AS AT 30TH JAN 2017 Financial Year Project Name Activity Completion Date Project Cost Status Remark 2013/2014 Contituency Office Administration fund 6% Day to day office operations,staff salaries & general office management July 2014 4,709,705 Complete Administrative activities done to enable of project implementation 2013/2014 Emergency Fund Reserve fund for emergencies and disasters July 2014 3,564,466.00 Complete Emergency roads rehabilitated 2013/2015 Monga Junction-Karota Road Grading and rehabilitation of Road July 2014 Complete Complete and in use 2013/2016 Bosose Junctio-Ramba Tea Buying Centre Road Grading and rehabilitation of Road July 2014 Complete Complete and in use 2013/2017 Karantina -Kiambere Road Grading and rehabilitation of Road July 2014 Complete Complete and in use 2013/2014 Education Bursary Fees Payment for needy students in colleges and universities and activities for enhancement in performance in national examinations. July 2014 7,000,000 Complete Bursary issued to students 2013/2014 Monitoring & Evaluation Ensuring sound management and successful completion of projects through through close supervision and evaluation. July 2014 2,354,852.00 Complete Effective monitoring and evaluation activities done. 2014/2015 Employee Salaries Payment of staff salaries and Gratuity July 2014 1,700,000 Complete Complete 2014/2015 Goods and Services Purchase of office stationary, fuel, vehicle repairs, telephone expenses and subsistence July 2014 2,623,610 Complete Complete 2014/2015 Purchase of Furniture and Office Equipments Purchase of office furniture and equipment July 2014 300,000 Complete Complete 2014/2015 Purchase of Computers Purchase of one CDFC laptop and One Computer July 2014 200,000 Not done Yet Awaiting funds from the CDF Board 2014/2015 NSSF Staff NSSF Remmitances July 2014 28,800 Ongoing Payment of NSSF deductions ongoing 2014/2015 NHIF Staff NHIF Remmitances July 2014 23,040 Ongoing Payment of NHIF deductions ongoing 2014/2015 Committee Allowances and Expenses Committee sitting allowances and expenses July 2014 2,300,550 Ongoing Paid CDFC Allowances 2014/2015 Emergency Fund Reserve fund for emergencies and disasters July 2014 5,400,259.00 Not Started Awaiting funds from the CDF Board 2014/2015 Education Bursary 8.0% Fees Payment for needy students in colleges and universities and activities for enhancement in performance in national examinations. July 2014 10,000,000 Ongoing Award process on going 2014/2015 Goods and Services Purchase of stationary, fuel, vehicle repairs, telephone expenses and subsistence in M&E July 2014 615,345.00 Ongoing Ongoing supprort activities to M AND E 2014/2015 Committee Expenses Committee M&E Expenses July 2014 2,000,000.00 Ongoing Ongoing supprort activities to M AND E WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY

Upload: others

Post on 23-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

AS AT 30TH JAN 2017

Financial

Year

Project Name Activity Completion Date Project Cost Status Remark

2013/2014

Contituency Office Administration fund

6%

Day to day office operations,staff salaries &

general office management

July 2014 4,709,705

Complete

Administrative activities

done to enable of project

implementation

2013/2014Emergency Fund Reserve fund for emergencies and disasters July 2014

3,564,466.00 Complete

Emergency roads

rehabilitated

2013/2015 Monga Junction-Karota Road Grading and rehabilitation of Road July 2014 Complete Complete and in use

2013/2016

Bosose Junctio-Ramba Tea Buying

Centre Road

Grading and rehabilitation of Road July 2014

Complete Complete and in use

2013/2017 Karantina -Kiambere Road Grading and rehabilitation of Road July 2014 Complete Complete and in use

2013/2014

Education Bursary Fees Payment for needy students in colleges

and universities and activities for

enhancement in performance in national

examinations.

July 2014 7,000,000

Complete Bursary issued to students

2013/2014

Monitoring & Evaluation Ensuring sound management and successful

completion of projects through through

close supervision and evaluation.

July 2014

2,354,852.00 Complete

Effective monitoring and

evaluation activities done.

2014/2015 Employee Salaries Payment of staff salaries and Gratuity July 2014 1,700,000 Complete Complete

2014/2015

Goods and Services Purchase of office stationary, fuel, vehicle

repairs, telephone expenses and subsistence

July 2014 2,623,610

Complete

Complete

2014/2015Purchase of Furniture and Office

Equipments

Purchase of office furniture and equipment July 2014 300,000 Complete

Complete

2014/2015Purchase of Computers Purchase of one CDFC laptop and One

Computer

July 2014 200,000

Not done Yet

Awaiting funds from the

CDF Board

2014/2015NSSF Staff NSSF Remmitances July 2014 28,800

Ongoing

Payment of NSSF

deductions ongoing

2014/2015NHIF Staff NHIF Remmitances July 2014 23,040

Ongoing

Payment of NHIF

deductions ongoing

2014/2015Committee Allowances and Expenses Committee sitting allowances and expenses July 2014 2,300,550

Ongoing Paid CDFC Allowances

2014/2015Emergency Fund Reserve fund for emergencies and disasters July 2014

5,400,259.00 Not Started

Awaiting funds from the

CDF Board

2014/2015

Education Bursary 8.0% Fees Payment for needy students in colleges

and universities and activities for

enhancement in performance in national

examinations.

July 2014 10,000,000

Ongoing Award process on going

2014/2015

Goods and Services Purchase of stationary, fuel, vehicle repairs,

telephone expenses and subsistence in M&E

July 2014

615,345.00 Ongoing

Ongoing supprort

activities to M AND E

2014/2015Committee Expenses Committee M&E Expenses July 2014

2,000,000.00 Ongoing

Ongoing supprort

activities to M AND E

WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY

Page 2: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015CDFC/PMC Capacity Building PMC Training and capacity building expenses July 2014

972,655.00 Ongoing

Ongoing supprort

activities to M AND E

2013/2014 Constituency Sports Committee Sports activities within the constituency

July 2014

390,000 Complete

Sports tournaments

organised

2014/2015 Constituency Sports Committee Sports activities within the constituency

July 2014

500,000 Not yet started

Awaiting disbursement of

funds from CDF Board

2013/2014 Bomorito Primary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Complete

Trees and flowers planted

in good condition

2013/2014 Nyansabakwa Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Complete

Trees and flowers planted

in good condition

2013/2014 Senator Kebaso Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Complete

Trees and flowers planted

in good condition

2013/2014 Kebirigo Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Complete

Trees and flowers planted

in good condition

2013/2014 Kianungu Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Complete

Trees and flowers planted

in good condition

2014/2015 Nyamira Primary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Complete

Awaiting Disbursement of

funds from CDF Board

2014/2015 Nyachogochogo Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Not yet started

Awaiting Disbursement of

funds from CDF Board

2014/2015 Bondeka Girls Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Not yet started

Awaiting Disbursement of

funds from CDF Board

2014/2015 Kianyabongere Primary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Not yet started

Awaiting Disbursement of

funds from CDF Board

2014/2015 Kianungu Secondary School

Planting of assorted tree varieties in

school compound

Aug 2014

80,000 Not yet started

Awaiting Disbursement of

funds from CDF Board

2013/2014

Barclays/Nyairicha/Nyanumba/Tai/Nyas

wabu/Osugo Road

Clearing side, grading, Drainage, and

escavation to level.4.5km

Aug 2014 800,000 Complete and in

use Road in use

2013/2014

Miruka - Bugo Road Bush clearing, and escavation to level. 0.8km Aug 2014 500,000 Complete and in

use Road in use

2013/2014

Bonyunyu- Onyabanga - Ikonge Road Bush Clearing, side drainage and escavation

to level.3.5 Km

Aug 2014 1,000,000 Complete and in

use Road in use

2013/2014

Bonyunyu-Nyakunguru-Nyabite Road Bush Clearing,grading, side drainage and

escavation to level.4km

Aug 2014 1,000,000 Complete and in

use Road in use

2013/2014

Nyabomite-Rianyagwoka-Marindi Road Bush Clearing, side drainage and escavation

to level.3.5 Km

Aug 2014 800,000 Complete and in

use Road in use

2013/2014

Nyagachi-Kianyabao-Riosiri Road Bush Clearing, side drainage and escavation

to level.4km

Aug 2014 800,000 Complete and in

use Road in use

Page 3: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Nyagachi-Rioindi-Mosobeti Road Bush Clearing, side drainage and escavation

to level.4.5km

Aug 2014 800,000 Complete and in

use Road in use

2013/2014

Gesiaga-Ekerubo-Erami Road Bush Clearing, side drainage and escavation

to level.3.5 Km

Aug 2014 800,000 Complete and in

use Road in use

2013/2014

Kabatia-Nyankongo-Mobamba Road Bush Clearing, side drainage and

Grading.4.6km

Aug 2014 1,000,000

Complete Road in use

2013/2014

Karantini-Bokimo Road Bush Clearing, side drainage and

Grading.3.5km

Aug 2014 1,000,000

Complete Road in use

2013/2014

Nyaigesa-Kemunguru Road Bush Clearing, side drainage and

Grading.4km

Aug 2014 1,000,000

Complete Road in use

2013/2014

Nyansabakwa-Mang'ong'o Road Bush Clearing, side drainage and

Grading.4km

Aug 2014 1,000,000

Complete Road in use

2013/2014

Nyamokenye-Omokonge-Gekomoni

Road

Bush Clearing, side drainage and

Grading.4km

Aug 2014 1,000,000

Complete Road in use

2013/2014

Rianyaundi-Kianginda Secondary School

Road

Bush Clearing, side drainage and

Grading.4km

Aug 2014 1,000,000

Complete Road in use

2013/2014

Nyamatoki-Egetongo-Nyamotentemi-

Erami Road

Grading 4km , and Culvert Installation 28m. Aug 2014 1,500,000

Complete Road in use

2014/2015

Etibu-Ikobe - Erami Road Bush Clearing, Opening of road,side

drainage and escavation to level.3. Km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Motagara Corner- Enchoro Road Clearing side, grading, Drainage, and

escavation to level.3km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Bonyunyu- Onyabanga - Ikonge Road Bush Clearing, side drainage and escavation

to level.3.5 Km

Aug 2014 800,000

Complete Complete and in use

2014/2015

Bonyunyu-Nyakunguru-Nyabite Road Heavy Bush Clearing,grading, side drainage

and escavation to level.6km

Aug 2014 2,000,000

Complete Complete and in use

2014/2015

Nyamokeri-Sironga-Erami Road Bush Clearing, side drainage and escavation

to level.3.0 Km

Aug 2014 800,000

Complete Complete and in use

2014/2015

Nyagachi-Kianyabao-Riosiri Road Bush Clearing, side drainage and escavation

to level.4km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Nyagachi-Rioindi-Mosobeti Road Bush Clearing, side drainage and escavation

to level.3.5km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Riobonyo-Rioigo-Riogao Road Bush Clearing, side drainage and escavation

to level.3.5 Km

Aug 2014 1,000,000

Complete Complete and in use

2014/2015

Kabatia-Nyankongo-Mobamba Road Bush Clearing, side drainage and

Grading.4.6km

Aug 2014 1,000,000

Complete Complete and in use

2014/2015

Bondeka-Tonga Omunuri Road Bush Clearing, side drainage and

Grading.3.km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Nyaigesa-Kemunguru Road Bush Clearing, side drainage and

