ID ItemNo.TND(GSH
Task Name Duration Start Finish Predecessors
0 Gurdaspur Sri Hargobindpur Road (Maintenance) 255 days Tue07-11-06
Tue04-09-07
1 General 83 days Tue 07-11-06 Thu 15-02-07
2 Date of Commencement of Work 0 days Tue 07-11-06 Tue 07-11-06
3 Mobilization by Contractor 30 days Tue 07-11-06 Mon 11-12-06 2
4 Start of Physical Execution of Work 0 days Wed 15-11-06 Wed 15-11-06 2SS+8 days
5 Non Working Period for Bitumenous Works 82 edays Sat 25-11-06 Thu 15-02-07 4
6 Re-Mobilization for Bitumenous Works 15 days Mon 29-01-07 Wed 14-02-07 5FS-15 days
7 Date of Re-Starting of Work after Non-Working Period 0 days Thu 15-02-07 Thu 15-02-07 5,6,76,78,80,82,84
8 Contract Milestones 248 days Tue 14-11-06 Tue 04-09-07
9 Cont Milestone-1: SAM 8,000 m2 0 days Tue 14-11-06 Tue 14-11-06
10 ?? Current Position for -1: SAM 8,600 m2 0 days Mon 19-02-07 Mon 19-02-07 111SS+1 day
11 Cont Milestone-2a: SAM 60,000 m2 0 days Tue 02-01-07 Tue 02-01-07
12 ?? Current Position for -2a: SAM 60,600 m2 0 days Tue 27-02-07 Tue 27-02-07 122FS-2 days
13 Cont Milestone-2b: SDBC & BC 400 m3 0 days Tue 02-01-07 Tue 02-01-07
14 ?? Current Position for -2b: SDBC 422 m3 0 days Mon 20-11-06 Mon 20-11-06 64
15 Cont Milestone-3a: Maint on Bridges / Culverts 0 days Tue 27-02-07 Tue 27-02-07
16 ?? Current Position for -3a: Maint of Bridges / Culverts Repair 0 days Tue 17-04-07 Tue 17-04-07 403
17 Cont Milestone-3b: Earthern Shoulders 0 days Tue 27-02-07 Tue 27-02-07
18 ?? Current Position for -3b: Earthern Shoulders / E/w Berms 0 days Fri 01-06-07 Fri 01-06-07 420
19 Cont Milestone-3c: Road Furniture 0 days Tue 27-02-07 Tue 27-02-07
20 ?? Current Position for -3c: Road Furniture / KM Stones & Signages
0 days Mon 04-06-07 Mon 04-06-07 421
21 Cont Milestone-4a: SAM 2,25,867 m2 0 days Tue 31-07-07 Tue 31-07-07
22 ?? Current Position for -4a: SAM Completion 2,25,867 m2 0 days Fri 04-05-07 Fri 04-05-07 418
23 Cont Milestone-4b: SDBC & BC 13,957 m3 0 days Tue 31-07-07 Tue 31-07-07
24 ?? Current Position for -4b: SDBC & BC Completion 13,958 m3
0 days Thu 24-05-07 Thu 24-05-07 417,419
25 Cont Milestone-5: Road Marking & KM Stones etc 0 days Tue 04-09-07 Tue 04-09-07
26 ?? Current Position for -5: Road Marking 0 days Sat 30-06-07 Sat 30-06-07 423
27 ?? Current Position for -6: Completion All Works 0 days Thu 12-07-07 Thu 12-07-07 428
28 Margin Time at End of All Works 45 days Fri 13-07-07 Tue 04-09-07 427
29 EMP Process 7 days Tue 07-11-06 Tue 14-11-06
30 Verification of Existing Hot Mix Plant 4 days Tue 07-11-06 Fri 10-11-06 2
31 Approval of existing Hot Mix Plant 0 days Fri 10-11-06 Fri 10-11-06 30
32 Verification of Relevant Docomentation EMP 7 days Tue 07-11-06 Tue 14-11-06 2
33 Approvals regarding various EMP Documentations 0 days Tue 14-11-06 Tue 14-11-06 32
34 Compliance with clauses of EMP 7 days Tue 07-11-06 Tue 14-11-06 2
35 Issue of Memo regarding compliance of various EMP Clauses 0 days Tue 14-11-06 Tue 14-11-06 34
36 Borrow Area Identification & Checking 2 days Tue 07-11-06 Wed 08-11-06 2
37 Approval of Borrow Areas 0 days Wed 08-11-06 Wed 08-11-06 36
38 Traffic Management Plan Preparation & Submission 5 days Tue 07-11-06 Sat 11-11-06 2
39 Approval of Traffic Management Plan 0 days Sat 11-11-06 Sat 11-11-06 38
40 Execution of Work 207 days Fri 10-11-06 Thu 12-07-07
41 30 mm SDBC 3.47 km (RD 37 to 40.47) 82 days Fri 10-11-06 Fri 16-02-07
42 SDBC Material & Job Mix 3 days Fri 10-11-06 Mon 13-11-06
43 Inspection & Checking of material 2 days Fri 10-11-06 Sat 11-11-06 51SS-5 days
44 Approval of Material 0 days Sat 11-11-06 Sat 11-11-06 43
45 Submission of Job Mix Formula 2 days Fri 10-11-06 Sat 11-11-06 51SS-5 days
46 Approval of Job Mix 0 days Mon 13-11-06 Mon 13-11-06 45FS+1 day
47 SDBC 37-38 (1 km) 3 days Tue 14-11-06 Fri 17-11-06
48 Approval to start work in this reach 0 days Tue 14-11-06 Tue 14-11-06 4FS-2 days,31,33,
49 Traffic Management, Day Night Signages, etc 2 days Thu 16-11-06 Fri 17-11-06 52SS
50 Watering Side Berms & other preparations, etc 2 days Thu 16-11-06 Fri 17-11-06 52SS
51 Preparation of surface 2 days Thu 16-11-06 Fri 17-11-06 4
52 02.b P/L Tack coat for SDBC 2 days Thu 16-11-06 Fri 17-11-06 51SS,48,46,44
53 04 Laying & Consolidation of SDBC 2 days Thu 16-11-06 Fri 17-11-06 52SS
54 Checking, Rectification & Field Tests, etc 2 days Thu 16-11-06 Fri 17-11-06 53SS
55 Completion & Approval SDBC 37-38 0 days Fri 17-11-06 Fri 17-11-06 51,52,49,50,54,53
56 SDBC 38-39 (1 km) 4 days Thu 16-11-06 Mon 20-11-06
57 Approval to start work in this reach 0 days Thu 16-11-06 Thu 16-11-06 55FS-2 days
58 Traffic Management, Day Night Signages, etc 2 days Sat 18-11-06 Mon 20-11-06 61SS
59 Watering Side Berms & other preparations, etc 2 days Sat 18-11-06 Mon 20-11-06 61SS
60 Preparation of surface 2 days Sat 18-11-06 Mon 20-11-06 57,55
61 02.b P/L Tack coat for SDBC 2 days Sat 18-11-06 Mon 20-11-06 60SS
62 04 Laying & Consolidation of SDBC 2 days Sat 18-11-06 Mon 20-11-06 61SS
63 Checking, Rectification & Field Tests, etc 2 days Sat 18-11-06 Mon 20-11-06 62SS
64 Completion & Approval SDBC 38-39 0 days Mon 20-11-06 Mon 20-11-06 60,61,62,58,59,63
65 SDBC 39-40 (1 km) 4 days Sat 18-11-06 Wed 22-11-06
66 Approval to start work in this reach 0 days Sat 18-11-06 Sat 18-11-06 64FS-2 days
67 Traffic Management, Day Night Signages, etc 2 days Tue 21-11-06 Wed 22-11-06 70SS
68 Watering Side Berms & other preparations, etc 2 days Tue 21-11-06 Wed 22-11-06 70SS
