Document ofThe World Bank
Report No: 69146-SD
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF THE
NATIONAL EMERGENCY TRANSPORT REHABILITATION PROJECT
(MDTF–NS GRANT TF057323)
APPROVAL DATE: AUGUST 28, 2006
TO THE
REPUBLIC OF SUDAN
June 22, 2012
Transport SectorMDTF–Sudan (National Secretariat) Country Department AFCE4Africa Region
ABBREVIATIONS AND ACRONYMS
AFESMUGONU
Additional FinancingEnvironment and Social Management UnitGovernment of National Unity
IRND Inland River Navigation DepartmentLCMDTF-NSMoFNEMOT
Letter of CreditMulti Donor Trust Fund for Sudan (National)Ministry of Finance and National EconomyMinistry of Transport
MTRB Ministry of Transport, Roads and Bridges NETREP National Emergency Transport Rehabilitation ProjectNHA National Highway AuthorityNTMP National Transport Master PlanOC Oversight CommitteePDO Project Development Objective PMS Pavement Management SystemPMTPPP
Program Management Team Private Public Partnership
PSP Private Sector ParticipationRPFRTC
Resettlement Policy Framework River Transport Corporation
SDGSRC
Sudanese PoundSudan Railway Corporation
TA Technical Assistance/Technical Advisory ServicesUS$ United States Dollar
Regional Vice President: Makhtar DiopCountry Director:Country Manager:
Bella Deborah Mary Bird Alassane Sow
Sector Director:Sector Manager:
Jamal SaghirSupee Teravaninthorn
Task Team Leader: Tesfamichael Nahusenay Mitiku
SUDAN NATIONAL EMERGENCY TRANSPORT REHABILITATION PROJECT
P098837CONTENTS
A. SUMMARY......................................................................................................................1B. PROJECT STATUS........................................................................................................2C. PROPOSED CHANGES.................................................................................................3
ANNEX 1: RESULTS FRAMEWORK AND MONITORING INDICATORS..............................................7
ANNEX 2: DETAILED PROJECT COST TABLE BY COMPONENT AND ACTIVITY.........................14
ANNEX 3: ALLOCATION OF GRANT PROCEEDS BY COMPONENT AND DISBURSEMENT CATEGORY.........................................................................................................................................................19
ANNEX 4: IMPLEMENTATION PLAN..........................................................................................................20
Data Sheet
Restructuring Status: DraftRestructuring Type: Level twoLast modified on date : 6/22/2012
1. Basic InformationProject ID & Name P098837: Sudan National Emergency Transport
Rehabilitation ProjectCountry Republic of SudanTask Team Leader Tesfamichael Nahusenay MitikuSector Manager/Director Supee Teravaninthorn/Jamal SaghirCountry Director Bella BirdOriginal Board Approval Date 08/28/2006Original Closing Date: 12/31/2009Current Closing Date 06/30/2012Proposed Closing Date 06/30/2013EA Category B- partial Assessment Revised EA Category B- partial Assessment EA Completion Date August 15, 2006Revised EA Completion Date N.A
2. Revised Financing Plan (US$m)Source Original RevisedBORR 93.68 65.82MDTF 43.50 64.70ZPCO 0.00 0.00Total 137.18 130.52
3. BorrowerOrganization Department LocationMinistry of Transport Roads and Bridges
Sudan
4. Implementing AgencyOrganization Department LocationMinistry of Transport, Roads and Bridges
Sudan
Sudan Railways Corporation SudanNational Highways Authority Sudan
5. Disbursement Estimates (US$m)Actual amount disbursed as of 05/24/2011 46.33Fiscal Year Annual Cumulative2011 0.00 39.17
i
2012 8.41 47.582013 17.12 64.70 Total 64.70
6. Policy Exceptions and Safeguard PoliciesDoes the restructured project require any exceptions to Bank policies? N
Does the restructured project trigger any new safeguard policies? If yes, please select from the checklist below and update ISDS accordingly before submitting the package.
N
7a. Project Development Objectives/OutcomesOriginal/Current Project Development Objectives/OutcomesThe PDO is “ to facilitate the country's economic and social recovery through improved physical access to goods, markets, and administrative and social services”.
7b. Revised Project Development Objectives/Outcomes [if applicable] N/A
ii
SUDAN - NATIONAL EMERGENCY TRANSPORT REHABILITATION PROJECT (NETREP – P098837)
RESTRUCTURING PAPER
A. SUMMARY
1. The proposed changes involve: (a) an extension of the project closing to complete the on-going road project which is stalled due to insecurity situation in the Blue Nile State; (b) reallocation within and among components to: (i) avail funds to institutional development to continue with the capacity building activities; (ii) provide additional funding to supervision services to cover the increased cost of supervision, during the extended period of roads contracts execution; and (iii) allocate the balance of the Multi Donor Trust Fund for Sudan National Secretariat (MDTF-NS) allocation for the first section of the Damazin-Kurmuk road to the second section of the Damazin- Kurmuk road contract to cover additional financing requirements due to the insecurity, increase in quantities of existing bill items and escalation of prices; (c) drop activities that would not be implemented under the National Emergency Transport Rehabilitation Project (NETREP); and (d) revision of targets to reflect the changes. The MDTF-NS Grant closing date is proposed to be extended to June 30, 2013, to allow the completion of ongoing contracts.
2. NETREP was approved by the Oversight Committee (OC) on August 28, 2006, and became effective on January 29, 2007. The original cost estimate for phase 1 of the project was US$140.36 million and funded in the proportion of US$43.50 million from MDTF-NS grant and US$96.86 million from the Government of National Unity (GONU). An Additional Financing (AF) in the amount of US$43.75 million was made available to the project in 2009, raising the MDTF-NS contribution to US$87.25. The purpose of the AF was mainly to increase the allocations for the road improvement component to improve accessibility on the entire length of Kadugli – Kaouda Road and Section 2 of Damazin – Kurmuk Road. However, due to the taking over of the Kadugli-Kaouda road by the State Administration of South Kordofan, which was construed as mis-procurement US$19.75 million was cancelled, reducing the MDTF-NS contribution to US$67.5 million.
