william j. andrews...2020/05/04 · bcsea final argument may 4, 2020 bc hydro f2020-f2021 rra page...
TRANSCRIPT
Page 1 of 1
William J. Andrews Barrister & Solicitor
1958 Parkside Lane, North Vancouver, BC, Canada, V7G 1X5
Phone: 604-924-0921, Fax: 604-924-0918, Email: [email protected]
May 4, 2020
British Columbia Utilities Commission
Sixth Floor, 900 Howe Street, Box 250
Vancouver, BC, V6Z 2N3
Attn: Patrick Wruck, Commission Secretary
By Email: [email protected]
Dear Sir:
Re: Re: British Columbia Hydro and Power Authority,
F2020 to F2021 Revenue Requirements Application,
BCUC Project No. 1598990
B.C. Sustainable Energy Association Final Argument
Attached please find BCSEA’s Final Argument in this proceeding.
Yours truly,
William J. Andrews
Barrister & Solicitor
Encl.
cc. Matt Ghikas
BRITISH COLUMBIA UTILITIES COMMISSION
British Columbia Hydro and Power Authority F2020 to F2021 Revenue Requirements Application
BCUC Project No. 1598990
Final Argument
of
BC Sustainable Energy Association
May 4, 2020
William J. Andrews, Barrister & Solicitor 1958 Parkside Lane North Vancouver, BC, V7G 1X5 Phone: 604-924-0921, Fax: 604-924-0918 Email: [email protected]
Contents PART ONE: INTRODUCTION AND SUMMARY ............................................................. 5
A. FINAL ARGUMENT OF BCSEA .............................................................................. 5
B. BCSEA’S INTERESTS IN THE PROCEEDING ....................................................... 5
C. HIGH-LEVEL SUMMARY ........................................................................................ 6
D. ORGANIZATION OF ARGUMENT .......................................................................... 7
E. RESPONSES TO PANEL’S THREE QUESTIONS .................................................. 7
F. BC HYDRO’S INTRODUCTION .............................................................................. 8
PART TWO: LEGAL FRAMEWORK AND SCOPE OF THE PROCEEDING ................... 8
PART THREE: PROVIDING SAFE, RELIABLE AND COST EFFECTIVE SERVICE, COMPLEX ENVIRONMENT ........................................................................................... 9
A. CONTAINING CONTROLLABLE COSTS ............................................................... 9
B. DEMANDS ON BC HYDRO .................................................................................. 10
C. ADDITIONAL INVESTMENT AFTER THE TEST PERIOD .................................... 11
PART FOUR: LOAD AND REVENUE FORECASTS ..................................................... 11
A. INTRODUCTION ................................................................................................... 11
B. SNAPSHOT OF THE OCTOBER 2018 LOAD FORECAST UNDERLYING THE EVIDENTIARY UPDATE ........................................................................................... 12
C. LOAD FORECAST METHODOLOGY ................................................................... 12
D. TEST PERIOD LOAD FORECAST ....................................................................... 12
E. THE CONFIDENCE INTERVAL AROUND THE MID FORECAST ........................ 12
F. THE JUNE 2019 20-YEAR LOAD FORECAST UPDATE IMPACTS THE YEARS AFTER THE TEST PERIOD ...................................................................................... 13
G. THE OCTOBER 2018 LOAD FORECAST, ASSUMED FORESTRY SUB-SECTOR DECLINE ................................................................................................................... 13
H. THE LOAD FORECAST AND THE PORTION OF THE CLEANBC “UPSIDE” POTENTIAL THAT CAN BE ASSESSED AT THIS TIME .......................................... 13
I. REGULATORY ACCOUNTS TRUE-UP VARIANCES FROM THE LOAD FORECAST ............................................................................................................... 14
J. REVENUE FORECAST, INDUSTRY STANDARD, PAST PRACTICE ................... 15
K. CONCLUSION AND REQUESTED FINDINGS ..................................................... 15
PART FIVE: FORECAST COST OF ENERGY .............................................................. 15
A. INTRODUCTION ................................................................................................... 15
B. FORECAST INCREASE IN THE COST OF ENERGY DRIVEN BY EXISTING EPAs, FOR WHICH COST RECOVERY IS DIRECTED ............................................ 15
C. BC HYDRO, STEPS TO MITIGATE IPP ENERGY COSTS .................................. 16
D. FORECAST COST OF ENERGY, HOW BC HYDRO OPERATES THE SYSTEM 16
E. BC HYDRO, HERITAGE ASSETS ........................................................................ 20
F. VARIANCE ACCOUNTS, CUSTOMERS PAY ACTUAL COST OF ENERGY ....... 21
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 3 of 74
G. CONCLUSION AND REQUESTED FINDINGS ..................................................... 21
PART SIX: OPERATING COSTS .................................................................................. 21
A. INTRODUCTION ................................................................................................... 21
B. OPERATING COSTS SNAPSHOT: COST PRESSURES WITH OFFSETTING TEST PERIOD SAVINGS .......................................................................................... 21
C. BCUC’S RECOMMENDATIONS AND COMMENTS ON OPERATING COSTS .... 22
D. BC HYDRO BUDGETING, GOVERNANCE PROCESSES, COST CONTAINMENT EFFORTS .................................................................................................................. 23
E. CONTROLLABLE COST PRESSURES WITHIN EXISTING BUDGETS, INCREASES AND UNCONTROLLABLE COSTS ...................................................... 23
F. MEANS TO CONTROL COSTS AND ABSORB NEW UNCONTROLLABLE OPERATING COST PRESSURES ............................................................................ 25
G. FTE NUMBERS, WORK ON SITE C, AND INSOURCING .................................... 26
H. OPTIMIZING POWER SYSTEM MAINTENANCE ................................................. 26
I. BRATTLE REPORT AND INDICATIVE COMPARISON, BC HYDRO’S OPERATING COSTS ...................................................................................................................... 27
J. CONCLUSION AND REQUESTED FINDINGS ...................................................... 29
PART SEVEN: CAPITAL EXPENDITURES AND ADDITIONS ...................................... 29
A. INTRODUCTION ................................................................................................... 29
B. BC HYDRO’S EVIDENCE SUPPORTING CAPITAL FORECASTS, AMOUNT, CAPITAL FILING GUIDELINES ................................................................................. 29
C. CAPITAL PLANNING PROCESS .......................................................................... 30
D. REDUCED CAPITAL FORECAST, AFFORDABILITY, SYSTEM PERFORMANCE AND RISK.................................................................................................................. 30
E. DELIVERY OF CAPITAL PROJECTS, EFFICIENCY, EFFECTIVENESS ............. 30
F. BC HYDRO’S CAPITAL MANAGEMENT PROCESSES, ENDORSEMENTS BY THIRD PARTIES ....................................................................................................... 31
G. AMORTIZATION OF CAPITAL ADDITIONS REGULATORY ACCOUNT, CUSTOMERS ONLY PAY ACTUAL COSTS ............................................................. 31
H. EXPENDITURES ON RIPRAP FOR W.A.C. BENNETT DAM ............................... 32
I. VARIANCE OF DIRECTIVE 3, MINETTE TO LNG CANADA PROJECT ................ 32
J. SPECIFIC ISSUES RAISED .................................................................................. 33
K. CONCLUSION AND REQUESTED FINDINGS ..................................................... 38
PART EIGHT: REGULATORY ACCOUNTS.................................................................. 39
A. INTRODUCTION ................................................................................................... 39
B. BC HYDRO’S REGULATORY ACCOUNTS, ACCOUNTING STANDARDS AND BCUC GUIDELINES .................................................................................................. 39
C. MERITS OF EACH REGULATORY ACCOUNT, NUMBER OF ACCOUNTS ........ 40
D. BC HYDRO’S REGULATORY ACCOUNTS, BENEFIT TO CUSTOMERS ............ 42
E. AUDITOR GENERAL’S CONCERNS ABOUT REGULATORY ACCOUNTS ......... 44
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 4 of 74
F. BC HYDRO MANAGEMENT OF REGULATORY ACCOUNT BALANCES ............ 45
G. BC HYDRO’S PROPOSED CHANGES TO REGULATORY ACCOUNTS ............ 47
H. FORECAST FOR REAL PROPERTY SALES ....................................................... 49
I. CONCLUSION AND REQUESTED FINDING ......................................................... 49
PART NINE: OTHER REVENUE REQUIREMENTS ITEMS ......................................... 49
A. INTRODUCTION ................................................................................................... 49
B. TEST PERIOD REVENUE REQUIREMENTS, DEPRECIATION RATES .............. 49
C. FORECAST FINANCE CHARGES ........................................................................ 49
D. INTERGROUP’S RECOMMENDATIONS REGARDING BC HYDRO’S FUTURE RETURN ON EQUITY ............................................................................................... 50
E. CONCLUSION AND REQUESTED FINDINGS ..................................................... 50
PART TEN: TRANSMISSION REVENUE REQUIREMENTS ........................................ 50
A. INTRODUCTION ................................................................................................... 50
B. TRR AND OATT RATES ....................................................................................... 50
C. THE OATT RATE DESIGN ................................................................................... 50
D. CONCLUSION AND REQUESTED FINDINGS ..................................................... 51
PART ELEVEN: DEMAND-SIDE MANAGEMENT......................................................... 51
A. INTRODUCTION ................................................................................................... 51
B. MODERATION APPROACH, ENERGY SURPLUS ............................................... 52
C. BC HYDRO’S TRADITIONAL DSM PLAN, BCUC DIRECTIVES, GOVERNMENT PRIORITIES, AND DSM REGULATION .................................................................... 54
D. DIRECTIVE 61 REGARDING ALLOCATION OF PORTFOLIO COSTS, RESCISSION ............................................................................................................ 62
E. TRADITIONAL DSM, UCA, CLEAN ENERGY ACT, AND DSM REGULATION .... 63
F. THE EXPENDITURE SCHEDULE EXCLUDES THERMO-MECHANICAL PULP EXPENDITURES ....................................................................................................... 67
G. LOW CARBON ELECTRIFICATION EXPENDITURES, PRESCRIBED UNDERTAKINGS, COST RECOVERY IS MANDATED ............................................. 67
H. BC HYDRO MANAGEMENT OF TRADITIONAL DSM AND LCE INITIATIVES .... 71
I. CONCLUSION AND REQUESTED FINDINGS ....................................................... 72
PART TWELVE: IMPLEMENTATION OF RATES AND CONSIDERATION OF NEW INFORMATION ............................................................................................................. 72
A. INTRODUCTION ................................................................................................... 72
B. BC HYDRO’S RATE IMPLEMENTATION PROPOSAL, INTERESTS OF BOTH CUSTOMERS AND THE COMPANY ........................................................................ 72
C. UPDATING EVIDENTIARY UPDATE INPUTS ...................................................... 73
D. CONCLUSION AND REQUESTED FINDING ....................................................... 74
PART THIRTEEN: CONCLUSION AND ORDER SOUGHT .......................................... 74
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 5 of 74
PART ONE: INTRODUCTION AND SUMMARY
A. FINAL ARGUMENT OF BCSEA
1. This is the final argument of the intervener B.C. Sustainable Energy Association
(BCSEA) in the Commission’s proceeding regarding the BC Hydro Revenue
Requirement Application for F2020 to F2021.
2. This final argument responds to BC Hydro’s April 1, 2020 Final Argument.1 It also
addresses the three topics on which the Commission Panel requested submissions.2
B. BCSEA’S INTERESTS IN THE PROCEEDING
3. BCSEA is a registered charity and a non-profit association of citizens, professionals
and practitioners committed to promoting the understanding, development and
adoption of sustainable energy, energy efficiency and energy conservation in British
Columbia. BCSEA supports the province’s transition to a lower-carbon economy.
BCSEA has four chapters across B.C. and approximately three hundred individual
and organizational members (including businesses, NGOs, community
organizations, local governments). BCSEA represents individuals and organizations
in BC who care about energy sustainability and climate change mitigation, and who
want the energy they purchase and use to be sustainably produced and transported.
4. Members of BCSEA are ratepayers of BC Hydro. BCSEA’s interests in this
proceeding are as a non-profit public interest energy policy organization, and as a
representative of its members’ interests as ratepayers.
5. BCSEA’s interests in the proceeding are indicated by their participation in related
BCUC proceedings including:
a. BC Hydro’s F2017-F2019 Revenue Requirement Application and Demand-
Side Management Expenditures Schedule,
b. BC Hydro's 2015 Rate Design Application, and
c. BC Hydro Regulatory Oversight of Capital Expenditures and Projects.
6. BCSEA has participated actively in the current proceeding.
1 https://www.bcuc.com/Documents/Arguments/2020/DOC_57721_2020-04-01-BCH-
FinalArgument.pdf. 2 Exhibit A-31.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 6 of 74
C. HIGH-LEVEL SUMMARY
7. BCSEA supports approval of BC Hydro’s F2020-F2021 Revenue Requirement
Application and acceptance of BC Hydro’s traditional DSM Expenditure Schedule for
the Test Period, subject to the specific reservations and comments set out in the
argument below.
8. BCSEA would strongly prefer a more ambitious traditional DSM spending envelope,
and a more ambitious amount of energy and capacity savings, in the Test Period. In
BCSEA’s view, the amount of low-carbon electrification needed for B.C. to meet its
legislated GHG reduction targets under the CleanBC Plan will put BC Hydro into an
energy and capacity deficit planning position sooner rather than later. BC Hydro will
then require all cost-effective traditional DSM savings. Despite BC Hydro’s
assurances, BCSEA is concerned that the “moderation approach” jeopardizes BC
Hydro’s ability to ramp up conservation and efficiency savings when they become
urgently needed. In addition, BCSEA is concerned that the decision not to achieve all
cost-effective energy and capacity savings during the Test Period will create “lost
opportunities” by allowing inefficient assets to be locked-in for the long term.
9. In BCSEA’s view, BC Hydro’s budget for low-carbon electrification is far too low.
BCSEA encourages BC Hydro to develop a comprehensive long-term plan for low-
carbon electrification measures across all sectors that will meet quantitative GHG
reduction objectives in order to achieve B.C.’s legislated GHG reduction targets.
10. BCSEA specifically supports the proposed increase in funding for the Low-Income
and Non-Integrated Areas DSM programs.
11. BCSEA strongly opposes BC Hydro’s decision to acquire biomass power from
contaminated retired rail ties under an EPA with Atlantic Power in Williams Lake..
12. BCSEA urges the Government to move expeditiously to allow BC Hydro (and
FortisBC Inc.) to recover their net costs of EV fast-charging stations up to a
reasonable limit. In addition, BCSEA recommends that the Legislature add “low-
carbon transportation” to the B.C. energy objectives in the Clean Energy Act.
13. BCSEA hopes and expects that there is room for improvement in BC Hydro’s
industrial load interconnection regime, particularly in order to foster low-carbon
electrification.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 7 of 74
14. As a matter of terminology, in BCSEA’s view, intergenerational equity should not be
used as a synonym for benefits matching. The present generation enjoys the benefit
of investments made by earlier generations. It is incumbent on the current generation
to pay this forward to future generations. Intergenerational equity means that the
present generation must not defer to future generations the costs of benefits
received by the present generation. Intergenerational equity does not prevent the
present generation deferring to future generations the costs of benefits that will be
received by future generations: that is benefits matching, which is an accepted
accounting principle.
D. ORGANIZATION OF ARGUMENT
15. For convenience, this argument follows the 13-Part structure of BC Hydro’s Final
Argument.
E. RESPONSES TO PANEL’S THREE QUESTIONS
16. BCSEA’s summary responses to the Panel’s three questions and the location of the
discussion in this argument are set out in the following table.
Panel Question3 BCSEA Response
1. Whether the Peace Region Electric Supply project meets the requirements to be considered a prescribed undertaking under section 18 of the Clean Energy Act, pursuant to section 4(2) of the Greenhouse Gas Reduction (Clean Energy) Regulation;
Yes. Paragraph 130
2. Whether the Minette Station to LNG Canada Interconnection project meets the requirements of the Transmission Upgrade Exemption Regulation, as amended by B.C. Reg. 160/2018, to exempt the project from Part 3 of the Utilities Commission Act; and
Yes. Paragraph 127
3. Whether British Columbia Hydro and Power Authority’s investments in electric vehicle charging infrastructure should be included in rate base during the current test period and recovered from ratepayers or be separately tracked and excluded from rate base until the British Columbia Utilities Commission directs otherwise, given the developing landscape of the electric vehicle charging stations market in BC.
The former. Paragraph 133
3 Exhibit A-31.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 8 of 74
F. BC HYDRO’S INTRODUCTION
17. BC Hydro says it has had two broad objectives for this proceeding. The first is “to
provide the Commission, interveners and customers with an open and transparent
view of its operations and cost structure and to be open to feedback and suggestions
received through this process.”4 In response:
a. BCSEA acknowledges that BC Hydro provided substantial new information
regarding its Operating Costs for each Key Business Unit (Application,
Chapters 5A to 5G) and its Capital Expenditures (Appendix K), compared to
the F2017-F2019 Revenue Requirements Application. This was very helpful.
b. BCSEA acknowledges that BC Hydro has provided a very large number of
very informative responses to information requests and questions during the
oral hearing from the Commission, the Panel and Interveners.
18. BC Hydro’s second broad objective is “to convey that BC Hydro’s revenue
requirements and requested rate changes reflect a pervasive culture of restraint and
cost containment in the face of external cost pressures and an increasingly complex
operating environment.”5 BCSEA considers that BC Hydro has met that objective
during this proceeding.6
PART TWO: LEGAL FRAMEWORK AND SCOPE OF THE PROCEEDING
19. BCSEA agrees with BC Hydro that there is no need for BC Hydro to distinguish
expenditures for export from other expenditures.7
20. Section 44.1 of the Utilities Commission Act (UCA) now applies to BC Hydro.8 This
means that BC Hydro’s next long-term resource plan (i.e., Integrated Resource Plan)
will be filed with the BCUC for review and acceptance under section 44.1 of the UCA,
rather than with the Minister of Energy under section 3 of the Clean Energy Act
4 BC Hydro Final Argument, para.1.
5 BC Hydro Final Argument, para.1.
6 In saying so, BCSEA is not commenting on any of the myriad issues within the proceeding.
7 Exhibit B-5, BCUC 1.2.1, pdf p.37.
8 Exhibit B-6, BCSEA 1.3.1, pdf p.627. Energy Statutes Amendment Act, 2019, 2019-24-2,
effective May 16, 2019 (Royal Assent).
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 9 of 74
(CEA), which has been repealed. The requirement that BC Hydro file a long-term
resource plan with the BCUC comes into effect on February 28, 2021.9
21. While the Remote Communities Regulation10 remains in effect, BC Hydro ended the
Remote Community Electrification Program in 2014. BC Hydro says, “Any future
consideration of communities which may be added to the Remote Communities
Regulation will be undertaken by BC Hydro on an individual project by project
basis.”11 BCSEA does not take issue with that approach. BCSEA supports the
addition of communities to the Remote Communities Regulation in the future. Also,
BCSEA supports measures by BC Hydro and the communities in question to reduce
GHG emissions caused by reliance on diesel generation in Non-Integrated Areas.
