2. approach to eia
TRANSCRIPT
2.1
2. Approach to EIA
Introduction
2.1 This chapter sets out the approach and methodology that has been undertaken to complete
the assessment of the likely significant environmental effects of the Proposed Development
(as described in Chapter 4: The Proposed Development and supporting plans).
2.2 This Chapter sets out the following:
• Adoption and application of best practice within the EIA process;
• Scope of the EIA, including a summary of the EIA Scoping process and the technical
disciplines scoped in and out of the EIA;
• Stakeholder engagement, summarising the level of engagement with statutory and
non-statutory consultees, public consultation events and other forms of engagement;
and
• Approach to the assessment of likely significant effects, specifically covering: approach
to baseline; future baseline; identification of sensitive receptors; information to inform
assessment; use of tolerances; implementation of mitigation; significance criteria; and
limitations/assumptions.
Adoption of Best Practice
2.3 As confirmed within Chapter 1: Introduction, this ES meets the requirements set out in
Regulation 18, Paragraphs 3 – 4 and Schedule 4 of the EIA Regulations.
2.4 In addition, the EIA (and therefore the ES) has been undertaken with due consideration of
the following guidance documents:
• Ministry of Housing, Communities & Local Government, Planning Practice Guidance
(Ref 2.1);
• IEMA, EIA Guide to Shaping Quality Development (Ref 2.2); and
• IEMA, EIA Guide to Delivering Quality Development (Ref 2.3).
Scope of the ES
EIA Scoping
2.5 A request for an EIA Scoping Opinion, together with an EIA Scoping Report (Appendix 1.1),
prepared in line with Regulation 15, of the EIA Regulations was submitted to SBC in August
2018.
2.6 In response, SBC provided an EIA Scoping Opinion on the 16th October 2018 (Appendix 1.2),
supported by technical responses from consultees (both statutory and non-statutory) and
other interested parties.
2.2
2.7 Table 2.1 summarises the comments received as part of the EIA Scoping Opinion (full details
of which can be found in Appendix 1.2) and how these have been addressed within the ES,
or if more appropriate, within a standalone planning document supporting the overall
Application.
2.8 Whilst the EIA Scoping Report sought to establish the overall framework for the EIA in
relation to the environmental topics and likely significant effects, the Proposed Development
and the strategies that underpin it have been refined or informed by further technical
studies, modelling and analysis works and engagement with consultees.
2.9 As a result, where the scope of the assessment proposed within the EIA Scoping Report has
changed, this has been clearly identified within the Scope of Assessment section of Technical
Chapters 6 – 18.
2.3
Table 2.1: Summary of EIA Scoping Opinion Comments
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“The proposed development, for which the above Opinion
is sought, conflicts with Swindon Local Plan Policy NC3
which covers development to the east of the A419 as
defined on the Policies Map. The site lies within the
Indicative Non-Coalescence area of NC3 and outwith the
allocated development area.”
Campaign for the
Protection of Rural
England (CPRE) and
North Wessex Downs
AONB
Compliance with policy is assessed within the Planning
Statement submitted in support of the Application.
“This Science Park is in reality an industrial site with some
specialised manufacturing. There is no estimated number
of jobs to be created. It appears to be a hybrid application
of low density.”
CPRE The job numbers that are anticipated during construction and
operation of the Proposed Development, and the
methodology to reach these numbers is described in Chapter
6: Socio-Economics.
“A Science and Technology centre is being developed at the
former Hullavington Airfield, being brownfield this would
be a more appropriate site.”
CPRE The alternatives considered by the Applicant are reported in
Chapter 5: Consideration of Alternatives.
“We consider the following areas necessary for inclusion
within the Environmental Statement / planning submission:
• Surface Water Drainage and Flood Risk
• Water Resources (supply) and Water Efficiency
• Wastewater
• Groundwater Protection
• Impact on protected species and habitat
Environment Agency The following are included in the ES as follows:
• Surface Water Drainage and Flood Risk
considered in Chapter 11: Water Resources, Food
Risk and Drainage.
• Water Resources (supply) and Water Efficiency
considered in Chapter 11: Water Resources, Food
Risk and Drainage.
• Wastewater considered in Chapter 11: Water
Resources, Food Risk and Drainage.
2.4
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
• Construction Environment Management Plan,
including pollution prevention measures, and
• Waste management”
• Groundwater Protection considered in Chapter
11: Water Resources, Food Risk and Drainage.
• Impact on protected species and habitat
considered in Chapter 18: Ecology.
• Construction Environment Management Plan,
including pollution prevention measures – these
are referenced throughout the Technical
Chapters (6 – 18) in the Primary and Tertiary
Mitigation section as well as Chapter 4: The
Proposed Development.
• Waste management is considered in Chapter 16:
Waste.
“The site may be at risk from other sources of flooding (e.g.
groundwater, surface water), which are not considered in
the mapping of flood zones.”
Environment Agency Groundwater and surface water are considered in Chapter 11:
Water Resources, Food Risk and Drainage.
“When drawing up wastewater treatment proposals for
any development, the first presumption is to discharge foul
drainage into a public sewer to be treated at a public
sewage treatment works (those provided and operated by
the water and sewerage companies). This should be done
in consultation with the local sewerage company.
