24
WIMES 5.01 Page 52 APPENDIX C1 - DATA SHEETS RAW WATER INTAKE SCREENS PROJECT TITLE (P) DOCUMENT REFERENCE (P) PROJECT NUMBER (P) REVISION (P) PROJECT LOCATION (P) DATE (P) SCREEN SUPPLIER (P/S) REFERENCE DRAWINGS INCLUDED (Y/N) (P) TAG NO/ASSET CODE (P) * - Indicates Purchaser’s default requirement 2.0 GENERAL 2.3 General 1 Screen Type () (P/S) Grab screen Bandscreen Drum screen Disc screen Hand raked bar screen CC raked bar screen Straight bar screen (front raked) Straight bar screen (back raked) Slot screen Passive wedge wire cylinder screen Spillway screen Wedge wire flat panel screen Other (specify) 2 Screen to be Eel/Fish Friendly (Y/N) (P) 3 No. of Identical Screens Reqd/Provided (P/S) 3.0 OPERATING ENVIRONMENT & SITE DETAILS 1 Operating Environment (P) Site/Screen Location () Inland Coastal Inside Outside Other (specify) ISSUE 3 JULY 2017

Upload: vunga

Post on 27-Mar-2018

220 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 52

APPENDIX C1 - DATA SHEETS

RAW WATER INTAKE SCREENS

PROJECT TITLE (P) DOCUMENT REFERENCE (P)PROJECT NUMBER (P) REVISION (P)PROJECT LOCATION (P) DATE (P)SCREEN SUPPLIER (P/S) REFERENCE DRAWINGS

INCLUDED (Y/N) (P)TAG NO/ASSET CODE (P)

* - Indicates Purchaser’s default requirement

2.0 GENERAL

2.3 General

1 Screen Type () (P/S)Grab screenBandscreenDrum screenDisc screenHand raked bar screenCC raked bar screenStraight bar screen (front raked)Straight bar screen (back raked)Slot screenPassive wedge wire cylinder screenSpillway screenWedge wire flat panel screenOther (specify)

2 Screen to be Eel/Fish Friendly (Y/N) (P)

3 No. of Identical Screens Reqd/Provided (P/S)

3.0 OPERATING ENVIRONMENT & SITE DETAILS

1 Operating Environment (P)Site/Screen Location ()InlandCoastalInsideOutsideOther (specify)

EMC Environment ()1st environment – C11st environment – C22nd environment – C3

2 Position in Process Chain & Details of Upstream and Downstream Processes (P)

3 Special Environmental Hazards (P)

4 References For Further Information (P)

4.0 PROCESS INFORMATION

1a Influent Source () (P)RuralUrbanOther (specify)

1a River Classification/Details (P)

1b Flow Rate (l/s) (P)MinimumMaximum

1b Approach Velocity (m/s) (P)MinimumMaximum

1c Fish/Eel Friendly Screen Data (P)Influent flow directionMaximum influent flow velocity (m/s)

1d Average Screenings Loading (P)

1e Screenings Peaking Factor (P)

ISSUE 3 JULY 2017

Page 2: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 53

2 Unusual Influent/Screenings Properties (P)

3 Water Levels (m) (P/S)Upstream (max)Downstream (min/max)

5.0 PERFORMANCE SPECIFICATION

5.1 General

1 Service Life (years) (P)2 Mode of Operation () (P)

DutyDuty/assistDuty/standby

2 Utilisation (% or hrs/day) (P)

3 Ambient Air Temp/RH (-10 to 40°C/< 95%*) (P)

5.2 Process Performance

5.2.1 General

2 Maximum Head Differential (mm) (P/S)

5.2.2 Hydraulic Performance

1 Tank/Channel Dimensions (m) (P)Width/depth

2 Blinding Factor (P/S)3 Influent Velocity Through Screen Curtain

Apertures at Maximum Flow Rate (m/s) (P/S)Maximum Allowable (1.2 m/s*) (P)Design (S)

