0986 m groundwater impact assessment peer review
TRANSCRIPT
![Page 1: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/1.jpg)
APPENDIX
Addendum - Peer Review of the Maules Creek Coal Project Groundwater Impact Assessment
M
![Page 2: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/2.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
M Groundwater Impact Assessment
HERITAGE COMPUTING REPORT
PEER REVIEW OF THE MAULES CREEK COAL PROJECT GROUNDWATER IMPACT
ASSESSMENT
FOR
ASTON RESOURCES LIMITED
By
Dr N. P. Merrick
Report Number: HC2011/3 Date: February 2011
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
i
![Page 3: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/3.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
DOCUMENT REGISTER
REVISION DESCRIPTION DATE COMMENTS
A DRAFT 11 FEBRUARY 2011 Original
B FINAL 15 FEBRUARY 2011 Updated for AGE Report V7
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
ii
![Page 4: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/4.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
TABLE OF CONTENTS
1.0 INTRODUCTION............................................................................................ 12.0 SCOPE OF WORK.......................................................................................... 1
3.0 MODELLING GUIDELINES ........................................................................ 24.0 EVIDENTIARY BASIS................................................................................... 25.0 PEER REVIEW ............................................................................................... 36.0 DISCUSSION ................................................................................................... 3
6.1 THE REPORT ................................................................................................... 36.2 DATA ANALYSIS ............................................................................................. 46.3 CONCEPTUALISATION ..................................................................................... 46.4 MODEL DESIGN............................................................................................... 56.5 CALIBRATION.................................................................................................. 66.6 PREDICTION .................................................................................................... 66.7 SENSITIVITY ANALYSIS ................................................................................... 76.8 UNCERTAINTY ANALYSIS ............................................................................... 7
7.0 CONCLUSION ................................................................................................ 7
8.0 REFERENCES ................................................................................................. 9
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
iii
![Page 5: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/5.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
1.0 INTRODUCTION
This report provides a peer review of the groundwater impact assessment of open cut mining for the Maules Creek Coal Project. The mine is to be situated about 18 km to the north-east of Boggabri in NSW.
The hydrogeological assessment is based on field investigations and a regional numerical groundwater model developed by Australasian Groundwater & Environmental Consultants (AGE) Pty Ltd.
The groundwater modelling forms an important component of the environmental assessment for the project. The main purpose of the modelling is to assess potential impacts on groundwater levels on the Project Site and in the surrounding area where private bores are situated, and also to assess potential interception of alluvial groundwater recharge in aquifer systems associated with Maules Creek to the north and Bollol Creek to the south. The model also provides an assessment of likely groundwater inflow to the open cut pit as the mine progresses in time.
2.0 SCOPE OF WORK
The agreed scope of work for the review consisted of the following tasks:
Attend a kickoff/conceptualisation meeting in Brisbane;
Maintain an overview of AGE’s modelling progress at all stages of model development;
Review a model study plan after the conceptualisation stage;
Attend a meeting in Brisbane after model calibration;
Assess the model component in the draft final report by means of the MDBC peer review checklists;
Review the full groundwater assessment draft report;
Prepare a report that outlines the key findings from the review; and
Provide phone/email advice as required.
This report addresses the penultimate dot point (above) by outlining the key findings from the review. As indicated in the second dot point (above), this review was conducted as a progressive review.
The reviewer has been engaged in all phases of the groundwater assessment since October 2010. Peer review was conducted progressively at key milestones:
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
1
![Page 6: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/6.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
Model conceptualisation;
Model calibration;
Model prediction; and
Final reporting.
The reviewer participated in meetings with the modelling team and project managers in Brisbane on 21 October 2010, 8 December 2010 and 27 January 2011.
3.0 MODELLING GUIDELINES
The review has been structured according to the checklists in the Australian Flow Modelling Guideline (MDBC, 2001). This guide, sponsored by the Murray-Darling Basin Commission, has become a de facto Australian standard. This reviewer was one of the three authors of the guide, and is the person responsible for creating the peer review checklists. The checklists have been well received nationally, and have been adopted for use in the United Kingdom, California and Germany.
The modelling has been assessed according to the 2-page Model Appraisal checklist in MDBC (2001). This checklist has questions on (1) The Report; (2) Data Analysis; (3) Conceptualisation; (4) Model Design; (5) Calibration; (6) Verification; (7) Prediction; (8) Sensitivity Analysis; and (9) Uncertainty Analysis.
