Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 1 of 26

SCHEDULE OF QUANTITIES

For

PIPELAYING

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 2 of 26

Sr. No. Description of Items Unit Quantity

PIPELINE LAYING / INSTALLATION:

PIPELINE LAYING / INSTALLATION :- Laying/installation of coated line pipe, associated fittings and accessories, etc. including laying of OFC (optical fiber cable) with or without conduit including the cost of all labour, equipment, material etc. complete as per scope of work, specifications, drawings, codes and standards, other terms and conditions of contract and as directed by the Engineer-in-charge including but not limited to the followings:

(a) “Receiving and taking-over”, handling, loading, transportation and unloading of all materials (Owner and contractor supplied) externally corrosion coated and bare line pipes from designated place(s) of issue/dump site(s) to Contractor’s own stock-yard(s)/workshop(s)/Work (site) including stringing on the pipeline Right of Use (ROU)/Right of Way (ROW);

(b) Arrangement of all additional land required for Contractor’s storage, fabrication, access for construction (other than Owner provided ROU/ROW); supply of all materials (except Owner supplied materials), consumables, equipment, labour, etc;

(c) Stacking and installation of construction markers, clearing, grubbing, grading (as required) of Right of Use/Right of Way;

(d) Counting the number and type of trees cut in presence of HPCL/Government concerned authorities and keeping record thereof;

(e) Trenching to all depth and to a width to accommodate the pipeline and/or optical fiber cable(OFC)/cable conduit as specified in scope document and as per the relevant standards, drawings, specifications, etc. by excavation in all types of soils, etc,

(f) providing trench padding as required with sand/graded earth approved by Engineer-in-Charge;

(g) Carrying out repairs of pipe and coating defects not attributable to Owner (i.e. defects

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 3 of 26

Sr. Description of Items Unit Quantity occurring after “taking over” of pipes from Owner);

(h) Thorough internal cleaning of all pipes by suitable methods to remove debris, shots, grits etc. to the satisfaction of Engineer-in-Charge;

(i) Stringing of line pipes along ROU/ROW including providing straw bags, soft padding/sand padding;

(j) Aligning, bending, cutting and beveled area, welding, carrying out destructive/non-destructive testing of welds as required including radiography and providing all requisite equipment, labour, supervision, materials, films, consumables, all facilities and personnel to process, develop, examine and interpret radiographs and other test as required; (Radiography shall be measured and paid for separately)

(k) carrying out repairs of weld joints found defective by Engineer-In-Charge, (Carrying out re-radiography and other non-destructive tests as required on repaired joints, etc);

(l) Installation of casing pipes (wherever required) at all crossings including roads/rail, foreign pipeline crossing, etc. by open cut or jacking/boring method including pre-testing as required;

(m) Carrying out installation of carrier pipe in the casing pipe at cased crossings in roads/rail, foreign pipeline crossing, etc (excluding supply and installation of casing pipe covered separately);

(n) Coating of all field weld joints, long radius bends (HI and Cold), buried fittings, valves etc;

(o) Lowering the pipelines in trench including providing Geo-textile/sand bag separators for parallel pipelines at the specified spacing (when applicable), backfilling with available, approved excavated material and/or other suitable soil approved by Engineer-In-Charge;

(p) Carrying out hydrostatic testing including air cleaning, flushing, filling, gauging, pressurization of complete pipeline in various test sections as approved by Engineer-In-Charge to the specified test pressure, providing all equipments, pumps, fittings, instruments, dead weight tester, etc. and services, supervision, labour, consumables,

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 4 of 26

Sr. Description of Items Unit Quantity water including supply of corrosion rectification of defects attributable to Contractor, re-testing after rectification, Successful completion of hydro testing of pipeline (De-watering covered else where in the SOR);

(q) All tie-ins, including the tie-in(s) with the pipeline/piping installed by others including cutting of test header, re-beveling as required;

(r) Carrying out all temporary ancillary, auxiliary works and all incidental works required to make the pipeline ready for pre-commissioning ;

(s) Fabrication of cold field bends with proper bending machine. Getting approved of method of bending, testing the bends using gauge plate before welding.

