0986 m groundwater impact assessment peer review

17
APPENDIX Addendum - Peer Review of the Maules Creek Coal Project Groundwater Impact Assessment M

Upload: others

Post on 10-May-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 0986 M Groundwater Impact Assessment Peer Review

APPENDIX

Addendum - Peer Review of the Maules Creek Coal Project Groundwater Impact Assessment

M

Page 2: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

M Groundwater Impact Assessment

HERITAGE COMPUTING REPORT

PEER REVIEW OF THE MAULES CREEK COAL PROJECT GROUNDWATER IMPACT

ASSESSMENT

FOR

ASTON RESOURCES LIMITED

By

Dr N. P. Merrick

Report Number: HC2011/3 Date: February 2011

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

i

Page 3: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

DOCUMENT REGISTER

REVISION DESCRIPTION DATE COMMENTS

A DRAFT 11 FEBRUARY 2011 Original

B FINAL 15 FEBRUARY 2011 Updated for AGE Report V7

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

ii

Page 4: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

TABLE OF CONTENTS

1.0 INTRODUCTION............................................................................................ 12.0 SCOPE OF WORK.......................................................................................... 1

3.0 MODELLING GUIDELINES ........................................................................ 24.0 EVIDENTIARY BASIS................................................................................... 25.0 PEER REVIEW ............................................................................................... 36.0 DISCUSSION ................................................................................................... 3

6.1 THE REPORT ................................................................................................... 36.2 DATA ANALYSIS ............................................................................................. 46.3 CONCEPTUALISATION ..................................................................................... 46.4 MODEL DESIGN............................................................................................... 56.5 CALIBRATION.................................................................................................. 66.6 PREDICTION .................................................................................................... 66.7 SENSITIVITY ANALYSIS ................................................................................... 76.8 UNCERTAINTY ANALYSIS ............................................................................... 7

7.0 CONCLUSION ................................................................................................ 7

8.0 REFERENCES ................................................................................................. 9

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

iii

Page 5: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

1.0 INTRODUCTION

This report provides a peer review of the groundwater impact assessment of open cut mining for the Maules Creek Coal Project. The mine is to be situated about 18 km to the north-east of Boggabri in NSW.

The hydrogeological assessment is based on field investigations and a regional numerical groundwater model developed by Australasian Groundwater & Environmental Consultants (AGE) Pty Ltd.

The groundwater modelling forms an important component of the environmental assessment for the project. The main purpose of the modelling is to assess potential impacts on groundwater levels on the Project Site and in the surrounding area where private bores are situated, and also to assess potential interception of alluvial groundwater recharge in aquifer systems associated with Maules Creek to the north and Bollol Creek to the south. The model also provides an assessment of likely groundwater inflow to the open cut pit as the mine progresses in time.

2.0 SCOPE OF WORK

The agreed scope of work for the review consisted of the following tasks:

Attend a kickoff/conceptualisation meeting in Brisbane;

Maintain an overview of AGE’s modelling progress at all stages of model development;

Review a model study plan after the conceptualisation stage;

Attend a meeting in Brisbane after model calibration;

Assess the model component in the draft final report by means of the MDBC peer review checklists;

Review the full groundwater assessment draft report;

Prepare a report that outlines the key findings from the review; and

Provide phone/email advice as required.

This report addresses the penultimate dot point (above) by outlining the key findings from the review. As indicated in the second dot point (above), this review was conducted as a progressive review.

The reviewer has been engaged in all phases of the groundwater assessment since October 2010. Peer review was conducted progressively at key milestones:

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

1

Page 6: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

Model conceptualisation;

Model calibration;

Model prediction; and

Final reporting.

The reviewer participated in meetings with the modelling team and project managers in Brisbane on 21 October 2010, 8 December 2010 and 27 January 2011.

3.0 MODELLING GUIDELINES

The review has been structured according to the checklists in the Australian Flow Modelling Guideline (MDBC, 2001). This guide, sponsored by the Murray-Darling Basin Commission, has become a de facto Australian standard. This reviewer was one of the three authors of the guide, and is the person responsible for creating the peer review checklists. The checklists have been well received nationally, and have been adopted for use in the United Kingdom, California and Germany.

