peer review and cdr preparation - stanford university lat project peer review & cdr preparation...
TRANSCRIPT
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 1
Peer Review and CDR Preparation
LAT Engineering MeetingDecember 17, 2002
ReferenceSEMP (LAT-MD-00066)NASA SRO – Design Review Guidelines (Section 4.3)
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 2
Preparation SchedulePreparation Schedule
• Subsystems Peer Reviews– ACD January 7-8, 2003– CAL March 17-18, 2003– Elec/DAQ/PWR/Flt SW March 19-20, 2003– TKR March 24-25, 2003– Mech March 26-27, 2003– I&T March 28, 2003
• Walk Through Review – Combined LAT IPO and GSFC Project Office chart walk
through to be performed in the week of April 8–9 • CDR
– Material available 4/18/03 for transmittal • This is 7 work days prior to review date per CDRL 306
– Review Dates 4/29 – 5/2/03 (1 month after completion of last Peer Review)
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 3
GSFC CDR GuidelineGSFC CDR Guideline
• Paragraph 4.3 from the GSFC System Review Office Guideline
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 4
Entrance & Exit CriteriaEntrance & Exit Criteria
Design StatusDesign Status
Demonstrate evolution & heritage of “Final Design”Demonstrate compliance of system performanceClosure of Actions from PDR & ∆PDRComplete ICDsFinal implementation plans– EM– Prototype– Flight Units– Spares
Complete design analysis
Fabrication StatusFabrication Status
Qualification/Environmental Test Plan and FlowGround OperationsControl methods for all safety hazards identifiedFMEAWorst case analysisFracture controlShipping environment and mode of transportation
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 5
CDR Check ListCDR Check List
• PDR – CDR Check List Comparison (reference GSFC SRO Checklist)PDR CDR Checklist Category
Closure of Action Item from Previous Reviews
Closure of Action Item from Previous Reviews
Action Item Database
Science/Technical Objectives, Requirements, General Specificaiton
Evolution & Heritage of the Final Design
Design Specifications
Performance RequiremensError budget determination Combined optical, thermal,
and mechanical budgets or total system performance
System Performance Analysis/Allocation
Weight, Power, Data rate, Commands, EMI/EMCSystem Performance budgetsInterface Requirements Interface Control Documents Design Specifications
Mechanical/structural design, analyses, and life tests
Complete design analyses Analysis/Modeling/EM Test Reports
Electrical, thermal, optical/radiometric design and analyses
Engineering Model/Breadboard Test Results and Design Margins
Software requirements and d iDesign verification, test flow and calibration/test plans
Qualification/Environmental Test Plans and Test Flow
Plans
Mission and ground system operations
Ground Operations Plans
Launch Vehicle interfaces Launch Vehicle interfaces Design Specificaitons
Parts selection, qualification, and Failure Mode and Effects Analysis plans
Reliability analyses results: FMEA, Worst Case Analysis, Fracture Control
Analysis/Modeling/EM Test Reports
Support MaterialsGround Support Equipment design
Plans for shipping containers, environmental control and mode of transportation
Support Materials
Problem Areas N/A
Schedule CMS
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 6
Breakdown of the CDR Check List for each Breakdown of the CDR Check List for each SubsystemSubsystem
Check list is designed to provide a quick look of the project readiness for CDR
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 7
CDR Check List (continued)CDR Check List (continued)
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 8
Preparation ExamplesPreparation Examples
• ACD has provided a website of their CDR preparation status• I encourage everyone to view posted material, including the
CDR Dry Run charts
http://lhea-glast.gsfc.nasa.gov/acd/cdr/index.html
• The following slides are examples for each Check List category presented in the ACD charts
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 9
Closure of Action ItemsClosure of Action Items
• Identified action items from PDR and ∆PDR• Show status and closure of NASA GSFC action items
AI# 2.Perform light yield tests and muon detection efficiency measurement of the final optical system (scintillator tiles; and fiber ribbons, connector, clear fibers, and photomultiplier tubes).
Complete – results are similar to those shown in January: with two phototubes, 0.9997 efficiency is met; with one phototube, efficiency is ~ 0.999
Light output of Fermilab tiles is good. Light losses in the optical connector and clear fibers were higher than expected. Design improvements were made to compensate for these losses.
