2. shri. baboo ram

Upload: vinod-mahajan

Post on 03-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 2. Shri. Baboo Ram

    1/79

    By: Baboo Ram

    Ex. Executive Director BHEL Power Sector

  • 7/29/2019 2. Shri. Baboo Ram

    2/79

    PRESENTATION NAME

  • 7/29/2019 2. Shri. Baboo Ram

    3/79

  • 7/29/2019 2. Shri. Baboo Ram

    4/79

  • 7/29/2019 2. Shri. Baboo Ram

    5/79

  • 7/29/2019 2. Shri. Baboo Ram

    6/79

    Pre-commissioning means preparation for

    commissioning.

    commissioning of various equipments and systems arepre-commissioning for commissioning of the power

    plant. It is a pre-requisite for commissioning.

  • 7/29/2019 2. Shri. Baboo Ram

    7/79

    Commissioning means to put the equipment into operation asenvisaged.

    For a thermal power plant commissioning means to set up andoptimise all its equipments and systems to get output, efficiency,auxiliary power consumption and emission on sustained basisas envisaged to drive the benefit.

    For super critical and ultra supercritical plant commissioningwould mean higher efficiency of the plant with lower emission

    level and lower auxiliary power consumption(as compared tosub critical plants ) on sustained basis in order to drive thebenefit of elevated steam parameters.

  • 7/29/2019 2. Shri. Baboo Ram

    8/79

    Out put

    Heat Rate ( Efficiency )

    Auxiliary power consumption

    Emission level

    Sustained generation

  • 7/29/2019 2. Shri. Baboo Ram

    9/79

    Material

    Infrastructure

    Expertise

  • 7/29/2019 2. Shri. Baboo Ram

    10/79

    ANNEX-1

  • 7/29/2019 2. Shri. Baboo Ram

    11/79

    36 units UMPP 27960MW

    32units SCPP 21540MW

  • 7/29/2019 2. Shri. Baboo Ram

    12/79

  • 7/29/2019 2. Shri. Baboo Ram

    13/79

  • 7/29/2019 2. Shri. Baboo Ram

    14/79

  • 7/29/2019 2. Shri. Baboo Ram

    15/79

  • 7/29/2019 2. Shri. Baboo Ram

    16/79

    Lower pressure drop means lower

    feed-pump power and lower.through-life energy consumption

    Other advantages include better

    turn-down, simpler construction and

    improved availability.

    FURNACE WALL DESIGNThe furnace walls are exposed to the greatest heat flux of all heat absorbing surface. This is

    because of the intense radiant heat from the fireball.For any given furnace size, the spiral wall unitin which the tube is wrapped around the

    unit has fever tubes then vertical wall unit.

    SPIRAL & VERTICAL WATER WALL CONFIGURATION

    Optimized Rifled Tube

  • 7/29/2019 2. Shri. Baboo Ram

    17/79

  • 7/29/2019 2. Shri. Baboo Ram

    18/79

    Nozzle box 12Crcast steel

    HP internal

    casing

    12Crcast steel

    Main steam

    stop valves12Crcast steel

    MainsteamInlet shortpipe

    9Cr-1Mosteel

    Combined reheat

    steam valves12Crcast steel

    Reheat steaminlet short pipes

    9Cr-1Mosteel

    No.1 IP

    internal casing12Crcast steel

    HP IP

    Main steam inlet

    flange elbow9Cr-1Mosteel

    Cooling structure withmain steam leading pipe

    Overlay coatingProtection of No.s 1,2journal thrust bearing

    Rotor cooling for IP section(Protection of aged bending)

    Control valves 12Crcast steel

    H-IP Combined Type 600 C / 600C to 620 C

    Steam Temperature

    HIP Rotor 12Cr steel

  • 7/29/2019 2. Shri. Baboo Ram

    19/79

  • 7/29/2019 2. Shri. Baboo Ram

    20/79

    660MW Steam turbine : Cross section View

  • 7/29/2019 2. Shri. Baboo Ram

    21/79

  • 7/29/2019 2. Shri. Baboo Ram

    22/79

  • 7/29/2019 2. Shri. Baboo Ram

    23/79

    Water-wall Cracking

    Higher metal temperatures and the use of low alloy steel.