(t) Repair of defects recorded during EGP/gauge plate run or otherwise including cutting, beveling, welding, radiography, field joint coating etc; as applicable,

(u) final clean-up and restoration of right of way/right of use including obtaining NOC from respective statutory authorities as required and disposal of debris and returning all surplus material to designated disposal areas/storage yard, as directed by Engineer-In-Charge;

(v) Restoration of land, facilities and boundary wall etc at associated facilities dismantled/damaged by the Contractor during construction;

(w) Obtaining work permits/NOC from various statutory authorities having jurisdiction, before execution of the work, and complying with all stipulation/conditions/recommendation of the said authorities;

(x) Preparation of as-built drawings, pipe-book and other records. SOR shall be read in conjunction with scope of work, job specific requirements, specifications, standards, drawing and other provisions of contract document. All above works for buried pipeline as per following details:

(y) Engaging Third Party Inspection agency as approved by HPCL for stage wise inspection.

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 5 of 26

Sr. Description of Items Unit Quantity

1

Installation of Coated Line Pipes (with OFC/OFC conduit) as per following details: Pipe OD-219mm, Wall Thickness-7.04mm, Pipe Material-LTCS, ASTM A 333 Gr. 6, Seamless, Coating -3 LPE.

M 3300

BACKFILLING WITH SAND (For Station Approach):

2

Unit rate over and above item for supply of specified and approved quality of sand including supply of sand in place of available excavated material and/or other suitable soil as per applicable standards/specifications, including backfilling of excavated trench for specified length after laying of pipeline, including transportation of backfill material over all distances and disposal of surplus excavated soil, complete.

CuM 100

SUPPLY AND INSTALLATION OF CASING PIPE:

Contractor has to procure and install including transportation of casing pipes/CS conduit for Carrier and OFC from Contractor’s storage point to worksite. Installation of casing pipe by jacking/boring or open cut for rail, road or foreign pipeline crossings wherever required in all types of soils and terrain and all other materials viz. casing insulators and casing end seals as per enclosed reference drawing, materials for casing vents and drain , etc. including supply of all other materials equipments, consumables, manpower, welding including visual inspection of all weld joints, installation of casing insulators, end seals, vents and drain-off pipes, back fillings and restoration as original of the facility crossed and performing all works as per drawings, specifications and instructions of Engineer-In-Charge and provisions of Contract document.

3 All works for item described above of open cut/jacking/boring for installation of Casing pipe size 304 mm, Material API 5L Gr. B, ERW pipe, of 4.78 mm of wall thickness.

M 72

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 6 of 26

Sr. Description of Items Unit Quantity

INSTALLATION OF VALVES/EQUIPMENTS/ABOVE GROUND PIPELINE AND OTHER FACILITY AT DESPATCH AND RECEIVING STATION:

Receiving and taking over of all Owner or contractor supplied materials, equipments from designated place(s) of issue, transportation including loading, unloading, handling from Owner’s designated places(s) of issue to Contractor’s own stock yard(s)/work shop(s) including arranging all necessary intermediate storage areas(s) thereof, as required; supply of all materials equipment, consumables as defined in Contractor’s scope of supply and its transportation to the work site(s); installations of valves, Bar Tee, IJ’s, equipment including welding, testing (destructive and non destructive), painting/coating (as per specification), fixing of gaskets, bolts, studs, nuts wherever requires, leveling, aligning, installation and assembly of accessories (including accessories for actuators including making electrical connections for such actuators, if any), by bolting/threading or welding of pipes at all elevations as per drawings, specification, other provisions of Contract and directions of the Engineer-In-Charge all for 8” Cross-country LPG Pipeline

4 Installation of pipeline Ball valves (below ground) MOVs. EA 2

5 Installation of Bar Tees EA 2

6 Installation of Isolation Joints EA 2

PERMANENT MARKER:

Supply, fabrication and installation of following types of permanent markers along the route including all associated civil works such as excavation in all types of soil, construction of pedestals and grouting with concrete, clearing, supply and application of approved colour and quality of primer and paint, stencil letter cutting for numbers, direction, chainage, etc.

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 7 of 26

Sr. Description of Items Unit Quantity restoration of area to original condition and performing all works as per drawings, specifications and instructions of Engineer-In-Charge. Note: The painting of all markers shall conform to normal corrosive to environment, irrespective of whatever shown on respective standards/drawings.