Grading.4km

Aug 2014 1,000,000

Complete Complete and in use

2014/2015

Nyansabakwa-Mang'ong'o Road Bush Clearing, side drainage and

Grading.4km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Gekomoni - Kemasare- Erami Road Bush Clearing, side drainage and

Grading.3km

Aug 2014 1,000,000

Complete Complete and in use

2014/2015

Rianyaundi-Kianginda Secondary School

Road

Bush Clearing, side drainage and

Grading.3km

Aug 2014 900,000

Complete Complete and in use

2014/2015

Nyamatoki-Egetongo-Nyamotentemi-

Erami Road

Bush Clearing, side drainage and

Grading.4km

Aug 2014 1,300,000

Complete Complete and in use

Page 4: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

BarclaysBank-Nyairicha Road to the

River

Bush Clearing, side drainage and

Grading.2km

Aug 2014 800,000

Complete Complete and in use

2014/2015

Kebirigo - Migingo Road Bush Clearing, side drainage and

Grading.5km

Aug 2014 1,100,000

Complete Complete and in use

2013/2014

Bosamaro Chache Water Springs Fencing Spring area, placing of water points

and protection of spring

Aug 2014 400,000

Complete Complete and in use

2013/2014

Bosamaro Masaba Water Springs Fencing Spring area, placing of water points

and protection of spring

Aug 2014 500,000

Complete Complete and in use

2013/2014

West Mugirango Water Springs Fencing Spring area, placing of water points

and protection of spring

Aug 2014 600,000

Complete Complete and in use

2013/2014

Township Water Springs Fencing Spring area, placing of water points

and protection of spring

Aug 2014 400,000

Complete Complete and in use

2013/2014

Kenyenya Water Project Construction of elevated tank and piping Aug 2014 2,000,000

Complete Complete and in use

2013/2014

Nkora Water Project Gravity water project:Protection of spring,

construction of elevated tank and piping

Aug 2014 2,800,000

Complete Complete and in use

2013/2014

Bogichora Water Springs Fencing Spring area, placing of water points

and protection of spring

Aug 2014 500,000

Complete Complete and in use

2013/2014

Bonyamatuta Water Springs Fencing Spring area, placing of water points

and protection of spring

Aug 2014 400,000

Complete Complete and in use

2013/2014

Keera Water Springs Fencing Spring area, placing of water points

and protection of spring

July 2014 400,000

Complete Complete and in use

2014/2015

Bosamaro Water Springs Fencing Spring area, placing of water points

and protection of spring

July 2014 1,000,000

Complete Complete and in use

2014/2015

Nyamaiya Water Springs Fencing Spring area, placing of water points

and protection of spring

July 2014 1,000,000

Complete Complete and in use

2014/2015

Township Water Springs Fencing Spring area, placing of water points

and protection of spring

July 2014 900,000

Complete Complete and in use

2014/2015

Kenyenya Water Project Completion of elevated tank and piping July 2014 1,500,000

Complete Complete and in use

2014/2015

Nkora Water Project Gravity water project:Protection of spring,

construction of elevated tank and piping

July 2014 2,000,000

Complete Complete and in use

2014/2015

Bogichora Water Springs Fencing Spring area, placing of water points

and protection of spring

July 2014 1,200,000

Complete Complete and in use

2014/2015

Bonyamatuta Water Springs Fencing Spring area, placing of water points

and protection of spring

July 2014 1,100,000

Complete Complete and in use

2014/2015

Ramba Water Project Water Pipiping, Installation of pump and

electricity installation

July 2014 1,700,000

Complete Complete and in use

2013/2014

West Mugirango Constituency Office Construction of CDF Office July 2014 5,000,000

Complete Complete and in use

2014/2015

West Mugirango Constituency Office Construction of CDF Office July 2014 10,500,000

Ongoing Works at 30%

2013/2014

Igena Itambe Health Centre Construction of Health Facility:Foundation,

walling, roofing, painting and electrical

works

July 2014 500,000

Ongoing Works on 2nd floor

Page 5: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Nyanturago Health Centre Construction of Maternity Ward and

Laboratory:Foundation, walling, roofing,

painting and electrical works

July 2014 400,000

Ongoing

Walling,

roofing,plastering,doors

and windows done

2013/2014

Motagara Health Centre Construction of Health Facility:Foundation,

walling, roofing, painting and electrical

works

July 2014 400,000

Ongoing

Complete and

inuse.Handed over to

county Government

2013/2014

Geta Health Centre Construction of Health Facility:Foundation,

walling, roofing, painting and electrical

works

July 2014 400,000

Ongoing

Need additional funds for

equipment and ceiling

2013/2014

Gianchore health centre Construction of a maternity

ward:Foundation, walling, roofing, painting

and electrical works

July 2014 500,000

Ongoing

Taken over by county

Government for

completion

2013/2014

Nyansabakwa Health Centre Construction of Health Facility:Fixing doors

and windows, roofing, painting and

electrical works

July 2014 300,000

Ongoing Complete and in use.

2013/2014

Ogango Health Centre Construction of Health Facility:Foundation,

walling, roofing, painting and electrical

works

July 2014

300,000.00 Ongoing

Walling, roofing

done.Need additional

funds for completion

2013/2014

Gianchore Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

500,000.00 Ongoing Works in progress at 80%

2013/2014

Nyansabakwa Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

600,000.00 New

Awaiting funds from CDF

Board

2013/2014

Kenyambi Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

600,000.00 New

Awaiting funds from CDF

Board

2013/2014

Mongorisi Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

600,000.00 New

Awaiting funds from CDF

Board

2013/2014

Nyanturago Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

600,000.00 New

Awaiting funds from CDF

Board

2013/2014

Kenyerere Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

600,000.00 New

Awaiting funds from CDF

Board

2013/2014

Ogango Health Centre Construction of Pre-Fabricated Staff

House:Foundation, walling, roofing,

plastering and Electrical Works

July 2014

982,769.00 New

Awaiting funds from CDF

Board

2014/2015

Igena Itambe Health Centre Completion of Health Facility:Construction

of 2nd floor slab and firrst floor columns

July 2015 700,000

Ongoing Works on 2nd floor

2014/2015

Nyanturago Health Centre Completion of Health Facility:Flooring,

plastering and painting

July 2015 500,000

Ongoing

Walling,

roofing,plastering,doors

and windows done

2014/2015

Geta Health Centre Completion of Health Facility:Flooring,

plastering and painting

July 2015 500,000

Ongoing

Need additional funds for

equipment and ceiling

Page 6: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

Gianchore health centre Completion of staff house:Flooring,roofing,

plastering and painting

July 2015 700,000

Ongoing

Taken over by county

Government for

completion

2014/2015

Ogango Health Centre Completion of health

facility:Flooring,roofing, plastering and

painting

July 2015

800,000.00 Ongoing

Need additional funds for

equipment , plastering,

doors and windowss,

paintingand ceiling

2014/2015

Nyamokenye Health Centre Completion of health

facility:Flooring,plastering, windows and

painting

July 2015

500,000.00 Ongoing

Need additional funds for

equipment and ceiling

2014/2015

Mongorisi Health Centre Completion of a staff house:Painting,

plastering, roofing and electrical works

July 2015

600,000.00 Ongoing Complete and in use

2014/2015

Masosa Secondary School Completion of a story building with

classrooms and hall:Construction of first

floor columns and electrical works

July 2015 1,100,000

Ongoing Works on first floor

2014/2015

Nyamira Technical School Completion of a multipurpose hall storey

building;Construction of columns, plastering

and electrical works.

July 2015 1,100,000

Ongoing

Walling, roofing, filling of

columns done.Needs

more funds for

completion

2014/2015

Nyamaiya Secondary School Completion of a hall;plastering, painting and

electrical works.

July 2015 800,000

Ongoing

Complete and in use.To

be officially

Commissioned

2014/2015

Rirumi Secondary School Completion of Storey Building with

laboratory and admin block:Construction of

first floor columns and plastering , and

electrical works

July 2015 700,000

Ongoing Ground floor complete

2014/2015

Makairo Secondary School Completion of Storey Building with

laboratory :Construction of first floor

columns and plastering , and electrical works

July 2015 700,000

Ongoing Ground floor complete

2014/2015

St Tiberious Nyamotentemi Sec School Completion of classrooms in a storey

building:First floor walling, plastering and

electrical works.