Where a connection to a public foul sewer is not feasible (in
terms of cost and/or practicality) a package sewage
treatment plant can be considered. This should offer
treatment so that its final discharge meets the standards
set by the required Environment Agency Environmental
Environment Agency Under the new charging arrangements brought out in April
2018 (Charging Rules for New Connection Services, OFWAT),
Thames Water has an obligation to provide infrastructure to
the Site once planning permission has been obtained. Thames
Water has proposed to provide a foul pumping station(s)
adjacent to Wanborough Wastewater Treatment Works to
divert flows from the existing 225mm foul sewer and the
proposed development up to the Swindon New Eastern
Villages development to support the Proposed Development.
Further details can be found in Chapter 11: Water Resources
2.5
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
Permit A proposal for a package sewage treatment plant
and infrastructure should set out clearly the responsibility
and means of operation and management to ensure that
the Permit is not likely to be breached during the life of the
plant.”
Flood Risk and Drainage and the Utilities Statement
(Appendix 11.3).
“Sustainable design and construction should be
implemented across the proposed development. This is
important in limiting the effects of, and adapting to climate
change.”
Environment Agency Chapter 4: The Proposed Development and Chapter 17:
Climate Change outline the measures to be implemented by
the Proposed Development to adapt to climate change.
“Information on biodiversity impacts and opportunities
should inform all stages of development including, for
instance, site selection and design including any pre-
application consultation as well as the application itself.”
Environment Agency The factors that have been considered in the site selection and
design are described in Chapter 5: Consideration of
Alternatives. Strategic landscape zones have been
incorporated into the design of the Proposed Development
and enhance biodiversity.
“If historic use of the site may have caused land
contamination then paragraph 109 of the NPPF states that
the planning system should help prevent both new and
existing development from contributing to, or being put at
risk from unacceptable levels of water pollution. Thorough
site investigation information must be prepared and
presented by a competent person.”
Environment Agency The potential risk of contamination of controlled waters from
ground contaminants and surface run-off is assessed during
construction and operation in Chapter 10: Geology and Soils.
“Safeguards should be considered for implementation
during the construction phase to minimise the risks of
pollution from the development.”
Environment Agency The mitigation to reduce the risk of pollution from
construction of the Proposed Development is outlined in
Chapter 4: The Proposed Development, Chapter 10: Geology
and Soils and Chapter 11: Water Resources, Flood Risk and
Drainage, and summarised in Chapter 20: Summary of the ES
and Schedule of Mitigation.
2.6
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“Should this proposal be granted planning permission, then
in accordance with the waste hierarchy, we wish the
applicant to consider reduction, reuse and recovery of
waste in preference to offsite incineration and disposal to
landfill during site construction.”
Environment Agency Chapter 16: Waste has considered reuse and recycling of
materials in the assessment of the increase in waste
generation during construction.
“Environmental impacts arising from any disruption during
construction, traffic volume, composition or routing change
and transport infrastructure modification should be fully
assessed and reported, along with the environmental
impact of the road network upon the development itself.”
Highways England The environmental impacts from construction traffic are
assessed within Chapter 12: Transportation, Chapter 13: Air
Quality, and Chapter 14: Noise and Vibration.
“Information relating to the flooding zone that the site is
located is required and we stress that development must
not lead to any surface water flooding on the SRN
carriageway.”
Highways England Chapter 11: Water Resources, Flood Risk and Drainage
confirms that the Site is in Flood Zone 1, so at low risk of
flooding, and that the Surface Water Drainage Strategy will
ensure that the risk of flooding is not increased elsewhere.
“Any assessment should consider the operation of the
Strategic Road Network – in this case M4 J15 and the A419
carriageway; specifically any links to the network which
could detrimentally affect its performance. This includes
the M4 J15 / A419 and A419 / Purley Road / Pack Hill /
A4259 interchanges.”
Highways England The traffic flows are based upon the SBC Strategic Saturn
Model covering Swindon and the wider area in agreement
with SBC. Further information on this is detailed in Chapter 12:
Transportation.
“Highways England should be involved in any discussions
regarding use of the Swindon Borough Council traffic
model in order to assess the impact of the proposed
development. This is to ensure that the scope of the model
and model outputs will be acceptable to Highways
England, before work is undertaken.”
Highways England Chapter 12: Transportation outlines the consultation that has
been undertaken with regards to the traffic model. Further
information on additional modelling is explained in the
Limitations and Assumptions section of this chapter.
“Analysis of accident data for the latest available full five-
year period regarding the SRN surrounding the site should
Highways England The assessment of accidents in Chapter 12: Transportation
has considered data for a five year period. The Baseline
2.7
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
be undertaken. Any relevant collision clusters or recurring
accident causation factors should be assessed and properly
mitigated where the proposed scheme is shown to make
conditions worse.”
Conditions section of this chapter considers collisions on key
routes and whether there are any trends in these accidents.
“The potential impact of construction vehicles on the SRN
should be included within the assessment work.”
Highways England The traffic flows are based upon the SBC Strategic Saturn
Model covering Swindon and the wider area, which was
agreed with SBC. Further information on this is detailed in
Chapter 12: Transportation.
“However, we have concerns with the scoping exercise
already undertaken (pages 32 to 42 of the Scoping Opinion
Request; Turley 2018), in particular the lack of a reference
to the Lower Wanborough Conservation Area or suitable
maps or figures to locate assets scoped in or out at this
stage.”
Historic England The Built Heritage Statement (Appendix 8.1) clarifies that
although the Lower Wanborough Conservation Area falls
within the study area, the analysis indicates that the
understanding or appreciation of the significance of this area
would be unlikely to be impacted by the Proposed
Development. The location of this Conservation Area is shown
in Appendix 3 of Appendix 8.1.
