Project Name Product ReleaseProject Manager Alex B.Project DeliverableScope Statement:
Start Date 2-SepEnd Date 10-OctOverall Progress 20%
Tasks Responsible Start End Days Status
Set kick-off meeting Alex B. 9/2 9/3 1 Complete
Agree on objectives Frank C. 9/3 9/7 4 Complete
Detailed Reqs. Jacob S. 9/7 9/12 5 Complete
Hardward Reqs. Jacob S. 9/9 9/11 2 Overdue
Final Resource Plan Jacob S. 9/11 9/15 4 In progress
Staffing Alex B. 9/16 9/17 1 In progress
Techincal Reqs. Frank C. 9/17 9/21 4 Not started
DB Development Shari W. 9/22 9/24 2 Not started
API Development Shari W. 9/23 9/27 4 Not started
UI Client Alex B. 9/25 9/29 4 Not started
Testing Kennedy K. 9/24 10/2 8 Not started
Dev. Complete Jacob S. 10/2 10/5 3 Not started
Hardware Config. Alex B. 10/5 10/7 2 Not started
System Testing Kennedy K. 10/6 10/9 3 Not started
Launch 10/9 10/10 1
Or, Click Here to Create Your Project Plan in Smartsheet
![Page 2: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/2.jpg)
![Page 3: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/3.jpg)
![Page 4: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/4.jpg)
Or, Click Here to Create Your Project Plan in Smartsheet
Set kick-off meeting
Agree on objectives
Detailed Reqs.
Hardward Reqs.
Final Resource Plan
Staffing
Techincal Reqs.
DB Development
API Development
UI Client
Testing
Dev. Complete
Hardware Config.
System Testing
Launch
9/2 9/7 9/12 9/17 9/22 9/27 10/2 10/7 10/12
![Page 5: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/5.jpg)
![Page 6: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/6.jpg)
![Page 7: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/7.jpg)
Set kick-off meeting
Agree on objectives
Detailed Reqs.
Hardward Reqs.
Final Resource Plan
Staffing
Techincal Reqs.
DB Development
API Development
UI Client
Testing
Dev. Complete
Hardware Config.
System Testing
Launch
9/2 9/7 9/12 9/17 9/22 9/27 10/2 10/7 10/12
![Page 8: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/8.jpg)
![Page 9: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/9.jpg)
![Page 10: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/10.jpg)
Stakeholder List
Name Position Role in project Email address
John Smith VP of ProductFinal approval of
milestones [email protected]
![Page 11: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/11.jpg)
Requirements Expectations
Downtime of no longer than 20 minutes
QA to take less than 1 week, marketing to promote new features in newsletter
![Page 12: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/12.jpg)
Cost Baseline
Item/task % Complete Base Cost Cost
Extra devices for QA testing 50% $2,800 $3,500
![Page 13: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/13.jpg)
Actual Cost % Budget Spent
$3,600 15%
![Page 14: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/14.jpg)
Communication Plan
Communication Type Deliverable Description
Presentation
Meetings Standup meetings Check in about status
15-minute Powerpoint presentation
Presentation to marketing team about new features
![Page 15: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/15.jpg)
Delivery Method Frequency Owner
In-person One time Alex B.
In-person 2x a week John S.
![Page 16: d2myx53yhj7u4b.cloudfront.net€¦ · XLS file · Web view · 2016-03-16Project Plan and Gantt Stakeholder List Cost Baseline Communication Plan](https://reader033.vdocuments.us/reader033/viewer/2022051106/5ae471787f8b9a5d648f5a8c/html5/thumbnails/16.jpg)
Audience
Marketing team
Project team