July 2015 700,000

Ongoing Ground floor complete

2014/2015

Nami Secondary School Completion of storey Building with

laboratory:plastering and painting

July 2015 300,000

Ongoing

Plastering and Painting in

progress

2014/2015

Gesore PAG Secondary School Completion of a Library :First floor walling,

plastering and electrical works.

July 2015 700,000

Ongoing 1st floor slab done

2014/2015

St Teresa Secondary School - Bugo Completion of 3 classrooms storied

building:plastering, painting and electrical

works.

July 2015 800,000

Ongoing

Plastering and Painting in

progress

2014/2015

Nyagachi Secondary School Completion of a Twin Laboratory: walling,

plastering, roofing and electrical works.

July 2015 1,000,000

Ongoing 1st floor slab done

2014/2015

St Patrice Nyantaro School Construction of administration block:Walling

and electrical works

July 2015 700,000

Ongoing

One quarter of flooring

pending.All other works

done

Page 7: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

Nyachururu Secondary School Completion of a Laboratory: plastering and

electrical works.

July 2015 500,000

Ongoing Works on 1st floor

2014/2015

Geta Secondary School Completion of a Laboratory:Flooring

painting and electrical works.

July 2015 500,000

Ongoing

Needs more funds for

plastering and painting

2014/2015

Nyameru Sec School Completion of classrooms in a storey

building:2nd floor walling, plastering and

electrical works.

July 2015 800,000

Ongoing

Ground floor and first

floor complete

2014/2015

Rangenyo Girls Secondary School Completion of dining hall:Flooring,plastering

and painting

July 2015 800,000

Ongoing

Walling, roofing, filling of

columns done.Needs

more funds for

completion

2014/2015

Nyaisa Secondary School Construction of A multi purpose storey

Building :Foundation and part walling

July 2015 700,000

Ongoing Ground floor done

2014/2015

Nyakemincha Secondary School Construction of A multi purpose storey

Building :Foundation and part walling

July 2015 1,000,000

New

Foundation

done.Additional funds

allocated for completion

2014/2015

Nyakeore Secondary School Completion of Twin Lab: Roofing and

plastering and electrical works

July 2015 800,000

Ongoing

Foundation, walling,

roofing done.Additional

funds allocated for

completion

2014/2015

Gucha Secondary School Completion of A multi purpose storey

Building with laboratory:plastering and

painting

July 2015 800,000

Ongoing Works on 1st floor

2014/2015

Gekomoni Secondary School Construction of one twin pit latrine:Digging

of pit, foundation, walling , roofing,

plastering and painting

July 2015 300,000

New complete and in use.

2014/2015

Ekenyoro Secondary School Construction of a computer laboratory

:Foundation and walling

July 2015 1,000,000

New

Foundation, walling,

roofing done.Additional

funds allocated for

completion

2013/2014

Masosa Secondary School Construction of a story building with

classrooms and hall:Foundation, walling,

plastering, roofing,painting and electrical

works

July 2015 750,000

Ongoing Works on first floor

2013/2014

Nyamira Technical School Construction of a multipurpose hall storey

building;Foundation, Walling, plastering,

roofing, painting and electrical works.

July 2015 800,000

Ongoing

Walling, roofing, filling of

columns done.Needs

more funds for

completion

2013/2014

Nyamaiya Secondary School Construction of a hall;Foundation, Walling,

plastering, roofing, painting and electrical

works.

July 2015 300,000

Ongoing

Complete and in use.To

be officially

Commissioned

2013/2014

Kenyenya Secondary School Construction of 3 classrooms;Foundation,

Walling, plastering, roofing, painting and

electrical works.

July 2015 400,000

Ongoing

Needs additional funding

for plastering, doors and

windows and painting

Page 8: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Rirumi Secondary School Construction of Storey Building with

laboratory and admin block:Foundation,

walling, plastering and roofing and electrical

works

July 2015 500,000

Ongoing Ground floor complete

2013/2014

Nyabisimba Secondary School Construction of a Laboratory :Foundation,

walling, roofing, plastering and electrical

works.

July 2015 400,000

Ongoing

Needs additional funding

for plastering, doors and

windows ,

EQUIPMENTand painting

2013/2014

Makairo Secondary School Construction of storey building containing

classrooms, staff offices and Library

July 2015 700,000

Ongoing Ground floor complete

2013/2014

St Tiberious Nyamotentemi Sec School Construction of classrooms in a storey

building:Foundation, walling, roofing,

plastering and electrical works.

July 2015 600,000

Ongoing Ground floor complete

2013/2014

Embonga Secondary School Construction of 4 classrooms :Foundation,

walling, roofing, plastering and electrical

works.

July 2015 400,000

Ongoing

Needs additional funding

for plastering, doors and

windows ,

EQUIPMENTand painting

2013/2014

Nami Secondary School Construction of storey Building with

laboratory:Foundation, walling, plastering

and roofing and electrical works

July 2015 450,000

Ongoing

Plastering and Painting in

progress

2013/2014

Gesore PAG Secondary School Construction of a Library :Foundation,

walling, roofing, plastering and electrical

works.

July 2015 400,000

Ongoing 1st floor slab done

2013/2014

St Teresa Secondary School - Bugo Construction of 3 classrooms:Foundation,

walling, roofing, plastering and electrical

works.

July 2015 700,000

Ongoing

Plastering and Painting in

progress

2013/2014

St Josephs Kemasare Secondary School Construction of 2 classrooms:Foundation,

walling, roofing, plastering and electrical

works.

July 2015 400,000

Ongoing

Needs additional funds for

doors/windows, painting

and plastering

2013/2014

Bondeka Girls Secondary School Construction of 3 classrooms:Foundation,

walling, roofing, plastering and electrical

works.

July 2015 400,000

Complete

Complete and in use.To

be officially

Commissioned

2013/2014

Enchoro Secondary School Construction of a Laboratory:Foundation,

walling, plastering, roofing, installation of

equipment and electrical works.

July 2015 500,000

Ongoing

Additional funds allocated

for doors/windows,

plastering and painting

2013/2014

Nyagachi Secondary School Construction of a Twin

Laboratory:Foundation, walling, plastering,

roofing, installation of equipment and

electrical works.

July 2015 500,000

Ongoing

Foundation and 1st floor

slab done

Page 9: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Kuura Secondary School Construction of a Domitory:Foundation,

walling, plastering, roofing, installation of

equipment and electrical works.

July 2015 500,000

Ongoing

Additional funds allocated

for equipment

2013/2014

Nyachururu Secondary School Construction of a Laboratory:Foundation,

walling, plastering, roofing, installation of

equipment and electrical works.

July 2015 500,000

Ongoing

Ground floor

complete.Additional funds

allocated for completion

2013/2014

Mongorisi Secondary School Construction of a Laboratory:Foundation,

walling, plastering, roofing, installation of

equipment and electrical works.

July 2015 400,000

Complete

Complete and in use.To

be officially

Commissioned

2013/2014

Ibucha Primary School Construction of one classrooms from

foundation,walling,roofing,fixation of

doorsand windows, painting and electrical

works.

July 2015 600,000

New

PMC IN PROGRESS TO

COMPLETION

2013/2014

Marindi Primary School Renovation of 4 classrooms and

administration block:Replacement of inner

wall, plastering and painting

July 2015 300,000

Complete

Complete and in

use.Funds allocated for

renovation of 2 more

classes

2013/2014

Marindi Primary School Completion of 2

classrooms:Flooring,plastering, fixing doors

and windows, painting and electrical works

July 2015 300,000

Complete Complete and in use.

2013/2014

Kenyenya Boarding Primary School Completion of 2 classrooms:walling,Roofing,

plastering and electrical works

July 2015 500,000

Ongoing

Work in progress to

completion

2013/2014

Kabatia Primary School Renovation of 6 classrooms:Roofing, fixing

doors and windows

July 2015 500,000

Ongoing

Work in progress to

completion

2013/2014

Nyakeore Special School Completionof 2 classrooms: walling,Roofing,

plastering, painting and electrical works

July 2015 650,000

Ongoing Complete and in use

2013/2014

Sironga Primary School Renovation of 5 classrooms:Roofing,

plastering and fixing doors and windows

July 2015 500,000

Ongoing Complete and in use

2013/2014

Makairo Primary School Completion of a hall:Plastering and painting

and electrical works

July 2015 500,000

Ongoing

Additional funds needed

fo completion

2013/2014

Bundo Primary School Completion of one classroom:Foundation,

walling, roofing and electrical works

July 2015 200,000

Complete Complete and in use

2013/2014

Bundo Primary School Construction of one classroom:Foundation,

walling, roofing and electrical works

July 2015 500,000

Complete Complete and in use

2013/2014

Marara Primary School Construction of admin block:Foundation,

walling, roofing and electrical works

July 2015 500,000

0ngoing

Additional funding

needed for plastering and

paintingAdditional funds

needed fo completion

Page 10: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Ratandi Primary School Renovation of of 3 classrooms:Flooring,

roofing and fixing doors and windows

July 2015 500,000

Complete Complete and in use

2013/2014

Riamandere Primary School Construction of 2 classrooms:walling,

roofing and plastering

July 2015 500,000

Ongoing

Plastering and painting to

be done

2013/2014

Bosose Primary School Construction of 2 classrooms: plastering ,

painting and electrical works

July 2015 300,000

Ongoing

Plastering and painting to

be done

2013/2014

Motagara Primary School Construction of 2 classrooms:plastering,

painting AND Electrical works

July 2015 300,000

Ongoing

Plastering and painting to

be done

2013/2014

Riasindani Primary School Completion of one twin Pit Latrine: walling,

roofing, painting, plastering and electrical

works

July 2015 200,000

Complete Complete and in use

2013/2014

Gianchore Primary School Construction of one twin Pit Latrine:Digging

pit, foundation, walling, roofing, painting

and electrical works

July 2015 300,000

Complete Complete and in use

2013/2014

Gianchore Primary School Construction of 2 classrooms:Roofing,

plastering and flooring

July 2015 400,000

Complete Complete and in use

2013/2014

Etono Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doors

July 2015 500,000

Complete Complete and in use

2013/2014

Kiambere Primary School Renovation of 4 classrooms:Repair of floor,

roof, windows and doors

July 2015 600,000

Complete Complete and in use

2013/2014

Rateti Primary School Completion of two classroom:Plastering,

flooring and painting

July 2015 300,000

Ongoing

Plastering and painting to

be done

2013/2014

Nyaigesa Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doors

July 2015 500,000

Complete Complete and in use

2013/2014

Bondeka Primary School Renovation of 4 classrooms:Repair of floor,

roof, windows and doors

July 2015 600,000

Complete Complete and in use

2013/2014

Riakimai Boarding Primary School Construction of Hall:Walling and roofing July 2015 600,000