4 Working Head Loss at Maximum Flow Rate (mm) (P/S)Maximum Allowable (P)Design (S)

5.3 Noise

1 Noise Levels (dB (A) at 1 m) (P/S)Maximum (< 80*) (P)Expected (S)

2 Additional Noise Requirements (P)

5.4 Life Cycle Costs

5.4.1 Energy Consumption

1 Energy Consumption(kWh/hr) (S)

5.4.2 Washwater Consumption

1 Washwater Consumption (l/hr) (S)

5.4.3 Service Lives and Costs of Components

1 Expected Service Lives of ComponentsComponent (specify) (P) Life (x 103 hrs) (S)

2 Costs of Components (£)/Time Required to Replace Components (hrs) (S)Component (specify) Cost Time

6.0 DESIGN SPECIFICATION

6.1 General (All Screen Types)

6.1.2 Weights and Lifting Arrangements

1 Weights of Major Components (S)Component (specify) Weight (kg)

1 Heaviest maintenance lift (kg)(S)

1 Heaviest erection lift (kg) (S)

6.1.5 Screen Curtain Support Structure

2 Material(s) (P/S)

ISSUE 3 JULY 2017

Page 3: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 54

6.1.6 Drive Systems

6.1.6.2 Motors/Gearboxes (If Required/Provided)

Refer to Appendix C2.

6.1.6.3 Hydraulic Drives (If Required/Provided)

1 Hydraulic Drive to Operate (P/S)

2 Rating (S)Motor rating (kW)Maximum operating pressure (bar)

3 Hydraulic Power Pack (P/S)b Control panel spec.

(WIMES 3.04*)c Motor specification

(WIMES 3.03*)d Coating specification

(WIMES 4.01*)5 Hydraulic System (P/S)a Oil reservoir capacity (l)b Maximum oil pump

delivery (l/min)7 Further Measures Required to Reduce

Impacts of Oil Spillage (P)

8 Rigid Pipework Type () (P/S)SeamlessFully welded

8 Rigid Pipework Material () (P/S)Stainless steelCarbon steel

10 Type of Hydraulic Oil (P/S)

6.1.7 Bearings and Lubrication

6.1.7.2 Rolling Element Bearings

3 Requirements for Split Type Bearings (P)

6.1.7.3 Lubrication

1 Bearing Lubrication Philosophy () (P/S)Sealed for lifeManual re-greasingAutomatic re-greasing

5 Minimum Capacity/Life of Auto Grease Dispensers (cc/mths) (P/S)

6.1.8 Screen Curtain Cleaning

6.1.8.1 General

2 Method(s) of Screen Curtain Cleaning Required/Provided () (P/S)Spray bar systemDeluge troughOther (specify)

6.1.8.2 Spray Bar System (If Required/Provided)

1 Washwater Availability/ Requirements (P/S)Pressure and Flow RateSupply Pressure (bar)Flow rate (l/min)Type ()Final effluentScreened effluentPotable waterFiltration Level (Microns)

5 Spray Bar/Nozzle Material(s) (P/S)

6 Valve Type () (P/S)Full bore, ¼ turn, actuatedSolenoid

6.1.8.3 Deluge Trough (If Required/Provided)

1 Washwater Availability/ Requirements (P/S)Pressure and Flow RateSupply Pressure (bar)Flow rate (l/min)Type ()Final effluentScreened effluentPotable waterFiltration Level (Microns)

4 Trough and Pipework Material(s) (P/S)

5 Trough Cleaning System Required. (Y/N) (P)

6 Valve Type () (P/S)Full bore, ¼ turn, actuatedSolenoid

ISSUE 3 JULY 2017

Page 4: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 55

6.1.10 Information Plate

1 Additional Information Reqd. on Plate (P)

2 Duplicate Plate Required (Y/N) (P)

2 Location of Duplicate Plate (P)

6.1.11 Lagging and Trace Heating

2 Frost Protection Afforded Down to: (-10°C*) (P)

3 Reference for Particular Specification (P)

6.1.12 Control Panel and Associated Electrical Installation

1 Control Panel Required/ Provided (Y/N) (P/S)

2 Control Panel Specification () (P)WIMES 3.04*Supplier’s standardPurchaser’s standard

6.1.13 Maintainability

5 Mesh Viewing Panels Required (Y/N) (P)

6.1.14 Theft Prevention

1 Painting of Stainless Steel Components Required (Y/N) (P)

6.1.15 Installation Accessories

1 Toe Plate Required (Y/N) (P)

6.1.16 O & M Manuals

1 Reference for Particular Specification (P)

6.2 Grab Screens

6.2.1 General

2 Angle of Installation (P/S)Maximum allowable (P)Design (S)

6.2.2 Screen Curtain

1 Bar Material (P/S)

2 Aperture Size (mm) (P)5 Bar Cross-Sectional Shape () (P/S)

SquareRectangularTaperedOther (Specify)