69 Preparation of surface 2 days Tue 21-11-06 Wed 22-11-06 64,66
70 02.b P/L Tack coat for SDBC 2 days Tue 21-11-06 Wed 22-11-06 69SS
71 04 Laying & Consolidation of SDBC 2 days Tue 21-11-06 Wed 22-11-06 70SS
72 Checking, Rectification & Field Tests, etc 2 days Tue 21-11-06 Wed 22-11-06 71SS
73 Completion & Approval SDBC 39-40 0 days Wed 22-11-06 Wed 22-11-06 69,70,71,72,67,68
74 EMP Process before re-starting work 7 days Mon 29-01-07 Mon 05-02-07
75 Verification of Existing Hot Mix Plant for re-start 4 days Mon 29-01-07 Thu 01-02-07 5FS-15 days
76 Approval of existing Hot Mix Plant to re-start 0 days Thu 01-02-07 Thu 01-02-07 75
77 Verification of Relevant Docomentation EMP, re-start 7 days Mon 29-01-07 Mon 05-02-07 5FS-15 days
78 Approvals regarding various EMP Documentations, re-start
0 days Mon 05-02-07 Mon 05-02-07 77
79 Compliance with clauses of EMP, re-start 7 days Mon 29-01-07 Mon 05-02-07 5FS-15 days
80 Issue of Memo regarding compliance of various EMP Clauses, re-start
0 days Mon 05-02-07 Mon 05-02-07 79
81 Borrow Area Identification & Checking, re-start 2 days Mon 29-01-07 Tue 30-01-07 5FS-15 days
82 Approval of Borrow Areas, re-start 0 days Tue 30-01-07 Tue 30-01-07 81
83 Traffic Management Plan Preparation & Submission, re-start
5 days Mon 29-01-07 Fri 02-02-07 5FS-15 days
84 Approval of Traffic Management Plan, re-start 0 days Fri 02-02-07 Fri 02-02-07 83
85 SDBC Material & Job Mix before re-starting work 3 days Sat 10-02-07 Tue 13-02-07
86 Inspection & Checking of material 2 days Sat 10-02-07 Mon 12-02-07 94SS-5 days
87 Approval of Material 0 days Mon 12-02-07 Mon 12-02-07 86
88 Submission of Job Mix Formula 2 days Sat 10-02-07 Mon 12-02-07 94SS-5 days
89 Approval of Job Mix 0 days Tue 13-02-07 Tue 13-02-07 88FS+1 day
90 SDBC 40-40.47 (0.47 km) 4 days Tue 13-02-07 Fri 16-02-07
91 Approval to start work in this reach 0 days Tue 13-02-07 Tue 13-02-07 7FS-2 days
92 Traffic Management, Day Night Signages, etc 1 day Fri 16-02-07 Fri 16-02-07 95SS
93 Watering Side Berms & other preparations, etc 1 day Fri 16-02-07 Fri 16-02-07 95SS
94 Preparation of surface 1 day Fri 16-02-07 Fri 16-02-07 73,5,3,7FS+1 day,
95 02.b P/L Tack coat for SDBC 1 day Fri 16-02-07 Fri 16-02-07 94SS,87,89,91
96 04 Laying & Consolidation of SDBC 1 day Fri 16-02-07 Fri 16-02-07 95SS
97 Checking, Rectification & Field Tests, etc 1 day Fri 16-02-07 Fri 16-02-07 96SS
98 Completion & Approval SDBC 40-40.47 0 days Fri 16-02-07 Fri 16-02-07 94,95,96,97,92,93
99 Stress Absorbing Membrane Crack Seal (upto 3500 m2 / 0.5 km)
71 days Mon 12-02-07 Fri 04-05-07
100 SAM Material & Job Mix 0-10 km 3 days Mon 12-02-07 Wed 14-02-07
101 Inspection & Checking of material 2 days Mon 12-02-07 Tue 13-02-07 109SS-5 days
102 Approval of Material 0 days Tue 13-02-07 Tue 13-02-07 101
103 Submission of Job Mix Formula 2 days Mon 12-02-07 Tue 13-02-07 109SS-5 days
104 Approval of Job Mix 0 days Wed 14-02-07 Wed 14-02-07 103FS+1 day
105 SAM 0-5 (5km) < 6 mm 7 days Thu 15-02-07 Thu 22-02-07
106 Approval to start work in this reach 0 days Thu 15-02-07 Thu 15-02-07 98FS-2 days
107 Traffic Management, Day Night Signages, etc 5 days Sat 17-02-07 Thu 22-02-07 109SS
108 Watering Side Berms & other preparations, etc 5 days Sat 17-02-07 Thu 22-02-07 109SS
109 Preparation of surface 5 days Sat 17-02-07 Thu 22-02-07 98,7,106
110 01.a P/L Tack Coat / CRMB 60 for SAM 4 days Mon 19-02-07 Thu 22-02-07 109SS+1 day,102,
111 01.a Laying & Consolidation of aggregate (SAM < 6 mm) 4 days Mon 19-02-07 Thu 22-02-07 110SS
07-11 Date of Commencement of Work
07-11 11-12
15-11 Start of Physical Execution of Work
25-11 15-02
29-01 14-02
15-02 Date of Re-Starting of Work after Non-Working Period
14-11 Cont Milestone-1: SAM 8,000 m2
19-02 ?? Current Position for -1: SAM 8,600 m2
02-01 Cont Milestone-2a: SAM 60,000 m2
27-02 ?? Current Position for -2a: SAM 60,600 m2
02-01 Cont Milestone-2b: SDBC & BC 400 m3
20-11 ?? Current Position for -2b: SDBC 422 m3
27-02 Cont Milestone-3a: Maint on Bridges / Culverts
17-04 ?? Current Position for -3a: Maint of Bridges / Culverts Repair
27-02 Cont Milestone-3b: Earthern Shoulders
01-06 ?? Current Position for -3b: Earthern Shoulders / E/w Berms
27-02 Cont Milestone-3c: Road Furniture
04-06 ?? Current Position for -3c: Road Furniture / KM Stones & Signages
31-07 Cont Milestone-4a: SAM 2,25,867 m2
04-05 ?? Current Position for -4a: SAM Completion 2,25,867 m2
31-07 Cont Milestone-4b: SDBC & BC 13,957 m3
24-05 ?? Current Position for -4b: SDBC & BC Completion 13,958 m3
04-09 Cont Milestone-5: Road Marking & KM Stones etc
30-06 ?? Current Position for -5: Road Marking
12-07 ?? Current Position for -6: Completion All Works
13-07 04-09
07-11 10-11
10-11 Approval of existing Hot Mix Plant
07-11 14-11
14-11 Approvals regarding various EMP Documentations
07-11 14-11
14-11 Issue of Memo regarding compliance of various EMP Clauses
07-11 08-11
08-11 Approval of Borrow Areas
07-11 11-11
11-11 Approval of Traffic Management Plan
10-11 11-11
11-11 Approval of Material
10-11 11-11
13-11 Approval of Job Mix
14-11 Approval to start work in this reach
16-11 17-11
16-11 17-11
16-11 17-11
16-11 17-11
16-11 17-11
16-11 17-11
17-11 Completion & Approval SDBC 37-38
16-11 Approval to start work in this reach
18-11 20-11
18-11 20-11
18-11 20-11
18-11 20-11
18-11 20-11
18-11 20-11
20-11 Completion & Approval SDBC 38-39
18-11 Approval to start work in this reach
21-11 22-11
21-11 22-11
21-11 22-11
21-11 22-11
21-11 22-11