22. BCSEA does not take issue with BC Hydro’s view that the Auditor General’s
comments regarding the use of rate-regulated accounting at BC Hydro in F2019
have been satisfied.12
23. BCSEA does not take issue with BC Hydro’s summary list of matters regarding which
BCUC is required to allow BC Hydro to recover its costs.13
24. BCSEA takes no position as to whether the BCUC has authority to identify the costs
of legislated policies where the BCUC cannot direct associated changes.14 However,
BCSEA doubts that there would be adequate evidence to do so in the current
proceeding.
PART THREE: PROVIDING SAFE, RELIABLE AND COST EFFECTIVE SERVICE, COMPLEX ENVIRONMENT
A. CONTAINING CONTROLLABLE COSTS
25. The evidence demonstrates that BC Hydro has made concerted efforts to contain
controllable costs in the Test Period, and that BC Hydro’s budgeting process is
rigorous.15
9 Section 44.1(2) of the UCA requires a public utility to file a long-term resource plan with the
Commission. Newly added section 44.1(2.1) states “The authority need not file a long-term resource plan before February 28, 2021.” 10
BC Reg. 240/2007, under the BC Hydro Public Power Legacy and Heritage Contract Act, SBC 2003, c.86. 11
Exhibit B-6, BCSEA 1.4.1, pdf p.629. 12
Exhibit B-12, BCUC 2.201.3, pdf p.10. 13
BC Hydro Final Argument, para.6. 14
BC Hydro Final Argument, para.7. 15
BC Hydro Final Argument, para.8.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 10 of 74
B. DEMANDS ON BC HYDRO
26. BCSEA concurs that the demands on BC Hydro are increasing as its service
environment becomes more complex.
27. BCSEA agrees that increased costs are being driven by more-stringent regulatory
requirements in areas such as reliability, cyber security, safety, archaeological,
groundwater and non-fish bearing streams, species at risk, and invasive species.16
BCSEA considers that these are important societal objectives and supports BC
Hydro meeting its corporate responsibilities in this regard.
28. BCSEA also agrees with the high-level observation by BC Hydro President and CEO
Chris O’Riley regarding increasing customer service and societal expectations:
“I think societal expectations on institutions are increasing across the board, and correspondingly societal risk tolerance is decreasing. And this in itself becomes a cost pressure for a critical infrastructure provider such as BC Hydro.”17
29. BCSEA highlights that BC Hydro now has a crucial role in achieving low-carbon
electrification in support of the Province’s CleanBC Plan to meet BC’s GHG
reduction targets, and affordability, economic development and Reconciliation
objectives. The CleanBC plan is the Province’s strategy to reach its 2030 climate
targets, through the use of clean and renewable energy in transportation, buildings
and industry in order to reduce greenhouse gas emissions and build British
Columbia’s economy.18
30. The Phase 1 Final Report of the Comprehensive Review of BC Hydro refers to “BC
Hydro’s role in implementing electrification initiatives critical to the CleanBC plan.”19
BC Hydro’s 2019/20 2021/22 Service Plan states that BC Hydro aligns with the
Government’s “strong, sustainable economy” priority by “[s]upporting the
implementation of the CleanBC plan to increase British Columbians’ use of cleaner
energy in key sectors of the economy and shift away from reliance on fossil fuels for
transportation, industry, and housing.”20 The Service Plan states:
“We are focused on delivering our renewed customer service strategy, with the goal of making it easier to do business with us and helping our
16
BC Hydro Final Argument, para.13. 17
BC Hydro Final Argument, para.14, citing Tr. 5, p. 359, l. 9 to p. 360, l. 5 (O’Riley). 18
Exhibit B-1, Appendix C, Comprehensive Review of BC Hydro – Phase 1 Final Report, p.44, pdf p.1284. 19
Exhibit B-1, Appendix C, p.1, pdf p.1241. 20
Exhibit B-1, Appendix E, p.12, pdf p.1352.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 11 of 74
customers make smart energy choices through our conservation and energy management programs, including encouraging our customers to use our clean and reliable electricity to power their homes, vehicles and businesses. We will support and align with the Province’s new CleanBC plan, which outlines significant greenhouse gas (GHG) reduction measures, by powering British Columbia’s economic growth with clean and renewable electricity”21
C. ADDITIONAL INVESTMENT AFTER THE TEST PERIOD
31. BCSEA agrees with Mr. O’Riley’s observation during his oral testimony that in the
context of new and rising expectations BC Hydro’s operating budgets will need to
increase in subsequent test periods.22
PART FOUR: LOAD AND REVENUE FORECASTS
A. INTRODUCTION
32. BCSEA agrees with BC Hydro that the actual sales for the first two months of F2020
and the October 2018 Load Forecast for the remainder of the F2020-F2021 Test
Period are a reasonable basis for setting rates for the Test Period.23
33. In BCSEA’s view, the October 2018 Load Forecast was reasonable at the time it was
made. And, it was not materially contradicted by actual experience up to the closing
of the evidentiary record in the proceeding on March 4, 2020.
34. BCSEA notes that the October 2018 Load Forecast includes only a limited amount of
low-carbon electrification implemented prior to the CleanBC Plan and it does not
include incremental load associated with BC Hydro implementing the CleanBC
Plan.24
35. BCSEA agrees with BC Hydro that the Panel can and should take judicial notice of
the COVID-19 pandemic that has erupted subsequent to the closing of the
evidentiary record.25 That said, as discussed further in Part Twelve, below, BCSEA’s
view is that the rates for the Test Period should be based on the evidentiary record,
and the evidentiary record should not be reopened.
21
Exhibit B-1, Appendix E, p.13, pdf p.1353. 22
BC Hydro Final Argument, para.15 citing Tr. 5, p. 372, l. 19 to p. 373, l. 9 (O’Riley). 23
BC Hydro Final Argument, para.17. 24
Exhibit B-6, BCSEA 1.9.1, pdf p.651; Transcript Vol.8B, p.1362, lines 7-16 (Rich). 25
BC Hydro Final Argument, para.595.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 12 of 74
B. SNAPSHOT OF THE OCTOBER 2018 LOAD FORECAST UNDERLYING THE EVIDENTIARY UPDATE
36. The October 2018 Load Forecast for domestic electricity sales after rates and DSM
savings for F2021 is 53,253 GWh in the Mid-Load Forecast and 51,364 GWh in the
Low-Load Forecast. For context, the F2021 Low-Load figure is less than the Actual
(temperature normalized) figure for F2014.26
C. LOAD FORECAST METHODOLOGY
37. BCSEA does not disagree with BC Hydro’s evidence that “The initial years of each
forecast vintage, which are of greatest relevance when setting rates for a single test
period, tended to be reasonably accurate.”27
D. TEST PERIOD LOAD FORECAST
38. BCSEA agrees that “Since the May 2016 Load Forecast, BC Hydro made
improvements to its load forecast methodology and governance based on feedback
from the BCUC and internal audit recommendations.”28
39. Regarding forecasting EV load, BC Hydro says its EV load forecasting model was
reviewed in the third party audit of the 2017 Load Forecast and no recommendations
for changes were made. BCSEA is satisfied with BC Hydro’s statement that “As part
of development efforts for future load forecasts, we intend to place more focus on our
EV modelling, given the emphasis that the CleanBC plan places on the electrification
of transportation.”29
E. THE CONFIDENCE INTERVAL AROUND THE MID FORECAST
40. BCSEA accepts BC Hydro’s argument that “The confidence interval, represented by
the high / low forecasts, is a critical part of the context when defining the
reasonableness of using the October 2018 Load Forecast for setting Test Period
rates.”30 Further, BCSEA accepts that “it is inevitable that actual results will vary from
forecasts.”31 And BCSEA accepts that the Monte Carlo analysis that informs the
26
Exhibit B-1, Appendix O, October 2018 Load Forecast, pdf p.1796 27
BC Hydro Final Argument, para.23, citing Tr. 10, p. 1633, ll. 20-25 (Rich). 28
BC Hydro Final Argument, para.24. 29
Exhibit B-6, BCSEA 1.7.1, pdf p.640. 30
BC Hydro Final Argument, para.44. 31
BC Hydro Final Argument, para.44, citing Tr. 10, p. 1633, ll. 6-10 (Rich).
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 13 of 74
High- and Low-Forecasts takes into account historical occurrences of economic
downturns.32 These factors reinforce the conclusion that the October 2018 Load
Forecast is the appropriate basis for setting rates in the Test Period, even though the
actual results for F2021 may turn out in hindsight to vary from the forecast.
F. THE JUNE 2019 20-YEAR LOAD FORECAST UPDATE IMPACTS THE YEARS AFTER THE TEST PERIOD
41. BCSEA agrees with BC Hydro that it was reasonable that the June 2019 Load
Forecast did not propose adjustments to the Evidentiary Update revenue forecast.
The difference was minute. Variances between actual and forecast during the Test
Period will result in a refund to, or recovery from, ratepayers. And, BCSEA agrees
that “It is impractical to continually update forecasts and expect to bring the
regulatory process to a timely resolution.”33
G. THE OCTOBER 2018 LOAD FORECAST, ASSUMED FORESTRY SUB-SECTOR DECLINE
42. BCSEA is satisfied that the October 2018 Load Forecast is the appropriate basis for
setting rates in the Test Period. In BCSEA’s view, the evidence as of October 2019
that actual load in the forestry sub-sector is below the forecast is not a sufficient
reason to reject or to modify the October 2018 Load Forecast for the purpose of
setting rates in the Test Period. Year-to-date F2020 sales as of December 31, 2019
were only 2.6% below the October 2018 Forecast.34 In BCSEA’s view, this variance
is not large enough to warrant reopening the October 2018 Forecast for the purpose
of setting rates in the Test Period.
H. THE LOAD FORECAST AND THE PORTION OF THE CLEANBC “UPSIDE” POTENTIAL THAT CAN BE ASSESSED AT THIS TIME
(a) The June 2019 Load Forecast Reflects Some, but Not All, of the CleanBC Initiatives
43. BCSEA supports use of the October 2018 Load Forecast as the basis for setting
rates in the Test Period, despite the potential load growth from electrification in the
32
BC Hydro Final Argument, para.46. 33
BC Hydro Final Argument, para.48. 34
BC Hydro Final Argument, para.56, citing Exhibit B-41, BC Hydro Undertaking No. 15.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 14 of 74
Test Period that is not yet reflected in the Evidentiary Update.35 BC Hydro’s next
revenue requirement application (expected in February 202136) will provide an
effective opportunity for new information to be considered.
(b) BC Hydro Continues to Work to Build Load and Remove Barriers to Electrification
44. BCSEA wishes to make an additional point on the treatment of low-carbon
electrification in the Application.
45. To be clear, BCSEA agrees with BC Hydro’s witness Mr. John Rich, Senior
Manager, Load Forecasting, that “there is a difference between a load forecast and a
sales target.”37 The load forecasting function is intended to be unbiased and data
driven.38 BCSEA does not object to BC Hydro’s load forecasting approach to the
potential upside of the CleanBC Plan (in the present case.)
46. However, the problem, in BCSEA’s view, is that BC Hydro’s low-carbon electrification
budget for F2020-F2022 is not sufficient and it is not linked to a long-term
comprehensive plan (which would include “sales targets”) for achieving the
electrification required under the CleanBC Plan.
47. BCSEA submits that BC Hydro is literally correct when it argues that “[t]here is ample
evidence on the record of BC Hydro’s ongoing work to build load to reduce
greenhouse gas emissions.”39 However, BCSEA submits that the evidence shows
that BC Hydro’s ongoing work to build load to reduce GHG emissions in the Test
Period is not yet sufficiently robust to meet the low-carbon electrification expectations
of the CleanBC Plan.
I. REGULATORY ACCOUNTS TRUE-UP VARIANCES FROM THE LOAD FORECAST
48. As BC Hydro states, “variances between actual and forecast Cost of Energy arising
from differences between forecast and actual domestic customer load are deferred to
the Non-Heritage Deferral Account.” BCSEA agrees that “[a] regulatory variance
35
BC Hydro Final Argument, para.55, citing Tr. 8B, p. 1295, ll. 1-11 (Clendinning). 36
Transcript Vol.5, p.425, lines 6-13 (Mr. O’Riley). 37
BC Hydro Final Argument, para.59, citing Tr. 10, p. 1682, l. 25 to p. 1683, l. 10 (Rich). 38
BC Hydro Final Argument, para.57, citing Tr. 10, p. 1682, l. 25 to p. 1683, l. 10 (Rich). 39
BC Hydro Final Argument, para.60.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 15 of 74
account is a fair and efficient means of addressing emerging conditions during the
regulatory process (and after it).”40
49. Similarly, BCSEA agrees with BC Hydro that the NHDA will “permit the fair and
efficient management of load variances associated with the ongoing COVID-19
pandemic that has emerged in the weeks after the closure of the evidentiary
record.”41
J. REVENUE FORECAST, INDUSTRY STANDARD, PAST PRACTICE
50. The Revenue Forecast is a straightforward calculation, based on the pertinent load
forecast and the existing rate schedules.42
K. CONCLUSION AND REQUESTED FINDINGS
51. BCSEA concurs with BC Hydro that the Load Forecast and Revenue Forecast for the
Test Period reflected in the Evidentiary Update are reasonable.43
PART FIVE: FORECAST COST OF ENERGY
A. INTRODUCTION
52. BCSEA agrees that “BC Hydro’s forecast Cost of Energy, as updated in the
Evidentiary Update, is reasonable for the purpose of setting rates in the Test
Period.”44
53. BCSEA notes that, as part of this Application, BC Hydro is not proposing any
generation projects or seeking acceptance of any electricity purchase agreement.45
B. FORECAST INCREASE IN THE COST OF ENERGY DRIVEN BY EXISTING EPAs, FOR WHICH COST RECOVERY IS DIRECTED
(a) The Vast Majority of Total IPP Purchase Cost Increases Are Related to Existing EPAs
54. The evidence46 supports BC Hydro’s position that:
40
BC Hydro Final Argument, para.65. 41
BC Hydro Final Argument, para.66. 42
BC Hydro Final Argument, para.67. 43
BC Hydro Final Argument, para.68. 44
BC Hydro Final Argument, para.69. 45
BC Hydro Final Argument, para.71.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 16 of 74
“The forecast increase in Cost of Energy in the Application is primarily driven by an increase in costs related to IPPs and Long-Term Commitments. The vast majority of those costs are associated with existing EPAs, the terms of which are fixed and for which cost recovery is mandated [i.e., legally required].”47
(b) A Small Portion of the Total IPP Purchase Cost Relates to EPA Renewals, which Includes Directed Biomass Purchases, and New EPAs
55. BCSEA is concerned that as of September 30, 2019, BC Hydro executed a new
long-term Electricity Purchase Agreement with Atlantic Power for its NorthWest
Energy facility in Williams Lake BC that contemplates burning retired rail ties
contaminated with creosote and pentachlorophenol as a portion of its fuel.48 When
asked if the EPA would require power to be exclusively from clean or renewable
resources, i.e., precluding the use of retired rail ties as fuel, BC Hydro stated, “[t]he
NW Energy EPA does not preclude delivery of power from retired railway ties.”49
56. BCSEA strongly opposes BC Hydro’s decision to acquire new generation under the
NW Energy EPA that is not exclusively from clean or renewable resources.
57. BCSEA acknowledges that the BCUC is prevented from denying recovery of the
costs of the NW Energy EPA by the Direction to the BCUC respecting the Biomass
Energy Program dated April 1, 2019 (Order in Council No. 158, BC Reg. 71/2019).”50
C. BC HYDRO, STEPS TO MITIGATE IPP ENERGY COSTS
58. In BCSEA’s view, the evidence supports BC Hydro’s position that it “is managing
energy costs from IPPs to the extent possible within the parameters of its contractual
obligations under EPAs.”51
D. FORECAST COST OF ENERGY, HOW BC HYDRO OPERATES THE SYSTEM
59. BC Hydro provides a useful summary of the distinction between planning and
operating, the forecast Cost of Energy for the Test Period, the Energy Studies, and
the objective of BC Hydro’s operation of the system.52
46
Cited in BC Hydro Final Argument, paras.73-75. 47
BC Hydro Final Argument, para.72. 48
Ibid. 49
Exhibit B-23, BCSEA 4.90.1, pdf p.72. 50
Exhibit B-17, BCSEA 3.82.1, pdf p.379; BC Hydro Final Argument, para.77, second bulleted paragraph. 51
BC Hydro Final Argument, para.79.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 17 of 74
60. BCSEA supports both the theory and the practice of how BC Hydro operates the
system within the operational timeframe.
(a) BC Hydro’s Operating Horizon Objective, the Best Interests of Ratepayers
61. BCSEA agrees that BC Hydro’s stated objective of operation of the system –
“meeting load first while maximizing value within a range of outcomes” – is in the
best interests of ratepayers. BC Hydro summarizes the objective as follows:
“In the operational (i.e., up to three years) time horizon, BC Hydro operates the system to meet load first and then makes decisions to dispatch resources and to undertake Electricity Purchases or Surplus Sales to maximize the expected value of its energy supply portfolio within a range of outcomes.”53
62. BCSEA accepts BC Hydro’s explanation that “Electricity Purchases or Surplus Sales
are undertaken to both cost-effectively meet load requirements and to take
advantage of trade opportunities.”54 As BC Hydro explains:
“Surplus Sales (also referred to as domestic sales) are sales to Powerex that occur because BC Hydro has a surplus. Market Electricity Purchases are purchases from Powerex to cost-effectively meet load. Net Purchases (Sales) from Powerex are transactions with Powerex to generate Trade Income. Powerex also generates Trade Income from a wide range of activities that are not connected to BC Hydro’s system. Ratepayers receive the full benefit of Trade Income generated by Powerex’s activities and bear no downside risk under BC Hydro’s definition of Trade Income, which has the effect of assigning any net loss in Trade Income to the Government of B.C.”55
63. BCSEA accepts that “While Powerex is able to use the residual capability of the BC
Hydro system to generate Trade Income, BC Hydro makes all of the decisions
related to system operations and has the ability to put constraints on Powerex’s
activities.”56
64. Similarly, BCSEA accepts that “meeting domestic load and maximizing the expected
value for ratepayers [are] complementary, rather than conflicting, objectives.”57 The
52
BC Hydro Final Argument, paras.82-83. 53
BC Hydro Final Argument, para.84. 54
BC Hydro Final Argument, para.85. 55
BC Hydro Final Argument, para.86, footnotes omitted. 56
BC Hydro Final Argument, para.87. 57
BC Hydro Final Argument, para.88.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 18 of 74
uncertainty and risk around domestic requirements requires an assessment of
probabilities, which is done as part of the Energy Studies.58 As BC Hydro states:
“BC Hydro’s approach recognizes that actual conditions will be different than expected conditions. While decisions are made to maximize value, BC Hydro manages those decisions to maintain its ability to respond to a range of probable future conditions.”59
(b) In 2018, BC Hydro Managed Through Significant Events While Maximizing Value for Ratepayers
65. BCSEA is familiar with the evidence regarding the unusual events and BC Hydro’s
operational activities between the summer of 2018 and the spring of 2019. Briefly, in
the summer of 2018 BC Hydro sold power, based on high market prices and a
forecast surplus at the time. System storage then became depleted due to: low
inflows to the Williston Reservoir in the Fall of 2019; the October 2019 Enbridge
natural gas pipeline explosion, which boosted electricity demand; unusually cold
temperatures in February 2019, which increased heating load; and dry conditions in
the spring of 2019, which reduced inflows to BC Hydro reservoirs and receipts of
power from run-of-river and wind IPPs. BC Hydro responded by entering the
“Powerex Letter Agreement” under which BC Hydro secured imports and reduced its
risk. In the end, BC Hydro’s operational decisions “saved money for the
ratepayers.”60
66. During the oral hearing, questions were put to BC Hydro’s witnesses regarding these
events. Ms. Heather Matthews, Director of the Generation System Operations Key
Business Unit at BC Hydro, took the lead role in responding on this topic. She
testified, in conclusion, that “certainly I stand by that those sales that we made in the
summer [of 2018] were the correct things to do and I’d do them again.”61
“THE CHAIRPERSON: So with hindsight you would go back and do exactly the same thing anyway?