Ongoing

Plastering, flooring and

painting to be done

2013/2014

Tente Primary School Construction of two class room:Walling of

2nd class, roofing, plastering and painting

July 2015 400,000

Complete Complete and in use

2013/2014

Omokonge Special Primary School Construction of 2 twin pit latrines :Digging of

pit, foundation, walling,plastering, painting

and electrical works

July 2015 300,000

Complete Complete and in use

2013/2014

Nyanturago Primary School Completion of hall:Walling and plastering July 2015 500,000

Ongoing

Additional funds needed

for completion

2013/2014

Enchoro Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doors

July 2015 500,000

Complete Complete and in use

Page 11: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Rirumi Primary School Construction of 2 twin pit latrines :Digging of

pit, foundation, walling,plastering, painting

and electrical works

July 2015 300,000

Complete Complete and in use

2013/2014

Ekoro Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doors

July 2015 400,000

Complete Complete and in use

2013/2014

Nyamwetureko Primary School Construction of one twin Pit Latrine:Digging

pit, foundation, walling, roofing, painting

and electrical works

July 2015 400,000

Complete Complete and in use

2013/2014 Mobamba Primary School Renovation of 4 classrooms:Roofing July 2015 400,000 Complete Complete and in use

2013/2014

Otanyore Primary School Construction of Hall:Walling and roofing July 2015 700,000

Ongoing

Additional funds needed

for completion

2013/2014

Embonga Primary School Completion of 2

classrooms:Flooring,plastering, fixing doors

and windows, painting and electrical works

July 2015 500,000

Ongoing

work in progress to

completion

2013/2014

Gesore Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doors

July 2015 400,000

Complete Complete and in use

2013/2014

Bomondo Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doors

July 2015 500,000

Complete Complete and in use

2013/2014

Tonga Omunuri Boarding Primary School Construction of a storey a Multipurpose

building:Filling first floor columns and

plastering

July 2015 800,000

Ongoing

1st floor slab done.More

funds allocated

2013/2014

Omosasa Primary School Completion of 2

classrooms:Flooring,plastering, fixing doors

and windows, painting and electrical works

July 2015 400,000

Ongoing

Additional funds allocated

for completion

2013/2014

Geseneno Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doors

July 2015 400,000

Complete Complete and in use

2013/2014

Omokonge Primary School Completion of 2 classrooms:plastering, fixing

doors and windows, painting and roofing

July 2015 200,000

Complete Complete and in use

2014/2015

Ibucha Primary School Construction of one classrooms from

foundation,walling,roofing,fixation of

doorsand windows, painting and electrical

works.

July 2015 500,000

Complete Complete and in use

2014/2015

Marindi Primary School Renovation of three classrooms:walling,

roofing (painting,plastering & flooring)

July 2015 700,000

Complete Complete and in use

2014/2015

Sasati Primary School Construction of 3 classrooms:Foundation,

walling,Roofing, painting and electrical

works

July 2015 400,000

Complete Complete and in use

2014/2015

Tonga Pri School Renovation of 2 classrooms:Plastering,

roofing and fixing doors and windows

July 2015 300,000

Complete Complete and in use

Page 12: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

Kenyenya Boarding Primary School Construction of 2 classrooms:Foundation,

walling,Roofing, painting and electrical

works

July 2015 300,000

Ongoing

Works heading to

completion

2014/2015

Kabatia Primary School Renovation of one classrooms:Roofing,

fixing doors and windows

July 2015 250,000

Complete Complete and in use

2014/2015

Nyakeore Special School Construction of 2 classrooms:Foundation,

walling,Roofing, painting and electrical

works

July 2015 350,000

Ongoing

Works heading to

completion

2014/2015

Bonyunyu Primary School Renovation of one classrooms:Roofing,

plastering, fixing of doors and windows

July 2015 300,000

Complete Complete and in use

2014/2015

Ekerama Primary School Construction of 2 classrooms:Foundation,

walling,Roofing, painting and electrical

works

July 2015 400,000

Ongoing

Additional funds allocated

for completion

2014/2015

Bobembe Boarding Primary School Construction of 4 CLASSROOMS:Foundation,

walling, roofing and electrical works

July 2015 400,000

2014/2015

Nyameru Primary School Construction of pit a latrine:Foundation,

walling, roofing and electrical works

July 2015 200,000

Complete Complete and in use

2014/2015

Sironga Primary School Renovation of 5 classrooms:Roofing,

plastering and fixing doors and windows

July 2015 600,000

Complete Complete and in use

2014/2015

Nyaisa Primary School Renovation of admin block:Plastering,

roofing and windows/doors and electrical

works

July 2015 300,000

Complete Complete and in use

2014/2015

Makairo Primary School Construction of a hall:Foundation, walling,

roofing and electrical works

July 2015 400,000

Ongoing

Additional funds NEEDED

for completion

2014/2015

Nyairicha Special School Construction of storey Building:Foundation,

walling, roofing, plastering and electrical

works.

July 2015 500,000

Ongoing

Additional funds NEEDED

for completion

2014/2015

Bundo Primary School Construction of classrooms:Foundation,

walling, roofing and electrical works

July 2015 300,000

Ongoing

Additional funds NEEDED

for completion

2014/2015

Matierio Primary School Renovation of 2 classrooms:Plastering,

roofing and fixing doors and windows

July 2015 300,000

Complete Complete and in use

2014/2015

Marara Primary School Construction of admin block:Foundation,

walling, roofing and electrical works

July 2015 200,000

Ongoing

Works at 80%.Additional

funds Allocated for

completion

2014/2015

Ratandi Primary School Renovation of of 3 classrooms:Flooring,

roofing and fixing doors and windows

July 2015 300,000

Complete Complete and in use

Page 13: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

St Josephs Nyamira Primary School Construction of 3 classrooms:Foundation,

walling, roofing and plastering

July 2015 600,000

Foundation and

walling done

Additional funds allocated

for completion

2014/2015

Riamandere Primary School Construction of classrooms:Foundation,

walling, roofing and plastering

July 2015 200,000

Complete Complete and in use

2014/2015

Nyagachi Primary School Renovation of 1 classroom:Plastering,

roofing and fixing doors and windows

July 2015 200,000

Complete Complete and in use

2014/2015

Nyantaro Primary School Renovation of 1 classroom:Plastering,

roofing and fixing doors and windows

July 2015 300,000

Complete Complete and in use

2014/2015

Ting'a Primary School Renovation of 1 classroom:Plastering,

roofing and fixing doors and windows

July 2015 200,000

Complete Complete and in use

2014/2015

Endabu Primary School Construction of 2 classrooms:Foundation,

walling, roofing and plastering

July 2015 300,000

Ongoing

Works heading to

completion

2014/2015

Bosose Primary School Construction of 2 classrooms:Foundation,

walling, roofing and plastering

July 2015 300,000

Ongoing

Works heading to

completion

2014/2015

Egesieri Primary School Renovation of one classrooms:Roofing,

plastering, fixing doors and windows

July 2015 200,000

Complete Complete and in use

2014/2015

Kenyambi Primary School Construction of an administration

block:Foundation, walling, roofing and

plastering AND Electrical works

July 2015 300,000

Ongoing

Additional funds allocated

for completion

2014/2015

Bomorito Primary School Renovation of 6 classrooms:Foundation,

walling, roofing and plastering

July 2015 300,000

Complete Complete and in use

2014/2015

Motagara Primary School Construction of 2 classrooms:Foundation,

walling, roofing and plastering AND Electrical

works

July 2015 300,000

Ongoing

Plastering and painting to

be done

2013/2014

Kiambere Polytechnic Construction of 2 pit latrines: Foundation,

walling,PLASTERING, roofing and painting

and electrical works

July 2015 300,000

Complete Complete and in use

2013/2014

Bobembe Village Polytechnic Construction of 2 classrooms: Foundation,

walling,PLASTERING, roofing and painting

and electrical works

July 2015 426,055

New Works In progress

2013/2014

Nyainogu Village Polytechnic Construction of administration block and

lecture hall:Foundation , walling, roofing,

painting and electrical works

July 2015 300,000

Complete Complete and in use

2013/2014

Nyaigesa Youth Polytechnic Construction of 3 classrooms:Foundation ,

walling, roofing, painting and electrical

works

July 2015 350,000

Ongoing

Foundation,walling and

part roofing done

2014/2015

Kiambere Polytechnic Completion of 2 Classrooms:

walling,PLASTERING, roofing and painting

and electrical works

July 2015 400,000

Ongoing

Plastering and painting to

be done

Page 14: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

Bobembe Village Polytechnic Completion of 2 classrooms: ,plastering,

roofing and painting and electrical works

July 2015 500,000

New Works I progress

2014/2015

Nyaigesa Youth Polytechnic Completion of a hall: walling, roofing, and

electrical works

July 2015 800,000

Ongoing

Foundation,walling and

part roofing done

2014/2015

Mariba Village Polytecnic Completion of two classrooms:flooring,

plastering and painting.

July 2015 300,000

Complete Complete and in use

2014/2015

Ibucha Polytechnic Completion of two classrooms:flooring ,

plastering, painting, fixing of glass windows/

doors.

