LAT Level Design StatusLAT Level Design Status

LAT Face to Face Manager’ Meeting

Nov. 3, 2004

LAT Level Design StatusLAT Level Design Status

Rob Black [email protected] Black [email protected]

2 11/3/2004

GLAST LAT Project

LAT Engineering Meeting AgendaAgenda

• Agenda– Last Month's Accomplishments

– Drawing Release Plan

– Issues and Concerns

3 11/3/2004

GLAST LAT Project

LAT Engineering Meeting Last Months AccomplishmentsLast Months Accomplishments

• Support of Mechanical Systems

– Released LAT-DS-01580, Grid Box Base Assembly

– Continued detail design efforts on MLI

– Continued documentation maintenance

• Support of DAQ

– Released Cable Way detail parts

– Continued documentation maintenance

– Instrumentation• Defined thermistor and accelerometer quantities and locations.

– Need to review with appropriate subsystems and update all documentation

• Established basic harness definitions, connector locations, pin outs etc.

• Top Assembly Documentation

– CAL-TEM Assembly Drawing submitted for release

– Reviewing Tower installation drawing with Design Integration

and I & T.

4 11/3/2004

GLAST LAT Project

LAT Engineering Meeting Drawing Release PlanDrawing Release Plan

DocumentDescription Issues

Release ECD

Need Date

LAT-DS-01624 LAT Assembly Drawing MLI design must be completed 4/30/2005 4/30/2005

LAT-DS-02561 LAT Tower & Elect Assembly Drawing Instrumentation routings defined 12/3/2004 11/1/2004

LAT-DS-02560 LAT Tower assembly drawingFinalizing instrumentation routing, TEM clocking, tracker cable bonding 11/12/2004 10/1/2004

LAT-DS-02559 CAL-TEM-PS Assembly drawingIn review cycle with changes based on NRL review 11/10/2004 10/1/2004

DocumentDescription

Pending Rev.

IssuesDrafting

ECD

LAT-DS-00309 ACD-LAT INTERFACE, IDD 04 Updates complete, waiting for comments

Submitted for review

9/22

LAT-DS-00233 CAL-LAT INTERFACE, IDD 07 Received comments from NRL 10/28

To Doc Control

11/3

LAT-DS-00040 LAT INSTRUMENT STAY CLEAR 12Update ACD envelope, Flexure clearance, MLI InterfaceWaiting for inputs from Spectrum ?

LAT-DS-00851 TRACKER-LAT INTERFACE, IDD 2  Received comments from I & T 10/28, need to resolveSubmitted 9/2

Top Level Drawings

Interface Drawings

5 11/3/2004

GLAST LAT Project

LAT Engineering Meeting Issues & ConcernsIssues & Concerns

• Timely and Appropriate review of Documents

• CAL Interface (CAL-LAT IDD LAT-DS-00233 Rev 07)

– 4 weeks to receive comments.

• ACD Interface (ACD-LAT IDD LAT-DS-00309 Rev 04)

– Check print sent out for review, 9/22, waiting for feedback

• MLI Blanket Design

– Conceptual design still in review by Spectrum

– The only feed back received since 9/7/04 is a request for additional drawing views on 10/28

– Note the additional work to provide views was not planned until conceptual design approval was given.

• Instrumentation

– Detail design of cabling over 50% complete, cooperation between subsystems is required

– Issues still open from last month• Instrumentation Termination Bracket design definition• Specific locations and mounting methods have been defined, need to be reviewed• Still need detail harness definition for accelerometers