21-11 22-11
22-11 Completion & Approval SDBC 39-40
29-01 01-02
01-02 Approval of existing Hot Mix Plant to re-start
29-01 05-02
05-02 Approvals regarding various EMP Documentations, re-start
29-01 05-02
05-02 Issue of Memo regarding compliance of various EMP Clauses, re-start
29-01 30-01
30-01 Approval of Borrow Areas, re-start
29-01 02-02
02-02 Approval of Traffic Management Plan, re-start
10-02 12-02
12-02 Approval of Material
10-02 12-02
13-02 Approval of Job Mix
13-02 Approval to start work in this reach
16-02 16-02
16-02 16-02
16-02 16-02
16-02 16-02
16-02 16-02
16-02 16-02
16-02 Completion & Approval SDBC 40-40.47
12-02 13-02
13-02 Approval of Material
12-02 13-02
14-02 Approval of Job Mix
15-02 Approval to start work in this reach
17-02 22-02
17-02 22-02
17-02 22-02
19-02 22-02
19-02 22-02
30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28November 2006 December 2006 January 2007 February 2007 March 2007 April 2007 May 2007 June 2007 July 2007 August 2007 September 2007
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Gurdaspur Sri Hargobindpur Road
Page 1
Project: Gurdaspur Sri Hargobindpur RDate: Mon 14-09-15
![Page 2: work program](https://reader035.vdocuments.us/reader035/viewer/2022080222/563db956550346aa9a9c5bac/html5/thumbnails/2.jpg)
ID ItemNo.TND(GSH
Task Name Duration Start Finish Predecessors
112 Checking, Rectification & Field Tests, etc 4 days Mon 19-02-07 Thu 22-02-07 111SS
113 Completion & Approval SAM 0-5 0 days Thu 22-02-07 Thu 22-02-07 109,110,111,112,1
114 SAM 5-10 (5 km) < 6 mm 7 days Wed 21-02-07 Wed 28-02-07
115 Approval to start work in this reach 0 days Wed 21-02-07 Wed 21-02-07 113FS-2 days
116 Traffic Management, Day Night Signages, etc 5 days Fri 23-02-07 Wed 28-02-07 118SS
117 Watering Side Berms & other preparations, etc 5 days Fri 23-02-07 Wed 28-02-07 118SS
118 Preparation of surface 5 days Fri 23-02-07 Wed 28-02-07 113,115
119 01.a P/L Tack Coat / CRMB 60 4 days Sat 24-02-07 Wed 28-02-07 118SS+1 day
120 01.a Laying & Consolidation of aggregate (SAM < 6 mm) 4 days Sat 24-02-07 Wed 28-02-07 119SS
121 Checking, Rectification & Field Tests, etc 4 days Sat 24-02-07 Wed 28-02-07 120SS
122 Completion & Approval SAM 5-10 0 days Wed 28-02-07 Wed 28-02-07 118,119,120,116,1
123 SAM Material & Job Mix 10-25 km 3 days Wed 07-03-07 Fri 09-03-07
124 Inspection & Checking of material 2 days Wed 07-03-07 Thu 08-03-07 133SS-5 days
125 Approval of Material 0 days Thu 08-03-07 Thu 08-03-07 124
126 Submission of Job Mix Formula 2 days Wed 07-03-07 Thu 08-03-07 133SS-5 days
127 Approval of Job Mix 0 days Fri 09-03-07 Fri 09-03-07 126FS+1 day
128 SAM 10-15 (5km) < 6 mm 15 days Tue 27-02-07 Thu 15-03-07
129 Margin Time to start 10 days Thu 01-03-07 Mon 12-03-07 122
130 Approval to start work in this reach 0 days Tue 27-02-07 Tue 27-02-07 122FS-2 days
131 Traffic Management, Day Night Signages, etc 3 days Tue 13-03-07 Thu 15-03-07 133SS
132 Watering Side Berms & other preparations, etc 3 days Tue 13-03-07 Thu 15-03-07 133SS
133 Preparation of surface 2 days Tue 13-03-07 Wed 14-03-07 129,130
134 01.a P/L Tack Coat / CRMB 60 for SAM 2 days Tue 13-03-07 Wed 14-03-07 133SS,125,127
135 01.a Laying & Consolidation of aggregate (SAM < 6 mm) 2 days Tue 13-03-07 Wed 14-03-07 134SS
136 01.a Builtup Area SAM <6 mm 1 day Thu 15-03-07 Thu 15-03-07 135
137 Checking, Rectification & Field Tests, etc 3 days Tue 13-03-07 Thu 15-03-07 135SS
138 Completion & Approval SAM 10-15 0 days Thu 15-03-07 Thu 15-03-07 133,134,135,136,1
139 SAM 15-20 (5 km) < 6 mm 5 days Wed 14-03-07 Mon 19-03-07
140 Approval to start work in this reach 0 days Wed 14-03-07 Wed 14-03-07 138FS-2 days
141 Traffic Management, Day Night Signages, etc 3 days Fri 16-03-07 Mon 19-03-07 143SS
142 Watering Side Berms & other preparations, etc 3 days Fri 16-03-07 Mon 19-03-07 143SS
143 Preparation of surface 3 days Fri 16-03-07 Mon 19-03-07 138,140
144 01.a P/L Tack Coat / CRMB 60 for SAM 2 days Sat 17-03-07 Mon 19-03-07 143SS+1 day
145 01.a Laying & Consolidation of aggregate (SAM < 6 mm) 2 days Sat 17-03-07 Mon 19-03-07 144SS
146 Checking, Rectification & Field Tests, etc 2 days Sat 17-03-07 Mon 19-03-07 145SS
147 Completion & Approval SAM 15-20 0 days Mon 19-03-07 Mon 19-03-07 143,144,145,141,1
148 SAM 20-25 (5 km) < 6 mm 23 days Sat 17-03-07 Thu 12-04-07
149 Margin Time to start 15 days Tue 20-03-07 Thu 05-04-07 147
150 Approval to start work in this reach 0 days Sat 17-03-07 Sat 17-03-07 147FS-2 days
151 Traffic Management, Day Night Signages, etc 6 days Fri 06-04-07 Thu 12-04-07 153SS
152 Watering Side Berms & other preparations, etc 6 days Fri 06-04-07 Thu 12-04-07 153SS
153 Preparation of surface 5 days Fri 06-04-07 Wed 11-04-07 149,150
154 01.a P/L Tack Coat / CRMB 60 for SAM 4 days Sat 07-04-07 Wed 11-04-07 153SS+1 day
155 01.a Laying & Consolidation of aggregate (SAM < 6 mm) 4 days Sat 07-04-07 Wed 11-04-07 154SS
156 01.a Builtup Area SAM <6 mm 1 day Thu 12-04-07 Thu 12-04-07 155
157 Checking, Rectification & Field Tests, etc 5 days Sat 07-04-07 Thu 12-04-07 155SS
158 Completion & Approval SAM 20-25 0 days Thu 12-04-07 Thu 12-04-07 153,154,155,156,1
159 SAM Material & Job Mix 25-37 km 3 days Sat 07-04-07 Tue 10-04-07
160 Inspection & Checking of material 2 days Sat 07-04-07 Mon 09-04-07 168SS-5 days
161 Approval of Material 0 days Mon 09-04-07 Mon 09-04-07 160
162 Submission of Job Mix Formula 2 days Sat 07-04-07 Mon 09-04-07 168SS-5 days
