znd332_a-base & top plate & anchors-rev-e (repaired)
TRANSCRIPT
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
1/15
ZND332_A-AMT-Td-0002-Rev.
Page. 1
ZND332_A-AMT-Td-0002-Rev. E
FAST PLANETS Co Ltd.,
ENGINEERING DEPARTMENT
P.0. BOX : 34620
RIYADH 15978
Base & Top Plate Connection Calculation(CI & 3G 2011 PROJECT)
Site No.: ZND332_ASite Name: ZND332_A / Bldg. of Ali Hussain Al-Sageer/ Dammam
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
2/15
ZND332_A-AMT-Td-0002-Rev.
Page. 2
Preface
General:
This document contains the capacity calculations of base and top plate and its weldedjoints, bolted joints and chemical anchorage bolts supporting the steel frames of the
equipment shelter.
The document consists of drawings and calculations necessary to assess the plates and its
connection capacity.
Analyzed by: Checked by: Approved by:
J.B.Vasquez J. Abo Hasson F.C.Falgui
Telecom Engineer Structural Engineer Prin. Structural Engineer
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
3/15
ZND332_A-AMT-Td-0002-Rev.
Page. 3
A. Connection Anchorage Check to the Existing Concrete Slab & to Bottom Plate
1. JOINT 17 (Exterior Column = 200 x 600)most Critical Joint
A) Tension
From STAAD Pro Output, Factored forces (Please refer to page 11/30 of STAAD Output)
Rx = -1.65 kNs Ry = -25.82 kNs Rz = 45.06 kNs (Load No. 10)
The orthogonality/45 degree direction of horizontal forces has been included in the load combinations of
STAADPro Inputs (Load Nos. 13 & 14) and from the results as per Support reactions, the values of forces are
critical. Please see page 11/30 of STAAD Pro outputs for reference.
Tension = -25.82 kNs
Actual tension for 1Anchor Bolt = 25.82 / 4 = 6.455 kNs
Using UpatUKA 3 EAP chemical anchor, M20
Shear: 27.0kN (@edge distance = 170 mm)
(@anchor spacing = 340 mm)
However for uniformity the size of bottom plate of 250 x 500mm is adopted.
100
200
100
100 300 100
500
factor 1 = ( 1 + 100 / 170) / 2 = 0.794
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
4/15
ZND332_A-AMT-Td-0002-Rev.
Page. 4
factor 2 = ( 1 + 170 / 170) / 2 = 1.00
factor 3 = ( 1 + 100 / 340) / 2 = 0.647
factor 4 = ( 1 + 340 / 340) / 2 = 1.00
red. F = 0.794 x 0.647 x 1.0 0 x 1.00 x 27.0 = 13.87 kNs > 6.455 kNs OK!
2. JOINT 17 ( Exterior Column = 200 x 600)most Critical JointB) Shear
From STAAD Pro Output, Factored forces (Please refer to page 11/30 of STAAD Output)
Rx = -15.65 kNs Ry = 40.74kNs Rz = 101.41 kNs (Load No.12)
The orthogonality/45 degree dirction of horizontal forces has been included in the load combinations of
STAADPro Inputs(Load Nos. 13 & 14) and from the results as per Support reactions, the values of forces are n
critical. Please see page 11/30 of STAAD Pro outputs for reference.
Total Factored Shear, V = (15.65)\2
+ 101.412
)0.50
= 102.61 kNs
Considering the effect of friction. Vf
Vf = 0.90x Fy x U, where U = 0.55
Vf = 0.90 x40.74 x 0.55
Vf = 20.17 kNs
Net Shear, V n = 102.61 - 20.17 = 82.44 kNs
Actual shear for 1Anchor Bolt = 82.44 / 4 = 20.61 kNs
Using UpatUKA 3 EAP chemical anchor, M20
Shear: 27.0kN (@edge distance = 200 mm)
(@anchor spacing = 340 mm)
However for uniformity the size of bottom plate of 250 x 500mm is adopted.