    Thermal fatigue cracking is caused by the combined

    action of elevated metal temperatures and thermal

    cycling.

    Growth of internal tube deposits, high heat flux,

    deterioration of fluid-side cooling or external fireside

    coatings.

    Slagging and shedding, Soot blowing, water cleaning orother factors may cause thermal cycling

  • 7/29/2019 2. Shri. Baboo Ram

    24/79

    Negative Flow Characteristic

    A high mass flux design.

    If the furnace heat flux distribution

    is non-uniform due to slagging.

    A FLOW RESPONSE CALCULATED FOR VARIOUS HEAT

    ABSORPTIONS FOR A BOILER WALL CIRCUIT WITH A HIGHMASS FLUX

    INCREASE IN HEAT ABSORPTION IS A

    REDUCTION IN TUBE FLOW

  • 7/29/2019 2. Shri. Baboo Ram

    25/79

    Slagging

    Due to Spiral tube configuration.

    Inclination of the tubes is thought to increase the

    propensity of slag and clinker.

    The higher fireside metal temperatures of

    supercritical boilers may also contribute toincreased slagging.

    Slagging refers to deposition of solid layers on theboiler tube, formed by sintering. Slagging is quite hard

    to remove and also (although it is sintered material) the

    slagging material is usually still a good insulator.

  • 7/29/2019 2. Shri. Baboo Ram

    26/79

    Welding of Special Materials

    Welding of dis-similar pieces i.e. two pieces fabricated

    out of different materials is a difficult process.

    The difficulty increases when the metals, out of which

    the pieces to be welded are fabricated, are newly

    developed and not conventional.

  • 7/29/2019 2. Shri. Baboo Ram

    27/79

    Tube Spacing to Handle Indian Coal

    Indian coal has high ash content and

    lower calorific value as compared to

    coals available in other countries such as

    Australia and South Africa.

    The designs of supercritical boilersdeveloped by foreign manufacturers are

    based on the superior type of coals.

    The tubing has to ensure that steam

    parameters required for the supercritical

    steam cycle are maintained and have tobe adopted to suit Indian coals.

  • 7/29/2019 2. Shri. Baboo Ram

    28/79

    Height of Structure

    Convenient and economical height of the

    boiler structure.

    The height of the boiler governed, however,

    by design considerations.

    The height of the (Chimney) is governed by

    environmental considerations.

  • 7/29/2019 2. Shri. Baboo Ram

    29/79

    Transportation of Major Equipment

    Imported equipment unloading facilities

    at port and project site.

    Load bearing capacity of bridgesinvolved (rail or road).

    Limited heavy equipment carriers

    Needs to develop approach road to the

    project site.

  • 7/29/2019 2. Shri. Baboo Ram

    30/79

    Skilled Manpower

    Shortage of enough experience and skill

    available for the erection and commissioning

    of a 660 MW/ 800 MW.

  • 7/29/2019 2. Shri. Baboo Ram

    31/79

  • 7/29/2019 2. Shri. Baboo Ram

    32/79

    INDIAN AMBIENT CONDITIONS AND INDIAN

    COALS

    OPERATION & MAINTENANCE ISSUES

    G coal is available for thermal power plants.The quality of coal available from domestic sources compares very unfavorably with the quality of coals

    imported from other countries such as Australia, Indonesia or South Africa.

    Problems associated with Indian coal are:

    Indian coal typically has higher moisture content. This can lead to lower boiler efficiencies than withimported coal.

    Low volatile matter in Indian coal leads to high-un-burnt carbon loses. Low boiler efficiency due to low CV and high ash content in Indian coals High ash and coal handling costs and milling power lead to high auxiliary power consumption High ash and high silica in the coal leads to higher erosion. Though lower flue gas velocities and

    provision of shielding plates can reduce erosion, it leads to higher capital costs for the boiler.

    Indian ambient condition

    High ambient temperature leads to higher cooling water temperature reducing the achievable

    condenser vacuum to a maximum of 0.13 bars. This in turn leads to higher steam consumption and a poorer turbine heat rate.

