Classroom Building at Charlottetowne & 5th
Weekly Update May 15, 2020
Central Campus
![Page 2: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/2.jpg)
Meetings & Milestones
• This Week:
• Continue First Floor Flooring
• Continue First Floor Point Up
• Continue First Floor Lobby Tile
• Install Second Floor Rubber Base
• Continue Second Floor Rodgers Punch
• Continue Third Floor Architect Punch
• Begin Cleaning Fourth Floor
• Continue Grading East Elevation
• Continue South Elevation FRP Cornice Framing
• Complete Plan South Masonry and Cast Stone
• Begin Cleaning South Elevation Masonry
• Install Dumpster Enclosure Gates
![Page 3: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/3.jpg)
Meetings & Milestones
• Next Week:
• Continue First Floor Flooring
• Continue First Floor Point Up
• Begin First floor Final Paint
• Install Monumental Stair Wood Handrail Cap
• Install Second Floor Rubber Base
• Begin Second Floor Architect Punch
• Continue Third Floor Architect Punch
• Continue Grading East Elevation
• Continue South Elevation FRP Cornice Framing
• Continue Balance of Masonry Caulking
![Page 4: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/4.jpg)
Progress Photos
Install Simulator
Computer Arms
Location: In-Patient SIM 442
![Page 5: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/5.jpg)
Progress Photos
Continue Fourth
Floor Punch Items
Location: Clinical Lab 434
![Page 6: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/6.jpg)
Progress Photos
Continue Third Floor
Punch Items
Location: Operatory 310B
![Page 7: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/7.jpg)
Progress Photos
Install Second Floor
Rubber Base
Location: Student Lounge 261
![Page 8: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/8.jpg)
Progress Photos
Install Second Floor
Rubber Base
Location: Virtual Anatomy 215
![Page 9: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/9.jpg)
Progress Photos
Continue Second
Floor Rodgers Punch
Location: Elv Lobby 273
![Page 10: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/10.jpg)
Progress Photos
Install Tile Base and
Wood Trim and
Lobby Columns
Location: Lobby 171
![Page 11: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/11.jpg)
Progress Photos
Continue Balance of
First Floor LVT
Location: Corridor 176
![Page 12: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/12.jpg)
Progress Photos
Install Dumpster
Enclosure Gates
Location: Dumpster Enclosure
![Page 13: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/13.jpg)
Progress Photos
Complete Cast Stone
Columns
Location: South Elevation
![Page 14: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/14.jpg)
Progress Photos
Complete South
Elevation Masonry
and Cast Stone
Location: South Elevation
![Page 15: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/15.jpg)
Progress Photos
Begin Cleaning
South Elevation
Masonry
Location: South Elevation
![Page 16: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/16.jpg)
Progress Photos
Continue East
Elevation Grading
Location: Plan East
![Page 17: Weekly Update May 15, 2020 · •Install Monumental Stair Wood Handrail Cap •Install Second Floor Rubber Base •Begin Second Floor Architect Punch •Continue Third Floor Architect](https://reader034.vdocuments.us/reader034/viewer/2022043009/5f9a5a2d5a78fb595723ff21/html5/thumbnails/17.jpg)
Conclusion of Weekly Update 05/15/2020