MS. MATTHEWS: [Answer] Yes.”62
58
BC Hydro Final Argument, para.89. 59
BC Hydro Final Argument, para.91. 60
Transcript, Vol.9, p.1470, lines 17-19, (Ms. Matthews). 61
Transcript, Vol.9, p.1485, lines 22-24, (Ms. Matthews). 62
Transcript, Vol.9, p.1485, line 25 to p.1486, line 1, (Ms. Matthews).
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 19 of 74
67. BCSEA considers Ms. Matthews to be a highly qualified witness who displayed an
impressive knowledge of the events in question. BCSEA submits that her evidence
on this point is persuasive and should be accepted by the Panel.
(c) Energy Study Methodology
68. BCSEA agrees with BC Hydro’s argument that the Energy Study methodology
produces a sound price signal that enables BC Hydro to achieve its operating
objective to meet load first while maximizing value within a range of outcomes.
69. Attributes of the Energy Study methodology include the following:
“The Energy Study models account for the trade-offs (risk/reward) between selling now and selling later, or buying now and buying later.”63
“A key output of the Energy Studies is a forecast of the marginal value of water in BC Hydro’s two largest reservoirs (Williston and Kinbasket).”64
“The Energy Studies account for a wide range of potential occurrences. The use of weather year ensembles ensures that the variability in inflows, prices, loads, and resources due to the impacts of weather are well represented in the models.”65
“BC Hydro updates the Energy Studies monthly with new input data pertaining to import/export transmission limits and market prices. BC Hydro also incorporates the most recent actual load data, augmented by the latest approved load forecast.”66
70. In BCSEA’s view, the Energy Study methodology has been explained persuasively in
the Application, the responses to Information Requests, oral testimony by BC Hydro
witnesses, and BC Hydro’s Final Argument.67 BC Hydro’s monthly Energy Studies
process received a favourable review by SINTEF and BC Hydro’s Internal Audit
group.68
(d) The Lower Cost of Energy Forecast in the Evidentiary Update
71. The forecast Cost of Energy in the October 2019 Evidentiary Update69 was materially
lower than the forecast in the Application.70 BC Hydro explains that “[t]his reflects [a]
63
BC Hydro Final Argument, para.104. 64
BC Hydro Final Argument, para.105. 65
BC Hydro Final Argument, para.106. 66
BC Hydro Final Argument, para.107, footnote omitted. 67
BC Hydro Final Argument, paras.102-107. 68
Exhibit B-1, p.4-14, pdf p.240. 69
Exhibit B-19.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 20 of 74
shift from run-of-river IPP power to lower cost market purchases due to low water
conditions.”71
E. BC HYDRO, HERITAGE ASSETS
72. BC Hydro argues that its management of the Heritage Assets provides optimal value
to BC Hydro customers, in both the operating and planning time horizons.72
(a) Operating Horizon
73. BCSEA agrees that, in the operating horizon, BC Hydro’s approach of “operating the
system in an integrated manner is better for ratepayers than prioritizing operating
specific Heritage Assets.” BCSEA accepts that “prioritizing operating specific
heritage assets over existing EPAs would be detrimental to ratepayers.”73 As BC
Hydro argues:
“While Heritage Assets are generally lower cost than IPP purchases, in the operating horizon the resource stack available to BC Hydro is essentially fixed. EPAs with IPPs are take-or-pay. BC Hydro’s monthly Energy Studies optimize the operational management of all sources of energy supply on BC Hydro’s integrated system. Over the operating horizon, BC Hydro operates the system to meet its objective of meeting load and otherwise maximizing net revenue for the benefit of its ratepayers. The price signals that come out of the Energy Studies are used to determine which basins to run, and in what order, or whether BC Hydro is willing to either import or export. This approach means that over the operating horizon, BC Hydro will obtain energy in the most economic manner possible, rather than prioritizing lower cost sources of energy.”74
(b) Planning Horizon
74. In the planning horizon, BC Hydro argues that its capital planning maximizes the
long-term benefits from the Heritage Assets. BCSEA agrees with BC Hydro’s high-
level summary as follows:
“BC Hydro is in a multi-decade period of significant renewal of its Heritage Assets. Investments are prioritized and staged to maintain overall system reliability and spread capital costs to avoid sudden rate impacts. For facilities that are not a significant contributor to overall system reliability, investments to restore generation have been deferred until such time that
70
BC Hydro Final Argument, para.109. 71
BC Hydro Final Argument, sub-heading (d) on p.53. 72
BC Hydro Final Argument, paras.111-115. 73
BC Hydro Final Argument, para.112. 74
BC Hydro Final Argument, para.112.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 21 of 74
there is a system need for energy and capacity; and they are of a high enough priority to be included within BC Hydro’s 10 year Capital Plan.”75
75. While BCSEA agrees that BC Hydro’s capital planning maximizes the long-term
benefits from the Heritage Assets, BCSEA believes that BC Hydro should plan much
more low-carbon electrification in order to maximize the long-term benefits from the
Heritage Assets and contribute to meeting B.C.’s legislated GHG reduction targets.
F. VARIANCE ACCOUNTS, CUSTOMERS PAY ACTUAL COST OF ENERGY
76. Variances between planned and actual costs of energy are deferred to the Heritage
Deferral Account or the Non-Heritage Deferral Account. The NHDA also captures the
Domestic Revenue Variance between planned and actual domestic customer load.
BCSEA agrees with BC Hydro’s statement that, “In the end, although BC Hydro’s
revenue requirements are based on a forecast Cost of Energy, customers only pay
the actual costs.”76
G. CONCLUSION AND REQUESTED FINDINGS
77. BCSEA supports BC Hydro’s request that the BCUC find that BC Hydro’s forecast
Cost of Energy for the Test Period is reasonable, being based on a sound
methodology and appropriate assumptions.
PART SIX: OPERATING COSTS
A. INTRODUCTION
78. This Part addresses planned operating costs for F2020-F2021.
B. OPERATING COSTS SNAPSHOT: COST PRESSURES WITH OFFSETTING TEST PERIOD SAVINGS
79. In paragraph 121 of its Final Argument, BC Hydro reproduces a table showing Total
Base Operating Costs (Fiscal 2019 – Fiscal 2021). For context, the table includes
columns showing figures prior to the Evidentiary Update and the variance. In order to
simplify the presentation and to focus on the numbers that are currently at issue,
BCSEA provides the following version showing only the figures for F2019 Actual,
F2020 Update, and F2021 Update.
75
BC Hydro Final Argument, para.113. 76
BC Hydro Final Argument, para.116.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 22 of 74
Total Base Operating Costs (Fiscal 2019 – Fiscal 2021 ($ millions)77
Operating Cost by Business Group F2019 Actual
F2020 Update
F2021 Update
Integrated Planning 285.9 290.8 293.0
Capital Infrastructure Project Delivery 85.9 80.1 81.1
Operations 215.6 237.3 240.1
Safety 53.6 56.8 57.5
Finance, Technology, Supply Chain 261.2 262.6 264.8
People, Customer, Corporate Affairs 105.5 110.6 111.9
Other78 (250.5) (244.3) (244.4)
Total Base Operating Costs 757.2 793.8 803.9
80. It can be observed that for F2020, the first of the two test years, Total Base
Operating Costs is approximately 5% above the preceding year (F2019). And for
F2021, the second test year, Total Base Operating Costs is approximately 1% above
the first test year.
C. BCUC’S RECOMMENDATIONS AND COMMENTS ON OPERATING COSTS
81. In its Decision on the Previous Application,79 the Commission made
recommendations and comments regarding BC Hydro’s Operating Costs. BCSEA
concludes that BC Hydro has responded adequately to these points in its evidence
and Final Argument.
82. In the current Application, BC Hydro provided:
a. additional information on each of BC Hydro’s Key Business Units (KBUs) and
their Departments,
b. details of BC Hydro’s budgeting process,
c. details of BC Hydro’s cost containment initiatives, and
d. additional benchmarking regarding operating costs.
83. BC Hydro also responded to questions regarding:
a. Total Rewards program, and employee retention,
77
Source: Exhibit B-11-2, Evidentiary Update, Appendix A, Schedule 5, Lines 1 to 9. Cited in BC Hydro Final Argument, para.121. 78
“Other” Operating Costs by Business Group is negative due to Capitalized Costs being removed from Operating Costs. Exhibit B-11-2, Evidentiary Update, Appendix A, Schedule 5.7, Line 5. 79
Decision and Order G-47-18, dated March 1, 2018. At: https://www.ordersdecisions.bcuc.com/bcuc/decisions/en/306836/1/document.do.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 23 of 74
b. Workforce Optimization Program, replacing contractors with employees,
c. Work Smart Program,
d. Full Time Equivalent (FTE) levels, and
e. Zero-based budgeting.
84. These topics are addressed in the paragraphs that follow.
D. BC HYDRO BUDGETING, GOVERNANCE PROCESSES, COST CONTAINMENT EFFORTS
85. BC Hydro’s operating costs budgeting process involves both bottom-up and top-
down elements.
86. BCSEA agrees that the bottom-up component went into depth and was not merely
incremental adjustments to previous spending.
87. In BCSEA’s view, the top-down component, which BC Hydro says “ultimately
dictated the budget amounts during the Test Period,”80 did result in lower budgeted
Operating Costs than would have resulted from a zero-based budgeting approach.
88. BCSEA believes the evidence establishes that BC Hydro has appropriate oversight
processes in place so that it operates within its budgets and targets, including a
vacancy management process, performance metrics and regular internal reporting.81
E. CONTROLLABLE COST PRESSURES WITHIN EXISTING BUDGETS, INCREASES AND UNCONTROLLABLE COSTS
89. BC Hydro’s budgeting for Operating Costs (and Capital Expenditures) in the Test
Period occurred in conjunction with BC Hydro’s participation in the BC Government’s
Phase One Comprehensive Review of BC Hydro.82
90. The evidence supports BC Hydro’s contention83 that its Executive Team determined
that all cost pressures would be managed within the F2019 forecast operating cost
budget, with the exception of (a) storm restoration costs, (b) the Employer Health
Tax and rising benefits costs, and (c) wage increases. A fourth exception was added
in the Evidentiary Update: (d) updated pension discount rate. BC Hydro describes
80
BC Hydro Final Argument, para.129. 81
BC Hydro Final Argument, para.134. 82
Exhibit B-1, p.1-8, pdf p.69. 83
BC Hydro Final Argument, para.139.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 24 of 74
these exceptions as “uncontrollable” operating costs pressures. In other words, the
determination was that for all “controllable” operating costs, upward pressure would
be balanced by found savings and efficiencies.
91. BCSEA accepts that the budgets for the four types of “uncontrollable” operating
costs in the Test Period are reasonable. Details are provided in the paragraphs that
follow.
92. The increase in the budget for storm restoration costs in the Test Period results from
application of the previously-approved methodology that uses a five-year average of
actual storm restoration costs for the five most recent normal weather years.
Customers pay for only the actual, not budgeted, storm restoration costs due to the
Storm Restoration Costs Regulatory Account.
93. The (new) Employer Health Tax increases BC Hydro’s Standard Labour Rates in the
Test Period.
94. The budgeted salary increases of 2% per year for unionized employees and 2.5%
per year for management and professional salaries are reasonable. For practical
purposes, compensation for the unionized employees is determined by provincial
guidelines. For the management and professional compensation, it is noted that
annual management and professional percentage increases from F2012 to F2019
averaged only 1%.84 BCSEA accepts that the compensation increases contemplated
by the Test Period budget are needed to keep pace with the market after some years
of restraint and thereby to retain and attract high quality employees.85 Similarly,
BCSEA does not object to the incentive pay component of BC Hydro’s total rewards
program.86
95. The updated (decreased) pension discount rate increases BC Hydro’s pension costs
in the Test Period. BCSEA accepts that the timing and size of the change were
routine.87
84
BC Hydro Final Argument, para.150. 85
BC Hydro Final Argument, paras.153-155. 86
BC Hydro Final Argument, paras.156-158. 87
BC Hydro Final Argument, paras.161-162.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 25 of 74
F. MEANS TO CONTROL COSTS AND ABSORB NEW UNCONTROLLABLE OPERATING COST PRESSURES
96. BC Hydro lists the following examples of measures to reduce Operating Costs in the
Test Period:
a. Workforce Optimization Program (replacing contractors with internal FTEs),
b. Accenture Repatriation,
c. Vacancy Factor,
d. elimination of the Unallocated Funds Budget,
e. elimination of a Property Lease,
f. reduced the Communications Budget,
g. expansion of Paperless Billing,
h. Work Smart Program, and
i. “Making it Easier to Get Work Done” Initiative.88
97. Regarding the Workforce Optimization Program, BCSEA agrees that BC Hydro has
given adequate consideration to the longer term costs of replacing contractors with
employees.89
98. Regarding elimination of the unallocated funds budget in the Test Period, BC Hydro
acknowledged that this “will, necessarily, have an impact on BC Hydro’s ability to
manage unanticipated costs pressures during the test period.90
99. Regarding the Work Smart Program, BCSEA accepts BC Hydro’s argument that the
objective of the Program is to increase employees’ work output (measured in
capacity hours), not to reduce employment levels. As BC Hydro says, “In the
absence of Work Smart BC Hydro would expect its operating costs to be driven
higher as a direct result of increased regulatory and compliance requirements.”91
88
BC Hydro Final Argument, para.163. 89
BC Hydro Final Argument, paras.166-169. 90
Exhibit B-6, Response to BCSEA 1.26.1, pdf p.700. 91
BC Hydro Final Argument, para.199.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 26 of 74
G. FTE NUMBERS, WORK ON SITE C, AND INSOURCING
100. BCSEA agrees that it is in the best interest of customers for BC Hydro to
continue managing the business with a focus on total cost, rather than the number of
FTEs per se.92
101. Regarding its number of FTEs over time, BC Hydro summarizes, correctly in
BCSEA’s view, that “apart from growth in the workforce directly related to increased
capital investment and the Accenture repatriation, BC Hydro’s FTEs have remained
relatively flat since fiscal 2012 and are forecast to remain flat over the Test Period.”93
102. The Site C Project is the only area driving net new FTEs. These costs are
capitalized and therefore do not affect the F2020-F2021 Revenue Requirement.
BCSEA notes, though, that BC Hydro’s customers will begin paying for the costs of
Site C when the Project comes into service.
103. BC Hydro argues that it uses overtime where it is cost-effective to do so, and has
reduced the amount of planned overtime for the Test Period.94 In BCSEA’s view, BC
Hydro has appropriate structures in place to manage overtime effectively.
H. OPTIMIZING POWER SYSTEM MAINTENANCE
104. The Operating Costs budget includes the costs of power system maintenance. In
the bigger picture, maintenance costs together with capital investments are within BC
Hydro’s asset management strategy.
105. BC Hydro says increases in power system maintenance costs in the Test Period
will be “mitigated,” but that it expects budgets will need to increase after this Test
Period.95
106. In BCSEA’s view, BC Hydro has provided extensive evidence regarding its
management of power system maintenance actions and costs in the context of risk
management and sustainment capital investments. BC Hydro’s asset management
practices have been reviewed favourably, for example by Navigant and the Auditor
General of BC.96 BC Hydro’s operations and maintenance costs compare favourably
for both transmission and distribution in utility industry benchmarking by First
92
BC Hydro Final Argument, para.206. 93
BC Hydro Final Argument, para.207. 94
BC Hydro Final Argument, paras.210-212. 95
BC Hydro Final Argument, para.215. 96
BC Hydro Final Argument, para.219.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 27 of 74
Quartile.97 For generation station maintenance, benchmarking by Navigant indicates
that BC Hydro’s costs are relatively low.98
107. While maintenance budgets are higher in the Test Period than in F2019, BC
Hydro says this is due largely to a combination of (a) storm restoration budget
(Distribution Emergency Response) increases under the five-year average
methodology, (b) funds spent on maintenance being transferred from “unallocated” to
“maintenance,” and (c) increases in the Standard Labour Rate.99 BCSEA accepts
this explanation.
108. Vegetation management spending in F2015 to F2019 and budgeted in F2020 to
F2021 is almost flat. BC Hydro says this will be adequate. In his opening statement
to the Commission Panel, Mr. O’Riley highlighted vegetation management as one of
three areas in which to expect operating cost increases beyond inflation in future
revenue requirements processes.100 He pointed to increasing concern in the electric
utility industry about forest fires, referring to damage to electric utility assets, as well
as to potential liability to third parties for fires started by power systems. He also
indicated that mandatory reliability standards address vegetation and that this will
drive up BC Hydro’s management, quality control, and quality assurance and actual
spending on vegetation.101
I. BRATTLE REPORT AND INDICATIVE COMPARISON, BC HYDRO’S OPERATING COSTS
109. In addition to the benchmarking by First Quartile and Navigant,102 BC Hydro
provided in evidence a 2019 report by Brattle Group benchmarking BC Hydro’s
operating costs against those of its peer U.S. utilities.103 The Brattle Report examined
“non-fuel operations and maintenance expenses,” i.e., excluding water rentals and
fuel which are included within BC Hydro’s Energy Costs. The Brattle Report
addresses total operating costs, and operating costs by function and sub-function.