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
5/15
ZND332_A-AMT-Td-0002-Rev.
Page. 5
100
200
100
100 300 100
500
factor 1 = ( 1 + 100 / 200) / 2 = 0.750
factor 2 = ( 1 + 200 / 200) / 2 = 1.00
factor 3 = ( 1 + 100 / 340) / 2 = 0.647
factor 4 = ( 1 + 340 / 340) / 2 = 1.00
red. F = 0.750 x 0.647 x 1.0 0 x 1.00 x 27.0 = 13.10 kN s < 20.61 kNs Not OK!
Therefore shear key is required.
Net Shear to be resisted by shear key = 4(20.6113.10) = 30.04 kNs
Consider a 2- 100 mm x 200 mm x 20 mm shear plate. Since the effective area will be 50 mm that will be embedded
into the concrete, the bearing pressure developed by the shear plate is = 30.04 x 1000 / (50 x 200) = 3.004 mPa
The max bearing pressure as per AISC = 0.35fc = 0.35(20) = 7.0 mPa > 3.004 mPa Therefore OK!
Check for thickness of the plate:
M = 3.004 x 200 x 50 x (50 + 25) = 2253000 N-mm
fb = 6M / bd2
fb = 6 x 2253000 / 200d2
Allow Fb = 0.75Fyd = 0.75 x 248 = 186 mPa
d2 = 6 x 2253000 / (200) x 186
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
6/15
ZND332_A-AMT-Td-0002-Rev.
Page. 6
d = 19.06 mm
However, the thickness of the shear plate is adopted as 20mmdue to the following facts;
1.
The shear plate is subjected to corrosion which is not considered in the calculations.
2. The strength of the shear plate is reduced by the intense heat due to welding process.3. The shear plate is subjected to thermal loads due to temperature changes which is not considered in th
calculations.
4. The minimum thickness of plate if 6 mm thick of weld is used is from 12 -20mm as per AISC manua
Check for Weld Capacity:
1.Shear Plate
P = 30.04 kNs Fu = 485 Mpa (for E-70XX) (Please refer to page 11/30 of STAAD Output)
fd = P/A Throat = 0.707 x 6 = 4.242 mm
The critical length of weld is 200 mm;
A = (200) x 4.242 = 848.40 mm2
fd = ( 30.04 x 1000 ) / 848.40 = 35.41 mPa
F = 0.30 Fu
F = 0.30 x 485
F = 145.5 mPa > fd = 35.41 mPa OK!
Therefore adopt 2-100 x 200 x 20 shear keys collinear with the longer side in all bottom plate plates
Weld Capacity Check:1. Bottom plate to Stiffener/column connection
P = 102.61 kNs Fu = 485 Mpa (for E-70XX)
fd = P/A Throat = 0.707 x 6 = 4.242 mm
From inspection , the length of weld is 175 x 3 = 525 mm
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
7/15
ZND332_A-AMT-Td-0002-Rev.
Page. 7
A = (525) x 4.242 = 2227.05 mm2
fd = ( 102.61 x 1000 ) / 2227.05 = 46.07 mPa
F = 0.30 Fu
F = 0.30 x 485
F = 145.5 mPa > fd = 46.07 mPa OK!
1. Top PlateP = 102.61 kNs Fu = 485 Mpa (for E-70XX) (Please refer to page 11/30 of STAAD Output)
fd = P/A Throat = 0.707 x 6 = 4.242 mm
From inspection, the length of weld is 270 x 3 = 810 mm
A = (810 x 4.242 = 3436.02 mm2
fd = ( 102.61 x 1000 ) / 3436.02 = 29.86 mPa
F = 0.30 Fu
F = 0.30 x 485
F = 145.5 mPa > fd = 29.86 mPa OK!