3. NETREP was prepared and implemented in post-conflict environment, but it has overcome the inherent challenges of lack of implementation capacity, meeting the Bank’s fiduciary and safeguard requirements and started delivering results, through: (a) full commitment of the Implementing Entities; (b) strong support of the Bank’s project management team to procurement and contract management tasks; (c) technical assistance; and (iv) applying risk mitigation measures concurrent to project implementation. In the latest ISR, archived on March 11, 2012, the project development objective (PDO) and implementation progress are rated “moderately satisfactory”, mainly due to the suspension of the contracts on Damazin – Kurmuk road, because of conflict and insecurity in the project implementation area, which will be addressed by the measures proposed under the repackaging section (para 12). The ISR rating for safeguards, project management, procurement, and counterpart funding are moderately satisfactory, due to delays in the preparation of Environmental and Social Impact Assessment, procurement, and release of counterpart funding. Except for the latter, the issues have been overcome. The Client, the Project Implementing Entities and the Program Management Teams (PMT) are complying
1
with key covenants specified in the Grant Agreement. The Project Implementing Entities have established an acceptable accounting and reporting system for the project that will also be applied to the restructured project. Timely release of counter-part funding to the ongoing road contracts is a challenge re-emerging from time to time. The government has reconfirmed its commitment to meet its obligation, and the Project Team and the Country Management Unit have to follow up this covenant regularly for the remaining life time of the project.
4. There are no unresolved fiduciary, environmental, social or other safeguard issues. The audit for the year ended December 31, 2011 is in progress. The Interim Financial Report (IFR) for the quarter ended March 30, 2012 did not indicate any significant financial management issue. Financial management, procurement arrangement, and institutional roles and responsibilities remain unchanged. There are no changes to the PDO, except the adjustment of the outcome targets on reduction in travel time, beneficiary population, and increase in traffic volume, due to the completion of the upgrading of part of the Damazin – Kurmuk road.
B. PROJECT STATUS
5. The project has three components, namely: component 1 – Rehabilitation of Critical Rail Infrastructure and Services, component 2 - Institutional Strengthening and Improvement to River Transport Services, and component 3- Road Improvement in the Three Areas. Project implementation progress is at a very advanced stage. The Babanusa – Wau rail line rehabilitation project was completed in March 2010 and rail transport services have resumed after 25 years of disruption. The upgrading of Kadugli – Kouda Road Lot B (30 km) and Gadamai – Hamashkoraib Road (81.5 km) has been completed. The engineering design of 945 km of national and rural roads has been completed. The feeder roads study will be completed by the end of June 2012. The studies on the private sector participation (PSP) in rail transport, Port Sudan trade facilitation, and Inland River Navigation Diagnostics, as well as the preparation of the National Transport Master Plan (NTMP) have delivered sound sector development policies and strategies, and implementation is in progress.
6. However, the contracts for the Damazin – Kurmuk road (Sections 1 and 2) have been suspended since September 2011 due to conflict and insecurity in the project area (Blue Nile State). The government and the contractors are monitoring the situation and indications are that the situation has normalized and would allow the contractors to resume works. The two contractors with representatives of the Client jointly visited the project site in March 2012 to assess the damages and finalize claims for compensation. The visit confirmed the contractors’ willingness to go back to work as they have noticed improvement in security in the project area. However, remobilization and recommencement of works will follow fulfillment of certain conditions put forward by the contractors e.g. payment of outstanding counterpart funds for Section 1 and compensation of damaged contractors’ properties.
7. Studies under the institutional development component have been completed. Currently Technical Assistance services in support of the Planning Directorate and the Environmental and Social management Unit (ESMU) are in progress. In addition, the Ministry of Transport, Roads and Bridges (MTRB) is coordinating the implementation of key recommendations of the studies carried out under the support of the MDTF-NS, including: (a) separating/splitting rail infrastructure management responsibilities from rail transport operation; (b) shortening the duration for clearance of goods at Port Sudan; and (c) promoting the establishment of an independent Road Fund.
2
C. PROPOSED CHANGES
8. The Project Development Objectives remain unchanged which is “to facilitate the country's economic and social recovery through improved physical access to goods, markets, and administrative and social services”. The outcome targets for reduction in travel time, beneficiary population, and increase in traffic volume, will be reduced to reflect the impact of the changes in the Damazin – Kurmuk road. The section along the Damazin – Kurmuk road to be fully upgraded by the end of the proposed grant closing date of June 2013 will reduce from 92 km to 45 km. For example, the baseline and target values for travel time reduction will change from the original - from 11.6 hours per trip to 1.3 hours to, from 11.6 hours to 2 hours. Also, the number of the beneficiary population will reduce from 301,000 to 287,500. The expected increase in traffic volume on Damazin –Kurmuk road from 40 trucks per day to 110 trucks per day will not be realized until the entire section will be upgraded. Nonetheless, the original objective of creating all season access between Damazin-and Kurmuk through spot improvement has been achieved, as the contractors have reconditioned the existing 92 km embankment, and the Blue Nile State Government has improved the remaining section up to Kurmuk. As an outcome the entire road is passable during the rainy season. Further, the upgrading of the remaining part of Section 1 of the Damazin-Kurmuk road is expected to be fully financed by the government.
9. The Results Framework (RF) is updated and revised as part of this restructuring to reflect the changes and reflect standard/commonly used indicator descriptions and Core Indicators.