97
BC Hydro Final Argument, paras.221-222. 98
BC Hydro Final Argument, para.223. 99
BC Hydro Final Argument, para.224. 100
Exhibit B-30, p.4. 101
Transcript Vol.5, p.504 line 17 to p.507 line 4. 102
Discussed in para.106, in the text above. 103
Exhibit B-1, Appendix T.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 28 of 74
The Brattle Report concludes that BC Hydro’s operating costs compare favourably
with those of its peers, on all of the metrics.104
110. As the Brattle Report benchmarked against U.S. utilities, BC Hydro also provided
its own high-level comparison of BC Hydro’s operating costs with those of Manitoba
Hydro, FortisBC, and Hydro-Québec. Acknowledging methodological limitations, the
internal review put BC Hydro’s operating costs “in line with those of other Canadian
utilities on both a per MWh and a per customer basis.”105
111. The Application requests that the BCUC rescind the requirement that BC Hydro’s
revenue requirements applications contain financial information that follows the
Commission’s Uniform System of Accounts (USoA).106 BC Hydro says this would
give it discretion to determine whether and how often to prepare these schedules107
(as a supplement to and based on BC Hydro’s existing system of accounts). BC
Hydro says preparing the BCUC USoA financial schedules is labour intensive
(something less than half an FTE per year108). BC Hydro says that “having the
discretion to prioritize these pressures against other requirements is an important
part of our ongoing efforts to limit overall base operating cost increases.”109
112. The topic of rescinding the mandatory production of BCUC USoA schedules
comes up in the context of benchmarking because the Brattle Report relies on the
FERC Uniform System of Accounts, which is different than both the BCUC USoA
and BC Hydro’s existing system of accounts. If BC Hydro was to obtain future
benchmarking reports based on the FERC USoA, then one possibility would be for
BC Hydro to prepare supplementary financial schedules based on the FERC USoA
rather than on the BCUC USoA. However, it is not yet known if the Commission will
direct BC Hydro to provide future iterations of the Brattle Report. BC Hydro states in
conditional terms:
“...if the BCUC and interveners found the Brattle Report valuable, then reporting based on the FERC Uniform System of Accounts would likely provide greater value, going forward, compared to reporting based on the BCUC Uniform System of Accounts.”110
104
Exhibit B-1, p.5-51, pdf p.322. 105
Exhibit B-1, p.5-55, pdf p.326. 106
Exhibit B-1, p.1-33, pdf p.94; BC Hydro Final Argument, para.237. 107
Transcript Vol.7, p.1015 line 25 to p.1016 line 6. 108
Transcript Vol.7, p.1014 line 17 to p.1015 line 24. 109
BC Hydro Final Argument, para.237, citing Exhibit B-13, BCOAPO 2.123.1. 110
BC Hydro Final Argument, para.239.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 29 of 74
113. Despite having said that using the FERC USoA would be of greater value than
using the BCUC USoA if Brattle Reports are to be prepared in the future, BC Hydro
also notes that the costs of new spending opportunities (such as future Brattle
Reports) “add up and push against BC Hydro’s ability to keep rates affordable and
competitive.” BC Hydro’s position is that the value of presenting BC Hydro’s
accounts according to the FERC Uniform System of Accounts “is insufficient at the
present time to justify a directive that would remove the ability of management to
prioritize this work against other pressures, as appropriate.”111
114. BCSEA’s view is that a direction by the Commission requiring BC Hydro to
present financial schedules under the FERC USoA, or the BCUC USoA for that
matter, is not warranted. BC Hydro should itself determine what method to employ
considering costs and priorities. BCSEA takes no position on whether the
Commission should direct BC Hydro to provide benchmarking studies equivalent to
the Brattle Report in future revenue requirements applications.
J. CONCLUSION AND REQUESTED FINDINGS
115. BCSEA supports BC Hydro’s request112 that the Commission find that the
forecast operating expenses in the Test Period are reasonable.
PART SEVEN: CAPITAL EXPENDITURES AND ADDITIONS
A. INTRODUCTION
116. This Part addresses BC Hydro’s capital planning and delivery processes and its
forecast capital expenditures and additions in the Test Period.
B. BC HYDRO’S EVIDENCE SUPPORTING CAPITAL FORECASTS, AMOUNT, CAPITAL FILING GUIDELINES
117. BC Hydro has certainly filed a significant volume of evidence supporting its
capital forecasts for the Test Period.113
118. BCSEA accepts that the nature of the information filed is generally consistent
with BC Hydro’s 2018 Capital Filing Guidelines approved with revisions by the
Commission on December 2, 2019.114
111
BC Hydro Final Argument, para.240. 112
BC Hydro Final Argument, para.241. 113
BC Hydro Final Argument, para.244.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 30 of 74
C. CAPITAL PLANNING PROCESS
119. BCSEA agrees that BC Hydro has a robust capital planning process. As BC
Hydro summarizes:
“BC Hydro’s Test Period capital forecast is the product of an enterprise-wide capital planning process. It incorporates top-down limitations, and risk-based project prioritization to balance affordability, system performance and risk. BC Hydro has developed an ex-plan governance process to respond to evolving circumstances.”115
D. REDUCED CAPITAL FORECAST, AFFORDABILITY, SYSTEM PERFORMANCE AND RISK
120. BC Hydro’s Current Capital Plan for F2020 to F2021 (the Test Period) is $682
million or 22.3 percent below the Previous Capital Plan for F2020 to F2021.116
Deferral of projects accounts for $137 million of the reduction.117 These reductions
occurred in the context of BC Hydro’s participation in Phase 1 of the Comprehensive
Review of BC Hydro. BC Hydro says this “moderating of capital spending” will reduce
upward pressure on rates and will not materially impact system performance due to a
combination of strong system performance and slower demand growth.118 BC Hydro
says it will monitor asset condition and performance and will respond as needed.119
121. BCSEA agrees that additional reductions in capital spending would be
undesirable.120
E. DELIVERY OF CAPITAL PROJECTS, EFFICIENCY, EFFECTIVENESS
122. Regarding delivery of capital projects, BCSEA considers that the evidence
supports BC Hydro’s summary position that it “has implemented delivery processes
tailored to the size and complexity of projects, is engaged in continuous improvement
114
Decision and Order G-313-19, at https://www.bcuc.com/Documents/Proceedings/2019/DOC_56448_2019-12-02-BCH-Review-of-BCH-Capital-Expenditures-Decision.pdf. The approved version of BC Hydro’s 2018 Capital Filing Guidelines is at https://www.bchydro.com/content/dam/BCHydro/customer-portal/documents/corporate/regulatory-planning-documents/regulatory-filings/cap-exp/2020-01-17-cepr-compliance-g-313-19-d2.pdf. 115
BC Hydro Final Argument, para.246. 116
Exhibit B-5, BCUC 1.108.1, cited in BC Hydro Final Argument, para.268. 117
Exhibit B-5, BCUC 1.108.1, cited in BC Hydro Final Argument, para.269. 118
BC Hydro Final Argument, paras.264-266. 119
BC Hydro Final Argument, para.272. 120
BC Hydro Final Argument, para.273.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 31 of 74
of those processes, has rigorous financial approval processes in place, and has
been delivering its portfolio of projects on budget.”121
123. BCSEA generally agrees with BC Hydro’s points as follows:
a. BC Hydro’s planning and delivery functions work together to ensure
[reasonably] seamless transition and accountability;
b. BC Hydro’s delivery processes are tailored to the size and complexity of
projects;
c. BC Hydro is continuously improving its delivery processes;
d. BC Hydro has rigorous financial approval processes in place for all
investments;
e. BC Hydro evaluates power system projects upon completion;
f. BC Hydro has delivered its capital portfolio on budget; and
g. improvements in Technology processes have brought strong results
[compared to the industry generally].
F. BC HYDRO’S CAPITAL MANAGEMENT PROCESSES, ENDORSEMENTS BY THIRD PARTIES
124. BC Hydro’s capital planning and delivery processes have been reviewed
favourably by third parties such as the Office of the Auditor General.122
G. AMORTIZATION OF CAPITAL ADDITIONS REGULATORY ACCOUNT, CUSTOMERS ONLY PAY ACTUAL COSTS
125. BC Hydro states, “the Amortization of Capital Additions Regulatory Account
captures the differences between the forecast and actual amortization of capital
additions, with variances recovered over the next test period.” BCSEA agrees that
this means that customers will only pay for actual costs when actual capital
expenditures and additions vary from forecast due to factors such as changes in
project timing and scope changes.123
121
BC Hydro Final Argument, para.274. 122
BC Hydro Final Argument, paras.302-303. 123
BC Hydro Final Argument, para.304.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 32 of 74
H. EXPENDITURES ON RIPRAP FOR W.A.C. BENNETT DAM
126. BC Hydro says its expenditure of $700,000 for the riprap stockpile for the W.A.C.
Bennett Dam was prudently incurred and should be recovered in rates.124 BCSEA is
not aware of any evidence contradicting BC Hydro’s justification of the expenditure.
I. VARIANCE OF DIRECTIVE 3, MINETTE TO LNG CANADA PROJECT
127. A brief background is as follows. BC Hydro’s Northwest Substation Upgrade
project was designed to serve LNG Canada’s load interconnection request.125 In
March 2018, Directive 3 of the Decision on the Previous Application126 required BC
Hydro to apply for a CPCN if it intended to proceed with the Northwest Substation
Upgrade project. In July 2018, the Government amended the Transmission Upgrade
Exemption Regulation127 under the UCA, to exempt BC Hydro from Part 3 of the
UCA regarding certain transmission upgrades. The Northwest Substation Upgrade
project has since been cancelled due to LNG Canada splitting its load
interconnection request into two phases. However, a new BC Hydro project called
the Minette to LNG Canada Interconnection Project facilitates the first phase of LNG
Canada’s interconnection and includes items that were part of the cancelled
Northwest Substation Upgrade project. BC Hydro says the Minette to LNG Canada
Interconnection Project is exempt under the Transmission Upgrade Exemption
Regulation. LNG Canada has not committed to the second phase of its project,
which would be supported by two potential BC Hydro projects: the Minette
Substation Upgrade project, and the Northwest Substations Outage Mitigation
project.128 BC Hydro says these two projects would also be exempt under the
Transmission Upgrade Exemption Regulation.129
128. BCSEA concurs with BC Hydro that the Minette Station to LNG Canada
Interconnection project meets section 2(1)(e) and section 2(2) of the Transmission
Upgrade Exemption Regulation and is therefore exempt from Part 3 of the UCA.130
129. In addition, BCSEA supports BC Hydro’s request131 that the Commission remove
Directive 3 requiring BC Hydro to file a CPCN application for the Northwest
124
BC Hydro Final Argument, paras.306-310. 125
LNG Canada is the proponent of an LNG export terminal in Kitimat, BC. 126
Decision and Order G-47-18, p.39, pdf p.46. 127
BC Reg. 140/2013. 128
Exhibit B-12, BCUC 2.247.2, pdf p.449. 129
BC Hydro Final Argument, para.314. 130
BC Hydro Final Argument, para.313.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 33 of 74
Substation Upgrade project if BC Hydro intends to proceed with it.132 In BCSEA’s
view, rescinding Directive 3 ‘for greater certainty’ would have no substantive legal
effect. However, it would eliminate the potential for uncertainty.
J. SPECIFIC ISSUES RAISED
(a) PRES Project
130. BCSEA concurs with BC Hydro that the Peace Region Electricity Supply (PRES)
Project is a prescribed undertaking under section 4(2) of the Greenhouse Gas
Reduction (Clean Energy) Regulation133 (GGRR) and section 18 of the CEA.134
(b) Bear Mountain Terminal to Dawson Creek Transmission Voltage Conversion Project and North Montney Transmission Development Project
131. BCSEA concurs with BC Hydro that the potential Bear Mountain Terminal to
Dawson Creek Transmission Voltage Conversion Project and the North Montney
Transmission Development Project may also qualify as prescribed undertakings
under the GGRR and the CEA.135
132. BCSEA supports in principle the development of a mechanism for the BCUC to
assess the applicability of the GGRR in advance.136
(c) EV Charging Infrastructure
133. Regarding BC Hydro’s investments in electric vehicle charging infrastructure,
BCSEA concurs with BC Hydro as follows:
a. Capital additions regarding EV charging infrastructure, net of contributions
from Government or third parties, are included in rate base pursuant to
section 1 of Direction No. 8.137
b. The inclusion of capital additions regarding EV charging infrastructure in rate
base has no practical effect during the Test Period, during which BC Hydro’s
net income is prescribed to be $712 million for each of F2020 and F2021.
131
BC Hydro Final Argument, para.311. 132
Decision and Order G-47-18. 133
BC Reg. 102/2012. 134
BC Hydro Final Argument, paras.317-322. 135
BC Hydro Final Argument, paras.323-326. 136
BC Hydro Final Argument, para.327. 137
Direction No. 8 to the British Columbia Utilities Commission, BC Reg. 24/2019, at http://www.bclaws.ca/civix/document/id/complete/statreg/24_2019.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 34 of 74
c. The question of whether investments in EV charging stations should be
included in rate base in the future should not be considered in this
proceeding. It is not relevant to the Test Period. And, it is anticipated that the
BC Government will issue a legislative response to the Phase Two Final
Report of the Commission’s Inquiry into the Regulation of EV Charging
Services.
134. BCSEA urges the Government to move expeditiously to allow BC Hydro (and
FortisBC Inc.) to recover their net costs of EV fast-charging stations up to a
reasonable limit. On this topic, BCSEA also recommends that the Legislature add
“low-carbon transportation” to the BC energy objectives in the CEA.
(d) Cybersecurity
135. BCSEA is satisfied that BC Hydro puts an appropriately high priority on
cybersecurity. BC Hydro acknowledges that cybersecurity risk is a significant issue. It
has provided a substantial body of evidence regarding its cybersecurity management
structure, practices, investments, incident response plan, and third party reviews. BC
Hydro’s position is that it manages cybersecurity risk appropriately and will continue
to do so with the budgeted spending during the Test Period. BC Hydro says it is
likely that additional investment in cybersecurity will be required following the Test
Period given the increasing challenges. In BCSEA’s view, there is no evidence of
any deficiency in BC Hydro’s approach to cybersecurity in the Test Period or beyond.
(e) Projects in the same location
136. Questions were asked about whether BC Hydro could gain efficiencies by
combining projects that are in the same location. BCSEA is persuaded by BC
Hydro’s evidence that BC Hydro appropriately coordinates projects in the same
location to achieve efficiencies, and that it would be detrimental to combine individual
projects at the same location simply because they are at the same location. The
examples of projects at Mica138 and at the Bridge River system139 indicate that BC
Hydro’s approach is reasonable, and consistent with the Capital Filing Guidelines.
138
BC Hydro Final Argument, para.352. 139
BC Hydro Final Argument, paras.353-355.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 35 of 74
137. BC Hydro argues specifically that the “Bridge River 1 Replace Units 1-4
Generators / Governors Project”140 (Bridge 1 to 4 Project) should not be combined
with the Bridge River Transmission Project.141 BCSEA’s view is that the need for
each project is independent of the other. The Bridge 1 to 4 Project is aimed at
improved generation and water conveyance reliability at a single BC Hydro facility. It
would incidentally increase generation by 8 MW. The Bridge River Transmission
Project is aimed at resolving insufficient transmission capability for the Bridge River
system as a whole – to handle BC Hydro generation, 400 MW of IPP generation and
50 MW of expected IPP generation.
138. BC Hydro says it intends to file a section 44.2 capital expenditure schedule
application for the Bridge 1 to 4 Project, and to file a CPCN application for the Bridge
River Transmission Project if it is over $100 million.142 This is consistent with the
recently approved Capital Filing Guidelines. Granted, the Capital Filing Guidelines
“do not bind the BCUC in the exercise of its jurisdiction.”143
139. The Clean Energy Association of B.C. (CEABC), representing IPPs, has called
for a “conceptual cost estimate for refurbishing the entire Bridge River system.”144
CEABC’s counsel asked the BC Hydro witnesses, “How do you know that it’s a low
cost facility until you look at the numbers for refurbishing the entire system?”145 The
witnesses provided a lengthy explanation of BC Hydro’s planning and project
development practices as applied in the Bridge River system.146 BCSEA’s view is
that these practices are reasonable as described. In particular, it would not be
accurate to generalize that BC Hydro develops projects without any consideration of
other projects and the system in the area. BCSEA expects that specific investments
in the Bridge River area will come before the BCUC, whether in a capital expenditure
schedule, a CPCN application or a revenue requirement application, at which time
the Commission and the interveners will have an opportunity to scrutinize how a
specific investment fits within the broader context.
140
Exhibit B-1, Appendix J, Attachment 1, p.50 of 133, pdf p.1553. 141
Exhibit B-1, Appendix J, Attachment 1, p.75 of 133, pdf p.1578. 142
BC Hydro Final Argument, para.355. 143
BC Hydro Capital Filing Guidelines, para.2. 144
Transcript Vol.11, p.1903, lines 5-11. 145
Transcript Vol.11, p.1909, lines 23-25. 146
Transcript Vol.11, pp.1902-1910.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 36 of 74
(f) Strategic property purchases
140. In the current proceeding, BCSEA is not critical of BC Hydro’s strategic
purchases of property in Vancouver to support future substation projects in the West
End and in East Vancouver.147 The substation projects will be the subject of CPCN
applications in due course. The Commission’s proceedings regarding those CPCN
applications will provide an appropriate opportunity to examine the merits of the
property purchases. In BCSEA’s view, early acquisition of property is reasonable
given the scarcity of available properties meeting the highly specific locational
requirements of these particular projects. Notably, the properties are not amortized
for accounting purposes, and so there will be no amortization expense during the
Test Period.148
(g) Project write-offs
141. The Application proposes to change the status quo regarding project write-offs.
Previously, project write-offs were to the account of the shareholder. The Application
proposes budgets for project write-offs of $9.9 million and $9.7 million in F2020 and
F2021 respectively. Actual write-offs up to the budgeted amounts would be to the
account of ratepayers. Actual write-offs above the budgeted amounts would be to the
account of the shareholder. The size of the F2020 and F2021 project write-off
budgets is based on three-year historical actuals as a percentage of capital
expenditures, applied to forecast capital expenditures in the Test Period.
142. BC Hydro justifies recovery of project write-offs from ratepayers (up to the
budgeted amount) on the ground that project write-offs reflect prudent capital
management. BC Hydro says project write-offs are “effective project and investment
management practices and are the result of mature portfolio management practices
to ensure our capital investments are prudent.” BC Hydro says, “BC Hydro makes
every effort to reduce and avoid project write-offs through the effective use of the
early project investigation process as well as making write-off decisions as early as
possible in the project lifecycle.”149
143. BCSEA accepts the concept that prudent capital management will result in
project write-offs to some extent. Directionally, this supports recovery from
147
BC Hydro Final Argument, paras.356-368. 148
Exhibit B-53, BC Hydro Undertaking No.46, cited in BC Hydro Final Argument, para.357. 149
Exhibit B-1, p.8-21, pdf p.983; BC Hydro Final Argument, paras. 369-371; Exhibit B-56, BC Hydro Undertaking No.49, pdf p.9.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 37 of 74
ratepayers rather than the shareholder. In BCSEA’s view, BC Hydro’s capped
approach (actual project write-offs above the budget figure are to the account of the
shareholder) limits any (theoretical) potential for the utility to allow increased project
write-offs due to recovery from ratepayers.150
144. In terms of the size of the proposed F2020 and F2021 budgets for project write-
offs, BCSEA considers the proposed methodology reasonable. The historical project
write-offs occurred when they were to the account of the shareholder, so they are not
influenced by moral hazard. For these reasons, BCSEA does not oppose approval of
BC Hydro’s proposed budgets for project write-offs in the Test Period.
(h) Variances from Plan on past projects
145. BC Hydro has explained variances from plan on past projects. BCSEA’s view is
that these explanations have been appropriately probed in the information requests
and the oral hearing. BCSEA is not aware of any evidence that would warrant a
finding by the Commission that BC Hydro’s spending on a capital project was
imprudent so as to justify denying recovery of costs.
