work zone safety using accelerated bridge construction (abc)

28
Work Zone Safety Using Accelerated Bridge Construction (ABC) Rukhsana Lindsey, UDOT Presented by Jim McMinimee Principal Engineer, Applied Research

Upload: georgia-robertson

Post on 30-Dec-2015

38 views

Category:

Documents


3 download

DESCRIPTION

Work Zone Safety Using Accelerated Bridge Construction (ABC). Rukhsana Lindsey, UDOT Presented by Jim McMinimee Principal Engineer, Applied Research Associates. Utah. Small State 2.5 M people $350 M Federal Program DOT 1650 employees Currently 6% unemployment statewide - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Work Zone Safety Using Accelerated Bridge Construction (ABC)

Rukhsana Lindsey, UDOTPresented by Jim McMinimee

Principal Engineer, Applied Research Associates

Page 2: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Utah Small State

• 2.5 M people• $350 M Federal Program• DOT 1650 employees • Currently 6% unemployment statewide

Big Transportation Program• 250+ projects• $3+ B under construction

Page 3: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Our Need for Speed Customer driven culture Willing to take risks Implement new

technologies:• Accelerated Bridge Construction• Accelerate Pavement Construction• Diverging Diamond Interchanges

Increased partnerships

Page 4: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Department Themes Accelerate Delivery Decrease and Minimize Detours or

Delays Encourage Innovation that speeds project or

provides value Get a Good PriceBalance of good price vs other themes

Page 5: Work Zone Safety Using Accelerated Bridge Construction (ABC)

New Business Model

• Societal Costs Minimized • Societal cost model includes safety costs• Lowest Construction Cost Lowest

Project Cost • Public Praise• Political Capital

Page 6: Work Zone Safety Using Accelerated Bridge Construction (ABC)
Page 7: Work Zone Safety Using Accelerated Bridge Construction (ABC)

I-15 Design Build a Case Study in Project Acceleration

I-15 Design Build – SEP 14• $1.6 B Contract• 17 Miles, 130 Bridges, 7 Urban/3 Interstate Interchanges• 10 Year Maintenance Period

Drivers for Project• Public Support – 4 Years Instead of 9 Years• 2002 Winter Olympics

I – 15 Incentives• Quality, Project Management, MOT, Early Completion• Potential $50M

Post Mortem User Cost Study UofU Dr Martin• USER COSTS SAVED > $500M• Saved estimated 4400+ accidents over Traditional• 14 Lives Saved

Page 8: Work Zone Safety Using Accelerated Bridge Construction (ABC)

What is ABC? Innovative methods to decrease

bridge construction time Build elements offsite/outside traffic

area Transport to site and install rapidly

Page 9: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Benefits of ABC Minimized traffic disruption – from

months to days Improved work zone safety – improved

worker safety Improved product quality – controlled

environment, cure times, easier access, etc.

Page 10: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Innovative Technology

• First implementation costs more• Potential for new methods to cost less• Promise of time savings• Positive cost-benefit ratios• Promise of cost savings

Page 11: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Utah Precast Deck Panel Projects

Page 12: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Family of Innovative ABC Elements and Methods

Precast Concrete Elements

Modular Construction

Structure PlacementMethods

Innovative Accelerated

Bridge Construction

Accelerated Geotech

Work

Fast Track Contracting

Page 13: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Benefits of ABC

Minimizes traffic disruption from months to days Improves work zone and worker safety User savings Improves product quality

• Controlled environment• Cure times• Easier access

Page 14: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Utah ABC Costs18 projects $45M

I-215; 4500 South I-80; State St. to 1300 East

I-80; Mt. Delle to Lambs Canyon

3300 South over I-215 I-15; Widening, 500 North to I-215

Pioneer Crossing$0

$5,000,000

$10,000,000

$15,000,000

$20,000,000

$25,000,000

$30,000,000

User Savings Valued Added

Page 15: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Animation

Page 16: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Media Support

Page 17: Work Zone Safety Using Accelerated Bridge Construction (ABC)

UDOT ABC HistoryABC Element Projects Bridges

Self Propelled Modular Transporters (SPMT) 8 17Half Thickness Deck Panels 5 74Full Depth Deck Precast Deck Panels 15 21Precast Voided Slabs 1 2Approach Slab Panels 10 15Precast Sleeper Slabs 12 19Precast Abutments 3 5Precast Bent Caps 2 2Precast Deck – Slide-in Technique 3 5Precast Box Culvert 3 7Heavy Lift Cranes 3 4

Page 18: Work Zone Safety Using Accelerated Bridge Construction (ABC)

ProjectsI-84 Riverdale Road; Lego Bridge

Page 19: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Projects800 North; Precast Deck Panels

Page 20: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Projects4500 South over I-215; SPMT

Page 21: Work Zone Safety Using Accelerated Bridge Construction (ABC)

ProjectsEagle Canyon Bridge; Precast Deck Panels

Page 22: Work Zone Safety Using Accelerated Bridge Construction (ABC)

2009 Slide ins

Page 23: Work Zone Safety Using Accelerated Bridge Construction (ABC)

2009 Slide ins

Page 24: Work Zone Safety Using Accelerated Bridge Construction (ABC)

ProjectsEcho Canyon Bridge; Slide-in

Page 25: Work Zone Safety Using Accelerated Bridge Construction (ABC)

UDOT Research Study

Reviewing status of ABC Program 161 ABC projects Started with SPMT projects

Page 26: Work Zone Safety Using Accelerated Bridge Construction (ABC)

18 Accelerated Bridge Projects- SPMTs• Traffic impacts Closures and Detours of 2-3 days• Channelizing work zones of usual durations• Zero crashes within work zone(!)• Bridge built away from traffic with better

worker safety and productivity.• One statistical surprise – Slightly more accidents after

construction over.

Preliminary Results

Page 27: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Public Support for ABC

3; 1.40% 4; 1.40% 5; 2.80%

6; 18.30%

7; 76.10%

1 2 3 4 5 6 7

Public Overall Satisfaction With Project Results(1 = not satisfied, 7 = very satisfied)

Page 28: Work Zone Safety Using Accelerated Bridge Construction (ABC)

Questions?