7 Pipeline Warning Sign, refer typical drawing 0435-JH0911-00-PL-DRD-0003-01. EA 05

8 Direction Marker, refer typical drawing 0435-JH0911-00-PL-DRD-0003-02. EA 31

9 Kilometer Post, refer typical drawing 0435-JH0911-00-PL-DRD-0003-03. EA 02

10 Right of Use Boundary Marker, refer typical drawing 0435-JH0911-00-PL-DRD-0003-04. EA 12

11 Supply and Installation of warning sheets (suitable poly-vinyl) over the electrical and foreign pipeline crossings. M 20

LEAKS/BURSTS (ATTRIBUTABLE TO OWNER):

MAJOR LEAK (DETECTED BY VISUAL METHOD): All works for locating major leak/burst (occurred during hydrostatic testing) including necessary repairing/replacing defective pipe length, including cutting and removing out defective pipes, pre-testing of replacement pipe and welding into mainline, NDT of welds and re-beveled area, repair and re-testing of defective welds, coating of welded joints, clean-up retesting the pipeline including providing all necessary equipments, labour, materials, consumables and inputs other than Owner supplied materials and performing all works as per drawings, specifications enclosed with the Contract and directions of Engineer-In-charge. Note: This rate is applicable for manufacturing defects in Company supplied material only.

12 Major Leak (detected by visual method): Pipeline Size-8 Inch. EA 1

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 8 of 26

Sr. Description of Items Unit Quantity

MINOR LEAK (DETECTED BY SECTIONALISING): All works for locating leak by sectionalizing or any other methods which cannot be located by visual means, including necessary repairing/replacing defective pipe length, including cutting and removing out defective pipes, pre-testing of replacement pipe and welding into mainline, NDT of welds and re-beveled area, repair and re-testing of defective welds, coating of welded joints, clean-up, retesting the pipeline including providing all necessary equipments, labour, materials, consumables and inputs other than Owner supplied materials and performing all works as per drawings, specifications enclosed with the Contract and directions of Engineer-In-Charge.Note: This rate is applicable for manufacturing defects in Company supplied material only.

13 Minor Leak (detected by sectionalizing): Pipeline Size-8 Inch EA 1

Supply including procurement and transportation to worksite(s)/workshop(s) including loading, unloading and handling for the following materials to be supplied by Contractor as per the requirement of PMS, specifications, data-sheets, standards, scope of work, instructions of Owner/Engineer-In-Charge and other provisions of Contract:

INSULATING JOINTS

14 Supply of Insulating Joints as per following details: (Size: 8 Inch, Rating-300, Data sheet no.-0435-JH0911-00-PL-DAS-0001).

EA 2

FLOW TEES

15 Supply of Barred Tees as per following details: (Size: 8X8X8 Inch, Rating-300, Data Sheet no.-0435-JH0911-00-PL-DAS-0002). EA 2

16 Supply of – 06 cores Multi mode silica / silica doped Optical Fiber cable (OFC) as per specification, scope of work, standard terms and condition.

M 5000

Permanent Cathodic Protection Systems (PCP):

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 9 of 26

Sr. Description of Items Unit Quantity

17

Design, Engineering, Supply, Installation, testing, pre-commissioning and commissioning of Permanent Cathodic Protection Systems as per scope of work, specification, standards, terms and conditions and as directed by Engineer-In-Charge. Rate quoted by the contractor shall include the cost of all labour, material, equipment, etc. complete. Pipeline will be protected by Impressed Current Cathodic Protection (ICCP) systems to mitigate the corrosion in the pipelines.

LS 1

Pigging (Cleaning & EGP):

18

Mobilization/Demobilization of pigging tools, tackles, consumables, compressors, accessories and personnel by CONTRACTOR at work site including but not limited to cleaning & electronic geometry pigs and other provisions of the bid document includes supply of material, equipment, manpower, etc. as required for geometry inspection and magnet cleaning of 8” diameter and preparation of site report, from ONGC, Hazira to New LPG Bottling Plant, Hazira, Pipeline.

LS 1

19

REPAIR OF DEFECTS IN LINE PIPE (ATTRIBUTABLE TO COMPANY) Repair of defects not attributable to Contractor on Company supplied bare line pipes, noted and recorded at the time of “Receiving and taking over” by Contractor , in the presence of Company representative including performing all works as per Scope of work document 0435-JH0911-00-PL-SOW-0001, specifications and instructions of Company representative in respect. Cutting and re-bevelling (Defects beyond 25mm from pipe ends due to lamination and carrying out ultrasonic inspection after repairing as per Scope of Work).