The modelling has been assessed according to the 2-page Model Appraisal checklist in MDBC (2001). This checklist has questions on (1) The Report; (2) Data Analysis; (3) Conceptualisation; (4) Model Design; (5) Calibration; (6) Verification; (7) Prediction; (8) Sensitivity Analysis; and (9) Uncertainty Analysis.

The effort put into a modelling study is often dependent on timing and budgetary constraints that are generally not known to a reviewer.

4.0 EVIDENTIARY BASIS

The primary documentation on which this review is based is:

1. Australasian Groundwater & Environmental Consultants Pty Ltd,2011, Maules Creek Coal Project Groundwater Impact Assessment. February 2011. Version 7. 85p + Drawings + 3 Appendices.

Apart from background knowledge of the area, no other documentation has been referenced in doing this review.

As a progressive review has been conducted, comments have been offered progressively by the reviewer on a series of draft AGE reports and model outputs.

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

2

Page 7: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

5.0 PEER REVIEW

In terms of the modelling guidelines, the Maules Creek Coal Project model is categorised as an Impact Assessment Model of medium complexity, as distinct from an Aquifer Simulator of high complexity.

The Australian best practice guide (MDBC, 2001) describes the connection between model application and model complexity as follows:

Impact Assessment model - a moderate complexity model, requiring more data and a better understanding of the groundwater system dynamics, and suitable for predicting the impacts of proposed developments or management policies; and

Aquifer Simulator - a high complexity model, suitable for predicting responses to arbitrary changes in hydrological conditions, and for developing sustainable resource management policies for aquifer systems under stress.

An Impact Assessment model is the appropriate level of complexity for an Environmental Assessment.

The appraisal checklists are presented in Tables 1 and 2 (at the back of this report). The current review has been based entirely on a written report, with no reference to electronic model files.

6.0 DISCUSSION

6.1 THE REPORT

The Model Report (Document #1) is a substantial, high quality document of 85 pages in the main body of the report plus 29 drawings and three appendices. To an external reader with no prior knowledge of the study area, the report is very good as a standalone document without need of supporting documents.

The objectives of the groundwater study and the scope of work to address those objectives are articulated clearly in Section 3.0 (Scope of Work). The specific objectives of the modelling study are stated in Section 9.1.

In Section 10.11, the findings of the modelling study are reported succinctly in the context of the objectives. This reviewer considers that the objectives have been met satisfactorily and the findings are well substantiated.

There is ample coverage of the modelling component of the study, with full disclosure of (uniform) aquifer/aquitard parameterisation.

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

3

Page 8: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

6.2 DATA ANALYSIS

While substantial hydraulic testing has been undertaken on coal seams in the Project area and neighbouring areas, assessment of interburden permeabilities is limited.

There is a substantial record of groundwater level variations (hydrographs) in government alluvial bores. However, there is limited hydrographic information available within the coal measures within the Project Boundary and for neighbouring mining operations. Hydrographs are presented for three vibrating wire installations that have piezometers at either one or two depths within the Project Boundary. Data acquisition commenced in September 2010. The lack of monitored sites and the shortage of the measurement record have limited model calibration to steady-state analysis. Transient calibration could have been done on alluvial hydrographs, in principle, but these datasets are affected by private pumping which is not on public record.

The vibrating wire installations would have benefitted from having more piezometers installed on the one string. The marginal cost is low, and vertical head profiles would provide a strong calibration target, especially during mining. Nevertheless, the quantification of vertical head difference between two depths provides some control for model calibration.

A good correlation has been demonstrated between alluvial hydrographs and rainfall trends.

Sufficient “snapshot” water levels are available for production of a regional water level map. This shows clearly the dominant directions of groundwater flow.

6.3 CONCEPTUALISATION

The conceptualisation of the local hydrogeology is sensible and is discussed in detail, in terms of geology and key recharge/discharge processes. Excellent graphics are provided in support of the conceptualisation (Figures 21, 22, 23).

Due to the number of coal plies, the stratigraphic division into model layers required a compromise. The plies were lumped into layers having aggregate thicknesses and placed at the base of a significant seam. This is a sensible compromise. The consequences of this action are well understood and are addressed in the report.

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

4

Page 9: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

6.4 MODEL DESIGN

The model has been built with MODFLOW-SURFACT in DOS mode with only incidental use of a commercial Graphic User Interface. This combination is unusual, as it limits transferability of models, but it does allow model refinements not available through other means.