(i) Industrial load interconnection
146. “Industrial load interconnection” in this section refers to interconnections by
customers or IPPs at transmission voltages and interconnections of large loads at
distribution voltages. This section does not address connections by residential and
small commercial customers to distribution feeders.
147. BC Hydro’s industrial load interconnection practices have long been criticized as
too slow and too expensive for the customer or IPP wanting to connect. BC Hydro
disagrees, stating:
“BC Hydro is managing its industrial load interconnection requests well, with study times comparing well against BC Hydro’s own business practice timelines and the practices at other utilities. BC Hydro is, however, continuing to look for opportunities to improve the process.”151
148. At a high level, BCSEA certainly wants to see interconnections being achieved in
shorter rather than longer timeframes, at lower rather than higher costs consistent
with safety, reliability and future needs, and with cost allocation that fairly balances
150
As of December 31, 2019, the actual project write-offs in F2020 already exceeded the F2020 budget of $9.9 million by $4.2 million. Exhibit B-56, BC Hydro Undertaking No.49, pdf p.9. 151
BC Hydro Final Argument, para.375.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 38 of 74
the interests of existing and future customers and IPPs, and promotes low-carbon
electrification. Of course, ‘the devil is in the details.’
149. In BCSEA’s view, BC Hydro’s specific arguments are well supported by the
evidence:
a. Distribution and transmission interconnection processes are governed by the
tariff and published business practices;152
b. BC Hydro has engaged in continuous improvement of interconnection
processes;153
c. Interconnections are prioritized in the capital planning process and well
supported;154
d. BC Hydro is engaging with customers on its interconnection processes;155
e. BC Hydro has been meeting its internal targets and also benchmarks
favourably;156 and
f. BC Hydro will continue to improve the interconnection process.157
150. Nevertheless, BCSEA hopes and expects that there is considerable room for
improvement in BC Hydro’s industrial load interconnection regime, particularly for the
purpose of fostering low-carbon electrification.
K. CONCLUSION AND REQUESTED FINDINGS
151. In BCSEA’s view, the evidence establishes that BC Hydro has well-developed
planning and delivery processes and that BC Hydro is delivering its projects
effectively and efficiently. BCSEA respectfully submits that the Commission should
find that the planned capital additions and expenditures for the Test Period are
reasonable.
152
BC Hydro Final Argument, para.376. 153
BC Hydro Final Argument, paras.377-380. 154
BC Hydro Final Argument, paras.381-384. 155
BC Hydro Final Argument, para.385. 156
BC Hydro Final Argument, paras.386-391. 157
BC Hydro Final Argument, para.392.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 39 of 74
PART EIGHT: REGULATORY ACCOUNTS
A. INTRODUCTION
152. BC Hydro seeks approval of the Dismantling Cost Regulatory Account, and
closure of four regulatory accounts. BCSEA agrees with BC Hydro that the
underlying rationale for the BCUC’s approval of the existing regulatory accounts
remains sound even though the Government has repealed directions regarding some
of BC Hydro’s regulatory accounts.158
B. BC HYDRO’S REGULATORY ACCOUNTS, ACCOUNTING STANDARDS AND BCUC GUIDELINES
153. BCSEA accepts BC Hydro’s premise that it uses regulatory accounts for four
purposes:
“(1) to ensure that customers pay actual costs (no more, no less) where uncontrollable and unpredictable factors could otherwise produce unfair results,
(2) to defer differences between forecast and actual costs or revenues due to uncontrollable risks,
(3) to smooth out the rate impact of large, non-recurring costs, and
(4) to better match costs and benefits for customers.”159
154. BCSEA also accepts BC Hydro’s premise that its regulatory accounts should
comply with International Financial Reporting Standards (IFRS) and the BCUC’s
Regulatory Account Checklist.160
155. BCSEA agrees with BC Hydro that rate-regulated accounting is permitted under
“IFRS 14, Regulatory Deferral Accounts.”161
156. BCSEA accepts BC Hydro’s evidence that its existing regulatory accounts fall
within the categories identified in the BCUC Regulatory Account Checklist.162
158
BC Hydro Final Argument, paras.394-395. 159
BC Hydro Final Argument, para.397. 160
BC Hydro Final Argument, para.397. 161
BC Hydro Final Argument, para.398. 162
BC Hydro Final Argument, para.399.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 40 of 74
C. MERITS OF EACH REGULATORY ACCOUNT, NUMBER OF ACCOUNTS
157. BCSEA considers that regulatory accounts can be an appropriate and desirable
mechanism to shift the timing and allocation of a utility’s costs and revenue. BCSEA
accepts application of the matching principle in situations in which current
expenditures benefit future customers. This accords with economically efficient price
signals. BCSEA opposes the misuse of regulatory accounts to shift to future
customers the costs of meeting the needs of current customers. This would be
contrary to economically efficient price signals and contrary to the principle of
intergenerational equity.
158. BCSEA would disagree with a suggestion that the number of BC Hydro’s
regulatory accounts warrants concern in and of itself. In BCSEA’s view, the focus
should be on the purposes for which each regulatory account is established and
maintained, the balance in each account and in total, and the mechanisms for
reducing the positive or negative balances in each account and in total. Moreover,
the number of BC Hydro’s regulatory accounts is within the industry range, which is
broad. And, BC Hydro is not proposing to increase the number of regulatory
accounts; rather, it is proposing to close four regulatory accounts, with up to four
more to follow.
159. The Association of Major Power Customers (AMPC) filed evidence prepared by
InterGroup Consultants. One of InterGroup’s recommendations addresses BC
Hydro’s regulatory accounts:
“7. The BCUC should direct BC Hydro to simplify the regulatory and deferral accounts as a long-term priority, to help ensure BC Hydro’s costs are fully regulated, and are transparent to the regulator and impacted parties (Section 4.5).”163
160. BCSEA asked AMPC to clarify if the intention was to simplify by combining
regulatory accounts to reduce the number of regulatory accounts, or to simplify by
removing certain types of spending from regulatory account treatment and
recovering such spending in the revenue requirement for a given test year.
161. AMPC’s response says BC Hydro’s regulatory accounts should be both reduced
in number and narrowed in scope. AMPC states:
“The scope of deferral accounts means that BC Hydro’s shareholder is at very little risk from normal business functions and variances. If the
163
Exhibit C-11-11, AMPC Evidence, pdf p.6.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 41 of 74
accounts are not simplified and narrowed (both in scope and number), the justification for a ROE is significantly undermined (i.e., the justification for reward based on assumed risk diminishes as the risk assumed diminishes). Further, the accounts are excessively broad which makes transparent regulation difficult. For these reasons the accounts should ideally be narrowed in scope (not just collapsed into fewer accounts). Absent such steps, the ROE should be adjusted materially downwards.”164
162. BCSEA is not persuaded that BC Hydro’s regulatory accounts should be reduced
in number and narrowed in scope, for the following reasons.
a. The number of regulatory accounts is not in itself a problem, and in any event
is being reduced.
b. AMPC does not identify which regulatory account(s) it says should be
narrowed in scope. It would be inappropriate to set out to narrow the scope of
all of BC Hydro’s regulatory accounts. AMPC acknowledges this when it
(appropriately) defends amortization of BC Hydro’s DSM expenditures.
c. The relevance and consequences of BC Hydro’s regulatory accounts on the
Commission’s forthcoming determination of BC Hydro’s return on equity is
not within the scope of the current proceeding. Moreover, even if it was
assumed for the sake of argument that the number and scope of BC Hydro’s
regulatory accounts points to a lower ROE, in BCSEA’s view the Panel in the
current proceeding could not, and should not, endeavor to boost BC Hydro’s
future ROE by somehow directing BC Hydro to reduce the number and scope
of its regulatory accounts.
d. There is no evidence that BC Hydro’s revenue requirement (and rates) would
necessarily, or even likely, be lower if the number and scope of regulatory
accounts was reduced. At face value, reducing the number and scope of
regulatory accounts would increase both shareholder’s and ratepayers’ risk of
variance between forecasts and actuals.165
163. BC Hydro says it plans to limit future applications for new regulatory accounts to
situations where there are un-forecast and non-controllable expenditures greater
than $10 million in a fiscal year. BC Hydro is not seeking approval of the $10 million
threshold. It says, “proposals regarding specific regulatory accounts should be
164
Exhibit C-11-13, AMPC Response to BCSEA 6.1, pdf pp.41-42. 165
Transcript Vol.7, p.978 line 26 to p.980 line 3 (Mr. Layton).
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 42 of 74
evaluated by the BCUC individually on their merits.”166 BC Hydro says the $10 million
threshold applies to new regulatory accounts, not to whether existing regulatory
accounts should be closed. BCSEA does not oppose this approach.
164. On the subject of whether existing regulatory accounts should be closed, the
Commission asked BC Hydro why it is appropriate to continue to defer the variances
between the actual and forecast cost of energy arising from differences between
actual and forecast domestic customer load to the NHDA. BCSEA agrees with BC
Hydro’s response that focuses on the variances being uncontrollable:
“Variances between the actual and forecast cost of energy arising from differences between actual and forecast domestic customer load are beyond BC Hydro’s control and are frequently volatile and unpredictable due to uncontrollable factors such as weather and economic conditions.
For example, if British Columbia experiences a cold winter, actual load may be higher than forecast, which would mean that BC Hydro would collect more revenue than forecast. If this variance was not deferred, this would result in an increase in BC Hydro’s net income, which would be to the account of the shareholder, rather than to the benefit of ratepayers.
Similarly, uncontrollable events could result in actual load being lower than forecast. A specific and notable example is the July 2015 closure of the Howe Sound Pulp and Paper facility due to low water levels. This closure was unexpected and represented approximately $40 million in reduced annual revenue to BC Hydro. If this variance was not deferred, it would have resulted in a significant impact to BC Hydro’s net income in that fiscal year...”167
D. BC HYDRO’S REGULATORY ACCOUNTS, BENEFIT TO CUSTOMERS
165. BCSEA agrees that BC Hydro’s regulatory accounts benefit customers.
166. The Cost of Energy Variance Accounts (Heritage Deferral Account and Non-
Heritage Deferral Account) manage uncontrollable factors and volatility.
Uncontrollable and difficult to predict factors include the weather, water inflows,
system load requirements, market commodity prices, exchange rates, transmission
rates, surplus sales, and domestic load. Customers pay the actual costs of energy,
and neither the ratepayers nor the shareholder reaps a windfall due to the inevitable
variance between forecast and actual costs of energy.168
166
Exhibit B-16, CEC 1.69.1, pdf p.1442. 167
Exhibit B-16, BCUC IR 3.301.4, pdf p.172. 168
Transcript Vol.7, p.978 line 26 to p.980 line 3 (Mr. Layton).
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 43 of 74
167. The regulatory accounts BC Hydro seeks to continue have each been approved
by the Utilities Commission in the past. The Commission has also approved
regulatory accounts for FortisBC Inc. (electric) to address variances between actual
and forecast figures for uncontrollable factors. More than half (54%) of the utilities
covered by S&P Global Market Intelligence’s Regulatory Research Associates use a
decoupling type of adjustment clause.169
168. Regarding the Non-Current Pension Costs Regulatory Account,170 the factors
affecting the variances are largely market driven and beyond BC Hydro’s control.
BCSEA agrees that the Non-Current Pension Costs Regulatory Account avoids
windfall gains and losses for either the shareholder or ratepayers, consistent with the
“forecast variance account” category of the BCUC’s Regulatory Account Checklist.171
169. BCSEA supports continuation of the Real Property Sales Regulatory Account.
BCSEA concurs with BC Hydro that this account allows ratepayers to receive
benefits that would otherwise flow to the shareholder.172 By default, the shareholder,
not ratepayers, is entitled to the proceeds of sale from properties that are no longer
used and useful for utility purposes.173 BC Hydro has properties and property rights
purchased over the decades for utility purposes, but that are now surplus to BC
Hydro’s requirements.174 As part of the former 10 Year Rates Plan, the Government
directed approval of the account, by which $100 million of net proceeds from sales of
surplus properties would benefit ratepayers.175 The Ratepayers have been getting
the financial benefit of sales of these properties since 2015, in the form of rates that
were lower than they would otherwise have been.176 There is minimal risk to
ratepayers, as each of the properties has been sold at a profit.177 BCSEA agrees that
the carrying and site improvement costs being paid by customers in rates are minor
in comparison with the sale proceeds from which customers are benefitting.178
170. BCSEA strongly supports continuation of the Demand Side Management (DSM)
Regulatory Account. The DSM Regulatory Account captures all of BC Hydro’s
169
Exhibit B-28-2, p.3 of 39, pdf p.5. 170
Exhibit B-1, p.7-44, et seq., pdf p.934. 171
BC Hydro Final Argument, para.411. 172
BC Hydro Final Argument, para.412. 173
BC Hydro Final Argument, para.413. 174
BC Hydro Final Argument, para.414. 175
BC Hydro Final Argument, paras.414-415. 176
BC Hydro Final Argument, para.416. 177
BC Hydro Final Argument, para.417. 178
BC Hydro Final Argument, para.420.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 44 of 74
traditional DSM costs, and also its low-carbon electrification expenditures on
undertakings defined in section 4 (3) (a), (b), (c) or (d) of the GGRR. The DSM
Regulatory Account is amortized over a period of time to reflect the average
persistence of the benefits of the expenditures. This is an application of benefit
matching. As BC Hydro notes, “Benefit matching is a recognized principle in the
BCUC Checklist, and the deferral of DSM costs is a common accounting treatment in
the industry.”179
171. In sub-heading (d) before para.422 of its Final Argument, BC Hydro says the
DSM Regulatory Account “ensures intergenerational equity by matching costs and
benefits.” [underline added] The DSM Regulatory Account certainly matches costs
and benefits. However, in BCSEA’s view this is not a matter of intergenerational
equity. Intergenerational equity means that the costs of present benefits are not
deferred to be paid by future ratepayers. This is explained further detail in
paragraphs 176 and 181, below.
172. BCSEA agrees with BC Hydro that all DSM costs are appropriately included in
the DSM Regulatory Account for amortization over a period of years reflecting the
(weighted) average measure life. The DSM benefits are the result of the entire DSM
portfolio. In BCSEA’s view, it would not be reasonable to exclude the costs of Indirect
and Portfolio Enabling activities from DSM Regulatory Account. These activities are
necessary to successfully design, develop, and implement a successful portfolio.180
173. BCSEA supports continuation of the Remediation Regulatory Account. It
captures variances between forecast and actual asbestos remediation costs and
costs related to compliance with polychlorinated biphenyl regulations. These costs
are unpredictable and there have been significant variances.
E. AUDITOR GENERAL’S CONCERNS ABOUT REGULATORY ACCOUNTS
174. The BC Auditor General removed her qualification regarding the use of rate-
regulated accounting at BC Hydro on the Government’s F2019 financial
statements.181
179
BC Hydro Final Argument, para.422. 180
Exhibit B-1, Appendix X, p.77, pdf p.2217. 181
Exhibit B-12, BCUC 2.201.3, cited in BC Hydro Final Argument, para.429.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 45 of 74
F. BC HYDRO MANAGEMENT OF REGULATORY ACCOUNT BALANCES
175. BCSEA does not disagree with BC Hydro’s observation that the overall regulatory
accounts net balance has declined significantly from its peak.
176. BC Hydro states, “Approximately 80% of the forecast balances in fiscal 2024
resides in five regulatory accounts that are being, or will be, recovered over a longer
period of time to promote intergenerational equity.”182 BCSEA does not disagree that
approximately 80% of the forecast balances in F2024 resides in five regulatory
accounts that are being, or will be, recovered over a longer period of time. This is a
matter of benefits matching,183 which BCSEA supports. However, it is not, in
BCSEA’s view as noted above, a matter of intergenerational equity. The present
generation enjoys the benefit of investments made by earlier generations. It is
incumbent on the current generation to pay this forward to future generations.
Intergenerational equity means that the present generation must not defer to future
generations the costs of benefits received by the present generation.
Intergenerational equity does not prevent the present generation deferring to future
generations the costs of benefits that will be received by future generations: that is
benefits matching, which is an accepted accounting principle.
177. Approved recovery mechanisms are in place for all the regulatory accounts
except three, which do not yet require a recovery mechanism.184 BCSEA concurs
with BC Hydro that the approved recovery mechanisms remain appropriate.
178. As stated in paragraph 170, above, BCSEA specifically endorses continuation of
the DSM Regulatory Account. In BCSEA’s view, the current 15-year amortization
period is appropriate for the DSM Regulatory Account, as it is based on evidence of
the weighted average (by GWh and by $) measure life of traditional DSM and low-
carbon electrification initiatives.185
179. The figures for weighted average measure life vary slightly between three
categories: measures in the DSM Regulatory Account at the end of F2021,
measures in the DSM Regulatory Account during the two-year Test Period, and
182
BC Hydro Final Argument, para.432, underline added. BC Hydro also cites intergenerational equity in paras.442 and 443 in support of amortizing the DSM Regulatory Account. 183
The five regulatory accounts in question are listed under the heading “Benefits Matching Accounts” in Table D-2, Exhibit B-19, pdf p.121 and in Table 7-2, Exhibit B-1, p.7-10, pdf p.900. 184
BC Hydro Final Argument, para.433. Recovery mechanism are not in place for the Mining Customer Payment Plan Regulatory Account, Customer Crisis Fund Regulatory Account, and the Site C Regulatory Account. 185
BC Hydro Final Argument, paras.438-440.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 46 of 74
measures over the ten-year period from F2020 to F2029. BCSEA provides a
summary in the table below:
Average Measure Life (years), Traditional DSM Programs and Low-Carbon Electrification
GWh Weighted $ Weighted
DSM RA end of F2019186 14.5 14.0
Test Period F2020-F2021187 17.1 15.0
F2020-F2029188 16.2 15.0
180. BCSEA submits that 15 years is the appropriate amortization period for the DSM
Regulatory Account at the present time, even though the weighted average measure
life for expenditures in the DSM RA at the end of F2019 was slightly below 15 years.
The following reasons support this view.
a. BCSEA agrees with BC Hydro that the weighted average measure life figures
for traditional DSM “are conservative because the calculation equates
persistence to the effective measure life of a DSM initiative and does not
consider that some customers will re-install an efficient measure when the
initial measure has reached its end-of-life, rather than revert to an inefficient
measure.”189
b. BCSEA submits that the evidence of measure life based on the Test Period
and the ten-year period going forward (i.e., F2020-F2029) should carry more
weight than the evidence based on the expenditures in the DSM RA at the
end of F2019.
c. The measure life of LCE initiatives is substantially longer than the measure
life of traditional DSM measures.190 BCSEA expects that LCE expenditures
will ramp up in the coming years at a higher rate than traditional DSM
expenditures. If so, then LCE will form an increasing proportion of the DSM
RA and this will tend to increase the average measure life.