    High relative humidity leads to more losses in cooling tower

  • 7/29/2019 2. Shri. Baboo Ram

    33/79

    AVAILABILITY OF CONTRACTOR FORMAINTENANCE

    OPERATION & MAINTENANCE ISSUES

    Specific skills for maintenance.

    Important to provide extensive training to the plant personnel

    using similar facilities abroad and also using training simulators.

  • 7/29/2019 2. Shri. Baboo Ram

    34/79

  • 7/29/2019 2. Shri. Baboo Ram

    35/79

  • 7/29/2019 2. Shri. Baboo Ram

    36/79

    Chemical Cleaning Oil flushing

    Steam blowing

    Restoration of system

    Barring gear

    Vacuum system check

    Commissioning of gland sealing system

    Commissioning of HP/LP bypass system

    Steam dumping

  • 7/29/2019 2. Shri. Baboo Ram

    37/79

    Control gear setting

    Checking of turbine and generator protection

    Rolling and synchronizing

    Loading and trial run

    Performance guarantee test

  • 7/29/2019 2. Shri. Baboo Ram

    38/79

    OBJECTIVE

    The objective of this procedure is to chemically clean and passivate the

    internal surfaces of the steam generating portion (water touched

    surfaces) and heating surfaces (Economizer) using specified chemicalsemploying a single step process. This will render the above mentioned

    surfaces free of mill scale, and other deposits and form uniform &

    smooth protective layer of magnetite. With this protective layer, the

    generating surfaces are rendered passive to generate adequate

    negative potential under the operating pH to resist corrosion.

  • 7/29/2019 2. Shri. Baboo Ram

    39/79

    Iron concentration in three consecutive samples show equilibrium status.

    When the iron concentration in the cleaning solution is constant, it indicates

    that all the oxides have been dissolved. However, a minimum EDTA(Ethelene

    Diamine Tetra Acid ) contact period of 6 hours from the time of attaining the

    required temperature (110 deg. C) shall be allowed.

    Completion of pickling process once the EDTA strength and iron concentrationlevel out and reach equilibrium.

    The system shall be allowed to cool with the ID & FD fans in operation. Open

    the drum air vents when the pressure reaches to 1 kg / sq.cm.

    When the temperature comes down to 95 deg. C, the system shall be drainedcompletely in hot condition to the effluent pit by opening all the drain valves .

  • 7/29/2019 2. Shri. Baboo Ram

    40/79

    The drum surface shall be visually inspected for uniform

    smooth coating of protective layer.

    The low point header will be inspected and loose debris ifany, will be removed

  • 7/29/2019 2. Shri. Baboo Ram

    41/79

    Hot DM water flushings shall be drained into plant normal drain.

    The organic spent EDTA chemical solution after the cleaning process is

    drained into a pit. The pH of the effluent will be in the range of 8.5 to

    9.0 and hence no treatment for pH adjustment is required as it wouldmeet the pH requirement for disposal.

    Compressed air shall be used to destroy the residual Hydrazine &

    organics and the effluent shall be disposed after aeration for 10 days.

    (The organic chemical is completely bio-degradable).

  • 7/29/2019 2. Shri. Baboo Ram

    42/79

    Lubricating oil system

    Seal oil system

    Jacking oil system

    Governing oil/ control fluid system

  • 7/29/2019 2. Shri. Baboo Ram

    43/79

    To clean and remove any foreign material from theoil system

  • 7/29/2019 2. Shri. Baboo Ram

    44/79

    Completion of oil piping

    Installation of temporary piping after proper cleaning

    Cleaning of main oil tank and bearing pedestal

    Oil throttles in the bearing supply lines must be removed and dummy

    provided

    Duplex filter element in oil supply line to thrust bearing should be removed

    initially however it may be installed during final stage of flushing

    Flushing devices are installed in the bearing pedestal to bypass the

    bearings

    MOP must be removed and flushing device installed

  • 7/29/2019 2. Shri. Baboo Ram

    45/79

    Jacking oil system is isolated and it should be flushed

    separately.