The effort put into a modelling study is often dependent on timing and budgetary constraints that are generally not known to a reviewer.
4.0 EVIDENTIARY BASIS
The primary documentation on which this review is based is:
1. Australasian Groundwater & Environmental Consultants Pty Ltd,2011, Maules Creek Coal Project Groundwater Impact Assessment. February 2011. Version 7. 85p + Drawings + 3 Appendices.
Apart from background knowledge of the area, no other documentation has been referenced in doing this review.
As a progressive review has been conducted, comments have been offered progressively by the reviewer on a series of draft AGE reports and model outputs.
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
2
![Page 7: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/7.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
5.0 PEER REVIEW
In terms of the modelling guidelines, the Maules Creek Coal Project model is categorised as an Impact Assessment Model of medium complexity, as distinct from an Aquifer Simulator of high complexity.
The Australian best practice guide (MDBC, 2001) describes the connection between model application and model complexity as follows:
Impact Assessment model - a moderate complexity model, requiring more data and a better understanding of the groundwater system dynamics, and suitable for predicting the impacts of proposed developments or management policies; and
Aquifer Simulator - a high complexity model, suitable for predicting responses to arbitrary changes in hydrological conditions, and for developing sustainable resource management policies for aquifer systems under stress.
An Impact Assessment model is the appropriate level of complexity for an Environmental Assessment.
The appraisal checklists are presented in Tables 1 and 2 (at the back of this report). The current review has been based entirely on a written report, with no reference to electronic model files.
6.0 DISCUSSION
6.1 THE REPORT
The Model Report (Document #1) is a substantial, high quality document of 85 pages in the main body of the report plus 29 drawings and three appendices. To an external reader with no prior knowledge of the study area, the report is very good as a standalone document without need of supporting documents.
The objectives of the groundwater study and the scope of work to address those objectives are articulated clearly in Section 3.0 (Scope of Work). The specific objectives of the modelling study are stated in Section 9.1.
In Section 10.11, the findings of the modelling study are reported succinctly in the context of the objectives. This reviewer considers that the objectives have been met satisfactorily and the findings are well substantiated.
There is ample coverage of the modelling component of the study, with full disclosure of (uniform) aquifer/aquitard parameterisation.
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
3
![Page 8: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/8.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
6.2 DATA ANALYSIS
While substantial hydraulic testing has been undertaken on coal seams in the Project area and neighbouring areas, assessment of interburden permeabilities is limited.
There is a substantial record of groundwater level variations (hydrographs) in government alluvial bores. However, there is limited hydrographic information available within the coal measures within the Project Boundary and for neighbouring mining operations. Hydrographs are presented for three vibrating wire installations that have piezometers at either one or two depths within the Project Boundary. Data acquisition commenced in September 2010. The lack of monitored sites and the shortage of the measurement record have limited model calibration to steady-state analysis. Transient calibration could have been done on alluvial hydrographs, in principle, but these datasets are affected by private pumping which is not on public record.
The vibrating wire installations would have benefitted from having more piezometers installed on the one string. The marginal cost is low, and vertical head profiles would provide a strong calibration target, especially during mining. Nevertheless, the quantification of vertical head difference between two depths provides some control for model calibration.
A good correlation has been demonstrated between alluvial hydrographs and rainfall trends.
Sufficient “snapshot” water levels are available for production of a regional water level map. This shows clearly the dominant directions of groundwater flow.
6.3 CONCEPTUALISATION
The conceptualisation of the local hydrogeology is sensible and is discussed in detail, in terms of geology and key recharge/discharge processes. Excellent graphics are provided in support of the conceptualisation (Figures 21, 22, 23).
Due to the number of coal plies, the stratigraphic division into model layers required a compromise. The plies were lumped into layers having aggregate thicknesses and placed at the base of a significant seam. This is a sensible compromise. The consequences of this action are well understood and are addressed in the report.
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
4
![Page 9: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/9.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
6.4 MODEL DESIGN
The model has been built with MODFLOW-SURFACT in DOS mode with only incidental use of a commercial Graphic User Interface. This combination is unusual, as it limits transferability of models, but it does allow model refinements not available through other means.
The use of MODFLOW-SURFACT is supported over standard MODFLOW as it is a more powerful version which is better able to handle desaturated conditions caused by mining.