LAT-TD-00843-D1, Design Qualification Tests for ACD TDA and Phototubes
Show results
Identify the action requested
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 10
Design SpecificationDesign Specification
• Science/technical objectives and technical budgets• Requirements & specifications metrics and flow down
– All TBX (TBD, TBA, TBS, etc…) should be removed or addressed• Drawing metrics
– Number and percent complete of major assemblies and critical component drawings
– Plans for completing the remaining drawings Parameter Requirement Expected Performance Verification
Method Detection of Charged Particles
≥ 0.9997 average detection efficiency over entire area of ACD (less for bottom row of tiles)
≥0.9997 ≥0.99 (bottom tiles)
Test and Analysis
Fast VETO signal Logic signal 200-1600 nsec after passage of charged particle
200-1600 nsec Test
PHA signal For each phototube, pulse height measurement for each Trigger Acknowledge (TACK) Below 10 MIP, precision of <0.02 MIP or 5% (whichever larger) Above 10 MIP, precision of < 1 MIP or 2% (whichever larger)
< 0.02 MIP or 5% < 1 MIP or 2%
Test and Analysis
False VETO rate - backsplash
< 20% false VETO's due to calorimeter backsplash at 300 GeV
< 20% Analysis
False VETO rate - noise < 1% gamma-ray rejection from false VETO's due to electrical noise
< 1% Analysis
High Threshold (Heavy Nuclei) Detection
Detection of highly-ionized particles (C-N-O or heavier) for calorimeter calibration.
Yes Analysis
Size Outside: 1796 x1796 x 1015 mm Inside Grid: 1574 x 1574 x 204.7 mm Inside TKR: 1515.5 x 1515.5 x 650 mm
1796 x1796 x 1015 1574 x 1574 x 204.7 1515.5 x 1515.5 x 650
Demonstrate
Mass < 228 kg 270 Demonstrate Power < 31 Watts (conditioned) 24 Demonstrate Instrument Lifetime Minimum 5 yrs > 5 yr. Analysis
Identify key requirements
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 11
Key Technical BudgetsKey Technical Budgets
Technical Resources
• ACD Mass– Allocation 235 kg– ACD detailed estimate 270 kg (15% over
PDR allocation. LAT has been notified, CR is being submitted)
• ACD Power– Allocation 31 W (conditioned)– ACD detailed estimate 14 W max
• Thermal Interface (max dissipation across ASD-LAT interface)
– Dissipation Allocation 16 W– Dissipation Estimate <14 W
• Identified technical budgets, it’s allocation from LAT System, changes since PDR
• Show allocation flow down within the subsystemItem Estimated
Mass (Kg)Calculated Mass (Kg)
Actual Mass (Kg)
Total Mass without
Margin (Kg)Mechanical Hardware
Tile Shell Assembly (TSA) 29.8004 29.8004
Shell/Base Middle & Corner Flexures 1.6000 5.9824 7.5824
Base Frame Assembly (BFA) 25.1535 0.1248 25.2783Tile Flexures 4.3900 5.0320 9.4220
Clear Fiber Cable & Fiber Ribbon Tiedowns 1.1840 0.1984 1.6800 3.0624
Shield/Blanket Attachments 0.4000 2.5840 2.9840ACD/LAT Interface Hardware 0.6000 0.6000
Uralane & Safety Cable 1.0000 1.0000
Mechanical Hardware Total 79.7295Tile Detector Assemblies
Tiles 95.3650 95.3650Tile Wrapping 7.7700 7.7700
Tile Pig Tails & Clear Fiber Cables 8.5026 3.7896 12.2922Fiber Ribbons 0.0000 1.3928 1.3928
Fiber Ribbon Wrapping 0.3472 0.3472Fiber Ribbon Pig Tails 0.1600 0.1200 0.1712 0.4512
Tile Detector Assemblies Total 117.6184Electronic Hardware
PMT Assemblies 0.2910 11.8340 12.1250Chassis Structure 13.8360 13.8360
FREE Board & PCB 6.0360 0.0000 6.0360HVBS 2.2560 2.2560
Power Distribution Board 1.7280 1.7280Bulkhead Connectors & Brackets 2.2352 1.3000 3.5352
