06 safeti offshore

Upload: huylan2204

Post on 04-Jun-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 06 Safeti Offshore

    1/25

    Safeti Offshore An Introduction

  • 8/14/2019 06 Safeti Offshore

    2/25

    Det Norske Veritas AS. All rights reserved.

    Background

    2

    Over the years, DNV has developed a number of tools for safety analysis ofOffshore installations

    Offshore Hazard and Risk Analysis Toolkit (OHRAT)

    - First version released in 1992 in direct response to Piper Alpha disaster- Joint industry project with numerous Operators, Consultants and EPCs

    Neptune

    - The OHRAT concept taken into Microsoft Windows environment (1999)

    Spreadsheet models (e.g. SOQRATES) (2005+)

    Phast also used for Offshore consequences

    All these tools have their own respective benefits and drawbacks

    As a result, in 2009 DNV started discussing a new tool to harness our Offshoreexperience so far and build a new tool for the future

    Welcome to Safeti Offshore!

  • 8/14/2019 06 Safeti Offshore

    3/25

    Det Norske Veritas AS. All rights reserved.

    Safeti Offshore

    A joint collaboration involving significant investment between:

    - DNV Consulting, providing their Offshore QRA and domain experience

    - DNV Software, delivering software engineering and mathematical modelling expertise

    Design discussions during 2009-2010

    Project and coding kick-off January 2011, starting with Proof of Concept

    First internal release planned for end-2012, plus regular interim releases

    Key project goals:- Develop an integrated and uniform approach to Offshore QRA based upon international

    standards such as ISO 17776 and NORSOK Z013

    - Integration of separate QRA models within one common software tool

    - Support risk management throughout the lifecycle of an installation from planning to

    decommissioning

    - Provision of a standardised tool building on the well-established Phast architecture

    - Benefit from software economies of scale

    3

  • 8/14/2019 06 Safeti Offshore

    4/25

    Det Norske Veritas AS. All rights reserved.

    Whats new in Safeti Offshore?

    Safeti Offshore incorporates significant new technology compared with currentSafeti (Phast Risk)

    Offshore asset hierarchy

    Automatic release case generation (subject to user defined rules)

    3-D graphical input and viewer

    Powerful data input grid

    New mathematical modelling, including:

    - Improved discharge modelling, allowing for safety systems:

    - Detection, isolation and blowdown

    - Integration of DNV Express, a probabilistic model for module explosions

    - New compartment fire model taking into account module geometry and flame development- Subsea releases

    - Escalation modelling

    Plus everything else that Safeti currently contains

    4

  • 8/14/2019 06 Safeti Offshore

    5/25

    Det Norske Veritas AS. All rights reserved.

    Safeti Offshore Basic Workflow

    Assets tab:

    Define Installation Areas

    Define Safety Barriers, Walls and Decks

    Define Escape Routes

    Define Structural Elements

    Process Tab:

    Define Isolatable Sections

    Define Equipment items

    Define Process Case options

    Define Risers & Pipelines

    Define Wellgroups

    Generate Leak Locations (Scenarios)and Cases (Safety Systems) for eachsection

    Add User Defined Scenarios

    Assign Explosion Targets &Vulnerabilities

    Define other data:

    Materials

    Weathers

    Worker population

    Then perform the calculations: Inventory volume

    Leak frequencies

    Consequences

    Risk

    Review results and perform sensitivityanalysis

    5

  • 8/14/2019 06 Safeti Offshore

    6/25

    Det Norske Veritas AS. All rights reserved.

    Building a 3D representation of the QRA (1)

    6

    2. Then add StructuralElements

    1. First add your

    installation areas (in termsof cuboids)

  • 8/14/2019 06 Safeti Offshore

    7/25

    Det Norske Veritas AS. All rights reserved.

    Building a 3D representation of the QRA (2)

    7

    3. Next add physical

    safety barriers, such aswalls and decks. Thesewill be used later asexplosion targets for yourLeak Locations

    (scenarios)

    4. Add isolatable sectionswith associated equipment,valves and pipework

  • 8/14/2019 06 Safeti Offshore

    8/25

    Det Norske Veritas AS. All rights reserved.