One limitation that both MODFLOW versions have for coal mining simulations is that they do not permit time-varying material properties (without frequent stops and starts). AGE has adopted the stop-start approach, which is the acceptable best practice approach. It is noted that MODFLOW-SURFACT has introduced a time-varying facility recently, and this is likely to become a better approach after it is fully tested.
Discretisation in space is appropriate. Model cells are a minimum 50 m square, maximum 500 m square, over a 30 km (east-west) by 40 km (north-south) area. Finer discretisation is applied in the area to be mined. The model has 12 layers.
The broad model extent isolates the boundaries from likely impacts and reduces the need for accurate representation of boundary fluxes which are set as no-flow for most layers except for prescribed heads in the alluvial Gunnedah Formation. Final predicted drawdowns verify that the adopted boundary conditions have had no undue effect.
The mining operation has been simulated appropriately by MODFLOW “drain” cells in each layer of the open cut excavation.
Watercourses are handled properly using the “river” (RIV) MODFLOW package.
Where uncertainty exists, a deliberately conservative approach has been adopted for the modelling. This is good practice. In particular, faults have not been included. Such faults and seam discontinuities are likely to limit the predicted extent of drawdown effects.
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
5
![Page 10: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/10.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
6.5 CALIBRATION
Calibration has been performed for steady-state conditions only, as insufficient data were available for transient calibration. The latter could have been done for alluvial hydrographs, but essential information on private groundwater abstraction is not available in the public domain. However, the alluvial system was adopted from a well calibrated government model. The only deficiency of the government model is that it assumes no interaction with hard rock. The Maules Creek model had to adopt a leakage coefficient (or equivalently a vertical permeability) at the sediment-rock interface. This was informed through steady-state calibration against long-term average alluvial groundwater levels. This is considered sufficient by the reviewer.
Several lines of evidence are provided in support of steady-state calibration in the form of a scatter plot, performance statistics, and a water level contour map for comparison with best-estimate field contours. Steady-state calibration is quite good, with satisfactory performance statistics: 5 % scaled RMS and ~6 m absolute RMS.
The inferred hydraulic conductivity magnitudes are consistent with aquifer tests and previous modelling, and the inferred rainfall recharge rates are plausible.
6.6 PREDICTION
Predictions are based on transient simulation for 21 years of continuous mining followed by 1000 years of recovery after the cessation of mining. Project-specific and cumulative effect simulations are performed.
The report presents continuous plots of mine inflow with time, and also of intercepted lateral groundwater flow normally destined for the alluvial system. Drawdown maps are offered at 5 year intervals.
All runs are performed properly and the findings are defensible.
Predicting mine inflow magnitude is always difficult in a “greenfields” application. The plausibility of the prediction (average 1.6 ML/day) would have benefitted from knowledge of measured or estimated mine inflows at the shallower neighbouring Boggabri and Tarrawonga mines. It is understood that reliable mine inflow estimates are not available, but they are expected to be less than 0.5 ML/day.
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
6
![Page 11: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/11.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
6.7 SENSITIVITY ANALYSIS
A sufficient sensitivity analysis has been reported. Perturbations of 50% are applied to rain recharge, specific yield, coal seam horizontal permeability, specific storage and Gunnedah vertical permeability. This is sufficient for bracketing the range of uncertainty for the first three parameters. For the latter two, an order of magnitude or half order of magnitude perturbation would normally be applied. The -50% perturbation gives a half order of magnitude change, but +50% is a multiplier of 1.5. This means that reduced specific storage and Gunnedah vertical permeability are assessed adequately, but increased values could be tested at higher levels.
Steady-state calibration statistics are reported for each sensitivity run. Calibration performance is affected significantly only by higher rain recharge. This suggests that the adopted rain recharge is confined to a small range of uncertainty (or that the ratio of rain recharge to surficial permeability is well defined). The mass balance elements are well defined except for rain recharge perturbation.
6.8 UNCERTAINTY ANALYSIS
Sensitivity simulations in predictive mode provide a way of quantifying the uncertainty in predicted outcomes.
Mine inflow rate was found to be sensitive to coal seam permeability, resulting in an average of 1.6 ± 0.5 ML/day. For other property perturbations, the uncertainty was found to be much smaller.