10. The Client, based on the request from the implementing institutions, has proposed the following changes:
11. Repackaging the Damazin – Kurmuk road and trading off funds between the two sections of the road as proposed by the Ministry of Finance and National; Economy (MoFNE): To complete section 2 of Damazin – Kurmuk road, which was suspended due to the conflict and insecurity in the Blue Nile State and compensate the contractor for damages caused due to the conflict MoFNE, by a letter dated April 23, 2012, has proposed swapping the provision for compensation (claims settlement) for section 2 of the Damazin – Kurmuk road with the MDTF-NS allocation for the gravel works on section 1 of the Damazin – Kurmuk road. The proposal is to apply US$6.59 million earmarked by the MDTF-NS for section 1, for the compensation of the damage on section 2, while GOS takes over the responsibility for fully financing the outstanding works for section 1, including the completion of the road up to sub-base level. Subsequently, section 1 of the Damazin-Kurmuk road has to be dropped from NETREP, and be taken up by GOS, as there will be no sufficient funding under the MDTF-NS to cover the gravelling work of section 1 and raise the additional resources required to complete section 2. Any additional compensation for section 2 will be borne by GOS. Further, this requires the Bank to verify eligibility of such payment. In addition, the Government has to confirm that the area would be safe to carry out construction activity and will ensure the provision of adequate security coverage around the project site.
12. Due to the separation of South Sudan, the ferry boat that was to be provided for Sobat River crossing near Malakal in Southern Sudan will be dropped from NETREP as requested
3
by the Client. The amount of US$240,000 allocated for this activity will be reallocated to other activities.
Financing
13. Project Costs: The Financing Arrangement is proposed to be amended to reflect the changes, as presented in Table 1.
Table 1: Project Cost Summary
Component Original Allocation Current1
Allocation Proposed Restructured Allocation
Total GONU MDTF Total GONU MDTF Total GONU MDTF
1. Rehabilitation of critical rail infrastructure and services
39.98 24.89 15.09 46.14 33.87 12.27 46.14 33.87 12.27
2. Institutional Strengthening and Improvement to River Transport Services
11.01 7.36 3.65 1.70 0.48 1.22 1.17 - 1.17
3. Road Improvements in the Three Areas
86.19 61.43 24.76 88.37 34.36 54.01 83.21 31.95 51.26
Total 137.18 93.68 43.50 136.2
1 68.71 67.50 130.52 65.82 64.70
14. As a result of the proposed changes, the contribution from MDTF-NS will reduce from US$67.5 million to US$64.7 million. Likewise, the contribution from GOS, in a form of counterpart funding, will reduce from US$68.71 million to US$65.82 million, as the counterpart payments for the services concluded at a lower price than budgeted and activities dropped from NETREP will not be required. However, GOS has to provide out of NETREP, additional funds to complete the section 1 of the Demazin - Kurmuk road.
Reallocations:
15. The proposed reallocations, by disbursement category, include:
a. Category 9: An increase of US$190,000 for project coordination and implementation support and Technical Assistance to MTRB.
b. Category 10; An increase of US$310,000 to cover the additional funds required to pay for works executed before repackaging of section one of the Damazin-Kurmuk road.
1 The current allocation reflects the latest approved project costs.
4
c. Category 11: An increase of US$180,000 to cover the balance required for the
project implementation support and LC charges for the PMS under the roads improvement component.
d. Category 12: An increase of US$6,590,000 to the civil works contract for Damazin – Kurmuk road (Section 2) to cater for compensation of damages due to the conflict in Blue Nile State and additional costs for supervision services.
e. Category (8): A reduction of US$240,000 due to dropping the procurement of a ferry boat.
f. Category (10): A reduction of US$1,270,000, unutilized funds (saving) from the allocation for Gadamai – Hamashkoraib Road and Kadugli-Kaouda road (Lot B)
g. Category (10): A reduction of US$1,190,000, recovery from advance payment to section one (1) of Damazin-Kurmuk road before repackaging
h. Category (10): A reduction of US$310,000, amount reserved to meet cost increase for projects under the road improvement components
i. Category (11): A reduction of US$160,000, saving from allocation for the feasibility studies and design services
j. Category (13): A reduction of US$6,590,000, to be transferred to Damazin – Kurmuk section two.
Cancellation:
16. Cancellation of US$2.8 million, representing: (a) US$1.61 million, part of the unutilized funds (saving) from the completed feasibility studies and design services, the completed Gadamai – Hamashkoraib and Kadugli – Kaouda road (Lot B), and allocation for the Ferry Boat; and (b) the recovery from the advance payment for section one of the Damazin-Kurmuk road, equivalent to US$1.19 million.
5
Table 2: Project Cost by Expenditure Category
Category of Expenditure Allocation (US$) % of FinancingCurrent Revised Current Revised
(1) Works, goods, services and training for Part 1 of the Project (SRC) (per memoria) 11,772.41 11,772.41 33-1/3 33-1/3
(2) Works, goods, services and training for Part 2 of the Project (RTC) (per memoria) 0.00 0.00 33-1/3 33-1/3
(3) Works, goods, services and training for Part 3 of the Project (NHA) (per memoria) 1,802,862.00 1,802,862.00 33-1/3 33-1/3
(4) Goods and services for demining activities (per memoria) 0 0 ----- -----
(5) Goods for Component 1 of the Project (SRC) 12,058,227.59 12,058,227.59 100 100(6) Services, training and operating costs for
Component 1 of the Project (SRC) 200,000.00 200,000.00 100 100
(7) Works for Component 1 of the Project (SRC) -------- ------- -------- --------(8) Goods for Component 2 of the Project (MTRB) 240,000.00 ------- 33-1/3 ----(9) Goods, services, training and operating costs for
Component 2 of the Project (MTRB) 980,000.00 1,170,000.00 100 100
(10) Works and Services for Part 3 (i) (a), (i) (b) and (i) (e) of the Project (NHA) 13,187,138.00 10,727,138.00 33-1/3 33-1/3
(11) Goods, services, training and operating costs for Part 3(ii) to (vi) of the Project (NHA) 11,850,000.00 11,870,000.00 100 100
(12) Works and Services for Part 3 (i) (d) of the Project 20,270,000.00 26,860,000.00 100 100(13) Works and Services for Part 3 (i) (c) of the Project
(NHA) 6,900,000.00 ---- 100 --
TOTAL 67,500,000.00 64,700,000
17. Closing date
The closing date is proposed to be extended from June 30, 2012 until June 30, 2013. The extension of the project closing date will allow the completion of the road construction contracts, establishment of a pavement management system (PMS) , and continue support for the Ministry of Transport, Roads and Bridges through coordination of policy reform implementation, project coordination and TA.
