ESTEC 12 february 2004 D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 1 ATV Jules Verne Ground Processing Cargo Physical Integration at KOUROU

Upload: dhruv-prashar

Post on 08-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 1/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 1

ATV Jules Verne

Ground Processing

Cargo Physical Integration atKOUROU

Page 2: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 2/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 2

ATV Jules Verne

Ground Processing

• Cargo Process

• Cargo Physical integration at S5C

• Cargo Late Access at BAF

Page 3: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 3/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 3

ESAContainer of CTB

NASAContainer of CTB

Arrival at

Rochambeau airport

NASA responsible ESA responsible

Transportation to Rochambeaufrom cargo packing facilities

Transportation to Rochambeaufrom cargo packing facilities

CTB containers unload from commercial passenger aircraftand support for customs process

(supervised by NASA/ESA TPOC)

CTB containers transfer from Rochambeau to S5 storage area

using covered truck

(supervised by NASA/ESA TPOC)

CTB containers opening in S5airlock and transfer into ICC

ARIANESPACE responsibleUnder launch contract

Normal process of work

under ground processingmanagement

Transport coordinationby ESA

Ground processing team

Cargo Process

Page 4: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 4/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 4

EPCU 3 - S5

S5AFILLING HALL

S5CPREPARATION HIGH BAY(S)

S5BINTEGRATION

&FILLING HALL

S5OFFICES

& OCOE ROOMSS5

TRANSFER CORRIDORS

A - 3

Page 5: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 5/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 5

A - 7.2

EPCU 3 – S5

• Dry cargo are packed in CTBs

• CTBs are protected by pink poly plastic bags

• CTBs are stored in dedicated containers or boxes

Part of Expected documentation for receiving operations

•Lists of the content of each container (CTBs identificationn°)•Content of the CTBs of which the handle can be dangerousfor the people or the material

Dry cargo transport configuration

Page 6: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 6/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 6

A - 7.2

EPCU 3 – S5

Page 7: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 7/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 7

Cargo physical integration at S5C

ATV configuration for cargo integration

•ICC is on its container base in horizontal position

•The REPA ID (Racks Equipment Payload & AAC Integration Device) is

correctly positioned

•The internal floor is

installed

Page 8: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 8/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 8

Cargo physical integration at S5C

•Necessary documentation : Cargo map

Page 9: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 9/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 9

Cargo physical integration at S5C

A

AC

clos

ure

ATV

Integ

ration

Possible Dry Cargointegration

• Additional sequence:– AAC door opening

– Internal floor set-up

– cargo introduction

– internal floor removal & AAC door closure

– AAC leak test

• Following ops :– ADB, ICC CoG,..

Impact on Launch

L - 54 days (8 weeks) L - 49 days (7 weeks) Up to L - 41daysContingency case

Nominal Dry Cargo integration

• Duration: 2 days in 2 shifts (ie.1 day = 2 x 8 hours)

Possible Dry Cargo integration beforeAAC closure 

Impact on Launch: max 3 days

depending on:

•overall unloading / loading duration

• Possibility of same times operations(bake out, prep. RFS & PM leak test, airrenewall, sampling,..)

Page 10: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 10/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 10

BAF - Late Access

Page 11: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 11/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 11

BAF - Late Access – RDS opening

Page 12: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 12/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP

ATV Ground Processing Team Slide Nr 12

BAF - Late Access – dry cargo

Page 13: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 13/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 13

BAF - Late Access – RDS closure

Page 14: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 14/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 14

Cargo physical integration at BAF

Late Access

„Nominal“ Late Access

• Duration: 1 day in 2shifts (ie. 1 day = 2 x8 hours)

L - 6 days L - 5days

Fairing

mating

Transfe

rtoLau

nchPa d

Up to L - 1day

Degraded Late Access if mandatory

• Additional sequence:

– Disarming & fairing removal

– Late Access Cargo integration

– Back to „nominal“ sequence

Impact on Launch:

depending on:

• launcher authorities approval

Contingency case

Page 15: 1_ATV Presentation on Cargo Processing

8/7/2019 1_ATV Presentation on Cargo Processing

http://slidepdf.com/reader/full/1atv-presentation-on-cargo-processing 15/15

ESTEC 12 february 2004D. SIRUGUET MSM-EAP ATV Ground Processing Team Slide Nr 15

Launch pad

STFO switch in ZL3

Payload checks after STFO switch

Payload Battery Charge Slots0h 4h 8h 12h 16h 20h 24h

Launch Vehicle Transfer to Launch Pad

D 0D - 1