163 Approval of Job Mix 0 days Tue 10-04-07 Tue 10-04-07 162FS+1 day
164 SAM 25-30 (5 km) < 6 mm 8 days Wed 11-04-07 Thu 19-04-07
165 Approval to start work in this reach 0 days Wed 11-04-07 Wed 11-04-07 158FS-2 days
166 Traffic Management, Day Night Signages, etc 6 days Fri 13-04-07 Thu 19-04-07 168SS
167 Watering Side Berms & other preparations, etc 6 days Fri 13-04-07 Thu 19-04-07 168SS
168 Preparation of surface 5 days Fri 13-04-07 Wed 18-04-07 158,165
169 01.a P/L Tack Coat / CRMB 60 for SAM 4 days Sat 14-04-07 Wed 18-04-07 168SS+1 day,161,
170 01.a Laying & Consolidation of aggregate (SAM < 6 mm) 4 days Sat 14-04-07 Wed 18-04-07 169SS
171 01.a Builtup Area SAM <6 mm 1 day Thu 19-04-07 Thu 19-04-07 170
172 Checking, Rectification & Field Tests, etc 5 days Sat 14-04-07 Thu 19-04-07 170SS
173 Completion & Approval SAM 25-30 0 days Thu 19-04-07 Thu 19-04-07 168,169,170,171,1
174 SAM 30-35 (5 km) 6-9 mm 13 days Wed 18-04-07 Wed 02-05-07
175 Margin Time to start 5 days Fri 20-04-07 Wed 25-04-07 173
176 Approval to start work in this reach 0 days Wed 18-04-07 Wed 18-04-07 173FS-2 days
177 Traffic Management, Day Night Signages, etc 6 days Thu 26-04-07 Wed 02-05-07 179SS
178 Watering Side Berms & other preparations, etc 6 days Thu 26-04-07 Wed 02-05-07 179SS
179 Preparation of surface 5 days Thu 26-04-07 Tue 01-05-07 175,176
180 01.b P/L Tack Coat / CRMB 60 for SAM 4 days Fri 27-04-07 Tue 01-05-07 179SS+1 day
181 01.b Laying & Consolidation of aggregate (SAM 6-9 mm) 4 days Fri 27-04-07 Tue 01-05-07 180SS
182 Checking, Rectification & Field Tests, etc 5 days Fri 27-04-07 Wed 02-05-07 181SS
183 Completion & Approval SAM 30-35 0 days Wed 02-05-07 Wed 02-05-07 179,180,181,176,1
184 SAM 35-37 (2 km) 6-9 mm 4 days Tue 01-05-07 Fri 04-05-07
185 Approval to start work in this reach 0 days Tue 01-05-07 Tue 01-05-07 183FS-2 days
186 Traffic Management, Day Night Signages, etc 2 days Thu 03-05-07 Fri 04-05-07 188SS
187 Watering Side Berms & other preparations, etc 2 days Thu 03-05-07 Fri 04-05-07 188SS
188 Preparation of surface 2 days Thu 03-05-07 Fri 04-05-07 183,185
189 01.b P/L Tack Coat / CRMB 60 for SAM 2 days Thu 03-05-07 Fri 04-05-07 188SS
190 01.b Laying & Consolidation of aggregate (SAM 6-9 mm) 2 days Thu 03-05-07 Fri 04-05-07 189SS
191 Checking, Rectification & Field Tests, etc 2 days Thu 03-05-07 Fri 04-05-07 190SS
192 Completion & Approval SAM 35-37 0 days Fri 04-05-07 Fri 04-05-07 188,189,190,186,1
193 50 mm BC 37 km (RD 0 to 37) 83 days Sat 17-02-07 Thu 24-05-07
194 BC Material & Job Mix 0-5 km 3 days Sat 17-02-07 Tue 20-02-07
195 Inspection & Checking of material 2 days Sat 17-02-07 Mon 19-02-07 203SS-5 days
196 Approval of Material 0 days Mon 19-02-07 Mon 19-02-07 195
197 Submission of Job Mix Formula 2 days Sat 17-02-07 Mon 19-02-07 203SS-5 days
198 Approval of Job Mix 0 days Tue 20-02-07 Tue 20-02-07 197FS+1 day
199 BC 0-5 (5 km) 12 days Wed 21-02-07 Tue 06-03-07
200 Approval to start work in this reach 0 days Wed 21-02-07 Wed 21-02-07 113FS-2 days
201 Traffic Management, Day Night Signages, etc 10 days Fri 23-02-07 Tue 06-03-07 203SS
202 Watering Side Berms & other preparations, etc 10 days Fri 23-02-07 Tue 06-03-07 203SS
203 Preparation of surface 10 days Fri 23-02-07 Tue 06-03-07 113,7,200
204 02.a P/L Tack coat for BC 10 days Fri 23-02-07 Tue 06-03-07 203SS,196,198
205 03 Laying & Consolidation of BC 10 days Fri 23-02-07 Tue 06-03-07 204SS
206 Checking, Rectification & Field Tests, etc 10 days Fri 23-02-07 Tue 06-03-07 205SS
207 Completion & Approval BC 0-5 0 days Tue 06-03-07 Tue 06-03-07 203,204,205,201,2
208 BC 5-10 (5 km) 12 days Mon 05-03-07 Sat 17-03-07
209 Approval to start work in this reach 0 days Mon 05-03-07 Mon 05-03-07 207FS-2 days
210 Traffic Management, Day Night Signages, etc 10 days Wed 07-03-07 Sat 17-03-07 212SS
211 Watering Side Berms & other preparations, etc 10 days Wed 07-03-07 Sat 17-03-07 212SS
212 Preparation of surface 10 days Wed 07-03-07 Sat 17-03-07 122,207,209
213 02.a P/L Tack coat for BC 10 days Wed 07-03-07 Sat 17-03-07 212SS
214 03 Laying & Consolidation of BC 10 days Wed 07-03-07 Sat 17-03-07 213SS
215 Checking, Rectification & Field Tests, etc 10 days Wed 07-03-07 Sat 17-03-07 214SS
216 Completion & Approval BC 5-10 0 days Sat 17-03-07 Sat 17-03-07 212,213,214,210,2
217 Material & Job Mix 3 days Tue 13-03-07 Thu 15-03-07
218 Inspection & Checking of material 2 days Tue 13-03-07 Wed 14-03-07 226SS-5 days
219 Approval of Material 0 days Wed 14-03-07 Wed 14-03-07 218
220 Submission of Job Mix Formula 2 days Tue 13-03-07 Wed 14-03-07 226SS-5 days
221 Approval of Job Mix 0 days Thu 15-03-07 Thu 15-03-07 220FS+1 day
222 BC 10-15 (5 km) 13 days Fri 16-03-07 Fri 30-03-07
223 Approval to start work in this reach 0 days Fri 16-03-07 Fri 16-03-07 216FS-2 days
19-02 22-02
22-02 Completion & Approval SAM 0-5
21-02 Approval to start work in this reach
23-02 28-02
23-02 28-02
23-02 28-02
24-02 28-02
24-02 28-02
24-02 28-02
28-02 Completion & Approval SAM 5-10
07-03 08-03
08-03 Approval of Material
07-03 08-03
09-03 Approval of Job Mix
01-03 12-03
27-02 Approval to start work in this reach
13-03 15-03
13-03 15-03
13-03 14-03
13-03 14-03
13-03 14-03
15-03 15-03
13-03 15-03
15-03 Completion & Approval SAM 10-15
14-03 Approval to start work in this reach
16-03 19-03
16-03 19-03
16-03 19-03
17-03 19-03
17-03 19-03
17-03 19-03
19-03 Completion & Approval SAM 15-20
20-03 05-04
17-03 Approval to start work in this reach