18. Implementation Schedule and Procurement Plan The Client has prepared and submitted updated Project Implementation schedule/Plan and Procurement Plan for the three components acceptable to the Bank. All activities under the project will be completed by the proposed extended closing date of June 30, 2013, and thus the project development objectives will be achieved.
6
ANNEX 1: RESULTS FRAMEWORK AND MONITORING INDICATORS
NATIONAL EMERGENCY TRANSPORT PROJECT (NETREP)
Revisions to the Results Framework Comments/Rationale for Change
PDOCurrent (PAD) ProposedTo improve physical access to goods, markets, and administrative and social services
No change
PDO indicatorsCurrent (PAD) Proposed change*1. Increase in access to an all-
season road 1. Number of people with all-season
access (roads/rail)Redefined to streamline with standard/commonly used indicator description
2. Reduction in average travel time to closest market, health clinic, primary school & administrative center
2. Travel time reduction on selected routes 2.1 (Babanousa-Wau Rail) – hours
average2.2 (Kadugli-Kauda Road) (hr) 2.3 (Hamsahkoreib-Gadamai Road)
(hr)2.4 Ed Damazin – El Kurmuk Road)
(hr)
Redefined and customized to streamline with standard/commonly used indicator description
3. Travel volume in selected routes3.1 rail (Babanusa-Wau) –ton/annum3.2 road (Gadamai-Hamashkorieb; Damazin Kurmuk; Kadugli – Kaouda) – Number of Medium Trucks/day
Redefined and customized to streamline with standard/commonly used indicator description
3. Reduced incidence of slowdown and derailment on Babanusa to Wau rail line
Replaced Replaced with travel time reduction and volume on Babanusa to Wau rail line (proposed change item 2 & 3 above)
Share of rural population with access to an all-season road (proportion)
Use of core indicator
Roads in good and fair condition as a share of total classified roadsSupplemental value: Size of the total classified networkBreakdown:
Use of core indicator
Direct Project Beneficiaries (number), of which female (%)
Use of core indicator
Intermediate Results indicatorsCurrent (PAD) Proposed change*Component One: Rail line rehabilitation
7
Revisions to the Results Framework Comments/Rationale for Change
446 km of rail line rehabilitated and opened for traffic
1. Rail line rehabilitated (km) streamline with standard/commonly used indicator description
Component Two: Institutional DevelopmentEnvironment and Social Assessment Unit (ESAU) established and functional
2. Environment and Social Assessment Unit Established under the Ministry (Yes/No)
Planning Department of MTRB strengthened and satisfactorily discharging its oversight role
3. Continued, (unit of measure- Yes/No added)
River transport regulatory body strengthened
4. Diagnostic study of the regulatory body in the River Transport Sector completed (Yes/No)
Streamlined with actual outcome
Action plan agreed for trade facilitation at Port Sudan
5. Action Plan for Port Sudan Trade Facilitation adopted by Ministry and recommendations under implementation (Yes/No)
Streamlined with actual outcome
Participation of the private sector in rail transport increased
6. Action Plan for Private Sector Participation in Railway Sector adopted by Ministry (Yes/No)
Streamlined with actual outcome
7. Environment and Social Assessment Framework adopted (Yes/No)
Added to reflect actual outcome
8. Staff trained in planning, budgeting, financing (number) (for all components)
Added to reflect actual outcome
Component ThreeRoads improvement and design
205km of rural roads improved 9. Roads rehabilitated ,- Rural (km) Use of Core Indicator
38km non-rural road improved 10. Roads rehabilitated, Non-Rural (km) Use of Core indicator
Design for 945 km secondary and tertiary roads completed
11. Feasibility and detailed design studies for new roads (km)
streamline with standard/commonly used indicator description
Feeder and community access road program prepared
12. Continued (Yes/No) added
Pilot Performance-Based Road Maintenance contracts initiated
13. Dropped To be carried out by the Client upon completion of the road rehabilitation/improvement works
Pavement Management system established
14. Continued (Yes/No) added
8
NETREP - Revised Project M&E Arrangement
PDO Level Results Indicators
Cor
e UOM2
BaselineOriginal ProjectStart
(2007)
Progress To Date(2012)
Cum. Target Values
Frequency Data Source/ Methodology
Responsibility for Data
CollectionComments
2012 2013
Number of people with an all-season access (road/rail) Number 0 272,500 272,500 287,000
Monthlt/Quarterly
local authorities/Site engineer/PMT/NHA Regional Manager
Western manager/Babanousa – Wau line manager/NHA Regional Manager
Original target was 301,500, but it is reduced to 287,000 to reflect the partial completion of the Damazin Kurmuk road upgrading by June 2013
Travel time on selected routes (Babanousa-Wau Rail)
hrs. N.A. 15 15 15
Monthlt/Quarterly
Site eng. Reports/Western Region traffic administration
Western manager/Babanousa – Wau line manager
Travel time on selected routes (Kadugli-Kauda Road)
hrs. 15. 2 2 2Monthlt/Quarterly
Local Authorities Reports
NHA Regional Manager
Travel time on selected routes (Hamsahkoreib-Gadamai Road)
hrs. 10. 1 1 1Monthlt/Quarterly
Local Authorities Reports
NHA Regional Manager
Travel time on selected routes (Ed Damazin-El Kurmuk Road)
hrs. 10 5 5 3 Monthly/Quarterly
Local Authorities Reports
NHA Regional Manager
Travel time was estimated to reduce from 10 to one (1) hour on the entire upgraded section of the Damazin –Kurmuk road. The travel time reduction is revised to be from 10 to three (3) hours due to expected completion of 45 km of the 92 km by the project closing date.
