1 4. flow-time analysis inventory adversely affects all competing edges (p/q/v/d) has cost ...
TRANSCRIPT
1
4. Flow-Time Analysis
Inventory adversely affects all competing edges (P/Q/V/D)Has cost
Physical carrying costs Financial costs
Causes obsolescence Due to market changes Due to technology changes
Leads to poor quality Feed back loop is long
Hides problems Unreliable suppliers. High defect rate, tools changeover times, machine
breakdowns.Causes long flow time
Lean Operations: The Real Cost of Inventory
2
4. Flow-Time Analysis
Flow-Time Analysis
Competitive Advantages of a shorter flow time
Shorter response time (both in production and product design)
Delayed differentiation (Postponement)
Lower inventory costs (due to Little’s Law)
3
4. Flow-Time Analysis
Direct Methods of Measuring Flow Time
Direct Method
Observe a process over an extended, specified period of time
Randomly sample flow units over the observation period
Measure the flow time for each flow unit from entry to exit
Compute the average of flow times measured
Example During a given month, a sample of 50 applications was taken The average flow time = 20.85 working days
4
4. Flow-Time Analysis
Indirect Methods of Measuring Flow Time
Indirect Method
Count the number of units produced over an extended period of time
R = number of units produced / duration of time period
Count the number of units of inventory at random points during the time period, and compute the average inventory (I).
Compute T =I/R
Example 200 applications processed during a given month, 20 days of operation
during the given month. Throughput for the sample is R=200/20 = 10 applications per day.
After counting the number of applications at 4 random points during the
month, the average inventory (I) was 215.
T=I/R T = 215/10 flow time is 21.5 days
5
4. Flow-Time Analysis
Process = network of activities performed by resources
1. Flow unit: The unit of analysis– Level of detail
2-3. Network of Activities & Storage/Buffers
Define Process Boundaries
Activities with activity times
Buffers with waiting flow times
Routes: precedence relationships (solid lines) with throughputs
4. Resources & Allocation
- Who does what?
5. Information Structure & flow (dashed lines)
Key for capacity analysis
Process Flow Chart
6
4. Flow-Time Analysis
Flowcharting
ActivityBuffer
Physical flowEvent
Information flow- See the total process; a systems view
- Define flow units and process boundaries
- Include only the key steps
- Clarify the level of detail needed. Processes can be broken down into sub-activities. On the other hand, cascading allows several activities to be combined in a single sub-process
- Depicts resources required to carry out activities
- Identify the processes that need attention (weak points)
Decision
7
4. Flow-Time Analysis
Wondershed Inc: Narrative Representation
Required activities :
1. Separate the roof and the base sheets
2. Punch the base
3. Punch the roof
4. Form the base
4. Form the roof
6. Sub-assemble the base
7. Assemble
8. Inspect
8
4. Flow-Time Analysis
End
Wondershed Inc. : Schematic Representation
StartSeparate
Sheet
Punch base
Punch roof
Form base
Form roof
Sub assemble base
InspectAssemble
StartActivity
AActivity
BActivity
CEnd
9
4. Flow-Time Analysis
Theoretical Flow Time
Theoretical Flow Time: The minimum amount of time required for
processing a typical flow unit without any waiting
Entry Buffer Activity Exit
Activity Time: The time required by a typical flow unit to complete
the activity once. Unless stated otherwise, we assume that an activity
can not be broken down into smaller activities that can be executed in
parallel. What does that mean???
10
4. Flow-Time Analysis
Critical Path
Theoretical flow time of each path in the process flowchart
= sum of the activity times of all activities on that path
Critical Path: the longest path
Critical Activities: activities that lie on the critical path
The theoretical flow time of the process = the time of the theoretical critical path
Activity Time 2Activity Time 1 Activity Time 3
Activity Time 5Activity Time 4 Activity Time 6
Sequential Activities
Sequential Activities
Parallel Activities
How many Paths?
Activity Time 2Activity Time 1 Activity Time 3
Activity Time 2Activity Time 1 Activity Time 3
11
4. Flow-Time Analysis
Wondershed Inc. Theoretical Flow Time
Path 1 (roof) Start 1 3 5 7 8 End = 80 minutes
Path 2 (base) Start 1 2 4 6 7 8 End = 90 minutes
Activity Times at Wonder Shed Inc.
Activity
Activity Time (minutes)
1 Separate 10
2 Punch the base 25
3 Punch the roof 20
4 Form the base 5
5 Form the roof 10
6 Subassemble the base 10
7 Assemble 108 Inspect 30
12
4. Flow-Time Analysis
Average Wait Time, Average Flow Time
Average waiting time for roof
T = I / R = 80 / 16.5 = 4.85 hours or
291 minutes
Average waiting time for base
T = I / R = 90 / 16.5 = 5.45 hours or
327 minutes
Theoretical flow times
Roof 80 minutes
Base 90 minutes
Flow Times
Roof 291 + 80 = 371 minutes
Base 327 + 90 = 417 minutes
Buffer
Average number of
bases
Average number of
roofs
2 30 -3 - 254 10 -5 - 206 20 -7 10 158 20 20
Total 90 80
16.5 sheds average flow rate (R) per hour based on empirical data
13
4. Flow-Time Analysis
Value-adding vs. Non-value-adding activities
Value-adding activities are those activities that increase the value
of a flow units Example: assembly, surgery, piloting an airplane, etc.