    Building a 3D representation of the QRA (3)

    Until finally the full 3D model is complete including:

    - Risers

    - Pipelines

    - Escapeways

    8

  • 8/14/2019 06 Safeti Offshore

    9/25

    Det Norske Veritas AS. All rights reserved.

    New Data Input Grid

    Allows import from other systems and manipulation of data in bulk grid format

    Comparable with Excel cells supports Copy and Paste from Excel

    9

    Data can begrouped accordingto your specificrequirements

  • 8/14/2019 06 Safeti Offshore

    10/25

    Det Norske Veritas AS. All rights reserved.

    New Time Varying Discharge Model

    Takes account of time dependent release characteristics together with incorporatedSafety Systems, for example:

    - Detection

    - Isolation

    - Blowdown

    10

  • 8/14/2019 06 Safeti Offshore

    11/25

    Det Norske Veritas AS. All rights reserved.

    Leak

    LocationIS1-G

    1.000E-14

    1.000E-13

    1.000E-12

    1.000E-11

    1.000E-10

    1.000E-09

    1.000E-08

    1.000E-07

    1.000E-06

    1.000E-05

    1.000E-04

    1.000E-03

    1.000E-02

    1.000E-01

    1.000E+00

    0.0 200.0 400.0 600.0 800.0 1000.0 1200.0 1400.0 1600.0 1800.0 2000.0

    Probability

    Time [s]

    Cumulative Probability of Ignition

    Small (main)

    Medium (main)

    Lare (main)

    Leak

    LocationIS1-G!E"#l$%i$n &are'

    1.000E-06

    1.000E-05

    1.000E-04

    1.000E-03

    1.000E-02

    1.000E-01

    1.000E+00

    0.0000 0.2000 0.4000 0.6000 0.8000 1.0000 1.2000

    Probability

    (givenI

    gnition)

    Pressure [bar]

    Aggregated Exceedance Probability vs Explosion verpressure

    Small (main)

    Medium (main)

    Lare (main)

    New probabilistic explosion model - EXPRESS

    EXPRESS is used to calculate the following:

    - Flammable cloud dispersion in source module (cloud volume)

    - Detection, Ignition and Explosion probabilities

    - Explosion Overpressure Exceedance Curves (at each defined target)

    11

  • 8/14/2019 06 Safeti Offshore

    12/25

    Det Norske Veritas AS. All rights reserved.

    New Compartment Fire Model

    Bridges the gap between existing Phastfire models and CFD

    Builds upon the existing Phast fire

    models by combining them in new ways

    Fires begin in the source module

    Fires allowed to develop and escalatebeyond the source module:

    - Overall volume of the flame is conservedand spread over the platform inaccordance with layout and geometry

    Also handles scenario where fire walls

    are damaged or removed by initialexplosion prior to fire

    12

  • 8/14/2019 06 Safeti Offshore

    13/25

    Det Norske Veritas AS. All rights reserved.

    New Compartment Fire Model An example (1)

    13

    Wind

    Geometry layout and setup consists of definingvarious platform elements, for example

    Horizontal decks

    Vertical walls

    Partial walls (eitherrestricted height or width)Fire start location

    Solid fire walls

  • 8/14/2019 06 Safeti Offshore

    14/25

    Det Norske Veritas AS. All rights reserved.

    New Compartment Fire Model An example (2)

    14

    Spill rate: 3.5kg/s

    Spill rate: 1.5kg/s

    Pool fire confined to the sourcemodule and modelled as cone

    Flame grows in size. Spreads toadjacent module (represented as

    cuboid) and outside the platform(represented as cylinders)

  • 8/14/2019 06 Safeti Offshore

    15/25

    Det Norske Veritas AS. All rights reserved.

    New Compartment Fire Model An example (3)

    15

    Spill rate: 11.0kg/s

    Spill rate: 16.0kg/s

    Fire in adjacent module now grows larger

    and it extends outside platform in multiplelocations. External wind effects now tilt theexternal flames.