    Turning gear nozzle box is removed and replaced with flushing

    device.

    Suitable oil heating arrangement must be available to raise

    the oil temperature to around 75 C.

    Oil cooling arrangement should also be there to cool the oil for

    giving thermal shocks.

    Arrangement for analysis of oil sample should be available.

  • 7/29/2019 2. Shri. Baboo Ram

    46/79

    Use of cotton waste is prohibited for cleaning the oil system. Markin cloth to

    be used.

    For checking the direction of rotation of the oil pumps oil must be filled in

    the oil tank

    Provision must be made for stopping the oil pumps from local as well as

    from UCB

    Fire fighting arrangement must be available during flushing

    Arrangement for cleaning the spilled oil should be available before starting

    the oil flushing.

    Motor current of the oil pumps specially the auxiliary oil pump should not

    exceed the rated value.

  • 7/29/2019 2. Shri. Baboo Ram

    47/79

    Oil flushing is considered complete when there is no

    mechanical impurities and traces of moisture as catched from

    oil sample.

    Duplex filter remains clean after 24 hours of flushing.

    Particle count is also some time used to declare completion

    of oil flushing.

    Recommendation of turbine supplier should be a guiding

    factor.

  • 7/29/2019 2. Shri. Baboo Ram

    48/79

    After oil flushing the system is restored to original position.

    All the temporary piping and flushing devices are removed.

    All the orifices/ restrictions are restored.

    All instrumentation pressure, temperature ,flow devices etc. are normalized.

    Blanks installed during flushing are removed.

    Main oil tank is drained , oil tank cleaned and recharged with fresh oil .

    Bearing pedestals are cleaned before boxing up

    Coolers are normalized

  • 7/29/2019 2. Shri. Baboo Ram

    49/79

    The function of barring gear is to rotate the shaft at low speed to

    remove the temporary bend during start up and after shut down

    to prevent hogging.

    Barring gear are :

    Electric motor operated

    Hydro motor operated

    Hydraulic barring gear

    All turbines have manual barring gear provision

  • 7/29/2019 2. Shri. Baboo Ram

    50/79

    Alignment of rotor train completed

    Rotors coupled

    Oil flushing completed

    Instrumentation inside the bearing pedestals completed.

    Bearing pedestals boxed up

    Generator work is completed and generator boxed up.

    Exciter is coupled.

    Insulation of generator bearing is checked before generator bearingpedestal box up.

    Condenser floated and joint between turbine and condenser made.

  • 7/29/2019 2. Shri. Baboo Ram

    51/79

    Lube oil and seal oil system commissioned

    Jacking oil pumps are available

    All the turbovisory , local and control room instrumentation are

    installed, calibrated and available for monitoring

    Interlock and protection for oil tank, oil pump and barring are

    tested and available

    Dc emergency power as well as DG set are commissioned and are

    available

    Shaft lift is checked in all the journals and is ok

    Direction of rotation of the shaft is checked.

  • 7/29/2019 2. Shri. Baboo Ram

    52/79

    ESTABLISH THE LUBE OIL SYSTEM ENSURE LUBE OIL TEMPERATURE AFTER OIL COOLER IS >35 C

    ENSURE PRESSURE IN ALL BEARING OIL SUPPLY LINE AND FLOW IS SITE

    GLASSES

    ENSURE PRESSURE IN SEAL OIL SUPPLY LINE AND FLOW IN SITE

    GLASSES.

    ENSURE DIFFERENTIAL PRESSURE REGULATOR IS FUNCTIONING.

    DC SEAL AND DC LUBE OIL PUMPS ARE ON AUTO START MODE AN CASEOF AC FAILURE

    SWITCH ON THE SUPPLY TO SUPPLY TO TURBOVISORY.

  • 7/29/2019 2. Shri. Baboo Ram

    53/79

    START JACKING OIL PUMP AND CHECK THE JACKING OIL PRESSURE

    AN ALL THE BEARINGS .