Non value adding activities are activities that do not directly
increase the value of a flow unit. Re-work Transport Inspection Waiting
Flow time = Value-adding times + Non-value-adding times
14
4. Flow-Time Analysis
Activity Time, Number of Visits and Work Content
Activity time is time required by a typical flow unit to complete the activity once.
Sometimes we may need to repeat an activity, i.e. the number of visits is not necessarily 1.
Work content = Activity time × Average number of visits
Theoretical flow time is computed based on work content not based on Activity time
16
4. Flow-Time Analysis
Theoretical Flow Time vs. Flow Time
(minutes)Roof Base Critical Path
Activity time 80 90 90
Wait time 291 327
Total time 371 417 417Work Content 90 105 105
Wait time 291 327
Total Time 381 432 432
Flow PathTheoretical flow time = 90
Flow time = 432
Flow Time Efficiency = Theoretical Flow Time / Flow Time
Flow Time Efficiency = 105/432 = 24%
17
4. Flow-Time Analysis
Industry Process Average Flow Time
Theoretical Flow Time
Flow Time Efficiency
Life Insurance New Policy Application
72 hrs. 7 min. 0.16%
Consumer Packaging New Graphic Design
18 days 2 hrs. 0.14%
Commercial Bank Consumer Loan
24 hrs. 34 min. 2.36%
Hospital Patient Billing 10 days 3 hrs. 3.75%
Automobile Manufacture
Financial Closing
11 days 5 hrs 5.60%
Flow Time Efficiencies in White Collar Processes
18
4. Flow-Time Analysis
Reducing Theoretical Flow Time: Shorten the Length of Every Critical Path by 3 Basic Approaches
Eliminate: Reducing the work content of critical activities
Work smarter: Eliminate non-value-adding aspects of the activity:
Work Faster: Increase the speed at which the activity is performed, e.g.
Better Methods, Training, Advanced Technology, Better Management.
Work right in the first time: Reduce repetitions of the activity
Work in parallel: Moving work off the critical path
Move work off the critical path to a noncritical activity
Move work off the critical path to the outer loop (pre- or post-processing)
Select: Modify the product mix
Make more of a product that requires less processing time reduce overall
flow time (Given market condition)
19
4. Flow-Time Analysis
Levers for Managing Theoretical Flow Time
Introductory client/adviser
meeting
Paraplanner-adviser meeting
Paraplannerprepares financial
plan
All thenecessaryinformation
obtained formthe client?
Advancedplanningrequired?
No Yes
Yes
No
Advancedplanning
professionals-adviser meeting
AdvancedFinancial plan
completed
Client takes theplan home to
review
Client/Advisermeeting to go over
the plan
Clientsatisfied?
Client/Advisermeeting to signand finalize the
plan
Yes No
Old Process,1.5 months
New Process,2 weeks
Introductory meeting client. Adviser/Paraplanner/Advanced Planning
Professionals
Financial plan completed and mailedto client
Client/Adviser/Paraplanner meetingto sign and finalize the plan
- Move work to the outer loop (pre-meeting “homework”)
- Work in parallel (professionals work simultaneously)
- Elimination of non-value-adding work(only two meetings)
20
4. Flow-Time Analysis
Critical Path Method: The Network
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
Find the Critical Path.
21
4. Flow-Time Analysis
Critical Path Method: Paths
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
10
Critical Path is the longest Path
11 8
How many path?
22
4. Flow-Time Analysis
Forward Path; Earliest Starts
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S0
0
0
0
0
0
4
3
3
4
4
3
4
4
3
4
4 10
8
5
5
5
8 8
10 10
8 11
11
1111
24
4. Flow-Time Analysis
Backward Path; Latest Starts
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S0
0
0
0
0
0
4
3
3
4
4
3
4
4
3
4
4 10
8
5
5
5
8 8
10 10
8 11
1111
1111
11
11
11
11555
88
8
8
8
8
8
4
6
4
4
66
633
3
40
0
0 11
11
26
4. Flow-Time Analysis
Activity Slack
Slack, or float: The amount of time a noncritical task can be
delayed without delaying the project
Slack—LFT – EFT or LST – EST
EST—Earliest Start Time; Largest EFT of all predecessors
EFT—Earliest Finish Time; EST + duration for this task
LFT—Latest Finish Time; Smallest LST of following tasks
LST—Latest Start Time; LFT – duration for this task
04/18/23 Ardavan Asef-Vaziri 5-1-26
27
4. Flow-Time Analysis
Critical Path, Slacks
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
0
0
4
3 3
4
4 10
8
5
8 11
11
11115
88
8
4
663
40
11
28
4. Flow-Time Analysis
Theoretical Critical Path vs. Critical Path
A1 A3
A4 A6
A5A2
4
3
6
4
2
3
E
S
W1
W2
W4
W3
W6
W7
W5
W9
W8
The time of the critical path differs from the time of the theoretical critical path. Why?
The critical path itself also may differ from the theoretical critical path. Why?
29
4. Flow-Time Analysis
Practice: Draw the Network of Activities
Task Pred. Dur. Task Pred. Dur.
a -- 4 g c,d 1
b -- 3 h e 4
c a 3 i f 5
d a 2 j e,g 6
e b 6 k h,i 1
f b 4
For each task, compute ES, EF, LF, LS, slack
04/18/23 Ardavan Asef-Vaziri 5-1-29