Sept 2015 500,000

Complete Complete and in use

2013/2014

Kiambere AP Camp Renovation of AP Camp:Roofing, Flooring

and windows

Sept 2015 200,000

Complete Complete and in use

2013/2014

Etono AP Camp Renovation of AP Camp:Roofing, Flooring

and windows

Sept 2015 200,000

Complete Complete and in use

2013/2014

Nyagachi Chiefs camp Construction of two pit latrines:Digging of

pit, foundation, walling, roofing and

plastering

Sept 2015 200,000

Complete Complete and in use

2014/2015

Kebirigo Chiefs Office Completion of chief's office:Roofing,

plastering

Sept 2015 700,000

ongoing

Additional funds allocated

for completion

2014/2015

Gianchore Chiefs Office Completion of chief's office:Roofing,

plastering

Sept 2015 700,000

ongoing

Additional funds allocated

for completion

2013/2014

Construction and Erection of

Constituency Project Sign Posts

Design, construction and erection of 200

project sign posts@ Ksh 10,000 each

Sept 2015 500,000.00

New

Awaiting Funds from CDF

board

2013/2014

Constituency Motor Vehicle Purchase of ONE CDF Office Motor Vehicle. Sept 2015 5,000,000.00

Complete

Vehicle purchased and

body built

2014/2015

Constituency Motor Vehicle Purchase of ONE CDF Office Motor Vehicle. Sept 2015 1,500,000.00

Complete

Vehicle purchased and

body built

2014/2015

Electricity Installation of electricity transformers in all

wards within the constituency.

Sept 2015

4,000,000.00

Ongoing

Funds transferred to REA

for installation of

transformers.Works at

50%

2013/2014

Marindi Tea Buying Centre Completion of Tea Buying Centre:Roofing

and plastering

Sept 2015 150,000

Complete Complete and in use

2013/2014

Getiesi Tea Buying Centre Completion of Tea Buying

Centre:Completion of Plastering and flooring

Sept 2015 150,000

Complete Complete and in use

2013/2014

Rianyaigoti Tea Buying Centre Completion of Tea Buying Centre:Roofing

and plastering

Sept 2015 150,000

Complete Complete and in use

2013/2014

Nyankongo Tea Buying Centre Completion of Tea Buying

Centre:completion of Roofing

Sept 2015 60,000

Complete Complete and in use

2013/2014

Kemasare Tea Buying Centre Completion of Tea Buying

Centre:completion of Roofing and plastering

Sept 2015 100,000

Complete Complete and in use

Page 15: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Kianyabao Tea Buying Centre Completion of Tea Buying Centre:Roofing

and plastering

Sept 2015 150,000

Complete Complete and in use

2013/2014

Nyabite Tea Buying Centre Completion of Tea Buying Centre:Roofing

and plastering

Sept 2015 60,000

Complete Complete and in use

2013/2014

Bosiango Tea Buying Centre Completion of Tea Buying Centre:Roofing

and plastering

Sept 2015 150,000

Complete Complete and in use

2013/2014

Bomondo Tea Buying Centre Completion of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2013/2014

Getare Tea Buying Centre Completion of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2013/2014

Riosiri Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 100,000

Complete Complete and in use

2013/2014

Riamisire Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 150,000

Complete Complete and in use

2013/2014

Sironga Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 200,000

Complete Complete and in use

2013/2014

Rianyagwoka Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 100,000

Complete Complete and in use

2013/2014

Nyamaiya Tea Buying Centre Completion of Tea Buying Centre: Roofing

and flooring

Sept 2015 150,000

Complete Complete and in use

2013/2014

Rangenyo Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 60,000

Complete Complete and in use

2013/2014

Karantina Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 150,000

Complete Complete and in use

2013/2014

Rianyachoti Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 150,000

Complete Complete and in use

2013/2014

Kebirigo Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 200,000

Complete Complete and in use

2013/2014

Momoima Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 130,000

Complete Complete and in use

2013/2014

Nyabomite Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 100,000

Complete Complete and in use

2013/2014

Gianchore Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooring

Sept 2015 150,000

Complete Complete and in use

2013/2014

Nyakeore Tea Buying Centre Completion of Tea Buying Centre:

Completion of plastering and flooring and

fixing of doors and windows

Sept 2015 150,000

Complete Complete and in use

2013/2014

Rianyachani Tea Buying Centre Construction of Tea Buying

Centre:Foundation and walling

Sept 2015 200,000

Complete Complete and in use

2013/2014

Kenyenya Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Riamoti Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Bundo KB Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Ibucha Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 65,787

Complete Complete and in use

2013/2014

Bosose Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofing

Sept 2015 200,000

Complete Complete and in use

Page 16: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2013/2014

Riorao Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Nyamonyo Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Rianyaundi Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Omotembe Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Getaari Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Monga Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 100,000

Complete Complete and in use

2013/2014

Makairo Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Nyagachi Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofing

Sept 2015 70,000

Complete Complete and in use

2013/2014

Nyaigwa Tea Buying Centre Renovation of Tea Buying Centre:Flooring,

plastering and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Miruka Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofing

Sept 2015 100,000

Complete Complete and in use

2013/2014

Riamaangi Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Matierio Tea Buying Centre Renovation of Tea Buying Centre:Flooring,

plastering and roofing

Sept 2015 150,000

Complete Complete and in use

2013/2014

Mabundu Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofing

Sept 2015 150,000

Complete Complete and in use

2014/2015

Konate Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Omosaria Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Kegogi Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Bosiango Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Ibucha Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Mabundu Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Gesore Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Matierio Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Gekomoni Tea Buying Centre Construction of Tea Buying

Centre:Foundation, walling,roofing and

electrical works

Sept 2015 150,000

Complete Complete and in use

2014/2015

Nyamokenye Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Ikobe Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

Page 17: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2014/2015

Nyanturago Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Bosose Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Motagara Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Riorao Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2014/2015

Embonga Tea Buying Centre Construction of Tea Buying Centre:Roofing Sept 2015 150,000

Complete Complete and in use

2013/2014

FORMULATION OF CONSTITUENCY

STRATEGIC PLAN

Formulation and design of 5 YearC

onstituency Strategic Plan

Sept 2015 600,000.00

Complete Complete

2014/2015

FORMULATION OF CONSTITUENCY

STRATEGIC PLAN

Formulation and design of 5 YearC

onstituency Strategic Plan

Sept 2015 1,200,000.00

Complete Complete

2014/2015

Audit Fees FY 14/15 Constituency Accounts Audit fees 500,000.00

New

Disbursement halted by

the board

2015/16 Employee Salaries Payment of staff salaries and Gratuity 1,800,000 Ongoing Salary Payment Ongoing

2015/16

Goods and Services Purchase of office stationary, fuel, vehicle

repairs, telephone expenses and subsistenceJuly 2016 3,000,000

Complete Complete

2015/16

Purchase of Furniture and Office

Equipments

Purchase of office furniture and equipment July 2016 200,000

Complete Complete and in use

2015/16

Purchase of Computers Purchase of one CDFC laptop and One

ComputerJuly 2016 200,000

Complete Complete and in use

2015/16 NSSF Staff NSSF Remmitances July 2016 45,000 Complete Complete

2015/16 NHIF Staff NHIF Remmitances July 2016 45,000 Complete Complete

2015/16

Committee Allowances and Expenses Committee sitting allowances and expenses July 2016 2,330,754

Complete Complete

2015/16

Emergency Fund Reserve fund for emergencies and disasters

within the constituencyJuly 2016

5,767,647.00 Complete

Emergency funds

allocated to emergency

projects now in use

2015/16

Tertiary Institutions Bursary Fees Payment for needy students in colleges

and universities and activities for

enhancement in performance in national

examinations.

July 2016 12,000,000

Complete

Funds allocated and

disbursed to needy

students

2015/16

Secondary Schools Bursary Fees Payment for needy students in

Secondary SchoolsJuly 2016 3,500,000

Complete

Funds allocated and

disbursed to needy

students

2015/16

Mocks/Cats Payments for mocks and CATS in Primary

and secondary schoolsJuly 2016 500,000

Complete

Funds released for mocks

and CATS

2015/16

Goods and Services Purchase of stationary, fuel, vehicle repairs,

telephone expenses and subsistence in M&EJuly 2016

1,000,000.00 Complete Complete

2015/16 Committee Expenses Committee M&E Expenses July 2016 2,060,377.00 Complete Complete

2015/16

CDFC/PMC Capacity Building PMC Training and capacity building

expensesJuly 2016

750,000.00 Complete Complete

2015/16 Nyabite - Riamine Soil ConservationPrevention of Soil Erosion- Building of Culverts and Gabions 1,500,000

Works yet to be done

Awaiting for funds from

NGCDF Board

Page 18: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

West Mugirango Constituency Sports Committee

Sports activities for men and women within the constituency

July 2016

500,000 Complete

Funds released and used

for sports activities

2015/16

Electricity Eletrification and wiring of schools in all

wards within the constituency.July 2016

4,000,000.00 Complete Complete and in use

2015/16

Nyabite-Omonyia-Nyabite Road Bush Clearing, Side Drainage and Grading

of Road .2.5kmJuly 2016

1,100,000 Complete Complete and in use

2015/16

Bonyunyu-Nyakunguru-Nyabite Road Bush Clearing, Side Drainage and Grading

of Road .6kmJuly 2016

2,100,000 Complete Complete and in use

2015/16

Nyamokeri-Ramba-Bosose-Erami Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,200,000 Complete Complete and in use

2015/16

Nyamatoki-Egetongo-Nyamotentemi-

Erami Road

Bush Clearing, Side Drainage and Grading

of Road .4kmJuly 2016

1,000,000 Complete Complete and in use

2015/16

Sironga Stage - Kebacha Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,000,000 Complete Complete and in use

2015/16

Riobonyo-Rioigo-Riogao Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,000,000 Complete Complete and in use

2015/16

Bondeni-Kianyabongere Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,100,000 Complete Complete and in use

2015/16

Nyabomite-Bundo-Ombaka Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,100,000 Complete Complete and in use