06-04 12-04
06-04 12-04
06-04 11-04
07-04 11-04
07-04 11-04
12-04 12-04
07-04 12-04
12-04 Completion & Approval SAM 20-25
07-04 09-04
09-04 Approval of Material
07-04 09-04
10-04 Approval of Job Mix
11-04 Approval to start work in this reach
13-04 19-04
13-04 19-04
13-04 18-04
14-04 18-04
14-04 18-04
19-04 19-04
14-04 19-04
19-04 Completion & Approval SAM 25-30
20-04 25-04
18-04 Approval to start work in this reach
26-04 02-05
26-04 02-05
26-04 01-05
27-04 01-05
27-04 01-05
27-04 02-05
02-05 Completion & Approval SAM 30-35
01-05 Approval to start work in this reach
03-05 04-05
03-05 04-05
03-05 04-05
03-05 04-05
03-05 04-05
03-05 04-05
04-05 Completion & Approval SAM 35-37
17-02 19-02
19-02 Approval of Material
17-02 19-02
20-02 Approval of Job Mix
21-02 Approval to start work in this reach
23-02 06-03
23-02 06-03
23-02 06-03
23-02 06-03
23-02 06-03
23-02 06-03
06-03 Completion & Approval BC 0-5
05-03 Approval to start work in this reach
07-03 17-03
07-03 17-03
07-03 17-03
07-03 17-03
07-03 17-03
07-03 17-03
17-03 Completion & Approval BC 5-10
13-03 14-03
14-03 Approval of Material
13-03 14-03
15-03 Approval of Job Mix
16-03 Approval to start work in this reach
30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28November 2006 December 2006 January 2007 February 2007 March 2007 April 2007 May 2007 June 2007 July 2007 August 2007 September 2007
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Gurdaspur Sri Hargobindpur Road
Page 2
Project: Gurdaspur Sri Hargobindpur RDate: Mon 14-09-15
![Page 3: work program](https://reader035.vdocuments.us/reader035/viewer/2022080222/563db956550346aa9a9c5bac/html5/thumbnails/3.jpg)
ID ItemNo.TND(GSH
Task Name Duration Start Finish Predecessors
224 Traffic Management, Day Night Signages, etc 11 days Mon 19-03-07 Fri 30-03-07 226SS
225 Watering Side Berms & other preparations, etc 11 days Mon 19-03-07 Fri 30-03-07 226SS
226 Preparation of surface 10 days Mon 19-03-07 Thu 29-03-07 138,216,223
227 02.a P/L Tack coat for BC 10 days Mon 19-03-07 Thu 29-03-07 226SS,219,221
228 03 Laying & Consolidation of BC 10 days Mon 19-03-07 Thu 29-03-07 227SS
229 02.a Builtup Area Tack Coat for BC 1 day Fri 30-03-07 Fri 30-03-07 228
230 03 Builtup Area BC 1 day Fri 30-03-07 Fri 30-03-07 229FF
231 Checking, Rectification & Field Tests, etc 11 days Mon 19-03-07 Fri 30-03-07 228SS
232 Completion & Approval BC 10-15 0 days Fri 30-03-07 Fri 30-03-07 226,227,230,228,2
233 BC 15-20 (5 km) 12 days Thu 29-03-07 Wed 11-04-07
234 Approval to start work in this reach 0 days Thu 29-03-07 Thu 29-03-07 232FS-2 days
235 Traffic Management, Day Night Signages, etc 10 days Sat 31-03-07 Wed 11-04-07 237SS
236 Watering Side Berms & other preparations, etc 10 days Sat 31-03-07 Wed 11-04-07 237SS
237 Preparation of surface 10 days Sat 31-03-07 Wed 11-04-07 147,232,234
238 02.a P/L Tack coat for BC 10 days Sat 31-03-07 Wed 11-04-07 237SS
239 03 Laying & Consolidation of BC 10 days Sat 31-03-07 Wed 11-04-07 238SS
240 Checking, Rectification & Field Tests, etc 10 days Sat 31-03-07 Wed 11-04-07 239SS
241 Completion & Approval BC 15-20 0 days Wed 11-04-07 Wed 11-04-07 237,238,239,235,2
242 BC 20-25 (5 km) 14 days Tue 10-04-07 Wed 25-04-07
243 Approval to start work in this reach 0 days Tue 10-04-07 Tue 10-04-07 241FS-2 days
244 Traffic Management, Day Night Signages, etc 11 days Fri 13-04-07 Wed 25-04-07 246SS
245 Watering Side Berms & other preparations, etc 11 days Fri 13-04-07 Wed 25-04-07 246SS
246 Preparation of surface 10 days Fri 13-04-07 Tue 24-04-07 241,158,243
247 02.a P/L Tack coat for BC 10 days Fri 13-04-07 Tue 24-04-07 246SS
248 03 Laying & Consolidation of BC 10 days Fri 13-04-07 Tue 24-04-07 247SS
249 02.a Builtup Area Tack Coat for BC 1 day Tue 24-04-07 Tue 24-04-07 248FF
250 03 Builtup Area BC 1 day Wed 25-04-07 Wed 25-04-07 249
251 Checking, Rectification & Field Tests, etc 11 days Fri 13-04-07 Wed 25-04-07 248SS
252 Completion & Approval BC 20-25 0 days Wed 25-04-07 Wed 25-04-07 246,247,250,248,2
253 Material & Job Mix 3 days Fri 20-04-07 Mon 23-04-07
254 Inspection & Checking of material 2 days Fri 20-04-07 Sat 21-04-07 262SS-5 days
255 Approval of Material 0 days Sat 21-04-07 Sat 21-04-07 254
256 Submission of Job Mix Formula 2 days Fri 20-04-07 Sat 21-04-07 262SS-5 days
257 Approval of Job Mix 0 days Mon 23-04-07 Mon 23-04-07 256FS+1 day
258 BC 25-30 (5 km) 13 days Tue 24-04-07 Tue 08-05-07
259 Approval to start work in this reach 0 days Tue 24-04-07 Tue 24-04-07 252FS-2 days
260 Traffic Management, Day Night Signages, etc 11 days Thu 26-04-07 Tue 08-05-07 262SS
261 Watering Side Berms & other preparations, etc 11 days Thu 26-04-07 Tue 08-05-07 262SS
262 Preparation of surface 10 days Thu 26-04-07 Mon 07-05-07 173,252,259
263 02.a P/L Tack coat for BC 10 days Thu 26-04-07 Mon 07-05-07 262SS,255,257
264 03 Laying & Consolidation of BC 10 days Thu 26-04-07 Mon 07-05-07 263SS
265 02.a Builtup Area Tack Coat for BC 1 day Tue 08-05-07 Tue 08-05-07 264
266 03 Builtup Area BC 1 day Tue 08-05-07 Tue 08-05-07 265FF
267 Checking, Rectification & Field Tests, etc 11 days Thu 26-04-07 Tue 08-05-07 264SS
268 Completion & Approval BC 25-30 0 days Tue 08-05-07 Tue 08-05-07 262,263,266,264,2
269 BC 30-35 (5 km) 12 days Mon 07-05-07 Sat 19-05-07
270 Approval to start work in this reach 0 days Mon 07-05-07 Mon 07-05-07 268FS-2 days
271 Traffic Management, Day Night Signages, etc 10 days Wed 09-05-07 Sat 19-05-07 273SS