“We also note a degree of apparent confusion between the
built heritage and archaeological assets: the Hall Place
Scheduled Monument (above) is referred to as part of the
historic built environment.”
Historic England Hall Place has been scoped out of the assessment of built
heritage assets in Chapter 8: Built Heritage.
“In terms of detailed assessment methodology, we would
expect any assessment of settings to be undertaken in
accordance with our recently-published guidance (HE 2017
[rev] Good Practice Advice in Planning, Note 3, The Setting
of Heritage Assets). Similarly, we would expect any over-
arching EIA methodology to accord with the guidance given
in Highways Agency note 20807 of 2007, commonly known
as DMBRB 2.”
Historic England Chapter 8: Built Heritage has given consideration to Good
Practice Advice Note 3: The Setting of Heritage Assets (2nd
Edition) (2017) and the Design Manual for Roads and Bridges
(Vol. 11 Section Part 2) (2nd Edition 2019).
2.8
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“The landscape assessment should also consider views to
the north Wessex downs as it is part of the experience
taken when using the PROW network on the edge of
Swindon and not merely views from as noted in para 7.1 of
the report.
Due to the potential for long distance views a 5km radius
should be set rather than 2km with a couple of ad hoc
locations. ZTVs would set the groundwork for an LVIA in
terms of potential viewpoints.
Liddington Castle should be included and the Ridgeway
national trail should also be landscape receptors (para
7.11).
Additional representative views should be included in an
LVIA from the PROW south of Wanborough House with
views towards the SE, the PROW to the NW of Marsh Farm
with a view SE from part way between the A419 and Marsh
Farm and a view N to NW from below Hill Barn adjacent to
the Ridgeway (road) at the base of Liddington Hill.
Representative view 13 should include a view from
Liddington castle and view 15 should include the Ridgeway
National Trail and simply the Road.”
North Wessex Downs
AONB
Chapter 7: Landscape and Visual contains a summary of
consultation and actions taken in response. This outlines that:
• Setting of the AONB was scoped into the
assessment;
• The ZTV study area was increased;
• The view from Liddington Castle was considered
but a separate representative viewpoint has not
been included due to similarity with VP13 and
VP15;
• The views from PRoW at Hill Barn were not
included, as this area is represented by VP15; and
• PRoW from south of Wanborough House and NW
of Marsh are included as part of a visual receptor
group, but were not included as additional
viewpoints, as VP03 is considered to be
representative of views from this side of the Site.
“Would disagree with para 15.3 in terms of the
Environmental Zone classification for lighting, given its
agricultural use and lack of street lights the site would be
categorised under EZ1 not EZ2 as stated. Dark skies are a
special quality of the AONB and this extends beyond the set
boundary into the setting.”
North Wessex Downs
AONB
The Baseline Conditions section of Chapter 15: Lighting
categorises the Site as on the border of Environmental Zones
E1 and E2.
2.9
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“Lighting effects need to be considered against the
landscape particularly the AONB and not simply to the
users of local road and footpath networks.”
North Wessex Downs
AONB
The changes from lighting on the North Wessex Downs AONB
are considered in Chapter 7: Landscape and Visual.
“A full ecological assessment should be carried out due to
the proximity of the local wildlife site and Coate Water
SSSI.”
North Wessex Downs
AONB
No effects on the Coate Water SSSI/LNR’ are expected due to
(i) distance from the Site, (ii) the habitats present within the
Site being highly sub-optimal for species the SSSI is designated
for, (iii) the nature of the Proposed Development which is
unlikely to increase recreational pressure on the SSSI, and (iv)
the relative resistance of habitats within the SSSI to the effects
of nitrogen deposition. Therefore this is scoped out of the EIA.
Chapter 18: Ecology contains further details.
“Thames Water considers the following issues should be
considered and covered in either the EIA or planning
application submission:
1) The developments demand for Sewage Treatment and
network infrastructure both on and off site and can it be
met.
2) The surface water drainage requirements and flood risk
of the development both on and off site and can it be met.
3) The developments demand for water supply and
network infrastructure both on and off site and can it be
met.
4) Build – out/ phasing details to ensure infrastructure can
be delivered ahead of occupation.
5) Any piling methodology and will it adversely affect
neighbouring utility services.”
Thames Water These issues are covered in Chapter 11: Water Resources,
Flood Risk and Drainage, Appendix 11.3: Utilities Statement
and Chapter 4: The Proposed Development.
2.10
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“I would except to see an EIA with a comprehensive
chapter on cultural heritage submitted with any planning
application to develop this site. The Chapter will be need to
include the results from a programme of archaeological
evaluation to include geophysical survey and trial
trenching.”
Archaeological
Advisor (Wiltshire
Council)
Cultural heritage is assessed in Chapter 8: Built Heritage and
Chapter 9: Archaeology. The results of the geophysical survey
and field evaluation (trenching) have informed Chapter 9:
Archaeology.
“Consideration of the effects of the proposed development
upon the setting of heritage assets includes the asset’s
physical surroundings as well as the experience of the
asset.”
SBC Conservation
Officer
Chapter 8: Built Heritage considers the effects upon setting of
heritage assets during construction and operation.
“Some of the omitted designated assets as identified at pre
application are now generically included in Table 8.1 (EIA
SOR Table 8.1) for example listed buildings which are also
contained within Conservation Areas. I note that those for
Upper Wanborough are seemingly restricted to those in
‘closer proximity’ whereas there is no seemingly
comparable limitation to those in Liddington (or Lower
Wanborough Conservation Area). Again the basis for
consideration for those included or excluded needs to be
fully evidenced.”
