1 tools and methods to ensure optimum returns from reippp generation...
TRANSCRIPT
1
Tools and Methods to ensure optimumreturns from REIPPP Generation Assets
Stephen Minné
14 May 2019
2
Index• GSAMS Overview and Operating Context
• Operating Challenges
• Maintenance and Materials Implementation
• Rollout Strategy
• Outcomes
• Success Contributors
• Questions
3
Globeleq: Mission, Vision and Values
“Some 24 percent of the population of sub-Saharan Africa has access to electricity versus 40 percent in
other low income countries”.
World Bank
4Globeleq: Mission, Vision and Values
Safety is fundamental to everything we doSafety
Fulfilment
Sustainability
Unity
Excellence
IntegrityIntegrity is central to all that we do. We act with honesty, openness and transparency. We maintain the highest ethical standards. We say what we do and we do what we say.
We work to be a leader in our field. We learn from our mistakes and we seek continuous improvement. To attain excellence we ensure our people have the opportunity to reach their full potential. We strive for excellence in all that we do.
Our diversity is our strength. We are united by our purpose and shared objectives. We treat everyone with respect. Together we are stronger.
We invest for the long term in economically viable businesses that we manage to the highest safety, environmental and operational standards. We are accountable for our actions. We seek to make a positive contribution to our local communities and other stakeholders to create a sustainable business in which we can all take pride.
We aim to achieve job fulfilment. Working in an open environment enables innovation and creative business solutions. We are self-driven and self-reliant. We seek to make a difference.
Vision
Mission
Values
5,000 MW Currently 1300MW operational
5
Globeleq SAMS Multi Technology Portfolio
• Three Round 1 REIPPPP Projects
• Jeffreys Bay Wind Farm (138MW) (EC)
• De Aar Solar Power (50MW) (NC)
• Droogfontein Solar Power (50MW) (NC)
• Running since 2014
• Operated by GSAMS since 2016
6Solar Assets
De Aar Solar Power (50MW), +- 175 000 PV Panels Droogfontein Solar Power (50MW), +- 175 000 PV Panels
7
Jeffreys Bay Wind Farm
• Jeffreys Bay Wind Farm (138MW) (EC)
• 3700 hectares over 4 farms
• 60 Wind Turbines (2.3MW each)
8
Globeleq SAMS Organisational History2012 2013 2014 2015 2016 2017 2018 2019 …2034
Project construction
SAMS Asset Management
Selection of ERP
COD
Construction Warranty (External O&M Contractor)
Project Moonlight (Taking over O&M)
GSAMS O&M
Project Aurora (ISO 55000 Maturity Assessment, OSP, AM Policy, Improvement Plan)
On Key (EAMS) Implementation
System optimisation
Project life
Construction + 1 month
2 years
6 months
Project life
~3 years
12 Months
Ongoing
9
Operating Challenges (2016 to start of 2018)Maintenance Management:
• Only information captured from the Maintenance module was a WO number
• No Work Order feedback in place, no equipment history
• Equipment Register is not an accurate reflection of what is installed on the plants (poor data management)
• Work Planning and Control is non existent
• Critical equipment failures due to poor maintenance plans (Inverters, transformers)
Materials Management:
• Materials stock levels stayed the same for 3 years
• No accurate parts list and poor stock control.
• No formal storage locations at the Solar Plants
• Spare parts redundancy
10
Operating Challenges
11
Risk Analysis: Top 10 Risks-December 2017
12Implementation Plan: Set Organisational KPI (end 2017 for 2018)
• The Maintenance and Materials Foundations KPI builds on the previous work
• ISO 55000 GAP analysis (2016)
• Strategic Asset Management Plans (2016/2017)
• Asset Care Plans Development (2017)
• Standards Manual for Business Processes (2017 KPI)
• Asset Management Plans (2017 KPI)
13
Maintenance and Materials Foundations KPI• Establish and maintain appropriate storage facilities.