The use of MODFLOW-SURFACT is supported over standard MODFLOW as it is a more powerful version which is better able to handle desaturated conditions caused by mining.

One limitation that both MODFLOW versions have for coal mining simulations is that they do not permit time-varying material properties (without frequent stops and starts). AGE has adopted the stop-start approach, which is the acceptable best practice approach. It is noted that MODFLOW-SURFACT has introduced a time-varying facility recently, and this is likely to become a better approach after it is fully tested.

Discretisation in space is appropriate. Model cells are a minimum 50 m square, maximum 500 m square, over a 30 km (east-west) by 40 km (north-south) area. Finer discretisation is applied in the area to be mined. The model has 12 layers.

The broad model extent isolates the boundaries from likely impacts and reduces the need for accurate representation of boundary fluxes which are set as no-flow for most layers except for prescribed heads in the alluvial Gunnedah Formation. Final predicted drawdowns verify that the adopted boundary conditions have had no undue effect.

The mining operation has been simulated appropriately by MODFLOW “drain” cells in each layer of the open cut excavation.

Watercourses are handled properly using the “river” (RIV) MODFLOW package.

Where uncertainty exists, a deliberately conservative approach has been adopted for the modelling. This is good practice. In particular, faults have not been included. Such faults and seam discontinuities are likely to limit the predicted extent of drawdown effects.

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

5

Page 10: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

6.5 CALIBRATION

Calibration has been performed for steady-state conditions only, as insufficient data were available for transient calibration. The latter could have been done for alluvial hydrographs, but essential information on private groundwater abstraction is not available in the public domain. However, the alluvial system was adopted from a well calibrated government model. The only deficiency of the government model is that it assumes no interaction with hard rock. The Maules Creek model had to adopt a leakage coefficient (or equivalently a vertical permeability) at the sediment-rock interface. This was informed through steady-state calibration against long-term average alluvial groundwater levels. This is considered sufficient by the reviewer.

Several lines of evidence are provided in support of steady-state calibration in the form of a scatter plot, performance statistics, and a water level contour map for comparison with best-estimate field contours. Steady-state calibration is quite good, with satisfactory performance statistics: 5 % scaled RMS and ~6 m absolute RMS.

The inferred hydraulic conductivity magnitudes are consistent with aquifer tests and previous modelling, and the inferred rainfall recharge rates are plausible.

6.6 PREDICTION

Predictions are based on transient simulation for 21 years of continuous mining followed by 1000 years of recovery after the cessation of mining. Project-specific and cumulative effect simulations are performed.

The report presents continuous plots of mine inflow with time, and also of intercepted lateral groundwater flow normally destined for the alluvial system. Drawdown maps are offered at 5 year intervals.

All runs are performed properly and the findings are defensible.

Predicting mine inflow magnitude is always difficult in a “greenfields” application. The plausibility of the prediction (average 1.6 ML/day) would have benefitted from knowledge of measured or estimated mine inflows at the shallower neighbouring Boggabri and Tarrawonga mines. It is understood that reliable mine inflow estimates are not available, but they are expected to be less than 0.5 ML/day.

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

6

Page 11: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

6.7 SENSITIVITY ANALYSIS

A sufficient sensitivity analysis has been reported. Perturbations of 50% are applied to rain recharge, specific yield, coal seam horizontal permeability, specific storage and Gunnedah vertical permeability. This is sufficient for bracketing the range of uncertainty for the first three parameters. For the latter two, an order of magnitude or half order of magnitude perturbation would normally be applied. The -50% perturbation gives a half order of magnitude change, but +50% is a multiplier of 1.5. This means that reduced specific storage and Gunnedah vertical permeability are assessed adequately, but increased values could be tested at higher levels.

Steady-state calibration statistics are reported for each sensitivity run. Calibration performance is affected significantly only by higher rain recharge. This suggests that the adopted rain recharge is confined to a small range of uncertainty (or that the ratio of rain recharge to surficial permeability is well defined). The mass balance elements are well defined except for rain recharge perturbation.

6.8 UNCERTAINTY ANALYSIS

Sensitivity simulations in predictive mode provide a way of quantifying the uncertainty in predicted outcomes.

Mine inflow rate was found to be sensitive to coal seam permeability, resulting in an average of 1.6 ± 0.5 ML/day. For other property perturbations, the uncertainty was found to be much smaller.