272 Watering Side Berms & other preparations, etc 10 days Wed 09-05-07 Sat 19-05-07 273SS
273 Preparation of surface 10 days Wed 09-05-07 Sat 19-05-07 183,268,270
274 02.a P/L Tack coat for BC 10 days Wed 09-05-07 Sat 19-05-07 273SS
275 03 Laying & Consolidation of BC 10 days Wed 09-05-07 Sat 19-05-07 274SS
276 Checking, Rectification & Field Tests, etc 10 days Wed 09-05-07 Sat 19-05-07 275SS
277 Completion & Approval BC 30-35 0 days Sat 19-05-07 Sat 19-05-07 273,274,275,271,2
278 BC 35-37 (2 km) 6 days Fri 18-05-07 Thu 24-05-07
279 Approval to start work in this reach 0 days Fri 18-05-07 Fri 18-05-07 277FS-2 days
280 Traffic Management, Day Night Signages, etc 4 days Mon 21-05-07 Thu 24-05-07 282SS
281 Watering Side Berms & other preparations, etc 4 days Mon 21-05-07 Thu 24-05-07 282SS
282 Preparation of surface 4 days Mon 21-05-07 Thu 24-05-07 277,192,279
283 02.a P/L Tack coat for BC 4 days Mon 21-05-07 Thu 24-05-07 282SS
284 03 Laying & Consolidation of BC 4 days Mon 21-05-07 Thu 24-05-07 283SS
285 Checking, Rectification & Field Tests, etc 4 days Mon 21-05-07 Thu 24-05-07 284SS
286 Completion & Approval BC 35-37 0 days Thu 24-05-07 Thu 24-05-07 282,283,284,280,2
287 Earth Work on berms 80 days Thu 01-03-07 Fri 01-06-07
288 Earth Material 0-20 km 2 days Thu 01-03-07 Fri 02-03-07
289 Inspection & Checking of Earth 2 days Thu 01-03-07 Fri 02-03-07 292SS-5 days
290 Approval of Earth 0 days Fri 02-03-07 Fri 02-03-07 289
291 E/W Berms 0-5 (5 km) both side 6 days Wed 07-03-07 Tue 13-03-07
292 Setting out berms 2 days Wed 07-03-07 Thu 08-03-07 207
293 05 Laying of Earth / Maint of Earthern Shoulders 4 days Thu 08-03-07 Mon 12-03-07 292SS+1 day,290
294 Consolidation of earth 5 days Thu 08-03-07 Tue 13-03-07 293SS
295 Completion & Approval Berm 0-5 0 days Tue 13-03-07 Tue 13-03-07 292,293,294
296 E/W Berms 5-10 (5 km) both side 6 days Mon 19-03-07 Sat 24-03-07
297 Setting out berms 2 days Mon 19-03-07 Tue 20-03-07 216
298 05 Laying of Earth / Maint of Earthern Shoulders 4 days Tue 20-03-07 Fri 23-03-07 297SS+1 day
299 Consolidation of earth 5 days Tue 20-03-07 Sat 24-03-07 298SS
300 Completion & Approval Berm 5-10 0 days Sat 24-03-07 Sat 24-03-07 297,298,299
301 E/W Berms 10-15 (5 km) both side 6 days Sat 31-03-07 Fri 06-04-07
302 Setting out berms 2 days Sat 31-03-07 Mon 02-04-07 232
303 05 Laying of Earth / Maint of Earthern Shoulders 4 days Mon 02-04-07 Thu 05-04-07 302SS+1 day
304 Consolidation of earth 5 days Mon 02-04-07 Fri 06-04-07 303SS
305 Completion & Approval Berm 10-15 0 days Fri 06-04-07 Fri 06-04-07 302,303,304
306 E/W Berms 15-20 (5 km) both side 6 days Thu 12-04-07 Wed 18-04-07
307 Setting out berms 2 days Thu 12-04-07 Fri 13-04-07 241
308 05 Laying of Earth / Maint of Earthern Shoulders 4 days Fri 13-04-07 Tue 17-04-07 307SS+1 day
309 Consolidation of earth 5 days Fri 13-04-07 Wed 18-04-07 308SS
310 Completion & Approval Berm 15-20 0 days Wed 18-04-07 Wed 18-04-07 307,308,309
311 Earth Material 20-40.47 km 2 days Mon 23-04-07 Tue 24-04-07
312 Inspection & Checking of Earth 2 days Mon 23-04-07 Tue 24-04-07 315FS-5 days
313 Approval of Earth 0 days Tue 24-04-07 Tue 24-04-07 312
314 E/W Berms 20-25 (5 km) both side 6 days Thu 26-04-07 Wed 02-05-07
315 Setting out berms 2 days Thu 26-04-07 Fri 27-04-07 252
316 05 Laying of Earth / Maint of Earthern Shoulders 4 days Fri 27-04-07 Tue 01-05-07 315SS+1 day,313
317 Consolidation of earth 5 days Fri 27-04-07 Wed 02-05-07 316SS
318 Completion & Approval Berm 20-25 0 days Wed 02-05-07 Wed 02-05-07 315,316,317
319 E/W Berms 25-30 (5 km) both side 6 days Wed 09-05-07 Tue 15-05-07
320 Setting out berms 2 days Wed 09-05-07 Thu 10-05-07 268
321 05 Laying of Earth / Maint of Earthern Shoulders 4 days Thu 10-05-07 Mon 14-05-07 320SS+1 day
322 Consolidation of earth 5 days Thu 10-05-07 Tue 15-05-07 321SS
323 Completion & Approval Berm 25-30 0 days Tue 15-05-07 Tue 15-05-07 320,321,322
324 E/W Berms 30-35 (5 km) both side 6 days Mon 21-05-07 Sat 26-05-07
325 Setting out berms 2 days Mon 21-05-07 Tue 22-05-07 277
326 05 Laying of Earth / Maint of Earthern Shoulders 4 days Tue 22-05-07 Fri 25-05-07 325SS+1 day
327 Consolidation of earth 5 days Tue 22-05-07 Sat 26-05-07 326SS
328 Completion & Approval Berm 30-35 0 days Sat 26-05-07 Sat 26-05-07 325,326,327
329 E/W Berms 35-40.47 (5.47 km) both side 7 days Fri 25-05-07 Fri 01-06-07
330 Setting out berms 2 days Fri 25-05-07 Sat 26-05-07 286,55
331 05 Laying of Earth / Maint of Earthern Shoulders 5 days Sat 26-05-07 Thu 31-05-07 330SS+1 day
332 Consolidation of earth 6 days Sat 26-05-07 Fri 01-06-07 331SS
333 Completion & Approval Berm 35-40.47 0 days Fri 01-06-07 Fri 01-06-07 330,331,332
334 Road Furniture 161 days Sat 25-11-06 Mon 04-06-07
335 KM Stone 40 Nos 121 days Tue 02-01-07 Wed 23-05-07
19-03 30-03
19-03 30-03
19-03 29-03
19-03 29-03
19-03 29-03
30-03 30-03
30-03 30-03
19-03 30-03
30-03 Completion & Approval BC 10-15
29-03 Approval to start work in this reach
31-03 11-04
31-03 11-04
31-03 11-04
31-03 11-04
31-03 11-04
31-03 11-04
11-04 Completion & Approval BC 15-20
10-04 Approval to start work in this reach
13-04 25-04
13-04 25-04
13-04 24-04
13-04 24-04
13-04 24-04
24-04 24-04
25-04 25-04
13-04 25-04
25-04 Completion & Approval BC 20-25
20-04 21-04
21-04 Approval of Material
20-04 21-04
23-04 Approval of Job Mix
24-04 Approval to start work in this reach
26-04 08-05
26-04 08-05
26-04 07-05
26-04 07-05
26-04 07-05
08-05 08-05
08-05 08-05
26-04 08-05
