Western Sydney Infrastructure Plan Delivering for growth, easing congestion and connecting communities March 2016 The Australian and NSW governments are funding a 10 year, $3.6 billion road investment program for western Sydney. The Western Sydney Infrastructure Plan will deliver major road infrastructure upgrades to support an integrated transport solution for the region and capitalise on the economic benefits from developing a planned western Sydney airport at Badgerys Creek. The Plan provides improved road transport capacity ahead of future traffic demand, as planned residential and employment development takes place in the Western Sydney Priority Growth Area, South West Priority Land Release Area and the Western Sydney Employment Area. This work will transform the region’s economy and make western Sydney an even better place to live and do business. Features Upgrade of The Northern Road to a minimum of four lanes between Narellan Road, Narellan and Jamison Road, South Penrith A new M12 Motorway with up to six lanes between the M7 Motorway at Cecil Hills and The Northern Road at Luddenham, connecting to the planned western Sydney airport site Upgrade of Bringelly Road to a minimum of four lanes between The Northern Road and Camden Valley Way Building the Werrington Arterial Road by upgrading Kent Road and Gipps Street to four lanes between the Great Western Highway and the M4 Motorway, including two new east facing ramps on the M4 Motorway Upgrading the intersection of Ross Street and the Great Western Highway, Glenbrook A $200 million Local Roads Package for councils to apply for local road upgrades (Australian Government funded). Did you know? Western Sydney is Australia’s third largest economy and in its own right would be Australia’s fourth largest city. During the next 20 years, the region is expected to grow from two million to three million people, which is why the Australian and NSW governments are fast‑tracking the development of new, and upgrades to existing infrastructure. $3.6billion investment in major transport infrastructure Make western Sydney an even better place to live and do business 4000 direct and indirect jobs over 10 years 61 km of new and upgraded roads Transform the local economy Improve the efficient movement of state and national freight Provide opportunities for improved public transport Reduced travel times to Penrith, Liverpool and Campbelltown CBD precincts Construction of the new bridge over the Upper Canal, Leppington for Bringelly Road Upgrade Stage 1.

Upload: others

Post on 05-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Western Sydney Infrastructure Plan · to existing infrastructure. $3.6. billion investment in major transport infrastructure. Make western Sydney. an even better place to live and

Western Sydney Infrastructure Plan

Delivering for growth, easing congestion and connecting communities

March 2016

The Australian and NSW governments are funding a 10 year, $3.6 billion road investment program for western Sydney. The Western Sydney Infrastructure Plan will deliver major road infrastructure upgrades to support an integrated transport solution for the region and capitalise on the economic benefits from developing a planned western Sydney airport at Badgerys Creek.

The Plan provides improved road transport capacity ahead of future traffic demand, as planned residential and employment development takes place in the Western Sydney Priority Growth Area, South West Priority Land Release Area and the Western Sydney Employment Area. This work will transform the region’s economy and make western Sydney an even better place to live and do business.

Features• Upgrade of The Northern Road to a minimum of

four lanes between Narellan Road, Narellan and Jamison Road, South Penrith

• A new M12 Motorway with up to six lanes between the M7 Motorway at Cecil Hills and The Northern Road at Luddenham, connecting to the planned western Sydney airport site

• Upgrade of Bringelly Road to a minimum of four lanes between The Northern Road and Camden Valley Way

• Building the Werrington Arterial Road by upgrading Kent Road and Gipps Street to four lanes between the Great Western Highway and the M4 Motorway, including two new east facing ramps on the M4 Motorway

• Upgrading the intersection of Ross Street and the Great Western Highway, Glenbrook

• A $200 million Local Roads Package for councils to apply for local road upgrades (Australian Government funded).

Did you know? Western Sydney is Australia’s third largest economy and in its own right would be Australia’s fourth largest city. During the next 20 years, the region is expected to grow from two million to three million people, which is why the Australian and NSW governments are fast‑tracking the development of new, and upgrades to existing infrastructure.

$3.6billion

investment in major transport infrastructure

Make western Sydney an even better place to live and do business

4000 direct and indirect jobs

over 10 years

61km

of new and upgraded roads

Transform the local economy

Improve the efficient movement

of state and national freight

Provide opportunities for improved

public transport

Reduced travel times to Penrith, Liverpool and Campbelltown CBD precincts

Construction of the new bridge over the Upper Canal, Leppington for Bringelly Road Upgrade Stage 1.