6.2.3 Screen Curtain Cleaning

6.2.3.1 General

1 Type of Screen Curtain Cleaning System Required/Provided () (P/S)Traversing grab assembly with opening/closing jawsRake assembly

6.2.3.2 Systems Inc. Traversing Grab Assemblies with Opening/Closing Jaws (If Required/Provided)

Grab Assemblies

1 Number of Assemblies Required/Provided (P/S)

3 Grab Assembly Material(s) (P/S)

Overhead Monorail System

2 Monorail Material (P/S)

2 Type of Monorail Construction (P/S)

3 Support Structure Material (P/S)

3 Protective Coatings (P/S)

Spray Bar System (If Required/Provided)

1 Spray Bar Required/ Provided (Y/N) (P/S)

ISSUE 3 JULY 2017

Page 5: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 56

6.2.3.2 Systems Incorporating a Rake Assembly (If Required/Provided)

General

2 Base Unit to be Mounted on a Moving Carriage (Y/N) (P)

Rake Assembly

1 Rake Assembly Material(s) (P/S)

6.2.4 Screenings Discharge

1 Screenings Discharge Height (m) (P/S)

6.3 Bandscreens

6.3.1 General

1 Bandscreen Type () (P/S)In-to-out (single entry)Out-to-in (double entry)

6.3.2 Screen Curtain

1 Screen Element Material (P/S)

2 Aperture Size (mm) (P)

6.3.3 Screen Curtain Drive System

2 Drive Chain Type () (P/S)Conveyor chainRoller chain

3 Chain Material (P/S)

4 Drive Chain Breaking Load (kN) (S)

5 Maximum Linear Speed of Screen Curtain (m/s) (P)

6.3.4 Screen Curtain Cleaning

6.3.4.1 General

4 Hopper/Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

6.3.5 Screenings Discharge

1 Screenings Discharge Height (m) (P/S)

6.3.6 Screenings Transfer

1 Screenings to be Transferred to () (P/S)The water courseScreenings treatment equipmentA skip

2 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)Fall (° from horizontal)

2 Cross-Sectional Profile () (P/S)TrapezoidalU-sectionOther (specify)

3 Maximum Combined Screenings, Washwater and Launder Water Flow Rate (l/s) (P/S)

5 Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

6 Stub Pipe Material (P/S)

6 Stub Pipe NB (mm) (P/S)7 Type of Launder Water () (P/S)

Screened influentPotable water

7 Pump Hydraulic Performance (P/S)Head (m)Flow (l/s)

7 Standby Pump Required (Y*/N) (P/S)

8a High Water Level Sensor Required/Provided (Y*/N) (P/S)

8b Overflow Required/ Provided (Y*/N) (P/S)

ISSUE 3 JULY 2017

Page 6: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 57

6.3.7 Fish Recovery and Return System (FRRS) (If Required)

6.3.7.1 General

1 FRRS Required (Y/N) (P)3 FRRS Discharge Height

(m) (P/S)

6.3.7.2 Elevator Buckets

1 Number of Buckets Required/Provided (P/S)

2 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)

2 Cross-Sectional Profile () (P/S)TrapezoidalU-sectionOther (specify)

4 Bucket Material (Stainless Steel Number 1.4307 (AISI 304/304L)*) (P/S)

6.3.7.3 Launder Trough

1 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)Fall (° from horizontal)