    TURN THE SHAFT MANUALLY WITH THE HELP OF MANUAL BARRING

    GEAR AND CHECK THE FREENESS OF THE SHAFT

    MOTIVE OIL CAN BE ALLOWED TO ENTER BARRING GEAR WHEELCHAMBER BY OPENING THE ELECTRICALLY OPERATED MOTIVE OIL

    VALVE

    JACKING OIL PUMP IS KEPT RUNNING AS LONG AS SHAFT IS TURNING.

  • 7/29/2019 2. Shri. Baboo Ram

    54/79

    ANY ABNORMAL IS NOISE IN THE TURBINE GLANDS OR BEARINGS.

    RETURN OIL FLOW FROM THE BEARINGS AND TEMPERATURE OF

    OIL.

    TURBOVISORY READINGS.

    GENERATOR SEAL OIL TEMPERATURE AND LINER METAL

    TEMPERATURE.

    COSTING DOWN TIME FROM FULL BARRING SPEED TO ZERO

  • 7/29/2019 2. Shri. Baboo Ram

    55/79

    MAIN STEAM

    COLD REHEAT

    HOT REHEAT

    HP BYPASS

    LP BY PASS

    AUXILIARY STEAM AND PRDS HEADER

    GLAND SEALING

    OTHER SMALL BORE LINES

  • 7/29/2019 2. Shri. Baboo Ram

    56/79

    The objective of steam blowing is to remove scales, loose

    material, iron cuttings etc, that might have been entrapped in

    Super Heaters, Steam piping, reheaters during manufacture,

    storage, erection at site. Failure to remove the debris may

    result in damage to turbine blades. Valves etc.

  • 7/29/2019 2. Shri. Baboo Ram

    57/79

    The steam blowing is done in four stages. Viz Stage 1(1a,1b) Stage 2

    (2a & 2b), Stage 3 (3a & 3b) & stage 4. Loop pipes from ESV and IV toturbine are to be taken care for cleanliness before erection and not to

    be steam blown.

    Steam blowing is carried out by adopting puffing method for stages

    1a, 2a 2b,&3a,3b. in which, boiler pressure is raised to 40 Kg/cm2

    and released through a quick opening valve and steam blowing done

    till the Drum pressure drops from 40 Kg/cm2 to 20 Kg/cm2

    Steam blowing for stages 1b & 4 are carried out by continuous

    method. Steam blowing by continuous method shall be done at 40-

    50% of normal operating pressure of the respective system for period

    of 20 to 30 minutes. Blowing repeated after a time gap of 2 Hrs.

  • 7/29/2019 2. Shri. Baboo Ram

    58/79

    Stage1a: SH, MSL, ESV, temporary line from ESV to EOTV and EOTV to exhaust with

    temporary piping will be concluded by observing the indents on the target plate.

    Stage1b:SH,MSL,Aux PRDS, Atomizing Steam lines & FO heating/tracing lines.

    Stage 2a SH, MSL, ESV, temporary lines from ESV to EOTV, EOTV to CRH line, CRH lines up

    to boiler end with temporary exhaust pipe. Tap off lines from CRH for deaerator, , auxiliary

    PRDS, HP heater 6a & 6b, gland sealing, etc. shall be remain closed/isolated. Stage 2a end

    point will be concluded by observing the indents on the target plate .

    Stage 2b : 2a plus HP bypass inter connection, hand operated valve mounted in place of

    HP bypass valve and CRH lines up to Boiler end with temporary exhaust piping. In this stage

    6 to 8 blows will be given through HP bypass to ensure cleanliness of the limb. Boiler MS

    stop valve will be used for stage 2b. EOTV will be kept closed. Manually Operated Isolation

    Valves in HP bypass lines will be kept opened fully.

    Stage

    3a : 2a plus reheater, HRHL, IV and temporary pipe.

    CRH line along with attemperator shall be welded with reheater before start of stage 3a. LP

    bypass lines shall be blanked during stage 3a. Stage 3a end point will be concluded by

    observing the indents on target plates .

  • 7/29/2019 2. Shri. Baboo Ram

    59/79

    Stage-3b: Stage 3a plus LP Bypass lines.

    Stage-4 :

    4a) APRDS to Gland seal steam

    4b) CRH to turbine extraction line (HPHS &LPHS).

