Page 1: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

WBS1 SBS Basic: Magnet and Infrastructure

Robin Wines

11/4/20131

SBS DOE Review

Page 2: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

FY13 Scope of Work

11/4/2013SBS DOE Review2

FY13• Magnet analysis • Experiment layouts in Hall A• 48D48 magnet transfer from BNL• Magnet Yoke Modifications• Power Supply selection and procurement• Design and Procure New Coils• Engineering of Support Structure/Magnet Platform• Engineering of Detector Supports• Engineering of Beam pipe and Shielding• Engineering of Field Clamps

Page 3: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

Hall A

Dump Beam Line

Truck Ramp

HRS-R HRS-L

Utilities

Floor plates SBS

BigBite

Beam Line

•Developed detailed floor plan of Hall A, existing equipment and SBS experiment configurations•Presently working on Hall configuration to allow clearance for truck ramp during operation •Modifying and relocating LCW and power utilities for SBS and future experiments

11/4/20133

SBS DOE Review

•Hall A is ~50 meter diameter with a 20 ton overhead crane capacity

•Two existing HRS ,HRS-R rotates to a maximum of 120 degrees

Page 4: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

Kinematics of SBS•SBS Program is defined by three experiments, each with multiple configurations of equipment. Each configuration has been modeled and the required layout of Hall has been determined.

11/4/20134

SBS DOE Review

Page 5: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

Layout of GMn Calibration Q2 = 6.0GeV2

•Calibration uses SBS at 3.0 m from target, HRS-R and HCal at 17m from target•HRS-R angles from 30.9 to 69.1 degrees and SBS angles of 15.6 and 31.1 degrees

11/4/20135

SBS DOE Review

HRS-R

HRS-L

SBS

Page 6: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

Layout of GEn Q2 = 10.18GeV2

•GEn uses SBS at 2.8 m from target, BigBite at 1.5 m from target and HCal at 17m from target•SBS angles of 17.5 to 39.4 degrees and BigBite angles of 34 and 40 degrees

11/4/20136

SBS DOE Review

HRS-RHRS-L

SBSBigBite

Page 7: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

Layout of GEp Q2 =12.0GeV2

•GEp uses SBS at 1.6 m, HCal at 6.8 m and Electron Arm at 3 to 4.2 m from target• SBS at angles 16.9 to 28.2 degrees and Electron Arm at angles 26.1 to 29 degrees

11/4/20137

SBS DOE Review

HRS-RHRS-L

SBS

HCal

ECal

Page 8: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

Layout of GMn Q2 = 13.5GeV2

•GMn uses SBS at 1.6 to 3.1 m, BigBite at 1.55 to 2.1 m and HCal at 6.8 to 17 m from target•SBS at angles 13.3 to 24.7 degrees and BigBite at angles 32.5 to 64.3 degrees

11/4/20138

SBS DOE Review

HCal

BigBite

SBS

HRS-L HRS-R

Page 9: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

BNL to Jlab, Magnet Transfer

11/4/20139

•SBS will utilize the BNL 48D48 Dipole magnet

•48D48 is 1.2 meters long dipole with gap of 47cm x 122cm, designed to operate at current of 4000 A

•SBS requires modification of the Yoke to allow beamline clearance and purchase of new coils to operate at maximum current of 2000A

•Jlab received two yokes and one set of coils from BNL in August 2013

•Assembly hardware was not received from BNL, so new hardware is being designed (+$14k)

SBS DOE Review

Page 10: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Dipole Yoke Modifications

•SBS Yoke requires cutout in yoke return to allow placement of beam pipe at various angles •Determined cutout through TOSCA analysis, allowing clearance for change out of beam pipe sections•Requires 13” vertical gap cutout in two sections•Assembly procedure of yoke and hardware requirements are determined

