WisDOT Bureau of Technical SevicesSpring 2014 QMP Training

Base Compaction SPV’s

and Project Design

Guidance

Outline

2

How’d we get here

Project selection/design guidance

SPV highlights

Still to come

How’d We Get Here?

3

2013 pilot projects IH-43 Ozaukee Co. USH 63 St. Croix Co. (x2) STH 179 Crawford Co. STH 29 Brown Co. STH 153 Marathon Co.

Spec revisions 1 ¼ – Inch BAD Mill/Pulverize and Relay

STH 47 Vilas Co. USH 51 Lincoln Co. STH 73 Wood Co. STH 29 Marathon Co. Fishel Road Forest Co.

HMA surfaced mainline AND QMP Subgrade and/or Subgrade improvement AND 30,000 tons+

Between 2010 and 2013 17% of all let projects 31% of HMA projects 54% of HMA projects with 1-1/4” base agg.

4

Project Selection – Base Agg. Dense

Minimum Mill and Relay or Pulverize and Relay Quantity of 40,000 SY

Between 2010 and 2013 3% of all let projects 43% of pulverize and relay projects 56% of mill and relay

5

Project Selection - Mill/Pulv. & Relay

QC plan IA requirementsPersonnel requirements93% of target densityTest frequency“Failing” test/corrective

actionMeasurement and

payment

6

Special Provision – Highlights

Organizational chart Communication process Source locations list (1 ¼” spec only) Stockpiling and hauling methods (1 ¼” spec only) Process control problem resolution process QC lab, sample, and documentation storage

locations Estimate of locations and calculated quantities to

be tested under this provision.

QC Plan Requirements

7

Personnel HTCP Nuclear Density Technician I Or ACT certified technician

IA According to the Department’s independent assurance

program

Misc Requirements

8

1 ¼ - Inch Base Aggregate Dense ≤20% Recycled Material

Modified Proctor Max Dry >20% Recycled Material

Mod. Proctor Max Wet Mod. Proctor Max Dry Control Strip

Mill/Pulverize and Relay Control Strip

Target Density Determination

9

1 ¼ - Inch Base Aggregate Dense Density – 1 per 1500 tons Gradation – 1 per 3000 tons Proctor – initial and then if trigger met

Mill/Pulverize and Relay Density – 1 per 3000 tons Proctor – initial and then if trigger met

CA – Optional Information Process control decisions Troubleshooting Limiting liability and/or corrective

action limits

Test Frequency – QC/CA

10

1 ¼ - Inch Base Aggregate Dense Gradation change > 10.0% Source change Recycle material blend change > 10.0% Density > 103% on two consecutive measurements If using control strips; thickness change > 2.0 inches

Mill/Pulverize and Relay Layer thickness change > 2.0 inches Density > 105% or <90.0%; AND outside of range of 10

avg control strip shots; on three consecutive measurements

QC/CA – Proctor Triggers

11

Density and gradations 30% of Contractor Frequency

Target densities; Same triggers as QC Control Strips

QV person must be present and verify sufficient compactive effort (including addition of water)

Will use same value as contractor

QV Frequencies

12

IA Highlights

13

Evaluate QV and QC sampling and testing

May include one or more of the following: Split sample testing Proficiency sample testing Witnessing sampling and testing Test equipment calibration checks Additional sampling and testing

<93.0%

Opt. Moisture

Deflection

<2.0 lb/ft3

No Deflection

<2.0 lb/ft3

Non-Opt. Moisture

Continue Compaction New %

Corrective Action

14

1 ¼ - Inch BAD; Tons

Mill/Pulverize and Relay; SY

Water; MGal

Measurement and Payment

15

Facilities Development Manual guidance – March 2014 Project selection guidance Water bid item

10 – 20 gallons per ton 1 ¼ - Inch BAD 3 – 6 gallons per SY Mill/Pulverize and Relay

Revisions – Fall 2014

Conversion to STSP – Spring 2015

16

Still To Come

QuestionsNow or On Projects

[email protected]

(608)220-0690

17

ftp://ftp.dot.wi.gov/dtsd/bts/pavement/Base_Comp_Docs