The interception of alluvial flow was found to be sensitive to specific storage, resulting in an average of about 0.35 ± 0.2 ML/day. It has been remarked already that specific storage can reasonably vary by more than 50% without affecting a (transient) calibration. Hence, the real uncertainty in alluvial groundwater interception could be higher. However, higher interception occurs only with a lower specific storage value, and this has been tested adequately by a half order of magnitude change. The value for this parameter should be refined when model recalibration is done after proposed mining commences. This reviewer agrees with the AGE recommendation for model updates every five years, to guide adaptive management.
7.0 CONCLUSION
The Maules Creek Coal Project groundwater model has been developed competently and is regarded as “fit for purpose” for addressing cumulative
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
7
![Page 12: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/12.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
impacts from three mines, for estimating indicative dewatering rates, and for assessing regional potential groundwater impacts.
Model predictions are expected to be conservative for two main reasons:
Exclusion of structural controls that are likely to cause some compartmentalisation of effects in reality and to limit the drawdown extent towards alluvial aquifers; and
Probable overestimation of mine inflow.
Model predictions of mine inflow are likely to be overestimated for two main reasons:
Aggregation of coal plies into a thicker coal seam at a lower depth; and
No allowance for the time taken for spoil to reach saturation.
The stated objectives of the modelling study have been addressed satisfactorily; namely:
Estimation of mine inflow to the open cut void for 21 years;
Prediction of drawdown magnitude and extent;
Prediction of alluvial groundwater losses;
Prediction of impacts on stream baseflows and other groundwater users; and
Identification of risks that might necessitate mitigation measures or controls.
It is considered that the model would benefit from refinement through transient calibration when sufficient hydrographic data become available in the Permian formations. As recommended in the AGE report, transient calibration should be performed after the first five years of mining.
Drawdown predictions indicate that the Project will not have significant impacts external to the mined area. This conclusion is well substantiated.
The model anticipates no change in baseflow at the neighbouring creeks. This conclusion is well substantiated.
There is a prediction of reduced average lateral recharge of groundwater in the alluvial system, in the order of 50 ML/a. This estimate is sensitive to the adopted specific storage values which cannot be calibrated properly until transient calibration becomes possible. Even allowing for uncertainty in
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
8
![Page 13: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/13.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
specific storage, this volume of water is less than 1% of rain recharge over the model area. It is likely that Aston Resources can offset this volume by acquiring existing water licences.
8.0 REFERENCES
Australasian Groundwater & Environmental Consultants Pty Ltd, 2011, Maules Creek Coal Project Groundwater Impact Assessment. February 2011. Version 6.
MDBC (2001). Groundwater flow modelling guideline. Murray-Darling Basin Commission. URL: http://www.mdbc.gov.au/nrm/groundwater/groundwater_guides/
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
9
![Page 14: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/14.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
Tabl
e 1.
MO
DEL
APP
RA
ISA
L: M
aule
s Cre
ek C
oal M
odel
Q.
QU
ES
TIO
N
Not
App
licab
leor
Unk
now
n
RA
TIN
G
CO
MM
EN
T
1.0
THE
REP
OR
T
1.1
Is th
ere
a cl
ear s
tate
men
t of p
roje
ct o
bjec
tives
in th
e m
odel
ling
repo
rt?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d S
cope
of W
ork
Sec
tion
3.0
1.2
Is th
e le
vel o
f mod
el c
ompl
exity
cle
ar o
r ack
now
ledg
ed?
M
issi
ng
No
Yes
Im
pact
Ass
essm
ent M
odel
, med
ium
com
plex
ity. E
xecu
tive
Sum
mar
y in
clud
es th
e re
leva
nt s
tate
men
t.
1.3
Is a
wat
er o
r mas
s ba
lanc
e re
porte
d?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d Ta
bula
ted
for s
tead
y st
ate
calib
ratio
n. P
rese
nted
as
time-
serie
s gr
aphs
for t
he p
redi
ctio
n m
odel
. Als
o ta
bula
ted
for 1
0%
sens
itivi
ty ru
ns.
1.4
Has
the
mod
ellin
g st
udy
satis
fied
proj
ect o
bjec
tives
?
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
Sub
ject
to s
tate
d lim
itatio
ns.
1.5
Are
the
mod
el re
sults
of a
ny p
ract
ical
use
?