Travel volume for rail (Babanusa-Wau) Tonnage 0 50,000 50,000 50,000 Monthly/
Quarterly
Site engineer’s Reports/Western Region traffic administration
Western manager/Babanousa – Wau line manager
Assuming two (2) trains per week, 20 wagons per train with 25 tons average load per wagon
2 UOM = Unit of Measurement.9
Travel volume for road (Gadamai - Hamashkorieb; Damazin - Kurmuk; Kadugli – Kaouda)
Number of
Trucks/ day
N.A. 210 210 210 Annual
Regional Managers/Local authorities
PMT
Data from project design reports. The expected increase in traffic volume on Damazin –Kurmuk road from 40 trucks per day to 110 trucks per day will not be realized until the entire section will be upgraded. Total traffic reduced from 320 to 210.
Share of rural population with access to an all-season road (proportion)
Number%
No data for the share of rural population with access to an all- season road. This will collected during the extension period.
Roads in good and fair condition as a share of total classified roads. Supplemental value: Size of total classified network breakdown:
Percentage
km 6,900
No data for percentage of roads in good and fair condition. This will collected during the extension period. The classified road network is the national road network, which is 6,900 km. The remaining roads are unclassified dray weather roads
Beneficiaries
Direct project beneficiaries Yes Number 0 272,500 272,500 287,000 Monthly/
Quarterly
Site Engineer’sReports/State and local Authorities
PMT
Original target was 301,500, but it is reduced to 287,000 to reflect the partial completion of the Damazin - Kurmuk road upgrading by June 2013
Of which female Yes % 0 48 48 48 State/local authorities PMT
Intermediate C o Unit Baseline Progres Target Values Frequency Data Source/ Responsibility for Comments
10
Results Indicators
re
of Measure-
-ment
Original ProjectStart
(2007)
s To Date
(2011)Methodology Data Collection2012 2013
1.1. Rail line rehabilitated Km 0 446 446 446 Monthly/
Quarterly
Site engineer report/PMT/W. Region traffic administration
Babanusa Wau rail line manager/PMT
1. Action Plan for Private Sector Participation in Railway Sector adopted by Ministry (Yes/No)
Y/N N Y Y Y Quarterly
PMT quarterly progress report
PMT and MoT - PD
2. Action Plan for Port Sudan Trade Facilitation adopted by Ministry and recommendations under implementation (Yes/No)
Y/N N Y Y Y Quarterly PMT quarterly progress report PMT
11
3. Diagnostic study of the regulatory body in River Transport Sector completed (Yes/No)
Y/N N Y Y Y Quarterly PMT quarterly progress report PMT
4. Environmental and social framework adopted (Yes/No)
Y/N N Y Y Y Quarterly PMT quarterly progress report PMT
5. Environmental and Social Assessment Unit established under the Ministry (Yes/No)
Y/N N Y Y Y Quarterly PMT quarterly progress report
PMT and MoT - PD
6. Staff training in planning, budgeting, financing for all components
Number 0 18 24 30 Monthly/Quarterly
Progress Reports PMT - NHA
Intermediate Result 3: Critical Roads in Post Conflict Areas Improved
1. Roads rehabilitated - Rural Km 0 69 112 112 Monthly/
QuarterlyProgress Reports PMT - NHA
Kadugli – Kauda Road (30km) and Gadamai – Hamashkoreib Road (82km)
2. Roads rehabilitated – Non - Rural Km 0 28 28 45 Monthly/
QuarterlyProgress Reports PMT - NHA
Section 1 of Damazin – Kurmuk Road (7 km) and section 2 of Damazin –Kumruk road (38 km)
3. Feasibility and detailed design studies for new roads
Km 0 310 945 945 Quarterly Progress Reports PMT - NHA
Abu Gebeiha –Talodi Rd (160km), Talodi – Kadugli Rd (150km), Toker – Garora – Rd. (215km), Damazin – Renk Rd (200km) and Muglad – Abyei Rd (220km). The total length reduced from 995 km to 945 km as the Kadugli – Heglig section was dropped.