SBC Conservation
Officer
The evidence base for scoping designated assets in and out of
the EIA is explained in the Scope of the Assessment section in
Chapter 8: Built Heritage. Since submission of the EIA Scoping
Report (Appendix 1.1), a number of assets are not considered
to have the potential to experience significant effects. The
evidence for this is also included in the Scope of the
Assessment section of this chapter.
“Regarding this request (EIA Scoping Opinion Request,
Turley, August 2018) to scope ecology out of the EIA, I am
of the opinion that it should be included within the EIA.”
SBC Ecology Officer Ecology has been scoped into the EIA, the assessment of
which can be found at Chapter 18: Ecology. The scope of the
ecology assessment is outlined in the Scope of the Assessment
section in Chapter 18: Ecology.
“Noise during the construction phase, especially from haul
routes in/out of the site. I would be concerned if the current
trackway serving Inlands Farm was used as the primary
haul route, as this would result in all construction traffic
SBC Environmental
Health Officer (Air
Quality & Noise)
Construction noise at residential receptors has been assessed
in Chapter 14: Noise and Vibration.
2.11
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
passing a noise sensitive receptor on the quiet north west
border of the proposed development.”
“Noise during the operational phase from plant equipment
and vehicle traffic on site, a robust BS 4142:2014
assessment should identify any potential issues at this
stage. Where the rating level of any noise source exceeds
5dB below the background level (LA90), as determined by a
BS 4142:2014 assessment, details of noise mitigation
would be expected.”
SBC Environmental
Health Officer (Air
Quality & Noise)
The assessment of noise from external fixed plant items and
heavy goods vehicles manoeuvring and loading/unloading
within the Site has used BS 4142 Noise Emission Limits.
Further information can be found in Chapter 14: Noise and
Vibration.
“Concerns surrounding dust and air quality will be
answered in the construction environmental management
plan.”
SBC Environmental
Health Officer (Air
Quality & Noise)
Chapter 13: Air Quality and Chapter 4: The Proposed
Development outline the measures to control dust and air
quality during construction, which will be included in a
Construction Environmental Management Plan.
“The final, and perhaps biggest concern is the risk of a
perceived loss of amenity for Wanborough residents
because the development will inevitably impact upon the
existing night-time scene between Wanborough and the
A419/Swindon, as well as the potential for light intrusion at
nearby sensitive receptor properties.”
SBC Environmental
Health Officer (Air
Quality & Noise)
The changes in night time scene for residential receptors with
direct and partial views of the Site during construction and
operation has been assesses in Chapter 15: Lighting.
“The study area needs to be informed by a robust ZTV
study, not a subjective one without apparent evidence
basis, as appears to have been proposed. Pending receipt
of this, the effects and receptors as described in the ESSR
(7.7/10, 7.11, 7.12) are not accepted. A ZTV study is
required with these parameters be
considered/amended/added to, as appropriate in
response.”
SBC Landscape Officer ZTV modelling has been undertaken and is included as Figure
7.7. This assessed the visibility of the Site and Proposed
Development and identifies the maximum area from which
part or all of the Proposed Development would potentially be
visible from a 1.6m high receptor. Further details are included
in the Assessment Methodology section of Chapter 7:
Landscape and Visual.
2.12
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“The study area needs to reflect identified effects in line
with accepted GLVIA terminology.”
SBC Landscape Officer The Extent of the Study Area section in Chapter 7: Landscape
and Visual explains that the approach to the study area is
supported by GLVIA3.
“The effect of sky glow needs to be properly assessed, not
discounted. This needs to be presented for inclusion in
Table 15.1: Likely Significant Effects. The findings of the
requested ZTV study needs to be accommodated in 15.10
‘Identification of Sensitive Receptors’.”
SBC Landscape Officer Changes in sky glow has been scoped out of the EIA. The
evidence for this is presented in Chapter 15: Lighting.
“As per these comments, a Tree survey to BS5837:2012,
incorporating an Arboricultural Impact Assessment (AIA)
must be undertaken as a minimum, which we would
anticipate being incorporated into the baseline studies as
part of the LVIA process.”
SBC Landscape Officer The Arboricultural Impact Assessment is submitted as a
standalone report to support the Application. Chapter 7:
Landscape and Visual refers to this assessment for the tree
and hedgerow removal.
“A flood Risk Assessment (FRA) and/or Drainage Strategy
(DS) will need to be submitted with any outline or full
application in relation to this site.”
Lead Local Flood
Authority
The Flood Risk Assessment is included as Appendix 13.2.
Detailed comments regarding trip generation and traffic
distribution (see Appendix 1.2).
Local Highway
Authority
Trip generation and traffic distribution are outlined in the
Transport Assessment (Appendix 14.1). This was agreed with
SBC and input into SBC’s SATURN strategic traffic model.
Further details are contained in Chapter 7 of Appendix 14.1.
“The application in para 7.3 of the Scoping Opinion Request
document has generally identified the public rights of way
that cross the application site. If the site is developed those
routes will need to be considered within any development
along with their connections outside of the site.”
SBC Rights of Way
Officer
Chapter 4: The Proposed Development outlines where Public
Rights of Way will be retained or diverted during construction.
2.13
Summary of Scoping Comment Consultee How/ Where the comment has been addressed
“This is an extremely archaeological sensitive site and
therefore a detailed assessment of the site and surrounding
area should be carried out and not just a desk based
assessment.”
Wanborough Parish
Council
The effect of the Proposed Development on archaeology is
reported in Chapter 9: Archaeology. This has been informed
by a geophysical survey and trial trenching surveys.