The interception of alluvial flow was found to be sensitive to specific storage, resulting in an average of about 0.35 ± 0.2 ML/day. It has been remarked already that specific storage can reasonably vary by more than 50% without affecting a (transient) calibration. Hence, the real uncertainty in alluvial groundwater interception could be higher. However, higher interception occurs only with a lower specific storage value, and this has been tested adequately by a half order of magnitude change. The value for this parameter should be refined when model recalibration is done after proposed mining commences. This reviewer agrees with the AGE recommendation for model updates every five years, to guide adaptive management.

7.0 CONCLUSION

The Maules Creek Coal Project groundwater model has been developed competently and is regarded as “fit for purpose” for addressing cumulative

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

7

Page 12: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

impacts from three mines, for estimating indicative dewatering rates, and for assessing regional potential groundwater impacts.

Model predictions are expected to be conservative for two main reasons:

Exclusion of structural controls that are likely to cause some compartmentalisation of effects in reality and to limit the drawdown extent towards alluvial aquifers; and

Probable overestimation of mine inflow.

Model predictions of mine inflow are likely to be overestimated for two main reasons:

Aggregation of coal plies into a thicker coal seam at a lower depth; and

No allowance for the time taken for spoil to reach saturation.

The stated objectives of the modelling study have been addressed satisfactorily; namely:

Estimation of mine inflow to the open cut void for 21 years;

Prediction of drawdown magnitude and extent;

Prediction of alluvial groundwater losses;

Prediction of impacts on stream baseflows and other groundwater users; and

Identification of risks that might necessitate mitigation measures or controls.

It is considered that the model would benefit from refinement through transient calibration when sufficient hydrographic data become available in the Permian formations. As recommended in the AGE report, transient calibration should be performed after the first five years of mining.

Drawdown predictions indicate that the Project will not have significant impacts external to the mined area. This conclusion is well substantiated.

The model anticipates no change in baseflow at the neighbouring creeks. This conclusion is well substantiated.

There is a prediction of reduced average lateral recharge of groundwater in the alluvial system, in the order of 50 ML/a. This estimate is sensitive to the adopted specific storage values which cannot be calibrated properly until transient calibration becomes possible. Even allowing for uncertainty in

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

8

Page 13: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

specific storage, this volume of water is less than 1% of rain recharge over the model area. It is likely that Aston Resources can offset this volume by acquiring existing water licences.

8.0 REFERENCES

Australasian Groundwater & Environmental Consultants Pty Ltd, 2011, Maules Creek Coal Project Groundwater Impact Assessment. February 2011. Version 6.

MDBC (2001). Groundwater flow modelling guideline. Murray-Darling Basin Commission. URL: http://www.mdbc.gov.au/nrm/groundwater/groundwater_guides/

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

9

Page 14: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

Tabl

e 1.

MO

DEL

APP

RA

ISA

L: M

aule

s Cre

ek C

oal M

odel

Q.

QU

ES

TIO

N

Not

App

licab

leor

Unk

now

n

RA

TIN

G

CO

MM

EN

T

1.0

THE

REP

OR

T

1.1

Is th

ere

a cl

ear s

tate

men

t of p

roje

ct o

bjec

tives

in th

e m

odel

ling

repo

rt?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d S

cope

of W

ork

Sec

tion

3.0

1.2

Is th

e le

vel o

f mod

el c

ompl

exity

cle

ar o

r ack

now

ledg

ed?

M

issi

ng

No

Yes

Im

pact

Ass

essm

ent M

odel

, med

ium

com

plex

ity. E

xecu

tive

Sum

mar

y in

clud

es th

e re

leva

nt s

tate

men

t.

1.3

Is a

wat

er o

r mas

s ba

lanc

e re

porte

d?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d Ta

bula

ted

for s

tead

y st

ate

calib

ratio

n. P

rese

nted

as

time-

serie

s gr

aphs

for t

he p

redi

ctio

n m

odel

. Als

o ta

bula

ted

for 1

0%

sens

itivi

ty ru

ns.

1.4

Has

the

mod

ellin

g st

udy

satis

fied

proj

ect o

bjec

tives

?

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

Sub

ject

to s

tate

d lim

itatio

ns.

1.5

Are

the

mod

el re

sults

of a

ny p

ract

ical

use

?

