://www.caiso.com/informed/Pages/ReleasePlanning/Default.aspx

• Stakeholder Initiative Milestones

– http://www.caiso.com/Documents/StakeholderInitiativeMilestones.pdf– Updated on the first of each month

– Multi-year time horizon

• Market Performance and Planning Forum– Every eight weeks

– Technical and release plan updates

• Release Users Group– Bi-weekly updates to release plan

– Interactive review of project impact assessment and milestones

• Technical Users Group– Monthly discussion forum of technical topics

– Brainstorm and evaluate solutions for technology and process based problems

Page 11: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 11ISO Public

Release Plan 2016

Independent 2016• Bidding Rules Enhancements – Part A• Aliso Canyon Initiative • Capacity Procurement Mechanism Replacement• Reliability Services Initiative • Commitment Cost Enhancements Phase 2 (remainder)• Post Implementation OMS Enhancements• Expanding Metering and Telemetry Options Phase 2• Demand Response Registration Enhancements• RIMS Functional Enhancements

Fall 2016 • BAL-003 Compliance• Flexible Ramping Product • BCR modifications and VER settlement • Acceptable Use Policy - CMRI• OMAR Replacement• PIRP System Decommissioning• Energy Imbalance Market (EIM) Year 1 Enhancements Phase 2• Energy Imbalance Market (EIM) 2016 Arizona Public Service (APS)• Energy Imbalance Market (EIM) 2016 Puget Sound Energy (PSE)• Energy Storage and Distributed Energy Resources (ESDER)

Page 12: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 12ISO Public

Release Plan 2017

Independent 2017• RTD Local Market Power Mitigation (LMPM) Enhancements

Fall 2017 (tentative, to be confirmed)• Reliability Services Initiative Phase 1B and Phase 2• Bidding Rules Enhancements – Part B• Stepped Constraints• Commitment Cost Enhancement Phase 3• Reactive Power Requirements and Financial Compensation• Flexible Resource Adequacy Criteria and Must-offer Obligation Phase 2• Bid Cost Recovery Enhancements• Contingency Modeling Enhancements• Energy Imbalance Market (EIM) Year 2 Enhancements• EIM 2017 Portland General Electric (PGE)

Spring 2018 • EIM 2018 Idaho Power Company

Fall 2018 (tentative, to be confirmed)• Metering Rules Enhancements• Regional Resource Adequacy• Transmission Access Charge Options

Page 13: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 13ISO Public

Project Summaries

Jan CogdillLead Financial Planning

Page 14: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 14ISO Public

2016 and 2017 Capital and Project Budgets

• 2016 Budget– Approved at $16.5M

• 2017 Budget

– Targeted at $18M - $20M

– Excess of 75 proposed projects will be prioritized to meet final budget limit

Page 15: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 15ISO Public

Summary of Completed and Active Projects

• Projects completed from April 2015 to March 2016 – 13 Capital Projects

• Budgeted costs $8.3M, actual costs $8M

– 39 Requirements & Other Projects• Budgeted costs $5.6M, actual costs $5.3M

• Active projects as of March 31, 2016– 44 Capital Projects

• Budgeted costs $21.5M, YTD spent $8.9M

– 34 Requirements & Other Projects• Budgeted costs $5.5M, YTD spent $3.3M

Page 16: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 16ISO Public

Summary of Supplemental Projects

• EMS and LOC Projects– Budgeted costs $43.9M, YTD spent $9.8M

• FERC and EIM Implementations– Budgeted costs $3.9M, YTD spent $1.7M

– EIM implementations include:

• Puget Sound Energy

• Arizona Public Service

• Portland General Electric

• Idaho Power Company

Page 17: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 17ISO Public

2015 & 2016 Q1 Financial Summaries

Denise WalshController

Page 18: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 18ISO Public

2015 Highlights

Key components of the 2015 actual to budget results:

• Operating revenues = $206.2 million vs. $206.0 million

- Higher miscellaneous revenues

• Operating expenses = $163.6 million vs. $165.1 million

- Lower outside legal and audit costs, partially offset by higher consulting and contracting

• Capital Expenditures = $8.3 million vs. $15.9 million (approved)

- Original budget was $20.0 million

Page 19: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 19ISO Public

Q1 2016 Monthly GMC Revenues

$10

$11

$12

$13

$14

$15

$16

$17

$18

$19

$20

$ in

mill

ions

Actual 14.89 13.66 14.96

Budget 14.96 13.40 15.30 14.81 15.27 17.43 18.87 19.52 18.31 16.66 15.03 15.79

Variance (0.07) 0.26 (0.34)

Cum Variance (0.07) 0.19 (0.15)

Jan-16 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Page 20: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 20ISO Public

Q1 2016 Cumulative Operating RevenuesRevenues = GMC & Other Revenues

$0

$25

$50

$75

$100

$125

$150

$175

$200

$225

$ in

mill

ions

Actual 15.90 30.42 45.77

Budget 15.69 29.83 45.86 61.40 77.40 95.56 115.16 135.41 154.45 171.84 187.60 204.12

Variance 0.20 0.59 (0.08)

Jan-16 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Page 21: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 21ISO Public

Jan-16 Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecMonthly Actual 10.53 12.98 13.50Monthly Budget 13.30 13.33 13.47 13.39 17.05 13.31 12.75 12.75 13.54 16.55 12.70 17.19Cum Actual 10.53 23.51 37.01Cum Budget 13.30 26.63 40.10 53.49 70.54 83.85 96.60 109.35 122.89 139.44 152.14 169.33Cum Variance 2.77 3.12 3.09

$0

$20

$40

$60

$80

$100

$120

$140

$160

$180

$ in

mill

ions

Q1 2016 Operating and Maintenance Expenses

Page 22: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 22ISO Public

2016 Budgeted Capital

Q1 2016 Cumulative Capital Expenditures

$0

$5

$10

$15

$20

$25

$ in

milli

ons

Budgeted capital 16.50

Cumulative Expenditures 0.06 0.07 1.33

Approved projects 5.16 7.91 7.91

Jan-16 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Page 23: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 23ISO Public

Budget Calendar and Next Steps

April GordonManager, Financial Planning and Procurement

Page 24: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 24ISO Public

2017 Budget and GMC Rates Timeline

Initial 2017Budget

Stakeholder Meeting

June 2016

BoardDec 2016

Stakeholder Input

We are here

PresentDraft 2017 Budget to

Board August 2016

2017 Budget

Stakeholder Meeting

Sept 2016

Public Comments to BoardOct 2016

Page 25: 2017 Budget Stakeholder Presentation DRAFTV2.0 · 2018. 2. 10. · Summary of Completed and Active Projects • Projects completed from April 2015 to March 2016 – 13 Capital Projects

Page 25ISO Public

Key Calendar Dates and Next Steps• Stakeholder comments due June 23

– Send to [email protected]• Internal budget process June - Aug• Board of Governors meeting (executive session) August 31

– Present preliminary 2017 budget• Post preliminary 2017 budget information for Stakeholders Sept 22• Stakeholder meeting to review preliminary budget Sept 29• Written Stakeholder comments due to ISO Oct 6• Board of Governors meeting Oct 2

– Public comments to board on 2017 budget• Board of Governors meeting Dec 14

– Request approval of 2017 budget• Post rates and budget documentation to ISO website Dec 21