4. Feeder and community access road program prepared
Yes/No N N N Y Quarterly Progress Reports PMT - NHA
5. Pavement Management system established Yes/No N N N Y Quarterly Progress
Reports PMT - NHA
Planning Department of MTRB strengthened and Yes/No N Y Y Y Quarterly Progress
Report MTRB
12
satisfactorily discharging its oversight roleFeeder and community access road program prepared
Yes/No N N Y Y Quarterly Progress Report PMT-NHA
13
ANNEX 2: DETAILED PROJECT COST TABLE BY COMPONENT AND ACTIVITYSudan: NETREP - Reallocation of Proceeds
Item Activity Current Allocation Proposed Restructured Allocation Remarks/Status and Next Steps
Total GOS MDTF Total GOS MDTF
COMPONENT 1: REHABILITATION OF CRITICAL RAIL INFRASTRUCTURE AND SERVICES (US$ million)
1.1 Equipment & Rehabilitation of Babanusa – Wau rail line. 43.34 31.27 12.07 43.34 31.27 12.07
All the required equipment was procured. A contract was signed for procurement of pipe culverts at a cost of US$300,000.Communication equipment has to be procured at a cost of about US$230,000. Using some balance remaining under this item spare parts will be purchased
1.2 Rail connection to Port Sudan South Quay. - - - - - -
The infrastructure development has been requested to be considered for future implementation under the Sea Ports Corporation, while the focus at this stage will be on promoting trade facilitation needs. Actions for the latter are incorporated under item 2.2
1.3 Mine clearance 2.60 2.60 - 2.60 2.60 - Completed.
1.4 PMT- support for project implementation including TA. 0.20 - 0.20 0.20 - 0.20
Project implementation support costs (consultancy, workshops TA, operating cost, and IT equipment purchase) are to be covered with these resources.
Component 1 Total 46.14 33.87 12.27 46.14 33.87 12.27
14
ANNEX 2: DETAILED PROJECT COST TABLE BY COMPONENT AND ACTIVITY (Continued)Sudan: NETREP - Reallocation of Proceeds
COMPONENT 2: INSTITUTIONAL STRENGTHENING AND IMPROVEMENTS TO RIVER TRANSPORT SEVICES (US$ million)
2.1 Studies and other activities to enhance private sector participation in the railways. 0.05 - 0.05 0.03 - 0.03
Study completed. Recommendations are being considered through a taskforce established within the MTRB.
2.2Improvement to inter-modal operations at Port Sudan (Port Sudan Trade facilitation Study)
0.05 - 0.05 0.03 - 0.03 Study completed and recommendations are being considered through a taskforce established within the MTRB.
2.3 Enhancement of sector management capacity of MTRB. 0.08 - 0.08 0.12 - 0.12
Develop plan of action for the sector management and capacity enhancement. Funds are allocated for the TA for the Planning Directorate.
2.4 Establish environmental and social safeguards unit including short term TA 0.08 - 0.08 0.11 - 0.11
The Unit has been established. Training of staff is to follow.Funds are allocated for the TA.
2.5 Equipment in support of port operations. 0.72 0.48 0.24 - - -Procurement of one ferry boats for operation along R. Sobat cancelled due to separation of South Sudan.
2.6 Study to establish need for emergency dredging and navigational aids. - - - - - -
Develop plan of action following the outcome and recommendations of the NTMP study and implement as part of the joint project.
2.7 Hydrographic survey and mapping of the White Nile. - - - - - -
Develop plan of action following the outcome and recommendations of the NTMP study and implement as part of the joint project.
2.8 PMT- support to project implementation including TA. 0.72 - 0.72 .88 - .88
Diagnostic study for IRND institutional strengthening completed.
ESIA studies for Babanusa – Wau Rail line and the ferry boat completed. Project implementation support costs, including project coordination, Financial Advisor, and operational costs, to be covered from this allocation. . PC + Project Support officer salaries for March-June added. Expected new contracts for FA US$0.066m , PC US$0.072 m; Project Support Officer US$0.024m
Component 2 Total 1.70 0.48 1.22 1.17 - 1.17
15
ANNEX 2: DETAILED PROJECT COST TABLE BY COMPONENT AND ACTIVITY (Continued)Sudan: NETREP - Reallocation of Proceeds
COMPONENT 3: ROAD IMPROVEMENTS IN THE THREE AREAS (US$ MILLION)
3.1 Program of Construction and Spot Improvement Works3.1.1 Construction of Kadugli-Kauda Road (135
Km).
(a) Section 1: Km 0.0 – Km 18.6:
(b) Section 2: Km 18.6 – Km 48.9
(c) Section 3: Km 48.9 – Km 123
-
4.50
-
-
3.00
-
-
1.50
-
-
4.50
-
-
3.00
-
-
1.50
-
Section 2 had been completed. Sections 1 and 3 were cancelled due to mis-procurement and implementation will be by the South Kordofan State.
Cost for Section 2 is the final contract amount.
3.1.2 Construction supervision:
(a) Section 2: Km 18.6 – Km 48.9
(b) Section 2: Km 18.6 – Km 48.9
0.17 - 0.17 0.16 - 0.16 Final cost of supervision services.
3.1.3 Construction of Hamsahkoreib – Gadamai (82km).
28.20 19.00 9.20 24.30 16.20 8.10 Works completed. From MDTF allocation cost savings of about US$1.1 million realized.
3.1.4 Construction supervision 1.80 1.20 0.60 1.32 0.88 0.44 Services completed. From MDTF allocation cost savings of about US$0.16 million realized. Additional amount to pay Consultant bills unpaid due to need to extend the contract + supervision of pending contractor work.
16
3.2Upgrading to paved road standard – Ed Damazin – El Kurmuk Road (93 Km)
3.2.1 Contract 1 Section 1 (57.7 km) –Combined
Contract 1 –a—1 Section 1 (57.7 km) – base and asphalt wearing course
Contract 1 –a-2– Section 1 (57.7 km)- Up to sub base level (inclusive)
9.60
6.75
6.40
-----
3.20
----
6.75
9.12 6.8
--
------
2.32
----
--
Construction will resume. Amounts shown represent payments already made (including Advance Payment) and value of work executed. (The balance of the advance payment that is not yet recovered through payment certificates prepared before the repackaging, in the amount of US$1.19 million shall be cancelled from NETREP and shall be reimbursed to the MDTF account) ). (amount = actual+retention-1.19) (3.40+.11-1.19). About US$0.31 was reserved for increase in quantity of works executed before repackaging, which is only included in the component and project total costs.