186
Exhibit B-5, BCUC 1.150.5.1, pdf p.1716. 187
Exhibit B-1, Table 10-14, p.10-37, pdf p.1067. 188
Exhibit B-1, Table 10-14, p.10-37, pdf p.1067. 189
BC Hydro Final Argument, para.440. 190
The Low-Carbon Electrification measure life estimates range from 19.8 to 27.8 years: Exhibit B-1, Table 10-14, p.10-37, pdf p.1067; Exhibit B-5, BCUC 1.150.5.1, pdf p.1716.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 47 of 74
d. Stability in the amortization period is desirable. Minor differences between the
estimated measure life and the amortization period, whether higher or lower,
do not justify changing the amortization period.
181. BCSEA agrees with BC Hydro that the amortization period for the DSM
Regulatory Account should not be shortened, e.g., to ten years from the current 15
years.191 However, BCSEA disagrees that this position is supported by
intergenerational equity. BCSEA’s position is based on the benefits matching
principle. Intergenerational equity is not a synonym for benefits matching. Future
generations do not owe us anything. We owe previous generations for making the
investments from which we are now benefiting.
182. Regarding the Non-Current Pension Costs Regulatory Account, BCSEA agrees
with BC Hydro that 13 years is the appropriate amortization period based on the
evidence. BCSEA accepts BC Hydro’s argument that accounting standards
precluded BC Hydro from recognizing the impact of changes in legislation relating to
B.C.’s Medical Services Plan before the required legislation had been passed.192
183. BCSEA agrees with BC Hydro’s summary argument that cost control measures
are in place for deferred controllable costs.193
G. BC HYDRO’S PROPOSED CHANGES TO REGULATORY ACCOUNTS
184. BCSEA supports BC Hydro proposals to:
a. reduce the DARR from 5% to 0% on April 1, 2019; and
b. refund over the Test Period the F2019 net closing balance, the forecast
F2020 and F2021 net additions, and net interest regarding the Cost of Energy
Variance Accounts.194
185. Based on the Evidentiary Update, these proposals result in a refund to the benefit
of ratepayers during the Test Period of approximately $630.8 million.195 BCSEA
considers this to be consistent with benefits matching and reducing upward pressure
on rates. In terms of intergenerational equity, to the extent that the Rate Smoothing
Regulatory Account deferred to future customers the costs of providing service to
191
BC Hydro Final Argument, para.443. 192
BC Hydro Final Argument, paras.444-445. 193
BC Hydro Final Argument, para.447. 194
BC Hydro Final Argument, para.449. 195
Exhibit B-17, Zone II RPG 3.60.1, pdf p.596.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 48 of 74
previous customers, the transfer of the $2.2 billion from BC Hydro to the Government
has the effect of transferring the intergenerational equity problem from ratepayers to
taxpayers. BCSEA is not suggesting that anything should be done differently at this
point.
186. BCSEA supports BC Hydro’s proposal to refund most of the approximately
$630.8 million in F2021. This avoids retroactively adjusting the interim F2020 rates,
and hence avoids a potential source of customer confusion.196
187. BCSEA supports BC Hydro’s proposal to return the net credit balance in the Cost
of Energy Variance Accounts to ratepayers during the Test Period. BCSEA agrees
with BC Hydro’s rationale that the one-time accounting adjustment of $319 million
related to the recognition of revenues under the Skagit River Agreement means that
previous ratepayers have overpaid.197 However, BCSEA characterizes this an
instance of benefits matching, not intergenerational equity.
188. BCSEA supports BC Hydro’s proposal to defer variances related to electricity
purchase agreements (EPAs) that are leases under IFRS 16 to the Non-Heritage
Deferral Account.
189. BCSEA generally supports BC Hydro’s proposal to defer variances between
forecast and actual amounts related to the Biomass Energy Program to the Non-
Heritage Deferral Account.198 For the record, however, BCSEA opposes BC Hydro
recovering from customers its costs of acquiring non-clean or renewable power
generated from contaminated rail ties pursuant to the EPA between BC Hydro and
Atlantic Power. BCSEA acknowledges that Order in Council No. 158/2019 requires
the BCUC to allow BC Hydro to recover the costs associated with the Biomass
Energy Program.
190. BCSEA supports BC Hydro’s proposal to continue to defer to the Dismantling
Cost Regulatory Account, on an annual and ongoing basis, any variances between
forecast and actual dismantling costs.199
196
BC Hydro Final Argument, para.450. 197
BC Hydro Final Argument, para.451. 198
BC Hydro Final Argument, para.459. 199
Exhibit B-6, CEC 1.71.1, pdf p.1474; BC Hydro Final Argument, para.460.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 49 of 74
H. FORECAST FOR REAL PROPERTY SALES
191. BCSEA accepts BC Hydro evidence regarding the reasonableness of BC Hydro’s
forecast of real property sales for the Test Period.200
I. CONCLUSION AND REQUESTED FINDING
192. BCSEA does not agree with BC Hydro’s use of the term “intergenerational equity”
as a synonym for the benefits matching principle. However, BCSEA supports a
finding that BC Hydro’s current use of regulatory accounts, its proposals to close and
modify some of them, and its forecasted additions, are just and reasonable.
PART NINE: OTHER REVENUE REQUIREMENTS ITEMS
A. INTRODUCTION
193. This Part addresses depreciation rates, finance charges and return on equity.
B. TEST PERIOD REVENUE REQUIREMENTS, DEPRECIATION RATES
194. BCSEA agrees that BC Hydro’s depreciation rates are appropriate for setting
rates in the Test Period.201 BC Hydro has said it will conduct a depreciation study in
the near future. In BCSEA’s view, BC Hydro should not be faulted for not prioritizing
a new comprehensive depreciation study until now.202
C. FORECAST FINANCE CHARGES
195. BCSEA accepts that the forecast finance charges in the Evidentiary Update are
reasonable for the purposes of setting rates during the Test Period.203
196. In the 2016 proceeding leading to Decision and Order G-42-16, BCSEA
supported the proposed Debt Management Regulatory Account and BC Hydro’s
Debt Management Strategy to use Future Debt Hedges. BCSEA accepts that the
purpose of the hedging strategy is to lock in a rate, rather than to make a profit.
200
BC Hydro Final Argument, paras.466-472. 201
BC Hydro Final Argument, paras.476-482. 202
BC Hydro Vice-President and Chief Financial Officer David Wong provides useful explanation of industry practice regarding depreciation studies for capital intensive utilities like BC Hydro at Transcript Vol.5, p.445 line 3 to p.446 line 16. 203
BC Hydro Final Argument, para.483.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 50 of 74
D. INTERGROUP’S RECOMMENDATIONS REGARDING BC HYDRO’S FUTURE RETURN ON EQUITY
197. BC Hydro’s return on equity is fixed for the Test Period. BC Hydro will apply to
the Commission for approval of a return on equity that will be applicable after the
Test Period. In BCSEA’s view, it would be premature for the Current Panel to
address the content of the future determination of BC Hydro’s future return on equity.
E. CONCLUSION AND REQUESTED FINDINGS
198. In BCSEA’s view, the Commission should find that BC Hydro’s depreciation rates
and forecast finance charges are reasonable for the Test Period.
PART TEN: TRANSMISSION REVENUE REQUIREMENTS
A. INTRODUCTION
199. The Transmission Revenue Requirements include the costs of the transmission
lines and high-voltage station equipment that provide transmission service under BC
Hydro’s Open Access Transmission Tariff (OATT). BC Hydro says its updated OATT
rates are just and reasonable and should be approved.
B. TRR AND OATT RATES
200. BCSEA has no reason to disagree with BC Hydro’s position that the
Transmission Revenue Requirements and OATT rates reflect established cost of
service methodology based on cost causation and rate design approved by the
Commission in past proceedings.204
C. THE OATT RATE DESIGN
201. BCSEA has reviewed BC Hydro’s informative history of the development of the
electricity industry and markets within the Western Interconnection, and the approval
and evolution of BC Hydro’s Open Access Transmission Tariff (OATT) to meet
evolving needs for access to the wholesale transmission grid and in particular the
requirements of the U.S. Federal Energy Regulatory Commission (FERC).205
204
BC Hydro Final Argument, para.494. 205
Exhibit B-31, Panel 2.8.5, 2.8.5.1, 2.8.5.2, 2.8.6, pdf pp.61-79. And, BC Hydro Final Argument, paras.498-501.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 51 of 74
202. As BC Hydro states:
“BC Hydro continues to monitor market evolution and FERC Orders and make applications to amend its OATT that it believes are appropriate in British Columbia. Such applications also keep the [BC Hydro] OATT aligned with the FERC pro forma OATT which allows Powerex to demonstrate to FERC that its comparability requirements are being met, which in turn allows Powerex to maintain its access to markets in the U.S. in order to generate Trade Income for the benefit of BC Hydro’s ratepayers.
BC Hydro is currently developing its response to three recent FERC Orders, including engagement with transmission customers and interested parties.”206
203. BCSEA agrees with BC Hydro that the BC Hydro OATT rate design remains
valid, and notes that BC Hydro is not requesting any determination in this proceeding
regarding the design of the OATT.207
D. CONCLUSION AND REQUESTED FINDINGS
204. BCSEA considers that the Test Period OATT rates as filed208 are just and
reasonable and should be approved.
PART ELEVEN: DEMAND-SIDE MANAGEMENT
A. INTRODUCTION
205. This Part addresses both BC Hydro’s traditional Demand-Side Management
(DSM) expenditures and its low-carbon electrification (LCE) expenditures on
undertakings defined in section 4 (3) (a), (b), (c) or (d) of the GGRR, both of which
are the subject of Chapter 10 of the Application.
206. In this proceeding, BC Hydro seeks Commission acceptance of a traditional DSM
Expenditure Schedule for the Test Period under s.44.2 of the UCA. The expenditure
schedule is for $90.8 million in F2020 and $89.1 million in F2021.209 The DSM
Expenditure Schedule reflects the first two fiscal years of the three-fiscal-year DSM
Plan in Appendix X of the Application.
206
Exhibit B-31, Panel 2.8.5.1, pdf p.68. 207
BC Hydro Final Argument, para.497. 208
Exhibit B-11-2, Appendix E. 209
Exhibit B-11, Evidentiary Update, p.7, pdf p.12.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 52 of 74
207. Regarding the budgeted expenditures for LCE Projects/Program during the Test
Period, BCSEA agrees with BC Hydro that these expenditures are exempt from
rejection by the Commission by virtue of the GGRR and section 18 of the CEA. BC
Hydro also requests approval to defer its LCE expenditures over the Test Period to
the DSM Regulatory Account, pursuant to the Direction to the BCUC Respecting
Undertaking Costs. These points are discussed below.
208. BCSEA supports a determination by the Panel that the traditional DSM
expenditure schedule for the Test Period is in the public interest, and that BC
Hydro’s LCE expenditures should be deferred to the DSM Regulatory Account.
209. Assuming the traditional DSM Expenditure Schedule for the Test Period is
accepted by the Commission, BCSEA is unsure whether BC Hydro requires the
Commission’s approval to record the DSM costs in the DSM Regulatory Account.
The Panel in the Previous RRA Decision noted that “pursuant to Direction No. 7 BC
Hydro’s development, implementation and administration costs for DSM are
recorded in the DSM Regulatory Account and amortized over 15 years.” However,
Direction No. 7 has since been repealed.210 If Commission approval is indeed
required, and if the traditional DSM Expenditure Schedule for the Test Period is
accepted (which BCSEA supports), then BCSEA supports approval of the costs
being recorded in the DSM Regulatory and (as argued below) being amortized over
15 years.
210. BCSEA is satisfied with BC Hydro’s explanation of why DSM is located with the
People, Customer and Corporate Affairs Business Group rather than the Integrated
Planning Business Group.211
B. MODERATION APPROACH, ENERGY SURPLUS
211. The spending envelope in the DSM Expenditure Schedule for the Test Period
roughly continues the “moderation approach” in the F2017-F2019 DSM Expenditure
Schedule accepted by the Commission.212
212. BC Hydro’s traditional DSM portfolio expenditures, planned and actual, excluding
expenditures on the Thermo-Mechanical Pulp Program (TMP), are shown in the
following table:
210
B.C. Reg. 28/2014, repealed by B.C. Reg. 24/2019, effective February 14, 2019. 211
Exhibit B-6, BCSEA 1.1.1, pdf p.616. 212
Decision and Order G-47-18, p.78, pdf p.85.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 53 of 74
Traditional DSM Portfolio Expenditures, Plan and Actual, excluding TMP213
$million Plan Actual
F2017 113.7 97.3
F2018 104.8 84.2
F2019 100.7 76.4
F2020 Test Period 90.8 TBD
F2021 Test Period 89.1 TBD
F2022214 85.5 TBD
213. BCSEA would strongly prefer a more ambitious traditional DSM spending
envelope, and a more ambitious amount of energy and capacity savings, in the Test
Period. In BCSEA’s view, the amount of low-carbon electrification needed for B.C. to
meet its legislated GHG reduction targets under the CleanBC Plan will put BC Hydro
into an energy and capacity deficit planning position sooner rather than later. BC
Hydro will then require all cost-effective traditional DSM savings. Despite BC Hydro’s
assurances, BCSEA is concerned that the “moderation approach” jeopardizes BC
Hydro’s ability to ramp up conservation and efficiency savings when they become
urgently needed. In addition, BCSEA is concerned that the decision not to achieve all
cost-effective energy and capacity savings during the Test Period will create “lost
opportunities” by allowing inefficient assets to be locked-in for the long term.
214. BCSEA acknowledges that BC Hydro currently has surplus energy and capacity
for planning purposes.215 In this context, the market price screening filter ensures
that the traditional DSM activities during the Test Period put downward pressure on
rates.
215. BCSEA acknowledges that the BC Government has expressed support for BC
Hydro maintaining its traditional DSM spending at the same level overall.216
216. BCSEA disagrees that the proposed level of traditional DSM spending in the Test
Period is supported by the B.C. energy objective “of the authority reducing its
expected increase in demand for electricity by the year 2020 by at least 66%.”217 BC
Hydro achieved the 66% reduction target several years ago, and in any event the
66% target is a floor not a ceiling.
213
Exhibit B-13, BCSEA 2.63.1, pdf p.478. 214
Exhibit B-1, Appendix X, Table 2, p.7, pdf p.2147. 215
BC Hydro Final Argument, para.509. 216
BC Hydro Final Argument, para.510. 217
BC Hydro Final Argument, para.511, underline added.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 54 of 74
217. As noted above, BCSEA is not convinced by BC Hydro’s assurance that it retains
the ability to ramp up traditional DSM activities in the future in response to the 2021
IRP or the CleanBC Plan.218
C. BC HYDRO’S TRADITIONAL DSM PLAN, BCUC DIRECTIVES, GOVERNMENT PRIORITIES, AND DSM REGULATION
(a) Increased Residential DSM, decreased Commercial and Industrial DSM
218. BC Hydro’s traditional DSM expenditure schedule for the Test Period increases
the spending on programs aimed at Residential customers and decreases the
spending on programs aimed at Commercial/Light Industrial customers. Program
spending aimed at Large Industrial customers remains more or less flat.
219. BCSEA provides the following table showing DSM Programs Expenditures,
without TMP. It can be observed that Residential DSM spending in the Test Period is
higher than in the Previous Test Period (F2017 to F2019). Commercial DSM
spending in the Test Period is below the levels in the Previous Test Period (and
Commercial DSM spending declined substantially over the course of the Previous
Test Period). Industrial DSM spending in the Test Period is about the same as in
F2019 (and rose during the Previous Test Period).
DSM Programs Expenditures, Actual/Forecast, without TMP219
$ millions F2017 F2018 F2019 F2020 F2021 F2022220
Residential 12.5 11.8 14.3 18.4 19.7 21.0
Commercial 34.5 24.7 21.2 18.9 17.5 17.2
Industrial 23.0 22.4 26.8 26.5 26.9 26.3
Total Programs w/o TMP
70.0 58.9 62.3 63.8 64.1 64.5
220. BCSEA supports increasing the Residential component of the DSM spending,
although BCSEA would have preferred that this be accomplished by increasing the
DSM envelope rather than by decreasing DSM spending aimed at Commercial/Light
Industrial customers.
221. The percentage split in traditional DSM program spending in the Test Period is
30%, 38% and 32% for Residential, Commercial/Light Industrial and Large Industrial,
218
BC Hydro Final Argument, para.512. 219
Exhibit B-6, Gjoshe 1.14.2, pdf p.1627. 220
Data in this column is from Exhibit B-1, Appendix X, Table 6, p.16, pdf p.2156.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 55 of 74
respectively. This is a significant change from the previous period (F2017-F2019), as
shown in the table below:
Traditional DSM Program Spend by Sector (excluding TMP)221
Residential incl. Low Income %
Commercial/Light Industrial %
Large Industrial %
Total %
F2017-F2018 Actual and F2019 Forecast
19 57 24 100
F2020-F2021 Forecast
30 38 32 100
222. The readjustment of traditional DSM program spending between customer
categories is consistent with the Commission Panel’s recommendation in Decision
and Order G-47-18 that BC Hydro consider more targeted DSM programs directed at
residential customers in the next DSM application.222 The Panel gave three reasons
for this recommendation:
“The Panel notes the relatively low level of DSM spending for residential customers (including low-income customers), despite DSM program utility costs that are comparable to those of BC Hydro’s commercial DSM programs.
The Panel further notes BC Hydro’s proposed 39 percent decrease in funding for non-low-income residential programs in this Application.
The Panel also notes that residential customers are allocated 40 percent of DSM program costs, but do not receive a comparable share of the DSM program funding.”223
221
Exhibit B-1, Table 10-4, p.10-8, pdf p.1038. 222
Decision and Order G-47-18, p.81, pdf p.88, and p.116, pdf p.123. 223
Decision and Order G-47-18, p.81, pdf p.88, bullets added for clarity.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 56 of 74
223. BCSEA supports the Low-Income Program. The DSM expenditure schedule for
the Test Period expands spending on the Low-Income Program.224 Spending and
energy savings under the Low-Income Program continue to follow an upward track,
as shown in the following table.
Low-Income DSM Program, Program Expenditures and Energy Savings by Year225
F2016 Actual
F2017 Actual
F2018 Actual
F2019 Plan
F2020 Plan Test
Period
F2021 Plan Test
Period
F2022 Plan
Program Expenditures $million
$2.4 $2.9 $3.5 $3.8 $5.8 $6.9 $7.8
Energy Savings GWh/y
4.8 4.5 5.7 6.2 8.9 8.8 9.3
224. The Low-Income Program contains three sub-components: Energy Savings Kits,
Energy Conservation Assistance Program, and a new Indigenous Customers Offer
for customers connected to the Integrated system. Participation in each component
continues to increase, as shown in the following table.
