wbts split procedure
TRANSCRIPT
WBTS SPLIT_________________________________________________________________________________________________
PURPOSE
Nokia Siemens Networks may be required to perform WBTS Split works on telecommunication networks across Australia in various locations and environments.
This document outlines the procedures to be adopted by NSN personnel, undertaking work for the Remote Integration Centre (RIC).
PRE-REQUISITES
The following are minimum pre-requisites to perform the RIC functions:
Optus remote desktop connection with OSS and UNIX logins
Access to RIC shared network drive and associated datafil
Access to CM Tools, Top Level User Interface, DNS Server & Network Licence Manager
SCOPE
The procedures in this document are designed to cover the various works performed by the RIC:
Pre-WBTS Split checks WBTS Split
DEFINITIONS
AXC – Asynchronous ATM Cross Connect
COCO – Connection Configuration.
IMA – Inverse Multiplexing of the ATM.
RIC – Remote Integration Centre.
RNC – Radio Network Controller.
SAXC – Stand Alone ATM Cross Connect.
VP– Virtual Path.
WBTS – Wideband Base Transmit Station.
© Copyright Nokia Siemens Networks Page 1 of 3Date: August 2007
Uncontrolled five (5) days after printing. Print Date: 10/04/2023
WBTS SPLIT_________________________________________________________________________________________________
PROCEDURES
RIC Staff Responsibilities
The RIC is responsible for performing and reporting all WBTS Split activities via the Spinoza_Site_Status.XLS report which is distributed daily at COB via email or available on the NSN Shared network drive at V:\Technology\Operations\Services Management\Nokia Operations\Integrations\Integrated Sites\Spinoza.
The following example is for an OPTUS Lead site where the Vodafone cells will migrate to the new Flexi node.
Pre-WBTS Split Checks
1. Check that site engineer and the RIC have the same target configuration. Ensure all are clear on what transmission and hardware re-arrangements will be implemented.
2. Perform E1 testing if required.3. Check the WBTS for existing alarms. Report to GSMPRO to gain approval prior to commencing
work.4. Create AXC commissioning files using the Sydney IP sheet.5. Launch CM Operations Manager and perform an Upload on all RNCs in the Regional Cluster you are
working on. If the Upload fails on the Target RNC the WBTS is on then DO NOT PROCEED WITH WBTS SPLIT.
WBTS Split
6. Lock down the WBTS’s
7. Update CCU’s (if Vodafone Lead site then the CCU will migrate to the new OPTUS Flexi)
8. Recommission AXC/Flexi
9. Inform site engineer to commence work.
10. Export .XML files for the Actual Configuration for the following Object Classes, ensure you have “include incoming adjacencies” checked in the Export Options window.
WBTS WCEL ADJS ADJI ADJG ADJW if applicable WLCSE if not already created for the 2FA
11. Edit .XML plans with new WBTS ID eg 24219 (use Replace All)
change COCOid eg 24219
change VPI
change WBTSName eg MARGATEoV
change name eg xMARGATEoV
12. Prepare WCELL deletion plan in CM Editor
Select all ADJS, ADJI, ADJG and change status to Delete
Select the WCELs and change status to Delete
13. Provision WCEL Deletion Plan
14. Change existing WBTS name in RNC eg MARGATEoO
15. Perform Upload on all RNCs in Regional Cluster.
© Copyright Nokia Siemens Networks Page 2 of 3Date: August 2007
Uncontrolled five (5) days after printing. Print Date: 10/04/2023
WBTS SPLIT_________________________________________________________________________________________________
16. Perform Topology Upload on RNC
17. Delete cells in NetAct view (from dbase).
18. Add 2FA cells to NetAct view if required and check Maintenance Region
19. Import the WBTS plan and Provision it.
20. Import the WCEL Plan and Provision it.
21. Perform Upload on RNC
22. Import the ADJS, ADJG & ADJI Plans and Provision them.
23. Perform Upload on all RNCs in Regional Cluster
24. Perform audit check of adjacencies. Export ADJS, ADJG & ADJI as per step 10
25. Delete SAXC cross connections and IMA Groups for existing WBTS
26. Create new IMA Groups and Cross connections for both WBTSs
27. Modify COCO for existing WBTS
28. Create COCO for new WBTS
29. Update HSDPA parameters for existing and new WBTS
30. Add new IP data in DNS
31. Perform Topology Upload
32. Create NetAct view for new WBTS
33. Add site to SAXC subview
34. Wait for site engineer to complete his work
35. Create DCN, Static & Forward Routes
36. Log into AXC, WBTS to confirm configurations. Take note of feeder loss values. Check Flexi node for
existing licences
37. Distribute required licences to Flexi node
38. Enter WCEL feeder loss values in RNC for both sites
39. Unlock both WBTSs
40. Ensure Test Calls complete
41. Check External Alarms (eg AC Mains for new flexi)
42. Perform LBS test on OPTUS 2FA if not already integrated
43. Lock new 2FA WCELs
Post-WBTS Split
44. Take WBTS backup
45. Generate soft copy checklist
46. Update Work Package in NOLS
47. Upload documents to NOLS
48. Update RIC Works & Spinoza reports
© Copyright Nokia Siemens Networks Page 3 of 3Date: August 2007
Uncontrolled five (5) days after printing. Print Date: 10/04/2023