Harnessing, Tiedowns & Fasteners 0.5000 0.3120 0.8120
Electronic Hardware Total 40.3282Thermal Hardware
Thermistors, Wiring & Tiedowns 2.3800 2.3800Micrometeoroid/Thermal Blanket 30.0800 30.0800
Thermal Hardware Total 32.4600TOTAL ACD 270.1361Show break down of
allocation within subsystem
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 12
Interface Control DocumentInterface Control Document
• ICD and IDD are completed and signed– Identify major trades to accommodate design– Remaining open issues should have closure
plan• 24 identical robust circular
connectors (38999, series 2)
• 2 circular housekeeping connectors (38999, series 2)
• Parts, pin outs, signal def, grounding all defined in ICD
DATA Products
•Channel specific charged particle VETOs
•VETO hit maps
•PHAs
•Diagnostics
•Housekeeping (thermistor output, voltage monitor output, direct to AEM)
DATA Products
•Channel specific charged particle VETOs
•VETO hit maps
•PHAs
•Diagnostics
•Housekeeping (thermistor output, voltage monitor output, direct to AEM)
FRont End Electronics(FREE) #1
HVBS Pri
HVBS Red
FREE #2
HVBS Pri
HVBS Red
FREE #12
HVBS Pri
HVBS Red
ACD ElectronicsModule (AEM)
Primary
#1
#2
#3
#12
ACD ElectronicsModule (AEM)
Secondary
#1
#2
#3
#12
Thermistors(-X, +Y, +Z)
Thermistors(+X, -Y, +Z)
ACD Base Electronics Assembly
PowerDistribution
Unit
SpacecraftInterface Unit
(TBD)
ACD-LAT ElectricalInterface
Show interfaces
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 13
Analysis/Modeling/EM ReportsAnalysis/Modeling/EM Reports• Identify analysis and modeling performed since PDR
– What are the impacts due to spacecraft/bus interface• Highlight impact to analysis due to design change• Highlight impact to design due to modeling change
Efficiency measurement setup:
M1, M2 - hardware trigger scintillators
S1, S2, S3 - software trigger scintillators
T1, and T2 - tested TDA’s
µ M1
S1
S2
T1
T2
S3
M2
Subject of the test - Fermilab made TDA prototypes (T1 and T2) equipped with clear fiber extensions and fiber-to-fiber connectors (made by GSFC)
Up to 50% of the light created in the tile, is being lost duringtransportation to the PMT
• Provide example of EM testing– Identify objective and resultsExample from ACD
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 14
Qualification/Environmental Test PlanQualification/Environmental Test Plan
• Identify qualification and environmental test to be performed in accordance to LAT Verification and Test Plan
ACD-LAT ICDRequirements and
Verification Database
ACD-LAT ICDRequirements and
Verification Database
Links between Requirements
ACD Level III and IV Requirements Database
ACD Level III and IV Requirements Database ACD Test
Databases
ACD Test DatabasesACD Allocation
Tables
ACD Allocation Tables
Development UnitPhase Design Fab Test
Engineering UnitPhase Design Fab Test
Flight UnitPhase Design Fab Test
Flight Environmental Testing
Acceptance Level
Environmental TestingQualification Level
PeerReviews
PeerReviews
Dev Unit Mods foldedinto Engineering Units
Design
RequirementsReview
Eng Unit Modsfolded into Flight
DesignSystems Eng
Pre-Fab Review
Systems EngPre-Fab Review
Leve
l of A
ssem
bly
Unit
Type
Supp
lier
Test
Lev
els
Test
Sta
tus
Mod
al S
urve
y (lo
w le
vel s
ine
surv
ey)
Stat
ic L
oads
Sine
Bur
st
Sine
Vib
ratio
n
Rand
om V
ibra
tion
Mec
hani
cal F
unct
ion
Perfo
rman
ce T
estin
g (O
ptic
al)
Acou
stic
s
Mas
s Pr
oper
ties
Inte
rface
Ver
if.