Low-Income DSM Program, Participation226
F2016 Actual
F2017 Actual
F2018 Actual
F2019 Plan
F2020 Plan Test
Period
F2021 Plan Test
Period
F2022 Plan
Energy Savings Kits 10,563 10,611 13,489 16,000 22,250 22,800 22,800
Energy Conservation Savings Program
2,764 2,836 3,600 3,040 3,905 4,360 4,495
Indigenous Customers Offer
0 0 0 0 70 150 315
Total 13,327 13,447 17,089 19,040 26,225 27,310 27,610
225. The Home Renovation Rebate Program focuses on customers with electric heat,
who typically have high electric bills as heating is normally 50% of a home’s energy
consumption.227 BCSEA supports BC Hydro’s measures to increase participation in
the Home Renovation Rebate Program228 through additional measures such as heat
pumps and smart thermostats, and increased incentives.229 BCSEA asked about the
224
Exhibit B-1, Appendix X, p.14, pdf p.2154. 225
Exhibit B-6, BCSEA 1.44.1, pdf p.799. As of May 2, 2019. 226
Exhibit B-6, BCSEA 1.44.1, pdf p.799. As of May 2, 2019. 227
Exhibit B-1, Appendix X, p.33, pdf p.2173. 228
Exhibit B-6, BCSEA 1.43.2.2, pdf p.787. 229
Exhibit B-6, BCSEA 1.43.2.1, pdf p.785.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 57 of 74
details of these improvements, including the specific measures, incentive level,
anticipated participation, and eligibility criteria.230 BCSEA is satisfied with BC Hydro’s
fulsome responses.
226. As the Home Renovation Rebate Program focuses on customers with electric
heat, BCSEA asked whether incentives are available for customers who are fuel-
switching from higher-carbon heating equipment (such as oil or natural gas). BCSEA
is satisfied with BC Hydro’s response that:
“BC Hydro does not offer heat pump incentives for residential customers who are fuel-switching from higher-carbon producing heating equipment because the Province of British Columbia already provides heat pump incentives for fuel switching through the CleanBC Better Buildings Program. BC Hydro administers these incentives on behalf of the Government of B.C. ... BC Hydro funded programs are designed to align with, and not overlap with, government funded programs.”231
(b) Social Housing DSM
227. Within the Commercial program area, in F2019 BC Hydro launched an initiative
aimed at providers of social housing, such as BC Housing, and the B.C. Non-Profit
Housing Authority. BCSEA supports this initiative, called the “Social Housing Retrofit
Support Offer for Multi-Unit Residential Buildings.” BCSEA has supported increased
coordination on DSM between BC’s energy utilities, and notes with approval that the
offer is a partnership between FortisBC Energy Inc., FortisBC Inc., BC Hydro and the
Government of B.C. (through Efficiency B.C.)232
228. The Social Housing Offer includes four measures:
Energy study funding to review the potential energy conservation measures;
Implementation support that provides engineering design, tendering and project management;
Rebates for upgrading eligible technologies for lighting, HVAC and commercial kitchen; and,
Rebates for low-carbon electrification opportunities.233
230
Exhibit B-6, BCSEA 1.43.2.1, 1.43.2.2, 1.43.2.3., 1.43.2.4, 1.43.3.5 and 1.46.1. 231
Exhibit B-6, BCSEA 1.43.2.6, pdf p.795. And see: Exhibit B-6, BCSEA 1.46.1, pdf p.803. 232 Exhibit B-1, Appendix X, p.45, pdf p.2185. “Efficiency B.C.” is now branded CleanBC Better
Homes for residential programs and CleanBC Better Buildings for commercial buildings: Exhibit B-31, Panel 2.18.2, Attachment 1, p.6, pdf p.192. 233
Exhibit B-1, Appendix X, p.45, pdf p.2185.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 58 of 74
229. BCSEA is satisfied with BC Hydro’s detailed description of the proposed F2020-
F2021 DSM incentives for social housing providers for existing buildings and new
construction.234
(c) Non-Integrated Areas DSM
230. BCSEA supports BC Hydro’s increased DSM activities in Non-Integrated
Areas.235
231. The non-integrated communities have been described as remote and heavily
reliant on electricity for heating, with many homes having poor construction and old
appliances.236 In the previous test period (F2017-F2019), BC Hydro was working with
First Nations and remote communities to trial a number of different approaches to
addressing barriers to DSM and energy efficiency upgrades (i.e. delivery of the
programs). At that time, BC Hydro did not track DSM spending in NIAs.237
232. The Commission Panel in the Previous RRA Decision noted with approval the
significant increase in DSM funding levels in the NIAs since F2016, and implied that
additional DSM expenditures in the NIAs might be justified considering the high
avoided cost of diesel. The Panel states:
“However, requested DSM funding levels as a percentage of revenues in the NIA over the test period are still are estimated to be similar to that of the integrated area, despite the unique market barriers of the NIA communities (including affordability), the significantly higher utility avoided fuel cost (six times higher than BC Hydro’s screening filter), and additional emissions reduction benefits.”238
233. The Panel in the Previous Decision directed BC Hydro to track its DSM spending
in the NIAs and to report on how it has addressed the DSM concerns raised by the
Non Integrated Areas Ratepayers Group and the Zone II Ratepayers Group.239
234. BC Hydro responded positively, in BCSEA’s view. BC Hydro has a new NIA DSM
program in the F2020-F2022 DSM Plan. It says this “is a comprehensive program
that builds on the pilot work conducted to explore delivery approaches and efficiency
234
Exhibit B-17, BCSEA 3.35.2, pdf p.395. 235
BC Hydro Final Argument, para.523. 236
Decision and Order G-47-18, p.82, pdf p.89. 237
Decision and Order G-47-18, p.82, pdf p.89. 238
Decision and Order G-47-18, p.84, pdf p.91. 239
Decision and Order G-47-18, p.84, pdf p.91.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 59 of 74
measures tailored for the NIA.”240 The NIA program includes new residential and
commercial program offers. It also includes “Community Support,” which provides
“financial and technical resources to Indigenous communities in Non-Integrated
Areas to support them in pursuing energy upgrades.”241
235. The following table shows the NIA DSM program expenditures as planned.
Non-Integrated Areas DSM Program Expenditures242
F2020 Plan Test Period
F2021 Plan Test Period
F2022 Plan
$million 1.2 1.4 1.5
236. The cost effectiveness of the NIA program benefits from a higher avoided cost of
energy due to the cost of diesel generation in the NIA communities. As a result, the
NIA program has a positive benefit cost ratio, even without the 40% adder under the
DSM Regulation.243
237. BCSEA asked for an explanation of how the NIA DSM program will ensure that
the training it provides will be sufficient to allow local contractors to effectively install
“deeper measures such as windows and doors, insulation, advanced air sealing,
ventilation systems, heat pumps and programmable thermostats,” given that the
savings that will result from such measures will be highly dependent on quality
installation practices. BCSEA is satisfied with BC Hydro’s detailed response.244
(d) Codes and Standards savings
238. Regarding the presentation of codes and standards savings, the Panel in the
Previous RRA Decision directed BC Hydro to review whether attributing all of the
savings occurring from the implementation of codes and standards to the utility’s
DSM codes and standards program is consistent with industry practice.245 BC Hydro
retained a third party expert, the Cadmus Group, which reported that industry
practice regarding codes and standards attribution is varied.
240
BC Hydro Final Argument, para.524. 241
Exhibit B-6, Zone II RPG 1.26.8, cited in BC Hydro Final Argument, para.524. 242
Exhibit B-1, Appendix X, p.36, pdf p.2176. 243
BC Hydro Final Argument, para.526. Demand-Side Measures Regulation, BC Reg. 326/2008, under the Utilities Commission Act. 244
Exhibit B-6, BCSEA 1.47.1, pdf pp.804-805. 245
Decision and Order G-47-18, p.82, pdf p.89.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 60 of 74
239. Based on the Cadmus Group’s report, BC Hydro introduced the following
changes:
a. codes and standards savings are excluded from benefit cost calculations and
levelized costs;
b. codes and standards savings are presented as a stand-alone bucket of
energy and associated capacity savings, and are not attributed to individual
programs; and,
c. a forecast of codes and standards savings is provided and incorporated into
BC Hydro’s Load Forecast.246
240. BCSEA supports these changes, which are consistent with the approach taken in
Ontario and Manitoba. As BC Hydro says, “This ensures that there is no distortion to
the cost-effectiveness results of the traditional DSM programs.” BCSEA agrees with
BC Hydro’s comment as follows:
“As BC Hydro’s codes and standards expenditures are still included at the portfolio level, the result is that the cost effectiveness of the DSM portfolio is more conservative than if the codes and standards savings were included. However, all of BC Hydro’s traditional DSM initiatives are cost-effective without any attribution from codes and standards.”247
(e) Capacity-focused DSM
241. BCSEA supports BC Hydro’s pilots and trial offers focused on shifting the timing
of peak demand in areas where BC Hydro faces capacity constraints.248 The
constrained substations where BC Hydro plans to test different capacity focused
solutions are Pineview, Hope and Kent.249 BC Hydro says it expects work from its
capacity focused DSM initiatives to inform the next Integrated Resource Plan.250 And,
BC Hydro is developing a DSM non-wires evaluation framework for planners to use
in identifying options for feeder reinforcement.251
242. BC Hydro describes “success” regarding its capacity-focused DSM pilots in the
following terms:
246
Exhibit B-1, p.10-10, pdf p.1040. 247
BC Hydro Final Argument, para.533, underline added. 248
Exhibit B-1, p.10-21, pdf p.1051. 249
Exhibit B-6, BCSEA 1.39.1, pdf p.758. 250
Exhibit B-6, BCSEA 1.38.2, pdf p.755. 251
Transcript Vol.12, p.2269 line 1 to p.2272 line 10; Transcript Vol.13, p.2395, line 22 to p.2395, line 5; Transcript Vol.14, p.2630, line 17 to p.2633, line 16.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 61 of 74
“Success with each capacity-focused DSM trial or pilot will be in the learning gained with regards to the capability to reliably shift and/or reduce load. This information will help to inform our ability to bundle capacity focused initiatives to defer upgrades at the local level or as resource options to inform the next Integrated Resource Plan.
Beyond the trial or pilot stage, the success of capacity focused initiatives will be based on the ability to reliably shift or reduce loads at a lower cost than supply side resources and infrastructure.”252
243. BCSEA supports BC Hydro’s proposal to extend the funding period for capacity
focused DSM initiatives.253 The dollar amounts and the corresponding fiscal years
are set out in Table 10-9 in the Application.254 BC Hydro describes the extension of
the funding period as follows:
“In the Previous Application, BC Hydro proposed a total budget of $38.6 million for these initiatives from fiscal 2017 to fiscal 2019. This DSM Plan
extends that budget to fiscal 2021 but reduces the overall total by 12 per cent to $34 million.”255
244. BCSEA accepts BC Hydro’s explanation that extending the time period is
desirable “due to the complexity of assessing the impacts and value of capacity-
focused DSM to BC Hydro’s system,” and to provide “more time to incorporate past
learnings into new activities, consider changing technologies and accommodate the
long lead times required for some customer projects.”256
245. Regarding the 12% reduction in capacity-focused DSM spending, BC Hydro’s
evidence is that the reduced budget will not impact its ability to test and analyze
opportunities. BC Hydro says, “The budget reflects the expenditures needed to
implement our capacity-focused DSM activities and is not constraining BC Hydro
during the test period.”257 BC Hydro states:
“Within this proposed budget, BC Hydro will continue to conduct demand response trials in the residential, commercial and industrial sectors. BC Hydro plans to test different solutions in a number of constrained substation areas. The objective of these tests will be to determine whether the combination of demand response activities and targeted energy
252
Exhibit B-6, BCSEA 1.39.4, pdf p.765. 253
BC Hydro Final Argument, para.534. 254
Exhibit B-1, p.10-22, pdf p.1052. 255
Exhibit B-1, p.10-21, pdf p.1051. 256
Exhibit B-1, p.10-22, pdf p.1052. A detailed rationale for the extension is provided in Exhibit B-5, BCUC 1.183.2, pdf p.2042; and Exhibit B-6, Willis 1.12.1, pdf p.2069. 257
Exhibit B-6, BCSEA 1.39.5.1, pdf p.769.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 62 of 74
efficiency offers can shift the timing of peak demand in a constrained local area.”258
246. Again, BCSEA supports the capacity-focused DSM initiative.
(f) Energy Management Activities
247. BCSEA has no objection to BC Hydro’s re-categorization of its existing energy
management activities into a new program, called Energy Management Activities,
within each sector. As BC Hydro explains, “The change aligns with 2017
amendments to the DSM Regulation that added ‘Energy Management Program’
(meaning a program to assist customers to optimize energy use) to the definition of
‘Specified Demand Side Measure’.”259
D. DIRECTIVE 61 REGARDING ALLOCATION OF PORTFOLIO COSTS, RESCISSION
248. BCSEA supports BC Hydro’s request that the BCUC rescind Directive 61 from its
October 2004 Decision on BC Hydro’s Fiscal 2005 to Fiscal 2006 Revenue
Requirements Application.260 Directive 61 requires portfolio level costs to be
allocated to programs.261
249. BCSEA’s view is that costs should only be attributed to programs if they are
solely connected to a specific program.
250. The DSM Regulation, adopted in 2008 after the issuance of Directive 61 in 2004,
contemplates that costs will be attributed to a program only if they are solely
connected to that program.
251. Current industry practice, as expressed in the National Standard Practice Manual
in 2017, is that “fixed portfolio-level costs should not be allocated to programs for the
purpose of assessing the cost-effectiveness of individual programs.”262
252. Decisions on individual programs should be based entirely on the merits of the
program itself. Portfolio-level costs should be considered only when looking at the
cost effectiveness of the overall portfolio, not the cost effectiveness of individual
programs. Including portfolio-level costs in the evaluation of a program could shift the
258
Exhibit B-1, p.10-22, pdf p.1052. 259
BC Hydro Final Argument, para.536. 260
Decision and Order No. G-96-04. 261
BC Hydro Final Argument, para.537. 262
National Standard Practice Manual, May 2017, cited in Exhibit B-5, BCUC 1.172.1, pdf p.1957.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 63 of 74
result from a net benefit to a net cost, which could lead to a program with a net
benefit not being implemented.263
E. TRADITIONAL DSM, UCA, CLEAN ENERGY ACT, AND DSM REGULATION
253. In determining whether to accept the traditional DSM Expenditure Schedule for
the Test Period, section 44.2(5.1) of the UCA requires the BCUC to consider:
a. the interests of persons in B.C. who receive or may receive service from BC
Hydro,
b. B.C.’s energy objectives,
c. the 2013 IRP,264
d. the B.C. energy objective to generate at least 93% of the electricity in British
Columbia from clean or renewable resources and to build the infrastructure
necessary to transmit that electricity, and
e. the extent to which the demand-side measures are cost-effective as defined
in the DSM Regulation.
254. Regarding the extent of the Commission’s discretion in relation to a DSM
expenditure schedule, section 44.2(3) of the UCA provides that the Commission
must accept a schedule if the commission considers that making the expenditures
referred to in the schedule would be in the public interest, or reject the schedule.
Section 44.2(4) provides that the commission may accept or reject, under subsection
(3), a part of a schedule. The Commission does not have authority to direct a utility to
file a DSM expenditure schedule, to make additions to a DSM expenditure schedule,
or to change the design of a particular program.265 However, the Commission has
authority to reject a DSM expenditure schedule, in whole or in part, for stated
reasons that the utility may consider in proposing a modified DSM expenditure
schedule.
263
Exhibit B-1, pp.1034-1035, pdf pp.1064-1065. 264
Section 44.2(5.2)(b) requires the Commission to consider “the most recent of the following documents: (i) an integrated resource plan approved under section 4 of the Clean Energy Act before the repeal of that section; (ii) a long-term resource plan filed by the authority under section 44.1 of this Act.” The 2013 IRP approved by the Government under the CEA is the most recent. Moreover, BC Hydro’s 2008 Long-Term Acquisition Plan, filed under section 44.1 and 44.2 of the UCA, was rejected by the BCUC in Decision and Order G-91-09. 265
Decision and Order G-47-18, p.73, pdf p.80.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 64 of 74
255. BCSEA agrees with BC Hydro that the traditional DSM Expenditure Schedule for
the Test Period is in the interests of persons in British Columbia who receive or may
receive service from BC Hydro.266
256. More broadly, the DSM Expenditures Schedule can be expected to generate
considerable economic impacts. For example, a 2017 study by the Deetken Group
for BC Hydro concluded that the DSM Plan is expected to generate the following
economic impacts from F2017 to F2026:
“• GDP impacts of $1.9B
• Employment of 23,300 FTEs
• Provincial tax revenue of $213M.”267
257. BCSEA agrees that the traditional DSM Expenditure Schedule for the Test Period
fosters the B.C. energy objective “to take demand-side measures and to conserve
energy.”268 However, as stated in paragraph 216, BCSEA submits that it cannot be
concluded that the DSM Expenditure Schedule for the Test Period fosters “the
objective of [BC Hydro] reducing its expected increase in demand for electricity by
the year 2020 by at least 66%,”269 because that particular objective has already been
met.
258. BCSEA disagrees with BC Hydro that the traditional DSM Expenditure Schedule
for the Test Period is “consistent with the 2013 IRP.”270 BC Hydro characterizes the
F2020-F2021 DSM spending as a continuation of the F2017-F2019 spending.
However, F2017-F2019 DSM Expenditure Schedule was a reduction in DSM
spending compared to the 2013 IRP. The Panel in the Previous RRA Decision
states, “The Panel also considered in its deliberations the Minister’s letter supporting
BC Hydro’s reduction in DSM spending compared to the 2013 IRP...”271 The Panel
chose to accept the F2017-F2019 DSM Expenditure Schedule, but it did not
conclude that the F2017-F2019 DSM spending was consistent with the 2013 IRP.
259. BCSEA agrees with BC Hydro that the “[traditional DSM] portfolio as a whole, as
well as rate structures and all programs, are cost effective using the modified total
266
BC Hydro Final Argument, para.541. 267
Exhibit B-6, Ince IR 1.12.15 Attachment 1, p.2, pdf p.1941. 268
BC Hydro Final Argument, para.543. 269
BC Hydro calculates the 66% reduction measure using F2008 as the base year and F2021 as an approximation of 2020. Exhibit B-5, BCUC 1.173.1, pdf p.1963. 270
BC Hydro Final Argument, para.544. 271
Decision and Order G-47-18, p.79, pdf p.86, underline added.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 65 of 74
resource cost test required by the DSM Regulation.” BCSEA also agrees that “[t]he
Test Period portfolio as a whole, as well as rate and all programs, also are cost
effective under the more stringent requirements of the total resource cost test
excluding non-energy benefits and utility cost test.”272
260. Under the DSM Regulation, BC Hydro’s long-run marginal cost of clean energy
delivered to the Lower Mainland (LRMC) is an input into the total resource cost test
(TRC). BC Hydro correctly used the most recent LRMC of $105/MWh in calculating
the TRCs of the portfolio and programs. BCSEA agrees that $105/MWh is an
outdated figure for BC Hydro’s LRMC. The next LRMC figure, to be determined in
the upcoming 2021 IRP, is expected to be considerably lower than $105/MWh.
261. At the request of the Commission, BC Hydro back-calculated a hypothetical
LRMC of $52/MWh that would produce TRCs of at least 1.0 for the portfolio and all
the programs of the DSM Expenditure Schedule for the Test Period.273 This
compares favourably to a range between $54/MWh and $80/MWh, which BC Hydro
recently estimated for the cost of new wind power delivered to the Lower
Mainland.274 This hypothetical analysis should allay any potential concern that BC
Hydro is proposing to spend too much on DSM.
