GOES-R User Requirements Change Process

Barbara PfarrBill Mazur

Monica Todirita

GOES-R Program Systems Engineering

Page 2: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

2

GOES-R Requirements Evolution

Key Decision Points (KDP): Launch Readiness

1999 2005 2007 2014

REQUIREMENTS

B C/D

System Architecture Government and Industry Studies Phase

Program Definition &

Risk Reduction (PDRR) Phase

Acquisition and Operations (A&O) Phase

2008

NWS ORD1999

GUCMay 2001

GUCOct 2002

GUCMay 2004

GUCMay 2006

GUCJan 2008

MRD 2’2005

MRD 32007

LIRD 2007

RequirementsDocuments

GOES Users Conferences

GPRD2004

CORL

MCP2007

NASA/MOU

7120.5D

Project Plans

Level I

Level II

Level IIa

Level III / Level IIIa

Project Interface Documents & Specifications

Update TBD

UpdateTBD

ACRONYMS

CORL Consolidated Observational Requirements List MOU Memorandum of Understanding

GPRD GOES Program Requirements Document MRD Mission Requirements Document

GUC GOES Users Conference ORD Operational Requirements Document

LIRD Level I Requirements Document NWS National Weather Service

MRD 12003

Page 3: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

3

NWS Operational Requirements Document (ORD) circa. 1999

• Top Priorities Operation of sensors through eclipse and “keep-out-zones.” Resolution of imaging conflict among climatic, synoptic,

and mesoscale requirements. Improved time and space resolution for the imager sensor.

X Improved spatial coverage of the sounder sensor.

Page 4: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

4

Oth

er U

sers

National Weather Service (NWS)

Oceanic & Atmospheric Research (OAR)

National Ocean Service (NOS)

National Marine Fisheries Service (NMFS)

NOAA Marine & Aviation Operations (NMAO)

Program Planning & Integration (PPI)

NOAA Users

National Environmental Satellite, Data & Information Service (NESDIS)

Eco

syst

ems,

Wea

ther

& W

ater

, C

lim

ate,

C

om

mer

ce &

Tra

nsp

ort

atio

n

L1RD

Aerosols

PrecipitationAtmospheri

c Profiles

Ocean

Space & Solar

Clouds

Land

Requirements

Atmospheric RadianceAtmospheri

c Winds

Coastal Waters & Estuaries

Mapping Requirements To GOES-R Approved System Solutions

Spacecraft

Up

com

ing

P

rocu

re-m

ents

Instru

men

ts

Ground Segment

MRD

MRD

Instruments

Advanced Baseline Imager

(ABI)

EUVS / XRS Irradiance Sensor

(EXIS)

Solar Ultra Violet Imager (SUVI)

Space Environment In-

Situ Suite (SEISS)

Geostationary Lightning Mapper

(GLM)

Page 5: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

5

GOES-R Requirements Process During Acquisition and

Operations

• Stability and clarity of requirements critical to successful implementation;

• As costs and implementation difficulties become apparent requirement updates may be necessary;

• Challenges for the Acquisition & Operations Phase:

– As products and services become available to the current series, these “Legacy” products must be integrated into the to-be-delivered GOES-R system.

– As technologies mature and funding is made available, additional new products and services may be added.

– As National priorities change, requirements will be reviewed and updated.

Page 6: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

6

GOES-R Requirements Documents Hierarchy

Requirement Level

Baseline DocumentDocument Custodian

& Control ProcessReviewing Body Approving Body

NOAA Observing Systems

Architecture (NOSA)

Consolidated Observational

Requirements List (CORL)

NOAA Observing Systems Council (NOSC)

NOAA Observing

Systems Council (NOSC)

NOAA Executive Council (NEC)

Level IGOES-R Level I

Requirements DocumentsGOES-R Program Office

(GPO)

NOSC,NOAA PMC,

NESDIS AA/DAANOAA DUS

Level IIGOES-R

Management Control Plan

GPONESDIS AA/DAANASA/GSFC PMC

NESDIS AA, NASA/GSFC Center Director

Level IIaMission Requirements

DocumentGPO

GOES-R Operational

Requirements

Working Group (GORWG)

GPO

GOES-R SPD

Level IIIGOES-R

Project Plans GOES-R Projects GPO GOES-R SPD

Level IIIaProject Level Interface

Documents and Functional Specifications

GOES-R Projects GPO GOES-R Project Managers

Page 7: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

7

User Request forChange Process

User Request

CORL

Implement Request

Non- Level 1 and funding available

Level 1 and / or funding required

CORL Consolidated Observational Requirements List

ECRB Engineering Change Review Board

GORWG GOES-R Operational Requirements Working Group

GPO GOES-R Program Office

PMC Program Management Council

TAP Technical Advisory Panel

GORWGReview / Analysis ECRB

Review(GPO)

Scientific Analysis(TAP)

CCBDisposition /

Approval (GPO)

