Case Study for Gas Pipelines
Construction
Bucharest, Crowne Plaza November 6th, 2013
WHY HSE IS EASY? You have to DO IT !!
1
About IPM - Partners Romania
General information
HSE start package for construction sites, drilling sites and operations
Risk management tools
HSE communication and reporting
Inspections and audits
Awards - Benefits - Resources
Questions & Answers
AGENDA
WHY HSE IS EASY? You have to DO IT !!
2
ABOUT IPM–PARTNERS ROMANIA
IPM - Partners Romania is an engineering & construction company providing services for the oil & gas industry. As a leading contractor in Romania, we are focused on building quality pipelines and associated facilities. Our excellence in safety, project management and experienced personnel are an asset to any project.
ENGINEERING
PROCUREMENT
CONSTRUCTION
COMMISSIONING
for projects requiring:
• FABRICATION
• CONSTRUCTION
• TECHNICAL SERVICES
• TURN KEY
WHY HSE IS EASY? You have to DO IT !!
3
ABOUT IPM – PARTNERS ROMANIA
OIL & GAS PROJECTS
• Oil & Gas upstream facilities,
• Oil & Gas pipelines - all value chain covered,
• Oil & Gas separation, treatment and metering
plants / stations,
• Gas dehydration plants,
• Fuel stations,
• Process salt water injection stations, collection, up
to three levels filtering, metering, injection,
• Automations for wells and oil / gas processing
installations.
CIVIL PROJECTS
• Access roads and platforms to/for oil fields and
civil objectives: concrete based roads,
• Gravel-top roads and macadam roads,
• Building rehabilitation systems: PVC-vinyl windows
and door systems, aluminum based windows and
door systems,
• Polyurethane based insulation systems for roofs
and facades,
• Pipelines and piping systems for urban areas: water,
gas, sewage piping.
TECHNICAL SERVICES
• Pipeline detection, Topographical Survey, DCVG,
soil resistivity assessment, NDT, technical evaluation
for buried pipelines,
• Survey, certified examination programs, NDT,
technical assessment reports for above ground
technological pipelines, vessels and tanks,
• Cathodic protection for pipelines and tanks
• Construction permitting and authorizing.
WHY HSE IS EASY? You have to DO IT !!
4
GENERAL INFORMATION
Key Points
Knowing the regulations
Knowing the interpretation and enforcement by the authorities
Compliance with the legislation
Compliance with the specific requirements of the industry
Compliance with the specific requirements of the client / contract
WHY HSE IS EASY? You have to DO IT !!
5
GENERAL INFORMATION
IPM - Partners Romania Policy
IPM-Partners Romania has implemented and certified an Integrated Management
System: Quality - Environment - Safety and Health at Work. This has been developed to
ensure that our Policies are systematically applied, and that best industry practice is
adopted within all operations.
We implement, follow and control the application of the system:
In all aspects of IPM - Partners Romania business activities
At all levels of the organization
For all subcontractors
WHY HSE IS EASY? You have to DO IT !!
6
HSE start package for construction sites, drilling sites and operations
Kick-off meeting handing over documents:
Health and safety plan
Environmental management plan
Emergency response plan
Waste management plan
Site induction
List of equipment
List of personnel
Interfaces with contractors
WHY HSE IS EASY? You have to DO IT !!
7
RISK MANAGEMENT TOOLS
Risk management consist in: Identification, Assessment, Prioritization of risks
followed by organizing the resources in order to: Minimize, Monitor, Control
the probability and/or impact of unfortunate events.
WHY HSE IS EASY? You have to DO IT !!
8
RISK MANAGEMENT TOOLS
PTW system (‘Permit to work’ system)
JSA (Job safety analysis) form
Risk assesment matrix
COSHH (Control of Substances Hazardous to Health)
PPE (Personal protective equipment)
WHY HSE IS EASY? You have to DO IT !!
