glast lat projectnovember 17, 2004 anticoincidnce detector 1 glast large area telescope: face to...
Post on 22-Dec-2015
215 views
TRANSCRIPT
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 1
GLAST Large Area Telescope:GLAST Large Area Telescope:Face to Face MeetingNovember 17, 2004AntiCoincidence Detector (ACD) Subsystem WBS: 4.1.6
David J. ThompsonThomas E. JohnsonNASA Goddard Space Flight CenterSubsystem Manager/Instrument Manager
[email protected]@nasa.gov
Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 2
OutlineOutline
• Cost Plan – Variance Summary• Lien List• Manpower Plan• FY05 Cost/Manpower Overview• FY06 & 07 Cost/Manpower Overview• Schedule• Backup Material
– Critical Path– Descope Options– Assumptions and Risks
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 3
COST PLAN – VARIANCE SUMMARYCOST PLAN – VARIANCE SUMMARY
ACD Subsystem Estimate at Complete (EAC), ($K)
Plan at Complete (PMCS), ($K)
Variance ($K)
4.1.6.1 Management/Systems/Science 3156.3 3930.0 226.3
4.1.6.2 Safety and Mission Assurance 817.7 585.0 223.9
4.1.6.3 Tile Shell Assembly 3723.0 3552.0 181.0
4.1.6.4 Base Electronics Assembly 5598.4 5242.0 356.4
4.1.6.4 BEA (SLAC) 684 640 44
4.1.6.5 Micrometeoroid Shield/Thermal Blanket
578.2 335.0 243.2
4.1.6.6 Mech Qual & Calibration Unit 160 108.0 52.0
4.1.6.7 Integration and Test 639.0 368.0 271.0
4.1.6.8 LAT Integration and Test 66.8 36.0 30.8
4.1.6.B Ground Support Equipment 951.2 799.0 152.2
TOTAL 17,340.6 15,595.0 1745.6
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 4
Lien ListLien List
Lien Description FY05 Liens*
EGSE SW Support $60K
FY05 portion of grassroots estimate (4-04) $226K
MS/TB $113K
Reduce Efficiency verif. Test duration ($20K)
Reduce shipping time ($10K)
Schedule Delay (including 2.5 month fab phase delay) $1230.6K
Streamline conformal coating FREE boards ($4K)
SLAC ASIC variance $44K
LAT I&T Support (½ time technician) $31K
Science Support for FY05 and ½ of FY06 (Grad Student) $75K
TOTAL $1745.6K* Updated Lien list from the lien list provided by Jay Doubrava on 10/13/04
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 5
Manpower PlanManpower Plan
• The following table provides both the Contractor and Civil Servant manpower plan for FY05-FY07
• Assumptions:– ACD RFI and integration to the LAT date is 5/17/04.– ACD Support Team ramps down significantly after 5/17/04.– From July – September, 1.8 FTE’s are for Science Support and the
remaining support is for Systems Engineering and Management.
Total TotalNov Dec Jan Feb Mar Apr May Jun Jul Aug Sep FY06 FY07 FY05
CS 26.1 20.4 18.2 21.7 16.8 16.3 16.6 8.6 1.3 1.3 1.3 0.8 0.0 13.2 12.4CON. 25.6 17.7 20.1 14.6 10.5 8.6 7.7 4.0 1.5 1.0 1.0 0.7 0.2 10.3 9.4TOTAL 51.7 38.1 38.3 36.3 27.4 24.9 24.3 12.6 2.8 2.3 2.3 1.5 0.2 23.4 21.7
FY05
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 6
FY05 Cost/Manpower Overview by TaskFY05 Cost/Manpower Overview by Task
WBS Element Total Cost M&S Labor Contract FTE CS FTE
4.1.6.1 Management/Systems Eng/Science Support
519.3 144.9 374.1 2.3 2.4
4.1.6.2 Safety & Mission Assurance 222.7 6.0 216.7 2.0 0.30
4.1.6.3 Tile Shell Assembly 10.0 10.0 0 0 0
4.1.6.4 Base Electronics Assembly 349.4 83.5 265.9 2.0 2.2
4.1.6.5 Micrometeoroid Shield/Thermal Blanket
167.2 135.0 32.2 0.3 0.23
4.1.6.6 Mechanical Qual & Calibration Unit
0 0 0 0 0
4.1.6.7 Integration & Test 492.0 250.6 241.4 1.9 6.2
4.1.6.8 LAT Integration & Test Support
66.8 33.1 33.7 0.2 0.4
4.1.6.9 Mission Integration & Test 0 0 0 0 0
4.1.6.B GSE 224.2 108.6 115.6 0.8 0.8
Total 2051.6 717.0 1334.6 9.4 12.4
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 7
FY06 & 07 Cost/Manpower Overview by TaskFY06 & 07 Cost/Manpower Overview by Task
Assumptions:
•Civil Service personnel salaries are paid by Goddard, not the LAT.