2015/16

Nyagachi-Kianyabao-Riosiri Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,100,000 Complete Complete and in use

2015/16

Rianyaundi-Kianginda Road Bush Clearing, Side Drainage and Grading

of Road .3kmJuly 2016

1,000,000 Complete Complete and in use

2015/16 Bundo Brothers Foot Bridge Installation of Culverts July 2016 1,500,000 Complete Complete and in use

2015/16 Nyabite - Rangenyo Foot Bridge Installation of Culverts July 2016 1,500,000 Complete Complete and in use

2015/16 Nyairicha - Bundo Foot Bridge Installation of Culverts July 2016 1,200,000 Complete Complete and in use

2015/16 Nyabite - Otanyore Foot Bridge Installation of Culverts July 2016 1,800,000 Complete Complete and in use

2015/16 Nyairosa - Bokimo Foot Bridge Installation of Culverts July 2016 1,500,000 Complete Complete and in use

2015/16 Kuura - Bosiango Foot Bridge Installation of Culverts July 2016 1,500,000 Complete Complete and in use

2015/16

Bosamaro Masaba Water Springs Fencing Spring area, placing of water points

and protection of springJuly 2016 700,000

Complete Complete and in use

2015/16

Nyamaiya Water Springs Fencing Spring area, placing of water points

and protection of springJuly 2016 1,000,000

Complete Complete and in use

2015/16

Mongorisi Bore hole Piping for water supply to community and

Installation of Power and other associated

Works

2,000,000

Works not yet done

Awaiting for funds from

NGCDF Board

2015/16

Keberigo - Songonga Bore hole Piping for water supply to community and

Installation of Power and other associated

Works

July 2016 2,000,000

Complete

Complete and works to be

commissioned

2015/16

Township Water Springs Fencing Spring area, placing of water points

and protection of springJuly 2016 800,000

Complete Complete and in use

2015/16

Kionyomo Water Project Piping for water supply to community from

Spring and Installation of Power and other

associated Works

1,000,000

Works not yet done

Awaiting for funds from

NGCDF Board

2015/16

Kenyenya Water Project Piping for water supply to community from

Spring and Installation of Power and other

associated Works

July 2016 1,400,000

Complete Complete and in use

2015/16

Ramba Water Project Completion of Pipiping, Installation of

pump and electricity installationJuly 2016 600,000

Complete Complete and in use

Page 19: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Bogichora Water Springs Fencing Spring area, placing of water points

and protection of springJuly 2016 1,300,000

Complete Complete and in use

2015/16

Bonyamatuta Water Springs Fencing Spring area, placing of water points

and protection of springJuly 2016 1,200,000

Complete Complete and in use

2015/16

Kemasare Tea Buying Centre Completion of Tea Buying

Centre:completion of Roofing and plasteringJuly 2016 100,000

Complete Complete and in use

2015/16

Getare Tea Buying Centre Completion of Tea Buying Centre:Roofing July 2016 100,000

Complete Complete and in use

2015/16

Riosiri Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooringJuly 2016 100,000

Complete Complete and in use

2015/16

Nyamaiya Tea Buying Centre Completion of Tea Buying Centre: Roofing

and flooringJuly 2016 100,000

Complete Complete and in use

2015/16

Karantina Tea Buying Centre Completion of Tea Buying Centre:

Completion of Roofing and flooringJuly 2016 100,000

Complete Complete and in use

2015/16

Rianyachani Tea Buying Centre Construction of Tea Buying

Centre:Foundation and wallingJuly 2016 150,000

Complete

Work in progress at

75%.Additional funds

needed for completion

2015/16

Riamoti Tea Buying Centre Completion of Tea Buying Centre:Flooring

and roofingJuly 2016 100,000

Complete Complete and in use

2015/16

Rianyaundi Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingJuly 2016 100,000

Complete Complete and in use

2015/16

Makairo Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingJuly 2016 100,000

Complete Complete and in use

2015/16

Miruka Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofingJuly 2016 100,000

Complete Complete and in use

2015/16

Matierio Tea Buying Centre Renovation of Tea Buying Centre:Flooring,

plastering and roofingJuly 2016 100,000

Complete Complete and in use

2015/16

Nyagwakwa Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofingJuly 2016 100,000

Complete Complete and in use

2015/16

Omosasa Tea Buying Centre Completion of Tea Buying Centre:Flooring,

plastering and roofingJuly 2016 150,000

Complete Complete and in use

2015/16

Tin'ga Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingJuly 2016 150,000

Complete Complete and in use

2015/16

Mogumo Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingJuly 2016 150,000

Complete Complete and in use

2015/16

Riamasi Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingJuly 2016 140,000

Complete Complete and in use

2015/16

Rionuko Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingJuly 2016 150,000

Complete Complete and in use

2015/16

Riamicheka Tea Buying Centre Construction of Tea Buying

Centre:Foundation and wallingJuly 2016 183,792

Complete Complete and in use

2015/16

Ramba Tea Buying Centre Renovation of Tea Buying Centre:Roofing

and FlooringJuly 2016 150,000

Complete Complete and in use

2015/16

Riamocheche Tea Buying Centre Construction of Tea Buying

Centre:Foundation and wallingSept 2016 150,000

Complete

Work in progress at

75%.Additional funds

needed for completion

2015/16

Iranda Tea Buying Tea Centre Renovation of Tea Buying Centre:Roofing

and FlooringSept 2016 150,000

Complete Complete and in use

Page 20: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Mokwerero Tea Buying Centre Renovation of Tea Buying Centre:Roofing

and FlooringSept 2016 150,000

Complete Complete and in use

2015/16

Nyamuronga Tea Buying Centre Renovation of Tea Buying Centre:Roofing

and FlooringSept 2016 150,000

Complete Complete and in use

2015/16

Nyachogochogo Tea Buying Centre Construction of Tea Buying

Centre:Foundation and wallingSept 2016 150,000

Complete

Work in progress at

75%.Additional funds

needed for completion

2015/16

Omosocho Tea Buying Centre Completion of Tea Buying Centre:Fooring,

plastering, Installation of doors and

windows

Sept 2016 100,000

Complete Complete and in use

2015/16

Nyabisimba Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingSept 2016 150,000

Complete Complete and in use

2015/16

Mageri Tea Buying Centre Construction of Tea Buying

Centre:Foundation and wallingSept 2016 100,000

Complete Complete and in use

2015/16

Nyankarangania Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingSept 2016 150,000

Complete Complete and in use

2015/16

Kiambere Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingSept 2016 100,000

Complete Complete and in use

2015/16

Kiabiraa Tea Buying Centre Renovation of Tea Buying Centre:Flooring

and roofingSept 2016 100,000

Complete Complete and in use

2015/16

Risa Tea Buying Centre Renovation of Tea Buying Centre:Roofing Sept 2016 150,000

Complete Complete and in use

2015/16

Igena Itambe Health Centre Completion of Health Facility:Roofing 400,000

Ongoing

Work in pogress at

45%.Awaiting for

allocated funds from NG-

CDF Board.Need more

funds for completion.

2015/16

Nyanturago Health Centre Completion of Health Facility: Plastering and

painting and Electrical Works

400,000

Ongoing

Work in pogress at

75%.PMC to speed up

works

2015/16

Geta Health Centre Completion of Health Facility:Painting, Land

scaping and Purchase of Equipment and

Furniture

July 2016 900,000

Complete Complete and in use

2015/16

Ogango Health Centre Completion of health facility:Plastering ,

Doors and Windows and painting 500,000.00 Ongoing

Awaiting for funds from

NGCDF Board

2015/16

Geta Health Centre Construction Pit Latrine:Digging of Pit,

Foundation,Walling,Roofing,Plastering,Painti

ng and Electrical Works

July 2016

300,000.00 Complete Complete and in use

2015/16

Nyamokenye Health Centre Completion of health facility:Land scaping ,

painting and acquisition

equipment/Furniture and Land 600,000.00 Ongoing

Awaiting for funds from

NGCDF Board

2015/16

Motontera Health Centre Construction of Incenerator:Foundation,

walling, plastering and Painting

300,000.00 Ongoing

Awaiting for funds from

NGCDF Board

2015/16

Kenyenya Health Centre Renovation of Health Facility:Repair of sewer

system 300,000.00 Ongoing

Awaiting for funds from

NGCDF Board

2015/16

Nyamaiya Health Centre Maternity Wing completion:Plastering,

Windows and Doors Painting and Electrical

works

July 2016

400,000.00 Complete Complete and in use

Page 21: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Ramba Health Centre Completion of Health facility:Purchase of

equipment and Furniture, completion of Pit

Latrine and Incenerator

700,000.00 Ongoing Work in progress at 50%.