• Setup adequate racking, shelving and binning
• Testing of all major spares for correct function
Storage and Protection
• Define policy and guidelines regarding MRO material
• Provide guidelines for the purchasing and managing of MRO items
• Address the whole supply chain, from supplier selection, procurement, receiving, storage and care, issuing and returns
Material Management Policy
• All MRO items are listed in an electronic catalogue with set information requirements
• Include non-stock items which are purchased on a regular basis
• Provide information for a spend analysis and spare parts optimisation exercise
Material Master
• Manage the physical stock levels of all stocked MRO items against the agreed standards, including regular stock takes, accurate stock valuation and obsolescence management
Stock Control
14
Maintenance and Materials Foundations KPI• Process to purchase non-stock items, as well as to replenish stock items.
• Process to formally receive goods into the stores
• Issuing spares through a requisition on the work order
MRO Item Receiving, Issuing and Purchasing
• Equipment register, equipment type tree and equipment tree in place
• Critical equipment audited and verified, with serial numbers, manufacturers and ratings recorded
• Standardised structure followed and documented
Equipment Register
•Define tactical tasks with sufficient detail to ensure effective maintenance planning and scheduling and budgeting
•Embed new asset care plans from FMEA sessions
•Standardise maintenance plans where possible
Asset Care Plans
• Implement processes to ensure the effective execution of tactical and non-tactical work
• Planning and scheduling meetings to effectively manage work within the maintenance plan
• Incorporate the remote Monitoring Center into WPC process
Work Planning and Control
15
Storage and ProtectionRequirement to Complete
• The physical stores are up and running and have standardized systems.
• All equipment / spares need to be held in stores and stores with stores management processes in place.
• Standardised racking and shelving across all three sites, with each spare part location reflective in the materials
management system
Risks• Spares were stored outdoors without adequate
protection• Spares were not properly maintained and could
potentially not function should they be placed in operation
• Extended plant outage due to inadequately managed spares
Challenges• Warehouses, racking and shelving were non existent
(Solar's)• Spares required to be catalogued, investigated, tested
to understand storage requirements• No set standard for spares storage
16
Storage and Protection: Building StoresEstablish a Storage Location Numbering System:
<Site code><Warehouse Code>-<Bay Nr><Rack Nr>/<Bin Nr>
• <Site code>:
• DA – De Aar
• DF – Droogfontein
• JB – Jbay
• <Warehouse code>:
• WH – Warehouse
• ES – Electrical Stores
• WS – Workshop
• PS – PPE Store
• YD – Yard
• CT - Container
• <Bay Nr>:
• Alphabetical numbering of Bays
Stores, racking and shelving coding convention applicable to all sites
17
Storage and Protection: Process
Moving and cataloguing all spares into the warehouse
Creating a comprehensive codification methodology for all parts
18
Storage and Protection: EvidenceStorage and Protection:
Solar's: Indoor Switchgear moved into the warehouse, followed by a comprehensive functionality test
Jbay: Spare Transformer Bund and clearly labelled main warehouse
19
Storage and Protection: Outcome• Standardised storage management system
•All stores have appropriate racking and shelving installed
•Spares taken out of containers placed in store
•Racking and binning system developed
•Store floors marked
•Spares that were kept outside were brought in and tested
•All spares accounted for and consolidated
• Improved health and safety due to correctly stored spares (reduced fire exposure, snakes)
•Critical equipment now tested and maintained
•Proper storage of spare transformers
20
Materials MasterRequirement to Complete
• A complete and controlled materials master exists for all assets within On Key• Materials Master to cover the following basic data GSAMS Unique Code, Description, Alternative Description,
Preferred Supplier, Supplier Part, Number, Manufacturer, Manufacturer Part Number, Part Rating, Re-order Level, Maximum Quantity and Commodity Code
• Controls in place to manage materials master centrally
