wk7.1 project financing evaluation ptii

37
PROJECT FINANCING & EVALUATION PTII BAA3032:Project Management in Construction SEM II 1011

Upload: mohd-asmawi

Post on 23-Dec-2015

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: WK7.1 Project Financing Evaluation PtII

PROJECT FINANCING & EVALUATION PTII

BAA3032:Project Management in Construction

SEM II 1011

Page 2: WK7.1 Project Financing Evaluation PtII

outcomes

The end of this class, students are able to: Describe the contract cash flow and its

elements Describe the construction project cost and

its elements Develop the S-Curve Calculate the contract cash flow

2

FKASA@SEMII1011ZZ

Page 3: WK7.1 Project Financing Evaluation PtII

1. Monitor & Controlling

FKASA@SEMII1011ZZ

3

5 phases in project management

Feasibility Design & Planning

Development Closeout Operation

•Project Evaluation•Project Finance

Today lecture

Page 4: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

4

Contract Cash Flow At the project level, a project’s cash flow is

the difference between the project’s expense and income.

At the construction company level, the difference between company’s total expense and its total income over a period of time is the company’s cash flow

Cash flow = Cash in – Cash out = Income - Expense

Page 5: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

5

Contract Cash Flow Forecasting cash flow is necessary for a

construction company for the following reasons: To ensure that sufficient cash is available to meet

the demands. It shows the contractor, the maximum amount of

cash required and when it will be required It provides a reliable indicator to lending institutions

that loans made can be repaid according to an agreed program

It ensures that cash resources are fully utilized to the benefit of the owner and investors in the company

Page 6: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

6

Contract Cash Flow The three main ingredients in determination of

cash flow are: Expenses (cash out) which represents the

aggregate of the payments which the contractor will make over a period of time for all resources used in the project such as labor, equipment, material, and subcontractors

Income (cash in) that represents the receipts a contractor will receive over a period of time for the work he/she has completed

Timing of payments: in cash flow analysis, we are interested in the timing of payments related to the work done by the contractor

Page 7: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

7

Construction Project Cost In preparing the cash flow for a project, it

is necessary to compute the costs that must be expended in executing the works using activities durations and their direct and indirect costs

The principal components of a contractor's costs and expenses result from the use of labors, materials, equipment, and subcontractors

Page 8: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

8

Construction Project Cost The costs that spent on a specific activity

or project can be classified as; Fixed cost: costs that spent once at specific

point of time (e.g., the cost of purchasing equipment, etc.)

Time-related cost: costs spent along the activity duration (e.g., labor wages, equipment rental costs, etc.)

Quantity-proportional cost: costs changes with the quantities (e.g., material cost)

Page 9: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

9

Construction Project Cost – Project Direct Cost The costs and expenses that are incurred

for a specific activity are termed direct costs

These costs are estimates based on detailed analysis of contract activities, the site conditions, resources productivity data, and the method of construction being used for each activity

Page 10: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

10

Construction Project Cost – Project Indirect Cost Other costs such as the overhead costs are

termed indirect costs The indirect costs always classified to:

project (site) overhead General (head-office) overhead

Page 11: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

11

Construction Project Cost – Project Indirect Cost Project overhead are site-related costs and

includes the cost of items that can not be directly charged to a specific work element and it can be a fixed or time-related costs

the costs of site utilities, supervisors, housing and feeding of project staff, parking facilities, offices, workshops, stores, and first aid facility

overhead costs are estimated to be between 5% - 15% of project total direct cost

Page 12: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

12

Construction Project Cost – Project Indirect Cost The costs that can not be directly attributed

a specific project called general overhead These are the costs that used to support

the overall company activities, they represent the cost of the head-office expenses, managers, directors, design engineers, schedulers, etc

the general overhead for a specific contract can be estimated to be between 2% - 5% of the contract direct cost

Page 13: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

13

Construction Project Cost Having defined the direct costs, indirect

costs, then the project total cost equals the sum of both direct and indirect costs

When studying cash flow, it is very important to determine the actual dates when the expenditures (cost) will take place

When the project started, the expenditures will renamed as the expenses

Page 14: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

14

Construction Project Cost As shown in the figure, they are the same

except the expenses are shifted (delayed) the costs

Page 15: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

15

The S-Curve The curve represents the cumulative

expenditures of a project direct and indirect costs over time is called the S-curve as it take the S-shape

In many contracts, the owner requires the contractor to provide an S-curve of his estimated progress and costs across the life of the project

This S-shaped of the curve results because early in the project, activities are mobilizing and the expenditure curve is relatively flat

Page 16: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

16

The S-Curve As many other activities come on-line, the

level of expenditures increases and the curve has a steeper middle section

Toward the end of a project, activities are winding down and expenditures flatten again

The S-Curve is one of the most commonly techniques to control the project costs

Page 17: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

17

The S-Curve

Page 18: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

18

Developing the S-Curve An S-curve for a project can be developed

using the following steps: Constructing a simple bar chart for all the tasks

of the project Assigning costs to each task using task

duration Plotting the cumulative amounts of

expenditures versus time by smoothly connecting the projected amounts of expenditures over time