    4c) CRH to Extraction 4 to Deaerator

    4d) CRH to Deaerator / FST

    4e) CRH to HP Heaters.

    4f) CRH steam line to Turbine gland sealing line

    4g) CRH to APRDS

  • 7/29/2019 2. Shri. Baboo Ram

    60/79

    BLANKING DEVICES ARE INSTALLED IN TURBINE MAIN TOP AND CONTROL

    VALVES AND SIMILARLY IN ESV

    TARGET PLATE IS INSTALLED BEFORE THE STEAM EXHAUST.

    TEMOPORARY PIPING ARE ERECTED FROM MAIN STOP VALVE TO OUTSIDE

    BUILDING

    TEMPORARY PIPING ARE ERECTED FROM ESV TO OUT SIDE BUILDING

    ARRANGEMENTS ARE MADE TO BLOW COLD REHEAT PIPE LINE TOWARDS

    BOILER END

    LOOPS ARE ERECTED TO BLOW HP BYPASS AND LP BY PASS

    TEMPORARY ARRANGEMENTS ARE MADE TO BLOW GLAND SEALING AND

    OTHER SMALL BORE LINES

  • 7/29/2019 2. Shri. Baboo Ram

    61/79

    The purpose of steam blowing of all critical piping, the steam blowing

    valve will be opened at 40 kg/Sq.Cm. and closed at 20 kg/sq.cm drumpressure.

    All the steam lines are purged as per various stages and it is a standard

    practice to limit number of blows per day to( 8-10) with an interval of 1-1

    hours.

    Blowing is carried out during the day and system is left cooling during

    night

    While blowing stage 3a, suitable dummies will be put at LPBP outlet

    temporary line. Required flange provisions are made in these temporarylines for installation of dummies.

  • 7/29/2019 2. Shri. Baboo Ram

    62/79

    All instruments coming in the steam flow are isolated or removed

    Temporary pipings are properly supported and insulated

    Steam exhaust is led to outside building to a safer place so as not to

    cause damage to equipment or person

    Steam blowing should be done preferably during day time due to

    noise pollution

    Sufficient quantity of dm water is stored

  • 7/29/2019 2. Shri. Baboo Ram

    63/79

    Steam blowing is considered complete when target plate remainsclean (2-3) small dots in three consecutive steam blows after

    overnight cooling.

    for stages 1, 2a, & 3a Disturbance factor value at selected locations

    should be greater than unity.

    More than 5 (five) pitting and shall not have any deformed edges.

    Besides, there shall be no pitting in the rim zone, i.e., area other than

    central zone

    Gland steam and other small bore pipings are blown for 1-2 hours and

    blowing is terminated on visual operation

  • 7/29/2019 2. Shri. Baboo Ram

    64/79

    Disturbance Factor = Qb2 x Vb

    Q2 MCR x VMCR

    Qb - Steam flow during blowing

    QMCR - Steam flow at MCR

    Vb - Sp. Volume of steam during blowing

    VMCR - Sp. Volume of steam at MCR

    Qb = Sonic Velocity During blowing x Area x 1

    Vb

    Where

    Qb = St. flow in kg/sec

    Sonic Velocity = KP Vb g =M/sec

    Area = Sq.MVb = Cu.m/Kg

    K = Constant = 1.3

    P = Pressure at the exit pipe = Kg/Sq.m

    Vb = Sp. Volume =Cu.M/Kg

    g = Acceleration due to gravity = M/Sec2

  • 7/29/2019 2. Shri. Baboo Ram

    65/79

    After steam blowing the system is restored to original position.

    All the temporary pipings and temporary supports are removed.

    All the orifices/ restrictions are restored.

    All instrumentation pressure, temperature ,flow devices etc. arenormalized

    Blanking arrangements are removed and valves restored .

    Blanks installed during steam blowing for system isolation are

    removed and system normalized.

