Westbury UFSDCapital Improvements Program
Construction Update
July 10, 2019
• High School Program– Review of Project Scope– Renderings of Facility– Construction Update– Minority / Women / Local Business Involvement
• Middle School Program– Review of Project Scope– Renderings of Facility– Construction Update (Roofing Project / Additions & Alterations)
Presentation Overview
• 14 classroom addition• Cafeteria addition with warming kitchen and connecting
link to existing building • Science Lab Alterations • Boilers, pumps and controls• Floors and ceilings• Site Work – parking lot modifications• Masonry Restoration – areas of work impact • Upgrade Electrical Service
Project Scope for HS
EVT-1 EVT-2
T-1 T2
TERRAZZO BASIS OF DESIGN
T4
EVT-2EVT-3
T3
EVT-3
Terrazzo Basis of Design1 3884 FROST -FORBO MARMOLEUM FRESCO
2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE
33736 GREEN SHIMMER -FORBO MARMOLEUM
CONCRETE T-4 3711
CLOUDY SAND -FORBO MARMOLEUM CONCRETE
Enhance Vinyl TileEVT-1 AD521 LIMO -ALTRO DOLCE TILE
EVT-2 AD512 LECHE -ALTRO DOLCE TILE
EVT-3 AD605 CILANTRO -ALTRO DOLCE TILE
LS-3LS-2
T-1 T2
TERRAZZO BASIS OF DESIGN
T4
LS-1
T3
Terrazzo Basis of Design1 3884 FROST -FORBO MARMOLEUM FRESCO
2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE
33736 GREEN SHIMMER -FORBO MARMOLEUM
CONCRETE T-4 3711 CLOUDY SAND -FORBO
MARMOLEUM CONCRETE
Sheet LinoleumLS-1 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE
LS-2 3240 WILLOW -FORBO MARMOLEUM CONCRETE
LS-3 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE
Cladding Panel SystemPRODEX CREAM -PRODEMA PANELS
Brick Veneer / Thin BrickPENNSYLVANIA MOLDED -BERKS WATSONTOWN BRICK COMPANY
Thin Cast LimestoneSMOOTH OAK RIDGE RENAISSANCE MASONRY UNITSARRISCRAFT INTERNATIONAL BUILDING STONE
• Poured concrete for footings and foundation walls for Classroom Addition
• Installed in-ground sanitary plumbing piping and electrical conduits in preparation of concrete slab at Classroom Addition
• Placed and compacted soil and stone bed in preparation for concrete slab pour
• Installed vapor barrier and slab reinforcement• Poured concrete slab for Classroom Addition• Received delivery for cold metal framing and commenced work
on perimeter walls
Construction Update
• Performed abatement and demolition of boilers: 66%• Formed and poured concrete pads for new boilers: 66%• Received boiler sections and relocated material to boiler room
for assembly• Existing sanitary system at Cafeteria Addition remediation: 100%• Installation of new sanitary structures and interconnecting
piping at Cafeteria Addition: 95%• Commenced excavation for foundation walls at Cafeteria
Addition
Construction Update
• Termination of feeders at new transformer in driveway: 60%• PSEG installed pole for new electrical service to transformer• Delivered new panelboards to electric room in basement• Commenced asbestos abatement operations at 2nd floor
classrooms• New Storm Drainage Installation: 60%• Working on drainage system for new courtyard by locker room• Completed foundations and concrete slab for East Connecting
Corridor
Construction Update
Classroom Addition – Prep for Pour
Classroom Addition – Slab Pour
Cafeteria Addition – Sanitary System
Boiler Room Operations – Demo & Assembly
Classroom Addition – Interior and Exterior Wall Framing
Electrical Service – Installation of New Transformer Vault
Electrical Service – Switchgear and Conduit Runs
Minority / Women / Local Business Involvement
Elite Construction has been actively meeting with each contractor on a weekly basis to examine their contract and workforce program. The contractors and consultants affiliated with the project are making a “Good Faith Effort” to achieve the District’s goals. • As the project continues, different skills will be required and
personnel currently assigned to the project will be modified accordingly.
• Individuals are required to obtain their OSHA 10 hour certification and provide to our office.
• Individuals are also required to be part of the Local Unions that will man this project: (Carpenters, Brick Masons, Laborers, Abatement, Plumbing, Mechanical, Electrical )
Minority / Women / Local Business Involvement
• VRD Contracting, Inc. – General Construction (WBE)– A&S Rebar, Inc. – Rebar Supplier (WBE)– Baybrent Construction – Ceramic Tiling (MBE)– Linda Lee Construction - Taping (WBE)– Park Ave Building Materials – Bldg Materials (MBE)– Island Nursery – Landscaping (WBE)
Minority / Women / Local Business Involvement
•Thermo Tech Combustion – Mechanical (HVAC)– DemoTec Mechanical – Boiler Demolition (WBE)
• WHM Plumbing & Heating, Inc.– Plumbing– AMG Demolition – Hot Water Tank Removal (WBE)
• Roland’s Electric, Inc. – Electrical & Fire Alarm– Advance Sound Co – PA/ Clocks / Smartboards (WBE)– CMT Lighting Co. – Lighting Supplies (WBE)
Minority / Women / Local Business Involvement
• 12 classroom addition with connection to existing building• Café addition-standard construction• Alterations to existing kitchen/cafeteria• Roof replacement and masonry• Mechanical system: replacement and abatement• Plumbing with abatement• Alterations-Increase corridor width, handicapped toilets
and handicapped access throughout building
Project Scope for MS
• P/A intercom, clocks, security, F/A• Ceilings, floors, and casework in all spaces• Site Work to include parking lot reconstruction• Upgrade Electrical Service• Abatement in Crawl Space, Floors & Ceilings
Project Scope for MS
Wiedersum
Associates
Architects
PERSPECTIVE VIEW 1
Wiedersum
Associates
Architects
PERSPECTIVE VIEW 2
Wiedersum
Associates
Architects
PERSPECTIVE VIEW 3
• Middle School Existing Roof Replacement Project– Contract was awarded to Niko K Construction– Work is scheduled to commence on July 15, 2019– Contract is scheduled for Summers of 2019 and 2020– Contract requires abatement, masonry reconstruction and roof
replacement of all existing surfaces– Requires coordination with prime contractors on Middle School
Additions and Alterations Project• Middle School Additions and Alterations Project
– Project is currently out of bidding– Bids due date to be established; Anticipate bid opening prior to
August 31, 2019
Construction Update
Westbury UFSDCapital Improvements Program
Construction Update
Question and Answer