PMCApproval

Validation

Page 8: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

8

Example of a User Requirements Change Currently Under

Consideration

Desired Growth in the capacity for the EMWIN and LRIT Communication Services

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 9: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

9

Command and Data Acquisition StationWallops, VA

NOAASatellite Operations Facility

Suitland, MD(LRIT Source)

EMWIN CC Silver Spring, MD(EMWIN Source)

GOES NOP SeriesGOES-R Series

Combination of Emergency Managers Weather Information Network (EMWIN) and Low Rate Information Transmission (LRIT) Services

Combination of Emergency Managers Weather Information Network (EMWIN) and Low Rate Information Transmission (LRIT) Services

Separate EMWIN/LRITCombined EMWIN/LRIT

EMWIN User

EMWINUser

LRIT User

LRIT User

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 10: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

10

EMWIN and LRIT Characteristics

• Currently the two services have separate broadcasts through each GOES satellite (East and West):– EMWIN:

• 9.6Kbps FM signal, 1690.725 MHz (GOES I-M series)• 19.2 Kbps OQPSK CCSDS packetized signal, 1692.7 MHz (GOES

NOP series)• Users utilize ~1 meter antenna

– LRIT:• 128 Kbps BPSK CCSDS packetized signal, 1691.0 MHz • Users utilize ~1.2 meter antenna

• Both User communities desire greater capacity for more products

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 11: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

11

EMWIN and LRIT Concerns and Proposed Solution

• Concern about impact to cost, complexity and transition difficulties to higher data rate service

– Bandwidth available for the entire GOES-R communications requirement is limited

– Impact to Users terminals-- particularly for EMWIN• Must be very portable• Users have limited budget/resources

• Candidate GOES-R solution:– EMWIN and LRIT combined with a data rate greater than both

current services– Design the satellite to transmit sufficient power that Users can still

utilize ~1 meter antennas – Separate Virtual channels for each service--allow users to receive

the content of either or both services– With software-based receiver technology, user terminals can be

designed to receive all past and future formats with no hardware changes

LRIT I, LRIT N

EMWIN I EMWIN N

EMWIN IEMWIN NLRIT I/NEMWIN/LRIT

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 12: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

12

PROs and CONs

• BENEFITS:– Allows desired increase in throughput capacity for both services.– Allows commonality of user receive systems.– Reduces cost/complexity of Spacecraft.– Both Services retain the ability to use the same relatively small antennas with the

new higher data rate.– Reduces spectrum requirements:

• Added benefit--allows critical S/C telemetry signal to be included in the GOES frequency band.   

• CHALLENGES:– Another change for the current users. However:

• New frequencies are necessary, but the GRB broadcast requirement (31 Mbps) forces a reallocation of the L-band frequencies anyway.

• New data rates are required to satisfy User-stated growth needs.

– Transition Concerns between legacy GOES and GOES-R

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 13: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

13

User Concern Mitigation:Prototyping the

solution• The GOES-R Program plans to demonstrate a prototype very low cost

EMWIN/LRIT receiver based on “Software Defined Radio” techniques which will:– Receive both services in any GOES I-M, N-P or –R+ frequencies, data rates and

modulation types.– Receiver signal processing to be performed by a simple USB interface board in

conjunction with a standard PC. Design for a prototype interface to be provided to the User community

– Utilize GOES-R developed software--source code which would be available to the User communities.

– Anticipate demonstration of a prototype in mid-2008.

Ettus Universal Software Radio Peripheral (USRP)early prototype

clock

A/D chip

USB connectorEthernet

USB chip

FPGA

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 14: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

14

Impacts to Requirements Documentation

• The proposed solution still supports the EMWIN and LRIT services.– Therefore the Level 1 Requirements are unaffected

• The MRD defines the unique properties of EMWIN and LRIT through unique Spacecraft-to-Ground Interface Requirements Documents (IRDs).– Existing separate IRDs for EMWIN and LRIT (417-R-IRD-0004 &

417-R-IRD-0003) to be merged– A new IRD, for the combined service, is being created and will be

referenced for both service requirements

• No cost impacts are required for implementation. – Savings on the satellite communication system will fund the

development of the demonstration prototype.The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 15: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

15

Impacts to Requirements Documentation (cont.)

EMWINMRD Req ID 463

EMWINMRD Req ID 463

LRITMRD Req ID 467

LRITMRD Req ID 467

Flight Project F&PS IDs

XXX

Flight Project F&PS IDs

XXX

Ground Project F&PS

IDs XXX

Ground Project F&PS

IDs XXX

CombinedLRIT/EMWIN

IRD

End results: one spacecraft transponder, one common receive system

OldLRITIRD

OldEMWIN

IRD

OldReference

OldReference

New Reference

The Government's firm requirement will be defined in the draft solicitation

and subsequent final solicitation

Page 16: 11 GOES-R User Requirements Change Process Barbara Pfarr Bill Mazur Monica Todirita GOES-R Program Systems Engineering

16

Upcoming NOAA-sponsored Direct Read-out User

Conference

December 8-12, 2008 Miami, Florida