Risks• No up to date record of inventory existed• Spare Parts were not catalogued so sites could order
incorrect spares• No historic history and set standards in place• No way to identify spares through the use of a system• Extended downtime due to inadequate spares
management
Challenges• Spare parts were kept all over the plant, the majority in
containers• Lack of datasheets or drawings to identify spares• Lack of technical knowledge of spares and where they
are used• Initially did not have a functioning system to house the
materials master
21
Materials Master: Process
• Start with technical drawings and spare parts bill of materials
• Confirm/Add to list as parts are brought into the store
• Document bin locations of each and every part
• Google helps for part information
22
Materials Master: Evidence• Criteria Covered in Materials Master:
• GSAMS Unique Code
• Description
• Alternative Description
• Preferred Supplier
• Supplier Part Number
• Manufacturer
• Manufacturer Part Number
• Part Rating
• Stock Item
• Re-order Level
• Maximum Quantity
Code DescriptionAlternative Description
Preferred Supplier
Supplier Part Number Manufacturer
Manufacturer part Number
GSA0000001 Solar Module, 295W Class I1 SUNTECH STP295-24/Vd Suntech STP295-24/Vd
GSA0000002 Solar Module, 295W Class I2 SUNTECH STP295-24/Vd Suntech STP295-24/Vd
GSA0000003 Solar Module, 295W Class I3 SUNTECH STP295-24/Vd Suntech STP295-24/Vd
GSA0000004 Solar Module, 290W Class I1 SUNTECH STP290-24/Vd Suntech STP290-24/Vd
GSA0000005 Solar Module, 290W Class I2 SUNTECH STP290-24/Vd Suntech STP290-24/Vd
GSA0000006 Solar Module, 290W Class I3 SUNTECH STP290-24/Vd Suntech STP290-24/Vd
GSA0000007 Solar Module, 305W Class I1 SUNTECH STP305-24/Ve Suntech STP305-24/Ve
GSA0000008 Solar Module, 305W Class I2 SUNTECH STP305-24/Ve Suntech STP305-24/Ve
GSA0000009 Solar Module, 305W Class I3 SUNTECH STP305-24/Ve Suntech STP305-24/Ve
GSA0000010Module Junction Box, For STP295/290, 105 X 80 Large SUNTECH ZH011-1Aa4Z110110 Suntech ZH011-1Aa4Z110110
GSA0000011Module Junction Box, For STP295/290, 75 X 75 Small SUNTECH BOX26JAa4BT110110 Suntech
BOX26JAa4BT110110
GSA0000012 Array Junction Box, Complete 5 String input SIEMENS AJB-5-63Phambili Interface AJB-5-63
GSA0000013Terminal, Feed-Through, Screw Connection, Dark Beige WDU 10
PHAMBILI INTERFACE 1020300000 Weidmuller 1020300000
GSA0000014 Terminal, Fused, Screw Connection, W-Series WSI 25/1 10x38 1KVPHAMBILI INTERFACE 1137790000 Weidmuller 1137790000
GSA0000015 Fuse, PV, 20A, DC 1000VPHAMBILI INTERFACE 1224950000 Weidmuller 1224950000
GSA0000016 Isolator, DC, 63A, DC 1000V 4 Pole SIEMENS 5TE2515-1 Siemens 5TE2515-1
GSA0000017Terminal, Feed-Through, Screw Connection, 120mm2 WDU 95N/120N
PHAMBILI INTERFACE 1820550000 Weidmuller 1820550000
GSA0000018Terminal, Feed-Through, Screw Connection, 35mm2 WDU 35N
PHAMBILI INTERFACE 1040400000 Weidmuller 1040400000
GSA0000019Voltage Surge Arrester, Low Voltage, Without Telecomm., With Aux Contact VPU II 3 PV 1000V DC
PHAMBILI INTERFACE 1351270000 Weidmuller 1351270000
23
Materials Master: Outcome
• 1735 individual items catalogued in the materials master
• 1440 viewed as stock items to be kept on site
• 176 Suppliers Identified• Globeleq ‘GSA’ numbers assigned to each
part• Centrally managed with processes in place
to add any new approved parts to the materials master
24
MRO Item Receiving, Issuing and PurchasingRequirement to Complete
• Goods receiving processes in place.• Stock issuing processes in place.• Business processes related to issuing and receiving of spares implemented as per the standards manual• Process to manage Interface between Ellipse and On-Key developed and implemented
Risks• Items not correctly received or issued will negatively
effect the financial reporting• Correctly recording what spares are used against a
work order allows one to track what has been put into operation
• Financial loss due to theft
Challenges• Effectively implementing a process that governs these
transactions• This required an interaction between our ERP and On
Key• Linking the spares to the maintenance activities
25
MRO Item Receiving and Issuing: Evidence • Formal process of raising a requisition
against a Work Order to issue any spare out of the warehouse in now in place
• This allows GSAMS to track the material cost of any job, as well as determine when spares need to be replenished.