N
o M
aybe
Ye
s
2.0
DA
TA A
NA
LYSI
S
2.1
Has
hyd
roge
olog
y da
ta b
een
colle
cted
and
ana
lyse
d?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d In
clud
es a
fiel
d pr
ogra
m p
acke
r tes
ts; 8
pie
zos;
4 V
W p
iezo
ne
sts
(x2)
; wat
er s
ampl
es. N
o pr
ior i
nfor
mat
ion
on v
ertic
al
head
pro
files
.
2.2
Are
gro
undw
ater
con
tour
s or
flow
dire
ctio
ns p
rese
nted
? M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d Fo
r 199
2 C
offe
y no
rther
n ar
ea a
nd re
cent
con
tour
s de
velo
ped
usin
g sh
allo
w s
tead
y st
ate
targ
ets
(Per
mia
n/Q
uate
rnar
y m
ix).
2.3
Hav
e al
l pot
entia
l rec
harg
e da
ta b
een
colle
cted
and
an
alys
ed?
(rai
nfal
l, st
ream
flow
, irr
igat
ion,
floo
ds, e
tc.)
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d R
ain
resi
dual
mas
s an
alys
is is
don
e. S
tead
y st
ream
sta
ge
base
d on
gro
und
elev
atio
n m
inus
est
imat
ed in
cisi
on.
2.4
Hav
e al
l pot
entia
l dis
char
ge d
ata
been
col
lect
ed a
nd
anal
ysed
? (a
bstra
ctio
n, e
vapo
trans
pira
tion,
dra
inag
e,
sprin
gflo
w, e
tc.)
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d P
rivat
e gw
abs
tract
ion
from
allu
vium
not
ava
ilabl
e in
the
publ
ic
dom
ain.
2.5
Hav
e th
e re
char
ge a
nd d
isch
arge
dat
aset
s be
en a
naly
sed
for t
heir
grou
ndw
ater
resp
onse
? N
/AM
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d S
trong
cor
rela
tion
of g
roun
dwat
er h
ydro
grap
hs w
ith ra
infa
ll tre
nds,
sho
wn
by re
sidu
al m
ass
anal
ysis
. Qua
ntifi
ed v
ertic
al
head
gra
dien
ts in
new
VW
P h
oles
. One
faul
ty V
WP
.
2.6
Are
gro
undw
ater
hyd
rogr
aphs
use
d fo
r cal
ibra
tion?
N
/AN
o M
aybe
Y
es
2.7
Hav
e co
nsis
tent
dat
a un
its a
nd s
tand
ard
geom
etric
al
datu
ms
been
use
d?
No
Yes
In
cons
iste
ncy
in s
ome
TDS
/EC
val
ues;
som
e ra
tios
are
very
lo
w (<
0.6)
for a
bic
arbo
nate
wat
er. T
wo
anom
alou
s TD
S.
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
10
![Page 15: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/15.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
3.0
CO
NC
EPTU
ALI
SATI
ON
3.1
Is th
e co
ncep
tual
mod
el c
onsi
sten
t with
pro
ject
obj
ectiv
es
and
the
requ
ired
mod
el c
ompl
exity
?
Unk
now
n N
o M
aybe
Ye
s
3.2
Is th
ere
a cl
ear d
escr
iptio
n of
the
conc
eptu
al m
odel
?
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
Sec
tion
9.2.
3.3
Is th
ere
a gr
aphi
cal r
epre
sent
atio
n of
the
mod
elle
r’s
conc
eptu
alis
atio
n?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d Fi
gure
21
for d
urin
g-m
inin
g si
tuat
ion.
3D
geo
met
ry s
how
n in
Fi
gure
s 22
and
23
– re
mov
al o
f allu
vium
is il
lust
rativ
e.
3.4
Is th
e co
ncep
tual
mod
el u
nnec
essa
rily
sim
ple
or
unne
cess
arily
com
plex
?
Ye
s N
o
Sen
sibl
e st
ratig
raph
ic d
ivis
ion.
Plie
s lu
mpe
d in
to la
yers
hav
ing
aggr
egat
e th
ickn
esse
s –
an a
ccep
tabl
e co
mpr
omis
e.
4.0
MO
DEL
DES
IGN
4.1
Is th
e sp
atia
l ext
ent o
f the
mod
el a
ppro
pria
te?
No
May
be
Yes
Ext
ensi
ve.
4.2
Are
the
appl
ied
boun
dary
con
ditio
ns p
laus
ible
and
un
rest
rictiv
e?