  • 7/29/2019 2. Shri. Baboo Ram

    66/79

    Remote trip from UCB Manual trip from local

    Low vacuum trip

    Low vacuum trip -hydraulic

    Low lube oil pressure

    Axial shift

    Over speed striker 1 and 2

    Fire protection channel -1

    Fire protection channel-2

    MOT low level

    Low lub oil pressure

    Boiler fire out

    Main steam temperature low

    Generator protection

  • 7/29/2019 2. Shri. Baboo Ram

    67/79

    Steam dumping is carried out before steam admission toturbine

    During steam dumping operation, quality of steam is

    improved by turbine supplier

    HP/LP by pass system is used for steam dumping

    Turbine is kept on barring gear

    Full vacuum is raised

  • 7/29/2019 2. Shri. Baboo Ram

    68/79

    Max flow is stabilized through HP/LP by pass with rated

    steam parameter.

    Steam dumping is carried out till quality of condensate at

    CEP discharge is same as inlet to hot well make up.

    After steam dumping hot well, deaerator & Boiler drum are

    drained, clean and inspected before recharging.

  • 7/29/2019 2. Shri. Baboo Ram

    69/79

  • 7/29/2019 2. Shri. Baboo Ram

    70/79

    GE,s Super Critical/ Ultra Super Critical Steam Turbine.

    Recommended procedure for commissioning of large steam turbine by BHEL.

    Analysis of Supercritical technology in Indian Environment and Utilizing Indian coal

    by Prof: M M Hasan, Mechanical Engineering dept (Jamia Islamiya New Delhi)

    STEAM TURBINE DESIGN CONSIDERATIONS FOR SUPERCRITICAL CYCLES,Presented by Bechtel Power Corporation, Frederick.

    Bituminous coal fired large SC Power Plants for the European Market presented by

    Mr.K. Busekrus(HITACHI) ON 2007

    Supercritical technology in Indian presented by NTPC Ltd.

  • 7/29/2019 2. Shri. Baboo Ram

    71/79

  • 7/29/2019 2. Shri. Baboo Ram

    72/79

    S. No. Name/Location No ofunits

    Capacity(MW)

    Utility

    1. UMPP, Mundra 5 800 M/S. Tata power Ltd

    2. UMPP, Sasan 6 660 M/S. Reliance Power

    Ltd

    3. UMPP, Krishnapatnam 5 800 M/S. Reliance PowerLtd

    4. UMPP, Tilaiya 5 800 M/S. Reliance Power

    Ltd

    5. UMPP, Orissa 5 800 -

    6. UMPP, Chatisgarh 5 800 -

    7. UMPP, Tamilnadu 5 800 -

  • 7/29/2019 2. Shri. Baboo Ram

    73/79

    S. No. Name/Location No ofunits

    Capacity(MW)

    Utility

    1. Hissar 2 660 M/S. HPGCL

    2. Jhajjar 2 660 M/S. HPGCL

    3. Talvandi Sabo 2 660 M/S. PSEB

    4. Mundra, Kutch 2 660 M/S. Adani Power Ltd

    5. Meja-IV, Uttar Pradesh 2 660 M/S NTPC Ltd Joint

    venture

    6. Sipat-I, Bilaspur 3 660 M/S NTPC Ltd

    7. New Nabinnagar, Bihar 3 660 M/S NTPC Ltd Jointventure

    8. Krishnapatnam 3 800 M/S. APGENCO

  • 7/29/2019 2. Shri. Baboo Ram

    74/79

    S. No. Name/Location No of

    units

    Capacity

    (MW)

    Utility

    9. Solapur Thermal Power

    Station, Maharashtra

    2 660 M/S. NTPC Ltd

    10. Barh Super Thermal

    Power Station

    3 660 M/S. NTPC Ltd.

    11. Raghunathpur-II, West

    Bengal

    2 660 M/S. DVC

    12. Gidderbaha Station-1,

    Punjab

    2 660 M/S. PSEB

    13. Shahpur Thermal

    Power Company Ltd

    2 660 M/S STPCL

    14. Jewargi Power

    Company of Karnataka

    Ltd

    2 660 M/S Power Company of

    Karnataka Ltd.

  • 7/29/2019 2. Shri. Baboo Ram

    75/79

    S. No. Name/Location No of

    units

    Capacity

    (MW)

    Utility

    1. Dhenknal, Orissa 2 660 M/S. Lenco Infratech

    2. Pussurar Region,

    Raigarh

    Chhatisgarh

    3 660 M/S. Infrastructure

    Leasing & Financial

    Service Ltd.