“Section 11.4 states low ground water levels during a three
month survey period from March 2018. This is not a true
indicator of the ground water levels when the survey was
carried out during one of the driest periods known. Parish
Council would like the ground water levels surveyed in a
more realistic period of time and also during the winter
months.”
Wanborough Parish
Council
Six months of groundwater monitoring has been completed on
Site. The results of this have been detailed in the Flood Risk
Assessment (Appendix 11.2).
“The Environmental Statement must fully consider and
address all implications arising from the proposed scheme,
particularly in relation to those which would have a wider
impact on the NEV and surrounding settlements.”
SBC Chapter 19: Cumulative Effects Assessment looks at the
effects of the Proposed Development in-combination with
seven Approved Projects, six of which form part of the New
Eastern Villages allocation.
“In reference to the chapters proposed for the
Environmental Statement, the Council broadly agree with
recommendations outlined within the ‘EIA: Scoping Opinion
Request’ (August 2018). Notwithstanding this, the Council
disagree with the proposals to scope out Ecology, and
therefore recommend that Ecology be fully assessed
through the EIA process, and form part of any submitted
Environmental Statement.”
SBC Ecology has now been included in the scope of the EIA. The
scope and assessment is presented in Chapter 18: Ecology.
2.14
Technical Disciplines Scoped In
2.10 Following the EIA Scoping exercise, the following technical disciplines and their associated
likely significant environmental effects have been taken forward and assessed within the EIA:
• Socio-Economics (Chapter 6);
• Landscape and Visual (Chapter
7);
• Built Heritage (Chapter 8);
• Archaeology (Chapter 9);
• Geology and Soils (Chapter 10);
• Water Resources, Flood Risk
and Drainage (Chapter 11);
• Transportation (Chapter 12);
• Air Quality (Chapter 13);
• Noise and Vibration (Chapter
14);
• Lighting (Chapter 15);
• Waste (Chapter 16);
• Climate Change (Chapter 17);
and
• Ecology (Chapter 18).
2.11 The likely significant environmental effects considered within each technical discipline are
detailed within the relevant technical chapters (Chapters 6 – 18).
2.12 As detailed within Schedule 4, Paragraphs 5 and 8 of the EIA Regulations, there is the
requirement to consider the risk of major accidents and/or disasters relevant to the
Proposed Development. Although there is the potential for a wide range of major accidents
and disasters that could occur, the Proposed Development is not of a nature that is
associated with high risks. The Proposed Development will accord with relevant health and
safety legislation, including the Construction (Design and Management) Regulations 2015
and Health and Safety at Work Act 1974. Further risks associated with potential exposure to
contamination and harmful materials and flooding are contained in Chapter 10: Geology and
Soils and Chapter 11: Water Resources, Flood Risk and Drainage. The risks associated with
road accidents are contained in Chapter 12: Transportation.
Effects Scoped Out
2.13 As part of the EIA process, there are several environmental effects which are considered not
significant and therefore ‘scoped out’ of the EIA. The evidence base to support ‘scoping out’
these environmental effects is presented in the EIA Scoping Report (Appendix 1.1) and
Scoping Opinion (Appendix 1.2), and these not significant effects have been documented in
the ‘Scope of the Assessment’ section of each Chapter (Technical Chapters 6 – 18).
Stakeholder Engagement
2.14 In addition to the consultation undertaken to inform SBC’s EIA Scoping Opinion (Appendix
1.2), the Project Team have undertaken technical consultation with relevant consultees to
inform the scope, assessment methodology/approach and in some instances the outputs of
baseline studies/surveys. The specifics of technical consultation are reported within
Technical Chapters 6 – 18.
2.15
Approach to Assessment of Likely Significant Environmental Effects
2.15 This section outlines the approach to the assessment of likely significant environment effects
adopted, as reported within this ES. This includes details on baseline conditions, future
baseline, identification of sensitive receptors, information to inform assessment, the use of
tolerances, implementation of mitigation, significance criteria and limitations and
assumptions.
2.16 The exact methodology for the assessment of likely significant effects of the Proposed
Development during demolition and construction and operational phases is varied across
each of the technical disciplines considered within the EIA, largely due to technical specific
guidance and best practice. Therefore, each of the Technical Chapters 6 – 18 specifically sets
out the relevant technical assessment methodologies.
Baseline Conditions
2.17 The boundary upon which baseline data has been collected (i.e. study area) varies between
the technical topics and therefore are reported specifically within Technical Chapters 6 – 18.
However, all study areas will be additional to the Site, as defined in the Planning Application
Boundary.
2.18 Schedule 4, Paragraph 3 of the EIA Regulations, states that an ES should include:
‘a description of the relevant aspects of the current state of the environment (baseline
scenario)’
2.19 Likely significant effects as a result of the Proposed Development has been described in the
ES in relation to the deviation from the baseline environment within the Site or/and relevant
technical study areas. Therefore, it is necessary to establish the existing baseline
environmental condition of the Site and study area.
2.20 The baseline environment comprises the prevailing existing environmental characteristics
and conditions of the Site, based upon:
• Site visits and surveys;
• Desk-based studies;
• Review of existing site-specific information or public literature;
• Modelling;
• Review of relevant national and local planning policies; and
• Consultation with the relevant statutory consultees through the EIA process.
2.21 The baseline conditions for the purpose of the ES will vary dependent on the timing of the
survey or the date when data sources will have been accessed. All baseline conditions are
based upon data accessed or surveys completed during 2018 and 2019.