Page 19: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

19

Developing the S-Curve Refer to table 1, draw the S-curve of the

total cost of the project

Page 20: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

20

Activities Date Duration Direct Cost Indirect Cost Total Cost

A 1 July 4 2,000.00 2,000.00 4,000.00

B 1 July 6 9,000.00 3,000.00 12,000.00

C 1 July 2 3,000.00 1,000.00 4,000.00

D 5 July 8 12,000.00 4,000.00 16,000.00

E 13 July 4 18,000.00 2,000.00 20,000.00

F 7 July 10 15,000.00 5,000.00 20,000.00

G 7 July 16 8,000.00 8,000.00 16,000.00

H 17 July 8 20,000.00 4,000.00 24,000.00

I 25 July 6 9,000.00 3,000.00 12,000.00

J 3 July 6 9,000.00 3,000.00 12,000.00

K 23 July 10 5,000.00 5,000.00 10,000.00

Page 21: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

21

Developing the S-Curve The Data & Data 2

Page 22: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

22

Calculating Contract Cash Flow If we plotted the contract expense and income curves

against each other, then the cash flow is the difference between the points of both curves

Having determined the contract expenses and income, it is possible to calculate the contract cash flow

The hatched area represents the difference between the contractor’s expense and income curves, i.e., the amount that the contractor will need to finance (loan from bank)

The larger this area, the more money to be financed and the more interest

charges are expected to cost the contractor

Page 23: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

23

Calculating Contract Cash Flow

Page 24: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

24

Calculating Contract Cash Flow The contractor may request an advanced or

mobilization payment from the owner. This shifts the position of the income profile

so that no overdraft occurs

Page 25: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

25

Calculating Contract Cash Flow In case of less number of payments (two or

three payments) along the contract period, this will lead to increase the overdraft

Page 26: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

26

Calculating Contract Cash Flow

Page 27: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

27

Calculating Contract Cash Flow

Page 28: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

28

Calculating Contract Cash Flow when calculating the cash flow the factors

that affect the project finance (cash flow) should considered Contractor method of paying his/her expenses. Contractor’s markup (mainly the profit margin) Retention amount and its payback time Time of payment delay by owner Advanced or mobilization payment

Page 29: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

29

Calculating Contract Cash Flow The cash flow calculations are made as

described in the following steps: Perform project schedule and determine project

and activities timing Draw bar chart based on early or late timings Calculate the cost per time period Calculate the cumulative cost Calculate the cumulative revenue (Cost + markup) Adjust the revenue based on the retention and

delay of owner payment to determine the Income Calculate the cash flow (cash flow = income –

expense) at the contract different times

Page 30: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

30

Calculating Contract Cash Flow Table 2, show the data for your next

project. Analyze the financial implication for that project. (Retention fund 5%, will be refund after project completed and 10% profit) - solutionActivities Start Durations Cost

A January 2 months RM40,000

B February 3 months RM30,000

C April 2 months RM60,000

D April 1 month RM40,000

E April 2 months RM40,000

F June 1 month RM30,000

Page 31: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

31

Minimizing Contractor Negative Cash Flow Among the procedures the contractor may

follow to minimize negative cash flow are: Adjustment of work schedule to late start

timing in order to delay payments. In this case, the contractor should be aware that in this case in delay might happen will affect the project completion time and may subject him/her to liquidated damages

Reduction of delays in receiving revenues Asking for advanced or mobilization payment

Page 32: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

32

Minimizing Contractor Negative Cash Flow Among the procedures the contractor may

follow to minimize negative cash flow are: Achievement of maximum production in the

field to increase the monthly payments Increasing the mark up and reducing the

retention Adjust the timing of delivery of large material

orders to be with the submittal of the monthly invoice

Delay in paying labor wages, equipment rentals, material suppliers and subcontractors

Page 33: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

33

Calculating Contract Cash Flow Exercise:

Your project director instruct you to prepare graphs of cumulative cost and monies received to date against time for activities, in order that he/she may have a clearer picture of financial implications of this contract. From these graphs calculate the net profit if interest is charged at 8% per annum (to financing this project, your company will apply loan from bank). The gross profit margin is 10% of contract value (cost + profit) and retention is 5% up to a maximum limit of RM15,000. Measurement is made monthly with payment delay of one month. Half of retention is paid on practical completion and the remaining half six month later. Determine the maximum amount of cash that your company needs to execute this contract and when does he/she require this amount?

Page 34: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

34

Calculating Contract Cash Flow Exercise:

Your project director instruct you to prepare graphs of cumulative cost and monies received to date against time for activities, in order that he/she may have a clearer picture of financial implications of this contract. The retention is 5%. Measurement is made monthly with payment delay of one month. Half of retention is paid on practical completion and the remaining half six month later. Develop the Gantt chart, Planned cost S-curve and Payment S-curve for the project.

Page 35: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

35

Calculating Contract Cash Flow Exercise: DataActivities Start Duration

(months)Contract Value

(RM)

A- Excavation 1st January 2 45,000.00

B- Concrete Base 1st February 3 60,000.00

C- Erect Frames 1st April 1 ½ 90,000.00

D- Concrete Flr Slab 1st April 1 75,000.00

E- Fix Cladding 15th April 1 ½ 30,000.00

F- Install Plant 1st June 1 100,000.00

Page 36: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

36

Calculating Contract Cash Flow Exercise: DataActivities Start Duration

(months)Contract Value

(RM)

A- Excavation 1st January 2 45,000.00

B- Concrete Base 1st February 3 60,000.00

C- Erect Frames 1st April 1 ½ 90,000.00

D- Concrete Flr Slab 1st April 1 75,000.00

E- Fix Cladding 15th April 1 ½ 30,000.00

F- Install Plant 1st June 1 100,000.00

Answer: a) Max. amount/capital: RM189,250 at month of May (5)b) Interest Charges (8% per annum) = RM31,914.20c) Net Profit = RM8,085.83

Page 37: WK7.1 Project Financing Evaluation PtII

2. Construction Financing

FKASA@SEMII1011ZZ

37