westfield square water main replacement square w… · westfield square water main replacement...
TRANSCRIPT
![Page 1: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/1.jpg)
Department of Watershed Management CIP Program
Westfield Square Water Main Replacement
Community Meeting
Margaret Tanner, P.E., DWM Deputy Director
Tuesday, June 27, 2017 – 6:30-8:00 pm
June 2017 1
![Page 2: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/2.jpg)
• Welcome
• Introductions
• Project Overview
• Contact Info
• Questions
Department of Watershed Management CIP Program
Agenda
![Page 3: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/3.jpg)
Replacement of 3,300 linear feet of 6-inch pipe with 8-inch iron ductile pipe throughout the Westfield Square Community
• Part of the CIP project completion list
• Improved water service to Westfield Square Community
• Eliminate water main breaks
• Reduce loss of water pressure
Department of Watershed Management CIP Program
Project Rationale
![Page 4: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/4.jpg)
PROJECT SCOPE
• Waterline replacement on:o Downing Lane
o Downshire Lane
o Downing Square
o Downshire Square
o Downshire Circle
• Installation of new water meters
• Installation of new hydrants
Department of Watershed Management CIP Program
Project Overview
![Page 5: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/5.jpg)
Department of Watershed Management CIP Program
Project Overview
![Page 6: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/6.jpg)
Department of Watershed Management CIP Program
Project Overview
![Page 7: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/7.jpg)
Department of Watershed Management CIP Program
Project Overview
Preliminary Project Schedule:
• July 5 – Start of construction, site mobilization
• July 5 to Mid-August – Fairoaks, Downing Lane and Downshire Lane
o Installation and Pressuring Testing
• Mid-August to Late September – Downing Square, Downshire Circle and Downshire Square
o Installation and Pressure Testing
• Late September to Early October – Final completion of project
o Milling and paving
![Page 8: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/8.jpg)
Department of Watershed Management CIP Program
Project Overview
Potential Project Impacts:
• Some instances of rolling lane closures; flaggers to direct traffic through construction zone
• Some instances of restricted driveway access as pipe is installed; prior notice to affected residences
• Possible delays due to weather, necessary parts replacement, delay in receiving parts
![Page 9: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/9.jpg)
Department of Watershed Management CIP Program
Community Outreach
6/28/2017 9
• Community Meetings
• Project Bulletins and Flyers
• Email Updates
• Door/Mailbox Hangers
• Social Media –
HOW WE WILL KEEP YOU INFORMED
![Page 10: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/10.jpg)
Department of Watershed Management CIP Program
Community Outreach
6/28/2017 10
• Website – www.dekalbwatershed.com
• Contact Uso Email: [email protected]
o Phone: 1-800-986-1108
HOW WE WILL KEEP YOU INFORMED
![Page 11: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/11.jpg)
Questions?
6/28/2017 11
![Page 12: Westfield Square Water Main Replacement Square W… · Westfield Square Water Main Replacement Community Meeting Margaret Tanner, P.E., DWM Deputy Director Tuesday, June 27, 2017](https://reader036.vdocuments.us/reader036/viewer/2022090606/605c1657c590b0369f51c564/html5/thumbnails/12.jpg)
REMINDER:Sign-up to receive project updates and
alerts via email and text!
THANK YOU!
6/28/2017 12