2.16
2.22 Some data obtained from third parties may be older; however, this is largely associated with
below ground data which is not anticipated to have significantly changed and therefore still
remains relevant.
2.23 Throughout the EIA, the origin of all third party data, the dates of surveys and the dates
when data sources have been accessed will be clearly outlined within the relevant Technical
Chapters 6 – 18, alongside any limitations or assumptions.
Future Baseline
2.24 Schedule 4, Paragraph 3 of the EIA Regulations states that an ES should include:
‘…an outline of the likely evolution thereof (without implementation of the development) as
far as natural changes from the baseline scenario can be assessed with reasonable effort on
the basis of availability of environmental information and scientific knowledge’
2.25 As required under the EIA Regulations the ES reports the future baseline scenario under a ‘do
nothing’ scenario, as further discussed in Chapter 5: Consideration of Alternatives. However,
the future baseline scenario is discussed within each of the Technical Chapters 6 – 18. The
discussion is associated with how the Site and study area may change assuming the Site was
not developed further and the existing management regime was maintained.
2.26 The assessments presented in the ES are based on the deviation from the existing baseline
scenario. In some cases, where helpful to the overall assessment, a future baseline condition
is also presented.
Identification of Sensitive Receptors
2.27 Schedule 4, Paragraph 4 of the EIA Regulations states that an ES should include:
‘a description of the factors specified in Regulation 4(2) likely to be significantly affected by
the development: population, human health, biodiversity (for example fauna and flora); land
(for example land-take), soil, (for example organic matter, erosion, compaction, sealing),
water (for example hydromorphological changes, quantity and quality), air, climate (for
example greenhouse gas emissions, impacts relevant to adaption), material assets, cultural
heritage, including architectural and archaeological aspects, and landscape’
2.28 Consistent with the EIA Regulations, the identification of the aspects of the environment
likely to be significantly affected by the Proposed Development has been identified. Table
2.2 confirms the sensitive receptors (as identified across Technical Chapters 6 – 18) at which
likely significant effects may occur and their relationship to the aspects of the environment
outlined in Schedule 4.
Table 2.2: Identified Sensitive Receptors
Sensitive Receptors Relation to Schedule 4 ‘factors’
• The economy in the local impact area
(the administrative area of SBC) and the
wider impact area (comprising
Wiltshire, Cotswold, West Berkshire,
Population and human health
2.17
Sensitive Receptors Relation to Schedule 4 ‘factors’
Vale of White Horse and West
Oxfordshire);
• Construction workforce in the local and
wider impact areas;
• The workforce in the local and wider
impact areas, across all industries;
• Residential properties: Applegate
House, 1 – 2 The Marsh, Keepers
Cottage, The Chantry, Chelwood House,
Marshlea, Nether Fenn, Winchmore,
The Verne, Marshside, Saratoga, Marsh
Cottages, Dema Cottage, Farncombe;
No. 10, 35, 44, 46, 48, 50, 56, 58, 60,
62, 62a and 64 Church Road; No. 1- 17
Underdown Close, Little Orchard,
Whynot, Nethercote, Le Chalet, Lae
Dakka, Coverback; Croftdene,
Clearwell, Wynnstay, Trevenna,
Borrowdale, Thornhill, Blenheim,
Ashview, Autumn View, Springfield,
Hillside; Sharpes Farm Stables;
Underdown Farm; Kings Lane Farm;
Great Moor Leaze Farm; Receptors E1-
E12 and N1-N19 as identified in Table
13.5;
• ‘Human receptors’ within 350m of the
Site boundary, or within 50m of the
route(s) used by construction vehicles
on the public highway, up to 500m
from the Site entrance(s);
• ‘ecological receptors’ within 50m of the
Site boundary, or within 50m of the
route(s) used by construction vehicles
on the public highway, up to 500m
from the Site entrance(s);
• Local road network: The Marsh; Pack
Hill; Kite Hill; Church Road; Links 1 – 19
(as described in Chapter 12:
Transportation); Upper Wanboroughl
A419l Ham Road; The Ridgeway; and
• Current Site users.
2.18
Sensitive Receptors Relation to Schedule 4 ‘factors’
• Network of hedgerows, treelines and
scattered trees;
• Ponds and ditches;
• Bats: roosting;
• Badgers: setts;
• Great Crested Newts (terrestrial phase);
and
• Woodland, wetland, grassland, tree and
scrub habitats; and
• Plants and vegetation.
Biodiversity
N/A Land and soil
• Groundwater body;
• Water resources – Thames Valley WRZ;
• Third parties, nearby development and
construction workers; and
• Thames Water Sewer and Drainage
Network; and
• Controlled waters (groundwater and
surface water).
Water
• Climatic system. Air and climate
• Local waste treatment and disposal
facilities;
• Public Rights of Way: Footpaths within
the Site; footpaths west of The Marsh;
Footpaths between Upper
Wanborough, Lower Wanborough and
The Marsh; footbath between Purley
Road and Pack Hill; Public footpath
between Medbourne and Glebe Farm;
Liddington Hill PRoW and permissive
paths; WA5, WA6, WA7, WA8, WA21
and WA22;
• Buildings;
Landscape and material assets
2.19
Sensitive Receptors Relation to Schedule 4 ‘factors’
• Underground service infrastructure;
• North Wessex Downs AONB;
• LLCA1 – LLCA6 (as identified in Chapter
7: Landscape and Visual); and
• Users of publically accessible open
spaces (Warneage Wood and Pack Hill
Wood).