    3. Chutru Region of

    Jharkhand

    3 660 M/S. Infrastructure

    Leasing & Financial

    Service Ltd.

    4. Gondia, Maharashtra 3 660 M/S. Adani Power

    Maharashtra Private

    Ltd

    5. Chandil Region ofJharkhand

    3 660 M/S. InfrastructureLeasing & Financial

    Service Ltd.

    6. Bade Dumarpali,

    Raigarh Chhatisgarh

    2 660 M/S Ahtena

    Chhatisgarh Power

    Private Ltd.

  • 7/29/2019 2. Shri. Baboo Ram

    76/79

    S. No. Name/Location No of

    units

    Capacity

    (MW)

    Utility

    7. East Godavari, Kakinda 2 660 M/S. Spectrum Power

    Generation Ltd

    8. Sinnar, Nasik

    (Maharashtra)

    2 660 M/S. Fama Power

    Company Ltd

    9. Nagapattinam,

    Tamilnadu

    2 660 M/S. PEL Power Ltd.

    10. Nandgaon pet,

    Amravati

    (Maharashtra)

    4 660 M/S. Sophia Power

    Private Ltd.

    11. Tamnar Raigarh,

    Chhatisgarh

    2 660 M/S. Opelina Finance &

    Investment Ltd

    12. Tamnar Raigarh,

    Chhatisgarh

    2 660 M/S Jindal Power Ltd

  • 7/29/2019 2. Shri. Baboo Ram

    77/79

    S. No. Name/Location No of

    units

    Capacity

    (MW)

    Utility

    13. Lathur, Maharashtra 2 660 M/S. Amravati Thermal

    Power Ltd.

    14. Machillipatnam, Andhra

    Pradesh

    2 660 M/S. Thermal

    Powertech

    Corporation(I) Ltd15. Gopuvanipalem,

    Krishna (Andhra

    pradesh)

    3 660 M/S. Nagarjuna

    Construction Company

    Ltd.

    16. Simar Thermal Power

    Plant, Junagarh (Guj.)

    2 800 M/S. JSW Energy Ltd.

    17. Salaboni Thermal

    Power Ltd, Paschim

    Midnapore

    2 800 M/S. JSW Energy Ltd.

    18. Manappad Tuticorin,

    Tamilnadu

    2 660 M/S Ind-Bharat Power

    (Madras) Ltd

  • 7/29/2019 2. Shri. Baboo Ram

    78/79

    S. No. Name/Location No of

    units

    Capacity

    (MW)

    Utility

    19. Mundra, Kutch, Gujrat 3 660 M/S. Adani Power Ltd.

    20. Sompeta, Dirkakulam

    (Andhra Pradesh)

    3 660 M/S. Nagarjuna

    Construction Company

    Ltd.

    21. Central India Power,

    Phase-II, Maharashtra

    3 668 M/S. Central India

    Power company Private

    Ltd.

    22. Tanda Expansion, Uttar

    Pradesh

    2 660 M/S. NTPC Ltd

    23. Katwa, West Bengal 2 660 M/S. WPDCL

    24. Bakreshwar Extesion

    Project

    1 660 M/S. WPDCL

  • 7/29/2019 2. Shri. Baboo Ram

    79/79

    S. No. Name/Location No of

    units

    Capacity

    (MW)

    Utility

    25. Koradi Extension

    Project Maharashtra

    2 660 M/S. Mahagenco

    26. East Coast, Andhra

    Pradesh

    2 660 M/S. East Coast Energy

    27. NSL Power, Tamilnadu 2 660 M/S. NSL Power Private

    Ltd

    28. Marakanam, Tamilnadu 4 800 M/S. NTPC Ltd

    29. Darlipali, Orissa 4 800 M/S. NTPC Ltd

    30. Lara, Chhatisgarh 5 800 M/S. NTPC Ltd31. Kudgi, Karnataka 3 660 M/S. NTPC Ltd. JV with

    M/S. PCKL