Building our future, together.

Why are we seeking a bond issue?

1. Growth. We’ve gained more than 600

students in the last five years alone.

2. Clear path ahead. Our parents and staff want

kindergarten returned to elementary buildings and a clear feeder system.

3. Need for technology improvements. Our

parents and staff show strong support for

greater use of technology K-12th.

4. Safety and security. Install security cameras at

all schools; relocate offices at 2 schools and

improve their traffic patterns; buy 7 school

buses.

Page 3: Zeebondproposal2010

Building our future, together.

What is the district requesting?

A $20.275 million bond proposal on May 4

that would require no increase in the

current tax rate of 6.63 mills.

This proposal is based upon the input we

received from hundreds of Zeeland

parents, staff, students, and citizens in the

fall of 2008.

Our original estimate for meeting the

district’s needs totaled $27 million. That

package has been reduced by about $7

million.

2010 Bond Proposal

Page 4: Zeebondproposal2010

Building our future, together.

The $20.275 million would be used to:

• Build Phase I of a new elementary school

• Place appropriate technology in the hands of all students

and update computer networks and audio-visual gear

• Transform ECC building into the new home for all of our

self-supporting child care programs

• Expand both high school cafeterias while transforming

them into creative learning spaces.

• Relocate offices and improve traffic and parking patterns

at New Groningen Elementary and Cityside Middle

• Install security cameras at all schools

• Purchase seven new buses

2010 Bond Proposal

Page 5: Zeebondproposal2010

23 29 23 4624 58 25 13

26 1227 02

28 08

29 9330 85

32 6534 08

35 7437 21

38 28

40 38

42 36

44 4246 05

46 82 47 1748 02

49 3850 46

51 7652 53

53 7754 50

55 80

0

1000

2000

3000

4000

5000

6000

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

2002

2004

2006

2008

Populati on

Continued growth for 27 years

Building our future, together.

Page 6: Zeebondproposal2010

Phase 1 of new elementary school

Cost: $8,500,000

Building our future, together.

Page 7: Zeebondproposal2010

Phase 1 of new

elementary school

Cost: $8,500,000

Building our future, together.

Page 8: Zeebondproposal2010
Page 9: Zeebondproposal2010

Transform ECC for use by tuition-

based programs that pay for

operations. Renovate with $1,500,000

low/no interest stimulus funds

Building our future, together.

Page 10: Zeebondproposal2010

Building our future, together.

2010 Bond Proposal

Technology plan

1. Provide individual learning devices for

more than 4,220 students in grades 3-12.

2. Provide updated computer labs and

appropriate learning devices for students

in grades K-2.

3. Update audio-visual, networking and

wireless components in all classrooms.

Cost: $5,350,000

Page 11: Zeebondproposal2010

New Groningen: Relocate

office and change parking

and bus patterns

Cost: $700,000

Building our future, together.

Page 12: Zeebondproposal2010

New Groningen: Relocate

office and change parking

and bus patterns

Cost: $700,000

Building our future, together.

Page 13: Zeebondproposal2010

Cityside: Relocate office

and change parking and

drop-off patterns.

Cost: $1,300,000

Building our future, together.

Page 14: Zeebondproposal2010

Two options for Zeeland East:

ZEHS & ZWHS: expand cafeterias &

transform them into group learning

spaces: $1,825,000

Building our future, together.

Page 15: Zeebondproposal2010

Two options for Zeeland West:

Building our future, together.

ZEHS & ZWHS: expand cafeterias &

transform them into group learning

spaces: $1,825,000

Page 16: Zeebondproposal2010

Building our future, together.

2010 Bond Proposal

Safety and security

1. Purchase seven new buses

2. Install digital security cameras at all

schools and at the transportation

building

Cost for buses and security: $1,100,000

Page 17: Zeebondproposal2010

Building our future, together.

2010 Bond Proposal

What else is on the ballot May 4?

• One-year renewal of the 18-mill

nonhomestead tax. The tax

generates more than $6 million for

the operation of our schools.

• Board incumbents Tom Den Herder

and David Lutz are running

unopposed.

Page 18: Zeebondproposal2010

Building our future, together.

2010 Bond Proposal

For more details . . .

• Visit us on at:

facebook.com/zpsfuture or zps.org

• Dates of public forums are:

• Wed., March 24, 7 p.m., Cityside Middle

• Mon., March 29, 4 p.m., Howard Miller Comm. Ctr.

• Wed., March 31, 10 a.m., Howard Miller Comm. Ctr.

• Mon., April 12, 7 p.m., New Groningen Elementary

• Wed., April 14, 7 p.m., ZWHS cafeteria

• Thurs., April 15, 4 p.m., Howard Miller Comm. Ctr.