EA 1

20 Preparation of final work report as per pre-agreed format and submission to COMPANY in total of 6 copies. LS 1

21 Carrying out pre-commissioning (dewatering, swabbing/flushing) checks and making the entire pipeline spread ready for commissioning including supply of all equipment, manpower, consumables (including all types of pigs and required materials), materials for all temporary works and performing all associated works, complete as per the relevant specifications, other

LS 1

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 10 of 26

Sr. Description of Items Unit Quantity provisions of Contract document and instructions of Engineer-In-Charge.

22 Transportation of surplus bare /coated line pipes from the dump sites and from ROU to Company’s designated storage area including loading/unloading/handling and carrying out all associated works like arranging for cranes, manpower, trailers, loading and unloading equipment; preparation of storage area at unloading point including providing all consumables, sand ridges, wooden sleepers, plastic sheets, etc; preparation of material reconciliation statement.

LS 1

23 Radiography of Pipeline weld joints ( using gama or x-ray) of 8” size, including the cost of supply of all material, equipment and manpower required for developing the films, review by ASNT qualified personnel, carrying out defect, repair, re-shoot etc. all complete as per specifications and as directed by the Engineer-in-charge. The radiography work shall be carried out complying with all the statutory and safety requirements. Measurement will be done for each weld joint. In case of any repair, re-shoot, re takes, the same shall not be measured again for payment.

EA 450

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 11 of 26

Schedule of Quantities for

PIPING

Erection, Testing & Pre- Commissioning for PUMPING STATION INSIDE ONGC TERMINAL

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 12 of 26

Sr. No. Description of Items

Qty Unit

LPG Hazira ONGC Terminal Station Piping SOR

Fabrication, welding, erection, installation and testing of above ground piping work including the cost of all labour, material, equipment etc. complete as per scope of work, specification, drawings, codes and standards, other terms and conditions and as directed by the Engineer-in-charge including but not limited to the following:

(a) Receiving and Taking over of all (Owner and contractor supplied) materials from Owner's designated place(s) of issue, transportation including loading, unloading, handling from Owner' designated place(s) of issue to Contractor's own stock yard(s)/ work site(s)/ work shop(s) including arranging all necessary intermediate storage area(s) thereof, as required;

(b) supply of all materials (except those specified subsequently in SOR), equipment, consumables as defined in Contractor's scope of supply and their transportation to the work site(s);

(c) performing all above ground/buried piping fabrication works including cutting, edge preparation (inclusive of grinding the edges of pipes, fittings, flanges etc. to match with the matching edges of uneven/different thickness wherever required),fit up, pre-heating wherever required, welding, threading etc,;

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 13 of 26

Sr. No. Description of Items Qty Unit

(d) erection of pipes of all types and thickness over sleepers, overhead on racks and at all elevations, hook-up with equipment nozzles; installation of all type of valves up to size of 1.5" NB, all types of inline and online instruments such as pressure/thermal safety valves(other than those covered separately), fittings of all sizes i.e, elbows, reducers, tees, 'o' lets, flanges, blind flanges, spectacle blinds, tappings for pressure gauges, thermo wells, hoses and hose couplings of all sizes, if applicable, sample connections, flame arrestors as applicable, vents and drains required for process and hydro-testing purposes etc. including fixing of all types of gaskets , bolts, studs and nuts of all sizes; fabrication of strainers of sizes up to 1.5" ,

(e) carrying out non-destructive testing (excluding radiography covered subsequently in SOR) such as magnetic particle/ liquid penetration etc. as required;

(f) hook-up with existing piping/pipeline installed by others as per drawings wherever required; (g) cleaning and flushing by water / compressed air, carrying out hydrostatic test, pneumatic test, valve

functional test and any other type of testing as specified, de-pressurizing, dewatering, drying by compressed air if applicable; cutting/ re beveling as required, dewatering, drying by compressed air

(h) Providing commissioning assistance for process piping and non-process piping if applicable; (i) clean - up and restoration of site, (j) preparation of as built drawings, documents and project records; (k) transportation of surplus free issue materials to Owner's designated place(s);.

Note :- (1) Installation of items such as valves (2" and above), flow meters, strainers of size 2" NB and above, equipments will be paid separately as per rates covered in appropriate items. (2) Radiography of weld joints would be measured and paid for separately as per separate schedule item.