• Parish Church of St Andrew (Grade I
listed building);
• Disney Cottage (Grade II listed
building);
• The White House (Grade II listed
building);
• Upper Wanborough Conservation Area;
and
• Buried archaeological assets within and
in the immediate vicinity of the Site.
Cultural heritage
Information to Inform Assessment
2.29 As indicated in Chapter 1: Introduction, the Application is hybrid, with Phase 1 submitted in
detail and Phase 2 submitted in outline.
2.30 The Application is required to provide sufficient information about the design, size and scale
of the Proposed Development, such that SBC can reasonably be satisfied that they have
sufficient information to decide that they have full knowledge of the likely significant
environmental effects of the Proposed Development. As such, the assessments within the
EIA and presented in the ES have been based on detailed plans for Phase 1 and a ‘parameter
based approach’ based on maximum parameters shown on Figure 4.10 for Phase 2, in
conjunction with the information set out within Chapter 4: The Proposed Development. The
parameter plan approach for the outline component of the Application is based on
established methodology, the 'Rochdale Envelope' (Ref 2.4) in which the maximum
parameters proposed can be tested in the EIA to demonstrate a 'worst-case' scenario. This
approach allows for the Proposed Development to evolve within the approved parameters,
with future detailed design controlled through planning conditions.
2.31 The quantum of development, set out in detail in Chapter 4: The Proposed Development, is
an upper limit within which the Proposed Development will come forward and has been a
key parameter used to assess likely significant environmental effects for the following
disciplines:
• Chapter 6: Socio-Economics, specifically in relation to the calculation of employment;
2.20
• Chapter 12: Transportation, specifically in relation to the trip generation and modal
split (which indirectly impacts upon Chapter 13: Air Quality and Chapter 14: Noise and
Vibration, given that they include road traffic related effects);
• Chapter 16: Waste, specifically regarding calculation of waste arisings; and
• Chapter 17: Climate Change, specifically in relation to the Greenhouse Gas (GHG)
emissions assessment.
2.32 The scale and location of development are shown and defined on Figures 4.1 – 4.9 for Phase
1 and Figure 4.10 for Phase 2, as well as described in Chapter 4: The Proposed Development.
These plans (including any necessary technical study areas) have been used to asses likely
significant environmental effects for the following disciplines:
• Chapter 7: Landscape and
Visual;
• Chapter 8: Built Heritage
• Chapter 9: Archaeology;
• Chapter 10: Geology and Soils;
• Chapter 11: Water Resources,
Flood Risk and Drainage;
• Chapter 12: Transportation;
• Chapter 13: Air Quality;
• Chapter 14: Noise and
Vibration;
• Chapter 15: Lighting; and
• Chapter 16: Ecology.
Assessment Scenarios
2.33 As outlined in Chapter 4: The Proposed Development, construction will commence in 2020
with Phase 1 operational by 2021, and Phase 2 operational by 2025. The Proposed
Development will become fully operational in 2025. The assessments within Technical
Chapters 6 – 18 have therefore considered the construction and operational phase of the
Proposed Development in line with these dates.
2.34 Chapter 12: Transportation, Chapter 13: Air Quality and Chapter 14: Noise and Vibration
consider an opening year of 2026, reflecting the first full year of operation. The assessment
years have been agreed with SBC and this is considered to represent a robust and worst case
assessment. Chapters 12, 13 and 14 provide further commentary on this point.
2.35 For the landscape and visual assessment (Chapter 7), there is a need to assess addition
specific scenarios, in line with relevant technical guidance. Chapter 7: Landscape and Visual
has assessed the effects at the operational phase at the Year 1 and Year 15.
Implementation of Mitigation
2.36 Schedule 4, Paragraph 7 of the EIA Regulations states that an ES should include:
‘a description of the measures to avoid, prevent, reduce, or if possible offset any identified
significant adverse effects on the environment and, where appropriate, of any proposed
monitoring arrangements (for example the preparation of a post-project analysis). That
description should explain the extent, to which significant adverse effects on the environment
2.21
are avoided, prevented, reduced or offset, and should cover construction and operational
phases.’
2.37 In accordance with IEMA Guidance, three types of mitigation have been identified and used
within the ES, comprising;
• Primary – modifications to the location or design of the Proposed Development made
during the pre-application stage that are in inherent part of the project;
• Secondary – actions that will require further activity in order to achieve the
anticipated outcome; and
• Tertiary – actions that would occur with or without input from the EIA feeding into the
design process. These include actions that will be undertaken to meet other existing
legislative requirements, or actions that are considered to be standard practices used
to manage commonly occurring environmental effects.
2.38 The design process has been informed by extensive studies/surveys/modelling so that
potential effects are well understood and primary and tertiary mitigation has been identified
and developed. The Proposed Development has evolved to take account of the
environmental constraints and opportunities within the Site and study area.
2.39 Such evolution, as defined above, constitutes primary mitigation and therefore for the
purpose of the EIA such measures are considered as part of the Proposed Development and
therefore set out in Chapter 4: The Proposed Development.
2.40 Those measures considered to constitute tertiary mitigation are also considered part of the
Proposed Development and set out in Chapter 4: The Proposed Development.
2.41 Therefore, Technical Chapters 6 – 18 have considered relevant primary and tertiary
mitigation for both the construction and operational phases prior to undertaking their
assessment of likely significant effects. Following the conclusion of effects based on the
Proposed Development (inclusive of primary and tertiary mitigation) any further mitigation
measures or monitoring arrangements have been identified (i.e. secondary mitigation).