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
Gen
eral
ly n
o-flo
w a
t dis
tant
bor
ders
, and
fixe
d he
ads
in L
ayer
2
(Gun
neda
h Fm
.). N
ot c
lear
if fl
ow b
ound
ary
has
been
ap
plie
d to
Nar
rabr
i Fm
. (La
yer 1
) – p
roba
bly
no fl
ow, a
s ap
plie
d in
dee
p la
yers
. Cou
ld h
ave
had
spat
ially
var
ying
fixe
d he
ad in
allu
vium
from
NO
W m
odel
. Stre
ams
are
RIV
cel
ls
(ofte
n =
DR
N).
Min
ing
by D
RN
cel
ls.
4.3
Is th
e so
ftwar
e ap
prop
riate
for t
he o
bjec
tives
of t
he s
tudy
?
N
o M
aybe
Ye
s M
OD
FLO
W-S
UR
FAC
T in
DO
S m
ode
(no
GU
I). T
ime
vary
ing
mat
eria
l pro
perti
es h
andl
ed b
y st
art-s
top
sim
ulat
ion.
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
11
![Page 16: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/16.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
Tabl
e 2.
MO
DEL
APP
RA
ISA
L: M
aule
s Cre
ek C
oal M
odel
Q.
QU
ES
TIO
N
Not
App
licab
leor
Unk
now
n
RA
TIN
G
CO
MM
EN
T
5.0
CA
LIB
RA
TIO
N
5.1
Is th
ere
suffi
cien
t evi
denc
e pr
ovid
ed fo
r mod
el c
alib
ratio
n?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d S
ever
al li
nes
of e
vide
nce:
sca
tterg
ram
for s
tead
y-st
ate;
pe
rform
ance
sta
tistic
s fo
r ste
ady
stat
e (%
RM
S a
nd a
bsol
ute
RM
S);
resi
dual
at e
ach
bore
; wat
er ta
ble
cont
our m
ap.
Pre
sum
ably
use
d P
ES
T –
not s
tate
d.
5.2
Is th
e m
odel
suf
ficie
ntly
cal
ibra
ted
agai
nst s
patia
l ob
serv
atio
ns?
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
Dra
win
g 14
com
pare
d w
ith “o
bser
ved”
con
tour
map
(Dra
win
g 11
).
5.3
Is th
e m
odel
suf
ficie
ntly
cal
ibra
ted
agai
nst t
empo
ral
obse
rvat
ions
?N
/AM
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d S
tead
y-st
ate
calib
ratio
n on
ly.
5.4
Are
cal
ibra
ted
para
met
er d
istri
butio
ns a
nd ra
nges
pl
ausi
ble?
Mis
sing
N
o M
aybe
Ye
s C
onsi
sten
t with
aqu
ifer t
ests
. Rai
n re
char
ge ra
tes
are
cons
iste
nt
with
dis
trict
kno
wle
dge
and
prio
r mod
ellin
g. S
houl
d no
t rep
ort S
s fo
r Lay
er 1
.
5.5
Doe
s th
e ca
libra
tion
stat
istic
sat
isfy
agr
eed
perfo
rman
ce
crite
ria?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d 4.
9% S
RM
S a
nd 5
.7m
RM
S; m
axim
um re
sidu
al 1
4m. S
RM
S is
ve
ry g
ood
and
mee
ts th
e M
DB
C g
uide
line.
5.6
Are
ther
e go
od re
ason
s fo
r not
mee
ting
agre
ed
perfo
rman
ce c
riter
ia?
N/A
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
Geo
logi
cal c
ompl
exity
. Mix
ed w
ater
leve
ls fr
om m
any
year
s.
6.0
VER
IFIC
ATI
ON
6.1
Is th
ere
suffi
cien
t evi
denc
e pr
ovid
ed fo
r mod
el
verif
icat
ion?
N
/AM
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d
6.2
Doe
s th
e re
serv
ed d
atas
et in
clud
e st
ress
es c
onsi
sten
t w
ith th
e pr
edic
tion
scen
ario
s?
N/A
Unk
now
n N
o M
aybe
Ye
s
6.3
Are
ther
e go
od re
ason
s fo
r an
unsa
tisfa
ctor
y ve
rific
atio
n?
