ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 1
ATV Jules Verne
Ground Processing
Cargo Physical Integration atKOUROU
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 2/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 2
ATV Jules Verne
Ground Processing
• Cargo Process
• Cargo Physical integration at S5C
• Cargo Late Access at BAF
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 3/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 3
ESAContainer of CTB
NASAContainer of CTB
Arrival at
Rochambeau airport
NASA responsible ESA responsible
Transportation to Rochambeaufrom cargo packing facilities
Transportation to Rochambeaufrom cargo packing facilities
CTB containers unload from commercial passenger aircraftand support for customs process
(supervised by NASA/ESA TPOC)
CTB containers transfer from Rochambeau to S5 storage area
using covered truck
(supervised by NASA/ESA TPOC)
CTB containers opening in S5airlock and transfer into ICC
ARIANESPACE responsibleUnder launch contract
Normal process of work
under ground processingmanagement
Transport coordinationby ESA
Ground processing team
Cargo Process
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 4/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 4
EPCU 3 - S5
S5AFILLING HALL
S5CPREPARATION HIGH BAY(S)
S5BINTEGRATION
&FILLING HALL
S5OFFICES
& OCOE ROOMSS5
TRANSFER CORRIDORS
A - 3
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 5/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 5
A - 7.2
EPCU 3 – S5
• Dry cargo are packed in CTBs
• CTBs are protected by pink poly plastic bags
• CTBs are stored in dedicated containers or boxes
Part of Expected documentation for receiving operations
•Lists of the content of each container (CTBs identificationn°)•Content of the CTBs of which the handle can be dangerousfor the people or the material
Dry cargo transport configuration
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 6/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 6
A - 7.2
EPCU 3 – S5
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 7/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 7
Cargo physical integration at S5C
ATV configuration for cargo integration
•ICC is on its container base in horizontal position
•The REPA ID (Racks Equipment Payload & AAC Integration Device) is
correctly positioned
•The internal floor is
installed
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 8/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 8
Cargo physical integration at S5C
•Necessary documentation : Cargo map
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 9/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 9
Cargo physical integration at S5C
A
AC
clos
ure
ATV
Integ
ration
Possible Dry Cargointegration
• Additional sequence:– AAC door opening
– Internal floor set-up
– cargo introduction
– internal floor removal & AAC door closure
– AAC leak test
• Following ops :– ADB, ICC CoG,..
Impact on Launch
L - 54 days (8 weeks) L - 49 days (7 weeks) Up to L - 41daysContingency case
Nominal Dry Cargo integration
• Duration: 2 days in 2 shifts (ie.1 day = 2 x 8 hours)
Possible Dry Cargo integration beforeAAC closure
Impact on Launch: max 3 days
depending on:
•overall unloading / loading duration
• Possibility of same times operations(bake out, prep. RFS & PM leak test, airrenewall, sampling,..)
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 10/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 10
BAF - Late Access
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 11/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 11
BAF - Late Access – RDS opening
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 12/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP
ATV Ground Processing Team Slide Nr 12
BAF - Late Access – dry cargo
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 13/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 13
BAF - Late Access – RDS closure
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 14/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 14
Cargo physical integration at BAF
Late Access
„Nominal“ Late Access
• Duration: 1 day in 2shifts (ie. 1 day = 2 x8 hours)
L - 6 days L - 5days
Fairing
mating
Transfe
rtoLau
nchPa d
Up to L - 1day
Degraded Late Access if mandatory
• Additional sequence:
– Disarming & fairing removal
– Late Access Cargo integration
– Back to „nominal“ sequence
Impact on Launch:
depending on:
• launcher authorities approval
Contingency case
8/7/2019 1_ATV Presentation on Cargo Processing
http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 15/15
ESTEC 12 february 2004D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 15
Launch pad
STFO switch in ZL3
Payload checks after STFO switch
Payload Battery Charge Slots0h 4h 8h 12h 16h 20h 24h
Launch Vehicle Transfer to Launch Pad
D 0D - 1