Page 2: Western Sydney Infrastructure Plan · to existing infrastructure. $3.6. billion investment in major transport infrastructure. Make western Sydney. an even better place to live and

ROADS IN PLANNING

PROJECT EARLY PLANNING STAGE

INVITE COMMUNITY

COMMENTS ON POTENTIAL ROUTE

OPTIONS

SELECT PREFERRED ROUTE OPTION

INVITE COMMUNITY

COMMENTS ON ACCESS STRATEGY AND PRELIMINARY

ROAD DESIGN

INVITE COMMUNITY COMMENTS ON CONCEPT DESIGN AND

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL APPROVAL

The Northern Road Upgrade Stage 3Littlefields Road to Jamison Road

10km

Late

2016Mid

2017

The Northern Road Upgrade Stage 4Mersey Road to Littlefields Road

11km

Late

2016Mid

2017

M12 MotorwayM7 to The Northern Road

15–17km

Mid

2016Early

2017Early

2018Mid

2018

The Northern Road Bringelly Road Interchange

1.5km

Mid

2016ROADS IN DETAILED DESIGN AND CONSTRUCTION

PROJECT ENVIRONMENTAL APPROVAL

DETAILED DESIGN

INVITE CONSTRUCTION

TENDERS

AWARD CONSTRUCTION

CONTRACT

STARTED CONSTRUCTION

OPEN TO TRAFFIC

Bringelly Road Upgrade Stage 1Camden Valley Way to King Street

5.7km

Late

2017

Bringelly Road Upgrade Stage 2King Street to The Northern Road

4.3km

Mid

2016Late

2016Early

2017Late

2019

Werrington Arterial RoadGreat Western Highway to M4 Motorway

2km2016

The Northern Road Upgrade Stage 1Camden Valley Way to Peter Brock Drive

3.3km2018

The Northern Road Upgrade Stage 2Peter Brock Drive to Mersey Road

10km

Early

2016Mid

2016Late

2016Early

2017Late

2019

Looking north at the Bringelly Road, Camden Valley Way and Cowpasture Road intersection, Horningsea Park.

Delivery of the shared pedestrian and cycle path bridge spans as part of Werrington Arterial Road upgrade.

Page 3: Western Sydney Infrastructure Plan · to existing infrastructure. $3.6. billion investment in major transport infrastructure. Make western Sydney. an even better place to live and

March 2016RMS 16.072

Privacy Roads and Maritime Services (“RMS”) is subject to the Privacy and Personal Information Protection Act 1998 (“PPIP Act”) which requires that we comply with the Information Privacy Principles set out in the PPIP Act. All information in correspondence is collected for the sole purpose of assisting in the assessment of this proposal. The information received, including names and addresses of respondents, may be published in subsequent documents unless a clear indication is given in the correspondence that all or part of that information is not to be published. Otherwise RMS will only disclose your personal information, without your consent, if authorised by the law. Your personal information will be held by RMS at 27 Argyle Street, Parramatta NSW 2150. You have the right to access and correct the information if you believe that it is incorrect.

This document contains important information about road projects in your area. If you require the services

of an interpreter, please contact the Translating and Interpreting Service on 131 450 and ask them to call the project team on 1800 703 457. The interpreter will then assist you with translation.

Learn more about the Western Sydney Infrastructure Plan at www.rms.nsw.gov.au/wsip and provide your feedback via:

Project information line: 1800 703 457

Email: [email protected]

Mail: PO Box 973 Parramatta NSW 2124

WESTERN SYDNEYEMPLOYMENT

AREA

WESTERN SYDNEYPRIORITY GROWTH AREA

SOUTH WESTPRIORITY LANDRELEASE AREA

Blacktown

Mt Druitt

Chullora

Parramatta

East Hills

Prairiewood

Bringelly

OranPark

Fairfield

Liverpool

Bankstown

St Marys

GlenmorePark

Luddenham

Penrith

Sutherland

Campbelltown

Minto

Narellan

Camden

Leppington

Greendale

Glenbrook

EasternCreek

The Northern Road upgrade $1.6 billionStage 1 construction started 2016

Diversion of The Northern Road

M12 Motorway study area$1.25 billionStudy area in planning

M4

M7

M5

M7

M2

M31

Elizabeth Drive

Bringelly Road

Narellan Road

Cam

den

Valle

y Way

The Northern Road

The

Nor

ther

n Ro

ad

Planned western Sydney airport at Badgerys Creek

Werrington Arterial Road $70 million Construction started 2015

Bringelly Road upgrade $509 millionConstruction started 2015

The Northern Road and Bringelly Road Interchange

Ross Street/Great Western Highway intersection upgrade $5 million In planning

Wetherill Street upgrade $8.2 million

Smithfield Road upgrade $16.4 million

Raby Road from Eschol Park Drive to Stranraer Drive scoping study $655,000

Cumberland Highway intersection upgrades $5.8 million

Argyle Street/Camden Valley Way • Corridor upgrade (underway) and studies (complete) $2.3 million• Stage 2 – Macarthur Road Intersection $4.3 million• Grahams Hill Road and Richardson Road Intersection $4.1 million

The Northern Road and Erskine Park Road • Intersection upgrade studies $1.1 million – complete• Erskine Park Road intersection upgrades $29.1 million• The Northern Road intersections upgrade $6.7 million

Bungarribee Road and Flushcombe Road traffic lights scoping study $526,000

Eagle Vale Drive upgrade $17.5 million

Porrende Street upgrade scoping study $120,000

Local Roads Package ($200 million Australian Government funded)Major road projectsThe existing The Northern Road

LEGEND

Western Sydney Infrastructure Plan