2.42 The primary, secondary and tertiary mitigation detailed within Technical Chapters 6 – 18 are
summarised in Chapter 20: Summary of ES and Mitigation Schedule.
Significance Criteria
2.43 The assessments within this ES reports likely significant environment effects for the
construction and operational phases of the Proposed Development.
2.44 In general, the following criteria have been taken into account when determining
significance:
• Relevant legislation;
• International, national, regional and/or local standards/guidance;
• Probability/likelihood of occurrence of likely effect;
2.22
• Geographical extent of likely effect;
• Magnitude and complexity of likely effects;
• Sensitivity/value/importance of the receptor/receiving environment;
• Duration of effect (short – up to 1 year, medium – 1 to 10 years, or long-term – over
10 years);
• Frequency and reversibility of effect (temporary/permanent); and
• Inter-relationship between effects (both cumulatively and in terms of potential effect
interactions).
2.45 The method for assessing significance of effects varies between environmental topics but in
principle is based on the environmental sensitivity (or value/importance) of an identified
receptor and the anticipated magnitude of change from the baseline conditions. Sensitivity
(or value/importance) has been reported on a scale of high, medium, low and negligible and
magnitude of change on a scale of large, medium, small and negligible.
2.46 Where a technical specific assessment methodology has been applied which uses differing
criteria, in order to align with applicable best practice or relevant guidance, the concluding
assessment of significance has been aligned with the above in order to provide continuity
across the entire EIA (especially with respect to cumulative effects) whilst aligning with
applicable guidance and best practice. This ensures that the conclusions of the different
effects can be compared during the decision making process and robustly considered within
the cumulative assessment. Where this has been applied the assessment methodology is
clearly set out within Technical Chapters 6 – 18.
2.47 In addition, a distinction has been made between direct and indirect (including secondary
effects); permanent and temporary; and positive and negative effects (reported as beneficial
or adverse within this ES). The duration of the effect is often linked to the demolition and
construction phases (i.e. 15 years and therefore long-term, albeit temporary) or operational
phase (also defined as long term, albeit permanent). Further consideration of whether the
effect is short (less than 1 year), medium (1 – 10 years) or long-term (more than 10 years has
been identified where necessary and different to the assumption provided above.
2.48 Cumulative effects have been considered as a single coordinated assessment (Chapter 19:
Assessment of Cumulative Effects).
2.49 The assignment of significance has been based on professional judgement and the matrix
below (Table 2.3) is intended to be a tool to assist with the process. Whilst the matrix
provides ranges this is to guide the competent expert and therefore a definitive level of
effect is concluded, wherever possible. A conclusion has also been provided as to whether
the effect is significant or not, again based on professional judgement.
2.23
Table 2.3: Matrix to Support Determining the Level of Effect
Sensitivity (or value / importance) M
agn
itu
de
of
Ch
ange
High Medium Low Negligible
Large Major Moderate to
Major
Minor to
Moderate
Negligible
Medium Moderate to
Major
Moderate Minor Negligible
Small Minor to
Moderate
Minor Negligible to
Minor
Negligible
Negligible Negligible Negligible Negligible Negligible
2.50 The following terms have been used to define the significance of the effects identified and
these can be ‘beneficial’ or ‘adverse’:
• Major effect: where the Proposed Development is likely to cause a considerable
change from the baseline conditions and the receptor has limited adaptability,
tolerance or recoverability or is of the highest sensitivity. This effect is considered to
be ‘Significant’;
• Moderate effect: where the Proposed Development is likely to cause either a
considerable change from the baseline conditions at a receptor which has a degree of
adaptability, tolerance or recoverability or a less than considerable change at a
receptor that has limited adaptability, tolerance or recoverability. This effect is
considered more likely to be ‘Significant’ but will be subject to professional judgement;
• Minor effect: where the Proposed Development is likely to cause a small, but
noticeable change from the baseline conditions on a receptor which has limited
adaptability, tolerance or recoverability or is of the highest sensitivity or a
considerable change from the baseline conditions at a receptor which can adapt, is
tolerant of the change or/and can recover from the change. This effect is considered
less likely to be ‘Significant’ but will be subject to professional judgement; and
• Negligible: where the Proposed Development is unlikely to cause a noticeable change
at a receptor, despite its level of sensitivity or there is a considerable change at a
receptor which is not considered sensitive to a change. This effect is ‘Not Significant’.
2.51 Technical Chapters 6 – 18 provide a summary of effects table, which outlines the effects
assessed, associated sensitive receptors, residual effects and whether the effect is significant
or not.
Limitation and Assumptions
2.52 Schedule 4, Paragraph 6 of the EIA Regulations state that an ES should include:
‘...details of difficulties (for example technical deficiencies or lack of knowledge) encountered
compiling the require information and the main uncertainties involved’
2.24
2.53 Where Technical Chapters 6 – 18 experience limitations or are based on assumptions these
have been clearly identified within the relevant chapter.
Reference List
Ref 2.1 Ministry of Housing, Communities & Local Government, Planning Practice
Guidance [Online], available at:
https://www.gov.uk/government/collections/planning-practice-guidance
(Accessed on 05.11.2019).
Ref 2.2 IEMA, Environmental Impact Assessment Guide to: Shaping Quality
Development, November, 2015.
Ref 2.3 IEMA, Environmental Impact Assessment Guide to: Delivering Quality
Development, July, 2016.
Ref 2.4 Rochdale (No. 1) - R v Rochdale MBC ex parte Tew 1999 and Rochdale (No.
2) - R v Rochdale MBC ex parte Milne 2001.