262. BCSEA agrees that the traditional DSM Plan for F2020-F2022 would meet the
adequacy requirements of the DSM Regulation, if it was legally subject to those
requirements. The F2020-F2022 DSM Plan is designed to meet the adequacy
requirements, and the details are set out in Table 10-7 of the Application.275
263. The following paragraphs up to paragraph 270 address inter-year and inter-
program transfers of allocations within an accepted traditional DSM expenditure
schedule.
264. BC Hydro’s position is that it “retains discretion to reallocate its DSM costs during
the Test Period, and this ability is important for the company and customers.”276 BC
Hydro states:
“BC Hydro’s interpretation of the Utilities Commission Act is that BC Hydro is permitted to reallocate costs or resources between program areas and years without seeking prior BCUC approval.”277
272
BC Hydro Final Argument, para.545. 273
Exhibit B-12, BCUC 2.274.1, pdf p.719. 274
Exhibit B-5, BCUC 1.175.3, pdf p.1974. 275
Exhibit B-1, p.10-17, pdf p.1047. 276
BC Hydro Final Argument, para.549.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 66 of 74
265. BCSEA notes that the Commission Panel in the 2019 Decision regarding
FortisBC Inc.’s 2019-2022 DSM Plan and Expenditure Schedule states:
“For reasons set out immediately below, the Panel finds that in the absence of explicit approval from the BCUC, BCUC acceptance of FBC’s 2019–2022 DSM as set out in detail in Table 5.1 of the Application does not provide acceptance of any Inter-Year Transfers or Inter-Program Transfers. For greater clarity, this finding is not directed at fettering FBC’s ability to spend DSM funds as it sees fit. Rather, it provides clarity on what expenditures are included in the accepted expenditure schedule for the purpose of recovering those expenditures in rates.”278
266. BCSEA agrees with BC Hydro that it is important for BC Hydro to have the
flexibility to respond to challenges or opportunities in the market. As BC Hydro
states:
“For instance, if an initiative is over-performing or underperforming, then BC Hydro may need to reallocate funds to maintain the overall portfolio performance and portfolio balance. BC Hydro’s spending may also vary from plan due to factors that are fully or in part outside its control, such as the timing of large customer projects or slower than anticipated participation in a program due to economic conditions BC Hydro.”279
267. BCSEA also agrees with BC Hydro that appropriate checks and balances are in
place regarding reallocations made during the test period. These include BC Hydro’s
Financial Approval Authority Policy, and BC Hydro’s annual DSM reports to the
Commission. In addition, BC Hydro acknowledges that “a significant deviation from
the expenditure breakdown shown in the expenditure schedule could result in cost
recovery risk.”280
268. Regarding inter-year transfers, BCSEA’s view is that the exact timing of the
expenditure would not change whether the DSM Expenditure Schedule is still in the
public interest. Regarding both inter-year and inter-program transfers, BCSEA’s view
is that flexibility would reduce the risk of underspending, which has been a concern
of BCSEA in the past.
269. BCSEA supports BC Hydro’s legal position that it retains discretion to implement
inter-year and inter-program transfers within an accepted DSM Expenditure
277
Exhibit B-5, BCUC 1.174.1.1. 278
Decision and Order G-47-19, pp.12-13, bold in the original. 279
Exhibit B-5, BCUC 1.174.1.1, cited in BC Hydro Final Argument, para.550. 280
BC Hydro Final Argument, para.551.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 67 of 74
Schedule for the Test Period, without prior approval by the Commission but subject
to the usual reporting requirements and to cost recovery risk.
270. In the alternative, BCSEA supports Commission approval of flexible rules for
inter-year and inter-program spending transfers regarding BC Hydro’s traditional
DSM Expenditure Schedule for the Test Period. In this respect, consideration should
be given to the approach taken by the Commission in the Decision regarding
FortisBC Inc.’s 2019-2022 DSM Plan and Expenditure Schedule,281 in summary:
a. approval of inter-year transfers within the same program area subject to
reporting in the annual DSM report to the Commission, and
b. approval of transfers of up to 25% of budgeted expenditures from an existing
program area to another existing program area subject to reporting in the
annual DSM report to the Commission.
F. THE EXPENDITURE SCHEDULE EXCLUDES THERMO-MECHANICAL PULP EXPENDITURES
271. BC Hydro amended its proposed expenditure schedule to remove expenditures
on the Thermo-Mechanical Pulp Program, because it is no longer forecasting
expenditures on the TMP Program.
G. LOW CARBON ELECTRIFICATION EXPENDITURES, PRESCRIBED UNDERTAKINGS, COST RECOVERY IS MANDATED
272. This section addresses BC Hydro’s Low-Carbon Electrification expenditures on
undertakings defined in section 4 (3) (a), (b), (c) or (d) of the GGRR, referred to as
“LCE Project/Programs.” This is comprised of “Initial LCE Projects” and “LCE
Program.” BC Hydro’s position, with which BCSEA agrees, is that the “LCE
Project/Programs” are prescribed undertakings under section 4(3)(a) to (d) of the
GGRR and section 18 of the CEA (discussed further, below).
273. To be clear, “LCE Project/Programs” does not include LCE infrastructure
projects, such as the PRES project, that BC Hydro also says, and BCSEA agrees,
are exempt under the GGRR and CEA s.18 (paragraph 130, above).
281
Decision and Order G-47-19, pp.14-16.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 68 of 74
a. One point of distinction is that “LCE infrastructure projects” are undertaken
under section 4(2) or section 4(3)(e) of the GGRR, whereas “LCE
Project/Programs” are undertaken under section 4(3)(a) to (d) of the GGRR.
b. Another point of distinction is that “LCE infrastructure projects” are brought
into the revenue requirement as capital expenditures, whereas “LCE
Project/Programs” are brought into the revenue requirement by being
recorded in the DSM Regulatory Account (discussed in paragraphs 280-287,
below.)
274. In BCSEA’s view, BC Hydro’s budget for low-carbon electrification is far too low.
BCSEA has assembled BC Hydro’s updated figures for LCE Projects/Program in the
table below.282
Expenditures for Initial LCE Projects and for LCE Program
$millions F2018 Actual
F2019 Actual
F2020 Forecast
F2021 Forecast
F2022 Forecast
F2023 Forecast
Total
Initial LCE Projects283
0.21 6.85 13.33 3.38 6.00 29.76
LCE Program284 0.48 4.49 4.36 3.13 4.20 16.66
Total LCE Projects/Program285
45.64
275. BC Hydro has set the following objectives for the LCE expenditures and activities
in the test period:
“Supporting the Government of B.C.’s climate change objectives by helping our customers to reduce their greenhouse gas emissions;
Assisting our customers in pursuing low carbon electrification opportunities that:
o Increase revenue from additional electricity consumption to reduce pressure on rates over the energy surplus period; and
o Reduce their greenhouse gas emissions;
282
This table does not show a test period (with shading), because there is no test period for the LCE Projects/Program expenditures as BC Hydro is not seeking approval of them. 283
Exhibit B-31, Panel 2.18.2, Attachment 1, Table 2-1, pdf p.196. 284
Exhibit B-31, Panel 2.18.2, Attachment 1, Table 3-2, pdf p.199. 285
Exhibit B-31, Panel 2.18.2, Attachment 1, Table 4-1, pdf p.202. The figure for LCE Projects/Program Total doesn’t equal the exact total of Initial LCE Projects Total and LCE Programs Total. Totals by fiscal year are not shown because they are not in the evidence.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 69 of 74
Assessing customer response to our program offers and gaining experience with new technologies to help us understand potential barriers that customers and BC Hydro may face when developing and advancing low carbon electrification alternatives; and
Acting early to capture time-sensitive opportunities.”286
276. BCSEA commends BC Hydro for articulating these important objectives.
However, BCSEA is concerned that the proposed LCE budget for F2020-F2023 is
inadequate to achieve the necessary quantity of electrification.
277. BC Hydro says that it “expects to develop a future plan for low carbon
electrification that is informed by the learning gained through Initial LCE Projects and
the BC Hydro LCE Program as well as Government of B.C.’s CleanBC Plan.”287
BCSEA asked if BC Hydro has assessed the quantity of LCE that it might be called
on to undertake to help achieve the Province’s legislated GHG reduction targets
under the CleanBC plan. Unfortunately, BC Hydro demurred, responding:
“BC Hydro expects that BC Hydro’s role, including its undertakings of Low Carbon Electrification projects and programs, in achieving the reduction targets under the CleanBC plan will be explored through Phase Two of the Comprehensive Review.”288
278. BCSEA encourages BC Hydro to develop a comprehensive long-term plan for
low-carbon electrification measures across all sectors that will meet quantitative
GHG reduction objectives in order to achieve B.C.’s legislated GHG reduction
targets.
279. BCSEA supports BC Hydro’s LCE Projects/Program expenditures that reduce
GHG emissions in B.C. by displacing the use of energy derived from fossil-fuels.289 In
addition, the LCE Projects/Program expenditures are estimated to decrease
cumulative bills in the Test Period by approximately 0.1%.290
280. Regarding cost recovery, BCSEA agrees with BC Hydro’s premise as follows:
“Sections 18(1) to 18(3) of the Clean Energy Act state that the BCUC must set rates to allow BC Hydro to recover the costs of prescribed undertakings, and must not exercise any power that would prevent BC Hydro from carrying out prescribed undertakings. The effect of section 18
286
Exhibit B-6, BCSEA 1.54.1, pdf p.828. 287
Exhibit B-1, p. 10-24, pdf p. 1054. 288
Exhibit B-6, BCSEA 1.54.2, pdf p.830. 289
BCSEA notes that the impact on global GHG emissions due to the export of natural gas from B.C. is debatable and is beyond the scope of this Argument. 290
Exhibit B-31, Panel 2.18.3, pdf p.207.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 70 of 74
of the Clean Energy Act is that the BCUC need only consider whether the LCE expenditures are prescribed undertakings as described in the GGRR. If the BCUC concludes that they are, then it must approve rates to allow BC Hydro to collect sufficient revenue to recover the costs of the prescribed undertakings.”291
281. BCSEA concurs with BC Hydro that there are two broad requirements for the
LCE expenditures to fall within the class of prescribed undertakings in sections
4(3)(a) to (d) of the GGRR:
“(a) The LCE expenditures must meet the descriptions in sections 4(3)(a), 4(3)(b), 4(3)(c), or 4(3)(d) of the GGRR; and
(b) At the time BC Hydro decided to undertake the LCE expenditures meeting the descriptions in sections 4(3)(a), 4(3)(b), BC Hydro must have reasonably expected the LCE expenditures to be cost effective as set out in section 4(4) of the GGRR.”292
282. Both of these requirements are met by the LCE Projects/Program expenditures,
in BCSEA’s view.
283. First, the Initial LCE Projects are in one or more class of undertakings defined in
subsections 4(3)(a) and 4(3)(c).293 And, the components of the LCE Program are in
the paragraphs of section 4(3)(a) to (d) of the GGRR set out in Table 3-1 of Appendix
Y.294
284. Second, the evidence is that the NPV of all of BC Hydro’s LCE expenditures
under sections 4(3)(a) and 4(3)(b) of the GGRR is $118.6 million,295 establishing that
these expenditures are cost-effective under the GGRR.296 It follows that when BC
Hydro decided to undertake these LCE expenditures it reasonably expected them to
be cost effective.
285. BCSEA agrees with BC Hydro as follows:
“The GGRR cost-effectiveness test does not require each individual component to be cost effective, nor does it require the BCUC to definitively determine whether the prescribed undertakings will in fact be
291
BC Hydro Final Argument, para.555. 292
BC Hydro Final Argument, para.557. 293
Exhibit B-31, Panel 2.18.2, Attachment 1, p.7, pdf p.193. 294
Exhibit B-1, Appendix Y, Table 3-1, p.10, pdf p. 2246. 295
Exhibit B-31, BCUC Panel 2.18.2, Attachment 1, LCE Program Updated in December 2019, p. 14, pdf p.200; and Exhibit B-5, BCUC 1.186.2, pdf p.2075, cited in BC Hydro Final Argument, para.563. 296
“Cost-effective” under the GGRR essentially means the NPV of the benefits (LCE sales revenues net of foregone export revenues) exceed the NPV of the LCE costs, both using a discount rate equal to BC Hydro’s weighted average cost of capital.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 71 of 74
cost effective. Rather, the requirement is that BC Hydro must reasonably expect all of the undertakings in those two subsections on a cumulative basis to be cost-effective at the time BC Hydro decides to carry them out.”297
286. BCSEA also agrees with BC Hydro that it is not required to seek acceptance of
an expenditure schedule under section 44.2 for the LCE expenditures, even if some
or all of the LCE expenditures were also to qualify as a “demand-side measure.”298
287. In the Application, BC Hydro requests approval to defer its LCE Projects/Program
expenditures to the DSM Regulatory Account on the basis that they are prescribed
undertakings pursuant to section 18 of the CEA and section 4(3)(a) to (d) of the
GGRR. BCSEA understands this request to be a formality. The Direction to the
BCUC Respecting Undertaking Costs299 under the UCA says the Commission must
allow BC Hydro to defer to the DSM Regulatory Account amounts equal to BC
Hydro’s costs of implementing an undertaking within a class defined in section 4 (3)
(a), (b), (c) or (d) of the GGRR.
H. BC HYDRO MANAGEMENT OF TRADITIONAL DSM AND LCE INITIATIVES
288. In BCSEA’s view the evidence supports the conclusion that BC Hydro’s
management of traditional DSM and the LCE Projects/Program is appropriately
informed by the identification and assessment of delivery risks and the development
of mitigation measures at various stages of DSM implementation. Risks are
assessed and mitigated at the initiative level as well as at the portfolio level.300
289. BC Hydro submits an annual DSM Milestone Evaluation Summary Report to the
Commission.301 BC Hydro elaborated:
“BC Hydro typically conducts evaluations of all its DSM programs. The frequency varies depending on the program but typically ranges between three years and six years. On an exception basis, a decision may be made to not evaluate a program. Examples include a program that has been or will be discontinued, or if the cost of an evaluation would be disproportionate relative to program expenditures.”302
297
BC Hydro Final Argument, para.562. 298
BC Hydro Final Argument, para.556. 299
B.C. Reg. 77/2017. http://www.bclaws.ca/civix/document/id/complete/statreg/77_2017 300
Exhibit B-1, p.10-41, pdf p.1071. 301
Exhibit B-1, Appendix AA, pdf p. 2294. 302
Exhibit B-6, BCSEA 1.53.1, pdf p.825.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 72 of 74
290. Regarding evaluation, measurement and verification of the traditional DSM
portfolio, BCSEA is satisfied that BC Hydro’s policies and procedures are guided by
industry best practices and are neutral and unbiased.
291. BCSEA is satisfied that BC Hydro’s evaluation function is sufficiently independent
and represents an appropriate blend of internal and external resources, taking into
account costs and expertise.303 As BC Hydro notes, BC Hydro does not profit from
any over-estimation of DSM savings.
I. CONCLUSION AND REQUESTED FINDINGS
292. In BCSEA’s view, BC Hydro’s traditional DSM expenditure schedule is in the
public interest and BC Hydro’s LCE Projects/Programs expenditures are a
prescribed undertaking under section 18 of the CEA. BCSEA submits that the BCUC
should accept the proposed DSM Expenditure Schedule for the Test Period, and
approve deferral of the LCE Projects/Programs expenditures to the DSM Regulatory
Account.
PART TWELVE: IMPLEMENTATION OF RATES AND CONSIDERATION OF NEW INFORMATION
A. INTRODUCTION
293. BCSEA agrees with BC Hydro’s proposal to implement the Evidentiary Update by
making the interim F2020 rates permanent, and decreasing rates by 1.01% on April
1, 2020 (i.e., the beginning of F2021).304
B. BC HYDRO’S RATE IMPLEMENTATION PROPOSAL, INTERESTS OF BOTH CUSTOMERS AND THE COMPANY
294. BCSEA accepts the four principles that BC Hydro applied in weighing the rate
implementation options:
a. recovery of the revenue requirements in the Test Period (no more and no
less),
b. rate stability in the Test Period,
c. avoiding bill adjustments, and
303
BC Hydro Final Argument, para.566. 304
BC Hydro Final Argument, para.572.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 73 of 74
d. avoiding the re-introduction of longer-term rate smoothing.305
295. BCSEA has reviewed the various rate implementation options and is satisfied
that the proposed option works the best in relation to the four criteria. In particular,
BCSEA would not support a rate implementation option that re-introduced longer-
term rate smoothing.
C. UPDATING EVIDENTIARY UPDATE INPUTS
296. BCSEA supports reliance on the financial data current to the Evidentiary Update.
In BCSEA’s view, the Evidentiary Update is a reasonable basis for setting rates in
the Test Period. A line has to be drawn somewhere. New financial data will never
stop emerging. BCSEA submits that the regulatory accounts are an appropriate way
to account for information that became available after the Evidentiary Update. The
proceeding will have been underway for 15 months by the time BC Hydro’s reply
argument is due on May 27, 2020. In BCSEA’s view it is time to bring this proceeding
to a conclusion.
297. Regarding COVID-19, BCSEA agrees that the BCUC can take judicial notice of
the fact that the COVID-19 pandemic is having ongoing detrimental economic effects
and is disrupting daily life in unprecedented ways. BCSEA joins BC Hydro in
acknowledging the hardships faced by customers due to the virus, including those
who have died, those who are in hospital or whose health has been impacted, and
those who are facing economic challenges and uncertainties.306
298. In case it needs to be said, BCSEA would oppose re-opening the evidentiary
record to consider the impacts of the COVID-19 pandemic on BC Hydro’s rates and
DSM expenditures during the Test Period. BCSEA agrees with BC Hydro that the
regulatory accounts “will mitigate much of the uncertainty caused by the pandemic by
capturing variances from forecast which can then be returned to or recovered from
customers in the next test period in accordance with existing BCUC orders.” In
BCSEA’s view, the appropriate approach is expressed by BC Hydro when it states,
“if any particular approval from the BCUC is required over the remainder of the Test
305
BC Hydro Final Argument, para.575. 306
BC Hydro Final Argument, para.595.
BCSEA Final Argument May 4, 2020 BC Hydro F2020-F2021 RRA Page 74 of 74
Period due to the pandemic, BC Hydro will bring forward requests to the BCUC in
separate applications as needed.”307
D. CONCLUSION AND REQUESTED FINDING
299. BCSEA submits that the Evidentiary Update remains a reasonable basis upon
which to base Test Period rates.
PART THIRTEEN: CONCLUSION AND ORDER SOUGHT
300. BCSEA supports Commission approval of the Draft Order set out in Appendix B
of the Evidentiary Update.308
ALL OF WHICH IS RESPECTFULLY SUBMITTED. May 4, 2020
____________________________ William J. Andrews Barrister & Solicitor Counsel for B.C. Sustainable Energy Association
307
BC Hydro Final Argument, para.598. 308
Exhibit B-19, Appendix B, pdf p.102, as corrected by Exhibit B-11-2.
1\