Page 1: West Lake Landfill 2016 - Timeline 2016 | US EPA ARCHIVE ... · TIMELINE 2016 - FUTURE Bridgeton, Missouri WEST LAKE LANDFILL SUPERFUND SITE 2016 ACTION TIMELINE This timeline depicts
Page 2: West Lake Landfill 2016 - Timeline 2016 | US EPA ARCHIVE ... · TIMELINE 2016 - FUTURE Bridgeton, Missouri WEST LAKE LANDFILL SUPERFUND SITE 2016 ACTION TIMELINE This timeline depicts

OPERABLE UNIT 1 REMEDIAL INVESTIGATION & FEASIBILITY STUDY

GROUNDWATER REMEDIAL INVESTIGATION FEASIBILITY STUDY

ISOLATION BARRIER SYSTEM

SURFACE FIRE REMOVAL

TIMELINE2016 - FUTUREBridgeton, Missouri

WEST LAKE LANDFILLSUPERFUND SITE

2016 ACTION TIMELINE

This timeline depicts projected target dates for completion of major milestone events associated with the four main project activities.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Visit: https://www3.epa.gov/region07/cleanup/west_lake_landfillContact: Ben Washburn, Community Involvement [email protected] | (913) 551-7364 | Toll-free: (800) 223-0425

MORE INFORMATIONhttps://www.facebook.com/WestLakeLandfillSuperfundSite https://twitter.com/WestLakeSite

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

RADIOLOGICALLY-IMPACTED MATERIAL

INVESTIGATIONSDEC 2015

DATA VALIDATION AND INTERPRETATION

SPRING 2016

REMEDIAL INVESTIGATION

ADDENDUMFINAL

SEPT 2016

FINAL FEASIBILITY

STUDY

OCT 2016

PROPOSED REMEDY

DEC 2016

MINIMUM PUBLIC

COMMENT PERIOD

(60 DAYS)

EPA DECISION ON ISOLATION BARRIER

SYSTEM

DEC 2015

PREPARE ORDER

SPRING 2016

WORK PLAN DEVELOPMENT

SUMMER 2016

START OF SUBSTANTIVE WORK

/ ISOLATION BARRIER DESIGN

FALL 2016

ORDER ISSUED

DEC 2015

WORK PLAN DEVELOPMENT

FEB 2016

START OF FIELD WORK

FEB 2016

COMPLETION OF FIELD WORK

APRIL 2016

FINAL REMOVAL ACTION REPORT

2016

REMEDIAL INVESTIGATION

FEASIBILITY STUDY SCOPING

SUMMER 2016

PREPARE ORDER

FALL 2016

WORK PLAN DEVELOPMENT

WINTER 2017

START OF FIELD WORK

SPRING 2017

ISOLATION BARRIER

DESIGN FINAL

WINTER 2016

ISOLATION BARRIER

CONSTRUCTION

2017