STATUS•Machining drawings in procurement •Bids due December 5th

11/4/201310

SBS DOE Review

Page 11: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Coils and Power SupplyPower Supply•Requires 2200A, 638kW supplySTATUS•Contract awarded August 2013•Design review scheduled for November, delivery scheduled for late June 2014, utilize in September 2014

Coils•New racetrack coils allow easy rotation of magnet and clearance of beam pipe•New saddle coils allow close proximity of detectors to magnet•Max current of 2000A, water-cooled conductor, dT < 5C at 100GPMSTATUS•4 bids, all above budgeted cost•Testing BNL saddle coils as backup•Alternate plan = purchase racetrack coils only and use one BNL saddle coil. BNL coils are longer, forcing detectors to lose some acceptance.(~10%)

11/4/201311

SBS DOE Review

Page 12: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Support Structure

•GEp experiment configurations require short distance between target to SBS Magnet•Support of SBS is limited by HRS links and pivot location•Resulted in a counterweight support system with magnet loaded on edge of frame- FEA analysis completed and preparing for internal engineering review in November. (Analysis in Breakout session)

•Using 2nd yoke pieces from BNL as counterweight, only frame to be fabricated - On track for procurement in January 2014

•Structure rolls on 2” surfaced floor plates, using hydraulic cylinders for lift and Hilman rollers - Rollers and counterweight material are existing in-house

•Floor plate drawings ready for procurement

•Detector supports to be integrated into frame design

11/4/201312

SBS DOE Review

Page 13: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Beam pipe and shielding

•Beam pipe to be designed to deliver beam to dump in multiple configurations•Design to allow sections to be changed for different configurations•Utilizing layers of shielding and solenoid magnets to reduce field in beam pipeSTATUS•Iterating through TOSCA analysis to minimize number of beam pipe sections and solenoids needed to meet configuration requirements•Design is 30% done. On track to complete in February 2014.

11/4/201313

SBS DOE Review

Plot of Bx along beam line from target . No shielding applied to beam line results in integral of 0.001 T-m. Need shielding to remove “spike” in field.

Page 14: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Field clamps•Upstream field clamps needed to limit target field, less than 40 G.•Downstream field clamps needed to limit detector field•Field clamp supports designed for adjustabilitySTATUS•Design of SBS field clamps complete•BNL and new Jlab saddle coils different in length; changes location and size of field clamps, drawings on hold until saddle coil is determined•Additional field clamp/shielding needed for BigBite configurations, design in progress•50% complete on all field clamp work

11/4/201314

SBS DOE Review

Page 15: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS and BigBite Analysis•2011 Review Recommendation to study affects of SBS and BigBite magnets on each other.

•Completed TOSCA study of SBS and BigBite in close proximity as in GMn experiment

•No change in SBS or BigBite field profiles (more in Breakout session)

•Remnant field of 100 Gauss close to BigBite detectors

•Additional shielding to be designed for BigBite detectors

11/4/201315

SBS DOE Review

SBS

BigBite yoke

1000G

500G

100G

Page 16: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Program

Assembly and Testing•Preliminary assembly plan of SBS magnet completed to determine assembly hardware.•Magnet to be assembled in TestLab facility to avoid interference with Hall A experiment schedule. Preparing area for July 2014 testing.•Power supply to be installed and tested in Hall A, in process of upgrading LCW and power.

Manpower•Hall A Design/Engineering – 3 designers, 2 engineers, 1 engineering associate

Hall Coordinator and 6 technicians•In FY14, SBS Program requires 68 manweeks design, 25 manweeks engineering and 30 manweeks technicians•Hall A to be ready to receive beam February 2014, sharing SBS resources to prepare Hall for next experiment run period.•Sufficient resources to accommodate SBS Program goals.

11/4/201316

SBS DOE Review

Page 17: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS ESH &Q

11/4/2013SBS DOE Review17

Fully integrate ESH&Q into planning ,design, fabrication and installation•Conducting design and safety reviews of major subsystems before fabrication and installation; such as review of support structure engineering.