24 Above ground Carbon Steel Process Piping: Size 1/ 2 INCH , Thk / Sch 80 , Material ASTM A106 Gr. B SMLS

10.00 M

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 14 of 26

Sr. No. Description of Items Qty Unit

25 Above ground Carbon Steel Process Piping: Size 3 / 4 INCH , Thk / Sch 80 , Material ASTM A106 Gr. B SMLS

30.00 M

26 Above ground Carbon Steel Process Piping: Size 1 INCH , Thk / Sch 80 , Material ASTM A106 Gr. B SMLS

40.00 M

27

Above ground Carbon Steel Process Piping: Size 2 INCH , Thk/Sch 40 , Material ASTM A106 Gr. B , 80.00 M

28

Above ground Carbon Steel Process Piping: Size 4 INCH , Thk/Sch 40 , Material ASTM A106 Gr. B , 60.00 M

29

Above ground Carbon Steel Process Piping: Size 6 INCH , Thk/Sch 40 , Material ASTM A106 Gr. B , 16.00 M

30

Above ground Carbon Steel Process Piping: Size 8 INCH , Thk/Sch 40 , Material ASTM A106 Gr. B , 60.00 M

31

Above ground Carbon Steel Process Piping: Size 10 INCH , Thk/Sch 40 , Material ASTM A106 Gr. B , 100.00 M

32

Above ground Carbon Steel Process Piping: Size 24 INCH , Thk/Sch 40 , Material ASTM A106 Gr. B , 10.00 M

Installation of Above ground CS water/Air Supply piping

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 15 of 26

Sr. No. Description of Items Qty Unit

33

Above ground Carbon Steel ERW Pipes: Size 6 INCH , Thk – 6.35mm , Material IS 3589 , Ends BE , Dmn. Std. 36.10 , (Internal Cement-Mortar Coated).

50.00 M

34

Above ground Carbon Steel ERW Pipes: Size 4 INCH , Sch-Heavy , Material IS 1239 , Ends BE , Dmn. Std. 36.10 ,

30.00 M

35

Above ground Carbon Steel ERW Pipes: Size 3 INCH , Sch-Heavy , Material IS 1239 , Ends BE , Dmn. Std. 36.10 ,

10.00 M

36

Above ground Galvanized Carbon Steel ERW Pipes: Size 2 INCH , Sch-Heavy , Material IS 1239 , Ends BE , Dmn. Std. 36.10 ,

10.00 M

37

Above ground Galvanized Carbon Steel ERW Pipes: Size 3 / 4 INCH , Sch-Heavy , Material IS 1239 , Ends PE , Dmn. Std. 36.10 ,

10.00 M

38

Above ground Galvanized Carbon Steel ERW Pipes: Size 1 / 2 INCH , Sch-Heavy , Material IS 1239 , Ends PE , Dmn. Std. 36.10 ,

10.00 M

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 16 of 26

Sr. No. Description of Items Qty Unit

FABRICATION , ERECTION ,INSTALLATION & TESTING OF UNDER GROUND PIPING : Receiving and Taking over of all materials (owner and contractor supplied) from Owner's designated place(s) of issue, transportation including loading, unloading, handling from Owner' designated place(s) of issue to Contractor's own stock yard(s)/ work site(s)/ work shop(s) including arranging all necessary intermediate storage area(s) thereof, as required; supply of all materials (except those specified subsequently in SOR), equipment, consumables as defined in Contractor's scope of supply and their transportation to the work site(s); performing all buried piping fabrication works including the cost of WRAP COAT with 4.0 mm thick pypekote or equivalent material, holiday testing as per specification, data sheet, drawings, terms and conditions and as directed by the Engineer-in-charge including the cost of all material, labour, equipment etc. complete. Earth work excavation shall be measured and paid for separately.