List of requisitions created by technicians for spares used against a work order.
On Key go-live training where the Solar Technicians trial creating a requisition
Requisition Number Status Work Order Requester Requested On Total Cost
REQ243 Awaiting Approval R01517 Pieter Botha 12-12-18 6:04 12300
REQ241 Closed R01357 Pieter Botha 05-12-18 10:51 19203.6
REQ240 Closed R01254 Sulana De Jager 21-11-18 13:24 2004
REQ238 Closed R00924 Nico Lombard 14-11-18 9:00 56631.62
REQ237 Closed R00924 Nico Lombard 14-11-18 8:48 64800
REQ221 Closed IP50 Sulana De Jager 13-11-18 10:47 35.91
REQ220 Closed IP40 Sulana De Jager 13-11-18 10:41 35.91
REQ219 Closed IP30 Sulana De Jager 13-11-18 10:39 35.91
REQ218 Closed IP20 Sulana De Jager 13-11-18 10:36 35.91
REQ217 Closed IP10 Sulana De Jager 13-11-18 10:24 35.91
26
MRO Item Purchasing: Evidence• The process for purchasing spares
was designed so as to cater for both the ERP and On Key
• This allows GSAMS to track the material cost of any job, as well as determine when spares need to be replenished.
27
MRO Item Receiving, Issuing and Purchasing: Outcome
• For the first time we are able to track what spares have been received into the store as well as where they have been placed
• We are also able to record the financial cost of a job that required a spare
• Spare parts reporting to assist with improvement initiatives
• Increased transparency between spares movement
• Standardised processes that can be replicated at other plants
28
Stock ControlRequirement to Complete
• Quarterly stock-take processes in place once the materials masters are complete and spares is in the physical stores.
• Stock takes to achieve at least a 90% accuracy rate on the last stock take.• All stock takes to be performed in On Key
Risks• Financial loss to theft• Inaccurate financial reporting• Extended plant outage due to incorrect spares on hand• Failure to control what spares are used on the plant,
which spares are procured
Challenges• Effective stock takes require a physical store, materials
master and stock list of what items are on site and where they are kept, without this, stock takes were not possible
• Trained staff to perform stock takes• The time taken to perform stock takes• Controlling stock takes/over inspecting work done
29
Stock Control: Process
Stock Take training and execution in line with the stock take process
30
Stock Control: Outcome
• Just over R28 000 000 of spares accounted for
• 4 full stock takes were completed
• Stock Accuracy of above 90% was achieved during the last Stock Takes
• Time to conduct stock take reduced from 5 days to 1 day
• Financial transparency for spare parts movement
Record of stock takes done in On Key to date, 2 more stock takes were also done in the Excel Templates prior to the On Key go-live
R10 010 020
R11 128 805
R7 290 447
Spare Parts Value
De Aar Droogfontein Jbay
31
Equipment RegisterRequirement to Complete
• All key physical assets installed in plant were physically audited and recorded using serial numbers• Equipment register, equipment type tree completed in a well structured layout• Critical Rotable Assets being managed through the asset tree, using serial numbers and storage locations
Risks• An inaccurate equipment register does not allow for
accurate maintenance reporting and history• Inability to generate proper maintenance plans or give
accurate feedback• Limits criticality analysis• This is the foundation of any maintenance system
Challenges• Align new equipment register to defined standards• Perform the equipment identification of all equipment
on site• Defining key equipment types• Mobilising teams to perform the verification and
identification• Lack of accurate technical drawings
32Equipment Register: Process
• The process of building a detailed, structured Equipment Register started in March 2018 and was completed in August 2018 for all 3 sites
• This was in alignment to the defined standards relating to the codification and structure.