08-05 Completion & Approval BC 25-30
07-05 Approval to start work in this reach
09-05 19-05
09-05 19-05
09-05 19-05
09-05 19-05
09-05 19-05
09-05 19-05
19-05 Completion & Approval BC 30-35
18-05 Approval to start work in this reach
21-05 24-05
21-05 24-05
21-05 24-05
21-05 24-05
21-05 24-05
21-05 24-05
24-05 Completion & Approval BC 35-37
01-03 02-03
02-03 Approval of Earth
07-03 08-03
08-03 12-03
08-03 13-03
13-03 Completion & Approval Berm 0-5
19-03 20-03
20-03 23-03
20-03 24-03
24-03 Completion & Approval Berm 5-10
31-03 02-04
02-04 05-04
02-04 06-04
06-04 Completion & Approval Berm 10-15
12-04 13-04
13-04 17-04
13-04 18-04
18-04 Completion & Approval Berm 15-20
23-04 24-04
24-04 Approval of Earth
26-04 27-04
27-04 01-05
27-04 02-05
02-05 Completion & Approval Berm 20-25
09-05 10-05
10-05 14-05
10-05 15-05
15-05 Completion & Approval Berm 25-30
21-05 22-05
22-05 25-05
22-05 26-05
26-05 Completion & Approval Berm 30-35
25-05 26-05
26-05 31-05
26-05 01-06
01-06 Completion & Approval Berm 35-40.47
30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28November 2006 December 2006 January 2007 February 2007 March 2007 April 2007 May 2007 June 2007 July 2007 August 2007 September 2007
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Gurdaspur Sri Hargobindpur Road
Page 3
Project: Gurdaspur Sri Hargobindpur RDate: Mon 14-09-15
![Page 4: work program](https://reader035.vdocuments.us/reader035/viewer/2022080222/563db956550346aa9a9c5bac/html5/thumbnails/4.jpg)
ID ItemNo.TND(GSH
Task Name Duration Start Finish Predecessors
336 Casting of KM Stone 4 days Tue 02-01-07 Fri 05-01-07 5SS,346
337 Curing of KM Stones 30 days Wed 03-01-07 Wed 07-02-07 336FS-3 days
338 Checking & Approval of KM Stones 0 days Tue 06-02-07 Tue 06-02-07 337FS-2 days
339 09 Fixing of KM Stone 7 days Wed 16-05-07 Wed 23-05-07 323,310,318,305,3
340 200 m Stone 162 Nos 120 days Sat 06-01-07 Sat 26-05-07
341 Casting of Stone 5 days Sat 06-01-07 Thu 11-01-07 5SS,346,336
342 Curing of Stones 30 days Mon 08-01-07 Mon 12-02-07 341FS-4 days
343 Checking & Approval of 200 m Stones 0 days Sat 10-02-07 Sat 10-02-07 342FS-2 days
344 10 Fixing of 200 m Stone 10 days Wed 16-05-07 Sat 26-05-07 323,310,318,305,3
345 Boundary Pillers 404 Nos 70 days Sat 25-11-06 Sat 17-02-07
346 Casting of Pillers 30 days Sat 25-11-06 Sat 30-12-06 5SS
347 Curing of Pillers 30 days Tue 28-11-06 Wed 03-01-07 346FS-28 days
348 Checking & Approval of Boundary Pillers 0 days Tue 02-01-07 Tue 02-01-07 347FS-2 days
349 11 Fixing of Boundary Pillers 40 days Tue 02-01-07 Sat 17-02-07 348
350 Retro Reflective Sign Boards (1138 Nos) 161 days Sat 25-11-06 Mon 04-06-07
351 Fabrication of Sign Boards 30 days Sat 25-11-06 Sat 30-12-06 5SS
352 Inspection of Fabricated Boards before transportation 0 days Sat 30-12-06 Sat 30-12-06 351
353 Transportation to site store 2 days Wed 03-01-07 Thu 04-01-07 352FS+1 day
354 Approval for fixing of Boards 0 days Thu 04-01-07 Thu 04-01-07 353
355 Shifting & Fixing of sign boards at site 7 days Mon 28-05-07 Mon 04-06-07
356 08.a Cautionary / Warning Signages 7 days Mon 28-05-07 Mon 04-06-07 344,354
357 08.b Informatory Signages 2 days Mon 28-05-07 Tue 29-05-07 344,354
358 08.c Place Identification Signages 3 days Mon 28-05-07 Wed 30-05-07 344,354
359 08.d Destination Sign Boards 3 days Mon 28-05-07 Wed 30-05-07 344,354
360 08.e Village Direction Sign Boards 7 days Mon 28-05-07 Mon 04-06-07 344,354
361 08.f Hazard marker boards 7 days Mon 28-05-07 Mon 04-06-07 344,354
362 08.g Delinators 7 days Mon 28-05-07 Mon 04-06-07 344,354
363 Overhead Gantry Boards (2 Nos) 19 days Sat 25-11-06 Sat 16-12-06
364 Fabrication of Boards 10 days Sat 25-11-06 Wed 06-12-06 5SS
365 Inspection of Fabricated Boards before transportation 0 days Wed 06-12-06 Wed 06-12-06 364
366 Transportation to site store 1 day Fri 08-12-06 Fri 08-12-06 365FS+1 day
367 Approval for fixing of Boards 0 days Fri 08-12-06 Fri 08-12-06 366
368 08.h Shifting & Fixing of Gantry OH boards at site 7 days Sat 09-12-06 Sat 16-12-06 367
369 Maintenance Culverts / Minor Bridges 127 days Fri 17-11-06 Tue 17-04-07
370 Submission of Safety Plan for Culvert works 4 days Fri 17-11-06 Tue 21-11-06 5SS-7 days
371 Approval of Culverts Safety Plan 0 days Tue 21-11-06 Tue 21-11-06 370
372 Culvert 1-26 (0-10 km) 26 Nos. 21 days Sat 25-11-06 Tue 19-12-06
373 Clearing of vegetation 5 days Sat 25-11-06 Thu 30-11-06 5SS,371
374 Repair to Parapet 20 days Sat 25-11-06 Tue 19-12-06
375 Inspection at site & Clearance to start repair 0 days Sat 25-11-06 Sat 25-11-06 373SS+1 day
376 07.a Brick Work 10 days Mon 27-11-06 Thu 07-12-06 375
377 07.b Plastering / Pointing 15 days Thu 30-11-06 Sat 16-12-06 376SS+3 days
378 07.c Painting Synthetic Enamel 2 days Mon 18-12-06 Tue 19-12-06 377
379 Completion & Approval Culverts Repair 1-26 0 days Tue 19-12-06 Tue 19-12-06 373,376,378
380 Culvert 27-45 (10-20 km) 19 Nos. 16 days Wed 20-12-06 Tue 09-01-07
381 Clearing of vegetation 4 days Wed 20-12-06 Sat 23-12-06 379
382 Repair to Parapet 15 days Wed 20-12-06 Tue 09-01-07
383 Inspection at site & Clearance to start repair 0 days Wed 20-12-06 Wed 20-12-06 381SS+1 day
384 07.a Brick Work 8 days Thu 21-12-06 Sat 30-12-06 383
385 07.b Plastering / Pointing 10 days Tue 26-12-06 Sat 06-01-07 384SS+3 days
386 07.c Painting Synthetic Enamel 2 days Mon 08-01-07 Tue 09-01-07 385
387 Completion & Approval Culverts Repair 27-45 0 days Tue 09-01-07 Tue 09-01-07 381,384,386