N

o M

aybe

Ye

s

2.0

DA

TA A

NA

LYSI

S

2.1

Has

hyd

roge

olog

y da

ta b

een

colle

cted

and

ana

lyse

d?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d In

clud

es a

fiel

d pr

ogra

m p

acke

r tes

ts; 8

pie

zos;

4 V

W p

iezo

ne

sts

(x2)

; wat

er s

ampl

es. N

o pr

ior i

nfor

mat

ion

on v

ertic

al

head

pro

files

.

2.2

Are

gro

undw

ater

con

tour

s or

flow

dire

ctio

ns p

rese

nted

? M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d Fo

r 199

2 C

offe

y no

rther

n ar

ea a

nd re

cent

con

tour

s de

velo

ped

usin

g sh

allo

w s

tead

y st

ate

targ

ets

(Per

mia

n/Q

uate

rnar

y m

ix).

2.3

Hav

e al

l pot

entia

l rec

harg

e da

ta b

een

colle

cted

and

an

alys

ed?

(rai

nfal

l, st

ream

flow

, irr

igat

ion,

floo

ds, e

tc.)

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d R

ain

resi

dual

mas

s an

alys

is is

don

e. S

tead

y st

ream

sta

ge

base

d on

gro

und

elev

atio

n m

inus

est

imat

ed in

cisi

on.

2.4

Hav

e al

l pot

entia

l dis

char

ge d

ata

been

col

lect

ed a

nd

anal

ysed

? (a

bstra

ctio

n, e

vapo

trans

pira

tion,

dra

inag

e,

sprin

gflo

w, e

tc.)

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d P

rivat

e gw

abs

tract

ion

from

allu

vium

not

ava

ilabl

e in

the

publ

ic

dom

ain.

2.5

Hav

e th

e re

char

ge a

nd d

isch

arge

dat

aset

s be

en a

naly

sed

for t

heir

grou

ndw

ater

resp

onse

? N

/AM

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d S

trong

cor

rela

tion

of g

roun

dwat

er h

ydro

grap

hs w

ith ra

infa

ll tre

nds,

sho

wn

by re

sidu

al m

ass

anal

ysis

. Qua

ntifi

ed v

ertic

al

head

gra

dien

ts in

new

VW

P h

oles

. One

faul

ty V

WP

.

2.6

Are

gro

undw

ater

hyd

rogr

aphs

use

d fo

r cal

ibra

tion?

N

/AN

o M

aybe

Y

es

2.7

Hav

e co

nsis

tent

dat

a un

its a

nd s

tand

ard

geom

etric

al

datu

ms

been

use

d?

No

Yes

In

cons

iste

ncy

in s

ome

TDS

/EC

val

ues;

som

e ra

tios

are

very

lo

w (<

0.6)

for a

bic

arbo

nate

wat

er. T

wo

anom

alou

s TD

S.

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

10

Page 15: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

3.0

CO

NC

EPTU

ALI

SATI

ON

3.1

Is th

e co

ncep

tual

mod

el c

onsi

sten

t with

pro

ject

obj

ectiv

es

and

the

requ

ired

mod

el c

ompl

exity

?

Unk

now

n N

o M

aybe

Ye

s

3.2

Is th

ere

a cl

ear d

escr

iptio

n of

the

conc

eptu

al m

odel

?

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

Sec

tion

9.2.

3.3

Is th

ere

a gr

aphi

cal r

epre

sent

atio

n of

the

mod

elle

r’s

conc

eptu

alis

atio

n?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d Fi

gure

21

for d

urin

g-m

inin

g si

tuat

ion.

3D

geo

met

ry s

how

n in

Fi

gure

s 22

and

23

– re

mov

al o

f allu

vium

is il

lust

rativ

e.

3.4

Is th

e co

ncep

tual

mod

el u

nnec

essa

rily

sim

ple

or

unne

cess

arily

com

plex

?

Ye

s N

o

Sen

sibl

e st

ratig

raph

ic d

ivis

ion.

Plie

s lu

mpe

d in

to la

yers

hav

ing

aggr

egat

e th

ickn

esse

s –

an a

ccep

tabl

e co

mpr

omis

e.

4.0

MO

DEL

DES

IGN

4.1

Is th

e sp

atia

l ext

ent o

f the

mod

el a

ppro

pria

te?

No

May

be

Yes

Ext

ensi

ve.