• The Identification and Verification Process to record Serial Numbers and Equipment specific Classifications was a major part of closing completing the task
33
Equipment Register: Outcome
Snapshot of Jbay Asset Tree
Roughly 3000 Assets per plant, 2900 being Maintenance Significant Items
Critical Rotable Assets being managed through the asset tree, using serial numbers and storage locations
34
Asset Care PlansRequirement to Complete
• Maintenance plans for all plants to be in FMEA format with all associated procedures identified and developed.
• All procedures required to perform maintenance tasks to be completed.
• Maintenance plans to be uploaded into EAMS once the system is implemented.
Risks• Ageing equipment requires updated maintenance plans
to deal with new faults• Ineffective OEM manuals• Lack of standardisation for common equipment• No proper way of tracking what maintenance is done
Challenges• Developing new asset care plans following the FMEA
methodology • Embedding asset care plans in a functioning
maintenance system• Standardising asset care plans across plants where
possible• Linking monitoring points, meters and work flows to
maintenance tasks
35
Asset Care Plans: Process• This was a three part exercise to embed the asset care
plans in On Key.
• The first step was to run FMEA sessions to determine the equipment type criticality, followed by the failure modes discussion as well as defining what preventive measures could be performed
• Next we consolidated all the existing OEM inspections and embedded this into On Key
• Lastly we had to test, implement and activate the plans to generate on an ongoing set frequency
FMEA Sessions for both Solar and Wind
36
Asset Care Plans: From Boardroom to Operational
• The Asset Care Plans Configured in On Key have been done in a complex, highly mature manner
• Monitoring Points linked to upper and lower bounds that will trigger alarms, meter readings and structured sequencing was all taken into consideration
Snapshot of the solar table asset care plan that will be rolled out to all tables on the plants
37
Asset Care Plans: Outcome
• For the first time we are able to generate Preventive Maintenance Work Orders that are system generated. We also have a annual view of the long term maintenance plan
• Following a structured FMEA process, we have custom developed maintenance plans and tactic for our equipment
• We now have a way of reporting on the completion progress of the maintenance plan
• This has shifted the focus from a reactive state of maintenance to a proactive, preventive mindset
38
Work Planning and ControlRequirement to Complete
• Work orders to be centrally generated by the Remote Operations Center
• Tactical and Non-Tactical work orders to be completed by allocated persons, all feedback to be closed on the tablet (paperless) with failure analysis compulsory for all corrective work
• Spares to be linked to work orders through requisitions
Risks• No maintenance or materials asset history• Work order feedback not in place• HSE risk with no formal transparency of work
happening on site• No standardised way of working
Challenges• Shift from a paper based system to a mobile solution• Implementing formal planning and scheduling
meetings• Quality of work order feedback
39
Work Planning and Control: Evidence
2080
1993
907
Work Orders: September 2018 - April 2019
De Aar Droogfontein Jbay
Over 6385hours of work captured in 8 months
5080 work orders created date
40
Work Planning and Control: Evidence
Top 10 failures by location Top 10 failures by component
Top 10 failures by Asset Top 10 failures by Repair Type
41
Work Planning and Control: Outcome
Effective execution of maintenance plan, ensuring the:• Correct people are available when needed• Spare parts availability• Quality feedback of work is provided• Reduced backlog of work
Transformer replacements and PV Module Health ProgrammeTesting, Repair and Replacement
42
Summary• Asset management maturity improved from firefighting (level 0/1) to preventive (level
3) in a few of the key enabler areas of the business such as asset care plans, materialsmanagement, work planning and control, focused improvement and technicalinformation.
• Key business risks have been mitigated
• The organisation has again made leaps and bounds within its maintenance andmaterial management capabilities
• The KPI achieved its key dual objective - in moving the organisation forward related toits key enablers and ISO 55000 maturity
• This was a organisation wide process that required – “the coordinated activity of theorganisation to realise value from its assets”
43Thank you, Questions?