•Coordinating work of outside institutions to insure Jlab policies are followed; Collaborators present designs for review in weekly meetings.

•Utilizing Jlab screened vendors and requiring vendor’s to have quality program in use.As program progresses into fabrication and installation,•Will perform hazard analysis and utilizing Jlab safety system for all testing and commissioning activities; such as load testing, weld inspection, TOSPs, coil acceptance tests, pre-assembly and testing of magnet.

•Each SBS Experiment will be required to complete the Jlab Readiness Review process.

Page 18: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Progress

11/4/2013SBS DOE Review18

WBS 1.1•Magnet Analysis – Completed TOSCA analysis for yoke cutout design, SBS and BigBite interaction and field clamp design . 30% complete on beam line shielding iterations. (FY13)

•Experiment Layouts – completed (FY13)

•BNL 48D48 Magnet – Received two yokes and one set of coils August 22nd. (FY13)

•Magnet Yoke Modifications – Completed design, drawings out for bid, bids due December 5th. (FY14)

•Power Supply – Contract awarded August 30th. Delivery June 2014. (FY13)

•New Coils – 4 bids received October 14th. Requested Best & Finals on November 1st. Alternate plan if coil bids remain above program budget. (FY13)

Page 19: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Progress

11/4/2013SBS DOE Review19

WBS 1.1 (continued)•Field clamps – 50% complete. Field clamps needed April 2015.(FY14)

WBS 1.2•Support Structure/Magnet Platform – 80% complete. Reviewing engineering design, ready for procurement January 2014. Platform needed July 2014. (FY14)

•Detector Supports – 40% complete . Detector supports needed March 2015. (FY14)

WBS 1.3•Beam pipe and shielding – 20% complete. Beam line needed September 2015. (FY14)

Page 20: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

BACKUPSBS

11/4/2013SBS DOE Review20

Page 21: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS

Calorimeter

Page 22: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

SBS Design/Engineering Plan

Design and Engineering Procurement/

Fabrication Milestone

Activity des eng early design finish

late proc/fab start Duration

mw mw mw

1 Magnet yoke received (FY13) August 2013(actual)

2 Magnet yoke modifications(FY14) 6 2 4-Oct-13 13-Dec-13 18 Apr-14

3 New coils(FY13) 2 2 13-Sep-13 19-Sep-13 28 Apr-14

4 Magnet assembly hardware(FY14) 4 1 8-Nov-13 14-Feb-14 8 Jul-14

5 Assemble magnet (Testlab) (FY14) 4 2 22-Nov-1331-May-

14 6 Jul-14

6 Commissioning tests of magnet (Testlab) (FY14) 2 12-Sep-14 4 Sep-14

7 Power supply(FY13) 11-Oct-13 12 Jan-14

8 Power supply test (Hall A)(FY14) 1 15-Mar-14 4 Sep-14

9 Magnet support structure (FY14) 8 3 13-Dec-13 25-Jan-14 24 Jul-14

11 Detector supports (FY14-FY15) 22 8 14-Mar-14 16-Jan-15 12 Mar-15

12 Field clamps and supports (FY14) 6 3 7-Feb-14 15-Aug-14 8 Apr-15

13 Beamline supports(FY14) 4 1 20-Dec-13 3-May-14 10 Sep-15

14 Shielded beampipe and vacuum chamber(FY14) 6 3 18-Jan-14 18-Oct-14 24 Apr-15

15 Beampipe solenoid correctors (FY14) 4 2 22-Feb-14 12-Sep-14 16 Jan-15

17 Pole inserts (FY14) 2 1 8-Mar-14 6-Dec-14 4 Feb-15

11/4/201322

SBS DOE Review

Page 23: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review
Page 24: WBS1 SBS Basic: Magnet and Infrastructure Robin Wines 11/4/2013 1 SBS DOE Review

11/4/2013SBS DOE Review24