4.2

Are

the

appl

ied

boun

dary

con

ditio

ns p

laus

ible

and

un

rest

rictiv

e?

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

Gen

eral

ly n

o-flo

w a

t dis

tant

bor

ders

, and

fixe

d he

ads

in L

ayer

2

(Gun

neda

h Fm

.). N

ot c

lear

if fl

ow b

ound

ary

has

been

ap

plie

d to

Nar

rabr

i Fm

. (La

yer 1

) – p

roba

bly

no fl

ow, a

s ap

plie

d in

dee

p la

yers

. Cou

ld h

ave

had

spat

ially

var

ying

fixe

d he

ad in

allu

vium

from

NO

W m

odel

. Stre

ams

are

RIV

cel

ls

(ofte

n =

DR

N).

Min

ing

by D

RN

cel

ls.

4.3

Is th

e so

ftwar

e ap

prop

riate

for t

he o

bjec

tives

of t

he s

tudy

?

N

o M

aybe

Ye

s M

OD

FLO

W-S

UR

FAC

T in

DO

S m

ode

(no

GU

I). T

ime

vary

ing

mat

eria

l pro

perti

es h

andl

ed b

y st

art-s

top

sim

ulat

ion.

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

11

Page 16: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

Tabl

e 2.

MO

DEL

APP

RA

ISA

L: M

aule

s Cre

ek C

oal M

odel

Q.

QU

ES

TIO

N

Not

App

licab

leor

Unk

now

n

RA

TIN

G

CO

MM

EN

T

5.0

CA

LIB

RA

TIO

N

5.1

Is th

ere

suffi

cien

t evi

denc

e pr

ovid

ed fo

r mod

el c

alib

ratio

n?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d S

ever

al li

nes

of e

vide

nce:

sca

tterg

ram

for s

tead

y-st

ate;

pe

rform

ance

sta

tistic

s fo

r ste

ady

stat

e (%

RM

S a

nd a

bsol

ute

RM

S);

resi

dual

at e

ach

bore

; wat

er ta

ble

cont

our m

ap.

Pre

sum

ably

use

d P

ES

T –

not s

tate

d.

5.2

Is th

e m

odel

suf

ficie

ntly

cal

ibra

ted

agai

nst s

patia

l ob

serv

atio

ns?

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

Dra

win

g 14

com

pare

d w

ith “o

bser

ved”

con

tour

map

(Dra

win

g 11

).

5.3

Is th

e m

odel

suf

ficie

ntly

cal

ibra

ted

agai

nst t

empo

ral

obse

rvat

ions

?N

/AM

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d S

tead

y-st

ate

calib

ratio

n on

ly.

5.4

Are

cal

ibra

ted

para

met

er d

istri

butio

ns a

nd ra

nges

pl

ausi

ble?

Mis

sing

N

o M

aybe

Ye

s C

onsi

sten

t with

aqu

ifer t

ests

. Rai

n re

char

ge ra

tes

are

cons

iste

nt

with

dis

trict

kno

wle

dge

and

prio

r mod

ellin

g. S

houl

d no

t rep

ort S

s fo

r Lay

er 1

.

5.5

Doe

s th

e ca

libra

tion

stat

istic

sat

isfy

agr

eed

perfo

rman

ce

crite

ria?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d 4.

9% S

RM

S a

nd 5

.7m

RM

S; m

axim

um re

sidu

al 1

4m. S

RM

S is

ve

ry g

ood

and

mee

ts th

e M

DB

C g

uide

line.

5.6

Are

ther

e go

od re

ason

s fo

r not

mee

ting

agre

ed

perfo

rman

ce c

riter

ia?

N/A

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

Geo

logi

cal c

ompl

exity

. Mix

ed w

ater

leve

ls fr

om m

any

year

s.

6.0

VER

IFIC

ATI

ON

6.1

Is th

ere

suffi

cien

t evi

denc

e pr

ovid

ed fo

r mod

el

verif

icat

ion?

N

/AM

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d

6.2

Doe

s th

e re

serv

ed d

atas

et in

clud

e st

ress

es c

onsi

sten

t w

ith th

e pr

edic

tion

scen

ario

s?

N/A

Unk

now

n N

o M

aybe

Ye

s

6.3

Are

ther

e go

od re

ason

s fo

r an

unsa

tisfa

ctor

y ve

rific

atio

n?

