© 2001-2008, all rights reserved, douglas d. gransberg 1 project management & controls douglas...
TRANSCRIPT
© 2001-2008, All rights reserved, Douglas D. Gransberg 1
Project Management & Controls
Douglas D. Gransberg, Ph.D., P.E., C.C.E.
Work Breakdown Structure
© 2001-2008, All rights reserved, Douglas D. Gransberg 2
Organizing for Project Management
• Internal Organization– PM controlled– Project-oriented
• External organization– Hierarchy above PM– Report-oriented
• Client Interface– Marketing– Legal
© 2001-2008, All rights reserved, Douglas D. Gransberg 3
Organizational Structures
• Customer: by client requirement– Government– Commercial
• Territorial: by geographic location– Domestic– International– Southwestern
© 2001-2008, All rights reserved, Douglas D. Gransberg 4
Internal Organization
• Positions– Estimator– Scheduler– Field
• Responsibilities– Budget– Schedule– Production
• Integrator: The Project Work Breakdown Structure
© 2001-2008, All rights reserved, Douglas D. Gransberg 5
Example Organization 1
Organizational Chart by Functions
Concrete Steel
Structural
Design
Testing Foundations
Geotechnical
Design
Hydraulics Hydrology
Hydraulic
Design
Project Manager
© 2001-2008, All rights reserved, Douglas D. Gransberg 6
Example Organization 2O
verh
ead
Organizational Chart by Project Teams
Pro
duct
ion
Structures Geotech Hydro
Project
Team #1
Structures Geotech Hydro
Project
Team #2
Structures Geotech Hydro
Project
Team #3
Project
Manager
© 2001-2008, All rights reserved, Douglas D. Gransberg 7
Project Work Breakdown Structures
“ …. a schematic presentation of the disaggregation-integration process .. to execute the project.” Shtub, et al, 1994
• Disaggregation: break down to finite components of work [Work Packages]
• Integration: allocate resources– Assign responsibility– Schedule
© 2001-2008, All rights reserved, Douglas D. Gransberg 8
Work Breakdown Structure
• Functional - breakdown by location/space & activity/function
• System - breakdown by building assemblies/systems
• Component - breakdown by materials• Activity - breakdown by tasks (verb + noun)• Cost - breakdown by cost categories
© 2001-2008, All rights reserved, Douglas D. Gransberg 9
WBS for Wood Frame HouseFunctional
Sitework Master BedroomEntry Bedroom #1Living Room Bedroom #2Family Room Bedroom #3Kitchen HallBathroom #1 Heater SpaceBathroom #2 Utility Room
© 2001-2008, All rights reserved, Douglas D. Gransberg 10
CSIGeneral ConditionsSite WorkConcreteMasonrySteelWoods & PlasticsThermal & MoistDoors WindowsFinishesSpecialtiesEquipmentHVACElectrical
WBS for Wood Frame HouseSystems
UniformatFoundationSubstructureSuperstructureExterior ClosureRoofingInterior ConstructionMechanicalElectricalGeneral ConditionsSpecialtiesSite Work
© 2001-2008, All rights reserved, Douglas D. Gransberg 11
Clear SiteBuilding LayoutForm/Pour FootingsPier MasonryWood Floor SystemRough Framing WallsRough Framing RoofDoors and WindowsExterior Wall BoardExterior InsulationRough PlumbingRough HVACRough ElectricalShingles
WBS for Wood Frame HouseComponent
Exterior SidingExterior Finish CarpentryHang DrywallFinish DrywallCabinetsExterior PaintInterior Finish CarpentryInterior PaintFinish PlumbingFinish HVACFinish ElectricalFlooringGrading & LandscapingPunch List
© 2001-2008, All rights reserved, Douglas D. Gransberg 12
WBS Components
• Objective : THE PRODUCT• Deliverables• Schedules• Budgets• Performance measures• Responsibilities
© 2001-2008, All rights reserved, Douglas D. Gransberg 13
Work Package
• Defined element of work– Series of activities– Result is a deliverable or major component of a
deliverable– Milestone on schedule
• Assigned responsibility• Scheduled start & finish• Budget
© 2001-2008, All rights reserved, Douglas D. Gransberg 14
Work Package Definition
• Logical• Contribute to:
– Deliverable– Milestone
• Single responsibility• Budget controlled by responsibility
© 2001-2008, All rights reserved, Douglas D. Gransberg 15
Work Breakdown StructureTotal Project
Subproject A Subproject B Subproject C
Unit A Unit B Unit C
Area A Area B Area C
Account A Account B Account C
Work Package
A
Work Package
B
Work Package
C
Activity A Activity C Activity D Activity EActivity B6
5
4
3
2
1
0
© 2001-2008, All rights reserved, Douglas D. Gransberg 16
WBS Format
- A c tivity A- A c tivity B- A c tivity C
- A c tivity D- A c tivity E- A C tivity F
- A c tivity X- A c tivity Y- A c tivity Z
W ork P ackag e # 1 W ork P ackag e # 2
F eatu re # 1
W ork P ackag e # 1 4
F eatu re # 2
S u b ob jec tive # 1
W ork P ackag e # 2 1
F eatu re # 3