1 Cross-Sectional Profiel() (P/S)TrapezoidalU-sectionOther (specify)

2 Maximum Launder Water Flow Rate (l/s) (P/S)

3 Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

5 Stub Pipe Material (P/S)

5 Stub Pipe NB (mm) (P/S)6 Type of Launder Water () (P/S)

Screened influentPotable water

6 Pump Hydraulic Performance (P/S)Head (m)Flow (l/s)

6 Standby Pump Required (Y*/N) (P/S)

6.4 Drum Screens

6.4.1 General

1 Screen Type () (P/S)In-to-out (single entry)In-to-out (double entry)Out-to-in

2 Max. Tolerance on Drum Concentricity (+ 3 mm on Radius*) (P/S)

3 Method of Sealing (P/S)

3 Seal Material (P/S)

6.4.2 Screen Curtain

2 Aperture Size (mm) (P)3 Panel Material (P/S)

3 Thickness (mm) (P/S)

6.4.3 Screen Curtain Drive System

3 Gear Material (P/S)

3 Pinion Material (P/S)

6.4.4 Screen Curtain Cleaning

6.4.4.1 General

4 Hopper/Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

6.4.5 Screenings Discharge

1 Screenings Discharge Height (m) (P/S)

ISSUE 3 JULY 2017

Page 7: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 58

6.4.6 Screenings Transfer

1 Screenings to be Transferred to () (P/S)The water courseScreenings treatment equipmentA skip

2 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)Fall (° from horizontal)

2 Cross-Sectional Profile () (P/S)TrapezoidalU-sectionOther (specify)

3 Maximum Combined Screenings, Washwater and Launder Water Flow Rate (l/s) (P/S)

4 Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

6 Stub Pipe Material (P/S)

6 Stub Pipe NB (mm) (P/S)7 Type of Launder Water () (P/S)

Screened influentPotable water

7 Pump Hydraulic Performance (P/S)Head (m)Flow (l/s)

7 Standby Pump Required (Y*/N) (P/S)

8a High Water Level Sensor Required/Provided (Y*/N) (P/S)

8b Overflow Required/ Provided (Y*/N) (P/S)

6.4.7 Fish Recovery and Return System (FRRS) (If Required)

6.4.7.1 General

1 FRRS Required (Y/N) (P)3 FRRS Discharge Height

(m) (P/S)

6.4.7.2 Elevator Buckets

1 Number of Buckets Required/Provided (P/S)

2 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)

2 Cross-Sectional Profile () (P/S)TrapezoidalU-sectionOther (specify)

4 Bucket Material (Stainless Steel Number 1.4307 (AISI 304/304L)*) (P/S)

6.4.7.3 Launder Trough

1 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)Fall (° from horizontal)

1 Cross-Sectional Profile () (P/S)TrapezoidalU-sectionOther (specify)

2 Maximum Launder Water Flow Rate (l/s) (P/S)

3 Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

5 Stub Pipe Material (P/S)

5 Stub Pipe NB (mm) (P/S)6 Type of Launder Water () (P/S)

Screened influentPotable water

6 Pump Hydraulic Performance (P/S)Head (m)Flow (l/s)

6 Standby Pump Required (Y*/N) (P/S)

ISSUE 3 JULY 2017

Page 8: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 59

6.5 Disc Screens

6.5.1 Screen

1 Shaft Material (P/S)

1 Disc Material (P/S)

1 Spacer Material (P/S)

2 Aperture Size (mm) (P)4 Comb Material (P/S)

6.5.2 Screen Drive System

2 Shaft Speed (rpm) (P/S)Maximum allowable (P)Design (S)

6.6 Raked Bar Screens

6.6.1 General

2 Angle of Installation (P/S)Maximum allowable (P)Design (S)

6.6.2 Screen Curtain

1 Screen Element (Bar) Material (P/S)

2 Aperture Size (mm) (P)5 Bar Cross-Sectional Shape () (P/S)

SquareRectangularTaperedOther (Specify)

6.6.3 Screen Curtain Cleaning (Mechanically Raked Screens)

6.6.3.1 General

3 Drive Chain Type () (P/S)Conveyor chainRoller chain

3 Drive Chain Breaking Load (kN) (S)

6.6.3.2 Rakes and Tines

2 No. of Rakes/Tines (P/S)3 Rake Material (P/S)

3 Tine Material (P/S)

6.6.3.4 Scraper Blade

1 Method of Returning Scraper Blade to Its Original Position (P/S)

2 Scraper Blade Material (P/S)

6.6.4 Screenings Discharge

6.6.4.1 General

1 Screenings Discharge Height (m) (P/S)

2 Discharge Chute Required (Y/N) (P)

6.6.5 Screenings Transfer

1 Screenings to be Transferred to () (P/S)The water courseScreenings treatment equipmentA skip

2 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)Fall (° from horizontal)