2015/16

Etono Health Centre Completion of health facility:Plastering ,

Doors and Windows, electrical works and

painting

July 2016

500,000.00 Ongoing

Work in progress at

35%.Need more funds for

completion

2015/16

Masosa Secondary School Completion of a story building with

classrooms and hall:Plastering

500,000

Ongoing

Additional funds allocated

for completion

2015/16

Nyamira Technical School Completion of a multipurpose hall storey

building;Plastering, doors and windows

1,200,000

Ongoing

Additional funds allocated

for completion

2015/16

Makairo Secondary School Completion of Storey Building with

laboratory :Completion of first floor,

roofing,plastering and electrical works

1,200,000

Ongoing

Additional funds allocated

for completion

2015/16

Nyagachi Secondary School Completion of a Twin Laboratory:

Completion of first floo columns and

plastering

500,000

Ongoing

Additional funds allocated

for completion

2015/16

Makairo Secondary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

300,000

Ongoing

Works at 50%.PMC to

speed up works

2015/16

Nyachururu Secondary School Completion of a Laboratory: Construction of

first floor columns and plastering

500,000

Ongoing

Additional funds allocated

for completion

2015/16

Geta Secondary School Completion of a Laboratory:Flooring

painting and electrical works.July 2016 600,000

Complete Complete and in use

2015/16

Rangenyo Girls Secondary School Completion of dining hall:plastering ,

electrical works and painting

400,000

Ongoing

Works at 90%.Additional

funds allocated for

completion

2015/16

Nyakemincha Secondary School Construction of A multi purpose storey

Building :First floor walling

500,000

Ongoing

Works at 30%.Additional

funds allocated for

completion

2015/16

Kebirigo High School Construction of Twin Lab: Foundation and

walling and roofing

1,000,000

Ongoing

Works at 10%.Additional

funds allocated for

completion

2015/16

Gucha Secondary School Completion of A multi purpose storey

Building with laboratory:Construction of

first floor columns and plastering

400,000

Ongoing

Works at 40%.Additional

funds allocated for

completion

2015/16

Kenyenya Secondary School Construction of Three Class

room:Roofing,painting, plastering and

electrical works

July 2016 500,000

Complete Complete and in use

2015/16

Marindi Secondary School Construction of a Storeyed Tuition

Block:Foundation and walling

1,000,000

Ongoing

Works at 10%.Additional

funds allocated for

completion

Page 22: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Bonyunyu Secondary School Construction of a dormitory:Foundation and

walling

500,000

Ongoing

Works at 20%.Additional

funds allocated for

completion

2015/16

Nyaigwa Girls Secondary School Construction of Three Class

room:Foundation , walling, electrical works

and roofing

1,200,000

Ongoing

Works at 25%.Additional

funds allocated for

completion

2015/16

Kebirigo High School Renovation 2 Classrooms:Repair of roof,

walls and floorJuly 2016 300,000

Complete Complete and in use

2015/16

Senator Kebaso Secondary School Construction of a Multi purpose

Hall:Foundation and walling

500,000

Ongoing

Works at 30%.Additional

funds allocated for

completion

2015/16

Marani Girls Secondary School Installation of Lightening Arrestors July 2016 300,000

New

Funds disbursed to PMC

which is planning to begin

works.

2015/16

Kemasare Secondary School Construction of One Classeroom:Foundation

, walling, electrical works, painting and

roofing

July 2016 500,000

Complete Complete and in use

2015/16

Rateti Secondary School Renovation 2 Classrooms:Repair of roof,

walls and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Bosiango Sec School Renovation 2 Classrooms:Repair of roof,

walls and floorJuly 2016 500,000

Complete Complete and in use

2015/16

Nyabisimba Secondary School Completion of a laboratory:Roofing,

plastering, painting and Purchase of

equipment and furniture

1,200,000

Ongoing

Works at 80%.Additional

funds to be allocated for

completion

2015/16

Nyachogochogo Secondary School Construction of 3 Classrooms:Foundation ,

Walling,Roofing,Installation of Doors and

Windows

1,000,000

Ongoing

Works at 80%.Additional

funds to be allocated for

completion

2015/16

Bomorito Sec School Completion of a hall:Plastering and fixing of

doors and windows

500,000

Ongoing

Works at 70%.Additional

funds to be allocated for

completion

2015/16

Nyachogochogo Secondary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Omosasa Secondary School Completion of a hall:Plastering and fixing of

doors and windows

500,000

Ongoing

Works at 50%Additional

funds allocated for

completion

2015/16

Nyamira Technical School Construction of Dormitory:Foundation,

walling and roofingJuly 2016 800,000

New

Funds disbursed to PMC

which is planning to begin

works.

2015/16

Bondeka Girls Secondary School Construction of an Administration

Block:Foundation, walling and roofing

500,000

Ongoing

Works at 20%.Additional

funds allocated for

completion

Page 23: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Kuura Secondary School Completion of a laboratory:Purchase of

equipment and furniture

400,000

Ongoing

Works at 80%.Additional

funds allocated for

completion

2015/16

Gekomoni Secondary School Construction of two Classrooms:Digging of

pit, foundation,walling,flooring, roofing,

painting and electrical works

July 2016 1,000,000

Complete Complete and in use

2015/16

Riamandere Secondary School Completion of two

Classrooms:Plastering,painting and electrical

works

July 2016 300,000

Complete Complete and in use

2015/16

Nyantaro Secondary School Completion of an administration

block:Roofing and PlasteringJuly 2016 300,000

Complete Complete and in use

2015/16

Marindi Primary School Renovation of 4 classrooms and

administration block:Replacement of inner

wall, plastering and painting and Roofing

July 2016 400,000

Complete Complete and in use

2015/16

Sironga Primary School Completion of administration

block.Plastering, flooring and Installation of

doors and windows.

July 2016 400,000

Complete Complete and in use

2015/16

Gianchore Primary School Renovation of 3 classrooms:Repair of roof ,

wall, doors and windows.July 2016 600,000

Complete Complete and in use

2015/16

Etono Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 800,000

Complete Complete and in use

2015/16

Kiambere Primary School Renovation of 4 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 1,000,000

Complete Complete and in use

2015/16

Rateti Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Bondeka Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Gekomoni Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Bomondo Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Tonga Omunuri Boarding Primary

School

Completion of a storey a Multipurpose

building:Construction of First Floor SlabJuly 2016 500,000

Complete Complete and in use

2015/16

Gesiaga Primary School Renovation of 3 classrooms:Repair of floor,

windows and doorsJuly 2016 540,000

Complete Complete and in use

2015/16

Igena Itambe Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Nyakemincha Primary School Construction of One Class room:Foundation,

walling and Roofing, Plastering, painting

and electrical works

July 2016 500,000

Complete Complete and in use

2015/16

Kianyabongere Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Kebirigo Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

Page 24: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Man'gon'go Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Getaari Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Bugo Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Tonga Primary School Construction of One Class room:Foundation,

walling and Roofing, Plastering, painting

and electrical works

July 2016 500,000

Complete Complete and in use

2015/16

Nyaisa Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 500,000

Complete Complete and in use

2015/16

St Josephs Nyamira Primary School Construction of a tuition block:Construction

of first floor slabJuly 2016 600,000

Complete Complete and in use

2015/16

Moruga Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Nyairicha Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Nyangoso Primary School Construction of One Class room:Foundation,

walling and RoofingJuly 2016 350,000

Complete Complete and in use

2015/16

Nyairicha Special Primary School Completion of a tuition block:Plastering,

wiring and RoofingJuly 2016 400,000

Complete Complete and in use

2015/16

Geta Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Kenyenya Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Ekenyoro Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Nyainogu Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Nyakeore Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Rangenyo Mixed Primary Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Kegogi Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Ramba Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Rirumi Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Kiambere Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Etono Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Ikurucha Primary School Renovation of 2 classrooms:Repair of Roof,

wall, doors, windows and floorJuly 2016 400,000

Complete Complete and in use

2015/16

Amatierio Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 600,000

Complete Complete and in use

Page 25: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Bosiango Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Bonyunyu Boarding Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Ibucha Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Ibucha Primary School Completion of 2

classrooms:walling,Roofing, plastering and

electrical works

July 2016 800,000

Complete Complete and in use

2015/16

Makairo Primary School Renovation of 4 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 800,000

Complete Complete and in use

2015/16

Riasindani Primary School Renovation of 4 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 700,000

Complete Complete and in use

2015/16

Geta Primary School Renovation of 3 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 600,000

Complete Complete and in use

2015/16

Nyachururu Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Kianungu Primary School Renovation of 2 classrooms:Repair of floor,

roof, windows and doorsJuly 2016 400,000

Complete Complete and in use

2015/16

Ikobe Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Nyakoria Primary School Construction of Pit Latrine:Digging of pit,

foundation,walling,flooring, roofing,

painting and electrical works

July 2016 300,000

Complete Complete and in use

2015/16

Kenyambi Primary School Renovation of two classrooms:Repair of roof,

windows and doors and wallJuly 2016 400,000

Complete Complete and in use

2015/16

Ekerama Primary School Completion of 2

classrooms:Roofing,Plastering, doors and

Windows

July 2016 300,000

Complete Complete and in use

2015/16

Nyainogu Youth Polytechnic Construction of a Pit Latrine:Foundation,

walling,Roofing,Plastering and Electrical

Works

July 2016 200,000

Complete Complete and in use

2015/16

Nyaigesa Youth Polytechnic Completion of a hall: Roofing 500,000

Works at 50%

Additional funds needed

for completion

2015/16

Geta Youth Polytechnic Construction of One Classroom:Foundation,

walling,Roofing,Plastering and Electrical

Works

July 2016 500,000

Complete Complete and in use

2015/16

Kiambere Youth Polytechnic Construction of One Classroom:Foundation,

walling,Roofing,Plastering and Electrical

Works

July 2016 500,000

Complete Complete and in use

2015/16

Kebirigo Chiefs Office Completion of chief's office:Plastering,

Painting and Electrical Works

350,000

Complete Complete and in use

2015/16

Gianchore Chiefs Office Completion of chief's office:Plastering ,

Painting , doors and windows

350,000

Works at 70%

Additional funds needed

for completion

Page 26: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2015/16

Nyagachi Chiefs Office Renovation of Chiefs Office:Repair of Roof,

Floor,windows and doorsJuly 2016 200,000

Complete Complete and in use

2015/16

Etono Chiefs Office Construction of a Pit Latrine:Digging of Pit,

Foundation,walling,roofing,Plastering and

Painting

July 2016 200,000

Complete Complete and in use

2015/16

Kiambere Chiefs Office Renovation of Chiefs Office:Repair of Roof,

Floor,windows and doorsJuly 2016 200,000

Complete Complete and in use

2015/16

Audit Fees FY 15/16 Constituency Accounts Audit fees

by KENAO

500,000.00

Funds not utilised

Awaiting for Funds from

NG-CDF Board

GRAND TOTAL 329,750,463.00

NG-CDF Contituency Office

Administration fund 6%

2016/17 Employee Salaries Payment of staff salaries and Gratuity 1,600,000 Ongoing Ongoing

2016/17

Goods and Services Purchase of office stationary, fuel, vehicle

repairs, telephone expenses and subsistence

1,500,000

Ongoing Ongoing

2016/17

Purchase of Computers Purchase of one CDFC laptop and One

Computer

200,000

Complete Complete and in use

2016/17 NSSF Staff NSSF Remmitances 80,000 Ongoing Ongoing

2016/17 NHIF Staff NHIF Remmitances 27,586 Ongoing Ongoing

2016/17

Committee Allowances and Expenses Committee sitting allowances and expenses 1,506,207

Ongoing Ongoing

2016/17

Emergency Fund Reserve fund for emergencies and disasters

within the constituency May-17

4,094,827.14

Complete Funds Utilised

Bursary schemes, Mock Examinations,

and Continuous Assessment Tests &

Social Security Programmes

2016/17

Universities and Colleges Fees Payment for needy students in colleges

and universities and activities for

enhancement in performance in national

examinations.

