1 ohio department of transportation michael miller, auditor division of finance & forecasting...
TRANSCRIPT
1
Ohio Department of Transportation
Michael Miller, AuditorDivision of Finance & Forecasting
Division of Finance & Forecasting Office of Audits
Rural Transit Roundtable
July 31, 2008
2
Office of AuditsTransit System Financial Audits• Oversight Role & Responsibility• Financial Integrity• Common Financial Audit Findings
Office of Transit• Data Reporting Compliance Review
Rural Transit Roundtable July 31, 2008
3
Oversight Role & Responsibility
• The Federal Transit Administration (FTA) is the grantor agency for the 49 U.S.C. Section 5311 Program a.k.a. Rural Transit Program
• ODOT is the Ohio grantee of the Rural Transit Program funds.
Rural Transit Roundtable July 31, 2008
4
Oversight Role & Responsibility
• Broadly defined, it is ODOT’s responsibility as the grantee to:– Provide financial stewardship to ensure federal
and state funds awarded to sub-grantees are used appropriately.
– Ensure costs submitted by sub-grantees comply with federal and state policies, procedures, rules, regulations, and principles.
Rural Transit Roundtable July 31, 2008
5
Oversight Role & Responsibility
– It is ultimately ODOT’s responsibility to ensure that the Ohio Rural Transit Program is reliable and accountable to the citizens of Ohio.
Ensure Prudent Use of Tax Dollars
Rural Transit Roundtable July 31, 2008
6
Financial Integrity
• Office of Transit partners with Office of Audits to conduct sub-grantee audits
• Office of Transit selects sub-grantees for audit based on combination of risk factors including:– Revenue received (federal/state sources)– Staff Turnover - key positions– Length of time since last audit– On-going issues/failure to address– Current issues
Rural Transit Roundtable July 31, 2008
7
Financial IntegrityOffice of Audits has performed financial audits of 8 rural transit systems
• City of Ashland
• Delaware County Transit Board
• City of Lancaster
• Tri-County CAC (Logan County)
• City of Marion
• City of Athens
• City of Chillicothe
• WSOS/TRIPS (Sandusky County)
Rural Transit Roundtable July 31, 2008
8
Financial Integrity• Audit consisted of 3 – 4 days on-site to test and confirm:– Compliance with OMB Circular A-87, Cost Principles for
State, Local and Indian Tribal Governments.
– Compliance with OMB Circular A-122, Cost Principles for Non-Profit Organizations
– Compliance with 49 CFR 18 – Uniform Administrative Requirements for Grants and Cooperative Agreements to States and Local Governments
Rural Transit Roundtable July 31, 2008
9
Financial Integrity• Audit consisted of 3 – 4 days on-site to test and confirm:– Compliance with ODOT’s Rural Transit Program
Requirements
– Compliance with the transit systems own policies and procedures.
– Ability to trace costs claimed on invoices to the entity’s financial accounting system.
Rural Transit Roundtable July 31, 2008
10
Financial Integrity
• Audit focused on:– Allowable, allocable and reasonable costs.– Ability of transit system to properly segregate direct and
indirect costs.– Appropriate and adequate Internal Controls.– Compliance with terms of ODOT contract.– Compliance with Generally Accepted Accounting
Principles (GAAP).
Rural Transit Roundtable July 31, 2008
11
Common Audit FindingsNon-Compliance Determined
• Unsupported or Inaccurate Costs.
• Ineligible Expenses.
• Failure of Internal Controls.
• Duplicate Costs.
• Non-compliance with Rural Transit Program Requirements.
• Inability to reconcile financial data reported on the 4th quarter operating invoice to the general ledger.
• Failure to comply with Ohio Revised Code §9.38 Timely Deposit of Public Funds.
Rural Transit Roundtable July 31, 2008
12
Office of Transit Data Reporting Compliance Review• Conducted by ODOT Transit Rep. in Conjunction with Financial
Audit• Compliance Review Purpose– Verify use of correct data definitions– Review data collection process
• Compliance Review Process– Desk review to prepare for on-site phase– Conduct on-site review process to include
• Testing of selected records and reports• Interviews with front line transit system staff
– Office of Transit issues report
Rural Transit Roundtable July 31, 2008
13
Office of Transit Data Reporting Compliance Review• Compliance Review Report Follow-up– If non-compliance is determined the report will document
required process improvements – ODOT Transit Rep. will work with transit system to develop
implementation schedule for required process improvements
– ODOT Transit Rep. will conduct follow-up with transit system to ensure continued compliance with Rural Transit Program requirements
• Questions regarding the Data Reporting Compliance Review process should be directed to ODOT Transit Rep. or Transit ManagerRural Transit Roundtable July 31, 2008
14
ODOT Office of AuditsContact Information
Michael Miller, Auditor(614) 466-0588
Jana Cassidy, Administrator(614) 644-7892
http://www.dot.state.oh.us/finance/TransitsMaterials.asp
Rural Transit Roundtable July 31, 2008
15
Questions?
Rural Transit Roundtable July 31, 2008