2 Cross-Sectional Shape () (P/S)TrapezoidalU-sectionOther (specify)

3 Maximum Combined Screenings, Washwater and Launder Water Flow Rate (l/s) (P/S)

4 Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

ISSUE 3 JULY 2017

Page 9: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 60

6 Stub Pipe Material (P/S)

6 Stub Pipe NB (mm) (P/S)7 Type of Launder Water () (P/S)

Screened influentPotable water

7 Pump Hydraulic Performance (P/S)Head (m)Flow (l/s)

7 Standby Pump Required (Y*/N) (P/S)

8a High Water Level Sensor Required/Provided (Y*/N) (P/S)

8b Overflow Required/ Provided (Y*/N) (P/S)

6.6.6 Additional Clauses for Continuous Chain Raked Bar Screens

6.6.6.2 Screen Curtain Cleaning - Rake and Chain Assembly Drive System

2 Method of Underwater Guidance of Rake and Chain Assembly (P/S)

6.6.7 Additional Clauses for Straight Bar Screens

6.6.7.2 Screen Curtain Cleaning - Rake and Chain Assembly Drive System

2 Type of Actuator Reqd/Provided () (P/S)HydraulicElectric

2 Number of Actuators Required/Provided (P/S)

4 Type of Limit/Proximity Switches Required/Provided (P/S)

6.7 Slot Screens

6.7.1 General

1 Angle of Installation (P/S)Maximum allowable (P)Design (S)

6.7.2 Screen Curtain

1 Screen Element Material (P/S)

2 Aperture Size (mm) (P)3 Method of Maintaining Gap () (P/S)

Intermediate spacersOther (specify)

6.7.3 Screen Curtain Drive System

2 Drive Chain Type () (P/S)Conveyor chainRoller chain

3 Chain Material (P/S)

4 Drive Chain Breaking Load (kN) (S)

5 Method of Underwater Guidance of Drive Chains () (P/S)Bottom bearing/sprocketStructural guide railOther (specify)

6.7.5 Screenings Discharge

6.7.5.1 General

1 Screenings Discharge Height (m) (P/S)

2 Discharge Chute Required (Y/N) (P)

6.7.6 Screenings Transfer

1 Screenings to be Transferred to () (P/S)The water courseScreenings treatment equipmentA skip

2 Principal Design Features (P/S)Width at base (mm)Width at top (mm)Depth (mm)Length (m)Fall (° from horizontal)

2 Cross-Sectional Shape () (P/S)TrapezoidalU-sectionOther (specify)

ISSUE 3 JULY 2017

Page 10: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 61

3 Maximum Combined Screenings, Washwater and Launder Water Flow Rate (l/s) (P/S)

4 Trough Material (Stainless Steel Number 1.4307 (AISI 304L)*) (P/S)

6 Stub Pipe Material (P/S)

6 Stub Pipe NB (mm) (P/S)7 Type of Launder Water () (P/S)

Screened influentPotable water

7 Pump Hydraulic Performance (P/S)Head (m)Flow (l/s)

7 Standby Pump Required (Y*/N) (P/S)

8a High Water Level Sensor Required/Provided (Y*/N) (P/S)

8b Overflow Required/ Provided (Y*/N) (P/S)