N/A

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

7.0

PRED

ICTI

ON

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY

Groundwater Impact Assessment M

12

Page 17: 0986 M Groundwater Impact Assessment Peer Review

110215 Review Maules Creek Groundwater Final.docHC2011/3

7.1

Hav

e m

ultip

le s

cena

rios

been

run

for c

limat

e va

riabi

lity?

N

/AM

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d N

o cl

imat

e va

riabi

lity

is s

imul

ated

. Ste

ady

aver

age

rain

is a

pplie

d –

appr

opria

te fo

r the

mod

el p

urpo

se.

7.2

Hav

e m

ultip

le s

cena

rios

been

run

for o

pera

tiona

l /m

anag

emen

t alte

rnat

ives

?

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

Sin

gle

min

e pl

an –

with

and

with

out t

wo

neig

hbou

ring

min

es.

Irrig

atio

n gw

abs

tract

ion

excl

uded

. App

ropr

iate

for t

he m

odel

pu

rpos

e. T

wo

final

voi

d op

tions

are

mod

elle

d.

7.3

Is th

e tim

e ho

rizon

for p

redi

ctio

n co

mpa

rabl

e w

ith th

e le

ngth

of t

he c

alib

ratio

n / v

erifi

catio

n pe

riod?

Mis

sing

N

o M

aybe

Y

es

21 y

ears

pre

dict

ion

base

d on

ste

ady

stat

e ca

libra

tion

and

prio

r/tex

tboo

k st

orag

e pr

oper

ties.

7.4

Are

the

mod

el p

redi

ctio

ns p

laus

ible

?

N

o M

aybe

Ye

s M

ine

inflo

w <

4 M

L/da

y; a

vera

ge <

2 M

L/da

y. C

onsi

sten

t with

prio

r m

odel

est

imat

es, b

ut c

onse

rvat

ivel

y hi

gh. N

o ac

cura

te

know

ledg

e of

cur

rent

min

e in

flow

at B

ogga

bri

and

Tarr

awon

ga,

but T

arra

won

ga is

bel

ieve

d to

be

<0.1

ML/

d an

d B

ogga

bri <

0.5

ML/

d.

8.0

SEN

SITI

VIT

Y A

NA

LYSI

S

8.1

Is th

e se

nsiti

vity

ana

lysi

s su

ffici

ently

inte

nsiv

e fo

r key

pa

ram

eter

s?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d D

one

for r

ain

rech

arge

, spe

cific

yie

ld, s

peci

fic s

tora

ge,

Gun

neda

h K

z, c

oal s

eam

Kx,

for 5

0% p

ertu

rbat

ion.

Thi

s w

ill

brac

ket l

ikel

y un

certa

inty

for t

he fi

rst t

wo

and

the

last

, but

not

for

Spe

cific

sto

rage

(Ss)

and

Kz.

Val

ues

are

low

ered

by

half

orde

r of

mag

nitu

de (m

ultip

lier 0

.5),

whi

ch is

ade

quat

e, b

ut h

ighe

r val

ues

shou

ld u

se a

mul

tiplie

r of 3

or 5

inst

ead

of 1

.5.

8.2

Are

sen

sitiv

ity re

sults

use

d to

qua

lify

the

relia

bilit

y of

m

odel

cal

ibra

tion?

Mis

sing

D

efic

ient

A

dequ

ate

Ver

y G

ood

RM

S a

nd S

RM

S a

re re

porte

d.

8.3

Are

sen

sitiv

ity re

sults

use

d to

qua

lify

the

accu

racy

of

mod

el p

redi

ctio

n?

M

issi

ng

Def

icie

nt

Ade

quat

e V

ery

Goo

d W

ater

bud

get i

tem

s ar

e re

porte

d.

9.0

UN

CER

TAIN

TY A

NA

LYSI

S

9.1

If re

quire

d by

the

proj

ect b

rief,

is u

ncer

tain

ty q

uant

ified

in

any

way

?

Mis

sing

N

o M

aybe

Ye

s R

ange

in a

vera

ge a

nd m

axim

um m

ine

inflo

w is

repo

rted

for

sens

itivi

ty a

naly

sis.

Rec

over

y tim

e is

inve

stig

ated

for 2

spo

il re

char

ge ra

tes.

Groundwater Impact Assessment

MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY

M

13