39 Installation of underground Carbon Steel ERW IS 3589 piping size 6 inch

10.00 M

40 Installation of underground Carbon Steel ERW IS 1239 piping size 4 inch

10.00 M

INSTALLATION OF VALVES/METERS/STRAINERS

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 17 of 26

Sr. No. Description of Items Qty Unit

Receiving and taking over of all (owner and contractor supplied) material from owner’s designated place of issue, transportation including loading, unloading, handling from owner designated place of issue to contractor’s own stock yard/work site/work shop including arranging all necessary intermediate storage thereof, as required; supply of all material, equipments, consumable as defined in contractor’s scope of supply and its transportation to the work site; installation of valves, flow meters, strainers, equipments including fixing of gaskets, bolts, studs, nuts, wherever required, leveling, aligning, installation and assembly of accessories including accessories for actuators, if any by bolting/threading or welding of pipes at all elevations, testing, completing all work in all respect as per drawings, specifications, other provisions of contact and direction of the engineer-in-charge

41

Installation of above ground Flanged Valves manual (Ball / Check / Globe) as per details given below: Size 4 INCH and below , Rating 300,

22.00 EA

42

Installation of above ground Flanged Valves manual (Ball / Check / Globe) as per details given below: Size 6 INCH to Size 10 INCH , Rating 300,

18.00 EA

43

Installation of above ground Flanged Valves manual (Ball / Check / Globe) as per details given below: Size 16 INCH , Rating 300,

1 EA

44

Installation of above ground Flanged Valves manual (Ball / Check / Globe) as per details given below: Size 24 INCH , Rating 300,

1 EA

45

Installation of above ground Flanged Valves motorized (Ball ) as per details given below: Size 8 INCH to Size 10 INCH , Rating 300,

5.00 EA

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 18 of 26

Sr. No. Description of Items Qty Unit

46

Installation of above ground Flanged Valves manual (Ball / Check / Globe / Gate / Globe) as per details given below: Size 4 INCH and below , Rating 150,

5.00 EA

47

Installation of above ground Flanged Valves manual (Ball / Check / Globe / Gate / Globe) as per details given below: Size 6” to 10” , Rating 150,

5.00 EA

ROTATING EQUIPMENT & PACKAGES

48

Transportation of Rotating Equipment & Package items from Owner’s storage points to work site / contractor’s stores, assembly of sub assemblies, placing the equipments on foundations, erection of interconnecting piping, leveling, aligning, including chipping & dressing of foundations, grouting and providing manpower for testing, rectifying defects if any and completing the work in all respects as per scope of work, drawings, and under the supervision of equipment manufacturer, codes and standards, other terms and conditions and as directed by the Engineer-in-charge P-10-001 /AB LPG PUMPS

2 EA

INSTALLATION OF FLOW METER

49

Transportation of Mass Flow Meter from Owner’s storage points to work site / contractor’s stores, assembly of sub assemblies, placing the equipments on foundations, erection of interconnecting piping, leveling, aligning, including chipping & dressing of foundations, grouting and providing manpower for testing, rectifying defects if any and completing the work in all respects as per scope of work, drawings, and under the supervision of equipment manufacturer, codes and standards, other terms and conditions and as directed by the Engineer-in-charge

2.00 EA

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 19 of 26

Sr. No. Description of Items Qty Unit

INSTALLATION OF CONTROL & SHUT DOWN VALVES

50

FLOW CONTROL VALVE -Type : ELECTRO HYDRAULIC GLOBE VALVE Installation of Flow control valve of 8” size & below including mounting on Yoke/ Surface, with piping & tubing materials such as valves, fitting, pipes, tubes, compression fitting as per specification and erection of supports for impulse lines wherever required, fabrication and installation of manifolds/ impulse lines with supports as per standard indicated below, fabricating of supports for capillary, laying of capillary on supports, painting, installation of flushing connection, hydraulic testing of impulse lines as per standard specification.

3.00 EA

51

SHUT DOWN VALVE -Type : ON-OFF BALL VALVE Installation of Shutdown valve of 8” size including mounting on Yoke/ Surface, with piping & tubing materials such as valves, fitting, pipes, tubes, compression fitting as per specification and erection of supports for impulse lines wherever required, fabrication and installation of manifolds/ impulse lines with supports as per standard indicated below, fabricating of supports for capillary, laying of capillary on supports, painting, installation of flushing connection, hydraulic testing of impulse lines as per standard specification.

1.00 EA

RADIOGRAPHY

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 20 of 26

Sr. No. Description of Items Qty Unit

Radiography of weld joints of piping ( using gama or x-ray), including the cost of supply of all material, equipment and manpower required for developing the films, review by ASNT qualified personnel, carrying out defect, repair, re-shoot etc. all complete as per specifications and as directed by the Engineer-in-charge. The radiography work shall be carried out complying with all the statutory and safety requirements. Measurement will be done for each weld joint of respective size of piping. In case of any repair, re-shoot, re takes, the same shall not be measured again for payment.