Contract 1-a-1 to be implemented under separate arrangement by Government of Sudan (GOS) on parallel financing. This part may extend beyond the proposed grant closing date and will be executed out of NETREP. Compensation for damage to be covered by GOS.
Contract 1-a-2 Cost of works up to sub base level including all drainage structures to be financed 100% by MDTF. (Variation Order)GOS decided to execute this work as part of Contract 1 –a-1 above and fully cover the associated costs.
3.2.2 Contract 1 - Combined
Construction Supervision – Contract 1-a-1
Construction Supervision – Contract 1-a-2
0.10
0.15
0.07
---
0.03
----
0.15
0.10
---
---
0.07
---
---
0.03
---
---
Actually disbursed amounts for the combined contract.100% increase over the contract amount to cater for any extended supervision services.
Parallel financing by GOS.
To be financed by GOS out of NETREP.3.2.3 Contract 2 – Section 2 (38 km + up to 5 km
road improvement into Section 1)19.50 - 19.50 26.01 - 26.01 Construction will resume . Cost increased to cater for increase in
quantities and price escalation and compensation for damages..
3.2.4 Construction supervision 0.77 - 0.77 0.85 - 0.85 Cost increased to cater for extended supervision services.
3.3 Spot Improvements in the Nuba Mountains – Detailed Designs
3.3.1 Abu Gebeiha-Talodi (160 km) Services completed
3.3.2 Talodi-Kadugli (150 km) 2.35 - 2.35 2.32 - 2.32 Costs are final.
3.3.4 Toker-Garora (215 km)
3.4 Rural Access Program for the Three Areas – Feasibility Studies and detailed Design17
3.4.1 Damazin – Renk (200km).1.67 - 1.67 1.54 - 1.54
Services completed.
Costs are final.3.4.2 Kadugli – Hegleig (170km)
3.4.3 Muglad – Abyei (220km)3.5 Studies, Institutional development and Support for Program Implementation
3.5.1 Support for project implementation including technical assistance. 0.25 - 0.25 .43 - .43
Studies and TA to support project implementation completed.. Increase represents $.02 million to cover balance of Financial Advisor contract(March to June) + $.05 million to provide for Letter of Credit opening fees about 1% of PMS value.
3.5.2 Establishing pavement management system and various studies including sustainable road sector financing, road safety and axle load control.
4.56 - 4.56 4.56 - 4.56Cost is based on the latest Financial Proposal received for the PMS design and establishment.
3.5.3 Institutional development and capacity building, including training, workshops, and study tours, etc.
0.20 - 0.20 0.20 - 0.20Training for NHA staff.
3.5.4 Design of pavement management system and improvement to materials testing laboratory -
- --
- -
Included in 3.5.2
3.5.5 Support to demining activities - - - - - - This allocation is cancelled due to mis-procurement of Kadugli – Kaouda Road, Lots A, C, D and E. Amount reallocated to other activities.
3.5.6 Mine clearance 5.00 5.00 - 5.00 5.00 - Completed.
3.5.7 TA for preparatory works in support of improving access to rural community, and ensuring sustainability of the road network.
2.80 - 2.80 2.80 - 2.80 In progress. Amount reflects the actual contract value. The work includes consultancy services to prepare rural community access programs in selected states.
Component 3 Total 88.37 34.36 54.01 83.21 31.95 51.26
GRAND TOTAL 136.21 68.71 67.50 130.52 65.82 64.70
18
ANNEX 3: ALLOCATION OF GRANT PROCEEDS BY COMPONENT AND DISBURSEMENT CATEGORY
Category
Current Allocation Proposed Restructured Reallocation
Amount (in US Dollars)
% of Expenditure to
be Financed
Amount (in US Dollars)
% of Expenditu
re to be Financed
1. Works, goods, services and training for Part 1 of the Project (SRC) (per memoria)
11,772.41 33-1/3 11,772.41 33-1/3
2. Works, goods, services and training for Part 2 of the Project (RTC) (per memoria)
------- -------- ------ -----
3. Works, goods, services and training for Part 3 of the Project (NHA) (per memoria)
1,802,862.00 33-1/3 1,802,862.00 33-1/3
4. Goods and services for demining activities (per memoria)
--------- ----- ------ -----
5. Goods for Part 1 of the Project (SRC) 12,058,227.59
100 12,058,227.59 100
6. Services, training and operating costs for Part 1 of the Project (SRC)
200,000.00
100 200,000.00 100
7. Works for Part 1 of the Project (SRC) --------- ---- ------ ----
8. Goods for Part 2 of the Project (MTRB)
240,000.00 33-1/3 ------- -----
9. Goods, Services, training and operating costs for Part 2 of the Project (MTRB)
980,000.00 100 1.170,000.00 100
10. Works for Part 3 (i)(a), (i)(b) an (i)(e) of the project (NHA) (1)
13,187,138.00
33-1/3 10,727,138.00 33-1/3
11. Goods, services, training and operating costs for Component 3 of the Project (NHA)
11,850,000.00
100 11,870,000.00 100
12. Works for Part 3 (i)(d) of the Project (NHA) (2)
20,270,000.00
100 26,860,000.00 100
13. Works and Services for Part 3 (i) (c) of the Project (NHA) (3) 6,900,000.00 100 ---- ---
TOTAL 67,500,000.00 64,700,000.00
Sudan: NETREP - Restructuring for Reallocation
Notes: (1) Category 10: For the costs of construction contracts and supervision contracts for the Gadamai – Hamashkoraib Road,
Damazin – Kurmuk Road, Section 1 (57.7 km) for works completed so far and the construction contract for Kadugli – Kaouda Road, Section 2 (km 18.6 to km 48.9)
(2) Category 12: For the costs of construction contracts and supervision contracts for Damazin – Kurmuk Road, Section 2 (38 km+ up to 5 km road improvement into Section 1).
