    Real-Time Final Effluent Ammonium & Other

    Key Parameter Monitoring

    Jo Cooper

    Product & Market Specialist

    Intellitect Water Limited

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    2/21

    Real-Time Final Effluent Ammonium & Other

    Key Parameter Monitoring

    Analysis of real data

    The monitor

    Hints and tips

    Benefits

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    3/21

    The Final Effluent (FE) Monitor

    A multi-parameter (7) monitor

    320mm in length

    Flow cell mounted

    24V DC

    Direct insertion

    Easy to fit sensors

    No sample preparation

    Flexible Real -Time Communications

    Ethernet: TCP/IP

    RS232/RS485:Modbus/SCADA

    GPRS: TCP/IP/FTPAnalogue Outputs: 0 - 2.5V

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    4/21

    The Multi-Parameter Sensors

    pH

    ORP

    Ammonium

    ISE

    Dissolved

    Oxygen

    (DO)

    Conductivity

    Turbidity

    Temperature

    36mm diameter sonde head

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    5/21

    The Ammonium ISE Sensor

    Fast and accurate measurements

    Stable measurement

    Robust

    Can be left dry for long periods

    Concentration range 020mg/l

    pH range 58

    Temperature range 0+50oC

    1 year life time

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    6/21

    Mounting of the FE Monitor in Flow Cell

    GPRS Antenna

    Inlet to Turbidity Sensors

    Inlet to Chemical Sensors

    Valves for flow

    controlOutlet

    PSU 24V DC

    FE Monitor

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    7/21

    In-Line StrainerHayward Simplex basket strainer

    Strainer basket 3.5mm mesh

    Vertical mounting

    Easy maintenance

    Larger strainers are available

    Spare Basket

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    8/21

    Strainer basket maintenance

    Wear Personal

    Protective Equipment

    (PPE)

    Clean with a water hose

    (5 minutes)

    For unmanned sites a

    drop in flow is a good

    indicator that the basketneeds cleaning

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    9/21

    Inbuilt Graphic User Interface (GUI)

    Established via an

    ethernet connection

    Real-time readings at

    a glance

    Allows an easy

    calibration (30 mins)

    Data logging

    frequency selection

    (1/min1/hr)

    Data retrieval (.dat,.xls)

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    10/21

    Heavy rainfall runoff seen in the peaks of increased

    levels of ammonium at waste water treatment site

    -

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    100.00

    0 1/ 01 /2012 31 /01/ 20 12 01/ 03 /201 2 31 /03/ 20 12 30/ 04/ 201 2 3 0/ 05/ 2012 29 /0 6/ 20 12 2 9/ 07 /2012 28 /0 8/ 20 12 27/ 09 /201 2 27 /10/ 2012

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    11/21

    Reduction in flow indicating the strainer basket is in

    need of cleaning

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0.4

    0.45

    0.5

    25/09/2012 30/09/2012 05/10/2012 10/10/2012 15/10/2012 20/10/2012 25/10/2012

    18/10: Clean strainer basket

    re-instates flow.

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    12/21

    Heavy rainfall runoff impacting on flow through to the

    FE Monitor

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    0.3

    0.35

    0.4

    0.45

    0.5

    25/09/2012 30/09/2012 05/10/2012 10/10/2012 15/10/2012 20/10/2012 25/10/2012

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    Flow Am monium

    Heavy rainfall runoff

    impacting on submersible

    pump flow through to the

    FE monitor

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    13/21

    Heavy rainfall runoff seen in the peaks of increased

    levels of ammonium at waste water treatment site

    -

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    100.00

    0 1/ 01 /2012 31 /01/ 20 12 01/ 03 /201 2 31 /03/ 20 12 30/ 04/ 201 2 3 0/ 05/ 2012 29 /0 6/ 20 12 2 9/ 07 /2012 28 /0 8/ 20 12 27/ 09 /201 2 27 /10/ 2012

    What happened

    here?

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    14/21

    Heavy rainfall runoff impacting on submersible pump

    flow through to the FE Monitor

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    23/12/201 1 12 /01 /2 012 01 /02 /20 12 2 1/ 02 /20 12 1 2/ 03/ 201 2 0 1/ 04/ 201 2 21 /04 /20 12 1 1/ 05/ 20 12 3 1/ 05/ 201 2 2 0/0 6/ 201 2 10 /07/2012

    0

    0.2

    0.4

    0.6

    0.8

    1

    1.2

    Ammonium Flow

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    15/21

    The importance of cleaning

    -

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    100.00

    29/07/2012 05/08/2012 12/08/2012 19/08/2012 26/08/2012 02/09/2012 09/09/2012 16/09/2012 23/09/2012 30/09/2012

    What happened

    here?

    17/09: Calibration of

    Ammonium after cleaning

    of the sonde head

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    16/21

    Sonde head prior to cleaning on 17/10

    http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    17/21

    An increase in ammonium also results in an increase in

    conductivity

    0

    200

    400

    600

    800

    1000

    1200

    06/02/2012 08/02/2012 10/02/2012 12/02/2012 14/02/2012 16/02/2012 18/02/2012 20/02/2012

    0

    1

    2

    3

    4

    5

    6

    7

    Conductivity Ammonium

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    18/21

    Increasing DO levels as the Ammonium levels drop

    after runoff highs

    0

    50

    100

    150

    200

    250

    300

    06/02/2012 08/02/2012 10/02/2012 12/02/2012 14/02/2012 16/02/2012 18/02/2012 20/02/2012

    0

    1

    2

    3

    4

    5

    6

    7

    DO Ammonium

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    19/21

    Other key parameters

    0

    200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    06/02/2012 08/02/2012 10/02/2012 12/02/2012 14/02/2012 16/02/2012 18/02/2012 20/02/2012

    0

    2

    4

    6

    8

    10

    12

    14

    ORP Turbidity Temperature pH Ammonium

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    20/21

    Hints and tips

    Keep the sensors clean Ensure adequate flow (25 litres/min at study site)

    Filter particles > 3.5mm via a strainer/basket

    Routine Maintenance Check basket every week

    Aim to clean the basket every 2/3 weeks (some sites may

    require a larger strainer/basket

    Clean the sonde head and sensors every 3-6 months (site

    specific)

    A drop in flow can be used as an indication that cleaning of

    the basket is required

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/
  • 8/11/2019 183 Real Time Final Effluent Monitoring

    21/21

    Benefits

    Multi-parameter Reagent free

    No sample preparation

    Easy to replace sensors

    Less frequent maintenance Ideal for unmanned sites

    Reduced overall costs compared to traditional reagentusing technologies

    Multi-parameter single source measurements to aid

    determination of inter-relationships More single source diagnostic information to guide

    preventative maintenance process improvements

    http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/http://www.intellitect-water.co.uk/