52 DN 50 100 EA

53 DN 100 80 EA

54 DN 150 10 EA

55 DN 200 90 EA

56 DN 250 70 EA

57 DN 600 4 EA

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 21 of 26

Sr. No. Description of Items Qty Unit

PIPE SUPPORTS: Supply, Fabrication and erection of pipe/equipment supports (for all sizes/thickness) including shoes, pipes, cradles, turn buckles, t-sopts for all types of guides, anchors, special supports for all types of pipes etc. If applicable, all necessary equipments, consumables, labour etc. for completing all works including supply of bolts, nuts, washers, U-clamp, wooden blocks etc. as required for supporting supply including the cost of surface preparation by blast cleaning to SA 2.5, primer and painting all complete as per specification, data sheets, drawings, terms and conditions and as directed by the Engineer-in-charge.

58 CS Structural Steel 1.00 MT

PAINTING

Surface preparation blast cleaning, supply of paints, solvents and primers, and application of primer and finish paints suitable for project specific environment as defined in contract documents and on pipes as per standard specification for painting and protective coating indentification, lettering / Numbering, colour coading etc. as specified including rub down and touch up wherever required and providing of scaffolding for all heights, labour, materials, tools and tackles, consumable, supervision etc. to complete the work in all respect as per specification, Drawings, standards and instruction of engineer-in -charge.

59

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 1 / 2 INCH

12 M

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 22 of 26

Sr. No. Description of Items Qty Unit

60

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 3 / 4 INCH ,

26 M

61

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 1 INCH ,

42 M

62

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 2 INCH ,

56 M

63

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 4 INCH ,

64 M

64

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 6 INCH

12 M

65

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 8 INCH ,

64 M

66

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 10 INCH ,

116 M

67

Painting of all above ground piping including all fittings, valves, flanges etc. including colour bands Size 24 INCH ,

6 M

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 23 of 26

Sr. No. Description of Items Qty Unit

68

PAINTING OF EQUIPMENTS : Surface preparation blast cleaning, supply of paints, solvents and primers, and application of primer and finish paints suitable for project specific environment as defined in contract documents for equipments, identification, lettering / Numbering, colour coading etc. as specified including rub down and touch up wherever required and providing of scaffolding for all heights, labour, materials, tools and tackles, consumable, supervision etc. to complete the work in all respect as per specification, Drawings, standards and instruction of engineer-in -charge. Weight of the equipment in MT as mentioned by the manufacturer will be considered for measurement.

1.00 MT

69

PAINTING OF MISCELLANEOUS STRUCTURES: Surface preparation blast cleaning, supply of paints, solvents and primers, and application of primer and finish paints suitable for project specific environment as defined in contract documents for miscellaneous structures , indentification, lettering / Numbering, colour coading etc. as specified including rub down and touch up wherever required and providing of scaffolding for all heights, labour, materials, tools and tackles, consumable, supervision etc. to complete the work in all respect as per specification, Drawings, standards and instruction of engineer-in -charge. Unit weight of the standards steel structures will be considered for measurement.

1.00 MT

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 24 of 26

Sr. No. Description of Items Qty Unit

70

LEAKS/ BURSTS (ATTRIBUTABLE TO OWNER) (FOR TERMINAL PIPING):All works for repairing leak/burst (occurring during hydrostatic testing) including necessary repairs/replacement of defective pipes length, cutting and removing out defective pipes, welding, NDT of welds, repair and retesting of defective welds, painting of welding joints, clean up, re-hydrotesting of pipe segments including providing all necessary equipments, labour material, consumables and input other then owner supplied materials and performing all works as per appropriate specifications, drawings, data sheets, terms and conditions and as per the direction of engineer-in-charge. Note : This rate shall be applicable for manufacturing defects in Company supplied material only. Inch Mtr ( Diameter in inch multiplied by length in meter) of the replaced pipe will be measured for payment. Radiography of the joint will be measured and paid separately.

10.00 M

71

Excavation and backfilling around foundation and trenches/pits in all types of soil viz. earth, sand, gravel, clay, soft & hard murum etc. (excluding soft/hard rock) for footings, steps, plinth beams, equipment foundations, drains, trenches, manholes, underground tanks/pits, etc including shoring strutting, dewatering where required (until foundation work is complete). Item also includes carting of surplus earth, stacking if required, spreading, leveling and compacting/consolidating surplus materials within HPCL's premises or outside as per instructions, removal of any vegetation, small shrubs etc. having girth of 300mm or less, complete including the cost of all labour, material, and equipment as per specifications, drawings, codes and standards, terms and conditions and as directed by the Engineer-in-charge.