B. Thickness of the 200 x 500 mm2
Bottom Plate:
JOINT 17 ( Interior Column = 200 x 600)most Critical Joint
1. Compression
From STAAD Pro Output, Factored forces (Please refer to page 11/30 of STAAD Output)
Rx = -16.13 kNs Ry = 80.06 kNs Rz = 74.20 kNs
Compression = 80.06kNs
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
8/15
ZND332_A-AMT-Td-0002-Rev.
Page. 8
However for uniformity the size of bottom plate of 200 x 500mm is adopted.
100
100
200
100
100 300 100
500
The bearing pressure developed on the base plate = 80.06 x 1000/.(200 x 500)
= 0. 814mPa
The max bearing pressure as per AISC = 0.35fc = 0.35(20) = 7.0 mPa > 0 0.814 mPa OK!
Considering a strip of 1 mm of base plate,
From inspection, the length of the base plate subjected to cantilever effect, L = 100 mm
The length of the base plate subjected to cantilever effect, L = 100mm
M = WL2
/ 2 = 0.814 x 1002/2 = 40700 N-mm
fb = 6M / bd2
fb = 6 x / 1.0d2
Allow Fb = 0.75Fyd = 0.75 x 248= 186 mPa
d2 = 6 x 40700 / 186
d = 11.45 mm
However, the thickness of the base plate is adopted as 20mm due to the following facts;
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
9/15
ZND332_A-AMT-Td-0002-Rev.
Page. 9
1. The base plate is subjected to corrosion which is not considered in the calculations.
2. The strength of the base plate is reduced by the intense heat due to welding process.
2.
The base plate is subjected to thermal loads due to temperature changes which is not considered in th
calculations.
3. The minimum thickness of plate if 6 mm thick of weld is used is from 12 -20mm as per AISC manua
D. Thickness of the 320 x 500 Top Plate
For the load acting on the top plate, neglecting the selfweight of the pipe pedestal, equilibrium is applied and from
STAAD Output, the factored reaction in Y direction is Ry = 80.06 kNs (Please refer to page 11/30 of STAAD Outp
The flange width of the main beam is 290 mm. A 320 x 500 plate is considered for the frame.
However for uniformity the size of top plate of 320 x 500mm is adopted.
100
160
320
160
100 300 100
500
For a 320 x 500 plate, the pressure is 80.06 x 1000/ (320 x 500) = 0.500 mPa
From Inspection, the length of the cantilever = 100 mm
Considering a 1mm strip of plate,
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
10/15
ZND332_A-AMT-Td-0002-Rev.
Page. 10
The moment, M = 0.500 x 1002/2 = 2500 N-mm
The actual fb = 6M / bd2 = 6 x 2500 / 1d2
The allow Fb = 0.75 x 248 = 186.0 mPa
186 = 6(2500) / 1d2
d = 8.98 mm
However, the thickness of the top plate is adopted as 20mm due to the following facts;
1. The top plate is subjected to corrosion which is not considered in the calculations.2. The strength of the top plate is reduced by the intense heat due to welding process.3. The top plate is subjected to thermal loads due to temperature changes which is not
considered in the calculations.
4. The minimum thickness of top plate if 6 mm thick of weld is used is from 12 -20mm asper AISC manual.
5. The minimum thickness of the top plate shall not be less than the flange thicknessof the main beam, tf = 17.50 mm for a HE360A .
Check Bolt Anchorage of Main Beam to Top Plate:
1. JOINT 17 (Exterior Column = 200 x 600)most Critical JointHowever for uniformity the size of top plate of 320 x 500mm is adopted.
100
160
320
160
100 300 100
500
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
11/15
ZND332_A-AMT-Td-0002-Rev.
Page. 11
A) Tension
From STAAD Pro Output, Factored forces (Please refer to page 11/30 of STAAD Output)
Rx = -1.65 kNs Ry = -25.82 kNs Rz = 45.06 kNs (Load No. 10)
The orthogonality/45 degree dirction of horizontal forces has been included in the load combinations of
STAADPro Inputs (Load Nos. 13 & 14)and from the results as per Support reactions, the values of forces are n
critical. Please see page 11/30 of STAAD Pro outputs for reference.