•Labor consists of science support only.
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 8
InitialTDA/TSA I&T in B7
ACD SubsystemEfficiency
Verification test(include rotate
ACD 90 degree)
EMI/EMC Test
Pre-shipReview (PSR)
Vibration Test
Thermal Balance/Thermal-Vac
Test
Mass Properties ACD ship to SLAC
Pre-EnvironmentalReview (PER)
Acoustic Test
Post-shipCheckout &
Full Functional Test at SLAC
Install & test 1st & 2nd flightChassis onto
ACD
Qual Electronics
ChassisEnvironmental
Test
1st flight chassis
Environmental Acceptance
Test
The remaining Seven Flight
Chassis Environmental
Acceptance tests
10/4 – 11/30 11/25 – 12/7 12/2 – 1/11
ACD FullFunctional
Test
Install ThermalBlanket &
MMS
2/10/05
Assemble last 2 rows of
TDAs & WSF (124-130, 224-230, 324-330, 424-430)
onto TSA
ACD Integrationcomplete
12/29/04 – 1/14/05
1/14/05 – 1/25/05
6/10 – 11/19 12/7 – 12/13
Install & test remaining six
flightChassis onto
ACD
12/14 – 1/13
1/14/051/25/05 – 1/27/051/27/05 – 2/10/05
2/11/05 – 2/23/052/23/05 – 3/4/05
3/4/05 –3/10/05 3/10/05 – 4/7/05 4/7/05 – 4/8/05 4/11/05
4/12/05-4/19/05(was 3/26/05 – 4/2/05) 4/19/05 – 5/17/05
Schedule FlowSchedule Flow
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 10
ACD Critical Path - PMTsACD Critical Path - PMTsACTIVITY COMPLETION DATE
First 10 PMTs completed 11/23/04
11-34 PMTs complete 11/29/04
# 1 Dual EC Assy 12/10/04
35-69 PMTs complete 12/6/04
# 1 Single EC Assy 12/15/04
# 2 Single EC Assy 12/15/04
70-104 PMTs complete 12/13/04
#2 Dual EC Assy 12/20/04
105-139 PMTs complete 12/18/04
#3 Dual EC Assy 12/29/04
140-174 PMTs complete 12/24/04
# 3 Single EC Assy 1/5/05
#4 Single EC Assy 1/8/05
175-194 PMTs complete 1/3/04
# 4 Dual EC Assy 1/13/04
BEA Integration Complete 1/13/05
ACD Integration Complete 1/14/05
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 11
Descope OptionsDescope Options
• Perform environmental testing at the LAT Level.– The ACD Subsystem would not be fully qualified prior to
integration to the LAT. This would transfer schedule and cost risk to LAT integration.
• The following table provides the cost and schedule savings for eliminating testing at the ACD Subsystem level.
ACTIVITY DURATION (days) COST ($K)
EMI/EMC Testing 9 $50.4
Vibration Testing 13 $44.9
Acoustic Testing 8 $27.1
TVAC/Thermal Balance 33 $158.2
Mass Properties 5 $14.4
TOTAL 68 $295
GLAST LAT Project November 17, 2004
AntiCoincidnce Detector 12
COST PLAN – Assumptions and RisksCOST PLAN – Assumptions and Risks
• Assumptions– Success based plan. Rapid resolution of current technical issues (PMTs and EGSE)
is required to stay on plan.
– ACD RFI date is 5/17/04.
– Minimal support (details provided on slides 3,4,6,&7) is provided following integration of the ACD to the LAT.
• Risks– No contingency in ACD cost plan.– A later than 5/17/04 integration date to the LAT will not allow the full
planned ramp down of ACD personnel.