18,700,000

Ongoing

Bursary disbursement

ongoing

2016/17

Secondary Schools Fees Payment for needy students in

Secondary Schools

6,097,414

Ongoing

Bursary disbursement

ongoing

2016/17

Mocks/Cats Payments for mocks and CATS in Primary

and secondary schools Apr-17

1,000,000

Complete Complete and in use

2016/17

Social Security Programmes Facilitation of social security programmes

within the Constituency

2,866,379 Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17 Monitoring & Evaluation 3%

2016/17

Goods and Services Purchase of stationary, fuel, vehicle repairs,

telephone expenses and subsistence in M&E

1,000,000.00

Ongoing Ongoing

2016/17 Committee Expenses Committee M&E Expenses 1,000,000.00 Ongoing Ongoing

2016/17

CDFC/PMC Capacity Building PMC Training and capacity building

expenses

456,897.55

Ongoing Ongoing

2016/17 Sports Activities

2016/17

West Mugirango Constituency Sports

Committee

Sports activities for men and women within

the constituency Feb-17 1,637,931 Complete Complete and in use

Page 27: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2016/17 Environmental Activities

2016/17

Rateti Primary School Planting of assorted tree varieties in the

school compound

80,000 Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17

Nyairicha Special School Planting of assorted tree varieties in the

school compound

80,000 Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17

Bosiango Secondary School Planting of assorted tree varieties in the

school compound

80,000 Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17

Moruga Primary School Planting of assorted tree varieties in the

school compound

80,000 Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17

Nyamwetureko Primary School Planting of assorted tree varieties in the

school compound

80,000 Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17

Township Ward Water Catchment

Protection

Protection of Township ward water

catchment areas:Rionyinge & Riasura Feb-17

600,000

Complete Complete and in use

2016/17

Bogichora Ward Water Catchment

Protection

Protection of Bogichora ward water

catchment areas:Riarieri & Sironga Feb-17

637,931

Complete Complete and in use

CONSTRUCTION OF WEST

MUGIRANGO CONSTITUENCY NG-

CDF OFFICE

2016/17

West Mugirango NGCDF Office Completion of an NG-CDF Office: Additional

funds for Construction of West Mugirango

NGCDF Office: Relocation of old water way

and Construction of Parking

3,000,000

Project ongoingat

80%

Awaiting for funds from

NG-CDF Board

2016/17

Purchase of NG-CDFC Office furniture Purchase of NG-CDFC Office furniture:10

Executive chairs, 4 Executive Tables, 3

Executive book shelves and 10 Cabinets

2,091,379

Project underway

Awaiting delivery on

completion of office

2016/17

SECONDARY SCHOOL PROJECTS

2016/17

Senator Kebaso Secondary School Completion of a Multi-Purpose

Hall:Additional funds for construction of a

multipurpose hall.

1,000,000

Works at 30%

Additional funds needed

for completion

2016/17

Nyanchururu Sec School Additional funds for construction of a

tuition block.First floor floor

walling,plasteringand electrical works

1,000,000

Works at 40%

Additional funds needed

for completion

2016/17

Marindi Sec School Completion of a tuition block:Additional

funds for construction of a tuition

block.Ground floor walling, plastering and

electrical works

1,000,000

Works at 20%

Additional funds needed

for completion

2016/17

Embonga Secondary School Completion of 4 classrooms :walling,

roofing, plastering and electrical works.

700,000

Works at 50%

Awaiting for funds from

NG-CDF Board

2016/17

Mongorisi Secondary School Renovation of 3 classrooms:Roofing,

florring, replacement of doors and windows

and painting.

500,000Project not yet

started

Awaiting funds from NG-

CDF Board

2016/17

Rangenyo Girls Secondary School Completion of dining hall:Additional funds

for completion of a dining hall.Plastering,

flooring , painting and electrical works

Dec-16

400,000

Complete Complete and in use

Page 28: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2016/17

Bonyunyu Secondary School Completion of a dining hall:Additional funds

for construction of a dormitory.Foundation

and walling

1,000,000

Works at 65%

Additional funds neede

for completion

2016/17

Riamandere Sec School Completion of a labaratory:Additional funds

for construction of a Labaratory.Foundation

and walling

800,000

Works at 50%

Awaiting for funds from

NG-CDF Board

2016/17

Gesiaga Secondary School Purchase of a School bus:First allocation for

purchase of a school bus

2,000,000 Project not yet

started

Awaiting for funds from

NG-CDF Board

PRIMARY SCHOOL PROJECTS

2016/17

Sasati Primary School Construction of 1 classroom:Foundation,

Walling, flooring and Plastering

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Tonga Pri School Renovation of 2 classrooms:Roofing, flooring

and fixing doors and windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Kenyenya Boarding Primary School Construction of 1 classroom:Foundation,

walling,Roofing, painting and electrical

works

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Bonyunyu Primary School Renovation of two classrooms:Roofing,

flooring, fixing of doors and windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Ekerama Primary School Construction of 1 classroom:Foundation,

walling,Roofing, painting and electrical

works

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Bobembe Boarding Primary School Completion of a storeyed tuition

block:Walling

700,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyairicha Special School Completion of storey Building:1st floor

walling

700,000

Works at 60%

More funds needed for

completion

2016/17

Bundo Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Matierio Primary School Renovation of 2 classrooms:Roofing, flooring

, fixing doors and windows and painting

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Marara Primary School Completion of admin block:Plastering,

Fixindg doors and windows, Painting and

electrical works

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Ratandi Primary School Renovation of of 2 classrooms:Flooring,

roofing and fixing doors and windows and

painting

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Gianchore Primary School Renovation of of 2 classrooms:Flooring,

roofing and fixing doors and windows and

painting

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyantaro Primary School Renovation of of 3 classrooms:Flooring,

roofing and fixing doors and windows and

painting

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Ting'a Primary School Renovation of of 2 classrooms:Flooring,

roofing and fixing doors and windows and

painting

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Endabu Primary School Completion of 2 classrooms:plastering,

fixing doors and windows, painting and

electrical works

400,000

Project not started

Awaiting for funds from

NG-CDF Board

Page 29: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2016/17

Egesieri Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Bomorito Primary School Renovation of 3 classrooms:Roofing,

Flooring, fixing doors and windows,

painting and electrical works

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Kemasare Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyairicha Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows Jan-17

600,000

Complete Complete and in use

2016/17

Igena itambe Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyabisimba Primary Schhool Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Kiambere Primary School Renovation of admin block:Roofing, Repair

of wall, flooring, fixing doors and windows

and Painting

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Geseneno Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Gesore Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyakeore Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

600,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyamwetureko primary school Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Rangenyo Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

600,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Omosasa Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Embonga Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Kiang'inda Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Tente Primary School Construction of 1 classroom:Foundation,

walling, plastering, fixing doors and

windows, painting and electrical works

500,000

Project not started

Awaiting for funds from

NG-CDF Board

Page 30: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2016/17

Kebirigo Primary School Construction of 1 classrooms:Foundation,

walling, plastering, fixing doors and

windows, painting and electrical works

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Tonga Omunuri Primary School Completion of a Tuition Block:Walling of

2nd floor

600,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Rateti Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

600,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Kianyabongere Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Bobembe Girls Boarding Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Ikurucha Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

600,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Moruga Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyaigesa Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Marindi Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyangoso Primary School Construction of 1 classroom:Foundation,

walling, plastering, fixing doors and

windows, painting and electrical works

Jan-17

500,000

Complete Complete and in use

2016/17

Bugo Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Masosa Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Riakimai Primary School Construction of 1 classroom:Foundation,

walling, plastering, fixing doors and

windows, painting and electrical works

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Mang'ong'o Primary School Renovation of admin block:Repair of Roof,

Repair of wall, flooring, fixing doors and

windows and Painting

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Getaari Primary Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Rirumi Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

Page 31: WEST MUGIRANGO CONSTITUENCY NYAMIRA COUNTY AS AT … · enhancement in performance in national examinations. ... 2013/2014 Bomorito Primary School Planting of assorted tree varieties

2016/17

Nyabisimba Primary School Completion of 2 classrooms:Plastering,

fixing doors and windows, painting and

electrical works

400,000

Works at 70%

Awaiting for funds from

NG-CDF Board

2016/17

Mariba DEB Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

500,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyagachi Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyamotentemi Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Tonga Primary School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Kenyenya Primary Boarding School Construction of a Pit Latrine:Digging of pit,

foundation, walling, roofing, painting and

electrial works

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Etono Primary School Renovation of 3 classrooms:Roofing,

flooring, painting, fixing doors and

windows

500,000

Works at 80%

Additional funds needed

for completion

2016/17

Bonyaiguba Primary School Renovation of 2 classrooms:Roofing,

flooring, painting, fixing doors and

windows

400,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17 SECURITY

2016/17

Kiambere AP Camp Renovation of AP Camp:Roofing, Flooring

and windows

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Gianchore Chief's Office Completion of AP Camp:Flooring and fixing

doors and windows and painting

300,000

Project not started

Awaiting for funds from

NG-CDF Board

2016/17

Nyagachi Chief's camp Renovation of AP Camp:Roofing, Flooring

and windows

500,000

Project not started

Awaiting for funds from

NG-CDF Board

TOTAL 81,896,551.72