19
(3) Category 13: For costs of works up to sub base level including drainage structures for Section 1 of Damazin – Kurmuk Road, transferred to section 2 of Damazin – Kurmuk road , after reduction of the additional funds required for works executed before repackaging of section 1 (combined contract for section 1).
20
ANNEX 4: IMPLEMENTATION PLAN
National Emergency Transport Rehabilitation Project (NETREP)
Component 1 – Rehabilitation of Critical Rail Infrastructure and Services
It No
Category/Activity Cost(US$’000)
Draft TOR/ Invite Cons. Firm/Negotiate and Award contract for design and bid document preparation
Detailed Design and Bid document preparation (Consultants)
Draft TOR/RFP/Evaluation/Award/Mobilization SPN Consultants
Bidding for Works/Evaluation/Award
Contractor(s) mobilization
Works implemented
Responsible/lead Institution
Start Finish Start Finish Start Finish Start Finish Start
Finish Start Finish
Component 1: Rehabilitation of Babanousa Wau Line
Procurement of Equipments1.1 Supply of Corrugated Circular and
Arch pipe culvertsEuros
301,300.00-
2006 2007 June 2008
June 2009
Sep 2009
Sep-09 May 2010
21-Feb-2011
May 2011
July2011
Aug 2011
March 2012
SRC
1.2 Supply of communications Equipments
USD 230,000
2006 2007 2008 April 2011
March2011
April 2011
Sept 2011
Dec 2011
Oct 2011
Oct 2011
Nov 2011
Sep 2012
SRC
1.3 Purchasing of Spare parts for Earth Moving Equipments
USD 30,000
2006 2007 Feb 2010
March 2011
April 2011
June 2011
June 2011
July 2011
Aug 2011
Aug 2011
July 2012
Sep2012
SRC
1.4 Purchase of local materials and tools for Stations rehabilitation
SDG 3157200.0
0
2006 2007 Feb 2011
April 2011
May 2011
June 2011
June 2011
Dec 2011
June 2011
July 2011
Aug 2011
Jun 2013
SRC
1.2 Rehabilitation Works
2.1 Rehabilitation of Stations SDG 2092800.0
0
2006 2007 March 2011
April 2010
April 2011
June 2011
June 2011
Dec 2011
June 2011
July 2011
Aug 2011
Jun 2013
SRC
2.2 Track maintenance SDG 1650000.0
0
2006 2007 - - - - - - - Dec 2008
Feb 2008
Jun 2013
SRC
2.3 Construction & Rehabilitation of Pipes & Small Bridges. &
SDG 1450000.0
0
2006 2007 - - - - - - - - June 2011
Jun 2013
SRC
21
Implementation PlanNational Emergency Transport Rehabilitation Project (NETREP)
Component 2 - Institutional Strengthening and Improvements to River Transport Services
Activity
Cost US$(000)EOI Evaluation
Contract Award
ImplementationResponsible/lead Institution
Start Finish Start Finish Start Finish
Technical Assistance to strengthen the
Environmental and Social Management
Unit in the Ministry of Transport110
Feb.
2011March2011 March2011 May2011 June2011 Feb2012 Dec.2012 MoT
Technical Assistance to strengthen the
Planning Directorate of the Ministry of
Transport120
May2011 Jan2012 Dec.2012 MoT
22
Implementation PlanNational Emergency Transport Rehabilitation Project (NETREP)
Component 3 – Road Improvements in the Three Areas
It No
Category/Activity Cost(US$’000)
Draft TOR/ Invite Cons. Firm/Negotiate and Award contract for design and bid document preparation
Detailed Design and Bid document preparation (Consultants)
Draft TOR/RFP/Evaluation/Award/Mobilization SPN Consultants
Bidding for Works/Evaluation/Award
Contractor(s) mobilization
Works implemented
Responsible/lead Institution
Start Finish Start Finish Start Finish Start Finish Start
Finish Start Finish
1 Gadamai - Hamashkoraib Road {81.5 Km)
24,300 - - - - Oct-06 Aug-08 Oct-06 Nov-07
Aug-08
Nov-08
Aug-08
June-12
NHA
2 Damazin - Kurmuk Road {57.7 Km.} 30,420 - - - - Nov-08
Apr-09 Jan-08 Jan-09 Apr-09
ongoing
Jun-09 June -13
NHA
3 Damazin - Kurmuk Road- Section 2 26,860 - - - - Jun-09 Apr-10 Apr-09
Nov-09
Jan-10 Mar-10
Mar-10
Mar-13
NHA
4 Kadougli - Kaouda Lot B 4,670 - - - - Oct-08 Dec-09 Sep-08
Jan-09 Oct-09 Dec-09
Dec-09
Dec-10
NHA
5 Abu Gubeiha – Talodi - Kadugli (310 Km) -
1,350 Jun-08 Mar-09 Apr-09 Jun-11 - - - - - - - - NHA
6 Toker - Garora (220 Km) 1,000 Jun-08 Mar-09 Apr-09 Jun-11 - - - - - - - - NHA
7 Damazin - Renk (200Km.) 850 May-07 May-08 Apr-08 Jun-11 - - - - - - - - NHA
8 Muglad- Abyei - Lot C 820 May-07 May-08 Apr-08 Jun-11 - - - - - - - - NHA
9 Feeder Roads & Community Access Program Development
2,799 Dec-09 Nov. 10 Dec-10 Jun-12 - - - - - - - - NHA
10 Pavement Management System 4,560 Dec-09 July -12 Aug-12
Mar-13 = = = = = = = = NHA
23
12 Capacity Building 200 May-09 Dec 12 NHA
13 Mine clearance 5,000 2006 2006
24