100 Cum

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 25 of 26

Sr. No. Description of Items Qty Unit

72

Providing and laying plain cement concrete PCC 1:4:8 (1cement ; 4 coarse sand : 8 stone aggregate 40 mm down size graded ) in making good soft & loose strata met under foundations, base slab, plinth beams, walls & rafts etc. including the cost of all labour, material, equipment etc. complete as per specifications, drawings, codes and standards, terms and conditions and as directed by the Engineer-in-charge.

25 Cum

73

RCC - Providing & laying in position Controlled grade Reinforced cement Concrete conforming to IS:456-2000,with design mix of M30 grade at all locations and levels using coarse sand and 20mm and down size graded aggregates in for equipment foundations / pipe sleeper [including leaving pockets, placing of conduits, making openings, pockets placing inserts/ sleeves in columns/ beams/ slabs etc.] machine mixing are required, lifting, placing, machine vibrating, tamping, curing etc. including the cost of all labour, material and equipment, complete all as per specifications, drawings, codes and standards and as directed by the Engineer-in-charge. NOTE :

1. The rate quoted by the contractor shall include the cost of formwork, centring & shuttering, providing offsets, cutouts, construction joints, making holes in or cutting formwork for taking out dowel bars, hacking the exposed surfaces to receive plaster as necessary.

2. Reinforcement steel will be measured and paid for separately. 3. Contractor may use ready mix concrete with prior approval of Engineer-in-charge at no extra cost to

owner.

50 Cum

74

Reinforcement - Providing, laying & fixing in position reinforcement steel as per approved drawings, locations & levels including preparing bar bending schedules & obtaining prior approval from Engineer-in-charge, cutting, bending & binding with 16G MS annealed binding wire incl. placing proper concrete cover blocks, chair supports etc complete including the cost of all labour, material, equipment, etc all per specifications, drawings, codes and standards, other terms and conditions and as directed by the Engineer-in-charge. HYSD conforming to IS:1786 of Grade Fe500

5

MT

Schedule of Rate For 8” dia ONGC Hazira to New LPG

Bottling Plant Pipeline (Ch.0.0 to Ch. 3.2Km)

CLIENT - HPCL PROJECT: ONGC, Hazira-New LPG Bottling Plant Pipeline.

0435-JH0911-00-PL-SOR-0001, Rev 0

Page 26 of 26

Sr. No. Description of Items Qty Unit

75

Insert/Anchor Bolt - Providing, fabricating and fixing in position at required locations to correct lines and levels, angles, inserts, pipe sleeves, anchor bolts for columns, floors, machine foundations, cable trenches and all types of RCC, PCC & masonry incl. necessary welding, machining, grinding, threading etc, providing, making and positioning templates, painting the exposed surface, etc. complete including the cost of all labour, material, equipment, etc all per specifications, drawings, codes and standards, other terms and conditions and as directed by the Engineer-in-charge.

500

Kg

76

Providing, fabricating, welding and/or bolting, as required, erecting and fixing in position all types of structural steel works (including painting as per specifications) made up of rolled & built up sections with moment or shear connections, shop/site fabricated including all accessories viz. nuts, bolts, cleats, gussets, suspenders etc., welding at heights, site connection, nut & bolts and same will not be measured for payment, surface preparation and painting, preparing detailed fabrication drawings, all complete including the cost of all labour, material, equipment, etc all per specifications, drawings, codes and standards, other terms and conditions and as directed by the Engineer-in-charge. Note : Painting - Primer & paint of approved quality & make. Surface preparation as per Sa 21/2, Primer coat Inorganic Zinc silicate coating 65 DFT in micron, Field primer shall be applied for touch up with protecto mastic or equivalent coating 65 DFT in micron; Finish coat shall be 2 coats of Epoxy high build finish paint @ 100 micron DFT/coat = 2x100 = 200 micron. Work shall be including scaffolding etc. all complete as directed & instructed by HPCL Engineer in charge.

2 MT

77 Providing and Applying non-shrink premix type grout (FOSROC or equivalent make) having compressive strength of not less than 40N/mm2 including providing necessary formwork as required.

0.5 CUM