Tension = -25.82 kNs
Actual tension for 1Anchor Bolt = 25.82 / 4 = 6.455 kNs
For M20 A325 Bolt
Allowable Tension Stress, Ft = 303 mPa
Actual Tensile Stress, ft = 6.455 x 1000 / (3.14 x 202/4) = 20.55 mPa < 303 mPa Therefore OK!
3. JOINT 17 ( Exterior Column = 200 x 600)most Critical JointB) Shear
From STAAD Pro Output, Factored forces (Please refer to page 11/30 of STAAD Output)
Rx = -15.65 kNs Ry = 40.74kNs Rz = 101.41 kNs (Load No.12)
The orthogonality/45 degree dirction of horizontal forces has been included in the load combinations of
STAADPro Inputs (Load Nos. 13 & 14)and from the results as per Support reactions, the values of forces are n
critical. Please see page 11/30 of STAAD Pro outputs for reference.
Total Factored Shear, V = (15.65)\2 + 101.412 )0.50 = 102.61 kNs
Actual shear for 1Anchor Bolt = 102.61 / 4 = 25.65 kNs
For M20 A325 Bolt
Allowable Shear Stress, Fv = 117 mPa
Actual Shear Stress, fv = 25.65 x 1000 / (3.14 x 202/4) = 81.68 mPa < 117 mPa Therefore OK!
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
12/15
ZND332_A-AMT-Td-0002-Rev.
Page. 12
C) Bearing
For M20 A325 Bolt
Allowable Bearing Stress, Fb = 145 mPa
Actual Bearing Stress, fb = 25.65 x 1000 / (20 x 17.50) (Thinner of two plates is applied)
Actual Bearing Stress, fb = 73.28 mPa < 145 mPa Therefore OK!
Check Short Column between Bottom Plate & Top Plate:
2. JOINT 17 most Critical JointHowever for uniformity the size of Short Column of 200mm x 120mm x 20mm is adopted.
100
160
320
160
100 300 100
500
From Inspection, the Critical Tributary Area is 150mm x 320mm
For a 320 x 500 plate, the pressure is 80.06 x 1000/ (320 x 500) = 0.500 mPa
Compression force acting on the short column = 0.500 x 1000\x 0.320 x 0.150 = 24 kNs
For fixed-fixed ends, K = 0.50
Iy = bh3/12 = 0.020 x 0.2003/12 = 1.333 x 10-05q.m.
Ix = bh3/12 = 0.200 x 0.020
3/12 = 1.333 x 10
-07q.m.
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
13/15
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
14/15
ZND332_A-AMT-Td-0002-Rev.
Page. 14
100
100
200
100
100 300 100
500
From algrebra, the area of the segment of connecting circles = 3364.31mm2
Area of Circle = D2/4 = 3.14 x 1702/4 = 22686.50 mm2
Net Area for 4 Circles subjected to 45 degree Cone Failure, An = 4 x 22686.503 x 3364.31 = 80653.07 mm2
For Anchor Tension Failure load;
Tensile capacity of 4 concrete cone, Fu = 4(fc)xAn = 0.075x 0.65 x (3000) x 125 = 178001 lbs
Fu = 79.21 kNs > ft = 25.82 kNs Therefore OK!
Check for min edge distance; The ACI
-
8/2/2019 ZND332_A-Base & Top Plate & Anchors-REV-E (Repaired)
15/15
ZND332_A-AMT-Td-0002-Rev.
Page. 15
Conclusion:In view of the above calculations, it is concluded that the top plate, top plate, Uma Ukat Chemical
Anchors and M20 A325 Bolts can safely carry the loads imposed by the Penetrating Tower + shelter
equipment including appurtenances.