week-3.1 line balancing

Upload: projjalgnit7378

Post on 06-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Week-3.1 Line Balancing

    1/20

    Work Analysis and Design

    Line Balancing

    Ayse AKBALIK-RAPINE

    January 2011

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    2/20

    Problem solving steps

    1 Select project (Pareto, Fish diagram, Gantt, PERT,

    Job/Worksite analysis guide)

    2 Get and present data (charts, computations)

    3 Analyze data (operation analysis)4 Develop ideal method (motion, work, equipment design)

    5 Present and install method (decision making tools)

    6 Develop job analysis

    7 Establish time standards (time study)8 Follow up

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    3/20

    Line Balancing -ideal case-

    See Beyond Lean page

    Everyone is doing the same amount of work

    Variation is smoothed

    No one overburdened

    No one waiting

    Everyone working together in a balanced fashion

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    4/20

    Line Balancing

    Example 1

    Operation 1 = 5 min

    Operation 2 = 15 min

    Operation 3 = 10 min

    Questions

    What is the cycle time of this system?

    If each operation was 15 min, what happens?If we consider Operation 2 = 10 min ?

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    5/20

    Line Balancing

    Example 1

    What is the system efficiency?

    What is the idle time percentage?

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    6/20

    Line Balancing

    Example 1

    What is the system efficiency?

    efficiency% = ( total actual standard minutestotal allowed standard minutes

    )%

    efficiency% = (

    lead timenumber of machines

    bottleneck time

    )%

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    7/20

    Line Balancing

    Example 2

    We want 960 pieces a day (with 8h a day)

    See the standard minutes for each operation below

    Operation Standard minutes Number of operators

    Op 1 1.2 min ?

    Op 2 2.4 min ?

    Op 3 1.9 min ?

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    8/20

    Line Balancing

    Operation Standard minutes Number of operators

    Op 1 1.2 min 3Op 2 2.4 min 5

    Op 3 1.9 min 4

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    9/20

    How to increase the efficiency of the operation 2?

    1 Reassign some of the work of operation 2 to the other

    operations

    2 Improve the method at operation 2 to decrease the cycle

    time

    3 Utilize a part-time worker

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    10/20

    Line Balancing, Example 3

    Operation Standard minutes Number of operators

    Op 1 1.25 min

    Op 2 1.38 min

    Op 3 2.58 minOp 4 3.84 min

    Op 5 1.27 min

    Op 6 1.29 min

    Op 7 2.48 min

    Op 8 1.28 min

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    11/20

    Line Balancing

    Example 3

    find the number of operators to assign to each operation

    for a production of 700 pieces per day

    minimization of the storage costs are of high importance!

    no stock level is required at the end of day

    which operation determines the output from the line?

    find the total number of pieces produced at the end of the

    day

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    12/20

    Assembly line improvement

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    13/20

    Disadvantages of element sharing

    sharable parts, tasks

    Increase in material handling (parts are delivered to more

    than one location)

    Duplication of tooling, additional costs

    If any competence or experience is required from the

    operators, training periods...

    divisible tasks

    not very economicaltwo times setup time, setup cost

    decrease on the efficiency

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    14/20

    Assembly line balancing -a precedence chart-

    Operation times are given as follows:

    0.46, 0.35, 0.25, 0.22, 1.10, 0.87, 0.28, 0.72, 1.32, 0.49, 0.55.

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    15/20

    Kilbridge and Websters Heuristic

    Rank operations according to their number of

    predecessors

    Assign first operations with least number of predecessorsIn case of tie, choose operation with longest operation time

    Total time at each work station cannot exceed the total

    cycle time

    Precedence relationships must be satisfied

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    16/20

    Helgeson and Birnie (1961) method

    Compute "Positional weight = Operation time + Total time

    of all operations that must follow it"

    Begin by assigning the operation with highest positional

    weightIf there is a tie, break it by

    higher operation timelower operation number

    Total time at a station cannot exceed the total cycle time

    Precedence relationship must be satisfied

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    17/20

    Assembly line balancing -a precedence chart-

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    18/20

    Assembly line balancing -precedence matrix-

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    19/20

    Assembly line balancing -positional weights-

    The system cycle time = 1.5 min is given.

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/
  • 8/3/2019 Week-3.1 Line Balancing

    20/20

    Assembly line balancing -balanced assembly line-

    End 202 - Work analysis and design Line Balancing

    http://find/http://goback/