EMC/
EMI
ESD
Com
patib
ility
(Gro
undi
ng)
Mag
netic
s
Scre
enin
g Pr
oces
s
Aliv
enes
s (A
) / F
unct
iona
l (F)
/ Co
mpr
ehen
sive
(C)
Ther
mal
-Vac
uum
Cyc
le
Ther
mal
Cyc
le
Ther
mal
Bal
ance
Remarks
ACD Subsystem (Integrated ACS F GSFC Acpt X X ? X?-r X X X X X X C 4 X Acceptance LevelsSA F GSFC Acpt X ?SA D GSFC Qual X-b X X X X X 6S F GSFC Qual X-e X-e X-e X-e X X 2 ACD Structure w/mass sims, no elect or detC F TBD Par Qual X-e X-e X-e X-e X 2 ?P D GSFC Qual X-b h h h
SA F Fermilab Acpt X X X-d h X A, F-h 117 Flt TDAs SA S Fermilab Acpt X X-d 8 28 Flight SparesSA EM Fermilab Qual X X X X-d X F 6 20 TDAs
Tile Detector Assembly SA D Fermilab Qual X X X X-d 6 Functional testing code660 TDA Tiedown (Flexure) P F GSFC TBD X-c X Test bonded joint TDA Tiedown (Flexure) ? P EM GSFC Par Qual X-c X X X X X h Test bonded joint TDA Tiedown (Flexure) P D GSFC Qual X-b h Characterize flexures
C F GSFC TBD X A, F-hC EM GSFC Par Qual h X X-c X F h
WSF/Clear Fiber Connector C D GSFC Qual X ? h X X-d A? h 8-d Several development modelsC F GSFC Acpt ? X-e-c X-e-c X-e-c X-e-c X 4-c
SA EM GSFC Qual X X-? X X X X? X? F 2? Corner or one side BFA, BEA assembC D GSFC Par Qual X X-e X-e
Shield & Thermal Blanket C F GSFC X 4-c Similarity to dev. model Shield & Thermal Blanket C EM GSFC X Similarity to dev. model
C D JSC, GSF Qual 6 Characterize thermal perf., particle impactClear fiber cable assembly SA F GSFC Qual X-c X-c X A
C F GSFC TBD X-c X-c X-c X AC EM GSFC Par Qual X X-c X F 6-c
PMT/Fiber Connector C D GSFC Qual X X X-d F 8-d Several development modelsS F GSFC Acpt X-? X-? F
SA F GSFC Acpt X X X X F 2? (FREE, HVBS, PMT)SA EM GSFC Qual X X X X X F 10 (FREE, HVBS, PMT)SA D GSFC Qual F 2 (FREE, HVBS, PMT)
Electronics Chassis SA BB GSFC F mech BEA parts
Electronics Chassis Electronics Chassis
Tile Detector Assembly
WSF/Clear Fiber Connector WSF/Clear Fiber Connector
Base Frame Partial BFA & Electronics Chassis
Base Electronics Assembly Electronics Chassis
Base Frame - partial
Thermal
Item
Tile Shell Assembly Tile Shell Assembly - partial
Structural/MechanicalHardware Electrical
Shield & Thermal Blanket
PMT/Fiber Connector PMT/Fiber Connector
ACD Mech S/S (no elect or Det) Shell Shell - partial Tile Detector Assembly Tile Detector Assembly
Show Flow
TraceabilityTest & Verification
Matrix
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 15
Parts & FMEA/WCA Parts & FMEA/WCA
• Parts and qualification status • FMEA/WCA/Fracture Control
Example - Results of Qualification PMT’s acceptance test
PMT 0882 0609 0610 0879 0883 0896 0885 1088 10851 Measured Sensitivity
At 900 VAt 1000 VAt 1050 V
209480
142340491
264609879
219512
249569
283619932
148330490
59146217
247578810
2 Measured L.Y. at900V-1050V
26-28.3 21.5-23.5
22.5-26 24-27 27-28 25-29 23-24 19-23 20-21.5
3 Measured L.Y. average,(place)
27.1(2-3)
22.5(7)
24.3(5)
25.5(4)
27.5(1)
27(2-3)
23.5(6)
21(8-9)
21(8-9)
4 Measured L.Y. atsensitivity of 600channels, (place)
28(1)
24(6)
24.5(5)
25.5(4)
27.5(2)
27(3)
23.5(7)
21(8-9)
21(8-9)
5 Q.E., from Data sheet(hereafter D.S.), (place)
16.0(5-6)
16.0(5-6)
15.4(7)
16.9(2)
16.8(3)
17.6(1)
16.1(4)
15.0(9)
15.2(8)
6 Measured Gain=sens(1000V)/L.Y. average,(place)
17.7(6)
15.1(7)
25.0(2)
20.1(5)
20.7(4)
22.9(3)
14.0(8)
7.0(9)
27.5(1)
7 Gain, from Data sheet,(place)
7.91(6)
6.19(8)
10.40(2)
8.66(5)
9.11(4)
10.10(3)
6.42(7)
3.00(9)
11.44(1)