6.8 Static Screens

6.8.1 Passive Wedge Wire Cylinder (PWWC) Screens

6.8.1.2 Screen Curtain

1 Screen Curtain Material (P/S)

2 Aperture size (mm) (P/S)3 Wedge Wire Dimensions (mm) (S)

Profile wiresSupport rods

4 Screen Curtain Free Area (%) (S)

6.8.1.3 Backwash System (If Required/Provided)

1 Backwash System Required/Provided (Y/N) (P/S)

6.8.2 Spillway Screens

6.8.2.2 Screen

1 Screen Element Material (P/S)

2 Aperture size (mm) (P/S)3 Wedge Wire Dimensions (mm) (S)

Profile wiresSupport rods

4 Screen Free Area (%) (S)

6.8.2.3 Screenings Discharge

1 Screenings Discharge Height (m) (P/S)

6.8.3 Wedge Wire Flat Panel Screens

6.8.3.1 General

1 Direction of Flow Through Screen () (P/S)UpwardsDownwardsSideways (weir mounted)

6.8.3.2 Screen

1 Screen Element Material (P/S)

2 Aperture size (mm) (P/S)3 Wedge Wire Dimensions (mm) (S)

Profile wiresSupport rods

4 Screen Free Area (%) (S)

6.8.3.3 Screen Cleaning System

1 Rotating Spray Bar Required (Y/N) (P)

7.0 INSPECTION AND TESTING

7.1 Factory Acceptance Testing

1 Reference for Particular Specification (P)

7.2 Site Acceptance Testing

1 Reference for Particular Specification (P)

ISSUE 3 JULY 2017

Page 11: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 62

APPENDIX C2 – DRIVE SYSTEM DATA SHEET

(TO BE COMPLETED FOR EACH MOTOR/GEARBOX ASSEMBLY)

Drive No.:

1 Driven Equipment (P/S)

2 Type of Drive () (P/S)FixedTwo speedVariable

3 Method of Power Transmission from Drive System to Driven Assembly () (P/S)Close coupledChainBeltOther (specify)

4 Method of Mechanical Overload Protection for Drive System () (P/S)Current monitoringTorque limiting couplingOther (specify)

5 Local Inching Facility () (P)Required (Y/N)ForwardReverse

6f IEC Input Design Required (Y/N) (P)

8 Gearbox Specification (S)ManufacturerType (e.g. helical)Number of stagesFinal Drive ratioService factorEfficiency (%)IP rating

9 Food Grade Oil Required (Y/N) (P)

Drive No.:

1 Driven Equipment (P/S)

2 Type of Drive () (P/S)FixedTwo speedVariable

3 Method of Power Transmission from Drive System to Driven Assembly () (P/S)Close coupledChainBeltOther (specify)

4 Method of Mechanical Overload Protection for Drive System () (P/S)Current monitoringTorque limiting couplingOther (specify)

5 Local Inching Facility () (P)Required (Y/N)ForwardReverse

6f IEC Input Design Required (Y/N) (P)

8 Gearbox Specification (S)ManufacturerType (e.g. helical)Number of stagesFinal Drive ratioService factorEfficiency (%)IP rating

9 Food Grade Oil Required (Y/N) (P)

ISSUE 3 JULY 2017

Page 12: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 63

Drive No.:

1 Driven Equipment (P/S)

2 Type of Drive () (P/S)FixedTwo speedVariable

3 Method of Power Transmission from Drive System to Driven Assembly () (P/S)Close coupledChainBeltOther (specify)

4 Method of Mechanical Overload Protection for Drive System () (P/S)Current monitoringTorque limiting couplingOther (specify)

5 Local Inching Facility () (P)Required (Y/N)ForwardReverse

6f IEC Input Design Required (Y/N) (P)

8 Gearbox Specification (S)ManufacturerType (e.g. helical)Number of stagesFinal Drive ratioService factorEfficiency (%)IP rating

9 Food Grade Oil Required (Y/N) (P)

Drive No.:

1 Driven Equipment (P/S)

2 Type of Drive () (P/S)FixedTwo speedVariable

3 Method of Power Transmission from Drive System to Driven Assembly () (P/S)Close coupledChainBeltOther (specify)

4 Method of Mechanical Overload Protection for Drive System () (P/S)Current monitoringTorque limiting couplingOther (specify)

5 Local Inching Facility () (P)Required (Y/N)ForwardReverse

6f IEC Input Design

ISSUE 3 JULY 2017

Page 13: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 64

Required (Y/N) (P)8 Gearbox Specification (S)

ManufacturerType (e.g. helical)Number of stagesFinal Drive ratioService factorEfficiency (%)IP rating

9 Food Grade Oil Required (Y/N) (P)

ISSUE 3 JULY 2017

Page 14: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 65

APPENDIX D – SUPPLIER’S SUPPLEMENTARY DATA SHEET INFORMATION

Clause Supplementary Information

ISSUE 3 JULY 2017

Page 15: WIMES 5.01, Issue 3, July 2017 Documents/Datasheets... · Web view6.1.6.2 Motors/Gearboxes (If Required/Provided) Refer to Appendix C2. 6.1.6.3 Hydraulic Drives (If Required/Provided)

WIMES 5.01 Page 66

ISSUE 3 JULY 2017