    Fire now at maximum size inside the module. Firemodel considers transition of burning process from

    fuel controlled to ventilation controlled inside themodule. This is shown as a similar fire size insidethe module (despite the increased spill rate) coupledwith increased external fires

  • 8/14/2019 06 Safeti Offshore

    16/25

    Det Norske Veritas AS. All rights reserved.

    Risk Results

    Detailed risk results produced for each potential outcome

    Work on-going to develop sophisticated reporting mechanisms

    16

  • 8/14/2019 06 Safeti Offshore

    17/25

    Det Norske Veritas AS. All rights reserved.

    Overview of Typical Results (1)

    Results related to frequency, consequence and risk results

    Frequency results

    - Generally frequencies per year for the specific end events

    - Grouped frequencies per year according to high-level hazard categories- Grouped frequencies by area of the platform

    Consequence results

    - Discharge, release rate data (by event scenario and safety system) including flow rate,

    duration- Explosion results: EXPRESS / DAL detailed results; overpressure / impact at targets;

    escalation result

    - Fire results: fire and radiation extent; impact at targets; escalation result

    - Toxic results: dispersion extent; impact at targets

    - Smoke results: dispersion extent; impact at targets

    17

  • 8/14/2019 06 Safeti Offshore

    18/25

    Det Norske Veritas AS. All rights reserved.

    Overview of Typical Results (2)

    Personnel risk

    - Number of fatalities by area, by event, by immediate / escape / evacuation

    - LSIR (Location Specific Individual Risk). The frequency with which a person located in aparticular area would become fatalities. This can be calculated on the assumption that a

    person is constantly present in an area, i.e. 365 days per year and 24 hours per day.- Maybe LSIR contours not so relevant for offshore. But areas may be colour coded according to LSIR

    results similar to LSIR contours

    - NOTE LSIR is key as all other calculations use it as basis

    - Potential loss of life (PLL) per area and for the entire facility

    - FAR (Fatal accident rate), for personnel inside the plant. The fatal accident rate (FAR) is theexpected number of fatalities per 108 hours of exposure:

    - FAR value for a defined group of personnel e.g. process operators.

    - FAR value for one specific area (Area FAR)

    - IRPA (Individual Risk per Annum). The probability of a given individual becoming a fatality in

    a year as a result of their work associated with an installation or group of installations.Positional IRPA

    - FN curves, Societal risk or Aggregate risk

    18

  • 8/14/2019 06 Safeti Offshore

    19/25

    Det Norske Veritas AS. All rights reserved.

    Sample Facility Geometry - FPSO

    19

  • 8/14/2019 06 Safeti Offshore

    20/25

    Det Norske Veritas AS. All rights reserved.

    Sample Facility Geometry - FPSO

    20

  • 8/14/2019 06 Safeti Offshore

    21/25

    Det Norske Veritas AS. All rights reserved.

    Sample Facility Geometry Jacket Platform

    21

  • 8/14/2019 06 Safeti Offshore

    22/25

    Det Norske Veritas AS. All rights reserved.

    Sample Facility Geometry Semi-submersible

    22

  • 8/14/2019 06 Safeti Offshore

    23/25

    Det Norske Veritas AS. All rights reserved.

    Sample Facility Geometry Semi-submersible

    23

  • 8/14/2019 06 Safeti Offshore

    24/25

    Det Norske Veritas AS. All rights reserved.

    Towards the Future - Timeline

    Safeti Offshore initial development project will run until end of 2012

    Initial project use within DNV from early 2013

    Timescales for commercialisation and rollout to our existing Phast Risk customers is

    not yet defined:- We would greatly welcome your feedback on this topic

    If anyone has specific needs for their own Offshore QRA analysis, now is a goodtime to talk with us. We have the possibility to include:

    - New calculation models

    - Specific features and customisations

    - Additional reporting mechanisms

    24

  • 8/14/2019 06 Safeti Offshore

    25/25