N/A
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
7.0
PRED
ICTI
ON
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENTHANSEN BAILEY
Groundwater Impact Assessment M
12
![Page 17: 0986 M Groundwater Impact Assessment Peer Review](https://reader034.vdocuments.us/reader034/viewer/2022051315/627a741cfdd9d139ac2c5693/html5/thumbnails/17.jpg)
110215 Review Maules Creek Groundwater Final.docHC2011/3
7.1
Hav
e m
ultip
le s
cena
rios
been
run
for c
limat
e va
riabi
lity?
N
/AM
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d N
o cl
imat
e va
riabi
lity
is s
imul
ated
. Ste
ady
aver
age
rain
is a
pplie
d –
appr
opria
te fo
r the
mod
el p
urpo
se.
7.2
Hav
e m
ultip
le s
cena
rios
been
run
for o
pera
tiona
l /m
anag
emen
t alte
rnat
ives
?
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
Sin
gle
min
e pl
an –
with
and
with
out t
wo
neig
hbou
ring
min
es.
Irrig
atio
n gw
abs
tract
ion
excl
uded
. App
ropr
iate
for t
he m
odel
pu
rpos
e. T
wo
final
voi
d op
tions
are
mod
elle
d.
7.3
Is th
e tim
e ho
rizon
for p
redi
ctio
n co
mpa
rabl
e w
ith th
e le
ngth
of t
he c
alib
ratio
n / v
erifi
catio
n pe
riod?
Mis
sing
N
o M
aybe
Y
es
21 y
ears
pre
dict
ion
base
d on
ste
ady
stat
e ca
libra
tion
and
prio
r/tex
tboo
k st
orag
e pr
oper
ties.
7.4
Are
the
mod
el p
redi
ctio
ns p
laus
ible
?
N
o M
aybe
Ye
s M
ine
inflo
w <
4 M
L/da
y; a
vera
ge <
2 M
L/da
y. C
onsi
sten
t with
prio
r m
odel
est
imat
es, b
ut c
onse
rvat
ivel
y hi
gh. N
o ac
cura
te
know
ledg
e of
cur
rent
min
e in
flow
at B
ogga
bri
and
Tarr
awon
ga,
but T
arra
won
ga is
bel
ieve
d to
be
<0.1
ML/
d an
d B
ogga
bri <
0.5
ML/
d.
8.0
SEN
SITI
VIT
Y A
NA
LYSI
S
8.1
Is th
e se
nsiti
vity
ana
lysi
s su
ffici
ently
inte
nsiv
e fo
r key
pa
ram
eter
s?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d D
one
for r
ain
rech
arge
, spe
cific
yie
ld, s
peci
fic s
tora
ge,
Gun
neda
h K
z, c
oal s
eam
Kx,
for 5
0% p
ertu
rbat
ion.
Thi
s w
ill
brac
ket l
ikel
y un
certa
inty
for t
he fi
rst t
wo
and
the
last
, but
not
for
Spe
cific
sto
rage
(Ss)
and
Kz.
Val
ues
are
low
ered
by
half
orde
r of
mag
nitu
de (m
ultip
lier 0
.5),
whi
ch is
ade
quat
e, b
ut h
ighe
r val
ues
shou
ld u
se a
mul
tiplie
r of 3
or 5
inst
ead
of 1
.5.
8.2
Are
sen
sitiv
ity re
sults
use
d to
qua
lify
the
relia
bilit
y of
m
odel
cal
ibra
tion?
Mis
sing
D
efic
ient
A
dequ
ate
Ver
y G
ood
RM
S a
nd S
RM
S a
re re
porte
d.
8.3
Are
sen
sitiv
ity re
sults
use
d to
qua
lify
the
accu
racy
of
mod
el p
redi
ctio
n?
M
issi
ng
Def
icie
nt
Ade
quat
e V
ery
Goo
d W
ater
bud
get i
tem
s ar
e re
porte
d.
9.0
UN
CER
TAIN
TY A
NA
LYSI
S
9.1
If re
quire
d by
the
proj
ect b
rief,
is u
ncer
tain
ty q
uant
ified
in
any
way
?
Mis
sing
N
o M
aybe
Ye
s R
ange
in a
vera
ge a
nd m
axim
um m
ine
inflo
w is
repo
rted
for
sens
itivi
ty a
naly
sis.
Rec
over
y tim
e is
inve
stig
ated
for 2
spo
il re
char
ge ra
tes.
Groundwater Impact Assessment
MAULES CREEK COAL PROJECT ENVIRONMENTAL ASSESSMENT HANSEN BAILEY
M
13