S u b ob jec tive # 2
W ork P ackag e # n
F eatu re # n
S u b ob jec tive # n
O B JE C TIV ELevel 1: Project
Level 2: Area
Level 3: Organization
Level 4: Work
Level 5: Schedule
© 2001-2008, All rights reserved, Douglas D. Gransberg 17
WBS Development Example
Project: Design & Build Tool Shed w/bathroomDeliverables:
- Real Estate- Septic Permit- Building Permit- Design- Building- Sidewalk
© 2001-2008, All rights reserved, Douglas D. Gransberg 18
Work Breakdown StructureWork Breakdown Structure
Find Land Foundation
Structure
Finishes
Earthwork
Structure
Septic
Building
Walk
Get Loan
Purchase
Tests Application
PermitApplication
Permit
Organization
Work Packages
Activities
Project
© 2001-2008, All rights reserved, Douglas D. Gransberg 19
CA1
CA2
CA4
CA3
CA5
Integrating the WBS with the Organization
CA Deliverables
CA1: Foundation Plans
CA2: Reactions @Foundation
CA3: Structural Plans
CA4: Arch Details to Structural Plans
CA5: Finish Plans
© 2001-2008, All rights reserved, Douglas D. Gransberg 20
Integrated Take-off
• Estimator– Quantities– Production Rates– Crew Sizes– Mark-ups– Bid
• Scheduler– Activities– Durations– Resources– Budget– Schedule of Values
© 2001-2008, All rights reserved, Douglas D. Gransberg 21
Activity Take-off
• Types of Activities– Production: consume time, resource, cost
• Erect structural steel
– Administrative: consume time,cost in overhead• Review and approve shop drawings
– Logistic: consume time, cost in associated production activity.
• Order and ship structurual steel
© 2001-2008, All rights reserved, Douglas D. Gransberg 22
Activity Take-off
• Initial take-off should be uncontrained• Estimate the duration of each activity
– Duration @ level of management– Use person-hours only if you intend to influence
the actions of every person every hour of the work day
• Establish relationships between activities
© 2001-2008, All rights reserved, Douglas D. Gransberg 23
Activity Take-off
• Allocate resources to each activity– Duration reflects assumed level of resource– Introduce resource constraints
• Types of Resources– Personnel– Equipment– Space
© 2001-2008, All rights reserved, Douglas D. Gransberg 24
Timing
• Pre-award (bid preparation)– Conceptual schedule– Detailed cost estimate
• Post-award– Detailed Schedule– Revised estimate for alternates, final subs, and
correct errors.– Must match exactly with cost control system.
© 2001-2008, All rights reserved, Douglas D. Gransberg 25
Pre-award Scheduling Concerns
• Can project be completed by specified contract completion date?
• If not, which activities are the most efficient to crash?
• What is the cost of accelerated work?• What administrative/logistic activities are
on the critical path? Cost to expedite?• What are the critical resources and can
they be leveled?
© 2001-2008, All rights reserved, Douglas D. Gransberg 26
Post-award Scheduling Concerns• What impact to alternates have on original
plan?• How do errors and omissions in bid impact the
original project plan?• Upon final sub selection, can actual subs meet
as-bid schedule?• At what rate should the project earn value?• Does project cash flow match financing
assumptions?
© 2001-2008, All rights reserved, Douglas D. Gransberg 27
Matching Elements
• From the WBS, the following MUST match between the estimate and the schedule:– Activity code numbers– Activity budgets– Activity resource allocation– Completion dates and milestones– Estimated Cost + Profit = Schedule of Values– Pay estimate cash flow projection
© 2001-2008, All rights reserved, Douglas D. Gransberg 28
Schedule
• Use of scheduling software to solve project network
• Convert to bar chart for easy manipulation and communication of schedule information
• Load with activity resource requirements• Identify resource shortfalls
© 2001-2008, All rights reserved, Douglas D. Gransberg 29
Identify resource shortfalls
• Integrate resource requirements with scheduled activity completions
• Mark maximum resource capacities• Reschedule to eliminate shortfalls or obtain
additional resources for limited periods of time.
© 2001-2008, All rights reserved, Douglas D. Gransberg 30
Identify resource shortfalls
0
1
2
3
4
5
6
7
JAN FEB MAR APR MAY JUN
Engineer(4)
© 2001-2008, All rights reserved, Douglas D. Gransberg 31
Conclusions
• PM must ensure that Scheduler and Estimator communicate during bid preparation and after award.
• The best means to ensure estimate and schedule are coordinated is through development of a good WBS.
• Must do some scheduling during bid prep to identify time constraints for estimator.