388 Culvert 46-70 (20-30 km) 25 Nos. 63 days Wed 10-01-07 Sat 24-03-07
389 Clearing of vegetation 5 days Wed 10-01-07 Mon 15-01-07 387
390 Repair to Parapet 20 days Thu 01-03-07 Sat 24-03-07
391 Inspection at site & Clearance to start repair 0 days Thu 01-03-07 Thu 01-03-07 288SS+1 day
392 07.a Brick Work 10 days Fri 02-03-07 Tue 13-03-07 391
393 07.b Plastering / Pointing 15 days Tue 06-03-07 Thu 22-03-07 392SS+3 days
394 07.c Painting Synthetic Enamel 2 days Fri 23-03-07 Sat 24-03-07 393
395 Completion & Approval Culverts Repair 46-70 0 days Sat 24-03-07 Sat 24-03-07 389,392,394
396 Culvert 71-97 (30-40.47 km) 27 Nos. 20 days Mon 26-03-07 Tue 17-04-07
397 Clearing of vegetation 5 days Mon 26-03-07 Fri 30-03-07 395
398 Repair to Parapet 19 days Mon 26-03-07 Tue 17-04-07
399 Inspection at site & Clearance to start repair 0 days Mon 26-03-07 Mon 26-03-07 397SS+1 day
400 07.a Brick Work 10 days Tue 27-03-07 Fri 06-04-07 399
401 07.b Plastering / Pointing 15 days Fri 30-03-07 Mon 16-04-07 400SS+3 days
402 07.c Painting Synthetic Enamel 1 day Tue 17-04-07 Tue 17-04-07 401
403 Completion & Approval Culverts Repair 71-97 0 days Tue 17-04-07 Tue 17-04-07 397,400,402
404 Painting & Lettering 39 days Thu 17-05-07 Sat 30-06-07
405 Sample Preparations 7 days Thu 17-05-07 Thu 24-05-07 403FF-2 days,339
406 Approval of Sample & to start work 0 days Thu 24-05-07 Thu 24-05-07 405
407 Painting & Lettering on KM Stone, m Stone, Culverts, etc 30 days Mon 28-05-07 Sat 30-06-07 412SS,339,344,39
408 Road Marking with thermoplastic paint 56 days Fri 27-04-07 Sat 30-06-07
409 Sample Preparations of all types of Road Markings 7 days Fri 27-04-07 Fri 04-05-07 268FS-10 days
410 Approval of Sample & to start work 0 days Fri 04-05-07 Fri 04-05-07 409
411 Traffic Management, Day Night Signages, etc 46 days Wed 09-05-07 Sat 30-06-07
412 06.a Centre Line Marking (Dashed) 35 days Wed 09-05-07 Mon 18-06-07 268,410
413 06.b Centre Line Marking (Solid) 15 days Wed 09-05-07 Fri 25-05-07 412SS
414 06.c Zebra Crossings (in front of Schools) 12 days Mon 18-06-07 Sat 30-06-07 412FS-1 day,413
415 06.d Zebra Crossings (at Bus Stops) 12 days Mon 18-06-07 Sat 30-06-07 414SS
416 Completion Stages 125 days Fri 16-02-07 Thu 12-07-07
417 SDBC 0 days Fri 16-02-07 Fri 16-02-07 98
418 SAM 0 days Fri 04-05-07 Fri 04-05-07 192
419 BC 0 days Thu 24-05-07 Thu 24-05-07 286
420 E/W Berms 0 days Fri 01-06-07 Fri 01-06-07 333,328,295,300,3
421 Road Furniture 0 days Mon 04-06-07 Mon 04-06-07 339,344,349,368,3
422 Culverts 0 days Tue 17-04-07 Tue 17-04-07 403
423 Road Marking, Painting & Lettering, etc 0 days Sat 30-06-07 Sat 30-06-07 407,414,415
424 Inspection & Preparing Check List of Defects, Modifications, etc
5 days Tue 05-06-07 Sat 09-06-07 421
425 Defects Removal & Modifications, etc 10 days Mon 11-06-07 Thu 21-06-07 424
426 Final Inspection Inspection of all works 5 days Fri 22-06-07 Wed 27-06-07 425
427 Accidental Defects removal 10 days Mon 02-07-07 Thu 12-07-07 423,421,426
428 Completion of Work 0 days Thu 12-07-07 Thu 12-07-07 417,418,419,420,4
429 Approval for Completion of Work 0 days Thu 12-07-07 Thu 12-07-07 428
02-01 05-01
03-01 07-02
06-02 Checking & Approval of KM Stones
16-05 23-05
06-01 11-01
08-01 12-02
10-02 Checking & Approval of 200 m Stones
16-05 26-05
25-11 30-12
28-11 03-01
02-01 Checking & Approval of Boundary Pillers
02-01 17-02
25-11 30-12
30-12 Inspection of Fabricated Boards before transportation
03-01 04-01
04-01 Approval for fixing of Boards
28-05 04-06
28-05 29-05
28-05 30-05
28-05 30-05
28-05 04-06
28-05 04-06
28-05 04-06
25-11 06-12
06-12 Inspection of Fabricated Boards before transportation
08-12 08-12
08-12 Approval for fixing of Boards
09-12 16-12
17-11 21-11
21-11 Approval of Culverts Safety Plan
25-11 30-11
25-11 Inspection at site & Clearance to start repair
27-11 07-12
30-11 16-12
18-12 19-12
19-12 Completion & Approval Culverts Repair 1-26
20-12 23-12
20-12 Inspection at site & Clearance to start repair
21-12 30-12
26-12 06-01
08-01 09-01
09-01 Completion & Approval Culverts Repair 27-45
10-01 15-01
01-03 Inspection at site & Clearance to start repair
02-03 13-03
06-03 22-03
23-03 24-03
24-03 Completion & Approval Culverts Repair 46-70
26-03 30-03
26-03 Inspection at site & Clearance to start repair
27-03 06-04
30-03 16-04
17-04 17-04
17-04 Completion & Approval Culverts Repair 71-97
17-05 24-05
24-05 Approval of Sample & to start work
28-05 30-06
27-04 04-05
04-05 Approval of Sample & to start work
09-05 30-06
09-05 18-06
09-05 25-05
18-06 30-06
18-06 30-06
16-02 SDBC
04-05 SAM
24-05 BC
01-06 E/W Berms
04-06 Road Furniture
17-04 Culverts
30-06 Road Marking, Painting & Lettering, etc
05-06 09-06
11-06 21-06
22-06 27-06
02-07 12-07
12-07 Completion of Work
12-07 Approval for Completion of Work
30 02 05 08 11 14 17 20 23 26 29 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28 01 04 07 10 13 16 19 22 25 28 31 03 06 09 12 15 18 21 24 27 30 03 06 09 12 15 18 21 24 27 30 02 05 08 11 14 17 20 23 26 29 01 04 07 10 13 16 19 22 25 28November 2006 December 2006 January 2007 February 2007 March 2007 April 2007 May 2007 June 2007 July 2007 August 2007 September 2007
Task
Critical Task
Milestone
Summary
Rolled Up Task
Rolled Up Critical Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Milestone
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Progress
Deadline
Gurdaspur Sri Hargobindpur Road
Page 4
Project: Gurdaspur Sri Hargobindpur RDate: Mon 14-09-15