10
RISK MANAGEMENT TOOLS
PTW System (‘Permit to work’ system)
A work permit system consists primarily of a standard procedure designed to ensure that potentially hazardous routine and non-routine work on industrial and gas instalations can be carried out safely.
The scope of the system is to provide recommendations on how to plan and execute potentially hazardous jobs in a safe manner.
WHY HSE IS EASY? You have to DO IT !!
11
RISK MANAGEMENT TOOLS
PTW System (‘Permit to work’ system) Essential steps to follow:
Details of the necessary preparatory work including assesment of hazards,
precautions necessary to make equipment safe and preparation of a clear work
procedure that defines the scope of works and describes the specific steps
required for its completion
A clear definition of responsibilities
Appropiate training for all involved parties
Provision of adequate safety equipment
A formal work permit that has to be signed by the responsible personnel of all
involved parties
WHY HSE IS EASY? You have to DO IT !!
12
RISK MANAGEMENT TOOLS
JSA (Job safety analysis) form
UNDERSTAND! A piece of paper will not make the job safe!
DISCOVER!
The risks and hazards associated with the job!
IMPLEMENT! The resources to eliminate or mitigate the risks.
REMEMBER!
JSA is not simply a piece of paper; it is a process!
WHY HSE IS EASY? You have to DO IT !!
14
RISK MANAGEMENT TOOLS
COSHH is the law
that requires employers
to control substances
hazardous to health
COSHH (Control of Substances Hazardous to Health)
WHY HSE IS EASY? You have to DO IT !!
15
RISK MANAGEMENT TOOLS
COSHH (Control of Substances Hazardous to Health)
You can prevent or reduce workers' exposure to hazardous substances by:
finding out what the health hazards are; deciding how to prevent harm to health (risk assessment); providing control measures to reduce harm to health; making sure they are used ; keeping all control measures in good working order; providing information, instruction and training for employees and others; providing monitoring and health surveillance in appropriate cases; planning for emergencies.
Never mix hazardous substances unless you are sure of what you are doing
WHY HSE IS EASY? You have to DO IT !!
16
RISK MANAGEMENT TOOLS
PPE (Personal protective equipment)
Define the minimum PPE standards
Define the special PPE requirements
Implement PPE to site representatives
and visitors
Implement PPE to site representatives
of subcontractors and suppliers
Check the use of extra PPE required by JSA
for all involved parties
WHY HSE IS EASY? You have to DO IT !!
17
RISK MANAGEMENT TOOLS
PPE (Personal protective equipment)
Make requirements
VISIBLE
with a fix or mobile
HSE SAFETY PANEL
WHY HSE IS EASY? You have to DO IT !!
18
HSE COMMUNICATION AND REPORTING
HSE site induction
Toolbox meetings
HSE weekly meetings
HSE weekly reports
Near miss report
Incident report
Accident report
KPI ( Key performance indicators)
WHY HSE IS EASY? You have to DO IT !!
19
INSPECTIONS AND AUDITS
Check the appliance of standards, guidelines,
contractual requirements
HSE site check form
Management walk around
Feedback report for improving the HSE
performance
Organize ‘Lessons learned’ sessions
WHY HSE IS EASY? You have to DO IT !!
20
AWARDS - BENEFITS
Evaluate the HSE performance
Implement the ‘Best HSE Performance Award’
WHY HSE IS EASY? You have to DO IT !!
21
AWARDS - BENEFITS
IPM - Partners Romania ‘Best HSE Performance Award’ criteria: Quality of reports Key Performance Indicator (near miss, incident, accident) Trainings performed Feedback from client Feedback from contractors Results of management walk around HSEQ Site inspections Safety milestones, goals and safety awareness on the job Presentation of HSEQ corner Creative ideas for improving the HSEQ level Commitment to improving corporate HSEQ
WHY HSE IS EASY? You have to DO IT !!
23
HAVE A SAFE DAY!
IPM-Partners Romania 2nd Trei Ierarhi Street, Ploiesti PH, RO-100010, Romania
www.IPM-Partners .com Alberto Dumitru