8 L.Y. average / Q.E.(D.S.) 1.69 1.41 1.58 1.51 1.64 1.53 1.46 1.40 1.389 L.Y.(600) / Q.E.(D.S.) 1.75 1.50 1.59 1.54 1.64 1.53 1.52 1.3810 Gain at 1000V/Gain D.S. 2.24 2.44 2.40 2.32 2.27 2.27 2.18 2.33 2.40
Identify status of qualification test
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 16
Peer Review Agenda
(Suggested)
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 17
Suggested Peer Review Agenda (1/3)Suggested Peer Review Agenda (1/3)
Subsystem introduction & overview– Schedule summary– Critical path analysis
Subsystem engineering– Overview - identify major subsystem and interface design changes since
∆PDR• CCB’s (approved since ∆PDR and pending)
– Requirements and budget allocation updates– Subsystem ICDs, drawings, and procedures status– Subsystem performance analysis
• Simulation updates• Design trades analysis performed• Verification matrix• Reliability results• FMEA• Worst case analysis or part stress results • Fault tree analysis or single point failure analysis results
– Subsystem technical risk assessment & mitigation plan– Engineering model assessment
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 18
Suggested Peer Review Agenda (2/3)Suggested Peer Review Agenda (2/3)
Major assemblies/elements within the subsystem– Requirement/compliance matrix – update since ∆PDR– Allocated budgets (mass, power, c.g., etc..) – updates from EM or
actual– Mechanical & electronic design changes since ∆PDR
• Performance modeling updates (structural, thermal, electronics)– Major assemblies/component
• Performance summaries– Performance prediction vs. requirement
– Engineering model test results• Test data discussion• Test result as compared to expected performance/prediction
– Design changes resulting from EM test• Qualification plan (including vibration, thermal, EMI/EMC, etc..)
– Procurement plan & Status• Identify critical component need dates vs. delivery dates• Summarize procurement contract status• EEE parts and material approval status/readiness• Long lead part requirement/procurement
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 19
Suggested Peer Review Agenda (3/3)Suggested Peer Review Agenda (3/3)
Subsystem assemblies (fabrication plan)– Assembly flow overview & facilities status– Production readiness reviews
• Performed or planned– Test plan– Test Equipment (mechanical & electrical) preparation
• MGSE and EGSE status• Rack elevation, cables, power, test adapter• Test software and scripts status
– Processes & procedures– Transportation and handling plan/procedures
• Transportation container designSubsystem product assurance– Non-conformance reporting tracking and readiness– Production travelers
GLAST LAT Project Peer Review & CDR Preparation
Document: LAT-PR-00771-04 20
ConclusionConclusion
““We are ready to proceed to subsystem fabrication”We are ready to proceed to subsystem fabrication”
Design StatusDesign Status
Demonstrate evolution & heritage of “Final Design”Demonstrate compliance of system performanceClosure of Actions from PDR & ∆PDRComplete ICDsFinal implementation plans– EM– Prototype– Flight Units– Spares
Complete design analysis
Fabrication StatusFabrication Status
Qualification/Environmental Test Plan and FlowControl methods for all safety hazards identifiedFMEAWorst case analysisFracture controlShipping environment and mode of transportation
√
√
√
√√
√
√
√
√√√√